Ithaca Commons Repair & Upgrade Project C#3ASurface, C#3BElectric
Date Start End Next Date Next Time Prepared By08/26/2014 10:00 AM 11:00 AM 09/02/2014 10:00 AM Jessica Buckley
Purpose Location
2014 Construction Meeting #23 Commons Project Office215 East State St Ithaca, NY
Distribution/Attendance: (Present at meeting unless noted: Aabsent)
City of Ithaca Michael Kuo, Jessica Buckley, Nicole Mason
Downtown Ithaca Alliance Tammy Baker
Sasaki Associates Susannah Ross, Eamonn Hutton(A), Kimberly MichaelsTWM(A)
Labella Associates Dan Walker, James Matzat(A)
Vacri Construction / ACP / Ralph Avery, Andy Breznay, Matt Thomas(A), Roberto DeVincentis(A),
Bob BellavignaACP(A)
Power & Construction Group Lou Zupan, Bill Planert
Verizon Gloria Moran(A), Jeff Utter(A)
NYSEG Gas Doug Stafford(A) Jack Barker(A), Dawn Stillwell(A), John Mattiace(A)
DDS Jeff Bubb(A), Flint Brann(A)
NYSEG Electric Jack Czapranski(A), Dennis Kuhn(A)
Item / Description Notes Due
1. RFIs, SUBMITTALS
1.1.
Vacri (Contract #3A):
1.1.1.
Granite Coordination (#87R2)
Submittal #87R2 issued 8/25/14
1.1.2.
Gateway (#106)see Bulletin #18
for steel cuts; need 2 diameter hole
in base plates for electric feeds
1.1.3.
Irrigation (#98)Deleted from
contract
1.1.4.
Structural Soil (#90R2)KM
contacted Paolangeli on 8/19;
subcontractor will prepare new mix
for week of 8/25
Granite submittal to be reviewed for
bench blocks, changes made by Totaro are
bubbled; DE is marking up gateway
submittal; Gateway at Aurora St can be
poured, there is power traffic signal;
Helical pile to be scheduled by Vacri,
second week of September; MK to discuss
volume of structural soil with the City; RA
to follow up with Paolangeli to resubmit
structural soil; RA to resubmit dcva for
hydrants; BB to resubmit epoxy
1.2.
P&CG (Contract #3B):1.2.1.
Lighting Submittal #13R7 and #13R8
Poles and fixtures issued 8/20 and
8/25
1.2.2.
Catenary Cabling #TBDPCG to
issue submittal
SR expects to send out reviewed lightingsubmittal soon; Supplier is out of Australia
with 6-8 week lead time, BP searching for
equal supplier in the US
2. DESIGN, FIELD DIRECTIVES
2.1.
TTC & Home Dairy Alley: Sasaki to issue Issued in conformance set
MEETING MINUTES
8/10/2019 2014-08-26 Construction Meeting Minutes.pdf
2/3
Page 2of 3
grading for alley
2.2.
139 Benchwarmers Vault: Site survey
8/21/14; Labella to issue detail for pricing
DW to follow up with MM on plan
2.3.
Conformance Set: Issued by Sasaki on
8/22/14
Material plan paving has changed
throughout the site; MK has requested
that a bulleted list of changes in theconformance set be issued by Sasaki; SR
doesnt believe that the square footage of
paver type has changed significantly; TIN
has been updated and will be sent out
3.
CRITICAL PATH ITEMS
3.1.
Bank Alley Planter: Slot drain conflict with
NYSEG vault; bollard base and light pole
base conflicts with curb line
Curb is to be shifted to the west to fit
between light pole and transformer vault;
Trench drain will be installed to the north;
Power bollards foundation overlaps with
the curb at north side of planter, curb to
be notched if power bollard can fit; PCG &
Vacris surveyor are to review layout of
bollard and curb; SR to determine if the
size of the power bollard base can be
reduced
3.2.
Water Feature Vault: Vacri to install
sanitary lateral and vault 8/25
NE corner of vault: Plans show 2 feet
between vault and bank building vault
corner; Vacri not concerned but may dig
exploratory
3.3.
Gateways: @Aurora: Test pit dug 8/22,
revealed no conflict with vault; @Cayuga:
Verizon will pull cable out of way as
required by Vacri during installation offooter
@Aurora foundations can be installed;
@Cayuga helical pile is to be scheduled by
Vacri
3.4.
NYSEG Gas:N/S services 100% complete,
need target date to purge main; Punchlist
sent to NYSEG; Benchwarmers service to
be dug/installed concurrent with vault
infill work (See Item #2.2)
NYSEG has two more tie-ins to do in
Aurora St, to be completed today;
Restoration remaining in Aurora St; North
side main has been purged; PCG needs to
dig for each lightpole bases to find
conflicts
3.5.
Pavilion Lighting: Vacri to advise on
additional costs to add HHs, delivery date
for steel
PCG has asked Raulli to visit yard to see
steel, BP asked Vacri to coordinate with
Raulli to arrange a visit
3.6.
Telecom 4 Service to Marriott:PCG tosubmit cost to perform the work
4. M&PTP: MAINTENANCE & PROTECTION
OF TRAFFIC & PEDESTRIANS
4.1.
Site Maintenance: Vacri shored up fence;
All trash and debris must be removed on
a weekly basis
5.
New Business
8/10/2019 2014-08-26 Construction Meeting Minutes.pdf
3/3
Page 3of 3
ADDITIONAL NOTES:
EX6 lights in eastern stairwell: one light in the block adjacent to the stairs and then every other
stone south for a total of 4 lights.
SR to issue granite curbing submittal this afternoon
RA concerned that the length of the trench drains will cause the 4pipe to be 4below finishgradedirectly under the pavers. SR to discuss trench drain connections with structural
engineer.
Storm lateral to Mansour Jewelers 140 E State St is to be installed in location of old sanitary MH
Delivered to Emerson and can be stored until next spring; City and DIA to find a location to store
furniture in the future