2013 GATWICK CAPITAL INVESTMENT PROGRAMME
Published following airline consultation in April 2013 – June 2013Figures correct as at 31.03.2013
Images on front cover:1. Emirates A380 at Gatwick2. Gatwick Main Runway Resurfacing project3. South Terminal International Departure lounge (ST IDL) Phase 1 Project
contents
SECTION SubJECT PAGEForeword by Stewart Wingate 1
Introduction 3
CHAPTER 1 Updated Traffic forecasts and Airport Master Plan 5
CHAPTER 2 Our Strategic Ambition: to become London’s airport of choice 15
CHAPTER 3 Consultation on the Capital Investment Programme 25
CHAPTER 4 Project Descriptions 35
APPENDICES
APPENDIX A Phased Capital Investment Programme 2013 93
APPENDIX B Phased Capital Investment Programme 2012 94
APPENDIX C Changes to Investment Programme - Tracker for the period April 2012 to March 2013
95
APPENDIX D Previous Traffic Forecasts as published in the 2012 CIP 96
APPENDIX E Meetings, Working Groups and Governance Boards 97
APPENDIX F Decision Log 103
APPENDIX G Annex G 108
APPENDIX H Gatwick’s updated Product Matrix 113
GLOSSARY 117
1FoReWoRD BY steWARt WInGAte
Since the last issue of the annual capital investment programme (CIP), we have published our ten year Business Plan for the period April 2014 up to March 2024. In the revised Business Plan, which is with the CAA for consideration, we’ve set out our vision for London Gatwick which builds on the great progress we’ve made in the last three years. We’re clearly now competing with the other London airports, and continue to build a world class experience for our passengers.
In respect to the current CIP I am pleased to report that as at 31st March 2013 a further 19 % of the capital investment has been delivered since April 2012, and we now have 82 % of our £1.172 billion CIP either completed or under construction. During 2012, our efforts at helping our airlines partners grow at Gatwick and transforming the passengers’ experience were recognised at several industry awards in 2012, including the much coveted Best UK airport at the 2012 British Travel Awards.
Since April 2012, easyJet has introduced seven new routes and also confirmed it will launch a new twice-daily service from Gatwick to Moscow Domodedovo airport from spring 2013. Norwegian Air Shuttle, one of Europe’s fastest-growing airlines, announced it is to establish a new base in London at Gatwick Airport in spring 2013. BA introduced a three-weekly service to Las Vegas and Colombo and Thomson announced a weekly service to Phuket from October 2013. New carriers to the airport during this period included Air Arabia and Gambia Bird, with Garuda Indonesia announcing their intention to commence services from Gatwick in the autumn. Clearly the growth of these routes demonstrates confidence from our airline partners in the facilities provided and shows airlines wanting to operate flights to London are actually choosing Gatwick over other London airports.
We delivered on several important projects during the year to support our current and future growth. The rehabilitation of Gatwick’s most critical asset, the Main runway, was substantially completed in December 2012 following a challenging period of delivery during a record breaking summer for rainfall. The impacts were managed through working collaboratively with the airlines to ensure completion of the most critical works prior to October.
In the South Terminal (ST), the ST International Departure Lounge (IDL) Phase 1 Project (WDF) was opened in July 2012, providing a brand new ST walk through duty free facility, Europe’s largest World Duty Free store. Big improvements were brought to the passenger experience in the North Terminal (NT) with the opening of Jamie’s Italian and the Yo! Sushi restaurants in June 2012. The opening of Jamie’s Italian is a great example of how Gatwick is competing to become London’s airport of choice with Gatwick being recognised as having delivered the best travel restaurant throughout the travel industry in 2012.
2
The Pier 5 project, which aims to deliver improved pier service levels to meet future growth in passenger numbers in North Terminal, is currently well underway with the completion of phase 1 anticipated in July 2013. In November 2012, Gatwick awarded its largest construction contract to date to demolish Pier 1 and construct a new building in the South Terminal to house both a new baggage system and a new pier. At a total cost of £178.9 million, this project is Gatwick’s largest capital investment since the change of ownership three years ago. It is also a historic milestone for Gatwick as Pier 1 is one of the oldest assets in South Terminal, first opened in 1958. Phase 1 of the South Terminal Baggage and Pier 1 project comprising the replacement of the HBS facility was completed in September 2012. Phase 2 comprising the construction of a new ST baggage factory and brand new pier with 5 fully serviced stands, entailing the demolition of the existing Pier 1 and delivery of an automated baggage storage facility, will open in 2015.
The A380 on Stand project came into service in March 2013 under budget, with the first A380 service utilising stand 110 on 26th March. There have also been major upgrades to the baggage system to increase capacity and improve efficiency with the NT Baggage upgrade project completing in December 2012.
As we continue to deliver our compelling vision and raise the profile of Gatwick as a major London airport it is imperative that an in-depth understanding of the needs of our passengers and business partners continues to drive our capital investment decisions. We have already undertaken further passenger survey work during 2012, validating previous studies and seeking new dimensions to the data. We also regularly meet with our airline community, individually and multilaterally, seeking to understand the needs and alignment of our stakeholders.
2013 will be a critical year. The sale of Stansted signals the first time that all London airports are under separate ownership, driving real competition. It is also the year that the CAA, will make decisions about which airports should be regulated. 2013 has also seen the start of a process that could lead to new runway development in the South East, Gatwick has now formally notified the Airports Commission that it will be developing options for expansion of the airport, these options could mean a second runway at Gatwick, but not until the mid-2020s at the earliest.
As we deliver the final 18 % of our £1.172 billion investment in 2013/2014, we’ll continue working together with our airline partners positioning Gatwick as ‘London’s airport of choice’.
Yours faithfully
Stewart Wingate Chief Executive
3
The 2013 Capital Investment Programme (CIP) is an annual document around which consultation between airlines and Gatwick Airport Ltd (GAL) takes place, in line with Annex G’s requirements. It forms part of our consultation with our airline partners about the future of Gatwick until 2024.
The 2013 CIP outlines in detail Gatwick’s performance in the first five years of the fifth quinquennium, commonly referred to as ‘Q5’. Q5 commenced on 1st April 2008 and was due to end in March 2013. In March 2011, the CAA published its decision to extend the current Q5 price control period by one year to 31 March 2014, therefore the projects expected to be completed within this time frame are also included.
For the purposes of this document, the Q5 price control period and the extension year 2013/2014 will henceforth be referred to as ‘Q5’.
This CIP also includes a summary sheet of the proposed projects for the period beyond Q5, i.e. for the next 10 years starting April 2014 to March 2024. As stated previously this proposal is subject to the CAA’s consideration, their initial view will be known at the end of April 2013.
ThE CIP IN CONTExT
As one of the three regulated airports in the UK, Gatwick is subject to regulatory review by the CAA and the Competition Commission every five years. Accordingly Annex G requires GAL to produce information within annual capital planning documents covering at least 10 years, around which consultation takes place. It states that the purpose of the CIP document is to allow the airport to consult on a number of matters relating to Q5 (and future price control periods)
Under Annex G, the key aspects to the airport - airline consultation on airport development plans consist of the following main documents:
• Gatwick Airport Master Plan • Gatwick Capital Investment Programme (CIP)• Consultation on individual projects.
Together the Master Plan and CIP documents provide a clear picture of Gatwick’s roadmap of development within the current, medium and long term view.
The final Gatwick Master Plan, identifying the high-level strategic development direction for Gatwick comprising current and future land use plans and taking account of the responses from the consultation process was published in July 2012.
The Gatwick Capital Investment Programme (CIP) includes a detailed description of individual projects designed to address these development requirements and reports on consultation with the airlines.
ASSuMPTIONS FOR ThE CIP
Although Gatwick has announced it will be developing options for expansion of the airport for submission to the Airports Commission, this CIP report is based on the assumption that Gatwick will remain a single runway airport up to the mid-2020s. This single runway-two terminal scenario is the key premise upon which the ten year airport investment programme is based. Gatwick continues to safeguard for a second runway.
There is still room to grow in the short to medium term, by using un-utilised runway capacity during off-peak periods. By making full use of the potential of the single runway we believe Gatwick can build capacity to accommodate up to 39.2 million passengers (high case scenario) by 2018/2019, as outlined in Chapter 1 - Traffic Forecasts.
IntRoDUctIon
4
ThE STRuCTuRE OF ThE CIP
The content of the CIP is guided by the CAA’s Annex G requirements for the Capital Investment Programme and is intended to describe the capital investment for Gatwick over an extended Q5. It aims to provide details regarding the drivers and priorities for investment as well as giving specific information on current and future projects.
The structure of this document is as follows:
• Chapter1 describes Gatwick’s existing traffic and provides details of our latest traffic forecasts. It articulates how these forecasts are translated into facility requirements.
• Chapter2 describes the Gatwick Investment Strategy, setting out the principal drivers and priorities for investment at the airport. It also includes a more detailed look at some of the investment initiatives at Gatwick that have already been delivered, are currently being delivered and will be delivered at Gatwick in the future. We have also included a high level overview of the ‘Beyond Q5’ Capital plan as set out in Gatwick’s Business Plan.
• Chapter3 provides an update on the consultative process undertaken at Gatwick and an overview of how we comply with the requirements of Annex G - outlining how we engage with all our customers and stakeholders comprising airlines, passengers and the wider Gatwick community. It highlights key elements of this consultation.
• Chapter4 contains individual project descriptions, including details on costs, for all projects or programmes over £5 million (out-turn prices).
Appendices are included showing the 2013 CIP forecast phasing of expenditure of all major projects and programmes of greater value than £1 million (Appendix A), the CIP 2012 forecast phasing of expenditure of all major projects and programmes of greater value than £1 million (Appendix B) and a tracker that highlights changes to the 2012 CIP report (Appendix c). The previous 2012 CIP report highlighted the changes brought to capital investment programmes at Gatwick since 2008 up to March 2012. Please refer to Appendix D in the previous 2012 CIP publication (pages 97 - 99).
Also included in the appendices are the previously published traffic forecasts (Appendix D) and a log of all the consultation fora and working groups since the publication of the previous CIP, highlighting subjects discussed and decisions made (Appendix e & F).
A copy of Annex G is included for reference (Appendix G). A copy of the indicative 2020 Gatwick Airport Layout plan, extracted from the published final Master Plan, was provided in the 2012 CIP publication. (Refer to Appendix H, page 119 in the 2012 CIP). A copy of the updated GAL Product Matrix is included in Appendix H.
In line with Annex G this CIP document should be regarded as a product of consultation at the time of publication and also as a basis for future consultation and thus, does not represent a mandatory investment programme.
FEEdbACK
This document was originally circulated amongst the JSG ACC members at Gatwick as a draft publication for consultation in April 2013, with a request for feedback. The period for formal feedback has since expired and this is the final version of the 2013 Gatwick CIP. We do of course value feedback throughout the year. The feedback will help us improve Gatwick’s future Capital plans.
If you have any queries on this document, or would like to comment, please email Neermala Khoobarry: [email protected].
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
5CHAPTER 11.1 Updated traffic forecasts
introdUction
As reported in previous CIP publications, we have commissioned ICF SH&E, a leading aviation consultancy to produce an independent view of the future demand for Gatwick. To align with the latest economic outlook, the forecasts were updated in September 2012. These latest forecasts are outlined in the following sections and were included in the revised GAL business plan.
overview of 2012/13
Gatwick is the UK’s second busiest airport. It is a vital part of the UK’s transport infrastructure offering more travel destinations than any other London airport. Gatwick’s operations are very much aligned to the needs of those travelling to and from London and the South East.
In 2012/13, Gatwick handled 34.2 million passengers; 1.2% more than in 2011/12 (33.8m). It is however 3.7% (1.3m passengers) below 2007/08 when 35.6m passengers were processed at Gatwick.
Growth was achieved through:
• Incumbent airlines such as easyJet, British Airways and Norwegian Air Shuttle growing frequencies on existing routes and with higher load factors
• New airlines operating out of Gatwick including Air China, Air Arabia Maroc, Iraqi Airways, Icelandair, WOW Air, Caribbean Airlines, Vueling and Gambia Bird all commenced operations at London Gatwick
• Newroutesbeingopened,includingeasyJetflyingtoMoscow,NorwegianAirShuttleopeningthefirstof 12 new routes, and British Airways increasing its services in Europe and the Caribbean
Converselyandreflectingtherealcompetitioninthemarket,someairlinesreducedservicesorceasedto operate at Gatwick. Ryanair withdrew all non-Irish routes, Korean Air consolidated winter services at Heathrow after renewed competition from BA, Adria Airways relocated to Luton and more recently, Air Moldova moved operations to Stansted.
Gatwick saw passenger load factors go up 1.4% points in 2012/13 (82.6%) compared to 2011/12 (81.2%). Capacity improved 1.1% as seats per movement increased from 172 in 2011/12 to 174 in 2012/13.
One of Gatwick’s strengths is its range of airline services and routes. Typically in 2012/13, Gatwick was served by 60 regularly operating passenger airlines, comprising a mix of full service, low cost, and charter airlines.Onaverage,passengerairlinesoperated653dailyflights.
Gatwick’stwolargestcarriersaccountforoverhalfthepassengertrafficatGatwick.easyJetisthelargest,accountingfor40%ofpassengertraffic,whileBritishAirwaysaccountsfor15%.
In2012/13,airlinesoperatingatGatwickflewatleastoneflightaweektoover200destinations.In2012/13, 88.8% of passengers travelled on international services and 11.2% on domestic. The majority of passengers were on short-haul routes to destinations in the UK and Europe, though a number of long-haul destinations such as Orlando, Dubai, Sharm El Sheikh, Bridgetown and Cancun are among Gatwick’s busiest services.
ThevarietyofaircrafttypesoperatingatGatwickreflectsadiversemixofairlinesandroutes.Narrow-bodyjetaircraftsuchastheBoeing737andAirbusA320arethemostcommontype,reflectingthedominanceofshort-haul operations. These account for 77.1% of total passenger operations.
Wide-body jet aircraft such as the B777 and B747 account for 8.1% of passenger operations and are typically deployed on long-haul routes to North America, the Caribbean, the Middle East and Far East.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
6
Regional jets and turboprop aircraft account for approximately 10.6% of passenger operations. Flybe is the main regional jet and turboprop operator, operating many of the domestic routes from Gatwick.
Marginal growth is forecast in 2013/14 as there are a number of airlines and routes that will no longer operateinthecomingfinancialyear.Theconstrainedeconomicclimatehasalsobeentakenintoconsideration.
Key drivers for demand
The demand for air travel is considered a derived demand, in that it is not demanded for its own sake, but rather to facilitate the movement of goods and people for business or leisure purposes.
As such, the main drivers of demand for air travel are the growth in economic activity, international trade, inbound and outbound tourism, the relative cost of air travel compared to other modes and other factors such as tastes and fashions, taxation and environmental legislation.
Economic activity shows strong historical correlation with air travel across many markets and GDP has been used by ICF SH&E as one of the key drivers of long term growth in these forecasts. It captures many of the keytrendsdrivingdemand,includingBusinessconfidence,Populationgrowth,Leisurespendingand Market maturity.
The current economic outlook for the UK continues to be weak and rather uncertain, although most independent commentators expect eventual recovery to positive growth following the recent widespread recession.Intheselongtermforecasts,abalancedviewhasbeentaken,whichreflectsrecoveryinthenearterm being modest but positive growth over the long run.
The economic headwinds buffeting aviation in the UK, such as fuel prices, APD, environmental legislation, dampeneddisposableincomesamongstothersarereflectedinthelowelasticityofdemandassumedforthe London market as a whole, considerably below the levels experienced historically.
external negative shocKs
In the UK, there has historically been a strong and consistent relationship between GDP and Air Travel, consistent with the basic premise that as incomes and economic activity increase, business and leisure demand also increase. This relationship has generally held during downturns also. For example, when there has been a recession, and economic growth has turned negative, demand for UK air travel has fallen also.
Atanindividualairportlevel,trafficgrowthtendstoshowgreatervariability,duetoothermarket-specificshocks such as the arrival or departure of a new airline, or based on local disruption weather, construction or political unrest.
Gatwick’straffichasexperiencedshocksovertime,duetoacombinationofbothbroadernationalandinternational shocks such as war, oil price hikes and recessions, as well as more local shocks such as weather disruption or the arrival or departure of based airlines.
assUmptions - general
ThethreetrafficscenariosproducedintheseforecastsareintendedtoprovidealikelyrangeofgrowthprofilesforGatwickovertheforecasthorizon.Asetofoptimisticandpessimisticassumptionshavebeenanalysed and a set of scenarios created, which provide a reasonable boundary for upside and downside risk. Over the very long term, the three cases converge towards the assumed runway capacity of Gatwick, beyond which they all grow very modestly.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
7
low case scenario
Thelowcasereflectsthedownsideriskintheforecasts,withamorepessimisticsetofassumptionsinboththe short and the long term. Possible scenarios include:
• Even lower economic growth, for a prolonged period
• Fuel price hike, leading to higher fares
• Loss of recently gained long haul services, and/or established carriers due to competition
Base case scenario
Inthefirstthreeyears,growthisdrivenbyknownandexpectedcapacityadditionsbyexistingandnewcarriers. The base case takes a balanced view of both positive and negative factors. Over the long term, aGDPelasticityofaroundunityisassumedinthebasecase,reflectinganon-goinglinktoeconomicgrowth,butalsoincreasingmarketmaturityandacombinationofnegativeinfluencesondemand,suchasincreasing air travel costs relative to other modes.
high case scenario
Thehighcaseisintendedtoreflectareasonableoptimisticscenario,illustratingasetofpositiveconditionsbut remaining within previously sustained growth rates seen at Gatwick. Possible scenarios include:
• Faster economic recovery and higher sustained growth rates
• Greater success in capturing market share from other London airports
The High case is considered appropriate for the purposes of capacity planning, as it provides an indication ofthemaximumlikelytrafficvolumeatGatwickovertheplanninghorizon.
As with all forecasts, actual events may, and probably will, differ from those assumed previously.
comparison Between 2012 forecast Used in gatwicK airport limited’s (gal) initial BUsiness plan, pUBlished april 2012 and the septemBer 2012 Updated forecasts
ThetablesbelowshowthepassengerandairtrafficmovementforecastspreparedinFebruary2012byICFSH&E and the subsequent re-forecast exercise by ICF SH&E in September 2012. The updated September 2012 forecast has been adopted by Gatwick for the three scenarios, Base, High and Low.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
8
February 2012 September 2012
Low Base High Low Base High
Q5 2008/09 actual 33.1 33.1 33.1 33.1 33.1 33.1
2009/10 actual 32.4 32.4 32.4 32.4 32.4 32.4
2010/11 actual 31.6 31.6 31.6 31.6 31.6 31.6
2011/12 actual 32.5 33.3 33.9 33.8 33.8 33.8
2012/13 33.8 34.6 35.2 33.4 33.8 33.9
2013/14 33.9 35.2 36.7 32.8 34.0 34.7
Beyond Q5 2014/15 34.2 35.7 37.8 33.0 34.5 35.8
2015/16 34.3 36.0 38.8 32.8 34.7 36.6
2016/17 34.6 36.4 39.7 32.7 35.0 37.4
2017/18 34.8 36.8 40.4 32.8 35.4 38.2
2018/19 35.1 37.3 41.1 32.9 35.9 39.2
February 2012
Passenger ATMs Base Case
Q5 Low Base High CATM* Non-ATM**
2008/09 actual - - - - -
2009/10 actual 244.4 244.4 244.4 0.06 6.8
2010/11 actual 235.6 235.6 235.6 0.16 6.8
2011/12 actual 242.1 242.1 242.1 0.35 6.2
2012/13 237.7 238.9 239.0 0.35 6.2
2013/14 232.6 239.5 243.5 0.35 6.2
Beyond Q5 2014/15 233.6 242.8 250.2 0.35 6.2
2015/16 231.0 243.8 254.2 0.35 6.2
2016/17 229.5 244.8 259.2 0.36 6.1
2017/18 228.7 246.4 264.4 0.36 6.1
2018/19 228.9 248.8 270.7 0.36 6.0
Growth Rate p.a.(2014/15 - 2018/19) -0.2% -0.6% 0.3% - -
Growth Rate p.a.(2014/15 - 2018/19) -0.5% 0.6% 2.0% - -
*CATM:CargoAirTransportMovementsi.e.CommercialCargoflights**Non-ATM:NonAirTrafficMovementsi.e.GeneralAviation,AirTaxi
As the overall economic outlook continues to deteriorate, GAL is undertaking a further refresh of the forecasts which are anticipated to be available for the Business Plan update due July 2013. The fortunes oftheEurozonewillbecriticalandtherecentsaleofStanstedAirportbyBAAtotheManchesterAirportGroup (MAG) will intensify the competition with Gatwick for airlines and passengers. These current uncertaintiesmaketrafficforecastingparticularlychallengingatthistime.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
9
Using gatwicK traffic forecasts to determine facility reQUirements
The driver for infrastructure capacity is peak demand. The need for infrastructure to satisfy the peak demand remains, regardless of annual passenger numbers as some slots will always be more commercially viable as certain times of the day are more attractive to passengers. It is for this reason that the busy day schedule and medium term forecasts are used to model facility requirements looking forward ten years.
The previous 2012 CIP included a detailed explanation of how GAL approaches the generation of a busy day schedule and then how that it is converted in order to understand the demand for facilities.
gatwicK terminal facilities - cUrrent and forecast
The tables that follow show the future forecast terminal facility requirements at Gatwick until 2020/21 in NorthTerminal,SouthTerminalandtheAirfield,usingthebusydayschedulestoassessdemand.Theservice level assumptions that have been used in these assessments are quoted in the tables that follow.
Gatwick Nt Facilities: existiNG aNd Forecast to 2020/2021 with raG status iNcludiNG Q5 & Q5+1 developmeNt
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Glossary
1 2 3 4 C D G HAppendix
Eea
sYJe
t sp
lit B
etw
eeN
term
iNal
s &
eZY
coNs
olid
ated
iN N
ort
h te
rmiN
al; h
iGh
case
aNd
Bas
e ca
seC
urre
nt p
rovi
sion
Serv
ice
Stan
dard
s as
sum
ed
in a
sses
smen
tsSu
mm
er 2
012,
bas
ed o
n ac
tual
sch
edul
eSH
&E
HIG
H C
ASE
201
6/17
(37.
5 m
ppa)
Faci
litie
s re
quire
d by
Sum
mer
201
6
SH&
E H
IGH
CA
SE 2
020/
21 (4
1 m
ppa)
Faci
litie
s re
quire
d by
Sum
mer
202
0
Airl
ine
/ Te
rmin
al
Ass
umpt
ions
EZY
split
bet
wee
n N
T &
ST
N
o To
p 10
car
rier m
oves
EZY
split
bet
wee
n N
T &
ST
N
o To
p 10
car
rier m
oves
EZY
split
bet
wee
n N
T &
ST
EZ
Y ba
lanc
e sh
ift to
ST
with
Pie
r 1 re
open
N
o To
p 10
car
rier m
oves
AN
NU
AL
PAX
ST: ~
16.9
mpp
a N
T: ~
17.2
mpp
aST
: ~18
.8m
ppa
NT:
~18
.8m
ppa
ST: ~
20.5
mpp
a N
T: ~
20.5
mpp
a
TOTA
L B
USY
DAY
M
OVE
MEN
TS86
8
(Aug
ust F
riday
sch
edul
e, s
naps
hop
at F
eb12
)88
894
3
MA
XIM
UM
HO
URL
Y M
OVE
MEN
TS53
5355
NO
RTH
TER
MIN
AL
BU
SY H
OU
R D
EPA
RTU
RES
RUN
WAY
FLO
W31
00 (r
ollin
g ho
ur)
3730
(rol
ling
hour
) [ro
lling
eve
ry 3
0 m
ins]
3760
(rol
ling
hour
) [ro
lling
eve
ry 3
0 m
ins]
INTE
RNA
TIO
NA
L A
RRIV
ALS
B
USY
HO
UR
RUN
WAY
FL
OW
2250
(rol
ling
hour
)24
00 (r
ollin
g ho
ur) [
rolli
ng e
very
30
min
s]27
50 (r
ollin
g ho
ur) [
rolli
ng e
very
30
min
s]
DO
MES
TIC
ARR
IVA
LS B
USY
H
OU
R RU
NW
AY F
LOW
550
(rolli
ng h
our)
540
(rolli
ng h
our)
[rolli
ng e
very
30
min
s]54
0 (ro
lling
hou
r) [ro
lling
eve
ry 3
0 m
ins]
CH
ECK
-IND
esk
Prov
isio
n: 1
59
Kio
sk P
rovi
sion
: 38
Bus
y H
our F
low
: ~31
50
@ 0
500
Bus
y H
our F
low
: ~33
50
@ 0
500
Bus
y H
our F
low
: ~36
00
@ 0
500
Econ
omy:
max
imum
que
ue
time
of 1
0 m
inut
es in
tota
l on
the
busy
day
(5 m
inut
es
each
for k
iosk
s an
d ba
g dr
op).
C
IP: m
axim
um q
ueue
tim
e of
3 m
inut
es in
tota
l at
trad
ition
al d
esks
Ass
umin
g 20
11 C
heck
In ty
pe s
plits
& c
heck
-in
open
s at
-4h
for L
H a
nd -2
.5h
for S
H, T
radi
tiona
l D
esk
and
Bag
Dro
p @
90%
Util
isat
ion,
and
10%
Se
rvic
e D
esk
Upl
ift
To
tal T
radi
tiona
l Des
k D
eman
d : 1
00
Tota
l Bag
Dro
p D
eman
d: 2
1 C
omib
ined
Tra
ditio
nal D
esk
& B
ag D
rop
Dem
and:
121
Kio
sk D
eman
d @
100%
Util
isat
ion:
15
- 35
Ass
umin
g an
ytim
e ch
eck-
in, T
radi
tiona
l Des
k an
d B
ag D
rop
@90
% U
tilis
atio
n, a
nd 1
0%
Serv
ice
Des
k U
plift
Tota
l Tra
ditio
nal D
esk
Dem
and:
63
Tota
l Bag
Dro
p D
eman
d: 3
6 C
omib
ined
Tra
ditio
nal D
esk
& B
ag D
rop
Dem
and:
99
K
iosk
Dem
and
@10
0% U
tilis
atio
n: 1
8 - 6
9
Ass
umin
g an
ytim
e ch
eck-
in, T
radi
tiona
l D
esk
and
Bag
Dro
p @
90%
Util
isat
ion,
an
d 10
% S
ervi
ce D
esk
Upl
ift
To
tal T
radi
tiona
l Des
k D
eman
d : 5
0 To
tal B
ag D
rop
Dem
and:
50
Com
ibin
ed T
radi
tiona
l Des
k &
Bag
Dro
p D
eman
d: 1
00
K
iosk
Dem
and
@10
0% U
tilis
atio
n:
18 -
79
BA
GG
AG
E SY
STEM
- C
HU
TES
/ M
UPs
MB
H P
rovi
sion
: 54
MU
Ps
TBF
Prov
isio
n: 9
4 M
UPs
Ass
umpt
ions
app
lied
to
figur
es fr
om 2
016:
onc
e EB
S op
ens
pass
enge
rs c
an
chec
k in
bag
s on
arr
ival
at
airp
ort.
Shor
t-ha
ul c
hute
s op
en 9
0 m
inut
es b
efor
e ST
D, l
ong-
haul
180
min
utes
. Chu
tes
clos
e 30
min
utes
bef
ore
STD
, with
15
min
ute
buffe
r fo
r suc
cess
ive
fligh
ts.
100%
LFs
and
20%
co
ntin
genc
y up
lift.
Ass
ume
SH c
hute
s op
en a
t STD
-150
min
s, L
H
at S
T-24
0 m
ins.
Som
e ch
utes
cha
nge
betw
een
hand
lers
dur
ing
the
day.
Chu
tes
clos
e 30
m
inut
es b
efor
e ST
D, w
ith 1
5 m
inut
e bu
ffer f
or
succ
essi
ve fl
ight
s.
A
ssum
ptio
n: S
wis
spor
t exc
ludi
ng B
A in
MB
H,
othe
rs in
TB
F M
BH
Req
uire
men
t: M
UPs
38
TBF
Requ
irem
ent:
MU
Ps 8
6
Ass
umpt
ion:
Sw
issp
ort e
xclu
ding
BA
in M
BH
, ot
hers
in T
BF
SH
chu
te o
peni
ng a
t STD
-150
, LH
at S
TD-2
40,
clos
e at
STD
-30
with
15
min
buf
fer:
M
BH
Req
uire
men
t: M
UPs
34
TB
F Re
quire
men
t: M
UPs
98
A
fter
EB
S ch
ute
open
ing
at S
H S
TD-9
0, L
H
STD
-180
: M
BH
Req
uire
men
t: M
UPs
22
TB
F Re
quire
men
t: M
UPs
70
Aft
er E
BS
chut
e op
enin
g at
SH
STD
-90,
LH
STD
-180
:
Ass
umpt
ion:
Sw
issp
ort e
xclu
ding
BA
in
MB
H, o
ther
s in
TB
F M
BH
Req
uire
men
t: M
UPs
31
TBF
Requ
irem
ent:
MU
Ps 7
6
Ass
umpt
ion:
BA
in M
BH
, oth
ers
in T
BF
MB
H R
equi
rem
ent:
MU
Ps 4
4 TB
F Re
quire
men
t: M
UPs
73
BA
GG
AG
E SY
STEM
- EA
RLY
BA
G S
TORE
Early
Bag
Sto
re: M
BH
0,
TBF
0
Requ
irem
ent:
Spar
e ch
utes
to s
tore
ear
ly b
ags
at p
eak,
to e
nabl
e so
me
carr
iers
to c
ontin
ue
anyt
ime
chec
k-in
.
Ass
umpt
ion:
Sw
issp
ort e
xclu
ding
BA
in M
BH
, ot
hers
in T
BF
MB
H: 4
30 b
ags
= 1
1 M
UPs
at 4
0 ba
gs /
MU
P TB
F: 2
50 b
ags
= 7
MU
Ps a
t 40
bags
/ M
UP
Ass
umpt
ion:
Sw
issp
ort e
xclu
ding
BA
in M
BH
, ot
hers
in T
BF
A
fter
EB
S op
enin
g an
d SH
chu
te o
peni
ng S
TD-
90, L
H S
TD-1
80:
MB
H R
equi
rem
ent:
EBS
1,27
0
TBF
Requ
irem
ent:
EBS
1,33
0
[S
ingl
e EB
S 2,
260]
Aft
er E
BS
open
ing
and
SH c
hute
op
enin
g ST
D-9
0, L
H S
TD-1
80:
A
ssum
ptio
n: S
wis
spor
t exc
ludi
ng B
A in
M
BH
, oth
ers
in T
BF
MB
H R
equi
rem
ent:
EBS
1,26
0 TB
F Re
quire
men
t: EB
S 1,
420
A
ssum
ptio
n: B
A in
MB
H, o
ther
s in
TB
F M
BH
Req
uire
men
t: EB
S 86
0 TB
F Re
quire
men
t: EB
S 1,
860
[S
ingl
e EB
S 2,
380]
CEN
TRA
L SE
ARC
HW
20 la
nes
Econ
omy:
bus
y ho
ur
pass
enge
rs d
o no
t que
ue
for l
onge
r tha
n 5
min
utes
on
the
busy
day
CIP
: bus
y ho
ur p
asse
nger
s do
not
que
ue fo
r lon
ger
than
1 m
inut
e on
the
busy
da
y
18 la
nes
@ 2
00 p
ph th
roug
hput
s19
lane
s @
200
pph
thro
ughp
uts.
21 la
nes
@ 2
00 p
ph th
roug
hput
s
IDL
TOTA
L A
REA
IDL
tota
l spa
ce: ~
14,1
50m
2 (D
ec12
aud
it)0.
45 -
0.50
sea
ts p
er p
eak
occu
panc
y pa
x;
1.3m
2 per
sea
t;
Re
tail
/ ca
terin
g - b
ased
on
GA
L co
mm
erci
al s
tand
ards
: 1.
3m2 f
or a
ll ID
L pa
x, 4
0% in
ca
terin
g;
3.0m
2 for
all
IDL
pax,
35%
in
reta
il;
C
ircul
atio
n sp
ace:
20%
-30%
of
tota
l ID
L sp
ace
Ass
umin
g ch
eck-
in o
pens
at -
4h fo
r LH
and
-2
.5h
for S
H: B
usy
Day
Pea
k O
ccup
ancy
: ~26
00
To
tal I
DL
spac
e re
com
men
ded:
at l
east
16
,100
m2 (
excl
udin
g to
ilets
, spe
cial
loun
ges,
re
tail
stor
age
etc)
.
Ass
umin
g an
ytim
e ch
eck-
in: B
usy
Day
Pea
k O
ccup
ancy
: ~29
90
To
tal I
DL
spac
e re
com
men
ded:
at l
east
18
,500
m2 (
excl
udin
g to
ilets
, spe
cial
loun
ges,
re
tail
stor
age
etc)
.
Ass
umin
g an
ytim
e ch
eck-
in: B
usy
Day
Pe
ak O
ccup
ancy
: ~34
00
To
tal I
DL
spac
e re
com
men
ded:
at l
east
20
,800
m2 (
excl
udin
g to
ilets
, spe
cial
lo
unge
s, re
tail
stor
age
etc)
.
IDL
SEA
TIN
G, R
ETA
IL &
C
ATE
RIN
G
Seat
ing
prov
isio
n: 1
200
(incl
udin
g 44
PRM
sea
ts)
C
ater
ing
area
pro
visi
on:
3000
m2 (
incl
udin
g ki
tche
n an
d ot
her n
on-p
asse
nger
ar
eas)
, with
157
7 se
ats
Re
tail
area
pro
visi
on:
4720
m2 .
Indi
cativ
e se
at re
quire
men
t 117
0 - 1
300,
to
mee
t tar
get Q
SM s
core
, but
this
is a
‘sof
t’ co
nstr
aint
.
Cat
erin
g ar
ea re
quire
men
t: up
to 3
,400
m2
Re
tail
area
requ
irem
ent:
up to
7,8
00m
2 .
Indi
cativ
e se
at re
quire
men
t 135
0 - 1
500,
to
mee
t tar
get Q
SM s
core
, but
this
is a
‘sof
t’ co
nstr
aint
.
Cat
erin
g ar
ea re
quire
men
t: up
to 3
,900
m2
Re
tail
area
requ
irem
ent:
up to
8,9
00m
2 .
NB
Ret
ail a
rea
prov
isio
n to
redu
ce a
fter
201
4 w
ith e
xpan
sion
to 2
0 se
curit
y sm
artla
nes
Indi
cativ
e se
at re
quire
men
t 153
0 - 1
700,
to
mee
t tar
get Q
SM s
core
, but
this
is a
‘s
oft’
cons
trai
nt.
C
ater
ing
area
requ
irem
ent:
up to
4,
400m
2
Reta
il ar
ea re
quire
men
t: up
to 1
0,20
0m2 .
N
B R
etai
l are
a pr
ovis
ion
to re
duce
aft
er
2014
with
exp
ansi
on to
20
secu
rity
smar
tlane
s
FLIG
HT
CO
NN
ECTI
ON
SC
urre
nt c
apac
ity 2
lane
s;
can
expa
nd to
3 la
nes
Bus
y ho
ur p
asse
nger
s do
no
t que
ue fo
r lon
ger t
han
5 m
inut
es o
n th
e bu
sy d
ay
2 la
nes
@ 2
00 p
ph th
roug
hput
s
(for m
ost o
f the
day
1 la
ne is
suf
ficie
nt)
2 la
nes
@ 2
00 p
ph th
roug
hput
s2
lane
s @
200
pph
thro
ughp
uts
IMM
IGRA
TIO
N IN
FLO
W
Bus
y ho
ur E
U p
asse
nger
s do
not
que
ue fo
r lon
ger
than
10
min
utes
; B
usy
hour
non
-EU
pa
ssen
gers
do
not q
ueue
fo
r lon
ger t
han
20 m
inut
es.
Bus
y H
our F
low
: ~22
00
@ 1
900
Bus
y H
our F
low
: ~24
50
@ 1
200
Bus
y H
our F
low
: ~30
00
@ 0
700
IMM
IGRA
TIO
N D
ESK
STr
aditi
onal
des
k pr
ovis
ion:
17
EU
E-g
ate
prov
isio
n: 5
Rang
e of
des
k re
quire
men
ts
depe
ndin
g on
pro
activ
e or
re
activ
e de
sk o
peni
ng.
Trad
ition
al d
esk
requ
irem
ent:
24-3
2 EU
E-g
ate
requ
irem
ent:
9-11
Figu
res
assu
me
no im
prov
emen
t in
tran
sact
ion
times
, fro
m 2
011
surv
ey: E
U T
rad
21se
c, E
U
E-ga
te 3
5sec
, N
EU 1
10se
c (e
asy)
/ 3
00se
c (h
ard)
EU
E-g
ate
reje
ct ra
te o
f 20%
with
reje
ct ti
me
of
10se
c be
fore
pax
use
s EU
Tra
d de
sk
Es
t max
. Frid
ay q
ueue
tim
es o
f no
build
are
20
min
s (E
U) a
nd 4
5 m
ins
(non
-EU
)
Trad
ition
al d
esk
requ
irem
ent:
22-2
7 EU
E-g
ate
requ
irem
ent:
12-1
3
Figu
res
assu
me
no im
prov
emen
t in
tran
sact
ion
times
, fro
m 2
011
surv
ey: E
U T
rad
21se
c, E
U
E-ga
te 3
5sec
, N
EU 1
10se
c (e
asy)
/ 3
00se
c (h
ard)
EU
E-g
ate
reje
ct ra
te o
f 20%
with
reje
ct ti
me
of
10se
c be
fore
pax
use
s EU
Tra
d de
sk
N
ew E
U E
-gat
es w
ith a
tran
sact
ion
time
of
15se
c w
ould
mea
n a
redu
ced
requ
irem
ent o
f 6
gate
s
Trad
ition
al d
esk
requ
irem
ent:
25-3
0 EU
E-g
ate
requ
irem
ent:
14-1
7
Figu
res
assu
me
no im
prov
emen
t in
tran
sact
ion
times
, fro
m 2
011
surv
ey: E
U
Trad
21s
ec, E
U E
-gat
e 35
sec,
N
EU 1
10se
c (e
asy)
/ 3
00se
c (h
ard)
EU
E-g
ate
reje
ct ra
te o
f 20%
with
reje
ct
time
of 1
0sec
bef
ore
pax
uses
EU
Tra
d de
sk
N
ew E
U E
-gat
es w
ith a
tran
sact
ion
time
of 1
5sec
wou
ld m
ean
a re
duce
d re
quire
men
t of 8
gat
es
REC
LAIM
BEL
TSC
urre
nt p
rovi
sion
9 In
t bel
ts
(of w
hich
1 lo
ng) a
nd 2
Dom
be
lts.
