Ithaca Commons Repair & Upgrade Project C#3ASurface, C#3BElectric
Date Start End Next Date Next Time Prepared By09/02/2014 10:00 AM 11:00 AM 09/09/2014 10:00 AM Jessica Buckley
Purpose Location
2014 Construction Meeting #24 Commons Project Office215 East State St Ithaca, NY
Distribution/Attendance: (Present at meeting unless noted: Aabsent)
City of Ithaca Michael Kuo, Jessica Buckley, Nicole Mason(A)
Downtown Ithaca Alliance Tammy Baker
Sasaki Associates Susannah Ross, Eamonn Hutton(A), Kimberly MichaelsTWM
Labella Associates Dan Walker, James Matzat(A)
Vacri Construction / ACP / Ralph Avery, Andy Breznay, Matt Thomas(A), Roberto DeVincentis(A),
Bob BellavignaACP
Power & Construction Group Lou Zupan, Bill Planert
Verizon Gloria Moran(A), Jeff Utter(A)
NYSEG Gas Doug Stafford(A), Jack Barker(A), Dawn Stillwell(A), John Mattiace(A)
DDS Jeff Bubb(A), Flint Brann(A)
NYSEG Electric Jack Czapranski(A), Dennis Kuhn(A)
Item / Description Notes Due
1. RFIs, SUBMITTALS
1.1.
Vacri (Contract #3A):
1.1.1.
Granite Coordination (#87R2):
Submittal #87R2 issued 8/25/14; SR
to update on status
1.1.2.
Structural Soil (#90R2): KM
contacted Paolangeli on 8/19;
subcontractor will prepare new mix
for week of 8/25; Vacri to update on
status of re-submittal
1.1.3.
Gateway (#106, #114a/b): Under
review by Elwyn & Palmer
1.1.4.
Double Check Valve (#TBD): RA to
submit for yard hydrants
1.1.1.
#87R2SR to review and return
1.1.2.
#90R2Soil is in lab for analysis;
KM to review mix design, soil spec,
and supplier submittal
1.1.3.DEs review is mostly complete;
Waiting for Selex for EX9 fixture
and base plate holes
1.1.4.
RA to submit double check valve
and locking valve boxes
1.1.5.
ACP asked about submittals on
expansion joint and curing
compound; SR to review and issue
early this week1.1.6.
RFI 32 finish elevations slot drains
to be 1/8-in below pavers
1.2.
P&CG (Contract #3B):
1.2.1.
Lighting Submittal #13R7: Reviewed
by Sasaki 8/28/14; Manufacturer has
questions on structural loading
1.2.1.
#13R7SR to issue later today
1.2.2.
#13R8PCG to address comments
and notes
1.2.3.
Catenary Cabling revision sent out
MEETING MINUTES
8/10/2019 2014-09-02 Construction Meeting Minutes.pdf
2/3
Page 2of 3
1.2.2.
Lighting Submittal #13R8: Sasaki
reviewed 8/29/14
1.2.3.
Catenary Cabling #TBD: PCG to issue
submittal
by PCG this morning, SR to assign
submittal #
1.2.4.
Bollards Submittal #18 to be
resubmitted by PCG
2. DESIGN, FIELD DIRECTIVES
2.1.
Bulletin 19 (New Circuits for Gateway
Recepts): PCG to provide cost estimate
PCG to submit cost estimate
2.2.
Bulletin 20 (Home Dairy Telecom, Bank
Alley Curb and Grade Adjustments):
Issued 8/29/2014; Grades for Home Dairy
and Tompkins Trust Alley previously
issued in Conformance Set
RA to submit cost estimate for HDA
2.3.
Bulletin 21 (140 E State Storm Lateral):
Issued 8/29/2014; Vacri to provide cost
estimate
RA to submit cost estimate; two roof
storm drains to be connected to
the storm lateral inside building
2.4.
139 Benchwarmers Vault: Labella issued
8/30/14; Vacri to provide cost estimate
Vault work to be paid for as T&M; Fire
lane will be restricted on south side
2.5.
Conformance Set: Issued 8/22/2014;
Sasaki to produce bulleted list of new
changes that were not previously issued
as Bulletins; Updated TIN to be sent today
3.
CRITICAL PATH ITEMS
3.1.
Bank Alley
3.1.1.
Concrete Slab: Need sequence and
target date for pour
3.1.2.
SW Planter: Ribbon footer to be field
adjusted to account for gradechanges from curb relocation
3.1.3.
Water Feature Vault: Vacri to install
sanitary lateral and vault
3.1.4.
Tompkins Trust Alley: Vacri to start
storm install
3.1.5.
Pavilion Lighting: Vacri to install steel
after concrete slab pour; Vacri to
advise on additional costs to add
HHs, delivery date for steel
3.1.1.
SlabPour to start next week;
waiting on analysis of structural soil
from lab; No structural soil is to be
installed in the planters; Only green
screen has structural soil installed3.1.2.
ACP will make up for grade
change in grout bed
3.1.3.
WFV work to be scheduled next
week
3.1.4.
TTCEverything needs to be
cleared out of Alley, TB to contact
business owners
3.1.5.
SteelTo be installed in 4 weeks
3.1.6.
Air intake at 202 E State St is to
remain
3.2.
200 Block
3.2.1.
Light Poles: PCG surveyor located
poles; PCG to identify conflicts with
old gas main
3.2.2.
Bollards: PCG to proceed with
installation of bollards
3.2.3.
Gateways: Vacri to proceed with
3.2.1.
PCG to located gas main tomorrow
and coordinate with NYSEG to have
sections in conflict removed
3.2.2.
PCG are to install bollards per
survey offsets
3.2.3.
GatewaysAurora St gateway
foundations to be scheduled by Vacri
8/10/2019 2014-09-02 Construction Meeting Minutes.pdf
3/3
Page 3of 3
Aurora Street gateway foundations
3.2.4.
Telecom 4 Service toMarriott: PCG
to install
3.3.
Trench Drains: Vacri to provide itemized
list of material ordered
RA to review layout and ensure that
drains components are deep enough for
gaps between drains
3.4.
NYSEG Gas:Punchlist sent to NYSEG;
Benchwarmers service to be dug/installed
concurrent with vault infill work (See Item
#2.4)
NYSEG expected to retire gas main on
south side of E State St next week
4.
M&PTP: MAINTENANCE & PROTECTION
OF TRAFFIC & PEDESTRIANS
4.1.
Site Maintenance: All trash and debris
must be removed on a weekly basis
5.
New Business
Additional Notes:
SR to verify distance between slot drain and planter curb is 1 ft on Bank Alley