Ithaca Commons Repair & Upgrade Project C#2 Utilities, C#3A Surface, C#3B Electric
Date Start End Next Date Next Time Prepared By05/13/2014 10:00 AM 11:00 AM 05/20/2014 10:00 AM Jessica Buckley
Purpose Location
2014 Construction Meeting #7 Commons Project Office215 East State St Ithaca, NY
Distribution/Attendance: (Present at meeting unless noted: Aabsent)
City of Ithaca Michael Kuo, Jessica Buckley, Nicole Mason
Downtown Ithaca Alliance Tammy Baker
Sasaki Associates Susannah Ross (A), Eamonn Hutton (A)
Labella Associates Dan Walker, James Matzat (A)
Vacri Construction Ralph Avery, Andy Breznay, Matt Thomas(A), Roberto DeVincentis (A)
Power & Construction Group Lou Zupan, Bill Planert, Brian Planert
Verizon James Edwards, Dave Comer (A)
NYSEG Gas Doug Stafford (A), Jack Barker, Dawn Stillwell (A)
DDS Jeff Bubb (A)
NYSEG Electric Jack Czapranski, Dennis Kuhn (A)
Item / Description Notes Due
1. RFIs
1.1.
Any open RFIs at this time
2.
SUBMITTALS
2.1.
Any open submittals
Vacri report on: TTC alley HH (needed this
week); WF vault; Granite & steel shop
drawings; BM Pavilion shop drawings
P&CG report on: Stage lighting
2.2.
Longest lead time items
P&CG: Kiosk lead time
3.
OPEN DESIGN ITEMS
3.1.
Water Feature Design pending approval
of health department
4. SCHEDULE
4.1.
P&CG to schedule 1-2 additional crews
05/12: Start NW & SW end of E State;
Working w/ NYSEG Electric at N Tioga &
NE side of E State St
05/1906/16: Complete N Tioga
4.2.
NYSEG Electric to complete relocation of
secondary to Aurora St by 05/16
4.3.
Vacri / AC&P
MEETING AGENDA
8/10/2019 2014-05-13 Construction Meeting Agenda.pdf
2/3
Page 2of 3
May: Complete utilities; Verizon MH entry
June: Site demo; Pour foundations /
footers; Site grading, curbs, expansion
joints
July: Prep & pour slab N Tioga; Paving
program
4.4.
NYSEG Gas Priorities:
A.
Make connection at Aurora St
B.
Test, charge main and run service to
bldg north branch between Aurora &
Trolley Circle
C.
Provide new service to 215 E State St
prior to July
5. UTILITIES COORDINATION
5.1.
Verizon / Gas Conflicts E State St:P&CG
to report on # of Verizon conflicts with
cat. poles
5.2.
Water Feature: Verizon scheduled to
start work 05/19; Vacri to submit on WF
vault as specd
5.3. TTC Alley/Telecom: 05/12: EE Root is to
expose TTC conduits to allow for the
installation of the TTC HH and storm
lateral by Vacri; Verizon scheduled to
expose cables in alley toward the end of
this week to allow installation of storm
lateral
5.4. Telecom Entry to Verizon MHs:Vacri
finished Cayuga St; Aurora & Seneca St tobe scheduled
5.5.
Asphalt Restoration: Vacri, NYSEG Gas &
Signals project (PC&G) to coordinatein
intersections
6.
VAULTS
6.1.
Vault Infill208/210 to be filled by 8 AM
05/13; 123 infill to be complete by 05/21;
Other possible vault infills at 118, 119,
135,137,139; Vacri to submit price
estimate on infill at 126 & 208/210
7.
ELECTRIC7.1.
Grading plan available for surveyor
7.2.
Electric feed to from panel west HH
exposed on fence hook east of 158 E
State St
8.
TELECOM DUCT BANK
8.1.
Bank Alley west walkway to be closed
week of 05/12; TTC east entrance to
8/10/2019 2014-05-13 Construction Meeting Agenda.pdf
3/3
Page 3of 3
remain open until 05/14
9.
M&PTP: MAINTENANCE & PROTECTION
OF TRAFFIC & PEDESTRIANS
9.1.
All trenches need to be prepared for
graduation weekend; GasAt least item
4; Vacriasphalt; PC&GBeautifulconcrete / plate combo
9.2.
Vacri is to power off the electric during
the day, and on at the end of the day; Any
variation is to be communicated to
JB/MK, AB, LZ, Andy (Gas)
9.3.
PERSONAL VEHICLES ARE PROHIBITED
FROM PARKING ON SITE
9.4.
Flaggers are required to bring trucks on &
off site, especially when backing up
9.5.
Pedestrian walkways are to be reinstated
at the end of each day; Only one crossing
may be closed at a time; If more than one
is to be closed a temporary crossing is to
be opened
9.6.
The mural fence may be disassembled to
allow work, however must be reinstated
at the end of each day
9.7.
Vacri to propose sidewalk demo plan
DATES TO REMEMBER
May 16 to May 18Ithaca College Graduation, no work on weekend May 23 to May 25Cornell Graduation, no work on weekend
May 30 to June 1Ithacafest, Cayuga St entrance closed
ADDITIONAL NOTES