Bel
t ava
ilabl
e fo
r all
fligh
ts d
urin
g bu
sy h
our,
to s
uppo
rt K
PI o
f all
pax
rece
ivin
g ba
ggag
e w
ithin
45
min
utes
of a
rriv
al o
n st
and.
Requ
irem
ent:
INT:
6-8
(of w
hich
1 lo
ng 7
0m+
be
lt, w
ith n
o w
ideb
ody
fligh
ts e
xpec
ted
to b
e sp
lit o
ver 2
bel
ts).
D
OM
: 1 b
elt j
ust s
uffic
ient
thou
gh 2
wou
ld b
e id
eal t
o re
duce
con
gest
ion
at p
eak
times
.
Requ
irem
ent:
INT:
7-8
bel
ts (o
f whi
ch id
eally
2
long
70m
+ b
elts
, alth
ough
1 lo
ng b
elt w
ould
be
suf
ficie
nt, c
ausi
ng o
nly
1 w
ideb
ody
fligh
t to
be s
plit
over
2 b
elts
).
A38
0 ar
rival
idea
lly re
quire
s 2
belt
feed
s to
a
long
bel
t, to
impr
ove
bagg
age
deliv
ery
time.
DO
M: 1
bel
t jus
t suf
ficie
nt; 2
bel
t fee
ds w
ould
be
requ
ired
to a
void
som
e fli
ghts
pot
entia
lly
expe
rienc
ing
5-10
min
ute
dela
ys in
acc
essi
ng it
.
INT:
7-8
bel
ts (o
f whi
ch 2
long
70m
+
belts
to h
andl
e w
ideb
odie
s on
a s
ingl
e be
lt; w
ith o
nly
1 lo
ng b
elt u
p to
5
wid
ebod
ies
in th
e m
orni
ng p
eak
are
split
ove
r 2 b
elts
or d
elay
ed b
y up
to 2
0 m
inut
es in
acc
essi
ng th
e lo
ng b
elt)
A
380
arriv
als
idea
lly re
quire
2 b
elt f
eeds
to
a lo
ng b
elt,
to im
prov
e ba
ggag
e de
liver
y tim
e.
D
OM
: 1 b
elt j
ust s
uffic
ient
; 2 b
elt f
eeds
w
ould
be
requ
ired
to a
void
som
e fli
ghts
po
tent
ially
exp
erie
ncin
g 5-
10 m
inut
e de
lays
in a
cces
sing
it.
LAN
DSI
DE
RETA
IL &
C
ATE
RIN
G
Cat
erin
g ar
ea p
rovi
sion
(lo
wer
& A
venu
e le
vels
): 1,
250m
2 Re
tail
area
pro
visi
on (l
ower
&
Ave
nue
leve
ls):
2,10
0m2
Arr
ival
s co
ncou
rse
non-
com
mer
cial
are
a (lo
wer
le
vel o
nly)
: 1,4
00m
2
Land
side
pea
k oc
cupa
ncy:
A
rriv
als
conc
ours
e pe
ak
occu
panc
y is
~16
% o
f pea
k ho
ur fl
ow +
La
ndsi
de d
wel
l ass
umed
~
10 m
inut
es o
n av
erag
e.
1.
3m2 c
ater
ing
area
per
pe
rson
at p
eak
occu
panc
y.
0.8
- 1.0
m2 r
etai
l are
a pe
r pe
rson
at p
eak
occu
panc
y N
on-c
omm
erci
al a
rea:
2.
3m2 p
er p
asse
nger
at
peak
Arr
ival
s co
ncou
rse
peak
occ
upan
cy: 3
70
Land
side
dep
artu
res
peak
occ
upan
cy: 5
30
Com
bine
d la
ndsi
de p
eak
occu
panc
y: u
p to
900
Cat
erin
g ar
ea re
quire
men
t: up
to 1
,170
m2
Reta
il ar
ea re
quire
men
t: 72
0 - 9
00m
2 A
rriv
als
conc
ours
e no
n-co
mm
erci
al a
rea:
850
m2
Arr
ival
s co
ncou
rse
peak
occ
upan
cy: 4
20
Land
side
dep
artu
res
peak
occ
upan
cy: 5
70
Com
bine
d la
ndsi
de p
eak
occu
panc
y: u
p to
990
Cat
erin
g ar
ea re
quire
men
t: up
to 1
,290
m2
Reta
il ar
ea re
quire
men
t: 79
0 - 9
90m
2 A
rriv
als
conc
ours
e no
n-co
mm
erci
al a
rea:
970
m2
Arr
ival
s co
ncou
rse
peak
occ
upan
cy: 5
10
Land
side
dep
artu
res
peak
occ
upan
cy:
600
Com
bine
d la
ndsi
de p
eak
occu
panc
y:
up to
111
0
Cat
erin
g ar
ea re
quire
men
t: up
to
1,44
0m2
Reta
il ar
ea re
quire
men
t: 89
0 - 1
,110
m2
Arr
ival
s co
ncou
rse
non-
com
mer
cial
are
a:
1170
m2
10
Gatwick st Facilities: existinG and Forecast to 2020/2021 with raG status includinG Q5 & Q5+1 development
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Glossary
1 2 3 4 C D G HAppendix
Eea
sYJe
t sp
lit B
etw
een
term
inal
s &
eZY
cons
olid
ated
in s
out
h te
rmin
al; h
iGh
case
and
Bas
e ca
seC
urre
nt p
rovi
sion
Serv
ice
Stan
dard
s as
sum
ed in
as
sess
men
tsSu
mm
er 2
012,
bas
ed o
n ac
tual
sc
hedu
le
SH&
E H
IGH
CA
SE 2
016/
17 (3
7.5
mpp
a)
Fa
cilit
ies
requ
ired
by S
umm
er 2
016
SH&
E H
IGH
CA
SE 2
020/
21 (4
1 m
ppa)
Faci
litie
s re
quire
d by
Sum
mer
202
0
Airl
ine
/ Te
rmin
al A
ssum
ptio
nsEZ
Y sp
lit b
etw
een
NT
& S
T
No
Top
10 c
arrie
r mov
es
EZY
split
bet
wee
n N
T &
ST
N
o To
p 10
car
rier m
oves
EZY
split
bet
wee
n N
T &
ST
EZ
Y ba
lanc
e sh
ift to
ST
with
Pie
r 1 re
open
N
o To
p 10
car
rier m
oves
AN
NU
AL
PAX
ST: ~
16.9
mpp
a N
T: ~
17.2
mpp
aST
: ~18
.8m
ppa
NT:
~18
.8m
ppa
ST: ~
20.5
mpp
a N
T: ~
20.5
mpp
a
TOTA
L B
USY
DAY
M
OVE
MEN
TS
868
(A
ugus
t Frid
ay s
ched
ule,
sna
psho
p at
Feb
12)
888
943
MA
XIM
UM
HO
URL
Y M
OVE
MEN
TS53
5355
Sou
th t
ERM
INA
LB
USY
HO
UR
DEP
ART
URE
S RU
NW
AY F
LOW
3700
(rol
ling
hour
)39
50 (r
ollin
g ho
ur) [
rolli
ng e
very
30
min
]42
50 (r
ollin
g ho
ur) [
rolli
ng e
very
30
min
]
INTE
RNA
TIO
NA
L A
RRIV
ALS
B
USY
HO
UR
RUN
WAY
FLO
W28
00 (r
ollin
g ho
ur)
2680
(rol
ling
hour
) [ro
lling
eve
ry 3
0 m
in]
3100
(rol
ling
hour
) [ro
lling
eve
ry 3
0 m
in]
DO
MES
TIC
ARR
IVA
LS B
USY
H
OU
R RU
NW
AY F
LOW
430
(rolli
ng h
our)
380
(rolli
ng h
our)
[rolli
ng e
very
30
min
]38
0 (ro
lling
hou
r) [ro
lling
eve
ry 3
0 m
in]
CH
ECK
-IN
Bus
y H
our F
low
: ~36
00
@ 0
700
Bus
y H
our F
low
: ~36
00
@ 0
700
Bus
y H
our F
low
: ~35
20
@ 0
700
Tota
l Tra
ditio
nal /
Bag
Dro
p D
esk
Prov
isio
n: 1
86
Tota
l Kio
sk P
rovi
sion
: 31
Econ
omy:
max
imum
que
ue
time
of 1
0 m
inut
es in
tota
l on
the
busy
day
(5 m
inut
es e
ach
for k
iosk
s an
d ba
g dr
op).
C
IP: m
axim
um q
ueue
tim
e of
3
min
utes
in to
tal a
t tra
ditio
nal
desk
s
Ass
umin
g 20
11 C
heck
In ty
pe
split
s &
che
ck-in
ope
ns a
t -4
h fo
r LH
and
-2.5
h fo
r SH
, Tr
aditi
onal
Des
k an
d B
ag D
rop
@90
% U
tilis
atio
n, a
nd 1
0%
Serv
ice
Des
k U
plift
:
Tota
l Tra
ditio
nal D
esk
Dem
and:
159
To
tal B
ag D
rop
Dem
and:
35
Com
bine
d Tr
aditi
onal
Des
k &
B
ag D
rop
Dem
and:
194
Kio
sk D
eman
d @
100%
U
tilis
atio
n: 1
4 - 3
4
Ass
umin
g an
ytim
e ch
eck-
in, T
radi
tiona
l Des
k an
d B
ag D
rop
@90
% U
tilis
atio
n, a
nd 1
0%
Serv
ice
Des
k U
plift
Tota
l Tra
ditio
nal D
esk
Dem
and:
104
To
tal B
ag D
rop
Dem
and:
30
Com
bine
d Tr
aditi
onal
Des
k &
Bag
Dro
p D
eman
d: 1
34
K
iosk
Dem
and
@10
0% U
tilis
atio
n: 1
6 - 4
7
Ass
umin
g an
ytim
e ch
eck-
in, T
radi
tiona
l Des
k an
d B
ag D
rop
@90
% U
tilis
atio
n, a
nd 1
0%
Serv
ice
Des
k U
plift
Tota
l Tra
ditio
nal D
esk
Dem
and:
70
Tota
l Bag
Dro
p D
eman
d: 4
4 C
ombi
ned
Trad
ition
al D
esk
& B
ag D
rop
Dem
and:
114
Kio
sk D
eman
d @
100%
Util
isat
ion:
17
- 67
BA
GG
AG
E SY
STEM
- M
AK
E U
P PO
SITI
ON
SPr
ovis
ion:
~14
3 us
eabl
e M
UPs
Ass
umpt
ions
app
lied
to fi
gure
s fro
m 2
016:
onc
e EB
S op
ens
pass
enge
rs c
an c
heck
in b
ags
on a
rriv
al a
t airp
ort.
Shor
t-ha
ul c
hute
s op
en 9
0 m
inut
es b
efor
e ST
D, l
ong-
haul
18
0 m
inut
es. C
hute
s cl
ose
30
min
utes
bef
ore
STD
, with
15
min
ute
buffe
r for
suc
cess
ive
fligh
ts.
100%
LFs
and
20%
con
tinge
ncy
uplif
t.
Ass
ume
SH c
hute
s op
en a
t ST
D-1
50 m
ins,
LH
at S
T-24
0 m
ins.
Som
e ch
utes
cha
nge
betw
een
hand
lers
dur
ing
the
day.
Chu
tes
clos
e 30
min
utes
be
fore
STD
, with
15
min
ute
buffe
r for
suc
cess
ive
fligh
ts.
Re
quire
men
t: M
UPs
140
(inc
20
% c
ontin
genc
y)
SH c
hute
ope
ning
at S
TD-1
50, L
H a
t STD
-240
, cl
ose
at S
TD-3
0 w
ith 1
5 m
in b
uffe
r: M
UPs
138
Aft
er E
BS
chut
e op
enin
g at
SH
STD
-90,
LH
ST
D-1
80: M
UPs
109
Plan
ned
MU
P Pr
ovis
ion:
108
Aft
er E
BS
chut
e op
enin
g at
SH
STD
-90,
LH
ST
D-1
80: M
UPs
104
Plan
ned
MU
P Pr
ovis
ion:
108
BA
GG
AG
E SY
STEM
- EA
RLY
BA
G S
TORE
Early
Bag
Sto
re: 0
Requ
irem
ent:
Spar
e ch
utes
to
sto
re e
arly
bag
s at
pea
k,
to e
nabl
e so
me
carr
iers
to
cont
inue
any
time
chec
k-in
.
Requ
irem
ent:
675
bag
stor
age
= 1
7 M
UPs
at 4
0 ba
gs /
MU
P
Aft
er E
BS
open
ing
and
SH c
hute
ope
ning
STD
-90
, LH
STD
-180
: 1,
940
bag
capa
city
Plan
ned
Prov
isio
n by
Dec
201
4:
Early
Bag
Sto
re 2
500+
Aft
er E
BS
open
ing
and
SH c
hute
ope
ning
STD
-90
, LH
STD
-180
: 1,
950
bag
capa
city
Plan
ned
Prov
isio
n by
Dec
201
4:
Early
Bag
Sto
re 2
500+
CEN
TRA
L SE
ARC
HC
urre
nt p
rovi
sion
: 19
lane
s
Econ
omy:
bus
y ho
ur
pass
enge
rs d
o no
t que
ue fo
r lo
nger
than
5 m
inut
es o
n th
e bu
sy d
ay
C
IP: b
usy
hour
pas
seng
ers
do
not q
ueue
for l
onge
r tha
n 1
min
ute
on th
e bu
sy d
ay
20-2
1 la
nes
@ 2
00 p
ph
thro
ughp
uts
20 la
nes
@ 2
00 p
ph th
roug
hput
s19
lane
s @
200
pph
thro
ughp
uts.
IDL
TOTA
L A
REA
IDL
tota
l spa
ce: ~
17,8
00m
2 (D
ec12
aud
it)0.
45 -
0.50
sea
ts p
er p
eak
occu
panc
y pa
x;
1.3m
2 per
sea
t;
Re
tail
/ ca
terin
g - b
ased
on
GA
L co
mm
erci
al s
tand
ards
: 1.
3m2 f
or a
ll ID
L pa
x, 4
0% in
ca
terin
g;
3.0m
2 for
all
IDL
pax,
35%
in
reta
il;
C
ircul
atio
n sp
ace:
20%
-30%
of
tota
l ID
L sp
ace
Ass
umin
g ch
eck-
in o
pens
at
-4h
for L
H a
nd -2
.5h
for S
H:
Bus
y D
ay P
eak
Occ
upan
cy:
~35
00
To
tal I
DL
spac
e re
com
men
ded:
at
leas
t 21,
400m
2 (ex
clud
ing
toile
ts, s
peci
al lo
unge
s, re
tail
stor
age
etc)
.
Ass
umin
g an
ytim
e ch
eck-
in: B
usy
Day
Pea
k O
ccup
ancy
: ~39
20
To
tal I
DL
spac
e re
com
men
ded:
at l
east
24
,100
m2 (
excl
udin
g to
ilets
, spe
cial
loun
ges,
re
tail
stor
age
etc)
.
Ass
umin
g an
ytim
e ch
eck-
in: B
usy
Day
Pea
k O
ccup
ancy
: ~38
20
To
tal I
DL
spac
e re
com
men
ded:
at l
east
23
,300
m2 (
excl
udin
g to
ilets
, spe
cial
loun
ges,
re
tail
stor
age
etc)
.
IDL
SEA
TIN
G, R
ETA
IL &
C
ATE
RIN
G
Seat
ing
prov
isio
n: 1
250
(incl
udin
g 12
PRM
sea
ts)
C
ater
ing
area
pro
visi
on:
3950
m2 (
incl
udin
g ki
tche
n an
d ot
her n
on-p
asse
nger
are
as)
with
123
4 se
ats
Re
tail
area
pro
visi
on: 8
240m
2 (li
kely
to re
duce
slig
htly
de
pend
ing
on c
ircul
atio
n sp
ace
prov
isio
n in
Q5
Phas
e 2
sche
me)
.
Indi
cativ
e se
at re
quire
men
t 15
75 -
1750
, to
mee
t tar
get
QSM
sco
re o
n bu
sy d
ay, b
ut
this
is a
‘sof
t’ co
nstr
aint
.
Cat
erin
g ar
ea re
quire
men
t: up
to
4,6
00m
2
Reta
il ar
ea re
quire
men
t: up
to
10,5
00m
2 .
Indi
cativ
e se
at re
quire
men
t 176
0 - 1
960,
to
mee
t tar
get Q
SM s
core
, but
this
is a
‘sof
t’ co
nstr
aint
.
Cat
erin
g ar
ea re
quire
men
t: up
to 5
,100
m2
Re
tail
area
requ
irem
ent:
up to
11,
700m
2 .
Indi
cativ
e se
at re
quire
men
t 172
0 - 1
910,
to
mee
t tar
get Q
SM s
core
, but
this
is a
‘sof
t’ co
nstr
aint
.
Cat
erin
g ar
ea re
quire
men
t: up
to 5
,000
m2
Re
tail
area
requ
irem
ent:
up to
11,
400m
2 .
FLIG
HT
CO
NN
ECTI
ON
SC
urre
nt p
rovi
sion
: 1 la
ne; c
an
expa
nd to
2 la
nes
Bus
y ho
ur p
asse
nger
s do
no
t que
ue fo
r lon
ger t
han
5 m
inut
es o
n th
e bu
sy d
ay1
lane
@ 2
00pp
h th
roug
hput
s1
lane
@ 2
00pp
h th
roug
hput
s1
lane
@ 2
00pp
h th
roug
hput
s
IMM
IGRA
TIO
N IN
FLO
W
Bus
y ho
ur E
U p
asse
nger
s do
no
t que
ue fo
r lon
ger t
han
10
min
utes
; B
usy
hour
non
-EU
pas
seng
ers
do n
ot q
ueue
for l
onge
r tha
n 20
min
utes
.
Bus
y H
our F
low
: ~27
00
@ 1
000
Bus
y H
our F
low
: ~27
20
@ 1
200
Bus
y H
our F
low
: 290
0
@ 1
200
IMM
IGRA
TIO
N D
ESK
STr
aditi
onal
des
k pr
ovis
ion:
18
EU E
-gat
e pr
ovis
ion:
5
Rang
e of
des
k re
quire
men
ts
depe
ndin
g on
pro
activ
e or
re
activ
e de
sk o
peni
ng.
Trad
ition
al d
esk
requ
irem
ent:
20-2
4 EU
E-g
ate
requ
irem
ent:
12-1
6
Figu
res
assu
me
no
impr
ovem
ent i
n tr
ansa
ctio
n tim
es, f
rom
201
1 su
rvey
: EU
Tr
ad 1
8sec
, EU
E-g
ate
40se
c,
NEU
110
sec
(eas
y) /
300
sec
(har
d)
EU E
-gat
e re
ject
rate
of 2
0%
with
reje
ct ti
me
of 1
0sec
be
fore
pax
use
s EU
Tra
d de
sk
Es
t max
. Frid
ay q
ueue
tim
es o
f no
bui
ld a
re 1
6 m
ins
(EU
) and
33
min
s (n
on-E
U)
Trad
ition
al d
esk
requ
irem
ent:
18-2
3 EU
E-g
ate
requ
irem
ent:
16-2
0
Figu
res
assu
me
no im
prov
emen
t in
tran
sact
ion
times
, fro
m 2
011
surv
ey: E
U T
rad
18se
c, E
U
E-ga
te 4
0sec
, N
EU 1
10se
c (e
asy)
/ 3
00se
c (h
ard)
EU
E-g
ate
reje
ct ra
te o
f 20%
with
reje
ct ti
me
of
10se
c be
fore
pax
use
s EU
Tra
d de
sk
N
ew E
U E
-gat
es w
ith a
tran
sact
ion
time
of
15se
c w
ould
mea
n a
redu
ced
requ
irem
ent o
f 9
gate
s
13 n
ew E
U E
-gat
es p
lann
ed fr
om s
umm
er 2
013
Trad
ition
al d
esk
requ
irem
ent:
14-1
8 EU
E-g
ate
requ
irem
ent:
21-2
8
Figu
res
assu
me
no im
prov
emen
t in
tran
sact
ion
times
, fro
m 2
011
surv
ey: E
U T
rad
18se
c, E
U
E-ga
te 4
0sec
, N
EU 1
10se
c (e
asy)
/ 3
00se
c (h
ard)
EU
E-g
ate
reje
ct ra
te o
f 20%
with
reje
ct ti
me
of
10se
c be
fore
pax
use
s EU
Tra
d de
sk
N
ew E
U E
-pas
s ga
tes
with
a tr
ansa
ctio
n tim
e of
15s
ec w
ould
mea
n a
redu
ced
requ
irem
ent
of 1
2 ga
tes
13
new
EU
E-g
ates
pla
nned
from
sum
mer
201
3
REC
LAIM
BEL
TSC
urre
nt p
rovi
sion
7 In
t bel
ts
(of w
hich
2 lo
ng 7
0m+
) and
1
Dom
bel
t.
Bel
t ava
ilabl
e fo
r all
fligh
ts
durin
g bu
sy h
our,
to s
uppo
rt
KPI
of a
ll pa
x re
ceiv
ing
bagg
age
with
in 4
5 m
inut
es o
f ar
rival
on
stan
d.
Requ
irem
ent:
INT:
7-8
(inc
2
long
bel
ts, t
houg
h th
ere
may
be
an
issu
e w
ith 3
Virg
in 7
47
arriv
als
sche
dule
d w
ithin
20
min
utes
- th
e 3r
d fli
ght m
ay
need
to b
e sp
lit o
ver 2
bel
ts,
else
del
ayed
in a
cces
sing
a
long
bel
t or u
se a
sho
rter
bel
t w
ith re
sulti
ng p
ax c
row
ding
)
DO
M: 1
bel
t jus
t suf
ficie
nt
Requ
irem
ent:
INT:
7 (i
nc 2
long
bel
ts; c
urre
nt
belt
leng
ths
suffi
cien
t, th
ough
one
wid
ebod
y m
ay n
eed
to b
e sp
lit o
ver 2
sm
alle
r bel
ts, o
r be
del
ayed
by
up to
20
min
s in
acc
essi
ng a
lo
ng b
elt),
DO
M: 1
bel
t suf
ficie
nt.
Requ
irem
ent:
INT:
7-8
(inc
2 lo
ng b
elts
; cur
rent
be
lt le
ngth
s su
ffici
ent,
thou
gh o
ne w
ideb
ody
may
nee
d to
be
split
ove
r 2 s
mal
ler b
elts
, or
be d
elay
ed b
y up
to 2
0 m
ins
in a
cces
sing
a
long
bel
t),
D
OM
: 1 b
elt s
uffic
ient
.
LAN
DSI
DE
RETA
IL &
C
ATE
RIN
G
Cat
erin
g ar
ea p
rovi
sion
(low
er
& u
pper
leve
l): 1
,230
m2
Reta
il ar
ea p
rovi
sion
(low
er &
up
per l
evel
): 85
0m2
Arr
ival
s co
ncou
rse
non-
com
mer
cial
are
a (lo
wer
leve
l on
ly):
1,87
0m2
Land
side
pea
k oc
cupa
ncy:
A
rriv
als
conc
ours
e pe
ak
occu
panc
y is
~20
% o
f pea
k ho
ur fl
ow +
La
ndsi
de d
wel
l ass
umed
~10
m
inut
es o
n av
erag
e.
1.
3m2 c
ater
ing
area
per
per
son
at p
eak
occu
panc
y.
0.8
- 1.0
m2 r
etai
l are
a pe
r pe
rson
at p
eak
occu
panc
y
Arr
ival
s co
ncou
rse
peak
oc
cupa
ncy:
560
La
ndsi
de d
epar
ture
s pe
ak
occu
panc
y: 6
00
Com
bine
d la
ndsi
de p
eak
occu
panc
y: u
p to
116
0
Cat
erin
g ar
ea re
quire
men
t: 1,
510m
2 Re
tail
area
requ
irem
ent:
930
- 1,1
60m
2 A
rriv
als
conc
ours
e no
n-co
mm
erci
al a
rea:
129
0m2
Arr
ival
s co
ncou
rse
peak
occ
upan
cy: 5
60
Land
side
dep
artu
res
peak
occ
upan
cy: 6
00
Com
bine
d la
ndsi
de p
eak
occu
panc
y: u
p to
11
60
C
ater
ing
area
requ
irem
ent:
1,51
0m2
Reta
il ar
ea re
quire
men
t: 93
0 - 1
,160
m2
Arr
ival
s co
ncou
rse
non-
com
mer
cial
are
a:
1290
m2
Arr
ival
s co
ncou
rse
peak
occ
upan
cy: 6
10
Land
side
dep
artu
res
peak
occ
upan
cy: 5
90
Com
bine
d la
ndsi
de p
eak
occu
panc
y: u
p to
12
00
C
ater
ing
area
requ
irem
ent:
1,56
0m2
Reta
il ar
ea re
quire
men
t: 96
0 - 1
,200
m2
Arr
ival
s co
ncou
rse
non-
com
mer
cial
are
a:
1400
m2
11
GATWICK AIRFIELD FACILITIES: PROVIDED AND FORECAST TO 2020 INCLUDING Q5 & Q5+1 DEVELOPMENTSCurrent Provision Service Standards assumed in assessments 2012 Based on actual schedule (34.1mppa) SH&E High Case 2016/17 (37.5mppa) SH&E High Case 2020/21 (41mppa)
ANNUAL PAX ST: 16.9 mppa NT: 17.2 mppa
ST: 18.4mppa NT: 19.3mppa
ST: 20.5mppa NT: 20.5mppa
BUSY DAY ATMS 868 888 943
PEAK HOUR ATMs 53 53 55
DAILY CAPACITY Maximum ATMs if all available daily slots are used. Sustained 55atms/hr achievable by 2020 over most of the operational day. 914 960 998
% Utilisation of Capacity on Busy Day % Utilisation of Capacity on Busy Day % Utilisation of Capacity on Busy Day
RUNWAY 3 RETs and 3 RATs on 26L & 08R
Maximum 10 minute delay. On a busy day almost all the available capacity is utilised and Gatwick is not able to satisfy
all demand for slots. However, on other days of the year utilisation is much reduced.
95.0% 92.5% 94.5%
A380 Capability Remote parking on NWzone for two code F. Diversionary (AACG) compliance on taxiways only.
Compliance with CAA CAP 168 required for full service scheduled operations. Pier Service for A380 turns. AACG compliance sufficient
New A380 stand on Push & Hold 125, Juliet minor works. Restrictions on P6 departure gates
and Alpha hold.
New A380 stand on Push & Hold 125, Juliet minor works. Restrictions on P6 departure gates and Alpha hold. Shortfall in forecast A380 Pier stand capacity
by 1 stand.
TAXIWAYS 5 Taxiways N-S and 3 taxiways E-W providing alternative routes to piers
There is no specific service standard for taxiways although on route delays between the runway and stand should be kept to a minimum and new developments should serve to maintain or
reduce taxi times.
Current problems in Pier 1 cul-de sac. Similar but less severe problem in Pier 2-3 cul de sac where push
back conflicts can occur.
New Pier 1 realigned to avoid pushback conflicts and improve flow to Alpha hold.
New Pier 1 realigned to avoid pushback conflicts and improve flow to Alpha hold.
STANDS
Provision: 110, 53E + 2F, 16 MARSAny arrival should have an available stand of the right size to park on at all times. Requirement equals Busy day peak
occupancy + 10%. Note that MARS centrelines may be added to the total provision. MARS centrelines are only counted if
they can accommodate A320 or larger.
Provision: 108, (incl. 53E, 2F) + 16 MARS Provision: 109, (incl. 58E, 3F) + 19 MARS Provision: 109, (incl. 58E, 3F) + 19 MARS
Requirement: 111, 31E Requirement: 115, 34E Requirement: 116, 35E
Note 734 MARS are excluded from count. Stand 57 included as E MARS. Holding stands excluded. Stands 60-63 closed, gate 59 closed for deps P1 & P5 reconfigured and code F on 110 P1 & P5 reconfigured and code F on 110
NORTH TERMINAL
PIER SERVED STANDS Provision: 27, 11E, 3 MARS
Pier Served demand is assessed in order that 95% of passengers are pier served and there should be sufficient
coaching capacity to accommodate all remote services. Very dependent on towing levelsw
Provision: 28 (incl 11E) + 3 MARS Provision: 31 (incl 16E, 1F) + 6 MARS. Provision: 31 (incl 16E, 1F) + 6 MARS.
Demand: 42, incl 11E Demand: 44, incl 15E + 1 F Demand: 46, incl 19E + 2F
93% PSL* 93% PSL 92% PSL
ARRIVALS COACH BAYS 2 Int (TBC) & 1 Dom 95% of arrivals coaches should not need to hold for offloading passengers. 2 Int (TBC) & 1 Dom 2-3 new facility in TBF 2-3 new facility in TBF
COACHING GATES 11 International coaching gates (gate 45) plus one domestic on P5Sufficient coaching gates should be provided so that there is always a coaching gate available to accommodate busy day
demandDemand for 9-10 coaching gates. 11 provided Demand for 9-10 coaching gates. 11 provided Demand for 9-10 coaching gates. 11 provided
SOUTH TERMINALPIER SERVED STANDS Provision: 36, 16E, 7 MARS
Pier Served demand is assessed in order that 97% of passengers are pier served as there are only 4 coaching gates
to accommodate all remote services in South Terminal.
Provision: 34 (incl 16E) + 7 MARS Provision: 31 (incl 16E) + 7 MARS Provision: 31 (incl 16E) + 7 MARS
Demand:35, incl 12E Demand: 37, incl 12E Demand: 40, incl 12E
98% 97% 97%
ARRIVALS COACH BAYS 1 int (gate 30) & 1 dom 95% of arrivals coaches should not need to hold for offloading passengers. 1 int & 1 dom 1 int & 1 dom 1 int & 1 dom
COACHING GATESAlthough there are 5 coaching gates provided on gates 90 - 95 , only 3 can be used simultaneously due to space constraints. plus
one additional domestic to be provided on 10A.
Sufficient coaching gates should be provided so that there is always a coaching gate available to accommodate busy day
demandDemand for 1 gate. 4 provided Demand for 2 gates 4 provided Demand for 2 gates 4 provided
*In 2012 GAL was given dispensation to deliver 93% PSL in NT while Pier 5 Development works were underway. However, an intensive towing regime was instigated during the works period enabling GAL to maintain PSL levels above 95%.
12GATWICK AIRFIELD FACILITIES: ExISTING AND FORECAST TO 2020/2021 WITh RAG STATUS INCLUDING Q5 & Q5+1 DEVELOPMENT
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
13
ConClusion
Gatwick is the busiest single-runway airport in the world. During the summer peak, demand outstrips available supply. With no second runway expected until at least the mid-2020s, the existing runway needs to be better utilised, particularly on a year-round basis to provide capacity for maximising further medium term growth.
The forecasts include assumptions on external shocks over the forecast period. Based on the last ten years the likelihood of an “event” is high and SH&E considered the nature of “external shocks” and their likely effect on passenger traffic and subsequent recovery rate. Economic shocks, particularly economic recessions, have typically had a larger and longer lasting negative impact on aviation growth than events such as SARS, terrorist attacks and political unrest.
The Low Case represents a set of negative yet conceivable circumstances, whereby the rebound from the recent downturn is slow and prolonged, and the long term average rate of growth is weakened by economic volatility and potential negative shocks to demand.
The Base Case forecast translates to a set of reasonable assumptions at the airline and market level, illustrating how growth may be achieved. Gatwick is and will remain a predominantly short haul European airport with all market sectors expected to grow. In terms of volume it will be the short haul segment that grows the most with growth on the long haul passenger segment driven by additional services from new and established carriers at Gatwick. These new carriers could be new operators to the London market or potential spill from an increasingly constrained Heathrow market.
In contrast, the High Case illustrates the volumes that may be expected if a more positive set of circumstances materialise, representing an optimistic but achievable growth path. In this scenario, a robust near-term rebound is assumed, coupled with on-going successes in attracting new carriers and routes to Gatwick now that Gatwick is free to compete and has developed a strong air service marketing approach. Over the longer term, market maturity and capacity constraints are still modelled, but to a somewhat lesser degree than in the Base Case.
The Base Case represents SH&E’s most likely forecasts, taking a balanced view of the demand and supply side factors driving future traffic volumes at Gatwick. However it is worth noting that recent changes in the competitive dynamics of the London market, for example the sale of Stansted to MAG, are not assumed in the Base Case, this will be taken account of in the next forecast refresh.
In spite of some major exogenous shocks, the global aviation market has grown mainly in a consistent manner, at a long term average rate of around 5-6% per annum. Growth has varied significantly by region of the world, with markets in some countries maturing earlier than others. While Europe and North America are now considered largely mature markets, some other regions such as the Middle East and Asia are still generating strong aviation growth as economies develop and expand.
Recovery started in 2012 and the long term outlook for aviation demand remains broadly positive. However market sentiment remains cautious and the shorter term outlook volatile with unrest in the Middle East and North Africa (MENA) region, a recurring rise in oil prices, and fragile economic recovery in many European markets, including the UK, as well as the fortunes of the Eurozone are continuing to impact aviation demand.
Over the past decade, the airline industry has been subject to a variety of external “shocks” e.g. Gulf War, SARS, 9/11 and volcanic activity, none of which could have been predicted, but all of which had a very significant impact on air travel. Due to its nature, such an event has not been built into our forecasts, but remains a very real risk.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
14
Moreover we expect the recent sale of Stansted to intensify the competition with Gatwick for airlines and passengers. Increased competition between airports will also have an impact with some airports winning and others losing passenger traffic.
1.2 GatwiCk airport Master plan
Following a three-month public consultation on its draft master plan, which closed in January 2012, Gatwick Airport published a report detailing the views and opinions of local residents, businesses, MPs and Councils in April 2012. The detailed document ‘Gatwick Airport: Draft Master Plan Summary Report on Public & Community Consultation’ is available to read and can be downloaded from the Gatwick Airport website gatwickairport.com/masterplan.
The final Master Plan document was published in June 2012 and is also available on the Gatwick Airport website. The Master Plan both informs and is informed by a variety of statutory planning documents that are produced by regional and local authorities, as well wider Government policy and the regulatory environment in which Gatwick operates.
As mentioned in the previous CIP documents, together, the Gatwick Airport Master plan, the Development Plans and the Capital Investment Programme are intended to present a clear picture of Gatwick’s development within the current, medium and long term view and are intrinsically linked through a common ambition and strategy. The relationship between these different documents and Gatwick’s Business Plan is GAL. Illustrated in the diagram below:
GAL recognises the importance of demonstrating a strong linkage between the CIP and our strategic ambition for Gatwick as described in our master plan. In the past we have used the term ‘Development Strategy’ to describe this linkage. We believe the revised GAL Business Plan (‘Connecting London to the World’, published in January 2013), goes a long way to making this connection. Chapters two to seven in the January 2013 revised GAL revised Business Plan describe our vision and strategic priorities for the airport, our traffic forecasts and the results of our passenger insight research. They also explain how we have used the latter material to create our product matrix which identifies future service outcomes, designed to deliver our ambition for Gatwick. The product matrix can be found in Appendix H.
We have shared with our airline partners via a pack of illustrative plans the differing options for development that are available and how we are taking these into account when we propose specific projects to take forward.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
15
Chapter Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
CHAPTER 2Our Strategic ambitiOn: tO becOme LOndOn’S airpOrt Of chOice
intrOductiOn
Since December 2009, we have made huge strides in improving the infrastructure and the passenger experience to position Gatwick as London’s airport of choice. From a service quality rebate (SQR) perspective, there has been a marked improvement in Gatwick’s performance against the CAA’s SQR measures, with all measures being met each month. As outlined in Chapter 8 (Service Quality Regime) of the January 2013 GAL Business Plan, Gatwick has had considerably more success in achieving 100% compliance with its SQR measures than the other regulated south east airports.
It is also no mere coincidence that Gatwick’s third birthday under new ownership coincides with a host of industry recognition, with no less than seven industry awards comprising Best UK airport at the British Travel Awards 2012, UK airport of the year at the 2012 Travel Agents Choice awards, Best Security & Immigration Experience award at the Future Travel Experience awards 2012, Best airport in social media at the ‘Simplifying’ Digital awards.
Increasingly passengers have more choice as to which airport they fly from and airlines have alternative bases from which to operate. As we compete to grow and attract new routes and airlines as well as passengers in the competitive South East airport market, we also need to ensure we continue to deliver facilities for both our airline partners and passengers in a cost effective manner. It is only by delivering continued improvement in the passenger experience at Gatwick and meeting the needs of a varying customer base that we will become London’s airport of choice.
