C:\Users\annel\AppData\Local\Temp\190116 Alexandrina Business Continuity Overarching Plan_C50D30.docx Page 1
Alexandrina CouncilBusiness Continuity Plan
Prepared by LGRS – Risk Management
Issue: Four Issue Date: 19 January 2016
1
Table of ContentsDocument Review ....................................................................................................................................3
Abbreviations and Definitions...................................................................................................................4
Introduction ...............................................................................................................................................5Purpose.................................................................................................................................................5Objectives .............................................................................................................................................5Use of the BCP .....................................................................................................................................5Assumptions..........................................................................................................................................6Limitations .............................................................................................................................................6Audience – Distribution .........................................................................................................................6Authority ................................................................................................................................................6Training and Communication................................................................................................................6Validation and Testing ..........................................................................................................................7Monitoring & review ..............................................................................................................................7Overview of Business Function Criticality.............................................................................................7Scope ....................................................................................................................................................9
Methodology ...........................................................................................................................................10
Continuity Management Team ...............................................................................................................12Roles and Responsibilities CMT.........................................................................................................12CMT – Structure..................................................................................................................................12
Notification – Declaration Process .........................................................................................................14Notification ..........................................................................................................................................14Assessment.........................................................................................................................................14Declaration ..........................................................................................................................................14Control Centre.....................................................................................................................................15Business Impact Analysis (BIA) ..........................................................................................................15Responsibility Statements...................................................................................................................15Business Continuity Instructions (BCI) ...............................................................................................15Emergency Contacts...........................................................................................................................16Initial CMT Meeting .............................................................................................................................16Communications – General ................................................................................................................16Communications – Staff......................................................................................................................17Communications – Community...........................................................................................................17General Statement to Media in the event of a business interruption event........................................17Responsibility Statements...................................................................................................................18
BCI 1 Emergency Contacts Continuity Management Team.............................................................28
BCI 2 Emergency Contacts External ................................................................................................30
BCI 2. Continuity Management Team Meeting Agenda....................................................................31
BCI 3 Staff Business Interruption Alert .............................................................................................32
BCI 4 Media Enquiry Record Form...................................................................................................33
BCI 5 Press Release ........................................................................................................................34
BCI 6 Telephone Redirection Authorisation .....................................................................................35
BCI 7 Business Continuity Coordination Centre Checklist ...............................................................36
BCI 8 Pandemic Response Information Guide.................................................................................38National, State & Local Pandemic Planning Matrix ............................................................................38Phases of Human Influenza Pandemic...............................................................................................39Recommended Actions for Australian Businesses.............................................................................40
BCI 9 Immediate Actions Guide .......................................................................................................42
2
................................................................................................................................................................43
Critical Function Sub Plans ..................................................................................................................44Organisation and Culture ....................................................................................................................45Service Centre – Call Centre............................................................................................................49Customer Service .............................................................................................................................52Engineering and Environment.............................................................................................................58CWMS.................................................................................................................................................59Food Safety Regulations ..................................................................................................................68Environmental Health Emergency Management ...........................................................................71Infrastructure & Assets........................................................................................................................74Information Management – Vital Records ......................................................................................75IT Services – Service Desk...............................................................................................................78IT Services Infrastructure.................................................................................................................80
3
Document ReviewWhenever this document is reviewed and or amended, details must be recorded on this page.
Date Review Summary
16 Jan 2014 Updated for organisation restructure and contact details
14 July 2014 Updated for BCP Maintenance Workshop on 9 July 2014
28 January2015
Updated for BCP Training Exercise on 28 January 2015
14December2015
Updated for BCP Logistical Test Exercise held on 10 December 2015
4
Abbreviations and DefinitionsTerm Definition Abbreviation
Business Continuity Is the uninterrupted availability of all key resources supportingessential business functions.
BC
Business ContinuityControl Centre
A central point of reference to co-ordinate the response to a businessinterruption event. To be established at the discretion of the CMTDirector.
BCCC
Business ContinuityManagement
Provides for the availability of processes and resources in order toensure the continued achievement of critical objectives.
BCM
Business ContinuityPlan(s)
A collection of procedures and information that is developed compiledand maintained in readiness for use in the event of an emergency ordisaster.
BCP
Business ProcessAssessment
A management tool designed to assist in the identification andassessment of criticality of business processes and functions
BPA
Business ImpactAnalysis
A management level analysis which identifies the impacts of functionloss on the organisation. The BIA provides management with dataupon which to base risk mitigation and continuity planning decisions.
BIA
Business InterruptionEvent
An event that by its duration exceeds the Maximum AcceptableOutage and / or has an adverse impact on business objectives andrequires the implementation of the BCP or sub plans.
BIE
Non Critical FunctionAction Plan
An agreed documented course of action that identifies mitigation,response and recovery actions for business functions identified asnon-critical.
