    Ithaca Commons Repair & Upgrade Project C#2 Utilities, C#3A Surface, C#3B Electric

    Date Start End Next Date Next Time Prepared By05/13/2014 10:00 AM 11:00 AM 05/20/2014 10:00 AM Jessica Buckley

    Purpose Location

    2014 Construction Meeting #7 Commons Project Office215 East State St Ithaca, NY

    Distribution/Attendance: (Present at meeting unless noted: Aabsent)

    City of Ithaca Michael Kuo, Jessica Buckley, Nicole Mason

    Downtown Ithaca Alliance Tammy Baker

    Sasaki Associates Susannah Ross (A), Eamonn Hutton (A)

    Labella Associates Dan Walker, James Matzat (A)

    Vacri Construction Ralph Avery, Andy Breznay, Matt Thomas(A), Roberto DeVincentis (A)

    Power & Construction Group Lou Zupan, Bill Planert, Brian Planert

    Verizon James Edwards, Dave Comer (A)

    NYSEG Gas Doug Stafford (A), Jack Barker, Dawn Stillwell (A)

    DDS Jeff Bubb (A)

    NYSEG Electric Jack Czapranski, Dennis Kuhn (A)

    Item / Description Notes Due

    1. RFIs

    1.1.

    Any open RFIs at this time

    2.

    SUBMITTALS

    2.1.

    Any open submittals

    Vacri report on: TTC alley HH (needed this

    week); WF vault; Granite & steel shop

    drawings; BM Pavilion shop drawings

    P&CG report on: Stage lighting

    2.2.

    Longest lead time items

    P&CG: Kiosk lead time

    3.

    OPEN DESIGN ITEMS

    3.1.

    Water Feature Design pending approval

    of health department

    4. SCHEDULE

    4.1.

    P&CG to schedule 1-2 additional crews

    05/12: Start NW & SW end of E State;

    Working w/ NYSEG Electric at N Tioga &

    NE side of E State St

    05/1906/16: Complete N Tioga

    4.2.

    NYSEG Electric to complete relocation of

    secondary to Aurora St by 05/16

    4.3.

    Vacri / AC&P

    MEETING AGENDA

  • 8/10/2019 2014-05-13 Construction Meeting Agenda.pdf

    2/3

    Page 2of 3

    May: Complete utilities; Verizon MH entry

    June: Site demo; Pour foundations /

    footers; Site grading, curbs, expansion

    joints

    July: Prep & pour slab N Tioga; Paving

    program

    4.4.

    NYSEG Gas Priorities:

    A.

    Make connection at Aurora St

    B.

    Test, charge main and run service to

    bldg north branch between Aurora &

    Trolley Circle

    C.

    Provide new service to 215 E State St

    prior to July

    5. UTILITIES COORDINATION

    5.1.

    Verizon / Gas Conflicts E State St:P&CG

    to report on # of Verizon conflicts with

    cat. poles

    5.2.

    Water Feature: Verizon scheduled to

    start work 05/19; Vacri to submit on WF

    vault as specd

    5.3. TTC Alley/Telecom: 05/12: EE Root is to

    expose TTC conduits to allow for the

    installation of the TTC HH and storm

    lateral by Vacri; Verizon scheduled to

    expose cables in alley toward the end of

    this week to allow installation of storm

    lateral

    5.4. Telecom Entry to Verizon MHs:Vacri

    finished Cayuga St; Aurora & Seneca St tobe scheduled

    5.5.

    Asphalt Restoration: Vacri, NYSEG Gas &

    Signals project (PC&G) to coordinatein

    intersections

    6.

    VAULTS

    6.1.

    Vault Infill208/210 to be filled by 8 AM

    05/13; 123 infill to be complete by 05/21;

    Other possible vault infills at 118, 119,

    135,137,139; Vacri to submit price

    estimate on infill at 126 & 208/210

    7.

    ELECTRIC7.1.

    Grading plan available for surveyor

    7.2.

    Electric feed to from panel west HH

    exposed on fence hook east of 158 E

    State St

    8.

    TELECOM DUCT BANK

    8.1.

    Bank Alley west walkway to be closed

    week of 05/12; TTC east entrance to

  • 8/10/2019 2014-05-13 Construction Meeting Agenda.pdf

    3/3

    Page 3of 3

    remain open until 05/14

    9.

    M&PTP: MAINTENANCE & PROTECTION

    OF TRAFFIC & PEDESTRIANS

    9.1.

    All trenches need to be prepared for

    graduation weekend; GasAt least item

    4; Vacriasphalt; PC&GBeautifulconcrete / plate combo

    9.2.

    Vacri is to power off the electric during

    the day, and on at the end of the day; Any

    variation is to be communicated to

    JB/MK, AB, LZ, Andy (Gas)

    9.3.

    PERSONAL VEHICLES ARE PROHIBITED

    FROM PARKING ON SITE

    9.4.

    Flaggers are required to bring trucks on &

    off site, especially when backing up

    9.5.

    Pedestrian walkways are to be reinstated

    at the end of each day; Only one crossing

    may be closed at a time; If more than one

    is to be closed a temporary crossing is to

    be opened

    9.6.

    The mural fence may be disassembled to

    allow work, however must be reinstated

    at the end of each day

    9.7.

    Vacri to propose sidewalk demo plan

    DATES TO REMEMBER

    May 16 to May 18Ithaca College Graduation, no work on weekend May 23 to May 25Cornell Graduation, no work on weekend

    May 30 to June 1Ithacafest, Cayuga St entrance closed