Our ambitiOn
The way in which we have sought to compete since December 2009 is encapsulated in our ambition to ‘’compete to grow and become London’s airport of choice”.
In the 2012 CIP, we explained how our ambition to ‘’compete to grow and become London’s airport of choice” is translated into six strategic priorities and how these strategic priorities provide a high level strategic direction for our development planning.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
16
1. Deliver the best passenger experience by listening to our passengers and delivering the kind of service that will make them choose to fly from Gatwick.
2. Help our airlines grow by understanding their goals and developing commercial partnerships
3. Increase value and efficiency by maximising income from retail, property and car parks, lowering our operating costs and investing efficiently
4. Protect and enhance our reputation by building strong and constructive relationships with our stakeholders based on openness and trust
5. Build a strong environment, health and safety culture by maintaining a relentless focus on achieving zero incidents
6. Develop the best people, processes and technology by investing in high performing people, driving continuous improvement and deploying the right systems.
These strategic priorities are then cascaded down to the individual objectives of each of our members of staff.
frOm Strategic priOritieS tO paSSenger cOmmitmentS
Underpinning these six strategic priorities is the recognition that to become London’s airport of choice in a competitive market, we need to put the passenger first. In 2010, Gatwick became the first UK airport to publish passenger commitments, which are central to our service focus and have been endorsed by our airline partners, handling agents and the UK Border Force (formerly known as UK Border Agency).
These passenger commitments, outlining the service standards our passengers can expect, are the results of the collaborative work undertaken with our partners and centre on three core pledges:
• We’ll treat you as our guest
• We hate queues
• We love to be on time
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
17
SummarY Of capitaL inVeStment at gatWicK in Q5
Under new ownership, we are on track to deliver the current capital programme, with 82% of the £1,172 billion capital investment programme either completed or nearing completion as at 31st March 2013.
Appendix A outlines the forecast phased capital of all major projects as well as projects completed in the current quinquennium (Q5). The following section describes on-going capital works across Gatwick that this phased forecast spend represents that will enable Gatwick to ‘compete to grow and become London’s Airport of Choice’. These projects have been developed and delivered with input from the airline community through project working groups, the Capital Programme Board (CPB) and the Joint Steering Group (JSG).
The 2012 CIP covered the period November 2011 to end March 2012. Following on from the last publication, the 2013 CIP covers the period April 2012 up to and including March 2013.
OVerVieW Of capitaL inVeStment Since apriL 2012
The total spend since the start of the financial year to date, from April 2012 to March 2013, totals £221.9m, whilst the Q5 total spend to date since the start of the current quinquennium from 2008 to March 2013 totals £958.1m.
Since April 2012, several projects have either been delivered or nearing completion. Out in the airfield, the rehabilitation of Gatwick’s most critical asset, the Main runway, has been undertaken, whilst keeping the world’s busiest single runway operational for the critical parts of the day. Over the course of the nine-month project, 400,000sqm of runway was resurfaced using 65,000 tonnes of Marshall Asphalt, the airfield ground lighting was upgraded with the installation of 1,900 runway and taxiway lights, and 530km of electrical cabling and 38km of ducting installed.
The rehabilitation of Taxiways Papa and November were completed in August 2012. The airfield asset replacement programme comprising stand rehabilitation, replacement of airfield ground lighting, Fixed Electrical Ground Power units and Lighting columns is on-going whilst the Stand Entry Guidance Systems (SEGS) project was delivered in November 2012.
The Pier 5 project, which aims to deliver improved Pier Service levels to meet future growth in passenger numbers in the North Terminal, is currently well underway. Pier service levels will be enhanced through stand reconfiguration and provision of independent centrelines access and provision of vertical segregation for arriving and departing passengers. Structural works will be completed in February 2013 and the completion of Phase 1 is planned in July 2013, whilst Phase 2 works are due for completion in May 2014.
In November 2012, Gatwick awarded its largest construction contract to date to demolish Pier 1 and construct a new building in the South Terminal to house both a new baggage system and a new pier. At a total cost of £178.9 million for both phases, this project is Gatwick’s biggest capital investment in recent years. It is also a historic milestone for Gatwick as the pier is one of the oldest assets in South Terminal, first opened in 1958. The ST Baggage and Pier 1 project, which in fact brings two separate projects together into a single build solution, will entail the demolition of Gatwick’s original 1950s Pier. Phase 1 of the South Terminal Baggage and Pier 1 project comprising the replacement of the hold baggage screening (HBS) facility was completed by September 2012. Phase 2 comprising the construction of a new ST baggage factory and brand new pier with 5 fully serviced stands, entailing the demolition of the existing Pier 1 and delivery of an automated baggage storage facility, will be completed in 2015.
The new two-storey Pier has been designed with the passenger in mind at every step, with quick and easy access from the departure lounge to the bright new gate rooms, linked to five new aircraft stands by air-bridges. With views over the airfield, the new gate rooms will also include new style seating and child-friendly zones.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
18
Within the heart of the building will be a new baggage system that will allow bags to be processed faster and enable our airlines the opportunity to use automated fast-bag drops. There will be an automated bag store too, giving airlines the ability to offer flexible check-in.
In the North Terminal, exciting improvements were brought to the passenger experience in the North Terminal with the opening of Jamie’s Italian and Yo! Sushi restaurants in June 2012. The opening of Jamie’s Italian in the North Terminal is a great example of how Gatwick is competing to become London’s airport of choice with Gatwick being recognised as having delivered the best travel restaurant throughout the travel industry in 2012.
The A380 on Stand 125 project came into service in March 2013 under the original budget of £6.5m, with the first A380 using the stand on 26th March.
There has also been a major upgrade to the baggage system to increase capacity and improve efficiency in the North Terminal, with the NT Baggage project completed in December 2012.
In the South Terminal, the ST IDL Phase 1 Project was opened in July 2012, providing a brand new ST walk through duty free facility. Gatwick South Terminal Security facility, the benchmark standard for UK airports, continues to win yet more awards, the latest being the Best Security & Immigration Experience award at the 2012 Future Travel Experience awards.
The ST Departure Lounge Phase 2 achieved tollgate 4 in December 2012. As at January 2013, the preliminary design is complete. Enabling works are completing with the strip out old WDF and other shops. This project is expected to be fully delivered by January 2014, with the first phase complete in July 2013.
The refurbishment of Atlantic House, as part of the Crew Reporting solution is due for completion in July 2013. The installation of the Jubilee House HBS equipment was completed in September 2012.
Appendix A - Phased Capital Investment Programme 2013 shows a phased forecast spend for the current regulatory cycle, April 2008 – March 2014.
Q5 - Key Metric
The graph below shows actual capital expenditure per year for Q5 to date and the forecast for the remaining year:
104.0
181.4
211.4
239.3221.9 213.9
0
50
100
150
200
250
300
2008 2009 2010 2011 2012 2013
£mill
ion
Financial Year ending 31 March
Q5 Capital Expenditure
Actual Forecast
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
19
The above commentary is not exhaustive but gives an indication of the scale and range of improvements that are underway or planned in the current Q5 regulatory cycle to enable Gatwick to compete to grow and retain airline and passenger traffic.
In Chapter 5 individual project description sheets (PDS) have been provided, outlining cost breakdowns for all the major projects and programmes in the Q5 CIP with a budget greater than £5 million.
OVerVieW Of recentLY cOmpLeted prOjectS and current & future miLeStOneS
The following sections provide an overview of recently completed projects and significant milestones achieved since April 2012 up to end of March 2013.
Projects TG1 TG2 TG3 TG4 TG5 TG6 Comments including trigger dates where applicable
Major Projects completed since April 2012
NT Extension N/A N/A N/A Oct-09 Dec-11 Feb-13 Achieved trigger requirements in December 2011
ST Security - Phase 3 IDL works N/A Aug-11 Sep-11 Oct-11 Nov-12 Feb-13
ST Immigration Hall Reconfiguration N/A Aug-10 Aug-10 Sep-10 Feb-12 May-12
Main Runway Rehabilitation Jun-10 Oct-10 Jul-11 Jul-11 Nov-12 May-13
NT Baggage (NTB) N/A N/A N/A Feb-10 Dec-12 May-13
ST Baggage Phase 1 (HBS installation) Apr-10 Apr-10 May-10 Oct-10 Aug-12 Apr-13
NT Security ( Phase 2) May-11 Jun-11 Jun-11 Oct-11 May-12 Nov-12
A380 on Stand 125 Jun-11 Aug-11 Dec-11 May-12 Feb-13 Mar-13
Other Significant Milestones achieved since April 2012
Papa November Taxiways Mar-11 Aug-11 Aug-11 Nov-11 Jun-12 Sep-13
Special Branch & UKBF accommodation Nov-12 Jan-13
NT IDL Reconfiguration N/A Sep-11 Dec-11 Dec-11 Jun-12 : Project 1 Feb-13 Project scope reduced
ST IDL Reconfiguration Ph-2 Dec-11 Feb-12 Jul-12 Dec-12 Dec-13 Mar-14
ST Baggage Phase 2 Apr-10 May-10 Jun-11 Jul-12May-15 : Baggage Factory
June-15 : Baggage Factory
Pier 1 closure in Apr-13; Pier 1 Gates 1-5 in Mar-15. Trigger date : 31 Dec 2013 (enabling works and demolition works)
Future Milestones - as at 31 March 2013
Piers, Infrastructure & Airfield
Pier 5 - Phase 1 N/A N/A Apr-11 Dec-11 Jul-13 Aug-13 Phase 1 completion : Trigger date : 16 Sep 2013 ; Phase 2 TG 5 & 6 in May 2014
NT Additional Pier Service May-10 Jun-12 Jun-13 Dec-15 Jan-17
NT Baggage Voids Jul-11 N/A Apr-13 N/A Dec-13
ST Baggage Phase 2 Apr-10 May-10 Jun-11 Jul-12May-15 : Baggage Factory
Jun-15 : Baggage Factory
Pier 1 closure in Apr-13; Pier 1 Gates 1-5 in Mar-15. Trigger date : 31 Dec 2013 ( enabling works and demolition works)
Surface Water Pond D Jul-10 Nov-10 Dec-11 Dec-11 Apr-13 May-13
Airfield Operations Building Apr-11 Apr-11 Dec-11 Jul-12 Nov-13 Jan-14
ADCM55 Apr-11 Apr-11 Dec-11 Jul-12 Nov-13 Jan-14
Taxiway AGL Aug-12 Aug-12 Jun-13 Oct-13 Nov-14 Nov-14
95% Pier Service N/A N/A t Apr-14 Oct-17 Jan-18
Gatwick Stream Flood Attenuation Mar-12 Apr-12 Aug-12 Mar-13 Jan-14 Jun-14
Consolidated Security Gate N/A Mar-12 Mar-13 Jul-14 Oct-14 Nov-14
Entrance Bridge Cladding Feb-11 Aug-11 Apr-12 Apr-12 Nov-13 Dec-13
Terminals
ST IDL Reconfiguration Phase 2 Dec-11 Feb-12 Jul-12 Dec-12 Dec-13 Mar-14 Trigger date: 31 March 2014
Crew Reporting N/A N/A Jun-11 Jun-12 Jul-13 Aug-13 Trigger date: 31 August 2013
Domestic Arrivals N/A N/A Jan-12 May-12 Apr-13 Apr-13
ST & NT Border Force Arrivals Zones Apr-12 Oct-12 Jul-13 Aug-13
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
20
‘Q5+1’ eXtenSiOn Year – StatuS Of prOjectS aS at end Of march 2013
Since late May 2012, weekly meetings have been held between GAL and the Airport Consultative Committee (ACC) representative to discuss capital expenditure for the relevant Q5+1 minor projects and to receive the ACC’s endorsement for individual projects. Both the Capital Programme Board (CPB) and Joint Steering Group (JSG) are kept informed on a monthly basis of the tracked forecast spend. This process, ratified by the ACC, has ensured that there is sufficient airline consultation and governance around the Q5+1 list of projects.
The sections below give an overview of both minor and major projects either endorsed by the JSG, or currently being considered by the ACC. Also included is the list of projects not supported by the ACC.
ACC Supported Major Projects
Since May 2012 and until 31 March 2013, the following list of ‘Q5+1’ major projects totalling £163.2 m have been endorsed by the ACC for progression:
1. Rail Station Contribution
2. NT Additional Pier Service - Pier 5
3. South Terminal Baggage & Pier 1
4. Crew Reporting
5. ST Domestic Arrivals
6. ST Entrance Bridge Cladding
7. Surface Water Infrastructure (Q5+1 phase)
8. Airfield Peak Cap Expansion ACDM55 - phase 2
9. NT IDL Reconfiguration phase 1
10. UKBA Arrivals Phase 1
11. NT IDL Reconfiguration phase 2
12. Flood Alleviation
13. ST IDL Reconfiguration
14. Consolidated Security Gate (ACC support anticipated at April JSG)
15. Gatwick Stream Flood Attenuation (ACC support given at March JSG)
ACC Supported Minor Works Projects
The list below provides an overview of the various minor projects (whose budget is above £1 million) endorsed by the ACC since June 2012. Altogether there are approximately 43 minor projects each with their respective estimated budget, totalling £53.7 million comprising:
1. ST Statutory Accommodation Compliance
2. LEPC
3. Remote Stand SEGS
4. S1/S2 Switchboard Replacement
5. NT Foul Rising Main Augmentation
6. Norfolk House Refurbishment
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
21
7. Low Voltage Electricity
8. Vehicle replacement
9. ST Landside Arrivals & Onward Travel
10. Life safety systems
11. HVAC systems
12. Property asset replacement
13. CCTV replacement
14. IT Core Infrastructure - Node Room Remediation
15. IT Infrastructure Platform upgrade
16. Check-in Common Bag Drop
17. Airfield Peak Capacity Expansion (ACDM – Phase 1)
18. IT Operations Centre
19. Minor works, building and fabric
20. Substations (Airfield)
21. FEGP (asset replacement only)
22. ST IDL Toilets (outside the Beehive Pub)
23. Gatwick Connect Pilot
24. Security Fixed Posts
ACC Major Projects still under ACC considerationThe A380 on Stand (Pier 6) is yet to obtain full ACC support as at 31 March 2013.
Projects still under ACC considerationThe following projects totalling £15.7m are being considered by the ACC:
1. Taxiway rehabilitation including AGL
2. Staff Car Parks
3. Minor projects – various (under £500k each)
Projects not endorsed by ACCThe following projects amounting to £15.7 m in total are not supported by the ACC:
1. Check-in Common Bag Drop (representing remainder of spend following individual trials – all of which have been supported by the ACC)
2. NT Early Bag Store
3. NT Staff Restaurant
4. UKBA Arrivals Phase 2 – South Terminal
5. Crew Reporting - the budget increase at TG4 from £14m to £20.55m (The scope of the Crew report-ing project was endorsed by the JSG/ACC, however, the budget increase from £14m to £20.55m is not supported by the ACC).
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
22
As mentioned in the 2012 CIP, the 6 year Q5 capital programme consists of major projects and programmes comprising current live projects, rolling programmes and a number of new projects required between February 2011 (when the Q5+1 programme was constructed) and the end of the quinquennium (March 2014).
Many of these projects were already in the Q5 programme. Some are new whilst others will either be completed in the extension year 2013/2014 or into the period beyond Q5. Examples of major projects which carry over from Q5 into the period beyond Q5 are NT Additional Pier Service – Pier 5, ST Baggage and Pier 1 and Rail Station improvement works.
beYOnd Q5 – Our reViSed buSineSS pLan The formal process of Constructive Engagement with the airline community for the post Q5 period commenced in April 2012, with the submission of the initial GAL Business plan, as requested by the CAA.
Once the business plan was published in April 2012, the CAA instructed the airport and its airlines to take the main elements of the Initial Business Plan through a process of Constructive Engagement. This was a multi-lateral process in which various elements of the business plan were discussed in a structured, transcript format. The subjects covered were agreed in advance with the CAA and the airlines in the form of the Constructive Engagement mandate. In total, GAL had 33 Constructive Engagement meetings. Topics covered included:
• Traffic forecasts;
• Capital expenditure;
• Service quality;
• Operating expenditure; and
• Commercial revenues.
changeS Since apriL 2012 initiaL buSineSS pLan As a result of Constructive Engagement, and due to other developments during 2012, some elements of the business plan have been changed. A new revised business plan (RBP) was thus launched in February 2013. It is worth noting that the traffic forecasts now show Gatwick reaching only 35.9 million passengers in 2018/19, down from the 37.3 million passengers forecast for the same year in the Initial Business Plan.
The capital expenditure total of £1.15bn in the April 2012 business plan has been reduced to £967.17m. This reflects a lack of airline support for some projects, as well as the reduced traffic forecasts delaying the need for some projects to the early 2020s.
The table below provides a high level summary (in 2013/2014 prices) of the revised Capital Programme for the period between the end of Q5 (1 April 2014) and 31 March 2019, totalling £967.17 million. Also shown is the predicted capital spend for the following 5 year period up to 2024.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
capitaL prOgramme SummarY bY Year buSineSS pLan - eaSYjet SpLit - prOgramme apprOach 10 Year pLanHigh Case (July 2013) easyJet Split - (v15 dated 21.06.2013)
23
BUSINESS PLAN - EASYJET SPLIT - PROGRAMME APPROACH 10 YEAR PLANHigh Case (July 2013) easyJet Split - (v15 dated 21.06.2013)
2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
ASSET STEWARDSHIP
AIRFIELD
6.70£ 6.95£ 15.33£ 23.67£ 32.05£ 84.70£ 28.00£ 36.00£ 39.50£ 34.50£ 34.50£ 172.50£
FACILITIES28.78£ 42.72£ 38.50£ 29.13£ 24.38£ 163.51£ 29.50£ 41.50£ 31.50£ 29.00£ 27.50£ 159.00£
COMMERCIAL 8.11£ 11.55£ 10.09£ 8.19£ 7.21£ 45.15£ 9.50£ 9.50£ 9.50£ 9.50£ 9.50£ 47.50£
COMPLIANCE & RISK9.38£ 15.30£ 5.28£ 4.88£ 4.89£ 39.73£ 6.10£ 8.10£ 8.10£ 5.10£ 6.60£ 34.00£
I.T.10.27£ 8.67£ 3.57£ 7.89£ 3.77£ 34.17£ 10.00£ 10.00£ 10.00£ 10.00£ 10.00£ 50.00£
TOTAL ASSET STEWARDSHIP 63.24£ 85.19£ 72.77£ 73.76£ 72.30£ 367.26£ 83.10£ 105.10£ 98.60£ 88.10£ 88.10£ 463.00£
CARRY OVER PROJECTSST Baggage & Pier 1 65.60£ 23.00£ -£ -£ -£ 88.60£ -£ -£ -£ -£ -£ -£ Pier 5 2.89£ -£ -£ -£ -£ 2.89£ -£ -£ -£ -£ -£ -£ Gatwick Stream Flood Attenuation 0.39£ -£ -£ -£ -£ 0.39£ -£ -£ -£ -£ -£ -£ Consolidated Security Gate 0.96£ -£ -£ -£ -£ 0.96£ -£ -£ -£ -£ -£ -£ FEGP Replacement 0.05£ -£ -£ -£ -£ 0.05£ River Mole 0.31£ -£ -£ -£ -£ 0.31£
-£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ 70.20£ 23.00£ -£ -£ -£ 93.20£
TOTAL ASSET REPLACEMENT PLUS CARRY OVERS 133.44£ 108.19£ 72.77£ 73.76£ 72.30£ 460.46£ 83.10£ 105.10£ 98.60£ 88.10£ 88.10£ 463.00£
CORE PROJECTS - 2013/14 - 2018/19Delivery of 95% Pier Service (North Terminal) 5.15£ 50.35£ 81.39£ 37.90£ 0.66£ 175.45£ -£ -£ -£ -£ -£ -£ NT Security Reconfiguration 6.11£ 8.42£ 7.46£ 3.18£ -£ 25.17£ -£ -£ -£ -£ -£ -£ Early Bag Store 1.02£ 1.23£ 10.57£ 10.22£ 0.96£ 24.00£ -£ -£ -£ -£ -£ -£ Upgrade Check In & Bag Drop & NT Ceilings and Floors 0.54£ 1.61£ 2.73£ 2.31£ 16.81£ 24.00£ -£ -£ -£ -£ -£ -£ Upgrade Check In & Bag Drop ST 0.50£ 1.60£ 2.61£ 2.52£ 10.37£ 17.60£ -£ -£ -£ -£ -£ -£ NT Border Zone -£ 0.76£ 1.47£ 7.80£ 3.19£ 13.22£ -£ -£ -£ -£ -£ -£ NT IDL Reconfiguration & Expansion 21.66£ 29.85£ 26.44£ 9.82£ -£ 87.77£ -£ -£ -£ -£ -£ Runway 2 5.70£ 4.30£ -£ -£ -£ 10.00£ -£ -£ -£ -£ -£ -£ Business Systems Transformation 3.29£ 3.29£ 3.29£ 2.97£ 2.95£ 15.79£ -£ -£ -£ -£ -£ -£ Stand Reconfigurations 0.74£ 7.53£ 1.47£ 0.26£ -£ 10.00£ -£ -£ -£ -£ -£ -£ Product Development - Car Parking -£ -£ -£ 0.61£ 4.39£ 5.00£ -£ -£ -£ -£ -£ -£ Digital Media - Return 0.08£ 2.59£ 0.82£ 0.15£ 1.66£ 5.30£ -£ -£ -£ -£ -£ -£ CIP Departures 0.14£ 2.16£ -£ -£ -£ 2.30£ -£ -£ -£ -£ -£ -£ NT Baggage Reclaim -£ -£ 0.18£ 1.34£ 1.28£ 2.80£ -£ -£ -£ -£ -£ -£ NT Arrivals Transformation 0.84£ 2.67£ 8.35£ -£ -£ 11.86£ -£ -£ -£ -£ -£ -£ ST IDL Capacity -£ 0.51£ 1.28£ 11.27£ 16.94£ 30.00£ 18.18£ 15.82£ -£ -£ -£ 34.00£ CIP Arrivals 0.15£ 1.99£ -£ -£ -£ 2.14£ -£ -£ -£ -£ -£ -£ Additional NT Coaching Bays 0.15£ 0.30£ 0.78£ 1.18£ -£ 2.41£ -£ -£ -£ -£ -£ -£ ST Public Transport / Accessibility 0.51£ 0.40£ 3.33£ 4.96£ -£ 9.20£ -£ -£ -£ -£ -£ -£ Stands 551 and 552 1.26£ 8.09£ -£ -£ -£ 9.35£ Hangar 5.35£ -£ -£ -£ -£ 5.35£ Minor Development Projects 2.00£ 2.00£ 2.00£ 2.00£ 2.00£ 10.00£ Consolidated Car Rental and Motor Transport Facility 0.45£ 1.58£ 5.97£ -£ -£ 8.00£ -£ -£ -£ -£ -£ -£
55.64£ 131.23£ 160.14£ 98.49£ 61.21£ 506.71£ 101.28£ 120.92£ 98.60£ 88.10£ 88.10£
SUBTOTAL 189.08£ 239.42£ 232.91£ 172.25£ 133.51£ 967.17£ 101.28£ 120.92£ 98.60£ 88.10£ 88.10£ 497.00£
DEVELOPMENT ROJECTS - 2013/14 - 2018/19
HBS Replacement 8.54£ 6.24£ 72.06£ 61.79£ 9.58£ 158.21£ Liquid Detection -£ 0.40£ 1.25£ -£ -£ 1.65£ Gatwick Express Rolling Stock - Capital Contribution -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£
SUBTOTAL 197.62£ 246.06£ 306.22£ 234.04£ 143.09£ 1,127.03£ 101.28£ 120.92£ 98.60£ 88.10£ 88.10£ 497.00£
PROJECTS - 2019/20 - 2023/24Long Stay Capacity (Decking) Post 2019 -£ -£ -£ -£ -£ -£ 2.00£ 5.00£ 12.50£ 10.80£ 8.00£ 38.30£ CIP Building Replacement (North Terminal) -£ -£ -£ -£ -£ -£ 10.00£ 10.00£ -£ -£ -£ 20.00£ North Terminal Avenue Reconfiguration -£ -£ -£ -£ -£ -£ 2.00£ 5.00£ 5.00£ -£ -£ 12.00£ North Terminal Baggage Reclaim Reconfiguration -£ -£ -£ -£ -£ -£ 3.00£ 15.00£ 23.00£ 23.00£ 64.00£ NT Short Stay Car Park -£ -£ -£ -£ -£ -£ 1.80£ 9.10£ 9.10£ -£ -£ 20.00£ Security Gate -£ -£ -£ -£ -£ -£ -£ -£ -£ 3.00£ 2.45£ 5.45£ ST Baggage Reclaim -£ -£ -£ -£ -£ -£ 1.00£ 1.00£ 5.00£ 5.00£ -£ 12.00£ Additional Staff Car Park Capacity -£ -£ -£ -£ -£ -£ 2.50£ 2.90£ -£ -£ -£ 5.40£ NT IDL Phase 2 (Post 2019) -£ -£ -£ -£ -£ -£ 20.00£ 20.00£ 13.00£ -£ -£ 53.00£ Baggage Capacity Expansion (Post 2019) -£ -£ -£ -£ -£ -£ -£ 2.00£ 2.00£ 8.00£ 8.00£ 20.00£ Railway Contribution -£ -£ -£ -£ -£ -£ 10.00£ 10.00£ 10.00£ 10.00£ 10.00£ 50.00£ Railway Station Upgrade -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ Bridge Over Railway -£ -£ -£ -£ -£ -£ -£ 1.00£ 1.50£ 7.50£ 10.00£ 20.00£ Urban Space Development -£ -£ -£ -£ -£ -£ -£ -£ 2.00£ 2.00£ 2.00£ 6.00£ ST Short Stay MSCP -£ -£ -£ -£ -£ -£ -£ 2.00£ 10.00£ 8.00£ -£ 20.00£ Product Development - Car Parking, Post 2019 -£ -£ -£ -£ -£ -£ 2.00£ 2.00£ 2.00£ -£ -£ 6.00£ Terminals Works Post 2019 -£ -£ -£ -£ -£ -£ 5.00£ 8.50£ 10.00£ 10.00£ 10.00£ 43.50£ Piers Works (Post 2019) -£ -£ -£ -£ -£ -£ 12.00£ 17.00£ 17.00£ 17.00£ 17.00£ 80.00£ CIP Growth -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ Airfield Capacity / Reconfiguration Works Post 2019 -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ Commercial Products -£ -£ -£ -£ -£ -£ 5.00£ 5.00£ 5.00£ 5.00£ 5.00£ 25.00£ Buy Back Cargo -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ New Build Office Development -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ Industrial Bays -£ -£ -£ -£ -£ -£ 4.00£ 4.00£ 4.00£ 4.00£ 4.00£ 20.00£ GASHCO -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ -£ Landside Restaurant -£ -£ -£ -£ -£ -£ 1.00£ 1.00£ 6.00£ -£ 8.00£
77.30£ 108.50£ 124.10£ 119.30£ 99.45£ 528.65£ SUBTOTAL 197.62£ 246.06£ 306.22£ 234.04£ 143.09£ 1,127.03£ 178.58£ 229.42£ 222.70£ 207.40£ 187.55£ 1,025.65£
-£
PROJECT NAME 5 YEAR TOTAL 5 YEAR TOTAL
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
24
SummarY
The total expenditure outlined in this investment plan for the 6 year Q5 totals £1,172 million in out-turn prices. We are continually striving to deliver more value for less by working more efficiently, ensuring that the right projects appearing in the CIP have been fully explored considering people, process, systems and infrastructure.
Looking ahead to 2014 and beyond, there is significant further investment required to expand current facilities where required, achieve greater operational efficiency and improve the passenger experience for all of our passenger segments. Beyond 2014, we are forecasting approximately £967.17 million of capital expenditure between 2014 and 2019, thereby continuing a similar rate of expenditure and improvement since the airport changed hands in December 2009.
This document represents a CIP issued as an output of and for the purposes of further consultation and thus does not represent a mandatory investment programme.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
3.1 Capital investment and the RegulatoRy and legislative Context
intRoduCtion
Capital development at Gatwick, as outlined in this chapter, takes place within a framework of regulatory and legislative policy.
CuRRent eConomiC Regulation
The current legislation which covers the economic regulation of airports is the Airports Act 1986 and the Civil Aviation Authority (Economic Regulation of Airports) Regulations 1986. Economic regulation applies in general to airports at which annual turnover has exceeded £1 million in two of the last three financial years.
Gatwick is currently a designated airport, regulated under the Airports Act 1986 and is therefore subject to economic regulation by the CAA. This regulation determines the level of airport charges Gatwick can charge its customers for the provision of services and establishes quality standards for those services. Regulatory bodies that influence Gatwick’s operations include:
• The Civil Aviation Authority (CAA), the UK’s independent aviation sector regulator that is responsible for airspace policy, safety regulation, consumer protection and the economic regulation of airports.
• The Competition Commission (CC), via an automatic referral from the CAA, is involved in the price control determinations for Gatwick, as well as being the UK’s overall competition regulator.
• The Department for Transport (DfT) is responsible for UK aviation policy and is currently undertaking a review of the economic regulation of airports.
The CAA (with an automatic referral to the Competition Commission) conducts a regulatory review every five years (known as the quinquennium), reviewing the setting of the level of airport charges at Gatwick every five years .The latest regulatory review took place in 2007/08 (i.e. price control review), where the regulator set the price cap for airport charges effective 1st April 2008 to 31st March 2013.
The review covers two major aspects of Gatwick’s business:
• The maximum level of charges that Gatwick can levy. In practice this has meant the CAA determining annual increases in revenue from airport charges per passenger restricted to not more than the rate of inflation (Retail Price Index) plus or minus x percentage points.
• Gatwick’s conduct in relation to customers, business partners and suppliers. The regulator is required to ensure that Gatwick acts in the interest of users.
Q5 extension
In February 2011 the CAA consulted on extending the current five-year regulatory period by one year to end on 31 March 2014 and published its decision in March 2011 formalising the extension.
Beyond Q5
The formal process of Constructive Engagement at Gatwick for the period beyond the end of Q5 commenced on 1 April 2012 with the publication of Gatwick’s initial business plan and ended in December 2012 with the publication of a joint (ACC/Gatwick) response to the CAA summarising the outputs of constructive engagement.
CHAPTER 3Consultation on the Capital investment pRogRamme
25
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
26
Review of the eConomiC RegulatoRy fRamewoRk Review of the eConomiC RegulatoRy fRamewoRk
Background
The Queen’s Speech (Airport Economic Regulation Bill) in May 2010 set out the intention of the new coalition Government to reform the law on the regulation of airports.
Under the existing regime, the CAA has 4 duties for the purposes of economic regulation, these are:
• to further the reasonable interests of users of airports within the UK. Users comprises airlines, passengers and other user of air transport services at the airport
• to promote the efficient, economic and profitable operation of such airports
• to encourage investment in new facilities at airports in time to satisfy anticipated demands by the users of such airports
• to impose the minimum restrictions that are consistent with the performance by the CAA of its functions.
In July 2010, the Government detailed its proposals for reform, and in March 2011 the Civil Aviation Bill was introduced in Parliament. In March 2011 the government also published ‘developing a sustainable framework for UK aviation: scoping document’. This document asked a series of questions about the future direction of aviation policy. The responses to the scoping document were subsequently used to inform the development of the draft aviation policy framework which the government published in July 2012 for consultation, and which closed in October 2012. The Civil Aviation Bill completed its passage through Parliament on 20 November 2012.
futuRe Regulation
The new Civil Aviation Act
The Civil Aviation Act became law on 19 December 2012 and paves the way for airports to offer better facilities and information for passengers. It is anticipated that the CAA will bring the new airport economic regulatory framework fully into force in April 2014.
The Act paves the way for the Civil Aviation Authority (CAA) to motivate airports to deliver better facilities, provide more information for passengers and give greater incentives for airports to prepare for disruptive events such as severe weather. The Act also makes provisions for future reforms to the Air Travel Organisers’ Licensing (ATOL) scheme, which offers financial protection for holiday makers in the event of their tour operator going bust.
The Act introduces, and enables, reform in 4 main areas:
• the framework for economic regulation of airports
• the legislative framework of the Civil Aviation Authority
• the Air Travel Organisers’ Licensing scheme (ATOL)
• conferring certain aviation security functions currently carried out by the Department for Transport, on to the CAA - responsibility for aviation security policy remains with the Secretary of State.
Under the new regulatory regime for airports, the CAA is empowered to carry out a market power test, as set out in the Act, to determine whether an airport operator should or should not be subject to economic regulation. This replaces the designation of airports for price control regulation by the Secretary of State.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
27
Gatwick along with Heathrow and Stansted airports are currently designated and their current price controls, set under the Airports Act 1986, will continue to run until 31 March 2014. Over the next few months, the CAA will determine how to apply the new regime set out in the Act to the airports that are subject to economic regulation after this date.
The new Act sees a number of key changes to the powers and responsibilities of the aviation regulator, the CAA, including:
• giving the CAA a single overriding duty, for its airport economic functions, to further the interests of passengers and owners of cargo in the provision of airport operation services
• creating a flexible licensing regime for regulated airports, enabling the CAA to include licence conditions that require airports to respond more effectively when things go wrong (e.g. severe weather)
• allowing the CAA, where appropriate, to replace fixed price caps on airports with lighter touch forms of regulation and removing unnecessary central government involvement from airport regulation
• giving the CAA more effective enforcement powers, allowing it to impose sanctions of up to 10% of an airport operator’s annual turnover and daily amounts of 0.1% of turnover for breaching licence conditions
• providing the CAA with a new role in promoting better public information about airline and airport performance levels, enabling passengers to make informed decisions when making travel arrangements
• providing the CAA with a new role to promote better public information about the environmental effects of aviation and measures taken to mitigate adverse effects
• conferring certain aviation security functions currently carried out by the Department for Transport, on to the CAA. Responsibility for aviation security policy, and giving aviation security directions to industry, will remain with the Secretary of State
Under the new measures the CAA will have a single primary duty and a number of further duties to which the CAA must have regard in carrying out the primary duty for the purposes of airport economic regulation.
Primary duty: to further the interests of passengers and owners of cargo (both present and future), in the provision of airport operation services and to do so, wherever appropriate, by promoting competition.
Further duties comprising:
• to ensure that licence holders are able to finance their provision of airport operation services
• to secure that all reasonable demands for airport operation services are met
• to promote economy and efficiency on the part of licence holders in their provision of airport operation services at regulated airports
• to secure that licence holders are able to take reasonable measures to reduce, control or mitigate adverse environmental effects of the airport to which the licence relates and aircraft using that airport
• to have regard to guidance issued by the Secretary of State
• to have regard to any international obligation of the UK notified to it by the Secretary of State
• to have regard to the principles of better regulation
In addition the CAA will have a duty not to impose or maintain unnecessary burdens.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
28
3.2 Consultative stRuCtuRe and annex g
The current consultative structure at Gatwick, born out of the Constructive Engagement process started in July 2005, which was initially focussed on the collaborative development Q5 between GAL and its airline community. Five years into Q5, the consultative dialogue between GAL and its airlines continues as an on-going process at Gatwick, helping in the assessment of the high-level options for the development of the airport. This includes details of costs for each option, impact on user charges, constructability, future-proofing, operational efficiency and, where possible, future airline costs.
Consultative Structure
The following diagram represents the current consultative structure at Gatwick:
annex g
Prior to the commencement of Q5, Gatwick airport and its airlines were invited by the CAA to consult on updating the existing agreement on information disclosure and consultation on investment plans. The outputs of this consultative process were passed over to the CAA for final adjudication. The CAA published the final agreement, namely Annex G incorporating its verdict on the outstanding issues of disagreement in its March 2008 Decision Document. A copy of Annex G can be seen in Appendix G.
Appendix E contains a summary of airline consultation at Gatwick since April 2012. This summary includes details of meetings and working groups relating to the development of Gatwick. The agenda items and topics of discussion between Gatwick and the airline community are listed by date and forum. Also included is a list of the agreements and disagreements in Appendix F since April 2012.
Consultation and the Design for Six Sigma (DfSS) Process
In order to adhere to Annex G consultation between the airport and airlines must take place:
• prior to Tollgate 2 decision(Brief) and
• prior to Tollgate 3 decision (Options) and
• prior to Tollgate 4 decision (Construction Decision)
Summary business cases are provided as soon as possible in draft form and finalised at Tollgate 4 as a method of articulating both the business case and cost benefit analysis. Business case summaries in effect
Joint Steering GroupCommunica�ons
and FeedbackACC
ACC Consulta�ve structure e.g. ACC
airport chargesannual mee�ng. ACCmembers will also berepresented at joint
working groups.
AOCAOC Consulta�ve
Structure
AOC members will alsobe represented at joint
working groups
- 9,1&1-(0#H(3&0<2)*(1&1,5&*)",-&
2$3&"%<()&1,5J*)",-1&21&)(K,#)(3&Jo
int W
orki
ng G
roup
s
Joint Working Structure AOC/IATA Structure
CapitalConsulta�on
for Beyond Q5projects
Capital ProgrammeBoard plus Working groups, set up to fact find for specificissues & projects -scheduled
throughout the year
Charges Group
plus specifiedcharges sub-
group and other sub-groups as
required
Input throughmembership
groups,communicatons
& feedback
Recommendatons, escala�ons & feedback
Decisions, guidance,recommenda�ons & feedback
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
29
provide a clear and concise summary including details of costs for each option, impact on user charges, constructability, future-proofing, operational efficiency and, where possible, future airline costs.
