    Ithaca Commons Repair & Upgrade Project C#3ASurface, C#3BElectric

    Date Start End Next Date Next Time Prepared By08/12/2014 10:00 AM 11:00 AM 08/19/2014 10:00 AM Jessica Buckley

    Purpose Location

    2014 Construction Meeting #21 Commons Project Office215 East State St Ithaca, NY

    Distribution/Attendance: (Present at meeting unless noted: Aabsent)

    City of Ithaca Michael Kuo, Jessica Buckley, Nicole Mason

    Downtown Ithaca Alliance Tammy Baker

    Sasaki Associates Susannah Ross, Eamonn Hutton(A), Kimberly MichaelsTWM

    Labella Associates Dan Walker, James Matzat(A)

    Vacri Construction / ACP / Ralph Avery(A), Andy Breznay, Matt Thomas(A), Roberto

    DeVincentis(A), Bob BellavignaACP

    Power & Construction Group Lou Zupan, Bill Planert

    Verizon James Edwards(A), Dave Comer(A)

    NYSEG Gas Doug Stafford(A), Jack Barker(A), Dawn Stillwell(A), John Mattiace(A)

    DDS Jeff Bubb(A), Flint Brann(A)

    NYSEG Electric Jack Czapranski, Dennis Kuhn(A)

    Item / Description Notes Due

    1. RFIs, SUBMITTALS

    1.1.

    Vacri (Contract #3A):

    1.1.1.

    Granite Coordination (#87)Granite

    shops expected by 08/08; Need to

    relocate conduit stubs for EX6s to

    butt joint

    1.1.2.

    Curb Sample (#99)Detail issued by

    Sasaki 08/08 (Bulletin #17);

    Resubmit shop drawing

    1.1.3.

    Gateway (#106)Add to agenda for

    steel meeting 08/13

    Shop drawings do not seem to reflect joint

    perpendicular to building edge on west

    seat wall; SR to review granite seat wall

    shop drawings; BB to put SR in contact

    with Jim; SR to review manufactures

    concern of light boxes cut into granite

    steps, no concern of light box in seat wall;

    Curb to be sawn on 6 sides and approved

    by the City and Sasaki; Concrete will not

    be poured around railing bolts; SR to

    review gateway footings with DE; Vacri to

    update city on helical pile schedule; Vacri

    to coordinate with Verizon to relocate DB1.2.

    P&CG (Contract #3B):

    1.2.1.

    Lighting Submittal #13R4EX1 poles

    to be issued 08/11; EX4 fixtures and

    mounting arm for EX8 not approved

    Sasaki reviewing RFI 21; Locations of tabs

    EX1 poles are to be taped off to be field

    welded; SR to review anchor bolt pattern

    for EX1 pole in regards to base plate being

    in line with diagonal bands; SR to resend

    example of EX4 junction boxes from

    lighting designer for tomorrows meeting;

    MEETING MINUTES

  • 8/10/2019 2014-08-12 Construction Meeting Minutes.pdf

    2/2

    Page 2of 2

    Catenary wire to be submitted on

    2.

    DESIGN, FIELD DIRECTIVES

    2.1.

    TTC Alley: Start today; Sasaki to issue

    grading for alley

    Electricity will be shut off on third floor

    tomorrow; Water pit may have to be

    moved, surveyor will layout Kiosk

    tomorrow and determine if there is aconflict;

    2.2.

    Electric Panel & Kiosk Housekeeping Pads:

    Vacri to relocate water meter pit per

    Bulletin 15

    NM to follow up with supplier on bolt

    detail

    3.

    CRITICAL PATH ITEMS

    3.1.

    Water Feature Vault: NYSEG to schedule

    crew to remove section of gas main

    Vault installation pending gas main

    retirement; PCG to determine which light

    poles are in conflicts gas main; MK to

    notify BP when NYSEG gas will be

    available to cut out old gas main

    3.2.

    Aurora Street Gateway: Vacri to dig test

    pit this week to verify if pier is in conflict

    with vault wall at 224 E State

    DW to review electric to gateway with BD;

    3.3.

    Vacri (Bank Alley): Sasaki issued 18 curb

    detail; Start pouring ribbon footers

    3.4.

    NYSEG Gas:4 flanged pipe is in; services

    remaining to dig: (4) 2, (4) 4, (1)

    medium pressure

    3.5.

    NYSEG Electric: Reschedule wire pull to

    Aurora (targeted for 08/09)

    Wire pull completed; Labella to send out

    revised service duct bank to LP

    3.6.

    202 E State Waterproofing: Vacri

    submitted cost for waterproofing

    Owner interested in replacing hatch with

    air intakes

    3.7.

    Pavilion Lighting: Meeting scheduled for08/13

    4.

    M&PTP: MAINTENANCE & PROTECTION

    OF TRAFFIC & PEDESTRIANS

    4.1.

    Site Maintenance: NYSEG to remove

    surplus fill to re-establish site to sub-

    grade; All trash and debris must be

    removed on a weekly basis

    NYSEG gas has denied responsibility of

    removing excess fill on site, Vacri hauls

    material on and off site, PCG hauled

    excess fill from north side of E State St.

    5.

    New Business