Upload
ithacavoice
View
213
Download
1
Embed Size (px)
Citation preview
Page 1 of 2
Ithaca Commons Repair & Upgrade Project C#2 – Utilities, C#3A – Surface, C#3B – Electric
Date Start End Next Date Next Time Prepared By
05/06/2014 10:00 AM 11:00 AM 05/13/2014 10:00 AM Jessica Buckley
Purpose Location
2014 Construction Meeting #6 Commons Project Office – 215 East State St. Ithaca, NY
Distribution/Attendance: (Present at meeting unless noted: A –absent)
City of Ithaca Michael Kuo, Jessica Buckley, Nicole Mason
Downtown Ithaca Alliance Tammy Baker
Sasaki Associates Susannah Ross (A), Eamonn Hutton (A)
Labella Associates Dan Walker, James Matzat (A)
Vacri Construction Ralph Avery, Andy Breznay, Matt Thomas(A), Roberto DeVincentis (A)
Power & Construction Group Lou Zupan, Bill Planert (A), Brian Planert (A)
Verizon James Edwards, Dave Comer (A)
NYSEG Gas Doug Stafford (A), Jack Barker, Dawn Stillwell (A)
DDS Jeff Bubb (A)
NYSEG Electric Jack Czapranski, Dennis Kuhn (A)
Item / Description Notes Due
1. RFI’s
1.1. Any open RFI’s at this time PC&G to submit RFI log
2. SUBMITTALS
2.1. Any open submittals City waiting on lighting submittals from P&CG; Vacri to submit on TTC Alley HH & WF Vault today; Vacri to submit shop drawings granite, steel; PC&G to submit on stage lighting
2.2. Longest lead time items P&CG: Kiosk lead time
PC&G to submit submittal log
3. OPEN DESIGN ITEMS
3.1. Water Feature Design City to request permit set for sewer commission and health department and possibly DEC
4. SCHEDULE
4.1. Status of deduct alternate reinstatement WF & BM Pavilion to be issued
Vacri to issue BM Pavilion shop drawings
4.2. P&CG to schedule 1-2 additional crews 05/12: Start NW & SW end of E State 05/19 – 06/16: Complete N Tioga
05/12: One crew Cayuga St north side
4.3. NYSEG Electric to relocate secondary on E State St in June
05/07: To pull secondary wire; 2x 4” conduit; NYSEG Electric would like to
MEETING MINUTES
Page 2 of 2
follow P&CG trench; Trench width: 18”; To backfill with ‘slurry’
4.4. Vacri / AC&P May: Complete utilities June: Verizon MH entry; Pour foundations/footers July: Prep & pour slab N Tioga
MK to submit payment to Verizon; Design team to submit location of conduit entry; Vacri proposes to enter Cayuga St Verizon MH week of 05/12; City will help set up detours on Aurora St for 3-4 days, Vacri to set up flagging crews
4.5. NYSEG Gas to start work on north side of Trolley Circle; Priority to make connection at Aurora St
Complete main and test, follow with saddle tapped services; Rothschild Bldg service connection cannot be relocated
5. UTILITIES COORDINATION
5.1. Verizon / Gas Conflicts E State St: P&CG to report on conflicts with cat. poles
05/08: PC&G to dig test pits
5.2. Water Feature: Verizon scheduled to start work 05/12; Vacri to submit on WF vault as spec’d
5.3. TTC Alley/Telecom: Work scheduled for week of 05/12; TTC to schedule EE Root
5.4. Verizon & TMH-5: Vacri & Verizon to schedule work to allow for backfill
Verizon to start work 05/07
5.5. Telecom Entry to Verizon MHs: Vacri to schedule work in June
City to complete application
6. VAULTS
6.1. Vault Infill – Wall to cure for 7 days at 208/210 & 126 E State St (05/12); Other possible vault infills at 118, 119,123, 135,137,139
Vacri to start 119 or 123 (west) E State St; Vacri to submit price estimate on previous infills.
7. ELECTRIC
7.1. FD #2 issued, defines traffic ratings for HH & designation of split HH
P&CG to send submittal
8. TELECOM DUCT BANK
8.1. Bank Alley west walkway to be closed week of 05/12
9. M&PTP: MAINTENANCE & PROTECTION OF TRAFFIC & PEDESTRIANS
9.1. Asphalt not to exceed contract #3A QTY; Pours are to be done week of graduation; Locations are to be specified by City
9.2. Vacri to propose sidewalk demo plan
DATES TO REMEMBER
May 16 to May 18 – Ithaca College Graduation, no work on weekend
May 23 to May 25 – Cornell Graduation, no work on weekend
May 30 to June 1 – Ithacafest, Cayuga St entrance closed