Over the course of Q5, Gatwick has been improving its capability and methodology for delivering projects in a complex environment of a space-constrained, ageing and regulated airport. The first phase of this improvement has been achieved with implementation of a suite of procedures and processes including the well-known Design for Six Sigma (DfSS) and Tollgate processes shown below:
engagement with ouR passengeRs and the wideR gatwiCk Community
The established formal structure for the collection of feedback and recommendations from Gatwick’s passengers and the wider Gatwick community can be seen next:
Established in 1956, GATCOM (Gatwick Airport Consultative Committee) is a statutory advisory body constituted by Gatwick in accordance with the Civil Aviation Act 1982 (as amended by the Airports Act 1986). It has 28 appointed representatives from a wide range of interests including local authorities, civil aviation, passenger, business and community and environmental groups. A Government representative is also present at the main Committee meetings, together with Gatwick’s Chief Executive Officer (CEO) and GAL senior management team.
PAG
GATCOM
Decisions, guidance,recommendations
& feedback
Decisions, guidance,recommendations
& feedback
GATCOMSteering Group
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
30
GATCOM meets quarterly to consider any question in connection with the operation and development of Gatwick and its effect on local communities, passengers, airlines and other users of the airport. GATCOM has two Sub-Groups, the GATCOM Steering Group and the Passenger Advisory Group (PAG). The role of the Steering Group is to give preliminary consideration to new or detailed matters to be dealt with by the Consultative Committee and to identify the facts and major issues, and make recommendations thereon.
Dialogue with the airport community will continue as we shape our future and build Gatwick’s reputation as London’s airport of choice. Further information about GATCOM can be accessed at http://www.ukaccs.info/gatwick/
As well as the formal structure outlined above, more informal communications are commissioned through the company website and using posters and other media. Gatwick also use YouGov (international market research agency) to carry out in-depth passenger research both face to face and via online questionnaires.
list of agReed stRategiC Changes to the Cip
The strategic change control process is well established at Gatwick as the agreed mechanism to facilitate changes to the CIP. Any significant change to the CIP occurs at a strategic level worked through at the working groups and Capital Programme Board (CPB) for submission to the Joint Steering Group (JSG).
Tactical changes associated with the day-to-day project delivery continue to happen through the capital project change control process at project board and working group level.
Strategic change control applies to projects that are identified in the CIP by a GAL Number. The criterion for listing a project in the CIP and thus allocation of a GAL Number is that the total Future Spend (including current year) or Anticipated Final Cost (AFC) is greater than £5 million. Any other projects that do not appear in the CIP as a separate line are included in the identified ‘Programme’ lines.
Changes to the CIP are tracked and submitted to the CPB and JSG for approval at milestone decision points in the development process. The triggers for evoking change control are:
• Spend in the year +/- 10% (or greater than £500k)
• Anticipated Final Cost (AFC) +/- 10% (or greater than £500k)
• Start/Finish +/- 1 year
• New projects
• Deleted projects
The process for making changes to triggers, as laid out in the CAA’s decision paper on trigger definition [Gatwick Airport - CAA decision on the specification of capital expenditure triggers March 2009] is outlined later in this chapter.
Since April 2012 a number of changes to the Capital Investment Programme (including R2 drawdowns) have been submitted to the Joint Steering Group (JSG). These changes covering the period April 2012 up to 31 March 2013 are summarised below:
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
31
CCRS LGW Ref No
GAL Project No Project Name Description of Change Date Approved at JSG
95a GAL184 ST & NT UKBA Arrivals Zones Creation of new project to support UKBA operations - Phase 1 13/06/2012
96 GAL 176 Facilities Asset Stewardship Fire Strategy - To address areas not complying with current Fire Safety regulations, following survey undertaken
11/04/2012
97 GAL 137 NT Baggage (NTB) Upgrade NT Baggage Hall access CCRS - Transfer of Scope and budget from NT Baggage Hall Access Project to NT Baggage project
13/06/2012
98 GAL 096 Main Runway Rehabilitation R2 Draw down for additional scope 13/06/2012
99 GAL124 Asset Stewardship R2 Draw down for additional scope - Pumping Station 18 09/05/2012
100 GAL 174 South Terminal Domestic Arrivals Confirmation of key elements of scope for Phase 1 09/05/2012
101 GAL 171 A380 on Stand Confirmation of budget and scope Project not yet supported by ACC
102 GAL 155 ST Security R2 Drawdown 13/06/2012
104 GAL173 Crew Reporting Confirmation of scope and budget at TG4 13/06/2012
105 GAL125 & 005 ST Baggage & Pier 1 R2 Draw down for additional scope 11/07/2012
106 GAL 179 AOB R2 Draw down for additional scope 08/08/2012
107 GAL 180 Q5 Minor Projects ( NT Baggage Voids) Confirmation of scope & AFC at TGA for NTB Voids 08/08/2012
108 GAL 125 & 005 ST Baggage & Pier 1 Confirmation of AFC at TG4 11/07/2012
109 GAL 175a NT IDL Project 2 Confirmation of AFC at TG3 11/07/2012
110 GAL 116 & 117 NT Extension Transfer of budget back into NTX 11/06/2012
111 GAL 183 Gatwick Stream Flood Attenuation Confirmation of AFC at TG3 17/07/2012
112 GAL 175b ST IDL at TG3 Confirmation of AFC at TG3 22/08/2012
113 GAL 111 P5 Reconfiguration - Scope changes R2 Draw down for additional scope In discussion
114 GAL 155 ST Security Scope & Budget Transfer Transfer Scope and Budget from ST Sec to ST Landside to align budget
05/09/2012
115 GAL 122 ST Landside Scope & Budget Transfer Transfer Scope and Budget from ST Sec to ST Landside to align budget
05/09/2012
118 GAL 184 ST & NT Border Force Arrivals Zones Phase 2 Not Supported by ACC
119 GAL 181 Beyond Q5 Capital Facilitation To carry out development works in NT & ST to inform the Gatwick Business plan for the period beyond Q5
Not Supported as capital funds by ACC
121 GAL 184 ST & NT Border Force Arrivals Zones Reduction in scope Not Supported by ACC
122 GAL 182 Q5+1 Minor Projects R2 Drawdown for additional scope - NT Foul Main revised alignment
10/10/2012
123 GAL 172 Airfield Peak Capacity Expansion ACDM55 - Phase 2 works 07/11/2012
124 GAL 175b ST IDL Phase 2 Confirmation of scope and budget at TG4 05/12/2012
125 GAL 185 Consolidated Security Gate R2 draw down to confirm brief at TG2 09/01/2013
126 GAL 005 & 125 Pier 1 & ST Baggage Transfer of scope and budget to NT voids project 09/01/2013
127 GAL 170 NT Voids Transfer of scope and budget from Pier 1 and ST Baggage project
09/01/2013
128 GAL 096 Main Runway Rehabilitation R2 Drawdown In discussion
129 GAL 182 Q5+1 Minor projects Check-in Bag drop trials 06/03/2013
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
32
The full list of changes brought through the established CCRS (Change Control Request Sheet) change control process since April 2012 is provided in Appendix C – Changes to Investment Programme – Tracker (April 2012 – March 2013).
Risk management (R2 dRawdown pRoCess)
Improved processes and practices have been implemented at Gatwick regarding the management of risk at a portfolio level. These updated processes and practices demonstrate a clear view of remaining risk allowances and where it has been allocated, driving project performance to deliver within their budgets and holding CIP funds outside of the projects for unforeseen portfolio risks. The portfolio risk (R2) / contingency procedures that have been implemented:
• Recognise the requirements of Annex G.
• Remove exposure by projects to uncontrolled allocation/expenditure.
• Demonstrate improved reporting, managed within Project Controls.
• All portfolio risk (R2) / contingency drawdown greater than £250k is consulted prior to drawdown with the airlines. If a portfolio risk (R2) / contingency drawdown is less than £250k, but a previous drawdown has been made for a particular project then this is also consulted prior to draw down with the airlines.
The drawdown of risk from the portfolio fund uses the agreed change control process, as outlined previously in this chapter. The full list of R2 drawdowns that have been consulted with the airline community at Gatwick since the publication of the 2012 CIP has been provided above.
CCRS LGW Ref No
GAL Project No Project Name Description of Change Date Approved at JSG
130 GAL 175b ST IDL Phase 2 Tollgate 4 Revised TG4 AFC & R2 Return In progress
131 GAL 134 Pier 6 TG3 06/03/2013
132 GAL 183 Gatwick Stream Flood Attenuation Confirmation of AFC at TG4 06/03/2013
133 GAL 185 Consolidated Security gate Confirming Scope Budget/ AFC at TG3 09/04/2013
134 GAL 175a NT IDL Reconfiguration Project 2 Revisited TG3 06/03/2013
0135a GAL 155 ST Security R2 Drawdown - Final Accounting 06/03/2013
136 GAL 116 & 117 NT Extension Final Accounts - R2 Drawdown 06/03/2013
137 GAL 186 NT IDL Project (BQ5) BQ5 pull forward - R2 Draw-down Updated and Approved as CCRS LGW '0141
138 GAL 187 NT Security Project (BQ5) BQ5 pull forward - R2 Draw-down Updated and Approved as CCRS LGW '0142
139 GAL 174 ST Domestic Arrivals R2 Drawdown in progress
140 GAL 183 Flood Attenuation R2 Drawdown in progress
141 GAL 186 NT IDL Project (BQ5 pull forward) R2 Drawdown 09/04/2013
142 GAL 187 NT Security Project (BQ5 pull forward) R2 Drawdown 09/04/2013
143 GAL 188 ST Landside Ceilings Project (BQ5 pull forward) R2 Drawdown 09/04/2013
144 GAL 182 Minor Projects - Security Fixed Posts R2 Drawdown 09/04/2013
145 GAL 134 Pier 6 - Pier Service Viability and Modelling R2 Drawdown 09/04/2013
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
33
tRiggeR pRojeCts
Capital investment triggers have been a feature at Gatwick since the beginning of the five-year price control period Q5 that commenced on 1 April 2008. In the broadest sense the trigger projects specify a reduction to the level of the revenues that the airport can expect in airport charges if certain milestones are not reached in respect of relevant capital projects by defined dates. The CAA considers capital investment triggers to be an important aspect of the financial incentives placed on Gatwick, to encourage timely and efficient delivery of the investment projects that airline users have discussed in constructive engagement and for which they are paying through airport charges.
The CAA published its final decision regarding trigger definition at Gatwick on 25 March 2009 [Gatwick Airport - CAA decision on the specification of capital expenditure triggers]. It establishes a baseline specification against which any proposed changes could be measured and assessed. It is worth noting that changes have been made to some of the trigger projects with agreement and airline support since then and are documented on the restricted website for Constructive Engagement. These changes have been made in accordance with the process set out by the CAA in their document ‘CAA decision on the specification of Capital Expenditure triggers - March 2009‘. There is also a process for testing whether the triggers have been met, this is laid out in the document ‘Proposed Change to trigger verification process for Gatwick Airport, CAA Decision – September 2011’. The CAA has emphasised that it expects the process of change control applied to triggers to enable an airport and its users to adapt to circumstances where priorities change.
Capital expenditure originally projected on one project may thus be diverted to extend the scope of, or bring forward, some other project. Although, whilst the CAA would be prepared to approve changes, which either added to, or reduced the amounts at risk, it did not anticipate that this would be likely and would normally seek to limit changes to the price control under these arrangements to triggers and would not seek to make other changes. Examples where capital expenditure has been re-allocated are as follows:
• Pier 7 project to Pier 2 and Pier 1
• Pier 7 to Pier 5 (Additional NT Pier Service)
summaRy of Q5 tRiggeR pRojeCts
All Q5 triggers have been completed apart from ST Baggage and Pier 7. The former project has been amalgamated with the Pier 1 project to deliver one single project comprising both the construction of a new South Terminal baggage factory (GAL 125) and Pier 1 (GAL 005). Likewise it was decided to halt the Pier 7 project and to instead refurbish Pier 2, reconfigure Pier 5 and build a new Pier 1, as outlined above. Airlines have been supportive of the above changes. The trigger date for delivery of benefits associated with the ST Baggage project was 31st January 2013. In light of the trigger documentation and Annex G, Gatwick paid the monthly ST Baggage factory trigger amounting to £0.53m.
tRiggeR pRojeCts in the Q5+1 extension yeaR
As part of the agreement to extend Q5 by one year, it was decided to trigger some major projects due to occur in the regulatory year 2013/14. The projects agreed by the airport and airlines at the May 2012 JSG to have triggers applied are detailed below:
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
34
Completion date Trigger date Trigger Value (monthly)
Trigger Value (maximum)
Project Capital Cost at TG4
NT Pier 5 Phase 1 Jul-13 16-Sep-13 £264,000 £1,320,000 £72.9m
Crew Reporting May-13 31-Oct-13 £189,000 £1,320,000 £20.55m
Pier 1 demolition Sep-13 31-Dec-13 £147,000 £440,000 £184m (Phase 1 and 2 )
ST IDL Phase 2 Dec-13 31-Mar-14 Not Applicable £1,320,000 £21.7m
the end of Q Review by the Caa
The End of Q review is an audit by the CAA focusing on:
• Capital expenditure efficiency taking account of the context of the evolution of the CIP discussions and agreements at airline forums
• Whether the overall capital programme has been efficiently incurred
• Whether capital expenditures on five specific projects have been efficiently incurred and met the consultation requirements of Annex G
• Whether consultation with users on airport development and investment in relation to scope changes for the five projects met requirements
• Lessons learnt and recommendations for assessing capital efficiency and consultation that can be practicably implemented during the preparation and implementation of the capital investment plan for the period beyond Q5.
Projects selected by the CAA in consultation with the Airport and the ACC were:
• North Terminal extension (check-in and baggage reclaim)
• South Terminal baggage and Pier 1
• North Terminal baggage upgrade
• Main runway resurfacing
• Crew reporting
A summary of the findings from the CAA’s end of year review will be provided in the next CIP publication.
futuRe Capital plan Consultation
GAL’s revised Business Plan was submitted in January 2013, representing Gatwick’s second regulatory submission to the constructive engagement process. As mentioned in the 2012 CIP, the formal consultation process of Constructive Engagement (CE) for the period beyond Q5 officially commenced in April 2012, with the initial GAL business plan submitted to the airline community in April 2012, representing Gatwick’s initial submission to the constructive engagement process. Our initial business plan explained how our service proposition results in the capital expenditure proposals contained in the business plan, outlining how we will bridge the gap between our current capability and our future service proposition. A proposition that we firmly believe will give us a competitive advantage and help Gatwick achieve our ambition to ‘ become London’s airport of Choice’.
Between April and mid December 2012, weekly Constructive Engagement Working Group (CEWG) meetings were held to consult on GAL’s initial Business Plan. The outcome of the weekly CEWG meetings has informed GAL’s second regulatory Business Plan submission in January 2013 including the revised submission of capital expenditure as explained previously in Chapter 2.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
35
IntroductIon
This chapter contains both individual projects and programme descriptions, including cost breakdowns for all individual projects over £5 million (out- turn) within the 6 year period of Q5. The drivers for investment at project level, the cost breakdowns of the projects as well as the outputs that will be delivered, in terms of infrastructure and benefits to airlines and passengers are also outlined.
crItErIA For ProVISIon oF InForMAtIon
Criteria for provision of information are as follows:
• Project Descriptions for all projects or programmes over £5 million (out -turn) within the 6 year period of Q5 provided
• Cost breakdowns have only been provided for Projects that are ‘in delivery’ but not for ‘Programmes’ as the latter consist of various initiatives , such as GAL 096 - Airfield Programme including Main Runway and Northern Runway re-surfacing.
• No cost breakdowns are provided post Tollgate 5 following completion of construction, however a total cost is provided.
• The project description sheets of Projects shown as completed in the 2012 CIP have not been re-produced in the following pages.
The table on the next page outlines the contents of Chapter 4.
CHAPTER 4ProjEct dEScrIPtIonS
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
36
GAL Number Project / Programme Name Q5 Cost Breakdown
Q5 +1 Project
Comment Page Number
GAL 063 Security Development Programme Y Programme 53
GAL 096 Airfield Programme including Runway Resurfacing Y Programme 51
GAL 111 North Terminal Additional Pier Service (Pier 5) Y Y Y 41
GAL 125 & GAL 005 South Terminal Baggage & Pier 1 Y Y Y 47
GAL 134 North Terminal Additional Pier Service (Pier 6) Y 44
GAL 137 North Terminal Baggage Upgrade Y 49
GAL 143 Clean, Working & Friendly Y Programme 55
GAL 157 North Terminal Security Y Y 39
GAL 159 & GAL 135 IT Transformation & IT Programme Y Programme 54
GAL 160 Surface Water including Pond D Y Programme 84
GAL 165 & GAL 166 Taxiway Papa & November Y Y 37
GAL 167 Railway Contribution Y Y 56
GAL 171 A380 on Stand Y Y Programme 57
GAL 172 Airfield Peak Capacity Expansion (ACDM 55) Y Y Programme 59
GAL 173 Crew Reporting Y Y 61
GAL 174 South Terminal Domestic Arrivals Y 63
GAL 175a North Terminal IDL Reconfiguration Y Y Y 65
GAL 175b South Terminal IDL Reconfiguration Y Y Y 67
GAL 176 Facilities Asset Stewardship Y Y Programme 69
GAL 177 Commercial Asset Stewardship Y Y Programme 71
GAL 178 Airfield Asset Stewardship Y Y Programme 73
GAL 179 Airfield Operations Building Y Y Y 75
GAL 180 Q5 Minor Projects Y Programme 77
GAL 181 Beyond Q5 (BQ5) Development Programme 79
GAL 182 Q5+1 Minor Projects Y Programme 81
GAL 183 Gatwick Stream Flood Attenuation Programme 82
GAL 184 ST & NT UK Border Force (UKBF) Arrival Zones Y 86
GAL 185 Consolidated Security Gate Y 89
ProjEct dEScrIPtIon ShEEt - SuMMAry oF InForMAtIon ProVIdEd
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
37GAL 165 & 166 tAxIwAyS PAPA & noVEMbErCurrent status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:Full rehabilitation to re-life the pavement: • Resurfacing 100mm of existing bituminous surfacing & re-profile• Replacement of AGL luminaire, primary and secondary cabling and
transformers• Rectification of full Code E taxiway non-conformances to CAP 168
Requirements Taxiways Papa and November are main arteries for the airport and are critical to maintaining airside operations, contributing to the airport achieving its targets on runway capacity and pier service for both the North Terminal and South Terminal. Full rehabilitation of the northern sections of Papa and November to re-life the pavement condition for a further 15 years for the bituminous pavements is required, as well as pavement, drainage and AGL repairs to the southern sections.
Benefits Rehabilitating at this time will:• prevent future deterioration of the pavement sub-layers;• ensure maintenance of CAP168 compliance and the ability to operate
safely;• mitigate against high maintenance (planned and unplanned) costs;• mitigate against unplanned closures and associated delays;• mitigate against a reduction in capacity and service to the main and
northern runways and service to piers 1 (during northern runway ops) 2, 3, 4, and 5.
Project Start Date December 2011
Project End Date June 2012 (Operational – TG 5)
Total Capital Expenditure£ millions (est.)
Total £5.4m Q5 - £5.1m Q5+1 - £0.3m
As this project has passed through Tollgate 4 this value represents a cost amount attributable to a defined scope and programme that will, or has been delivered.
Likely impact on operating costs
The main runway rehabilitation business case summary, as submitted to the JSG , in July 2011 highlighted the likely impact on operating costs
Indicative impact on airport charges in Q5 and/or Beyond Q5
Additional airport charges per total Gatwick passenger beyond Q5 : £0.03
Impact on Gatwick’s competitive position
Rehabilitation of taxiways Papa and November assures on-going delivery of service for the airport’s primary asset, thereby enabling airlines to operate and provide consistent levels of service for passengers.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
38
Basis of decision (options) Required to maintain Gatwick’s aerodrome license with options to improve performance and optimise capacity. Option evaluation has thus far focused on the location and size of the future developments as part of the master plan and Constructive Engagement work.
Linked projects / interdependencies
• Main Runway Rehabilitation• A380 on Pier• Airfield Peak Capacity Expansion• Airfield Asset Stewardship
Asset lifecycle 15 years
Drawing/Image showing location
Current Stage Cost Breakdown
Total £ M % of Total Cost
Base Construction / Direct Costs
4.4 81
Project Design / on-Costs 0.6 11
Risks: Project Risk (R1) 0.4 8
overall Total 5.4 100
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
39GAL 157 north tErMInAl SEcurIty Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:This project aims to provide additional Security lanes for use during peak periods to maintain or improve the passenger experience. Failure to deliver this enhancement will degrade customer service levels and increase queue times as passenger numbers increase at peak operational times.
Requirements Delivering of capacity of an additional 4 lanes within central search. It is assumed 17 lanes are delivered in Q5 with safeguarding for an eventual 24 lanes in the future.
Delivery of a professional, efficient and courteous experience for passengers
Benefits Supports Gatwick’s strategic priority to “deliver the best passenger experience “through the provision of infrastructure that provides resilience for our security product at peak times in the North Terminal. Supports Gatwick’s strategic priority to “help airlines grow” by providing facilities to support on time departure by delivering appropriate capacity requirements.
Project Start Date October 2010
Project End Date May 2012 (Operational – TG 5)
Total Capital Expenditure£ millions (est.)
Total - £10.6m Q5 - £10.4m Q5+1 - £0.2m
As this project has passed through Tollgate 4 this value represents a cost amount attributable to a defined scope and programme that will, or has been delivered.
Likely impact on operating costs
Increases to utilities and rates.
Operating costs may see reductions.
Indicative impact on airport charges in Q5 and/or Beyond Q5
It has been agreed that summary business cases will be provided at either Tollgate 4 (Construction Decision) or potentially at Tollgate 3 (Options Decision) for some projects as a method of articulating business case and cost benefit analysis [Joint Steering Group, 7th September, 2011]. This particular project was past Tollgate 4 prior to this agreement.
Impact on Gatwick’s competitive position
Fast, efficient and effective security search processes enhance Gatwick’s ability to compete through provision of efficient passenger process facilitating the airlines’ ability to depart on time.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
40
Basis of decision (options) The option evaluation focused on the development in the context of Gatwick’s master plan and included non-build options. The conclusion recommended a consolidated area with sufficient flexibility to safeguard for future expansion.
Linked projects / interdependencies
• North Terminal Extension• North Terminal Baggage• North Terminal Forecourt• North Terminal Interchange
Asset lifecycle Taxiways Papa and November are main arteries for the airport and are critical to maintaining airside operations, contributing to the airport achieving its targets on runway capacity and pier service for both the North Terminal and South Terminal. Full rehabilitation of the northern sections of Papa and November to re-life the pavement condition for a further 15 years for the bituminous pavements is required, as well as pavement, drainage and AGL repairs to the southern sections.
Benefits 20 years
Drawing/Image showing location
Current Stage Cost Breakdown
Total £ M % of Total Cost
Base Construction / Direct Costs
7.6 72
Project Design / on-Costs 2.0 19
Risks: Project Risk (R1) 1.0 9
overall Total 10.6 100
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
41GAL 111 north tErMInAl AddItIonAl PIEr SErVIcE (PIEr 5)Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:The Pier 5 project has the overall business objective of delivering improved Pier Service Levels to meet future growth in passenger numbers in the North Terminal and support the overall Pier Service Level target of 95%. This will be achieved by reconfiguring the stands, providing independent access to each aircraft parking position, dedicated gate rooms for each stand and removing passenger cross flows within the pier. Additional objectives include ensuring efficient operations, improving passenger experience and improving the quality of service.
Requirements • Modernisation of outdated facility to improve passenger experience• Reconfiguration of stands to accommodate Full Code C• Removal of passenger cross flows within the Pier to allow simultaneous
gate and stand operations
Benefits • 0.8 million additional passengers rising to 1.1 million by 2024 will be Pier served (equivalent to 4% of North Terminal passengers rising to 5% by 2024)
• A greater number of people will walk less distance to gate, and spend more time in the IDL
• Improved PRM facilities• Reduced dwell time at gate• Flexible stands accommodate different aircraft types with independent
and simultaneous embarkation/disembarkation on MARs stands• Additional nodes allow simultaneous operations• Provision of facilities for additional 3 x Full Code C and 1 x Code D/E• Greater flexibility to respond to schedule change, positively impacting
On Time Performance and Punctuality• Removal of current stand planning constraints• More efficient utilisation of space for servicing of aircraft• Removal of passenger cross-flows and associated operations
inefficiency• Current segregation of arrivals and departures relies on adherence to
operating procedures. Vertical segregation will mitigate risk of security breaches
Project Start Date January 2011
Project End Date May 2014
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
42
Total Capital Expenditure£ millions (est.)
Q5 - £35.6m Q5+1 - £38.7 m
As this project has passed through Tollgate 4 this value represents a cost amount attributable to a defined scope and programme that will, or has been delivered.
Likely impact on operating costs
Reduction in airline coaching costs of £1.00 per passenger (estimated benefit of £820k in 2015/16)
Increased IDL dwell time of up to 5 mins per incremental pier served passenger (an estimated benefit of £170K in 2015/16)
Indicative impact on airport charges in Q5 and/or Beyond Q5
Beyond Q5 Over Pier 5 Life (20 yrs)
Additional airport charges per total Gatwick passenger
£0.26 £0.18
Airline Cost per incremental Pier 5 served passenger
£10.6 £6.2
Basis of decision (options) Do nothing – implications of the do-nothing scenario include:• Pier Service Level in the North Terminal will reduce from 96% (2012) to
92% in 2018.• Remote stand coaching requirements will increase• 17 Construction options identified
Linked projects / interdependencies
• North Terminal Interchange• North Terminal Extension• North Terminal Multi-storey Car Park• North Terminal Early Bag Store Expansion• North Terminal Security• North Terminal IDL Capacity Expansion• North Terminal Landside Arrivals/Onward Travel• Check-in Hall Reconfiguration• North Terminal Pier Service
Asset lifecycle 20 years
Drawing/Image showing location
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
43
Current Stage Cost Breakdown
Total £ M % of Total Cost
Base Construction / Direct Costs
55.7 75
Project Design / on-Costs 11.2 15
Risks: Project Risk (R1) 7.4 10
overall Total 74.3 100
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
44GAL 134 north tErMInAl AddItIonAl PIEr SErVIcE (PIEr 6) Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:To deliver the required Pier Service Levels to meet the future growth in passenger numbers and fleet mix in the North Terminal. This will ensure efficient operations and an improved passenger experience. The purpose of the project is to continue to maintain Pier Service Levels above 95%, and to safeguard operations and Pier Service Levels for future forecastst.
Requirements • To meet 95% Pier Service Levels in line with forecasts• To meet future fleet mix requirements including the provision for
Code F• Acceptable travelling time to gate and passenger journey quality • New air bridges and MARS capable stands with independent aircraft
parking positions serving short and long haul aircraft
Benefits • Maintain Pier Service Levels above 95% as passenger numbers increase• Provision of A380/Code F and increased long haul capability• Provision of IATA Level of Service C gate lounges• Improved PRM facilities• Greater flexibility to respond to schedule change, and improve On
Time Performance• More efficient utilisation of space for aircraft servicing• Independent embarkation/disembarkation on MARS stands
Project Start Date April 2008
Project End Date To Be Confirmed - Dependant on chosen option
Total Capital Expenditure£ millions (est.)
£184.2m Q5 - £8.7m Q5+1 - £2.8m BQ5 - £175.5m
Likely impact on operating costs
Revenue Impact• Incremental revenues of £1m per annum due to new CIP provision
from 2019/20 onwards• Potential additional income upside from additional WDF and catering
provisions: to be quantified at TG4On-going Opex• £600k per annum increase in rates• £400k per annum increase in utilities for heating and lighting• £50k per annum increase in cleaning costsOne-Off Costs• No one-off costs assumed at this stage.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
45
Indicative impact on airport charges in Q5 and/or Beyond Q5
BQ5 Over Asset Life (40 yrs)
Increase in airport charges per passenger
£0.236 £0.239
Impact on Gatwick’s competitive position
Provision of long term Code F capability to allow Gatwick to compete with other UK and European airports, in line with future forecast fleet mix and long haul growth, further supporting our ambition to become London’s airport of choice.
Basis of decision (options) A detailed options assessment process has been undertaken, driven by the use of the Quality Function Deployment (QFD) process to select the site, and option within that site. The Level 1 QFD to select the site included the following options: • Cargo Pier (Pier 7) • Tower Stands Shuttle Pier (Single Mode) • Tower Stands Shuttle Pier (Mixed Mode) • Pier 6 Southern Extension • Pier 6 Deepening • Pier 6 Deepening & Tower Stands Shuttle Pier (Single Mode) • Pier 6 Deepening & Tower Stands Shuttle Pier (Mixed Mode) • Pier 6 South Ext & Tower Stands Shuttle Pier (Single Mode) • Pier 5 Extension (Fuel Farm)
The preferred site after this analysis was Pier 6 Southern Extension across the base QFD and all sensitivity tests.
The Level 2 QFD analysed the potential options within the site boundary and considered 5 options (A to E) against 31 stakeholder identified criteria and scoring parameters. The working session to agree the results of the options assessment unanimously agreed that Option E was to be taken forward. This is reflected in the scope section of this Business Case.
Linked projects / interdependencies
• North Terminal Interchange• North Terminal Extension• North Terminal Multi-storey Car Park• North Terminal Early Bag Store Expansion• North Terminal Security• North Terminal Pier Service (Pier 5) • North Terminal IDL Capacity Expansion• North Terminal Landside Arrivals/Onward Travel• Check-in Hall Reconfiguration• North Terminal Pier Service
Asset lifecycle 40 years
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
46
Drawing/Image showing location
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
47GAL 125 & GAL 005 South tErMInAl bAggAgE & PIEr 1Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:Construction of a new South Terminal Baggage Factory and Pier 1, including delivery of an automated baggage storage facility.
Requirements • New South Terminal Baggage Factory with up to 100 make up positions and facilities for out of gauge and transfer baggage make up.
• New automated departures baggage store for up to 2600 bags.• New Pier 1 with 5 gates and stands.
Benefits • Increase in hourly throughput from 3800 to 4250 bags per hour• 5 fast turn stands with push-back conflicts eliminated – will increase
OTP, reducing delays to push backs due to the new design of the Apron/stands.
• New 2600 bag early bag store enabling early check in.• Support for reduction in check-in transaction times• Support for reduction in resource requirements at check-in and in
baggage make-up areas• Consistent, reliable baggage system performance:• Reduction in short shipped bags due to system failure• Operationally the solution will enable GAL to route around ‘outages’
which will improve the ‘upstairs’ experience and reduce the need to utilise cages.
• Improved passenger perception of pier, gate and stand facilities• All departing South Terminal passengers and some arriving Pier 1
passengers will benefit.• Support for reduction in aircraft turnaround times
Project Start Date April 2008
Project End Date May 2015
Total Capital Expenditure£ millions (est.)
Total £178.9m Q5 - £63.3m Q5+1 - £27m BQ5- £88.6m
As this project has passed through Tollgate 4 this value represents a cost amount attributable to a defined scope and programme that will, or has been delivered.
Likely impact on operating costs
Operating costs will increase slightly due to increases in utilities and maintenance associated with the baggage store. Operating costs for airlines are expected to decrease due to potential for more efficient resourcing at check-in and baggage make up positions.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
48
Indicative impact on airport charges in Q5 and/or Beyond Q5
Additional airport charges per passenger in Beyond Q5 amounts to £0.44
Impact on Gatwick’s competitive position
Provision of new baggage system required to enable Gatwick to compete with other European airports’ check-in and pier products.
Basis of decision (options) Option evaluation has reviewed: • Option 1: HBS replacement only – does not meet capacity/service
requirements • Option 2: Replacement of HBS in Q5 and partial construction of
baggage factory in Q5 with the remaining construction beyond Q5.• Option 3 (Preferred Option) Delivery of entire Baggage and Pier 1
project spanning Q5 and beyond.
Linked projects / interdependencies
• South Terminal IDL Reconfiguration• Crew reporting improvement• Domestic Arrivals• Airfield projects
Asset lifecycle 25 years
Drawing/Image showing location
Current Stage Cost Breakdown
Total £ M % of Total Cost
Base Construction / Direct Costs
110.9 62
Project Design / on-Costs 46.5 26
Risks: Project Risk (R1) 21.4 12
overall Total 178.9 100
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
49GAL 137 north tErMInAl bAggAgE (ntb) Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:The North Terminal Baggage Upgrade specifically supports the North Terminal extension, providing infrastructure in line with future passenger and fleet mix growth forecasts.
Requirements • Any input/output.• Direct bag processing • Integrated transfer operation• Intra-terminal transfer time within 15 minutes• Baggage storage
Benefits • Safe traffic segregation in bag halls• Manual Handling - compliance to latest HSE requirement.• Security – compliance to latest DfT requirements for baggage halls • Full bag tracking through the system
Project Start Date April 2008
Project End Date December 2012 (Operational – TG5)
Total Capital Expenditure£ millions (est.)
Total : £46.4m Q5 - £45.2m Q5+1 - £1.2m
As this project has passed through Tollgate 4 this value represents a cost amount attributable to a defined scope and programme that will, or has been delivered.
Likely impact on operating costs
Increases to utilities, operating costs and rates.
Indicative impact on airport charges in Q5 and/or Beyond Q5
It has been agreed that summary business cases will be provided at either Tollgate 4 (Construction Decision) or potentially at Tollgate 3 (Options Decision) for some projects as a method of articulating business case and cost benefit analysis [Joint Steering Group, 7th September, 2011]. This particular project was past Tollgate 4 prior to this agreement.
Impact on Gatwick’s competitive position
To support the capacity increases in the North Terminal, in line with future growth forecasts, and providing a flexible efficient baggage system to support out airlines and passengers.
Basis of decision (options) Option evaluation focused on the location and size of the development as part of the master plan and Constructive Engagement work and the delivery of associated benefits to all airport users. The image shown is for illustrative purposes only. Option evaluation reviewed all potential build and non-build options.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
50
Linked projects / interdependencies
North Terminal Extension
Asset lifecycle 20 years
Drawing/Image showing location
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
51GAL 096 AIrFIEld ProgrAMME IncludIng runwAy rESurFAcIngCurrent status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:Programme of airfield works incorporating a project to resurface the northern and main runways as well as other airfield works.
Requirements Requirements of the main runway rehabilitation are as follows:The rehabilitation of block pavements and replacement of airfield ground lighting to assure compliance with CAP 683 and CAP 168• Potential provision of additional Rapid Exit Taxiways• Targeted operational cost reductions • Targeted reduction in CO2 emissions
Benefits Protecting and enhancing Gatwick’s reputation and helping our airlines grow through rehabilitation of the airport’s primary asset, meeting the requirements of the forecast fleet mix with potential opportunity to enhance value and efficiency.
Project Start Date November 2011
Project End Date November 2012 (Operational – TG5)
Total Capital Expenditure£ millions (est.)
Total £66.3m Q5 - £66.0m Q5+1 - £0.3m
As this project has passed through Tollgate 4 this value represents a cost amount attributable to a defined scope and programme that will, or has been delivered.
Likely impact on operating costs
The main runway rehabilitation business case summary, as submitted to the JSG, includes additional information and highlights the likely impact on operating costs.
Indicative impact on airport charges in Q5 and/or Beyond Q5
Additional airport charges per total Gatwick passenger in Beyond Q5 £(0.18)
Impact on Gatwick’s competitive position
Rehabilitation of the main runway ensures on-going delivery of service for the airport’s primary asset, thereby enabling airlines to operate and provide consistent levels of service for passengers.
Basis of decision (options) Required to maintain Gatwick’s aerodrome license with options to improve performance and optimise capacity. Option evaluation has thus far focused on the location and size of the future developments as part of the master plan and Constructive Engagement work.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
52
Linked projects / interdependencies
• Taxiways Papa & November• A380 on Pier• Airfield Peak Capacity Expansion• Airfield Asset Stewardship
Asset lifecycle 11 years
Drawing/Image showing location
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
53GAL 063SEcurIty dEVEloPMEnt ProgrAMMECurrent status within Gatwick project process
Various projects at various stages
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:Portfolio of projects designed to broaden the airport security footprint to constantly reduce vulnerability at tour airport campus.
Requirements Provision of a safe environment for travellers and other stakeholders by mitigating security risks. The types of protection provided by this programme provides and enhances can be physical, technological and process improvements.
Benefits Security Development Programme ensuring the provision of a safe environment for travellers and other stakeholders by mitigating security risks.
Project Start Date April 2008
Project End Date March 2013
Total Capital Expenditure£ millions (est.)
Total £5.5m Q5 - £5.5m
As this project has passed through Tollgate 4 this value represents a cost amount attributable to a defined scope and programme that will, or has been delivered.
Likely impact on operating costs
It is unlikely there will be an impact on handling agent and airline costs. Airport impacts are expected to be minimal.
Indicative impact on airport charges in Q5 and/or Beyond Q5
Not provided as this is a programme of works with various individual elements that attract different opex, revenue and asset life assumptions.
Impact on Gatwick’s competitive position
This programme will ensure that Gatwick can ‘Protect and enhance our reputation’ through ensuring operational availability of its assets, and no H&S risk to our passengers.
Basis of decision (options) Portfolio of projects at various development stages.
Linked projects / interdependencies
Portfolio of projects that are linked with many other projects in the CIP by the location within which they are executed
Asset lifecycle Various projects with varying asset lifecycles
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
54GAL 159 & GAL 135 It trAnSForMAtIon & It ProgrAMMECurrent status within Gatwick project process
Various projects at various stages
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:Continued transformation, and replacement of Gatwick’s operational systems, infrastructure and processes
Requirements A range of initiatives designed to separate and transform Gatwick’s systems, infrastructure and processes, maximising airport efficiencies, undertaken in priority order.
Benefits The primary strategic driver of the IT Programme is to ‘Deliver the best passenger experience “by improving our operational systems and thereby facilitating operational efficiencies.
Project Start Date April 2008
Project End Date March 2013
Total Capital Expenditure£ millions (est.)
