Upload
ithacavoice
View
213
Download
0
Embed Size (px)
Citation preview
8/10/2019 2014-06-10 Construction Meeting Minutes.pdf
1/3
Page 1of 3
Ithaca Commons Repair & Upgrade Project C#2Utilities, C#3ASurface, C#3BElectric
Date Start End Next Date Next Time Prepared By06/10/2014 10:00 AM 11:00 AM 06/17/2014 10:00 AM Jessica Buckley
Purpose Location
2014 Construction Meeting #11 Commons Project Office215 East State St Ithaca, NY
Distribution/Attendance: (Present at meeting unless noted: Aabsent)
City of Ithaca Michael Kuo, Jessica Buckley, Nicole Mason
Downtown Ithaca Alliance Tammy Baker
Sasaki Associates Susannah Ross, Eamonn Hutton (A0
Labella Associates Dan Walker (A), James Matzat
Vacri Construction / ACP Ralph Avery, Andy Breznay, Matt Thomas (A), Roberto DeVincentis (A),
Bob Belavigna - ACP
Power & Construction Group Lou Zupan, Bill Planert, Brian Planert (A)
Verizon James Edwards, Dave Comer (A)
NYSEG Gas Doug Stafford, Jack Barker, Dawn Stillwell (A), John Mattiace (A)
DDS Jeff Bubb (A), Flint Brann, Andy Gana
NYSEG Electric Jack Czapranski (A), Dennis Kuhn (A)
Item / Description Notes Due
1. RFIs, SUBMITTALS
1.1.
Vacri (Contract #3A):
1.1.1.
Water Feature Vault #73
1.1.2.
Glass Submittal #85
1.1.3.
Granite Submittal
1.1.4.
Trench Drain and Vault Setting
Material (sand vs. mortar)
Binghamton precast to revise cost
estimate; Bundling of plumbing is to be
revised, however the vault core location
will not change; Submittals 85 & 86 are
being reviewed by Sasaki; Granite to be
submitted by Vacri today; Response to
setting bed RFI is to be reviewed by Sasaki
today; Tables are in production; Custom
chair submittal from supplier is a wk out
from submission
1.2.
P&CG (Contract #3B):
1.2.1.
Lighting Submittal #13
1.2.2.
Rebar Shop Drawings
Light pole foundation to be submitted by
P&CG today; Alternate foundation for
Kiosk to be submitted; Foundation designto be reviewed by City and P&CG after
meeting
2. DESIGN, FIELD DIRECTIVES
2.1.
TTC Alley Storm: Addl survey needed;
LaBella to issue FD; Areaway at #156 to
be abandoned
To be issued wk of 06/16
MEETING MINUTES
8/10/2019 2014-06-10 Construction Meeting Minutes.pdf
2/3
Page 2of 3
2.2.
Home Dairy Alley: Addl survey needed;
LaBella to issue FD
To be issued wk of 06/16
2.3.
119 E State Vault Infill:Scheduled to be
backfilled (06/11)
AG is aware of backfilling around the gas
main
2.4.
CB #5.D: Storm design at N Tioga /
Seneca St to be revised
To be issued 06/11 or 06/12
2.5.
EX-6: Granite roughing detail #3/DT506 P&CG to submit RFI; MK to review
acceptance of using granite or flex pipe in
lieu of conduit; P&CG to send fixture cut
sheet to Vacri; Pavilion lighting junction
box to be surface mounted as per
response to RFI; Detail to be provided by
Sasaki on lighting feed
2.6.
Handhole Compilation: Used by HHs have been ordered
2.7.
Electric Panel Housekeeping Pads: LP-3
requires coordination with new TCAT bus
shelter at Aurora St
FD to be issued by Sasaki
3.
OPEN ITEMS
3.1.
P&CG: Installation of Bank Alley Electric
DB
City / Engineer reviewing alternate
alignment
3.2.
TTC Telecom: Scheduled F.O. switch over
date pending response from TTC
Waiting on response to backfill trench at
Trolley Circle
3.3.
Pavilion / Gateway Footings: Vacri / ACP
to schedule footer install simultaneously
(Wk of 06/16)
Pending Bank Alley availability
3.4.
Catenary Lighting: 14-wk lead time on
lighting package (09/08); Gas main
retirement required prior to installation
P&CG to re-submittal #13; No comments
on bolt submittal
3.5.
NYSEG Gas:Schedule to test & chargemain (06/16?); Tioga St to be tied-in first;
South side of Cayuga St intersection
needs to be tied-in prior to all services
being connected; JB to update on
possibility of retiring part of gas main on
N/S of 200 Block E State after new
services complete in this area
Gas shifted to the south of proposed cat.light pole; City to confirm ; Priority to start
from Trolley Circle moving to the west
with services on the north side of E State
St; Medium pressure service are to be tie-
in from Green St prior to retirement of
main on south side of E State St;
3.6.
NYSEG Electric available to pull wire btw
Bank Alley & Aurora St
To be scheduled wk of 06/30
4.
M&PTP: MAINTENANCE & PROTECTION
OF TRAFFIC & PEDESTRIANS4.1.
Vacri to submit work sequence to City for
review prior to start of Bank Alley work
(sidewalk demo, grading/compaction
testing, set valve boxes, MH covers, slab
pour, pavers, etc.)
Vacri is to submit plywood bridges for
business access; Temp chain link fence to
be used on site
5. New Business: Open RFIs, submittals,
concerns, etc.
8/10/2019 2014-06-10 Construction Meeting Minutes.pdf
3/3
Page 3of 3
5.1.
Pay Req City comments to be issued to P&CG and
Vacri today
5.2.
Site work hours Work can take place from 7 AM to 7:30
PM; Announcement went out that work
may continue later into the evening this
week
ADDITIONAL NOTES