Total £46.6m Q5 - £46.5m Q5+1 - £0.1m
Likely impact on operating costs
This programme seeks to facilitate operational efficiencies and thereby improve the passenger journey.
Indicative impact on airport charges in Q5 and/or Beyond Q5
Not provided as this is a programme of works with various individual elements that attract different opex, revenue and asset life assumptions
Impact on Gatwick’s competitive position
Gatwick needs to take advantage of technological advances in order to ensure it can provide the best passenger experience and thereby compete with other airports.
Basis of decision (options) Portfolio of projects at various development stages.
Linked projects / interdependencies
Various linked projects with interdependencies across the airport campus
Asset lifecycle Various projects with varying asset lifecycles
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
55GAL 143 clEAn, workIng And FrIEndly ProgrAMMECurrent status within Gatwick project process
Various projects at various stages
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:The Clean, Working and Friendly programme demonstrates Gatwick’s on-going commitment to invest in passenger-facing infrastructure such as flooring and seating, in order to fix the basics
Requirements A range of investments in passenger facing and core operational infrastructure in North and South Terminals, undertaken under prioritisation and in conjunction with other developments at Gatwick
Benefits The Clean, Working and Friendly programme demonstrates Gatwick’s on-going commitment to invest in passenger-facing infrastructure such as flooring and seating, in order to fix the basics.
Project Start Date April 2008
Project End Date March 2013
Total Capital Expenditure£ millions (est.)
Total £13.6m Q5 - £13.6m
Likely impact on operating costs
Airport impacts are expected to be minimal.
Indicative impact on airport charges in Q5 and/or Beyond Q5
Not provided as this is a programme of works with various individual elements that attract different opex, revenue and asset life assumptions.
Impact on Gatwick’s competitive position
The Clean, Working and friendly programme ensures that Gatwick can ‘Protect and enhance our reputation’.
Basis of decision (options) Portfolio of projects at various development stages.
Linked projects / interdependencies
Portfolio of projects that are linked with many other projects in the CIP by the location within which they are executed.
Asset lifecycle Various projects with varying asset lifecycles
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
56GAL 167 rAIlwAy contrIbutIon
SCoPE:Make a contribution towards the upgrade of the Gatwick Railway station, to enhance passenger experience and flow and to make a more economical sustainable future for Gatwick.
Requirements • Improvements to the main station concourse to update and its appearance.
• An additional seventh platform capable of handling trains of up to 12 carriages, with Vertical Circulation Core from a new walkway.
• Improvements to access and egress to and from platform 5 & 6.• Renewal of existing signalling system in the Gatwick area.
Benefits • Additional capacity at Gatwick stations.• Improve passenger experience at Gatwick Station.• Support Section 106 agreement.• Improved access to platforms.• Supports retention for Gatwick Express
Project Start Date January 2011
Project End Date December 2013
Total Capital Expenditure£ millions (est.)
Total £7.7m Q5 - £1.8m Q5+1 - £5.9m
Likely impact on operating costs
None anticipated.
Indicative impact on airport charges in Q5 and/or Beyond Q5
Additional airport charges per passenger (in 2013 constant prices)
Beyond Q5 £(0.019)
Impact on Gatwick’s competitive position
Providing an improved Gatwick Station will increase Gatwick’s competitiveness with other airports who have modern rail facilities.
Basis of decision (options) A formal agreement has been drawn up and executed between Network Rail and Gatwick Airport Limited, it is now a legal requirement to make the contribution provided Network Rail meet their obligations under the Deed of Contribution.
Linked projects / interdependencies
• South Terminal Forecourt• South Terminal Landside
Asset lifecycle Contribution to Network Rail Asset.
Drawing/Image showing location
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
57GAL 171 A380 on StAnd Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:Deliver a single Code F pier-serviced stand to the west end of Pier 6. In line with Gatwick’s growth aspirations and projected passenger and aircraft fleet mix.
Requirements • To accommodate future fleet mix.• It is currently proposed to create a Code F stand and associated
facilities on Pier 6, by converting push and hold stand 125 and stand 110. The node and air-bridge on stand 110 will be demolished and a new node and air-bridge created to service the new stand.
Benefits • Earliest possible provision of A380 capable infrastructure• Delivery of infrastructure to support future passenger and fleet mix
forecasts• Value solution providing good passenger proposition• No loss of code C stands• Provision of products meeting a wider mix of passenger types• Flexible infrastructure accommodates various aircraft types
Project Start Date August 2011
Project End Date February 2013
Total Capital Expenditure£ millions (est.)
Total £5.9m Q5 - £5.6m Q5+1 - £0.4m
As this project has passed through Tollgate 4 this value represents a cost amount attributable to a defined scope and programme that will, or has been delivered.
Likely impact on operating costs
Minimal impact expected on resourcing for A380 operations.
Indicative airline impact £ in 2013 constant prices (assumes unconstrained traffic growth)
Beyond Q5 Over Asset Life (6 yrs)
Reduction in airport charges per passenger
£0.01 £0.01
Tollgate 4 business case submitted to CPB on 23 May, 2012.
This project is currently not supported by the airlines (Joint Steering Group, 11th January , 2012)
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
58
Impact on Gatwick’s competitive position
Gatwick’s growth aspirations, projected passengers and aircraft fleet mix projections together with its ability compete with other airports would be compromised without the delivery of one Code F pier served product facility.
Basis of decision (options) Further investigation into the various options for providing a facility for the A380 is underway to ensure the best value solution is developed.
Linked projects / interdependencies
• North Terminal Additional Pier Service (option dependant)• Runway & Taxiway projects
Asset lifecycle 10 years
Drawing/Image showing location
Current Stage Cost Breakdown
Total £ M % of Total Cost
Base Construction / Direct Costs
4.7 80
Project Design / on-Costs 0.6 10
Risks: Project Risk 0.6 10
overall Total 5.9 100
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
59GAL 172 AIrFIEld PEAk cAPAcIty ExPAnSIon (AcdM55)Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:Aircraft movement processes, turn around (Ramp) processes and upgrade/New NATS, Gatwick, Airline, Ground-handlers systems
Requirements • Adherence to schedule, optimized aircraft movement and increase punctuality
• Stand Designation 2 hours prior to planned departure time• Accurate Estimated In Block Time (EIBT)• Target start up time (TSAT), optimized sequencing to maximize runway
throughput• Stand ready / Safedock on arrival and accurate Target Off Block Time
(TOBT)• Ready to move at TSAT• Reduced variance to enable reducing mean for ADA and ADDA
spacing• Full compliance Eurocontrol CDM requirements and maximize ATM
flow rate +55• Airline and Ground handler cost minimize
Benefits • Increase peak hours throughput runway capacity to 55 on a consistent basis
• Improve on time performance during busy period to maintain greater than 85%
• Maintain delays below average 10 minutes on arrivals and departures• Reduced holding at runway departure queue and more efficient taxiing• Reduce ground handler and service providers’ costs• Reduced Turnaround time variance• Ability to prioritize late inbound or outbound flights to help get back
on schedule• Increase utilization of constrained assets to create incremental capacity• Improved operational efficiency through improved analysis and
reporting tools• Improved analysis to support slot declaration process using more
robust models
Project Start Date February 2012
Project End Date January 2014
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
60
Total Capital Expenditure£ millions (est.)
Total £6.0m Q5 - £2.9m Q5+1 - £3.1m
Likely impact on operating costs
Reduced airline fuel cost and costs associated with delays. Reduce ground handler cost through more predictable planning and minimization of people/asset movement.
Indicative impact on airport charges in Q5 and/or Beyond Q5
Not provided as this is a programme of works with various individual elements that attract different opex, revenue and asset life assumptions.
Impact on Gatwick’s competitive position
Increase in airfield movements at critical peak times, generating further business and improving Gatwick’s capability to cope with projected rises in service levels.
Basis of decision (options) Portfolio of projects at various development stages.
Linked projects / interdependencies
• Alpha Box• Stands Replacement• Taxiway Rehabilitation
Asset lifecycle 10 Years
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
61GAL 173 crEw rEPortIng Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:South Terminal and North Terminal crew reporting solution, as well as a UKBF operations solution for the South Terminal.
Requirements • South Terminal and North Terminal crew report facilities• Relocation of United Kingdom Border Force (UKBF) Custody Suite and
operations functions from Concorde House to Ashdown House• Relocation of ST crew reporting from Concorde House to Atlantic
House• Optimised layout for Jubilee House requirements
Benefits • Enhances crew report processes• Improves on-time departure performance• Enhances security capability and provides compliant and effective
UKBF operational facility• Additional ST landside coach drop lane • Elimination of vehicle / pedestrian conflict at airside coach pick up
Project Start Date August 2011
Project End Date July 2013 (Operational – TG5)
Total Capital Expenditure£ millions (est.)
Total £20.6m Q5 - £10.9m Q5+1 - £9.7m
As this project has passed through Tollgate 4 this value represents a cost amount attributable to a defined scope and programme that will, or has been delivered.
Likely impact on operating costs
Increase in operating costs for airport and airlines due to provision of compliant hold baggage screening for crew baggage and additional security screening facility. The crew reporting business case summary, as submitted to JSG in June 2012, highlighted the impact on operating costs.
Indicative airline impact £ in 2013 constant prices (assumes unconstrained traffic growth)
Beyond Q5 Over Asset Life (25 yrs)
Increases in airport charges per passenger
£0.068 £0.040
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
62
Impact on Gatwick’s competitive position
Efficient and effective crew reporting supports on time performance for airlines and enhances Gatwick’s reputation. Provision of safe and secure detention facilities for UKBF protects Gatwick’s reputation.
Basis of decision (options) Provision of a crew reporting, hold baggage, coach and vehicle solution in an alternative location
Linked projects / interdependencies
South Terminal Baggage and Pier 1, ST Domestic Arrivals, GAL Commercial Portfolio works and plans
Asset lifecycle 25 years
Drawing/Image showing location
Current Stage Cost Breakdown
Total £ M % of Total Cost
Base Construction / Direct Costs
16.2 79
Project Design / on-Costs 3.3 16
Risks: Project Risk 1.0 5
overall Total 20.6 100
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
63GAL 174 South tErMInAl doMEStIc ArrIVAlSCurrent status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:Reconfiguration of the South Terminal Arrivals area to enhance the Arrivals experience, facilitating seamless process whilst maximising commercial
Requirements • Relocate selected retail outlets• Reconfigure onward travel
Benefits • Reconfiguration of the South Terminal Arrivals area to create an enhanced passenger experience.
• Improved ground transportation, hotel, and baggage services.• Reduced coaching costs.• Improved stand operations.• Consolidate arrivals
Project Start Date April 2011
Project End Date March 2015 (Operational – TG5)
Total Capital Expenditure£ millions (est.)
Total £11.2m Q5 - £6.1m Q5+1 - £5.1m
Likely impact on operating costs
Operating costs will increase marginally whilst income will be increased.
Indicative airline impact £ in 2013 constant prices (assumes unconstrained traffic growth)
Beyond Q5 Over Asset Life (25 yrs)
Increase in airport charges per passenger
£0.024 £0.014
Impact on Gatwick’s competitive position
Reconfiguration required to ensure no degradation to passenger service levels, which could mean that passengers would choose to fly from other airports.
Basis of decision (options) • Option evaluation: o Do nothing – implications of the do-nothing scenario include:
n No improvement in passenger experience – remain at status quo. n Limited retail income opportunities n Limited improvement in participation of onward travel
o Reconfigure existing o Reconfigure existing and install new retail units.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
64
Linked projects / Interdependencies
• South Terminal Baggage and Pier 1• South Terminal Landside Arrivals/Onward Travel• Check in hall reconfigurations• PRM & DDA Infrastructure• South Terminal IDL Reconfiguration• Railway • Crew Reporting
Asset lifecycle 25 years
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
65GAL 175A north tErMInAl Idl rEconFIgurAtIon Current status within Gatwick project process
DFSS
Stage1DFSS
Stage2DFSS
Stage3DFSS
Stage4DFSS
Stage5DFSS
Stage6DFSS
Stage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:To reconfigure the North Terminal departures lounge in order to enhance the passenger experience and support commercial returns.
Requirements • The enhancement of the passenger experience through the reconfiguration of the existing lounge.
• Provision of additional Food and Beverage• Provision of additional department store by re-use of underutilised
space.• This project will provide resilience to GAL’s Business As Usual.• To remedy the impact of prioritisation of security development on NT
retail income.
Benefits • Improved passenger experience• Retention of existing retail revenue, and expansion through new
brands.• Smoking area.• Increased catering on offer (4,000 square feet).
Project Start Date October 2011
Project End Date November 2012
Total Capital Expenditure£ millions (est.)
Total £6.5m Q5: £5.6m Q5+1 : £0.9m
As Project 1 of the NT has passed through Tollgate 4 this value represents a cost amount attributable to a defined scope and programme that will, or has been delivered.
Likely impact on operating costs
It is anticipated that there will be a small increase in operating costs associated with this reconfiguration due to additional terminal gross floor area being created. It is anticipated that there will be an uplift in retail income.
Indicative airline impact £ in 2013 constant prices (assumes unconstrained traffic growth)
Beyond Q5 Over Asset Life (15 yrs)
Reduction in airport chargesper passenger – Project 1
£0.010 £0.010
Reduction in airport chargesper passenger – Project 2
£0.019 £0.020
Project 2 Project 1
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
66
Impact on Gatwick’s competitive position
Enhances Gatwick’s reputation for Departures Lounge product.
Basis of decision (options) Options: 1) Do all ; 2) Partial / Phased implementation; 3) Do nothing.
Linked projects / interdependencies
North Terminal Security
Asset lifecycle 20 years
Current Stage Cost Breakdown
Total £ M % of Total Cost
Base Construction / Direct Costs
5.2 80
Project Design / on-Costs 0.8 12
Risks: Project Risk 0.5 8
overall Total 6.5 100
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
67GAL 175B South tErMInAl Idl rEconFIgurAtIon Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:To maximise the retail space available and to provide appropriate facilities to improve passenger experience and maximise revenue. New retail space in previous World Duty Free (WDF) space.
Requirements • Current retail space in South is 1/3 less per passenger than North.• Prioritisation of security development impacts South Terminal IDL retail
income.• Offers and adjacencies in South inconsistent with segmentation.• Re-configuration of lower level WDF to accommodate additional retail
facilities.• Remedy ‘dated’ look and feel of IDL..
Benefits • Improved passenger experience• Increased income driven by a reconfigured layout.• Maximises passenger exposure to offers that are designed with
Gatwick passengers in mind.• Increased Retail footprint without compromise to passenger service
(i.e. seating)• Improve circulation space
Project Start Date March 2012
Project End Date December 2013
Total Capital Expenditure£ millions (est.)
Total £21.7m Q5 - £5.9m Q5+1 - £15.8m
As this project has passed through Tollgate 4 this value represents a cost amount attributable to a defined scope and programme that will, or has been delivered.
Likely impact on operating costs
No on-going change to operating costs: no change anticipated to existing operations, including PRM. One-off costs: Amortisation.
Indicative impact on airport charges in Q5 and/or Beyond Q5
BQ5 Over Asset Life
Reduction in airport charges per passenger:
-£0.07 -£0.07
Impact on Gatwick’s competitive position
Enhances Gatwick’s reputation for Departures Lounge product and thus enables the differentiation with other South East and other European airports.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
68
Basis of decision (options) Option evaluation will focus on the location and size of the development as part of the master plan and Constructive Engagement work and the delivery of associated benefits to all airport users. Option evaluation will review all potential build and non-build options.
Linked projects / interdependencies
• South Terminal Security• South Terminal Baggage & Pier 1
Asset lifecycle 15 years
Drawing/Image showing location
Current Stage Cost Breakdown
Total £ M % of Total Cost
Base Construction / Direct Costs
16.1 74
Project Design / on-Costs 2.8 13
Risks: Project Risk 2.8 13
overall Total 21.7 100
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
69GAL 176 FAcIlItIES ASSEt StEwArdShIP ProgrAMMECurrent status within Gatwick project process
Various projects at various stages
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:A continuing programme of asset replacements / refurbishments across the whole asset base to support Gatwick’s service levels.
Requirements • A range of investment in passenger facing and core operational infrastructure undertaken in priority order and in conjunction with other developments at Gatwick to ensure that maximum benefit is gained without duplication of efforts.
• Passenger service assets must be maintained to meet regulatory and service standards.
• Identified safety and environment risks must be mitigated.
Benefits • Provide fit for purpose facilities which enable consistent delivery of core services, such as the functionality of passenger facing equipment and infrastructure. This will enable Gatwick to meet service expectations, maintain a safe and reliable operation while improving business resilience.
• Less frequent disruptions• Maintain ability of equipment performance• Compliance with Publicly Available Specification (PAS) 55.• Protect & maintain Service Quality Rebate measures across the airport
estate.
Project Start Date April 2013
Project End Date March 2014
Total Capital Expenditure£ millions (est.)
Total £21.8m Q5 - £8.0m Q5+ 1 - £13.8m
Likely impact on operating costs
It is unlikely that there will be a significant impact on handling agent and airline costs. Airport impacts are expected to be minimal. Where CAPEX is spent in upgrading, improving or replacing existing infrastructure Gatwick may realise OPEX savings.
Indicative impact on airport charges in Q5 and/or Beyond Q5
Not provided as this is a programme of works with various individual elements that attract different opex, revenue and asset life assumptions.
Impact on Gatwick’s competitive position
Gatwick’s ability to compete would be compromised without the delivery of a comprehensive Facility Asset Stewardship Programme. The Facility Asset Stewardship Programme will ensure that Gatwick can ‘Protect and enhance our reputation’ through ensuring availability of critical assets.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
70
Basis of decision (options) Portfolio of projects at various development stages. Option evaluation has thus far focused on the location and size of the future developments as part of the master plan and Constructive Engagement work.
Linked projects / interdependencies
Various
Asset lifecycle Various
Drawing/Image showing location
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
71GAL 177 coMMErcIAl ASSEt StEwArdShIP ProgrAMMECurrent status within Gatwick project process
Various projects at various stages
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:A continuing programme to sustain airport facilities core to Gatwick’s commercial operation.
Requirements • A range of investments to enable the continuing provision of commercial space within the airport campus.
• The product areas that benefit from the Commercial Asset Stewardship Programme are retail space, CIP space, office space and industrial space.
• Replacement of Commercial, Property, and Staff Assets as prioritised by condition surveys and compliance requirements.
Benefits • Protect the current and future commercial income from revenue generating assets across the estate.
• Maintain commercially acceptable building standards across GAL’s portfolio, thus protecting commercial propositions to the airlines, passengers and GAL customers including staff and statutory bodies.
• Environment, Health and Safety compliance.• Operational reliability.• Avoidance of excessive maintenance costs.• Provide fit for purpose facilities that provide high quality commercial
and property products in order to attract future Airline growth at Gatwick.
Project Start Date April 2013
Project End Date March 2014
Total Capital Expenditure£ millions (est.)
Total £4.5m Q5 - £0.1m Q5+1 - £4.4m
Likely impact on operating costs
Indicative reduced OPEX costs of £0.2m per annum (indicative).
Indicative impact on airport charges in Q5 and/or Beyond Q5
Not provided as this is a programme of works with various individual elements that attract different opex, revenue and asset life assumptions.
Impact on Gatwick’s competitive position
Gatwick needs to be able to compete with other airports and local market offers, by ensuring the provision of high quality commercial and property products in order to maintain airline operations, and to give passengers more choice.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
72
Basis of decision (options) Portfolio of projects at pre-tollgate zero stage. Option evaluation has thus far focused on the location and size of the future developments as part of the master plan and Constructive Engagement work.
Linked projects / interdependencies
Various
Asset lifecycle Various
Drawing/Image showing location
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
73GAL 178 AIrFIEld ASSEt StEwArdShIP ProgrAMMECurrent status within Gatwick project process
Various projects at various stages
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:A continuing programme of asset replacement / refurbishment across the airfield.
Requirements • A range of investments in the airfield infrastructure, undertaken in priority order and in conjunction with other developments at Gatwick.
• The airfield emergency vehicle fleet must meet compliance and response requirements.
• Electrical systems must be maintained to ensure compliance, and to meet requirements of a high utilization runway.
Benefits • The primary strategic drivers of the Airfield Asset Stewardship Programme are to “Deliver the best passenger experience” and “Maintain a strong Environment, Health and Safety culture”.
• The Airfield Asset Stewardship Programme is to enable delivery of a reliable service from Gatwick’s airfield.
• Provide a fit for purpose facility that enables consistent airport operations.
• Aerodrome and Environment, Health and Safety Compliance.• Avoidance of increased basic maintenance costs.
Project Start Date April 2013
Project End Date March 2014
Total Capital Expenditure£ millions (est.)
Total £11.8m Q5 - £5.3m Q5+1 - £6.4m
Likely impact on operating costs
It is unlikely that there will be a significant impact on handling agent and airline costs.
Where CAPEX is upgrading, improving or replacing existing infrastructure Gatwick may realise OPEX savings.
Indicative impact on airport charges in Q5 and/or Beyond Q5
Not provided as this is a programme of works with various individual elements that attract different opex, revenue and asset life assumptions.
Impact on Gatwick’s competitive position
The Airfield Programme will ensure that Gatwick can ‘Protect and enhance our reputation’ through ensuring availability of the airfield.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
74
Basis of decision (options) Portfolio of projects at various development stages. Option evaluation has thus far focused on the location and size of the future developments as part of the master plan and Constructive Engagement work. Numerous projects and initiatives, therefore no early stage cost breakdown included.
Linked projects / interdependencies
All other Airfield projects including: Pier 5, North Terminal Additional Pier Service, Papa November, Snow Vehicles, ST Baggage & Pier 1, Main Runway Rehabilitation, A380 on Pier and Airfield Peak Capacity Expansion
Asset lifecycle Various
Drawing/Image showing location
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
75GAL 179 AIrFIEld oPErAtIonS buIldIng Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:Create a new Airfield Operations building for Gatwick to facilitate any future development of the area south of Pier 6.
Requirements The current ‘base’ facility housing the Airfield Operations team (located between the 130s and 140s stands) has been identified as the location for the provision of future pier served stands. The project presents the opportunity to improve the airfield operations facilities and resolve the issues which exist with the current building which is now 25 years old and no longer fit for purpose.
Benefits • Help our airlines grow by providing the flexibility required to change key stands to meet future needs in terms of fleet mix and aircraft type. Vacates the only feasible area left to grow pier served stand capability
• Upgrades all critical operational facilities (built in the 1980s) including telecoms and welfare.
• Increase value and efficiency by improving the efficiency of the airside operations team
• Provides a new modern, energy efficient facility which will reduce operational costs and creates a facility in a central location with better airfield sightlines.
• Protect and enhance our reputation by removing the single point of failure which currently exists for Idaho on airport
• Improves coordination between Airfield Operations, AGL and AFS teams and allowing more efficient processes. Improves response times to critical areas of the runway.
Project Start Date June 2012
Project End Date November 2013
Total Capital Expenditure£ millions (est.)
Total £7.5m Q5 - £2.1 m Q5+1 - £5.3m
Likely impact on operating costs
Operating costs are assumed to be neutral: any expected increase in rates to be offset by increased energy efficiencies
Indicative impact on airport charges in Q5 and/or Beyond Q5
BQ5 Over Asset Life (40 yrs)
Increase in airport charges per passenger:
£0.018 £0.010
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
76
Impact on Gatwick’s competitive position
The project will give Gatwick a fit for purpose facility positioned in a prime airfield position adjacent to the runway. Gatwick will be investing in one of its key operational facilities.
Basis of decision (options) 1. Do nothing – implications of the do-nothing scenario include: n Increased pressure on existing facility and inadequate working
conditions for key operational staff n Impact on programme of future pier works n Requirement to spend circa £4m to refurbish the existing facility
2. The minimal scope is assumed to be the refurbishment of the existing facility which is 25 yrs old
Linked projects / interdependencies
This project is part of the overall programme to increase capacity and flexibility of the airfield and has links to the following projects :• Pier 6 southern extension• Foul main• Snow base
Asset lifecycle 40 years
Drawing/Image showing location
Location of the Airfield Operations Building on Stand 169:
Current Stage Cost Breakdown
Total £ M % of Total Cost
Base Construction / Direct Costs
4.6 62
Project Design / on-Costs 2.0 26
Risks: Project Risk 0.9 12
overall Total 7.5 100
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
77GAL 180 Q5 MInor ProjEctS ProgrAMMECurrent status within Gatwick project process
Various projects at various stages
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:The Minor Projects programme is a range of investment, typically projects of a value less than £250k and of a tactical nature, undertaken in priority.
Requirements The Minor Projects programme is a range of investments which supplements the asset replacement programme, typically projects of a value less than £250k and of a tactical nature, undertaken in priority order. The typical make-up of project is:• 35-40% each year have Environmental Health and Safety, issues as the
main driver with around 10-15% of these are unplanned, arising from recommendations following incidents, risk assessments & audits.
• 35-40% of projects each year have ‘Deliver the best passenger experience’ Infrastructure as main driver.
• 15-20% of projects each year are related to investment in tenanted accommodation to protect existing income
• 5-10% of projects each year are related to investment in retail accommodation to protect existing income.
Benefits The primary strategic drivers of the Minor Projects programme are to ‘Deliver the best passenger experience’ and “ Maintain a strong EH&S culture”.
Project Start Date April 2008
Project End Date March 2013
Total Capital Expenditure£ millions (est.)
Total £9.3m Q5 - £8.8m Q5+1 - £0.5m
Likely impact on operating costs
Airport impacts are expected to be minimal.
Indicative impact on airport charges in Q5 and/or Beyond Q5
Not provided as this is a programme of works with various individual elements that attract different opex, revenue and asset life assumptions.
Impact on Gatwick’s competitive position
The Minor Projects programme will ensure that Gatwick can ‘Protect and enhance our reputation’ through ensuring operational availability of its assets, and no H&S risk to our passengers.
Basis of decision (options) Portfolio of projects at various development stages.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
78
Linked projects / interdependencies
Portfolio of minor projects that are linked with many other projects in the CIP by the location within which they are executed.
Asset lifecycle Various minor projects with varying asset lifecycles
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
79GAL 181 bEyond Q5 dEVEloPMEnt ProgrAMMECurrent status within Gatwick project process
Various projects at various stages
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:It is a regulatory requirement that GAL submits a Business Plan by 1st April 2012, necessitating the submission of a set of capital plans with sufficient detail (scope, cost and programme) to facilitate the airline consultation process for the post Q5 period.
Requirements Detail scope and costing on major projects as per the following phases:• Phase 1 up to 01/04/2012 : commence detail scope & costing on major
projects prior to Beyond Q5• Phase 2 up to 01/01/2013: Business Cases submitted as part of the
Business Plan to be further developed with airlines.• Phase 3 up to 31/03/2014: Post Consultation: agree on outcomes.
Progress projects up to Tollgate 4
Benefits • To develop a Beyond Q5 CIP submission in the most efficient manner that achieves the maximum benefit for all parties for the Beyond Q5 settlement.
• The development of a robust Beyond Q5 CIP will enable the implementation to be planned and executed in the most efficient manner and will provide maximum benefit for all parties from the Beyond Q5 regulatory settlement
• Learning from the Q5 Constructive Engagement process would support the value of early investment of time and resources to develop a robust plan.
• Identify assets which will be life expired and need replacing or will require capital investment to extend asset life during Beyond Q5.
Project Start Date September 2011
Project End Date March 2014
Total Capital Expenditure£ millions (est.)
Total - £10m Q5 - £4.6m Q5+1 - £5.4m
Likely impact on operating costs
On-going operating costs : None assumed One-off costs: None assumed
Indicative impact on airport charges in Q5 and/or Beyond Q5
Beyond Q5 Over Asset Life (7 yrs)
Increase in airport charges per passenger:
£0.050 £0.046
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
80
Impact on Gatwick’s competitive position
To continue to deliver passenger improvements in line with our aim of being London’s airport of choice. Whilst Safeguarding and maintaining existing facilities in a timely and efficient fashion is important to maintain Gatwick’s competitive position.
Basis of decision (options) Option 1 – Do nothing and we start Airline consultation without a business plan or capital plan.
Option 2 – Produce a business plan and a capital plan without any scope, costs, programme or suggested options for consultation process.
Option 3 – Progress development of capital plan for the business plan with an understanding what our customers are looking for from airports. Developing our master plan, development strategy leading into our traffic analysis, market research and understanding our gaps. To formulate an emerging capital programme which is focused on delivery of a service proposition, whilst maintaining our current assets in an efficient way.
Linked projects / interdependencies
Linked to the Q5 + Q5+1 programme
Asset lifecycle 7 years
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
81GAL 182 Q5+1 MInor ProjEctS ProgrAMME < £5MCurrent status within Gatwick project process
Various projects at various stages
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:The Q5 + 1 Minor Projects programme is a range of investment, typically projects of a value less than £5m and of a tactical nature, that will be undertaken in priority in the extension year, 2013/2014.
Requirements The Q5 + 1 Minor Projects programme is a range of investments which supplements the asset replacement programme, typically projects of a value less than £5m and of a tactical nature, undertaken in priority order.
Whilst some of the projects have Environmental Health and Safety issues as the main driver with around 10-15% of these being urgent unplanned, arising from recommendations following incidents, risk assessments & audits, other projects have ‘Deliver the best passenger experience’ Infrastructure as main driver. The remaining projects each year are related to investment in tenanted accommodation to protect existing income.
Benefits The primary strategic drivers of the Q5 + 1 Minor Projects programme are to ‘Deliver the best passenger experience’ and “Maintain a strong EH&S culture”.
Project Start Date April 2013
Project End Date March 2014
Total Capital Expenditure£ millions (est.)
Total £49.5m Q5 - £20.6m Q5+1 - £28.9m
Likely impact on operating costs
Airport impacts are expected to be minimal
Indicative impact on airport charges in Q5 and/or Beyond Q5
Not provided as this is a programme of works with various individual elements that attract different opex, revenue and asset life assumptions
Impact on Gatwick’s competitive position
The Minor Projects programme will ensure that Gatwick can ‘Protect and enhance our reputation’ through ensuring operational availability of its assets, and no H&S risk to our passengers.
Basis of decision (options) Portfolio of projects at various development stages.
Linked projects / interdependencies
Portfolio of minor projects that are linked with many other projects in the CIP by the location within which they are executed.
Asset lifecycle Various minor projects with varying asset lifecycles.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
82GAL 183 gAtwIck StrEAM Flood AttEnuAtIon ProgrAMMECurrent status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:Reduction and management of flood risks at Gatwick by the construction of an inline flood storage and flow attenuation reservoir.
Requirements • To minimise as far as reasonably practicable the risk of pollution to adjoining water courses.
• Minimise the risk to personal safety and asset damage as a result of flooding.
• Project must demonstrate to Network Rail (NR) that the scheme will protect the integrity of the adjoining London to Brighton line
• Scheme is subject to local authority planning approval and through the consultation process must address the concerns of all local stakeholders as far as reasonably practicable.
Benefits • To develop a Beyond Q5 CIP submission in the most efficient manner that achieves the maximum benefit for all parties for the Beyond Q5 settlement.
• The development of a robust Beyond Q5 CIP will enable the implementation to be planned and executed in the most efficient manner and will provide maximum benefit for all parties from the Beyond Q5 regulatory settlement
• Learning from the Q5 Constructive Engagement process would support the value of early investment of time and resources to develop a robust plan.
• Identify assets which will be life expired and need replacing or will require capital investment to extend asset life during Beyond Q5.
Project Start Date February 2012
Project End Date January 2014
Total Capital Expenditure£ millions (est.)
Total £8.2m Q5 - £0.8m Q5+1 - £7.4m
Likely impact on operating costs
On-going Operating costs:• Annual structural inspection £3k/annum - Current preferred option
is the construction of an inline flood storage and flow attenuation reservoir south of the airport on airport land, as outlined in the business case submitted to JSG.
• The impact of a 1 in 100 year event would be likely to cause a full closure of Gatwick Airport. This would result in lost income for GAL of circa £1m per day. The impact to our airlines has not been quantified at this stage.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
83
Indicative impact on airport charges in Q5 and/or Beyond Q5
Beyond Q5 Over Asset Life (35 yrs)
Additional airport charges per passenger:
£0.018 £0.012
Impact on Gatwick’s competitive position
Gatwick’s reputation is safeguarded through management of flood risks and prevention of sewage leaks and environmental incidents.
Basis of decision (options) Currently proposed that a build solution is the only viable option and any future optioneering will focus on the nature of this solution.
Linked projects / interdependencies
All projects currently constructed within the designated flood area (Q5/Q5+1) have had a requirement to compensate for any flood impacts through local storage. Any future post Q5 projects constructed within the flood zone in particular the proposed Pier 6 Southern Extension are currently being planned without the need for this provision.
Asset lifecycle 35 Yrs
Drawing/Image showing location
Site of proposed flood storage reservoir
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
84GAL 160 SurFAcE wAtEr IncludIng Pond d Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:The key objective of the surface water project is to manage and minimise as far as reasonable practicable the risk of pollution to adjoining water courses.
Requirements • To provide a new very dirty water lagoon of approximately 100,000m2 to receive, attenuate and transfer surface water to the existing dirty water lagoon.
• To extend the operational lift of the Pond D fire main pumping station, pollution control system and flood alleviation infrastructure by a minimum of 25 years.
Benefits • Help our airlines grow by ensuring GAL has the ability to continue de-icing the airfield operational area.
• Build a strong EH&S culture by reducing the risk of Gatwick breaching the current discharge consent to the river mole.
Project Start Date November 2011
Project End Date October 2013
Total Capital Expenditure£ millions (est.)
Total £12.2m Q5 - £8.4m Q5+1 - £3.8m
Likely impact on operating costs
On-going Operating costs:• Net effect to operating costs will be negligible One-off costs:• Net effect to operating costs will be negligible
Indicative airline impact £ in 2013 constant pricesunconstrained traffic (assumes unconstrained traffic growth)
Beyond Q5 Over Asset Life (25 yrs)
Additional airport charges per passenger:
£(0.03) £(0.57)
Impact on Gatwick’s competitive position
Gatwick’s reputation is safeguarded through management of flood risks and prevention of sewage leaks and environmental incidents.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
85
Basis of decision (options) • As part of the agreed procurement strategy and during this phase of the project, Gatwick approached the market looking for options which would completely eliminate the potential to breach the current discharge consent except during exceptional weather events. This option has been discounted due to a lack of budget, high operational costs, and a lack of maturity and detail on the technology proposed by bidders.
• Between tollgate 1 and 2, workshops were held to consider alternative means of de-icing and methods by which the use of de-icent could be optimise. This resulted in new vehicles being procured which attempt to optimise the use of current de-icent.
• Finally, discussions with both Thames water and the EA to maximize our discharge consents have been progressed and while these are on-going they continue not to yield any contribution to the current challenge.
Linked projects / interdependencies
This project is part of the overall surface water infrastructure programme to:• Eliminate the risk of prosecution from surface water discharges in to
adjoining water courses• Protect Gatwick in the event of a 1:100 year stormProject InterdependenciesThis project is required to be delivered before any long term options can be considered
Asset lifecycle 25 Yrs
Drawing/Image showing location
Notes:
1. New Lagoon shown in red adjacent to existing lagoon
2. Pond shown in white
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
86GAL 184 St & nt uk bordEr ForcE (ukbF) ArrIVAl ZonES Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:To support the delivery of a consistent and reliable service for EU passengers at UK Borders.
Requirements Phase 2 (Part 1 & 2) – by July 2013• Reduction of queues for EEA passengers to a Gatwick aspirational
average of 10mins during peak hours (Border Force national target: maximum queue of 25mins for EEA passengers).
• Reduction in transaction times for EEA e-pass gates from current 38 secs per passenger (existing e-pass gates) to 15 secs per passenger (validated by operational trials carried out in Apr/May 2012), equivalent to a flow rate of 20 secs per passenger.
• Efficient and intuitive passenger flow to and from e-pass gates.• Reduction of user errors (currently up to 60%) to estimated 5% (excl.
deliberate ‘test rejections’ required by UKBA as part of their process).• Safeguarding of layouts for further increases in capacity for E-pass
gates and desks and potential differentiation of products.• 48% utilisation of e-gates by EEA passengers by 2013 to a maximum of
65% by 2018.• Service level for response to failures of E-pass gates: within 1 hour.• Optimisation of space in Immigration Halls to deliver service levels
within the existing building envelope for as long as possible without extending the building envelope.
Phase 1 – utilised successfully during summer 2012 • Additional processing capability through installation of 8 temporary
manual desks in each terminal to manage the 2012 summer season in conjunction with the Border Force who have undertaken to supply additional staff during this period.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
87
Benefits • Phase 1 of this project along with the provision of additional Border Force volunteers during the summer of 2012 are to reduce queue times for EEA (European Economic Area) passengers to aspire to average queue times of 10mins during daily peak hours (Border Force national target: 25mins).
• Phase 2 aims to consolidate achievements beyond 2012 after Border Force summer volunteers are withdrawn.
• Without intervention beyond summer 2012, maximum and average queue times are predicted to increase again since Border Force staffing levels are predicted to remain below 2011 staffing levels.
• Phase 2 of this project is part of a longer term plan to deliver a step change in passengers’ experience of the Arrivals process through targeting installation of more and faster e-gates for use by EEA passengers.
• Approx. 80% of all South Terminal passengers will benefit from phase 2 this project. A planned investment in the North Terminal beyond Q5 is to include delivery of e-gates to benefit passengers in that terminal following the initial pilot in the South Terminal.
• Indirect benefits are expected for non-EEA passengers as an increase in automation of the EEA process will release resources to process non-EU passengers.
• The proposed automated gate solution is safeguarded to be developed for future use by non-EEA passengers.
Project Start Date Phase 1: April 2012 ; Phase 2: October 2012
Project End Date Phase 1: July 2012 ; Phase 2: June 2013
Total Capital Expenditure£ millions (est.)
Total £6.6m Q5 - £2.8m Q5+1 - £3.8m
Likely impact on operating costs
On-going Operating costs:• The business case assumes no significant impacts on operating costs.
Opportunities to reduce reliance on operational support staff during peak seasons to be validated and confirmed during the next project stage prior to TG4. Potential opportunity for cost reduction: £16k per month for 4 months each year in the South Terminal = £64k p.a. (NB: deployment of operational resource remains subject to ongoing review).
• Potential cost reductions may be possible through removal of the need for manual queue measurement through introduction of an automated system, however, currently this task is to be performed by resources who also deliver customer service in the Immigration Hall.
• The business case assumes zero incremental cost of maintenance for e-gates, subject to delivery of acceptable service levels for maintenance response (required: within one hour). This is to be validated as part of the procurement process for e-gates led by the Border Force.
• Incremental cost of additional dynamic wayfinding and queue measurement technology: £25k p.a.
One-off costs:• None anticipated
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
88
Indicative airline impact £ in 2013 constant pricesconstant prices (assumes unconstrained traffic growth)
Beyond Q5 Over Asset Life (10 yrs)
Additional airport charges per passenger:
£0.027 £0. 022
Impact on Gatwick’s competitive position
The creation of additional space for and installation of desks and e-gates will require areas to be hoarded off temporarily and will therefore have an impact on passenger flows to and in Immigration Halls.
Basis of decision (options) NB: Areas shaded grey relate to North Terminal scope to be delivered as part of proposed future investments beyond Q5.
Option 1 – low impact
13 E-Pass gates/ST
14 E-Pass gates/NT –removed from scope
Option 2 – medium impact
13 E-Pass gates/ST
14 E-Pass gates/NT –removed from scope
Option 3 – highimpact: removed from
scope
13 E-Pass gates/ST
18 E-pass gates/NT
Reconfiguration ofImmigration Desks
Meets queue target of avg 10mins at peak for EU pax
Yes Yes yes
Pax flow from piers Good Good Excellent
Meets Border Force layout requirements
Yes Yes Yes
Impact on tenants Low Medium High
Integrates with future investment plans
Yes Yes No
Capital cost £9.45m £10.65m £11.45m
Cost per pax £0.029 (over asset life) Est. £0.031 (over asset life)
Est. £0.032 (over assetlife)
Programme By July 2013 By Autumn 2013 By Autumn 2013
Linked projects / interde-pendencies
This project is part of the overall programme to reduce queues in all parts of the process in both terminals• Potential investment in Arrivals Halls to meet service and capacity
requirements beyond 2014• On-going minor works to refurbish Immigration offices and relocate
Special Branch in the ST Immigration Hall• Proposed investments in Arrivals Halls beyond Q5 include full
refurbishment, reconfiguration and increase in capacity with service enhancements for the NT Immigration Hall.
• A minor works project to refurbish Immigration offices and relocate the Special Branch will release space to support the delivery of this project phase.
Asset lifecycle 10 years
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
89GAL 185 conSolIdAtEd SEcurIty gAtE Current status within Gatwick project process
DFSSStage1
DFSSStage2
DFSSStage3
DFSSStage4
DFSSStage5
DFSSStage6
DFSSStage7
TG0TG0 TG1 TG2 TG3 TG4 TG5 TG6 TG7
Initiate Scope Options Build OperateHand-over
Close-out
Require-ments
SCoPE:The key objective of the Consolidated Security Gate project is to provide a fit for purpose facility to allow secure and efficient access flows to and from the airfield. By optimising the efficiency of the external airfield access points, the project aims to reduce operational costs through consolidation of external security posts.
Requirements • Provision of optimum infrastructure and technology to support processes and operating procedures to ensure efficient people and vehicle movements through external security posts.
• Reduce operating costs through efficiencies and consolidation of security posts.
• Improve staff satisfaction levels with working environment• Achieve SQR targets for waiting times and Airside access• Facilitate improved detection levels• Future proof the facility by safeguarding for medium capacity building• Queuing space available for up to 10 trucks• Solution should provide resilience
Benefits • Assist our airlines in continual achievement of their On Time Performance targets, by providing a less constrained access to the airfield with improved resilience and throughput.
• Identify savings through consolidated facilities and reduced manning levels.
• Allow Gatwick to compete to grow and become London’s airport of choice by providing an efficient external security post product, with minimal delays and resilience in case of faliure.
• Provide improved facilities for security staff and a better working environment.
Project Start Date September 2011
Project End Date August 2013
Total Capital Expenditure£ millions (est.)
Q5+1 - £5.5m
Likely impact on operating costs
On-going Operating costs:• Savings of circa £1.3m p.a. based on saving 26 FTEs
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
90
Indicative airline impact £ in 2013 constant pricesconstant prices (assumes unconstrained traffic growth)
BQ5 Over Asset Life (15 yrs)
Decrease in airport charges per passenger:
£0.018 £0.017
Impact on Gatwick’s competitive position
The project will deliver a more efficient transition process from Landside to Airside, ensuring benefits for Gatwick and business partner staff.
Basis of decision (options) Level 1 and 2 QFD exercises completed to determine the location and options within the site.
Level 1 QFD agreed by stakeholders showed that preferred site is Timberham House
Level 2 QFD agreed by stakeholders showed that preferred option is for 250m2 building in 4 lane, double configuration, with ATIX machines and conventional roller beds, using an automated queue measurement system.
Options investigated with cost/savings and approximate payback period:
Linked projects / interdependencies
The scope of this project has interdependencies with the following:1. Construction Gate – future construction traffic flows2. Atlantic House and Crew reporting – Queensgate3. Property moves – Hangar lane (BA/Servisair ramp accommodation4. Airport Logistics Project
Asset lifecycle 15 Yrs
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
91
Drawing/Image showing location
92APPENDICES
APPENDIX A - 2013 Phased Capital Investment Programme
APPENDIX B - 2012 Phased Capital Investment Programme (as published in 2012CIP)
APPENDIX C - Changes to Investment Programme - Tracker (April 2012- March 2013)
APPENDIX D - Previous Traffic Forecasts (as published in 2012CIP)
APPENDIX E - Meetings, Working Groups and Governance Boards (April 2012 – March 2013)
APPENDIX F - Decision Log (April 2012 – March 2013)
APPENDIX G - Annex G
APPENDIX H - Gatwick‘s updated Product Matrix
APPENDIX A - Gatwick airport phased capital investment proGramme 2013 (in out-turn prices)
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A C D G HAppendix
E
Lond
on G
atw
ick
Airp
ort
Proj
ecte
d Sp
end
(Out
-turn
Pric
es)
Q5
Tota
lQ
5Q
5Q
5Q
5Q
5Q
5
£ m
illio
nsPr
ojec
ted
as a
t 31s
t Mar
ch 2
013
(Fut
ure
Spen
d in
cl 2
008/
09, 2
009/
10,
2010
/11,
201
1/12
and
201
2/13
)20
08/0
9 (A
ctua
l)20
09/1
0 (A
ctua
l)20
10/1
1 (A
ctua
l)20
11/1
2 (A
ctua
l)20
12/1
3 (A
ctua
l)20
13/1
4
Proj
ects
in D
evel
opm
ent o
r Des
ign
Stag
e
GA
L170
Bag
gage
Voi
ds (
incl
udin
g ST
& N
T)7.
40.
30.
56.
6
GA
L 18
5C
onso
lidat
ed S
ecur
ity G
ate
5.5
5.5
Tota
l for
Pro
ject
s in
Dev
elop
men
t or D
esig
n St
age
12.9
0.3
0.5
12.1
Proj
ects
in Im
plem
enta
tion
Stag
e
GA
L125
& G
AL0
05So
uth
Term
inal
Bag
gage
& P
ier 1
90.3
4.3
12.7
t9.
819
.217
.227
.0
GA
L111
Nor
th T
erm
inal
Add
ition
al P
ier S
ervi
ce (P
ier 5
)74
.30.
44.
930
.038
.7
GA
L096
Airfi
eld
Prog
ram
me
incl
udin
g Ru
nway
Res
urfa
cing
66.3
1.4
10.9
0.8
9.1
43.9
0.3
GA
L155
Sout
h Te
rmin
al S
ecur
ity47
.60.
214
.430
.02.
90.
2
GA
L137
Nor
th T
erm
inal
Bag
gage
(NTB
) Upg
rade
46.4
0.5
1.9
11.8
19.1
12.0
1.2
GA
L175
aN
orth
Ter
min
al ID
L Re
confi
gura
tion
6.5
1.5
4.1
0.9
GA
L157
Nor
th T
erm
inal
Sec
urity
10.6
1.5
5.7
3.3
0.2
GA
L122
Sout
h Te
rmin
al L
ands
ide
22.7
1.9
4.6
2.6
4.3
8.8
0.4
GA
L160
Surf
ace
Wat
er in
clud
ing
Pond
D R
ehab
ilita
tion
12.2
0.1
0.5
1.8
5.9
3.8
GA
L167
Railw
ay C
ontr
ibut
ion
7.
71.
10.
75.
9
GA
L171
A38
0 on
Sta
nd5.
90.
65.
00.
4
GA
L165
& G
AL1
66Ta
xiw
ay P
apa
& N
ovem
ber
5.4
2.7
2.4
0.3
Exte
rnal
Cla
ddin
g to
Ent
ranc
e br
idge
6.2
1.0
4.6
0.6
GA
L134
Nor
th T
erm
inal
Add
ition
al P
ier S
ervi
ce (
Pier
6)
8.7
1.4
0.6
0.2
1.4
2.2
2.9
GA
L183
Gat
wic
k St
ream
Flo
od A
tten
uatio
n8.
20.
87.
4
GA
L161
Rive
r Mol
e Fl
ood
Alle
viat
ion
4.1
2.7
0.5
0.9
GA
L172
Airfi
eld
Peak
Cap
acity
Exp
ansi
on (A
CD
M)
6.0
0.2
2.7
3.1
GA
L173
Cre
w R
epor
ting
20
.60.
810
.19.
7
GA
L174
Sout
h Te
rmin
al D
omes
tic A
rriv
als
11.2
0.9
5.2
5.1
GA
L175
bSo
uth
Term
inal
IDL
Reco
nfigu
ratio
n21
.75.
915
.8
GA
L179
Airfi
eld
Ope
ratio
ns B
uild
ing
7.5
1.0
1.1
5.3
GA
L184
ST &
NT
UK
Bor
der F
orce
(UK
BF)
Arr
ival
Zon
es
6.6
2.8
3.8
Tota
l for
Pro
ject
s in
Impl
emen
tatio
n St
age
496.
69.
831
.042
.010
8.0
172.
013
3.8
Com
plet
ed P
roje
cts
GA
L027
Inte
r Ter
min
al S
hutt
le36
.69.
017
.210
.30.
2
GA
L031
bSo
uth
Term
inal
Fire
Pro
tect
ion
Syst
em14
.43.
45.
94.
90.
2
GA
L058
Tele
com
ms
Prog
ram
me
(Dat
a &
Voi
ce)
1.0
0.9
0.1
GA
L069
Sout
h Te
rmin
al D
epar
ture
Lou
nge
Cap
acity
19.8
13.9
5.6
0.3
GA
L109
Nor
th W
est Z
one
39.1
2.4
23.8
12.8
0.2
GA
L115
Nor
th T
erm
inal
Sho
rt T
erm
Car
Par
king
(MSC
P6)
16.9
1.0
0.7
14.3
1.0
GA
L116
& G
AL1
17N
orth
Ter
min
al E
xten
sion
(NTX
)84
.74.
611
.628
.639
.80.
2
GA
L120
Sout
h Te
rmin
al F
orec
ourt
30.2
1.2
2.1
7.1
19.0
0.9
GA
L140
Pier
2 m
odifi
catio
ns38
.30.
110
.020
.87.
10.
2
GA
L144
Sout
h Te
rmin
al T
unne
l Sec
urity
& R
oad
Cap
acity
2.2
0.5
1.2
0.5
GA
L145
Sout
h Te
rmin
al T
unne
l Ref
urbi
shm
ent
1.2
0.2
0.5
0.4
0.1
GA
L147
Dig
ital M
edia
Upg
rade
2.0
0.1
0.1
0.8
1.1
GA
L149
Sout
h Te
rmin
al Im
mig
ratio
n 6.
41.
33.
61.
5
GA
L150
Nor
th T
erm
inal
For
ecou
rt (N
TF)
7.7
0.7
3.4
3.6
GA
L151
Nor
th T
erm
inal
Inte
rcha
nge
(NTI
)24
.61.
218
.15.
3
GA
L153
Alp
ha H
old
(Tax
iway
& H
olds
, JA
Z)0.
20.
1
GA
L154
Sout
h Te
rmin
al A
rriv
als
Con
cour
se R
econ
figur
atio
n5.
61.
20.
32.
02.
0
GA
L156
Julie
t Kin
k3.
10.
52.
6
GA
L162
Pollu
tion
Lago
on1.
41.
30.
1
GA
L163
Nor
th T
erm
inal
Can
opy
& P
avin
g Lo
wer
For
ecou
rt3.
21.
31.
9
GA
L164
Taxi
way
Lim
a2.
62.
6
GA
L168
Snow
Equ
ipm
ent
11.7
5.0
6.7
Tota
l for
Pro
ject
s C
ompl
eted
353.
041
.610
4.9
124.
578
.83.
00.
2
Prog
ram
mes
GA
L063
Secu
rity
Dev
elop
men
t Pro
gram
me
5.5
1.9
1.4
0.4
1.9
GA
L124
Ass
et R
epla
cem
ent P
rogr
amm
e63
.619
.314
.06.
812
.56.
44.
6
GA
L126
Com
mer
cial
and
Pro
pert
y Pr
ogra
mm
e25
.65.
83.
88.
56.
31.
2
GA
L128
Ope
ratio
nal E
ffici
ency
Pro
gram
me
12.1
3.8
7.2
1.1
GA
L131
Airfi
eld
Ass
et6.
00.
60.
63.
11.
30.
4
GA
L143
Cle
an, W
orki
ng &
Frie
ndly
13.6
5.7
3.3
2.0
2.6
GA
L159
& G
AL1
35IT
Tra
nsfo
rmat
ion
& IT
Pro
gram
me
46.6
1.7
4.1
19.6
20.9
0.1
0.1
GA
L176
Faci
litie
s A
sset
Ste
war
dshi
p /
NT
Foul
Ris
ing
Mai
n A
ugm
enta
tion
21.8
0.1
7.9
13.8
GA
L177
Com
mer
cial
Ass
et S
tew
ards
hip
4.
50.
14.
4
GA
L178
Airfi
eld
Ass
et S
tew
ards
hip
11.8
5.3
6.4
GA
L180
Q5
Min
or P
roje
cts
9.3
2.1
3.9
1.1
1.0
0w.8
0.5
GA
L182
Q5+
1 M
inor
Pro
ject
s <
£5m
49.5
20.6
28.9
PAX
ITPa
ssen
ger F
acin
g IT
(Q5+
1)
4.4
1.1
3.3
Tota
l for
Pro
gram
mes
274.
240
.838
.342
.545
.344
.862
.4
Oth
er P
roje
cts
GA
L181
BQ
5 D
evel
opm
ent
10.0
0.8
2.6
1.2
5.4
R2/C
ontin
genc
yR2
/Con
tinge
ncy
Oth
er P
roje
cts
25.3
11.8
7.3
1.6
4.3
0.3
Tota
ls fo
r All
Proj
ects
1,17
2.0
104.
018
1.4
211.
423
9.3
221.
921
3.9
Subc
o C
ar P
arks
*
*Sub
co (p
revi
ousl
y kn
own
as E
nter
pris
e) C
ar P
arks
hav
e be
en s
how
n fo
r ref
eren
ce b
ut h
ave
not b
een
incl
uded
in th
e to
tal c
apex
val
ue
Plea
se n
ote
2009
/10
and
2010
/11
tota
ls h
ave
been
adj
uste
d to
acc
ount
for r
ecla
ssifi
ed c
apita
l spe
nd. T
his
shou
ld h
ave
been
incl
uded
in th
e pr
evio
us C
IP10
.
93
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D G HAppendix
E
94BGatwick airport phased capital investment proGramme 2012 (in constant prices)
london Gatwick airport
projected spend (constant prices)
£ millions (constant 2012 prices)
Q5 Total Q5 Q5 Q5 Q5 Q5 Q5 Q5 Total
(Future Spend incl 2008/09, 2009/10,
2010/11 & 2011/12)
2008/09(Actual)
2009/10(Actual)
2010/11(Actual)
2011/12(Actual) 2012/13 2013/14 Out-turn
Equivalen
GAL167 Railway Contribution 7.6 1.1 6.5 7.6
GAL165 & GAL166 Taxiway Papa & November 7.3 2.7 4.6 7.3
GAL134 North Terminal Additional Pier Service 7.1 1.4 0.6 0.2 1.4 3.5 7.1
GAL150 North Terminal Forecourt (NTF) 11.4 0.7 3.4 3.6 1.3 2.4 11.4
Total for Projects in Implementation Stage 445.6 13.8 34.4 50.6 108.8 154.1 83.9 445.0
completed projects
GAL027 Inter Terminal Shuttle 36.7 9.0 17.2 10.3 0.2 0.1 36.7
GAL031b South Terminal Fire Protection System 14.4 3.4 5.9 4.9 0.2 14.4
GAL058 Telecomms Programme (Data & Voice) 1.0 0.9 0.1 1.0
GAL069 South Terminal Departure Lounge Capacity 19.8 13.9 5.6 0.3 19.8
GAL109 North West Zone 39.1 2.4 23.8 12.8 0.2 39.1
GAL115 North Terminal Short Term Car Parking (MSCP6)
16.9 1.0 0.7 14.3 1.0 16.9
GAL116 & GAL117 North Terminal Extension (NTX) 85.9 4.6 11.6 28.6 39.8 1.4 85.9
GAL120 South Terminal Forecourt 30.3 1.2 2.1 7.1 19.0 1.0 30.3
GAL140 Pier 2 modifications 38.1 0.1 10.0 20.8 7.1 38.1
GAL141 Roadway Improvements 1.0 1.0 1.0
GAL144 South Terminal Tunnel Security & Road Capacity
2.2 0.5 1.2 0.5 2.2
GAL145 South Terminal Tunnel Refurbishment 1.2 0.2 0.5 0.4 0.1 1.2
GAL147 Digital Media Upgrade 2.5 0.1 0.1 0.8 1.1 0.5 2.5
GAL149 South Terminal Immigration 6.4 1.3 3.6 1.5 6.4
GAL151 North Terminal Interchange (NTI) 24.6 1.2 18.1 5.3 24.6
GAL153 Alpha Hold (Taxiway & Holds, JAZ) 0.2 0.1 0.2
GAL154 South Terminal Arrivals Concourse Reconfiguration
7.6 1.2 0.3 2.0 2.0 2.0 7.6
GAL156 Juliet Kink 3.1 0.5 2.6 3.1
GAL161 River Mole Flood Alleviation 4.0 2.7 1.3 4.0
GAL162 Pollution Lagoon 1.5 1.3 0.1 0.1 1.5
GAL164 Taxiway Lima 2.6 2.6 2.6
Total for Projects Completed 339.1 40.9 101.5 115.9 73.4 7.4 339.1
programmes
GAL063 Security Development Programme 6.5 1.9 1.4 0.4 1.9 0.9 6.5
GAL124 Asset Replacement Programme 62.5 19.3 14.0 6.8 12.5 9.8 62.5
GAL126 Commercial and Property Programme 25.9 5.8 3.8 8.5 6.2 1.7 25.9
GAL128 Operational Efficiency Programme 12.1 3.8 7.2 1.1 12.1
GAL131 Airfield Asset 5.0 0.6 0.6 3.1 0.7 5.0
GAL143 Clean, Working & Friendly 15.4 5.7 3.3 2.0 2.6 1.8 15.4
GAL159 & GAL135 IT Transformation & IT Programme 48.1 1.7 4.1 19.6 20.9 1.7 48.1
GAL176 Facilities Asset Stewardship 19.0 0.2 9.0 9.8 18.9
GAL177 Commercial Asset Stewardship 4.7 4.7 4.7
GAL178 Airfield Asset Stewardship 15.1 15.1 15.0
GAL180 Q5 Minor Projects 9.3 2.1 3.9 1.1 1.0 1.3 9.3
GAL182 Q5+1 Minor Projects < £5m 37.4 5.7 31.6 37.1
GAL183 Flood Alleviation 8.2 8.2 8.2
Total for Programmes 269.0 40.8 38.3 42.5 45.3 40.8 61.2 268.6
other projects
GAL181 Beyond Q5 Development 10.0 0.8 2.6 6.6 10.0
R2/Contingency R2/Contingency 12.3 12.3 12.3
GAL not needed Other Projects 26.2 8.5 6.3 3.0 4.8 3.5 26.2
Totals for All Projects 1,173.2 104.0 180.4 212.9 239.2 265.6 171.1 1,172.0
Subco Car Parks*
*Subco (previously known as Enterprise) Car Parks have been shown for reference but have not been included in the total capex value Please note 2009/10 and 2010/11 totals have been adjusted to account for reclassified capital spend. This should have been included in the previous CIP10. The 2013/14 programme may be subject to changes in phasing. This is currently in discussion
COPI Assumption: 2013/14 @ -0.7%
APPENDIX c - Changes to Investment Programme - traCker for the PerIod aPrIl 2012 to marCh 2013
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Glossary
1 2 3 4 C D G HAppendix
E20
1220
13
GA
L N
oN
ame
Firs
t App
eare
d
Tota
l Q5
(ext
ende
d) S
pend
(£
mill
ions
, out
-tur
n)Pr
ogra
mm
e C
hang
eC
hang
e C
ontr
ol R
ecor
d Sh
eet
(CC
RS)
Trig
ger C
hang
e
(CA
A A
ppro
ved)
Tota
l Q5
(ext
ende
d) S
pend
(£
mill
ions
, out
-tur
n)Pr
ogra
mm
e C
hang
eC
hang
e C
ontr
ol R
ecor
d Sh
eet
(CC
RS)
Trig
ger C
hang
e
(CA
A A
ppro
ved)
GA
L146
Port
als
(Sta
ndar
disa
tion
ATI
X)
CIP
200
8-
--
--
--
--
--
--
--
-
GA
L147
Dig
ital M
edia
Upg
rade
CIP
200
82.
5-
--
--
--
2.0
▼-
--
--
-
GA
L128
Ope
ratio
nal E
ffici
ency
Pro
gram
me
CIP
200
812
.1-
--
--
--
12.1
--
--
--
-
GA
L096
cN
orth
ern
Runw
ay R
esur
face
CIP
200
8-
--
--
--
--
--
--
--
-
GA
L027
Inte
r Ter
min
al S
hutt
leC
IP 2
008
36.7
--
--
--
-36
.6▼
--
--
--
GA
L031
bSo
uth
Term
inal
Fire
Pro
tect
ion
Syst
emC
IP 2
008
14.4
▼-
--
--
-14
.4-
--
--
--
GA
L144
Sout
h Te
rmin
al T
unne
l Sec
urity
& R
oad
Cap
acity
CIP
200
82.
2-
--
--
--
2.2
--
--
--
-
GA
L039
Gro
und
Run
Pen
CIP
200
8-
--
--
--
--
--
--
--
-
GA
L145
Sout
h Te
rmin
al T
unne
l Ref
urbi
shm
ent
CIP
200
81.
2-
--
--
--
1.2
--
--
--
-
GA
L133
Add
ition
al S
ecur
ity C
apac
ityC
IP 2
008
--
--
--
--
--
--
--
--
GA
L080
DEE
Pro
gram
me
CIP
200
8-
--
--
--
--
--
--
--
-
GA
L034
bFI
DS
CIP
200
8-
--
--
--
--
--
--
--
-
GA
L041
Load
ing
Brid
ge P
rogr
amm
eC
IP 2
008
--
--
--
--
--
--
--
--
GA
L070
bN
orth
Ter
min
al T
oile
t Ref
urbi
shm
ent
Prog
ram
me
CIP
200
8-
--
--
--
--
--
--
--
-
GA
L067
bN
orth
Ter
min
al A
dditi
onal
Bag
gage
Cap
acity
CIP
200
8-
--
--
--
--
--
--
--
-
GA
L063
Secu
rity
Dev
elop
men
t Pro
gram
me
CIP
200
86.
5-
--
--
--
5.7
▼-
--
--
-
GA
L069
Sout
h Te
rmin
al D
epar
ture
Lou
nge
Cap
acity
CIP
200
819
.8-
--
--
--
19.8
--
--
--
-
GA
L058
Tele
com
ms
Prog
ram
me
(Dat
a &
Voi
ce)
CIP
200
81.
0-
--
--
--
1.0
--
--
--
-
GA
L124
Ass
et R
epla
cem
ent P
rogr
amm
eC
IP 2
008
62.5
▲Sc
ope
Cha
nge
- TB
F H
BS
-LG
W /
0083
--
63.6
▲Pr
ogra
mm
e /
Scop
e ch
ange
-LG
W 0
099
--
GA
L131
Airfi
eld
Ass
etC
IP 2
008
5.0
--
--
--
-6.
0▲
--
--
--
GA
L143
Cle
an, W
orki
ng &
Frie
ndly
CIP
200
815
.4-
--
--
--
13.9
▼-
--
--
-
Min
or P
roje
cts
CIP
200
8-
--
--
--
--
--
--
--
-
GA
L096
Airfi
eld
Prog
ram
me
incl
udin
g Ru
nway
Re
surf
acin
gC
IP 2
008
61.5
▲-
--
--
-66
.3▲
Prog
ram
me
/ Sc
ope
chan
ge-
LGW
009
8-
--
GA
L126
Com
mer
cial
and
Pro
pert
y Pr
ogra
mm
eC
IP 2
008
25.9
▼Sc
ope
Cha
nge
-
LGW
/009
3-
--
25.6
▼-
--
-
GA
L135
IT P
rogr
amm
eC
IP 2
008
--
--
--
--
--
--
--
--
GA
L116
& G
AL1
17N
orth
Ter
min
al E
xten
sion
(NTX
)C
IP 2
008
85.9
▲-
--
--
85.3
▼Tr
ansf
er o
f bud
get
back
to N
T Ex
tens
ion
-LG
W 0
110
--
GA
L134
Nor
th T
erm
inal
Add
ition
al P
ier S
ervi
ceC
IP 2
008
7.1
▼-
--
-8.
7▲
Bud
get i
ncre
ase
LGW
013
1-
--
GA
L136
Airl
ine
Relo
catio
nsC
IP 2
008
--
--
--
--
--
--
--
--
GA
L125
& G
AL0
05So
uth
Term
inal
Bag
gage
Fac
tory
& P
ier 1
CIP
200
811
6.4
▼C
onfir
mat
ion
of
Pref
erre
d sc
ope
-LG
W/0
062
--
-97
.7▼
Tran
sfer
of £
18.7
Sc
ope
to B
eyon
d Q
5 &
Tr
ansf
er o
f £4.
9m s
cope
to
NT
Void
s Pr
ojec
t
-
LGW
010
5
LGW
010
8
LGW
012
6
LGW
0127
--
-
GA
L137
Nor
th T
erm
inal
Bag
gage
Upg
rade
CIP
200
850
.2▲
Scop
e C
hang
e
-LG
W/
0084
- 00
92
(
9 N
os C
CRS
s)-
--
49.7
▼Tr
ansf
er o
f sco
pe
/ bu
dget
from
NT
Bag
gage
Hal
l Acc
ess
-LG
W 0
097
--
-
GA
L115
Nor
th T
erm
inal
Sho
rt T
erm
Car
Par
king
(M
SCP6
)C
IP 2
008
16.9
--
--
--
-16
.9-
--
--
--
GA
L109
Nor
th W
est Z
one
CIP
200
839
.1▼
--
--
--
39.1
▼-
--
--
-
GA
L111
Nor
th T
erm
inal
Add
ition
al P
ier S
ervi
ce -
Pier
5
(pre
viou
sly
‘ Sta
nd R
econ
figur
atio
n’ )
CIP
200
872
.9▼
Con
firm
atio
n of
Fi
nal s
cope
-LG
W/0
077
--
-74
.3▲
Scop
e ch
ange
-LG
W 0
113A
--
-
GA
L122
Sout
h Te
rmin
al L
ands
ide
CIP
200
817
.2▼
--
--
--
23.0
▲Sc
ope
tran
sfer
fro
m S
T Se
curit
y -
LGW
011
4
LG
W 0
115
--
-
GA
L120
Sout
h Te
rmin
al F
orec
ourt
CIP
200
830
.3▼
--
--
-30
.1▼
--
--
-
GA
L138
Early
Bag
Sto
reC
IP 2
008
--
--
--
--
--
--
--
--
GA
L139
Pier
4 M
odifi
catio
nsC
IP 2
008
--
--
--
--
--
--
--
--
GA
L140
Pier
2 M
odifi
catio
ns
CIP
200
838
.1▼
--
--
-38
.4▼
--
--
-
GA
L152
Pier
3 M
odifi
catio
ns
CIP
200
9-
--
--
--
--
--
--
--
-
GA
L132
Sout
h Te
rmin
al A
irsid
eC
IP 2
008
--
--
--
--
--
--
--
--
GA
L141
Road
way
Impr
ovem
ents
CIP
200
81.
0-
--
--
--
1.1
--
--
--
-
GA
L005
Pier
1C
IP 2
008
--
--
--
--
--
--
--
--
GA
L142
Sout
her n
For
ecou
rt E
nhan
cem
ents
CIP
200
8-
--
--
--
--
--
--
--
-
GA
L153
Alp
ha H
old
(Tax
iway
& H
olds
, JA
Z)C
IP 2
009
0.2
--
--
--
-0.
2-
--
--
--
GA
L149
Sout
h Te
rmin
al Im
mig
ratio
nC
IP 2
009
6.4
--
-LG
W/0
064
LG
W/0
065
LG
W/0
081
--
-6.
4-
--
--
-
Oth
er P
roje
cts
CIP
200
8-
▲-
--
--
--
▲-
--
--
-
GA
L154
Sout
h Te
rmin
al A
rriv
als
Con
cour
se
Reco
nfigu
ratio
nC
IP 2
009
7.6
--
--
--
-7.
7-
--
--
--
GA
L150
Nor
th T
erm
inal
For
ecou
rt (N
TF)
CIP
200
911
.4-
--
--
--
11.4
--
--
--
-
GA
L151
Nor
th T
erm
inal
Inte
rcha
nge
(NTI
)C
IP 2
009
24.6
--
--
--
-24
.6-
--
--
--
GA
L159
& G
AL1
35IT
Tra
nsfo
rmat
ion
CIP
201
048
.1-
--
LGW
/007
1 LG
W/0
072
--
-46
.6▼
--
--
-
GA
L155
Sout
h Te
rmin
al S
ecur
ityC
IP 2
010
52.3
▲Sc
ope
Cha
nge
-
LGW
/007
3
LGW
/007
4-
-47
.7▼
Scop
e ch
ange
&
Sc
ope
tran
sfer
to S
T La
ndsi
de
-LG
W 0
102
LG
W 0
114
LGW
011
5-
-
GA
L160
Surf
ace
Wat
er in
clu
Pond
DC
IP 2
010
8.3
--
--
--
-12
.2-
--
--
--
GA
L161
Rive
r Mol
e Fl
ood
Alle
viat
ion
CIP
201
04.
0-
--
--
--
4.1
--
--
--
-
GA
L162
Pollu
tion
Lago
onC
IP 2
010
1.3
--
--
--
-1.
4-
--
--
--
GA
L163
Nor
th T
erm
inal
Can
opy
& P
avin
g Lo
wer
Fo
reco
urt
CIP
201
01.
4-
--
--
--
3.2
▲-
--
--
-
GA
L157
Nor
th T
erm
inal
Sec
urity
CIP
201
011
.5▼
--
--
10.7
▼-
--
-
GA
L156
Julie
t Kin
kC
IP 2
010
3.1
--
--
--
-3.
1-
--
--
--
GA
L164
Taxi
way
Lim
aC
IP20
102.
6-
--
--
--
2.6
--
--
--
-
GA
L165
& G
AL1
66Ta
xiw
ays
Papa
& N
ovem
ber
CIP
2010
7.3
▼-
--
--
5.4
▼-
--
--
GA
L167
Railw
ay C
ontr
ibut
ion
CIP
2010
7.6
--
--
--
-7.
7-
--
--
--
GA
L168
Snow
Equ
ipm
ent
CIP
2010
11.7
▲-
--
--
11.7
--
--
--
GA
L169
Nor
th T
erm
inal
Ear
ly B
ag S
tore
CIP
2011
0.4
▼D
efer
red
to
Bey
ond
Q5
-LG
W/0
082
--
-0.
4-
Def
err e
d to
B
eyon
d Q
5-
--
-
GA
L170
Nor
th T
erm
inal
Bag
gage
Voi
dsC
IP20
113.
2▲
--
--
-7.
4▲
Scop
e ch
ange
to
incl
ude
ST V
oids
&
Scop
e tr
ansf
er fr
om S
T B
agga
ge &
Pie
r 1
-LG
W 0
126
LGW
012
7-
--
GA
L171
A38
0 on
Sta
ndC
IP20
116.
5▲
--
LGW
/006
7-
--
5.9
▼C
onfir
mat
ion
of
Bud
get &
Sco
pe
at T
G4
-LG
W 0
101
--
-
GA
L172
Airfi
eld
Peak
Cap
acity
Exp
ansi
on (A
CD
M)
CIP
2011
7.0
▲-
--
--
-6.
0▼
Prog
ram
me
- Ph
ase
2 w
orks
-LG
W 0
123
--
-
GA
L173
Cre
w R
epor
ting
C
IP20
1112
.0-
--
--
--
20.5
5▲
Con
firm
atio
n of
Sc
ope
& B
udge
t at
TG
4-
LGW
010
4-
--
GA
L174
Sout
h Te
rmin
al D
omes
tic A
rriv
als
CIP
2011
9.5
--
--
--
-11
.2▲
Scop
e ch
ange
-LG
W 0
100,
LG
W01
39-
--
GA
L175
aN
orth
Ter
min
al ID
L Re
confi
gura
tion
CIP
2011
10.2
▲-
--
--
-6.
5▼
Redu
ctio
n in
Sc
ope
& B
udge
t -
LGW
010
9, L
GW
013
4-
--
GA
L175
bSo
uth
Term
inal
IDL
Reco
nfigu
ratio
nC
IP20
1124
.4▲
--
--
--
20.5
▼C
onfir
mat
ion
of
AFC
at T
G4
-LG
W 0
112
LG
W 0
124
-
--
GA
L176
Faci
litie
s A
sset
Ste
war
dshi
p C
IP20
1118
.9▼
Scop
e C
hang
eLG
W /
0066
LGW
/00
94
-
-21
.8▼
Prog
ram
me
LGW
009
6
--
GA
L177
Com
mer
cial
Ass
et S
tew
ards
hip
CIP
2011
4.7
▼-
--
--
-4.
7▼
--
--
--
GA
L178
Airfi
eld
Ass
et S
tew
ards
hip
CIP
2011
15.0
▲-
--
--
-11
.8▼
Prog
ram
me
--
--
-
GA
L179
Airfi
eld
Ope
ratio
ns B
uild
ing
CIP
2012
7.9
▲N
ew P
roje
ct-
LGW
/00
80-
--
7.9
▲B
udge
t inc
reas
e-
LGW
010
6-
--
GA
L180
Q5
Min
or P
roje
cts
Prog
ram
me
<£5
.0 m
illio
nC
IP20
119.
3▼
Prog
ram
me
--
--
-9.
3▼
Prog
ram
me
-LG
W 0
107
--
-
GA
L181
Bey
ond
Q5
Dev
elop
men
tC
IP20
1010
.0-
--
LGW
/007
9-
--
10.0
-Pr
ogra
mm
e-
LGW
011
9-
-
GA
L182
Q5+
1 M
inor
Pro
ject
s Pr
ogra
mm
e <
£5.0
m
illio
nC
IP20
1137
.1▲
Prog
ram
me
-48
.4▲
Prog
ram
me
LGW
012
2
-
GA
L183
Gat
wic
k St
ream
Flo
od A
tten
uatio
n Pr
ogra
mm
eC
IP20
128.
2-
Prog
ram
me
-8.
2-
Prog
ram
me
LGW
011
1-
GA
L184
ST &
NT
UK
Bor
der F
orce
Arr
ival
Zon
esC
IP20
13-
--
--
6.6
-N
ew P
roje
ct L
GW
009
5a
LGW
011
8
LGW
012
1-
-
GA
L 18
5C
onso
lidat
ed S
ecur
ity G
ate
CIP
2013
--
--
-5.
5-
New
Pro
ject
LGW
012
5
LG
W 0
133
--
95
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
DAPPENDIX D - PrEvIous TrAffIc forEcAsTs (As PublIshED IN 2012cIP)
2012 cIP Annual Passenger forecasts (millions)
May 2011 february 2012
low base high low base high
Q5 2008/09 actual 33.1 33.1 33.1 33.1 33.1 33.1
2009/10 actual 32.4 32.4 32.4 32.4 32.4 32.4
2010/11 actual 31.6 31.6 31.6 31.6 31.6 31.6
2011/12 actual 32.5 33.3 33.9 33.8 33.8 33.8
2012/13 32.8 34.1 35.2 33.8 34.3 35.2
2013/14 33.1 34.9 36.3 34.0 35.2 36.7
beyond Q5 2014/15 33.6 35.6 37.4 34.2 35.7 37.8
2015/16 34.1 36.3 38.6 34.3 36.0 38.8
2016/17 34.6 37.1 40.0 34.6 36.4 39.7
2017/18 35.0 37.9 41.6 34.8 36.8 40.4
2018/19 35.5 38.7 42.2 35.1 37.2 41.1
Growth Rate per annum
2010/11 – 2013/14 1.5% 3.3% 4.6%
2011/12 – 2013/14 0.2% 2.1% 4.2%
2013/14 - 2018/19 1.4% 2.1% 3.1% 0.7% 1.1% 2.3%
2012 cIP Annual Aircraft Movements (thousands)
february 2012
Passenger ATMs base case
Q5 Low Base High CATM* Non-ATM**
2008/09 actual - - - - -
2009/10 actual 244.4 244.4 244.4 0.06 6.8
2010/11 actual 235.6 235.6 235.6 0.16 6.8
2011/12 actual 242.1 242.1 242.1 0.35 6.2
2012/13 244.2 247.6 251.1 0.35 6.3
2013/14 243.2 249.9 258.5 0.36 6.4
beyond Q5 2014/15 242.7 252.6 264.6 0.36 6.4
2015/16 242.3 253.5 270.4 0.36 6.4
2016/17 242.1 254.6 276.1 0.37 6.3
2017/18 242.2 255.6 279.4 0.37 6.2
2018/19 242.2 256.8 281.6 0.37 6.3
Growth Rate p.a. (2011/12 – 2013/14) 0.2% 1.6% 3.3% - -
Growth Rate p.a. (2014/15 - 2018/19) 0.1% 0.4% 1.6% - -
* CATM: Cargo Air Transport Movements i.e. Commercial Cargo flights**Non-ATM: Non Air Traffic Movements i.e. General Aviation, Air Taxi
96
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
97eAppendix e - Meetings, Working groups And governAnce BoArds, froM April 2012 to MArch 2013
Please note there were weekly Beyond Q5 working groups. Topics discussed included traffic forecasts, service quality, capital projects, operational costs and commercial revenue.
date Meeting discussion / items on the Agenda
03 April 2012 South Terminal Stakeholder Working Group Discuss impacts of construction work to airport and airlines operations. Advise of upcoming planned work and major works over the next 5 weeks.
03 April 2012 Pier 1 Working Group Construction Phasing - use of temporary stands, management of gates and stands
03 April 2012 ST Baggage Working Group Project and process workstream update. Potential MuP allocation. ST rush bag unit. Out of Gauge proposals.
04 April 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
05 April 2012 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
10 April 2012 Service Quality Exclusions Group Monthly agreement of exclusions for the 6 week look ahead, Review of previous month exclusions and service performance. Review of pier service exceptions.
10 April 2012 Crew Access Working Group Jubilee House - construction phasing and HBS replacement. Atlantic House - crew hold baggage process; airside coaching process; pre-TG4 layout detail update.
10 April 2012 South Terminal Stakeholder Working Group Discuss impacts of construction work to airport and airlines operations. Advise of upcoming planned work and major works over the next 5 weeks.
11 April 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
11 April 2012 Joint Steering Group Q5+1 Update - Programme; ACC Update on Projects Support; Trigger Projects. ST & NT UKBA Arrivals Phase 1 Tollgate 4. Capital Programme Board Update - ST Entrance Bridge Cladding Tollgate 4; Fire Strategy CCRS; NT Baggage Hall Access CCRS; Q6 Capital Facilitation CCRS; Snow Equipment inc Konsin De-Icer Tanks CCRS; ST Forecourt Trigger Achievement. Q6 Engagement Update. AOC Executive Update. Service Delivery Update.
13 April 2012 Q5+1 Working Group ACC Feedback on current Q5+1 Projects status. Airfield Projects. Next Steps.
17 April 2012 South Terminal Stakeholder Working Group Discuss impacts of construction work to airport and airlines operations. Advise of upcoming planned work and major works over the next 5 weeks.
18 April 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
19 April 2012 Beyond Q5 Business Plan & Constructive Engagement Launch
Introduction. Business Plan Overview & Questions - Traffic; Service; Capital; Risks; Price; Q6 Process
20 April 2012 Q5+1 Working Group ACC Feedback on current Q5+1 Projects status.
24 April 2012 South Terminal Stakeholder Working Group Discuss impacts of construction work to airport and airlines operations. Advise of upcoming planned work and major works over the next 5 weeks.
25 April 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
25 April 2012 Capital Programme Board ST Domestic Arrivals - Tollgate 4. Crew Reporting Update. Pumping Station 18 - Tollgate 2. Main Runway Rehabilitation R2 Draw-down CCRS. NT Baggage CCRSs. CIP Performance Pack. Projects Overview.
27 April 2012 Main Runway Rehabilitation Project Board Programme and Progress Update. Operational Interfaces & Constraints. Risk & Opportunity.
02 May 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
03 May 2012 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
08 May 2012 Service Quality Exclusions Group Monthly agreement of exclusions for the 6 week look ahead, Review of previous month exclusions and service performance. Review of pier service exceptions.
09 May 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
09 May 2012 Joint Steering Group Q5+1 Update - ACC Update on Q5+1 Projects Support; Trigger Projects. Capital Programme Board Update: ST Domestic Arrivals Phase 1 Tollgate 4; Pumping Station 18 Tollgate 2; Main Runway Rehabilitation R2 draw-down. Crew Reporting Project Tollgate 4 Update. Revisited Projects: NT Baggage CCRSs; NT Baggage Hall Access CCRS; UK Borders Arrivals Phase 1. CEWG (Q6 Engagement) Update. AOC Executive Update. Service Delivery Update. AOB - Main Runway Rehabilitation Project Update
16 May 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
17 May 2102 Crew Access Working Group Discussion of project options and costs
18 May 2012 Main Runway Rehabilitation Project Board Programme and Progress Update. Operational Interfaces & Constraints. Risk & Opportunity.
23 May 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
23 May 2012 Capital Programme Board ITTS & ST IDL Investment Performance Reviews. ST Security R2 draw-down CCRS. A380 Tollgate 4. Crew Reporting Tollgate 4 Update. Q5+1 Update: Trigger Definitions (Pier 5, ST Baggage & Pier 1, Crew Reporting, ST IDL). Main Runway Rehabilitation: R2 draw-down for ducts/cabling beneath M23 & railway - on-costs explanation; Programme Update. NT Baggage CCRSs. CIP Performance Pack. Projects Overview.
29 May 2012 Crew Access Working Group Discussion of project options and costs
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
98
date Meeting discussion / items on the Agenda
30 May 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
31 May 2012 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
31 May 2012 Additional Pier Service (Pier 5) Working Group Gateroom Detailed Design Review
04 June 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks. Traffic Forecasts.
08 June 2012 Service Quality Exclusions Group Monthly agreement of exclusions for the 6 week look ahead, Review of previous month exclusions and service performance. Review of pier service exceptions.
11 June 2012 Crew Access Working Group Discussion of project options and costs
13 June 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
13 June 2012 Joint Steering Group Q5+1 Update: GAL response to ACC position on Q5+1 Projects; Trigger Projects Liability & Definitions. Capital Programme Update: ST Security R2 draw-down CCRS; A380 Tollgate 4 CCRS; Main Runway Rehabilitation R2 Draw-down CCRS; Crew Reporting Tollgate 4. Revisited Projects: NT Baggage CCRSs; NT Baggage Hall Access CCRS; UK Borders Arrivals Phase 1 CCRS signature. CEWG (Q6 Engagement) Update. AOC Executive Update. Service Delivery Update. CIP 2012 Consultation. Main Runway Rehabilitation update.
15 June 2012 Main Runway Rehabilitation Project Board Programme and Progress Update. Operational Interfaces & Constraints. Critical Items. Risk & Opportunity.
20 June 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
20 June 2012 Capital Programme Board ST Baggage & Pier 1: Phase 2 Pre-Tollgate 4 Update; Phase 1 R2 draw-down CCRS. Airfield Operations Building Tollgate 4. NT IDL Project 2 Tollgate 3. Pier 5 Gateroom Seating Update. NT Baggage CCRSs. Q5+1 Projects Update. CIP Performance Pack. Projects Overview. Capital "Gateway" Consultation Process.
27 June 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
04 July 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
05 July 2012 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
09 July 2012 South Terminal Baggage & Pier 1 Workshop Business Case, Project Execution
10 July 2012 Service Quality Exclusions Group Monthly agreement of exclusions for the 6 week look ahead, Review of previous month exclusions and service performance. Review of pier service exceptions.
11 July 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
11 July 2012 Joint Steering Group Q5+1 Update: ACC Projects Endorsement Update; Joint Submission to CAA on Triggers. Capital Programme Board Update: ST Baggage & Pier 1 Tollgate 4; ST Baggage & Pier 1 R2 Draw-down; Airfield Operations Building Tollgate 4; NT IDL Project 2 Tollgate 3. Revisited Project: NT Baggage CCRSs. easyJet Terminal Consolidation Update. CEW6 (Q6 Engagement) Update including ACC Project Recommendations. AOC Executive Update. Service Delivery Update. Main Runway Rehabilitation project update.
18 July 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
20 July 2012 Main Runway Rehabilitation Project Board Programme and Progress Update. Operational Interfaces & Constraints. Critical Items. Risk & Opportunity.
25 July 2012 Capital Programme Board ST IDL Reconfiguration Tollage 3. NT Extension CCRS. NT Baggage Voids Tollgate A. NT Baggage Update. Pier 5 Gateroom Seating Update. Gatwick Stream Flood Attenuation Tollgate 3. Consultation Process Review. Minor Projects Update. A380 on Stand 125 Update. Q5+1 Projects Update. CIP Performance Pack & Projects Overview. AOB including NT Baggage CCRSs update.
25 July 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
25 July 2012 Additional Pier Service (Pier 6) Working Group Capacity update – BA and GAL; Agree assumptions behind the Level 1 QFD
25 July 2012 Charges Group Regulatory Accounts Overview; 2013-14 Consultation Calendar
01 August 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
02 August 2012 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
03 August 2012 Main Runway Rehabilitation Project Board Programme and Progress Update. 7 Options. Current Plan.
07 August 2012 Service Quality Exclusions Group Monthly agreement of exclusions for the 6 week look ahead, Review of previous month exclusions and service performance. Review of pier service exceptions.
07 August 2012 UK Borders Arrivals Zones Working Group Site visit to gate 10A - operational layout of trial of e-gates. Potential concepts for ST & NT.
08 August 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
99
date Meeting discussion / items on the Agenda
08 August 2012 Joint Steering Group Q5+1 Update - ACC Projects Endorsement Update; Joint Submission to CAA on Triggers. Capital Programme Board Update - ST IDL Reconfiguration Tollgate 3; NT Baggage Voids Tollgate A; Gatwick Stream Flood Attenuation Tollgate 3; NT Extension Budget Transfer CCRS; Consultation Process Review. Revisited Projects - NT Baggage CCRSs; Airfield Operations Building Tollgate 4. CEWG (Q6 Engagement) Update including ACC Project Recommendations. Charges Group Update. AOC Executive Update. Service Delivery Update. AOB - Main Runway Rehabilitation project update; CAA Performance Charter proposals.
15 August 2012 Additional Pier Service (Pier 6) Working Group Capacity Analysis Update. Level 2 QFD.
15 August 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of plat
15 August 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
17 August 2012 Main Runway Rehabilitation Project Board General Update. Programme and Progress Update.
22 August 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
22 August 2012 Capital Programme Board Pier 5 Gateroom Seating, Stand Numbering & Dynamic Signage Update. ST Security - Scope & Budget Transfer to ST Landside Project CCRSs. ST & NT Border Force Arrivals Zones Phase 2 - Tollgate 3. Q5+1 Projects Update. CIP Performance Pack. Projects Overview. AOB - NT Baggage CCRSs Update; Main Runway; Beyond Q5 Capital Draw-down.
29 August 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
30 August 2012 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
05 September 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
05 September 2012 Joint Steering Group Q5+1 Update - ACC Projects Endorsement Update; Joint Submission to CAA on Triggers. Capital Programme Board Update - ST Security - scope & budget transfer to ST Landside CCRSs; ST & NT Border Force Arrivals Zones Phase 2 Tollgate 3; Beyond Q5 Capital Facilitation CCRS. Revisited Project - NT Baggage CCRSs. CEWG Update - ACC Project Recommendations; CAA CE Mid-Term Review Joint Submission. AOC Executive Update. Service Delivery Update. AOB - Main Runway Rehabilitation Update; Snow SLA; Charges Group.
07 September 2012 Service Quality Exclusions Group Monthly agreement of exclusions for the 6 week look ahead, Review of previous month exclusions and service performance. Review of pier service exceptions.
12 September 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
12 September 2012 Additional Pier Service (Pier 6) Working Group Stand Gap Analysis. Update on Capacity Analysis.
18 September 2012 Charges Group Specified Activities 2011/12 Summary and 2013/14 Charging Proposal. Feedback on PRM pricing proposal. Setting the Scene for 2013/14 Airport Charges incl EU Airport Charges Directive Information Request.
19 September 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
19 September 2012 Asset Stewardship Working Group Terms of Reference agreement. Example of level of information available on assets. Request for ACC to pick key areas under asset stewardship to "deep dive".
19 September 2012 Capital Programme Board Baggage Reconciliation System Tollgate 2. Foul Main R2 Draw-down. NT Additional Pier Service Update. Pier 5 Update. NT Baggage Update. Q5+1 Projects Update. CIP Performance Pack. Projects Overview. AOB - CAA End Q5 Review.
26 September 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
26 September 2012 Service Working Group Working Group Objectives. Areas for Measurement. Timetable. Agenda for next meeting.
03 October 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
04 October 2012 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
09 October 2012 Service Quality Exclusions Group Monthly agreement of exclusions for the 6 week look ahead, Review of previous month exclusions and service performance. Review of pier service exceptions.
10 October 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
10 October 2012 Joint Steering Group Q5+1 Update - ACC Projects Endorsement Update. Capital Programme Board Update - NT Foul Main R2 Draw-down CCRS; Baggage Reconciliation System Tollgate 2. Revisited Projects - ST & NT Border Force Arrivals Zones Phase 2 Tollgate 3 Update; Beyond Q5 Capital Facilitation CCRS. easyJet Terminal Consolidation. CEWG Update - ACC Project Recommendations. AOC Executive Update. Service Delivery Update. Charges Group Update. AOB - Airport Charter Meeting; Main Runway Rehabilitation Update.
11 October 2012 Additional Pier Service (Pier 6) Working Group Capacity Update. Handling Agents workshop update. Next steps and Terms of Reference.
17 October 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
17 October 2012 Service Working Group Areas for Measurement - Airline Proposal. Proposed Targets Discussion. Agenda for next meeting.
18 October 2012 Additional Pier Service (Pier 6) Working Group Terms of Reference and future working groups. easyJet South Terminal Consolidation presentation.
18 October 2012 Charges Group Specified Activities Consultation 2013/14. Airport Charges Consultation 2013/14.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
100
date Meeting discussion / items on the Agenda
24 October 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
24 October 2012 Capital Programme Board Pier 5 - scope & budget changes R2 draw-down CCRS. ACDM 55 Phase 2 Tollgate 4. ST & NT UKBF Arrivals Phase 2 Tollgate 4. Crew Reporting Update. Impact of Changes to Projects. Q5+1 Projects Update. CIP Performance Pack. Projects Overview.
29 October 2012 Baggage Service Level Agreement (SLA) meeting Draft proposal for departures baggage SLA
31 October 2012 Service Working Group Underlying Principles - GAL Proposal. Elements for Service Scheme. Agenda for next meeting.
31 October 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
01 November 2012 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
01 November 2012 Additional Pier Service (Pier 6) Working Group Terms of Reference. Assumptions for underlying GAP analysis.
05 November 2012 Baggage Service Level Agreement (SLA) meeting Future Service Standards
06 November 2012 Service Quality Exclusions Group Monthly agreement of exclusions for the 6 week look ahead, Review of previous month exclusions and service performance. Review of pier service exceptions.
07 November 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
07 November 2012 Charges Group 2013/14 Airport Charges proposals
07 November 2012 Joint Steering Group Q5+1 Update - ACC Projects Endorsement Update. Capital Programme Board Update - Pier 5 Scope and budget changes draw-down; ACDM 55 Phase 2 Tollgate 4; ST & NT UK Border Force Arrivals Zones Phase 2 Tollgate 4. CEWG Update - ACC Recommendations. AOC Executive Update. Service Delivery Update. Charges Group Update. AOB - Main Runway Rehabilitation Update.
13 November 2012 Asset Stewardship Working Group Cost of Asset Stewardship programme of projects and the IDL projects (contained in the April 12 Business Plan). Benchmarking and procurement procedures.
14 November 2012 North Terminal Stakeholder Working Group General Update. Programme and Progress Update.
16 November 2012 Service Working Group Follow-up issues discussed at last meeting. Proposal re Service Priorities. Agenda for next meeting.
20 November 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
28 November 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
29 November 2012 Asset Stewardship Working Group Cost explanation
29 November 2012 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
29 November 2012 South Terminal IDL Workshop Phase 2 - Pre-Tollgate 4
04 December 2012 Service Working Group Follow-up issues discussed at last meeting. Check-in & Baggage Reclaim Passenger Feedback presentation.
05 December 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
05 December 2012 Piers Working Group Agreement of primary output of the requirement to achieve 95% pier service in NT including delivery of Pier 6 southern extension. Scenarios that will be modelled for pier service requirement. Inputs to the pier service models. Methodology for calculating pier service requirement. Outputs of the pier service models.
05 December 2012 Joint Steering Group Q5+1 Update. Capital Programme Board Update Report. ST IDL Phase 2 - Tollgate 4. Crew Reporting Update. Revisited Project - Pier 5 - scope and budget changes R2 draw-down. CEWG Update Report. AOC Executive Update. Service Delivery Update. Charges Group Update.
07 December 2012 Service Quality Exclusions Group Monthly agreement of exclusions for the 6 week look ahead, Review of previous month exclusions and service performance. Review of pier service exceptions.
11 December 2012 Crew Access Working Group Atlantic House: Building Layout (ground floor); Process flow through building crew & hold baggage; Baggage input control inc tagging; Make-up & reconciliation of hold baggage. Delivery to stand.
12 December 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
19 December 2012 North Terminal Stakeholder Working Group NT projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
19 December 2012 Capital Programme Board Consolidated Security Gate - R2 draw-down CCRS. Externally accredited assessment of Project Management Maturity. Crew Reporting Update. Q5+1 Projects Update. Projects Overview.
20 December 2012 Pier Service Working Group Proposed Schedule for modelling work
21 December 2012 Crew Access Working Group Atlantic House: Hold Baggage Screening; HBS Contingency
02 January 2013 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
04 January 2013 Pier Service Working Group Schedule for agreement for modelling work
08 January 2012 Charges Group 2013/14 Airport Charges Decision. Specified Activities - Check-in & Baggage. 2013/14 Conditions of Use. Airport Charges Structural Changes Consultation Process for Summer 2014 Implementation
09 January 2013 easyJet Consolidation to South Terminal - JSG Working Group
Purpose & Terms of Reference. ACC questions / GAL response. Analysis of easyJet in ST - Questions & Debate. Next Meetings - timing and agenda's
09 January 2013 North Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
101
date Meeting discussion / items on the Agenda
09 January 2013 Joint Steering Group Q5+1 Update. Capital Programme Board Update Report inc Consolidated Security Gate TG2 R2 Draw-down. Crew Reporting Update. Revisited Project - Pier 5 - scope and budget changes R2 draw-down. CEWG Update Report. AOC Executive Update. Service Delivery Update. Charges Group Update.
11 January 2013 Service Quality Exclusions Group Monthly agreement of exclusions for the 6 week look ahead, Review of previous month exclusions and service performance. Review of pier service exceptions.
16 January 2013 North Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
23 January 2013 Capital Programme Board Check-in Trials Update. NT IDL Update. Main Runway R2 Draw-down. ST Baggage & Pier 1 and NT Voids Scope and Budget Move. Crew Reporting Update. Q5+1 Minor Projects Update. CIP Performance Pack. Projects Overview. Investment Performance Review - NT Forecourt.
23 January 2013 North Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
24 January 2013 South Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
30 January 2013 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
30 January 2013 North Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
31 January 2013 South Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
06 February 2013 Joint Steering Group Gatwick Business Plan Publication. Capital Programme Board Update: Main Runway Rehabilitation - R2 draw-down CCRs; Voids Project - Scope and Budget moves from the ST Baggage & Pier 1 and NT Voids CCRS; Q5 Capex Programme Spend Update. Crew Reporting Update. AOC Executive Update. Service Delivery Update. Charges Group Update.
06 February 2013 North Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
07 February 2013 South Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
08 February 2013 Service Quality Exclusions Group Monthly agreement of exclusions for the 6 week look ahead, Review of previous month exclusions and service performance. Review of pier service exceptions.
13 February 2013 North Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
14 February 2013 South Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
14 February 2013 Business Plan Event Business Plan to 2024 and 2nd Runway Update
14 February 2013 NT Capital Programme Consultation Introduction & Purpose of Consultation. NT Programme Overview. NT IDL and Security projects - Tollgate 2.
15 February 2013 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
20 February 2013 North Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
21 February 2013 South Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
21 February 2013 Capital Programme Board Check-in Trials - R2 Draw-down CCRS. Revisited Main Runway - R2 Draw-down CCRS. Flood Attenuation - Tollgate 4. Consolidated Security Gate - Tollgate 3. Delivery of 95% Pier Service (NT) - Tollgate 3. NT IDL (Project 2) - Revisited Tollgate 3. ST Security & ST IDL (Phase 1) - Budget Transfers CCRSs. NT Extension - Final Accounts R2 Draw-down CCRS. Crew Reporting Update. Q5+1 Minor Projects Update. CIP Performance Pack. Projects Overview.
21 February 2013 ST Capital Programme Consultation Introduction and Purpose of Consultation. ST Programme Overview: ST Development Plan; ST Programme (projects in programme scope)
27 February 2013 North Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
28 February 2013 South Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
28 February 2013 Airfield Capital Programme Consultation Introduction and Purpose of Consultation. Airfield Programme Overview. NT Capital Programme Consultation Continuation: NT IDL & Security Projects - Tollgate 2
28 February 2013 2nd Runway Consultation Introduction and Purpose of Consultation. Airports Commission Work Programme. GAL Work Programme.
06 March 2013 Joint Steering Group Q5+1 Update: ACC Projects Endorsement Update (Version 9); ST IDL Phase 2 Trigger Definition. Capital Programme Board Update: Revisited Main Runway Rehabilitation - R2 Draw-down CCRS; Consolidated Security Gate - Tollgate 3; Flood Attenuation - Tollgate 4; NT IDL (Project 2) - Revisited Tollgate 3; ST Security & ST IDL (Phase 1) - R2 Draw-down CCRS; NT Extension - Final Accounts R2 Draw-down CCRS; Delivery of 95% Pier Service (NT) - Tollgate 3. Crew Reporting Update. Beyond Q5 Capital Programmes and 2nd Runway Consultation Update: NT IDL - Tollgate 2; NT Security - Tollgate 2; ST Ceilings - pre-Tollgate 2. AOC Executive Update. Service Delivery Update.
06 March 2013 North Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
07 March 2013 South Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E F G H
102
date Meeting discussion / items on the Agenda
08 March 2013 Service Quality Exclusions Group Monthly agreement of exclusions for the 6 week look ahead, Review of previous month exclusions and service performance. Review of pier service exceptions.
13 March 2013 North Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
13 March 2013 NT Capital Programme Consultation Acceptance of Transcript and Actions Log. Progress Update on NT IDL and Security Projects. Revisit of NT Development Plan Options. Look Ahead for Next Meeting. easyJet Willingness to Pay Research.
14 March 2013 South Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
20 March 2013 Capital Programme Board Domestic Arrivals (Phase 1) - R2 Draw-down CCRS. Investment Performance Reviews - MSCP6; NT Interchange. Crew Reporting Update. Q5+1 Minor Projects Update including ST Toilets; Gatwick Connect. CIP Performance Pack. Projects Overview.
20 March 2013 Pier Service Working Group Overview of work completed to date. Next Steps. Terminal Occupancy Criteria. easyJet ST Consolidation - overview. easyjet NT Consolidation - overview. Stand Reconfiguration - update.
20 March 2013 North Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
22 March 2013 GAL/AOC Executive Key items for discussion (maximum of 5); GAL Service Metrics; Capital Project Update
22 March 2013 ST Capital Programme Consultation Acceptance of Transcript. Progress of Actions. ST Ceilings - breakdown of cost. Look Ahead for Next Meeting. ST Ceilings - Site Visit.
27 March 2013 North Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
28 March 2013 South Terminal Stakeholder Working Group Projects construction work impacts for safety, disruption over previous week, communication of planned work for following week and discussion of planned works for the following 5 weeks.
28 March 2013 Airfield Capital Programme Consultation Acceptance of Transcript. Review of Actions Log. Airfield Development Plan: Pier 6 Update; Stand Reconfiguration Works. NT IDL and Security Projects Economics Sheets. Look Ahead for Next Meeting. easyJet Willingness of Pay Research.
28 March 2013 2nd Runway Consultation Acceptance of Transcript. Actions from previous meeting. Review GAL Submissions of 15 March. Runway Options. Look Ahead for Next Meeting.
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HAppendix
E
103fAPPENDIX f - DEcIsIoN Log fRoM APRIL 2012 to MARch 2013
Issue forum Meeting Date Agree / Disagree
Reason/comment
1 Endorsement of ST Security IDL to progress through Tollgate 4 (Construction Decision) (CCRS LGW0074)
JSG 11 April 2012 Agree Change control record form signed-off
2 Endorsement of ST & NT UKBA Arrivals Zones to progress through Tollgate 4 (Construction Decision) (CCRS LGW0095)
JSG 11 April 2012 Disagree Airlines asked GAL to consider having an SQR for UKBA's performance linked to this project (see line 17 below)
3 Endorsement of ST Entrance Bridge Cladding to progress through Tollgate 4 (Construction Decision)
JSG 11 April 2012 Agree
4 Endorsement of Fire Strategy R2 draw-down of £3.6m to remove safety related risks (CCRS LGW0096)
JSG 11 April 2012 Agree Change control record form signed-off
5 Endorsement of NT Baggage Hall Access CCRS to transfer £872K into the NT Baggage Upgrade projects (CCRS LGW0097)
JSG 11 April 2012 Undecided Airlines wished to consider this with the wider NT Baggage project CCRSs (see line 18 below)
6 Endorsement of Q6 Capital Facilitation of £815K to fund the preparatory work for the Q6 capital plan (CCRS LGW0079)
JSG 11 April 2012 Disagree Further work required between GAL and ACC members before this could be endorsed (see line 64 below)
7 Endorsement of purchase of Snow Equipment including Konsin De-Icer Tanks (CCRS LGW0055)
JSG 11 April 2012 Disagree Konsin De-Icer tanks to be treated as separate from the snow equipment purchase and the airlines re-stated their request for the purchase to be linked to an SLA/SQR measure for estimated snow clearance times. Snow to be revisited at September JSG. (see line 86 below)
8 Endorsement that the ST Forecourt Trigger has been achieved JSG 11 April 2012 Agree Joint Letter to be sent to the CAA
9 Endorsement of ST Domestic Arrivals to progress through Tollgate 4 (Construction Decision) (CCRS LGW0100)
CPB 25 April 2012 Undecided Anticipated agreement to follow at JSG meeting but unable to provide recommendation at this time (see line13 below)
10 Endorsement of Pumping Station 18 to progress through Tollgate 2 (Brief Decision) (CCRS LGW0099)
CPB 25 April 2012 Agree
11 Endorsement of an R2 Draw-down of £725K for replacing cabling ducts for the approach lighting on the Main Runway Rehabilitation project (CCRS LGW0098)
CPB 25 April 2012 Agree
12 Endorsement of 9 CCRSs on NT Baggage for scope and AFC changes (CCRS LGW0084-92)
CPB 25 April 2012 Undecided Airlines confirmed that they needed no further information from GAL but were not in a position to progress prior to the May JSG (see line 16 below)
13 Endorsement of ST Domestic Arrivals to progress through Tollgate 4 (Construction Decision) (CCRS LGW0100)
JSG 09 May 2012 Agree Change Control Record Sheet signed-off
14 Endorsement of Pumping Station 18 to progress through Tollgate 2 (Brief Decision) (CCRS LGW0099)
JSG 09 May 2012 Agree Change Control Record Sheet signed-off
15 Endorsement of an R2 Draw-down of £725K for replacing cabling ducts for the approach lighting on the Main Runway Rehabilitation project (CCRS LGW0098)
JSG 09 May 2012 Disagree Airlines requested an explanation of the on-costs to be provided at the June CPB before coming back to the JSG (see line 21 below)
16 Endorsement of 9 CCRSs on NT Baggage for scope and AFC changes (CCRS LGW0084-92)
JSG 09 May 2012 Undecided Airlines asked for this to be deferred to the June CPB & JSG (see line 23 below)
17 Endorsement of ST & NT UKBA Arrivals Zones to progress through Tollgate 4 (Construction Decision) (CCRS LGW0095)
JSG 09 May 2012 Agree Airlines agreed only to Phase 1 of this project and requested that a separate CCRS was provided just for this phase for endorsement (see line 29 below)
18 Endorsement of NT Baggage Hall Access CCRS to transfer £872K into the NT Baggage Upgrade projects (CCRS LGW0097)
JSG 09 May 2012 Undecided Airlines asked for this to be deferred to the June JSG (see line 28 below)
19 As part of the Main Runway Rehabilitation project, downgrading of the runway lighting to Category 3 to Category 1 on 14 May with the use of the full ILS system
JSG 09 May 2012 Agree
20 Endorsement of ST Security R2 Draw-down of £2.1m for close-out of the project with contractors
CPB 23 May 2012 Disagree Airlines requested this was re-presented to the ACC prior to the June JSG (see line 25 below)
21 Endorsement of an R2 Draw-down of £725K for replacing cabling ducts for the approach lighting on the Main Runway Rehabilitation project (CCRS LGW0098)
CPB 23 May 2012 Agree Airlines asked for the on-costs explanation to be added to the CCRS for the JSG (see line 26 below)
22 Endorsement of A380 on Stand 125 to progress through Tollgate 4 (Construction Decision) (CCRS LGW0101)
CPB 23 May 2012 Disagree Airlines were informed that this would be presented at the June JSG and that GAL intends to continue with the project (see line 31 below)
23 Endorsement of 9 CCRSs on NT Baggage for scope and AFC changes (CCRS LGW0084-92)
CPB 23 May 2012 Undecided Airlines were still not in a position to give their view on this and it would go to the June JSG (see line 32 below)
24 Provision of a Joint GAL/ACC Submission to the CAA on the Q5+1 Trigger Projects including Liability and Trigger Definitions
JSG 13 June 2012 Agree Joint Letter to be sent to the CAA
25 Endorsement of ST Security R2 Draw-down of £2.1m for close-out of the project with contractors
JSG 13 June 2012 Agree Change Control Record Sheet signed-off
26 Endorsement of an R2 Draw-down of £725K for replacing cabling ducts for the approach lighting on the Main Runway Rehabilitation project (CCRS LGW0098)
JSG 13 June 2012 Agree Change Control Record Sheet signed-off
27 Endorsement of Crew Reporting to progress through Tollgate 4 (Construction Decision) (CCRS LGW0104)
JSG 13 June 2012 Agree Change Control Record Sheet signed-off
28 Endorsement of NT Baggage Hall Access CCRS to transfer £872K into the NT Baggage Upgrade projects (CCRS LGW0097)
JSG 13 June 2012 Agree Change Control Record Sheet signed-off
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HAppendix
E
104
Issue forum Meeting Date Agree / Disagree
Reason/comment
29 Endorsement of ST & NT UKBA Arrivals Zones Phase 1 to progress through Tollgate 4 (Construction Decision) (CCRS LGW0095a)
JSG 13 June 2012 Agree Change Control Record Sheet signed-off
30 Endorsement of the Service Matrix developed by the CEWG JSG 13 June 2012 Agree
31 Endorsement of A380 on Stand 125 to progress through Tollgate 4 (Construction Decision) (CCRS LGW0101)
JSG 13 June 2012 Disagree GAL informed the airlines that it would be continuing the project and continue consulting with airlines
32 Endorsement of 9 CCRSs on NT Baggage for scope and AFC changes (CCRS LGW0084-92)
JSG 13 June 2012 Undecided Airlines deferred to July JSG (see line 41 below)
33 Endorsement of ST Baggage and Pier 1 R2 Draw-down of £805K for additional scope (CCRS LGW0105)
CPB 20 June 2012 Undecided Airlines requested that they needed to investigate the circumstances of this request with easyJet but that it should be brought to the July JSG (see line 38 below)
34 Endorsement of Airfield Operations Building to progress through Tollgate 4 (Construction Decision)
CPB 20 June 2012 Agree
35 Endorsement of NT IDL Project 2 to progress through Tollgate 3 (Options Decision)
CPB 20 June 2012 Agree
36 Q5+1 Projects Endorsement- IT Infrastructure Platform Upgrade- CCTV replacement- IT Core infrastructure / Node Room remediation- Common bag drop phase 1- ST Statutory Accommodation
JSG 11 July 2012 Agree
37 Endorsement to ST Baggage and Pier 1 to progress through Tollgate 4 (Construction Decision) (CCRS LGW0108)
JSG 11 July 2012 Agree Airlines requested a letter regarding access to Concorde House which GAL provided and the Change Control Record Sheet was signed-off
38 Endorsement of ST Baggage and Pier 1 R2 Draw-down of £805K for additional scope (CCRS LGW0105)
JSG 11 July 2012 Agree Change Control Record Sheet signed-off
39 Endorsement of Airfield Operations Building to progress through Tollgate 4 (Construction Decision) (CCRS LGW0106)
JSG 11 July 2012 Disagree Airlines requested further information on the on-costs on the project (see line 53 below)
40 Endorsement of NT IDL Project 2 to progress through Tollgate 3 (Options Decision) (CCRS LGW0109)
JSG 11 July 2012 Agree Change Control Record Sheet signed-off
41 Endorsement of 9 CCRSs on NT Baggage for scope and AFC changes (CCRS LGW0084-92)
JSG 11 July 2012 Undecided Airlines asked for this to be deferred to the August meeting (see line 52 below)
42 Beyond Q5 Capital Projects to be progressed to Tollgate 3 (Options Decision)- NT Security- Borders (both NT and ST)- ST & NT Check-in upgrade and bag drop- NT Early bags store- NT Baggage reclaim
JSG 11 July 2012 Agree
43 Endorsement of Beyond Q5 Constructive Engagement Facilitator and Dispute Resolution Procedure
JSG 11 July 2012 Agree
44 Endorsement of ST IDL Reconfiguration Phase 2 to progress through Tollgate 3 (Options Decision) (CCRS LGW0112)
CPB 25 July 2012 Undecided Airlines asked for further information to be made available for the JSG meeting (see line 48 below)
45 Endorsement of NT Extension transfer of scope and funds from NT Baggage of £4.8m (CCRS LGW0110)
CPB 25 July 2012 Agree
46 Endorsement of NT Baggage Voids to progress through Tollgate A (CCRS LGW0107)
CPB 25 July 2012 Agree
47 Endorsement of Gatwick Stream Flood Attenuation to progress through Tollgate 3 (Options Decision) (CCRS LGW0111)
CPB 25 July 2012 Undecided Airlines asked for the business case to be amended for the JSG meeting (see line 51 below)
48 Endorsement of ST IDL Reconfiguration Phase 2 to progress through Tollgate 3 (Options Decision) (CCRS LGW0112)
JSG 08 August 2012 Agree Change Control Record Sheet signed-off
49 Endorsement of NT Extension transfer of scope and funds from NT Baggage of £4.8m (CCRS LGW0110)
JSG 08 August 2012 Agree Change Control Record Sheet signed-off
50 Endorsement of NT Baggage Voids to progress through Tollgate A (CCRS LGW0107)
JSG 08 August 2012 Agree Change Control Record Sheet signed-off
51 Endorsement of Gatwick Stream Flood Attenuation to progress through Tollgate 3 (Options Decision) (CCRS LGW0111)
JSG 08 August 2012 Agree Change Control Record Sheet signed-off
52 Endorsement of 9 CCRSs on NT Baggage for scope and AFC changes (CCRS LGW0084-92)
JSG 08 August 2012 Undecided Airlines asked for this to be deferred to the September meeting (see line 63 below)
53 Endorsement of Airfield Operations Building to progress through Tollgate 4 (Construction Decision) (CCRS LGW0106)
JSG 08 August 2012 Agree Change Control Record Sheet signed-off
54 Beyond Q5 Capital Projects to be progressed to Tollgate 3- NT IDL Reconfiguration- ST IDL Capacity- Passenger Service Improvements through IT- Runway Safeguarding- ST IDL Reconfiguration Phases 3 & 4- PTI and Surface Access
JSG 08 August 2012 Agree
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HAppendix
E
105
Issue forum Meeting Date Agree / Disagree
Reason/comment
55 Endorsement of ST Security - Scope & Budget Transfer to ST Landside Project (CCRS LGW0114+0115)
CPB 22 August 2012 Undecided See line 59 below
56 Endorsement of ST & NT Border Force Arrivals Zones Phase 2 to progress through Tollgate 3 (Options Decision)
CPB 22 August 2012 Undecided See line 62 below
57 Q5+1 Projects Endorsement• Airfield Peak Capacity Expansion (ACDM 55)• Passenger Information Display Screens • NT Domestic Arrivals Toilets
JSG 05 September 2012
Agreed
58 Total Trigger Liability for Q5+1 fixed at £4.4m JSG 05 September 2012
Agreed
59 Endorsement of ST Security - Scope & Budget Transfer to ST Landside Project (CCRS LGW0114+0115)
JSG 05 September 2012
Agreed Change Control Record Sheets signed-off
60 Beyond Q5 Capital Projects to be progressed to Tollgate 3• CIP Arrivals and Departures Lounges• ST Baggage & Pier 1 carryover
JSG 05 September 2012
Agreed
61 JSG Chairs delegated authority to Q6 Working Group to finalise the joint submission for the CAA's Mid-Term Review
JSG 05 September 2012
Agreed Submission sent to CAA 15 September
62 Endorsement of ST & NT Border Force Arrivals Zones Phase 2 to progress through Tollgate 3 (Options Decision) (CCRS LGW0118)
JSG 05 September 2012
Disagreed Discussion continued at Q6 Working Group on 6 September (see line 72 below)
63 Endorsement of 9 CCRSs on NT Baggage for scope and AFC changes (CCRS LGW0084-92)
JSG 05 September 2012
Disagreed Update on whether the project is included in the CAA's End of Q5 Review to be provided at October JSG (see line 71 below)
64 Endorsement of Beyond Q5 spend of £5.5m to develop projects to progress to Tollgate 3 (Options Decision) (CCRS LGW0119)
JSG 05 September 2012
Disagreed GAL & ACC discussions to continue
65 Endorsement of NT Foul Main R2 Draw-down of £580k for scope change (CCRS LGW0122)
CPB 19 September 2012
Agreed Subject to provision of further information for the JSG (see line 68 below)
66 Endorsement of the Baggage Reconciliation System (BRS) to progress to Tollgate 3 (Options Decision)
CPB 19 September 2012
Undecided Further information was requested and this is also dependent of the outcome of the SSB/AOC tender process (see line 70 below)
67 Q5+1 Projects Endorsement• CAPI Extension• Mobile website re-design• Fire training facilities• PA Automation• Disruption suite
JSG 10 October 2012
Agreed
68 Endorsement of NT Foul Main R2 Draw-down of £580k for scope change (CCRS LGW0122)
JSG 10 October 2012
Agreed Change Control Record Sheet signed-off
69 Beyond Q5 Capital Projects to be progressed to Tollgate 3• Airfield, Facilities, Commercial Asset Stewardship programmes & projects• Compliance and Risk programme• Digital media• Delivering 95% pier service (NT)• Consolidated Car Rental & Motor Transport• Hangar facilities
JSG 10 October 2012
Agreed
70 Endorsement of the Baggage Reconciliation System (BRS) to progress to Tollgate 3 (Options Decision)
JSG 10 October 2012
Undecided This is subject to the outcome of the AOC's tender process which had not yet concluded
71 Endorsement of 9 CCRSs on NT Baggage for scope and AFC changes (CCRS LGW0084-92)
JSG 10 October 2012
Undecided This project was now subject to the CAA's End of Q5 Review and the ACC wished to wait for the outcome of this review before making any decision
72 Endorsement of ST & NT Border Force Arrivals Zones Phase 2 to progress through Tollgate 3 (Options Decision) (CCRS LGW0118)
JSG 10 October 2012
Undecided ACC requested meeting to be arranged with UKBF which took place on 17 October (see line 76 below)
73 Endorsement of Beyond Q5 spend of £5.5m to develop projects to progress to Tollgate 3 (Options Decision) (CCRS LGW0119)
JSG 10 October 2012
Undecided ACC to put forward their own proposal
74 Endorsement of Pier 5 R2 Draw-down of £2,237K for scope and budget changes (CCRS LGW0113)
CPB 24 October 2012
Agreed
75 Endorsement of ACDM 55 Phase 2 to progress to Tollgate 4 (Construction Decision) (CCRS LGW0123)
CPB 24 October 2012
Agreed
76 Endorsement of ST and NT UKBF Phase 2 Arrivals to progress to Tollgate 4 (Construction Decision) (CCRS LGW0121)
CPB 24 October 2012
Undecided ACC to consider on upcoming conference call (see line 79 below)
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HAppendix
E
106
Issue forum Meeting Date Agree / Disagree
Reason/comment
77 Q5+1 Projects Endorsement• Passenger Identification & Verification• IT Operations Centre• Building & Civils• Minor Works Engineering• Minor Works Building & Fabric• Minor Works Security• Increase in common user bag drop• Decrease in lighting columns
JSG 07 November 2012
Agreed
78 Endorsement of ACDM 55 Phase 2 to progress to Tollgate 4 (Construction Decision) (CCRS LGW0123)
JSG 07 November 2012
Agreed Change Control Record Sheet signed-off
79 Endorsement of ST and NT UKBF Phase 2 Arrivals to progress to Tollgate 4 (Construction Decision) (CCRS LGW0121)
JSG 07 November 2012
Disagreed
80 Endorsement of Pier 5 R2 Draw-down of £2,237K for scope and budget changes (CCRS LGW0113)
JSG 07 November 2012
Undecided ACC wished to have further time to consider and would provide their decision in writing (see line 84 below)
81 Endorsement of ST IDL Reconfiguration Phase 2 to progress through Tollgate 4 (Construction Decision) (CCRS LGW0124)
JSG 05 December 2012
Agreed Change Control Record Sheet signed-off
82 Endorsement of all the recommendations in the CEWG report JSG 05 December 2012
Agreed
83 Endorsement of NT Staff Canteen as a Q5+1 Project JSG 05 December 2012
Disagreed
84 Endorsement of Pier 5 R2 Draw-down of £2,237K for scope and budget changes (CCRS LGW0113)
JSG 05 December 2012
Undecided ACC were waiting further cost information before being in a position to make a decision (see line 88 below)
85 Endorsement of Consolidated Security Gate to progress through Tollgate 2 (Brief Decision) (CCRS LGW0125)
CPB 19 December 2012
Undecided ACC were only able to partially support the project and requested further information on the supporting analysis (see line 87 below)
86 Snow Disruption SLA JSG 09 January 2013
Undecided ACC wished to look at an SLA currently being used at a Norwegian Airport before coming back to GAL on its proposal
87 Endorsement of Consolidated Security Gate to progress through Tollgate 2 (Brief Decision) (CCRS LGW0125)
JSG 09 January 2013
Agree Change Control Record Sheet signed-off
88 Endorsement of Pier 5 R2 Draw-down of £1,977K for scope and budget changes (CCRS LGW0113A)
JSG 09 January 2013
Agree Change Control Record Sheet signed-off
89 Endorsement of all the recommendations in the CEWG report JSG 09 January 2013
Agree
90 Endorsement of Main Runway Rehabilitation R2 Draw-down of £4,168K for budget increase (CCRS LGW0128)
CPB 23 January 2013
Undecided To be reviewed by ACC prior to February JSG meeting
91 Endorsement of ST Baggage & Pier 1 and NT Voids Scope and Budget moves to a consolidated Voids Project (CCRS LGW0126 +LGW0127)
CPB 23 January 2013
Undecided To be reviewed by ACC prior to February JSG meeting
92 Endorsement of Main Runway Rehabilitation R2 Draw-down of £4,168K for budget increase (CCRS LGW0128)
JSG 06 February 2013
Undecided ACC asked for a break-down of the funds requested to go back to CPB before coming to the following JSG (see line 95 below)
93 Endorsement of ST Baggage & Pier 1 and NT Voids Scope and Budget moves to a consolidated Voids Project (CCRS LGW0126+7)
JSG 06 February 2013
Agreed Change Control Record Sheets signed-off
94 Recommendation to ACC to Endorse the Check-in Bag-drop Trials R2 Draw-down of £449K (CCRS LGW0129)
CPB 21 February 2013
Agreed
95 Recommendation to ACC to Endorse the Main Runway Rehabilitation Budget Increase R2 Draw-down of £4,168K (CCRS LGW0128)
CPB 21 February 2013
Undecided To be reviewed by ACC prior to March JSG meeting (see line 105 below)
96 Recommendation to ACC to Endorse the Flood Attenuation to progress through Tollgate 4 (CCRS LGW0132)
CPB 21 February 2013
Agreed
97 Recommendation to ACC to Endorse the Consolidated Security Gate to progress through Tollgate 3 (CCRS LGW0133)
CPB 21 February 2013
Agreed
98 Recommendation to ACC to Endorse the Delivery of 95% Pier Service (North Terminal) to progress through Tollgate 3 (CCRS LGW0131)
CPB 21 February 2013
Disagreed ACC asked for this decision to be postponed until work on the Pier 2, Pier 3 and NT Piers were at the same level of detail (see line 112 below)
99 Recommendation to ACC to Endorse NT IDL (Project 2) to progress through a Revisited Tollgate 3 (CCRS LGW0134)
CPB 21 February 2013
Agreed
100 Recommendation to ACC to Endorse the ST Security Final Accounts R2 Draw-down of £1.31m (CCRS LGW0135)
CPB 21 February 2013
Agreed Following confirmation by Jamie Hobbs this figure was reduced to £1.1m for JSG endorsement
101 Recommendation to ACC to Endorse the ST IDL (Phase 2) Final Accounts confirmation of AFC from £21.7m to £20.518m (CCRS LGW0134)
CPB 21 February 2013
Withdrawn GAL withdrew the request to amend funding for this phase of the project pending investigation of a potential R2 claim
102 Recommendation to ACC to Endorse the NT Extension Final Accounts R2 Draw-down of £4.42m (CCRS LGW0136)
CPB 21 February 2013
Agreed
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F G HAppendix
E
107
Issue forum Meeting Date Agree / Disagree
Reason/comment
103 Endorsement of Q5+1 Minor Projects FEGP and Sub-Stations replacement
JSG 06 March 2013 Agreed
104 Endorsement of the Q5+1 ST IDL Phase 2 Trigger Definition JSG 06 March 2013 Undecided ACC required further time to consider
105 Endorsement of the Main Runway Rehabilitation Budget Increase R2 Draw-down of £4,168K (CCRS LGW0128)
JSG 06 March 2013 Postponed ACC agreed to wait for final accounting on this project rather than endorsing the budget increase at this time
106 Endorsement of the Consolidated Security Gate to progress through Tollgate 3 (CCRS LGW0133)
JSG 06 March 2013 Undecided ACC requested this to be reviewed by the AOC at their March meeting and then come back to April JSG
107 Endorsement of the Flood Attenuation to progress through Tollgate 4 (CCRS LGW0132)
JSG 06 March 2013 Agreed Change Control Record Sheet signed-off
108 Endorsement of the NT IDL (Project 2) to progress through Revisited Tollgate 3 (CCRS LGW0134)
JSG 06 March 2013 Agreed Change Control Record Sheet signed-off
109 Endorsement of the Check-in Bag-drop Trials R2 Draw-down of £449K (CCRS LGW0129)
JSG 06 March 2013 Agreed Change Control Record Sheet signed-off
110 Endorsement of ST Security & ST IDL (Phase 2) R2 Draw-down of £1.1m for Final Accounting (CCRS LGW0135a)
JSG 06 March 2013 Agreed Change Control Record Sheet signed-off
111 Endorsement of the NT Extension Final Accounts R2 Draw-down of £4.42m (CCRS LGW0136)
JSG 06 March 2013 Agreed Change Control Record Sheet signed-off
112 Endorsement of the Delivery of 95% Pier Service (North Terminal) to progress through Tollgate 3 (CCRS LGW0131)
JSG 06 March 2013 Agreed ACC caveated their endorsement requesting that GAL explore other solutions for providing 95% Pier Service in the North Terminal at the same speed as progressing this option. Change Control Record Sheet signed-off
113 Endorsement of the BQ5 NT IDL to progress through Tollgate 2 (CCRS LGW0137)
JSG 06 March 2013 Undecided ACC required further time to consider
114 Endorsement of the BQ5 NT Security to progress through Tollgate 2 (CCRS LGW0138)
JSG 06 March 2013 Undecided ACC required further time to consider
115 Recommendation to ACC to Endorse the Consolidated Security Gate to progress through Tollgate 3 (CCRS LGW0133)
CPB 20 March 2013 Agreed
116 Recommendation to ACC to Endorse the Domestic Arrivals (Phase 1) R2 draw-down of £1.597m for unforeseen scope (CCRS LGW0139)
CPB 20 March 2013 Undecided To be reviewed by ACC prior to April JSG meeting
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E HAppendix
E F
GAppendix G - Annex G
G. [GATWICK’S] AGREEMENT ON ENHANCED INFORMATION DISCLOSURE AND CONSULTATION AT HEATHROW AND GATWICK AIRPORTS - UPDATE FOR Q5G.1 [Gatwick] recognises that consultation with airlines on its proposals for the development of the airport is critical to ensure its plans are both fully understood by airlines and informed by their knowledge and requirements. To facilitate this, [Gatwick] proposes to provide airlines with the following information, detailed below as part of the constructive engagement process. This proposal is intended to address consultation on the delivery of the plan in Q5 as well as issues that will need to be discussed in preparation for future price control periods. To ensure effective consultation this proposal also outlines the requirements for the consultative process, including a high level view on the remit of airport-airline consultative bodies established for this purpose.
G.2 Ultimately, decisions on capital expenditure are fundamental to [Gatwick’s] business and as such [Gatwick] is accountable for the final decision with regard to how capital expenditure monies are deployed. Equally, the CAA has stated that it will take account of this constructive engagement process when establishing the regulatory settlement for a period, basing decisions on agreement wherever possible.
G.3 [Gatwick] anticipates that through the provision of the information detailed in this paper and with the constructive engagement of all parties in the process, the level of consultation supporting the airport’s development proposals will be enhanced. This should result in a greater understanding of the drivers for investment, the cost of the plan and the outputs that will be delivered, in terms of infrastructure and benefits to airlines and passengers as well as the impact on user charges.
G.4 There will be three key aspects to the consultation on airport development plans:
1. The Airport Master Plan and long term land use plan;
2. The Capital Investment Plan (CIP);
3. Consultation on individual projects.
G.5 This consultation will take place within and be aligned to the broader context of consultation, typically on the elements covered by the constructive engagement process used to inform the Q5 regulatory review.
AIRPORT MASTER PLAN AND LONG-TERM LAND USE PLAN G.6 Each airport will produce and maintain a Master Plan document in consultation with airlines. The timing of this document depends partly on Government airport policy consultations/decisions and on the need to keep the overall vision for the airport up to date. Updates will also be necessary to deal with strategic aspects (such as scope and timing) of major developments left open in a previous version. Consultations on the airport’s development strategy and also on the necessity and scope of specific projects need to proceed in the confidence that the proposals are aligned with the overall airport Masterplan. It is envisaged that the annual CIP document will be supported with a long-term land use plan, highlighting the infrastructure to be delivered across the airport campus by the investment proposals. The annual CIP document would also provide updated information on the long-term land use plan (at a level of granularity that permits informed discussion) which is likely to be relevant to airlines’ consideration of the CIP. The long term land use plan will provide a view on how best to use the land well into the future, and from which the incremental infrastructure plans (next 5 to 10 years), both above and below the surface, can be considered and shown to align with the long term land use plan within the context of the current Masterplan.
G.7 Consultation on the long-term land use plan should also incorporate information on asset disposals. The airport will consult airlines before disposing of any land or buildings from the Regulated Airport Base, whether through sale, partial sale, long lease or joint venture, including disposals from the respective airport company (Heathrow Airport Limited (HAL) or Gatwick Airport Limited (GAL)) to other entities within the
108
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E HAppendix
E F
BAA group. Consultation information will include the timing of the proposed disposal, potential impact on both current airport operations and on future airport development, and measures taken to protect future airport development (e.g. proposed buy back options and their terms). The airport will also inform users and the CAA on any subsequent disposal of assets which were formerly within the Regulated Asset Base and which had been transferred out of the HAL or GAL Regulated Asset Base during the Q5 price control period to another entity within the BAA group. Where there may be reasonable doubt as to whether or not a particular asset does or does not fall within the Regulated Asset Base, the airport will consult with airlines on its disposal in advance.
CAPITAL INvESTMENT PLAN (CIP)G.8 Consultation will require the provision by [Gatwick] of information within a capital planning document covering a period of at least 10 years. This document will provide information to airlines on development plans for each airport and will be a key document around which airline-airport consultation will take place. It is recognized that some elements of the data may need to be covered by a confidentiality agreement (and/or disclosed in a restricted manner) to ensure that consultation does not prejudice commercial interests.
G.9 The purpose of the document will be to allow the airport to consult airlines on the following matters relating both to Q5 and to future price control periods:
1 The principal business drivers behind the airport’s development strategy: Including assumptions made by [Gatwick] regarding the future operating environment of the airports including desired levels of service, those constraints faced by the airports that are a material influence on the plans and jointly developed benchmarks of external performance.
2 The forecast demand for airport outputs for the duration of the plan: Consulting airlines on the disaggregated forecast levels of demand for airport capacities and services, under one or more future scenarios developed following consultation with airlines, including scenarios that may be recommended formally by airlines at the Joint Steering Group (JSG) at Gatwick / Joint Steering Team (JST) at Heathrow, together with the principal factors that are expected to drive different categories of the demand. Use of different forecast scenarios may be particularly important where there is some uncertainty or risk about future demand and where it is necessary to test the robustness of the plan against uncertain outcomes.
3 Options for the development of the airport: Consulting with airlines on the high level options for the development of the airport, including details of the cost and output trade-offs involved in each option, and the relative impact on user charges and, where possible, on future airline costs. This user charge impact assessment should be conducted on a per passenger basis, and employ high level assumptions on incremental passenger numbers, costs and income associated with alternate options. Assumptions employed should be clearly stated, with reasons, so that airlines can understand the inherent risks and sensitivities. This should include similar analyses of reasonable options formally requested by airlines at the JSG/JST.
Consultation with airlines will also be required to take account of their views on current and future operational processes, requirements and airline moves. This may involve discussions about future airline plans for check-in, fleet, baggage etc.
The airport and airlines need to respect the agreed process and timescales when making their contributions. Where airlines cannot provide inputs in time, the airport may need to make informed assumptions which can be adjusted through the stakeholder project boards or the JSG/JST if necessary. It may also be necessary to revise assumptions later, but the aim should be to ensure that delays caused by airlines’ limited resource do not put at risk [Gatwick’s] ability to deliver the investment programme or specific projects or the functional needs of airlines.
109
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E HAppendix
E F
4 The capacities that the airport intends to provide: Consulting with airlines on the facilities the airport intends to supply, and the extent to which the different parts of the infrastructure (passenger areas, stands, baggage belts, runways and airfield facilities etc.) will meet demand forecasts under the different scenarios. This will provide users with a forecast of the extent to which the airport will be able to meet expected demand for outputs, and the implications of this for the quality of service that airlines receive at the airports. This should also quantify other benefits to be delivered by the plan. As with consultation on options for airport development, the discussion on specific capacities to be provided should also encompass airlines’ views on current and future operational processes, requirements and airline moves. This may involve discussions about airlines’ future plans for check-in, fleet, baggage etc.
5 The cost of the capital investment plan: Giving airlines an overall picture of the estimated total cost of the plan and pricing implications (informed, where appropriate, by the price control formula imposed by the CAA, and any long term pricing policies laid out by the CAA). This should state what major assumptions have been made, including timing of key projects and the expected levels of any operational disruption. Consultation on the total cost of the investment plan for future price control periods will also encompass consultation on the appropriate level of risk that should be incorporated into the cost of the programme. This will be informed by the future scenarios work and will be required before the capital investment programme for any future price control period is finalised.
6 Cost estimates and efficiencies of individual projects: Providing airlines with information, to an appropriate level of detail, on total capital expenditure and the anticipated incremental impact upon the operating costs of both [Gatwick] and the airline community. The amount of cost detail will be related to the stage of the development process. For those projects that have reached a high level of definition, specific cost estimates and indications of benefits will be expected. For projects envisaged in the longer term more general capital cost provisions may be appropriate and, if so, this should be stated. Where costs are shown for specific projects these should be broken down into base construction costs, risk allowances, on-costs and any other provisions such as site-specific costs. Information on anticipated asset lives associated with the development proposal should also be included. The costs for individual projects should be accompanied by an explanation of any positive or negative cost comparison with similar past projects. Specific data, including details of alternatives considered, should be provided. This information may be given in individual project consultations, rather than in the overall plan. Some information may need to be provided in confidence to individual occupiers of projects.
7 The outputs that are expected from individual projects: This should be both in terms of infrastructure that will be provided/replaced and the benefits that will be realized in terms of increased capacity, improved service levels, statutory compliance etc. The outputs should be quantified and provided on an incremental basis at a level of detail appropriate to the stage of the project. For any project, it should be clear how the benefits justify the costs: information should, therefore, be shared by the airport operator, as provider of the facility, and by those that operate the facility to enable users to assess the relative financial and operational benefits of the proposed development.
G.10 [Gatwick] will share with the appropriate airlines and/or or their representative bodies the commercial revenues it anticipates the investment will generate, except where [Gatwick] considers that disclosure of the information could jeopardise either its, or a third party’s, commercial interests. It is recognised by all parties that this may require a limit on the number of consultees and that confidentiality agreements (or other restrictions) may be needed to ensure the security of the information. [Gatwick] will make best endeavours to find practical means by which information can be both shared appropriately as necessary and given adequate protection from wider release, where this may be contrary to [Gatwick’s] or other parties’ commercial interests. There may be cases where [Gatwick] does not consider it appropriate to release this information even with the above safeguards and in these instances the airport will explain why disclosure is not possible.
110
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E HAppendix
E F
G.11 Where [Gatwick] considers that its commercial or operational interests will not be compromised, it will provide information on the relative impact upon operating costs resulting from the development.
CONSULTATION ON INDIvIDUAL PROjECTS G.12 Consultation will concentrate on the delivery of key projects or programmes of investment. The projects/programmes that will be subject to individual consultation will be agreed by stakeholder programme boards or via the JSG/JST. These will, as a minimum, be those projects with triggers attached and should be selected after consideration has been given as to how best to utilise airline and airport resource to facilitate this consultation without compromising the delivery of the overall plan. In addition to consultation on those projects agreed at the outset via Programme Boards or JSG/JST, [Gatwick] will try to accommodate all reasonable requests made by airlines for information/consultation about the progress of individual projects. These requests should be made via the relevant programme board. If agreement cannot be reached through this forum, the matter may be raised at JSG/JST.
G.13 It is envisaged that this consultation will be structured to support the key decision points in [Gatwick’s] Gateway process. For those key projects subject to individual consultation, [Gatwick] will ensure that airlines are consulted in a timely fashion at the following stages: (i) prior to [Gatwick] moving the project from brief description to options development, (ii) prior to option decision, and (iii) prior to construction design. [Gatwick] expects that the airlines involved in this process will make best endeavours to ensure that their inputs to such consultation are timely and do not delay the overall timeliness of programme and project delivery. If airlines do not participate when invited and subsequently try to hold up or reject the project proposals, [Gatwick] may need to proceed (and document the reasons why) without airline sign-off, in order to protect delivery for the wider user benefit.
G.14 Consultation on those selected projects will encompass the progression of the design and delivery of the project and best endeavours should be made to keep to the master delivery programme agreed at the outset of a project. Consultation should also focus on the utilisation of the risk allowance factored into the project cost. [Gatwick] will provide reports to show how risk money has been used and airlines will be consulted in advance of any significant use of risk monies.
Change Control
G.15 The CIP acts as a basis for consultation only and does not represent a mandatory investment programme.
G.16 The plan produced at any one time will be subject to change as the external environment alters, as project information become more detailed or as operational issues become apparent. Best endeavours should be made however to stick to the plan and changes should be proportionate, and the rationale for significant changes should be discussed with airlines before decisions are taken. These changes need to be made transparently and may involve difficult choices. All parties need to recognise that changes to the plan are inevitable and prioritisation of the plan will be ongoing within a fixed level of expenditure within the quinquennium. Where significant disagreements arise reasonable efforts should be undertaken by all parties to resolve disputes. Depending on the significance of the matter in dispute this may involve the use of the Dispute Resolution Process established for Q4.
G.17 An important part of each CIP document will be to provide airlines with an account of how the plan has changed from both previous versions and the plan that was anticipated in the Q5 price control. It should also provide an explanation for the change, whether to individual projects or at a higher level. It is not intended that the airport should be required to consult in advance about minor modifications to the plan unless they have significant effects; however airlines should be consulted before decisions are taken in relation to significant changes. In instances where [Gatwick] feels it is necessary to make significant changes to the plan, even when there is strong opposition from the airline community as a whole, [Gatwick] will commit to providing detailed reasons for its decision.
111
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E HAppendix
E F
G.18 In addition to providing airlines with transparency on changes to projections of future investment, it will also be necessary to review the out-turn performance of completed projects against the outputs an-ticipated in previous plans. Project evaluation should highlight performance in terms of cost, infrastructure delivered and benefits realised.
THE CONSULTATION PROCESSG.19 The Capital Investment Plan should form the basis of an effective consultation process, designed to provide airport facilities to best meet the current and future needs of airlines. Within this process, [Gatwick] should ensure that the material stated above is provided to, and consulted with, all major airlines at the individual airports. As well as publishing an annual document containing this information, each airport and its airlines are expected to establish the appropriate consultative bodies to facilitate this process.
G.20 Proposals from [Gatwick] for the consultative structure to be applied at Heathrow and Gatwick have been developed and are attached as annexes to this paper.
G.21These consultative bodies should agree membership and term s of reference supporting a structure of consultation that ensures a logical sequence of information flow is followed in order for the linkages be-tween the different information requirements stated above to be understood.
G.22 An important part of the work of these consultative bodies will be to track progress against the plan, to review implementation issues such as airline moves, and to act as a consultative forum for any proposed changes to the plan, for example changes to the scope, timing, costs or benefits of a project. These bodies should also provide the forum to discuss and agree any changes to the triggers identified for the Q5 price control period. Beyond the current price control period these bodies should also provide the consultative platform to agree future ‘trigger’ projects and the detailed definition of the associated milestones, which will be used to adjudicate whether or not the trigger has been successfully met.
G.23 Consultation should encompass the exchange of information and subsequent discussion between [Gatwick] and airlines with the objective of achieving agreement within an appropriate timescale to enable the successful delivery of the plan. A project plan will be developed by [Gatwick] which will show reason-able timescales for consultation commensurate with project complexity. The plan will show the timing of key decisions needed to maintain project programme in line with the CIP. All parties will endeavour to meet this timescale. However, it is recognised that agreement may not always be achieved in the time available to progress the investments. With this in mind it will be the responsibility of these bodies on a yearly basis to provide an agreed record of the agreements reached and those areas where there has been disagreement. This record of agreement/disagreement should also highlight the process undertaken to attempt to resolve any disputes.
112
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E HAppendix
E F
113HAppendix H - GAtwick’s updAted product MAtrix
product MAtrixsurface Access
core premium Business Assistance Family1.1 Service offer that encourage
the use of public transport modes
1.1 Dedicated chauffer / limo drop off area
1.1 Priority parking areas (fast connection)
1.1 Dedicated drop off area
1.1 Dedicated parking
1.2 No road traffic queues on airport
1.2 Premium and valet parking
1.2 Maximum wait 5 minutes
1.2 Accessible routes into Terminals
1.3 Real time transport network and service information
1.3 Kerb side lounge with concierge(Heated & dry)
1.3 Child friendly concierge service
1.4 Bag drop valet parking facility 1.4 Mulitple pick up points at all areas eg: Bus, Coach, Rail
1.5 Fit for purpose smoking facilities
1.6 Contemporary design for external areas
1.7 Clear routing for pax from / to onward travel
1.8 Accessible drop-off areas to match demand
1.9 Sufficient public car park capacity to meet demand for on-airport parking
check in concourse
2.1 Maximum 10 minute queue 2.1 No queue 2.1 Business segregated check-in
2.1 Accessible check in with flexible hours
2.1 Dedicated area for families
2.2 Intuitive flow through design 2.2 Dedicated area, aesthetically differentiated
2.2 System for pre-order in flight products
2.2 Check in available at earliest point in journey to get rid of bags and not just for those using PRM service
2.2 Space = IATA A
2.3 Space = not less than IATA C (at peak)
2.3 Space = IATA A 2.3 Technology for “swipe” check-in
2.3 Distractions for children
2.4 Well lit and clutter free environment
2.4 Kerb side check-in & bag drop
2.4 Off site bag drop
2.5 Remote check-in (passenger acceptance)
2.5 Minimal travel distances
2.6 Common use areas for bag tag & drop
2.6 Off site bag drop
2.7 Anytime check-in 2.7 Premium check-in lounge
2.8 Segregated group check-in 2.8 Premium PRM pick up service from home
2.9 Any bag to any chute
2.10 Staff and mobile technology to proactively assist passengers
2.11 Display of check-in location and queue (via smart phone app)
2.12 Display of security queue (visual display screens & via smart phone app)
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E HAppendix
E F
114
security core premium Business Assistance Family
3.1 Maximum 10 minute queue 3.1 No queue 3.1 Maximum queue 5 minutes
3.1 Maximum 10 minute queue
3.1 Dedicated lanes (not with PRM)
3.2 Space = not less than IATA C 3.2 Dedicated area with personal service
3.2 Dedicated lane with efficient service
3.2 Dedicated lanes (not with families)
3.2 Space = IATA A
3.3 Friendly, helpful and efficient staff
3.3 Space = IATA A 3.3 Loyalty based segregation
3.3 Privacy Cubicles 3.3 Cheerful aesthetics (visuals etc.)
3.4 Effective multilingual comms 3.4 Shoe Scanners 3.4 Shoe Scanners 3.4 DDA compliant seating for recomposure
3.4 Helpful staff
3.5 Eliminate clothing removal 3.5 AMD “friendly process”
3.5 Shoe Scanners
3.6 Mobile technology for boarding passes
3.6 Shoe Scanners
3.7 Space and seating for recomposure
3.8 Display of security queue (visual display screens & via smart phone app)
idL 4.1 Segregated / quiet zones 4.1 Direct routes through to lounges
4.1 Business centre facilities
4.1 Reception points close to security exit
4.1 Family areas (kids and teens)
4.2 Airside smoking areas for passengers
4.2 Personal shopping / retail pods
4.2 Quiet areas for business travellers
4.2 Seating with real time information
4.2 Family F&B offers
4.3 Push info to passengers 4.3 Segregated Premium lounges
4.3 Close to toilet facilities
4.3 Leisure lounges
4.4 Personalised call to gate (via SMS & smart phone app)
4.4 Exclusive / luxury retail
4.4 Access to F&B and shops
4.4 Entertainment
4.5 FIDS with departure gate specific distance / times & flight status
4.5 Massage & relaxation facilities
4.5 Minimal level changes
4.5 Teen Music Lounges (iTunes)
4.6 Comfortable seating / social areas
4.6 Showers 4.6 DDA compliant seating in F&B outlets
4.7 Airfield views (outdoor or indoor)
4.8 Retail to suit whole schedule (late night)
4.9 Space = minimum IATA C / commercial benchmark
4.10 Gateway / Portal to distinguish pier entry points
4.11 Uncluttered structured retail layout
4.12 Efficient VAT refund service
piers 5.1 95% Pier Service 5.1 Separate passenger access
5.1 Gate room business facilities
5.1 Toilet provision at recommended frequency
5.1 Experiential activities in gate rooms
5.2 “Clopen” Flexible gate rooms
5.2 Priority boarding 5.2 Changing areas with adult bed facilities
5.2 Strollers at aircraft side on inbound flights
5.3 Minimum gate room dwell time
5.3 Segregated seating in the gate room
5.3 Lifts for all vertical movements
5.4 Comfortable gate room seating (customer group)
5.4 Minimal distance to gate
5.5 Airline consolidated on piers / gates
5.5 Resting points
5.6 Vertical segregation of passengers in piers
5.6 Facilities for Guide Dogs
5.7 Lifts close to stands (for w/chairs etc.)
5.8 Automate boarding & displays for aircraft status
5.9 Space = not less than IATA C
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E HAppendix
E F
115
transfers core premium Business Assistance Family
6.1 Airside transfer facilities (domestic & international)
6.2 Space = not less than IATA C
6.3 Visual display for “next service” real time information
6.4 Call facility for on demand off peak service
Arrivals Border Zones
7.1 Max Q = 10 mins EU Non-EU = 20 mins
7.1 No queue 7.1 Maximum 5 minute queue
7.1 Maximum 10 minute queue
7.1 Maximum 10 minute queue
7.2 Space = not less than IATA C 7.2 Space = IATA A 7.2 Registered traveller programme
7.2 Dedicated lane 7.2 Dedicated lane
7.3 A “Warm welcome to Gatwick” & UK
7.3 Dedicated lanes 7.3 Segregated lanes
7.4 Display of border queue (visual display screens & via smart phone app)
7.4 Arrival lounge / facilities and/or seating
7.5 Registered traveller programme
reclaim 8.1 Onward travel tickets / information
8.1 Meet & greet in hall (including bags)
8.1 Priority bag identification & delivery
8.1 DDA compliant reserved seats by reclaim
8.1 Own strollers at loading bridge
8.2 Maximum 45 minute last bag 8.2 Priority bag identification & delivery
8.2 Accessible toilets and change facilities
8.2 Baby change facilities
8.3 Bag recovery processes on failure
8.3 Hotel / home drop off
8.3 Help points 8.3 Luggage delivered to your car
8.4 Catering facilities 8.4 DDA compatible trollies
8.5 Automated kiosks for lost baggage
8.6 Bag delivery status (visual display screens & via smart phone app)
8.7 Real time transport network and service information
onward travel & Arrivals
9.1 Stress free pick up 9.1 Chauffeur pick up areas at level
9.1 Clear routing to priority parking / pick up
9.1 Kerb side lounge with concierge (Heated and dry)
9.1 Parent/s and baby rooms
9.2 Minimise passenger routing conflicts (arrivals)
9.2 Concierge service 9.2 Dedicated pick up area
9.3 Roaming, helpful staff 9.3 Valet pick up areas
9.4 Airline branded arrivals products
9.5 Consolidated onward travel facilities & information
9.6 Clear routing to products
9.7 Hotel desk, F&B, Retail & Bureaux
9.8 Real time transport network and service information
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D G HChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E HAppendix
E F
116
Airport wide
core premium Business Assistance Family
10.1 Core ambience 10.1 Premium ambience 10.1 Business ambience 10.1 PRM ambience 10.1 Family ambience
10.2 Intuitive wayfinding throughout
10.2 Premium reward scheme
10.2 Frequent flyer rewards (access to premium services)
10.2 PRM seating at agreed intervals
10.2 Seating at agreed frequency
10.3 Airport / flight info application
10.3 Use of dynamic lighting displays
10.3 Predictable processes 10.3 DDA compliance 10.3 Improved frequency of toilet / change facilities
10.4 Free Wi-Fi across whole airport
10.4 Consistent Premium product offer
10.7 Modified “Premium” arrivals lounge offering
10.4 Accessibility to all services
10.5 Disruption / recovery areas 10.5 Minimise level changes
10.6 A Gatwick palette 10.6 Minimise travel distances
10.7 Real time service information 10.7 Premium arrivals lounge
10.8 Airline branding / differentiation opportunities 10.8 Concierge services
10.9 Natural light in passenger areas
10.10 Murals and experiential displays
10.11 Clean, spacious, bright modern environment
10.12 Process to buy one off Premium services
10.13 Push communications to passengers (e.g. text)
10.14Toilets provided throughout airport to meet latest GAL standards
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F GChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E GAppendix
EAppendix
H
117Glossary
ACC Airport Consultative Committee
ACL Airport co-ordination limited
AFC Anticipated Final Cost
Annex G [ Gatwick’s] agreement on enhanced information disclosures and consultation at Heathrow and Gatwick Airports - update for Q5
AOC Airline Operators Committee
APD Airport passenger duty
CAA Civil Aviation Authority
CapEx Capital Expenditure
CAST Comprehensive Airport Simulation Tool
CATMs Cargo Air Transport Movements i.e. commercial cargo flights
CPB Capital Programme Board
CC Competition Commission
CCRS Change Control Record Sheet
CE Constructive Engagement
CIP Capital Investment Programme
CEO Chief Executive Officer
COPI Construction Output Price
DfT Department for Transport
DOM Domestic
DFSS Design For Six Sigma
EU European Union
FIDS Flight Information Display Screen
GA General aviation
GAL Gatwick Airport Limited
GAL Number Gatwick Project / Programme Reference Number
GATCOM Gatwick Consultative Committee
GDP Gross domestic product
HBS Hold Baggage Scanner
IDL International Departure Lounge
INT International
IT Information Technology
ITTS Inter Terminal Transit System
JSG Joint Steering Group
KPI Key Performance Indicator
LACC London Airports Consultative Committee
M Million
MARS multi aircraft ramp system
MENA middle east and north africa (region)
mppa million passengers per annum
MSCP6 Multi Storey Car Park (Six)
NATS National Air Traffic Services
Non ATMs Non-commercial flights e.g. General Aviation, Air Taxi
NT North Terminal
NTF North Terminal Forecourt
NTI North Terminal Interchange
NTX North Terminal Extension
Chapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D F GChapter Chapter Chapter Chapter Appendix Appendix Appendix Appendix Appendix Appendix Glossary
1 2 3 4 A B C D E GAppendix
EAppendix
H
118
NWZ North West Zone
Opex Operating cost
p.a. Per annum
PATMs Passenger Air Transport Movements i.e. commercial passenger flights
PAG Passenger Advisory Group
Pax Passengers
PPH Passengers per hour
PRM Passengers with Restricted Mobility
Q5 The 5th Quinquennium (regulatory period)
Beyond Q5 Post Q5 period
QSM Quality Service Measure
R1 Risk held at project level
R2 Risk held at Portfolio level
SERAS South East and east of England Regional Air Services
SH&E Consultancy
ST South Terminal
SQR Service Quality Rebate
SQWG Service Quality Working Group
Trigger Projects Financial incentives placed on Gatwick to encourage timely & efficient delivery of strategically important projects, known as trigger projects.
UKBF United Kingdom Border Force ( previously known as UK Border Agency)
119Notes