Non CriticalFunctionAction Plan
Critical Function SubPlan
An agreed documented course of actions to be taken in the event ofbusiness function loss. Plan describes the key actions required underpreparation, response and recovery phases.
CFSP
ContinuityManagement Team
An assembly of executive management representatives and otherseconded staff formed for the express purpose of responding to anorganisational crisis. CMT management structure will overlay allnormal management structures during the response process.
CMT
Emergency Event An event due to an actual or imminent occurrence (such as a fire,earthquake, or epidemic which:
1. endangers or threatens to endanger the safety or health of staff orvisitors to the organisation
2. destroys or damages, or threatens to destroy or damage, propertyof the organisation
3. Has the capacity to disrupt operations to the extent that it impactson business objectives.
EmergencyEvent
Maximum AcceptableOutage
The maximum period of time that Council can tolerate the loss ofcapability of a critical business function, process, asset or ITapplication.
MAO
Corporate Governance A system by which the organisation is directed and controlled.Corporate Governance activities are represented as four principalcomponents: direction, executive action, supervision andaccountability.
CG
Risk Management The culture, processes and structures that are directed towardsrealising potential opportunities whilst managing adverse effects.
RM
InformationTechnology
The technology involved with the transmission and storage ofinformation, especially the development, installation, implementation,and management of computer systems and telephone systems.
IT
5
IntroductionPurpose
The Alexandrina Council has adopted a comprehensive and integrated approach to the development of aBusiness Continuity Management Plan. The purpose of this plan is to build organisational capabilities tosupport the continued achievements of critical business objectives in the face of uncertainty or disruption.
Council recognises that this plan (Business Continuity Plan) in isolation does not build capability; itprovides the approach to establishing effective capability. Whilst the plan is important, it is an outcome ofthe more important planning and analysis process, and is a blueprint to kick-start the response to abusiness interruption event.
This plan identifies the required facilities, technical infrastructure, key responsibilities, and processes thatwill be required to position Council to be able to respond and recover from a business interruption event.
Objectives
The objectives of the Alexandrina Council’s Business Continuity Framework is to provide a mechanismthat enables Council and its officers to:
Identify business functions that are critical to Council in meeting its business objectives
Develop resumption plans based on criticality of business functions rather than geographic location
Build resilience within Council’s operational framework
Identify and document roles and responsibilities for key staff positions
Minimise the impact of function loss on stakeholders and the community.
The business continuity plan provides a framework for management and staff to enable them toimplement an agreed response process.
In assessing the business continuity risks of the Alexandrina Council it became evident that given thestructure local government a number of inherent advantages were identified such as:
Multiple facilities providing common services reducing the impact of a single facility loss
Common IT systems with duplication and access across most facilities
Ability to transfer staff and tasks to other facilities, and
The ability to call on adjoining Councils for assistance in service delivery.
In the event of a business interruption event, these advantages would suggest the business impact is areduction in capacity rather than a loss of capability in a particular area.
Use of the BCP
This plan should be used in the event of a business interruption event that may impact on the ability of theAlexandrina Council to deliver business objectives. Managers and staff with responsibility for impactedareas of the business should use the BCP and any relevant sub plans to ensure a consistent and agreedcourse of action is implemented.
6
Assumptions
The BCP is intended to provide guidance to Council officers to assist continuity of service for criticalfunctions, where those officers are not normally responsible for managing the specific function affected.Where the Council officer who is normally responsible for managing the specific function is available, it isassumed that this document will serve as a check document to reduce the possibility for omission ofimportant actions.
Limitations
It is not the intent of this document or process to develop Information Technology Disaster RecoveryPlans. (IT DR) This process will however identify from a business perspective the business requirementsfor Information Technology resources that support the delivery of business critical function. Thisinformation should then be used to inform the development of ITDR plans.
Audience – Distribution
The intended audience for the Alexandrina Council Business Continuity Plan is:
Council
Executive Team
Critical Function Sub Plan Managers and Staff
Non Critical Function Action Plan Managers and Staff.
The plan is available to all Managers and staff via Councils intranet and is to be reviewed annually by theexecutive.
Authority
1. The Alexandrina Council Business Continuity Plan has been developed under the authority of themanaging executive. Prior to implementation the plan was reviewed and approved by that body.
2. A standing authority is given to the Sub-Plan owners by the managing executive to implement theactions identified within the sub plans.
Training and Communication
A key objective of the BCP is to increase the awareness within the Alexandrina Council of potentialbusiness interruption events that could impact Council. The plan outlines the response / recoveryprotocols associated with such an event. Training and communication will play a key role in achieving thisobjective.
Initial training has been provided by the process facilitators however one of the benefits of a facilitatedprocess is that engagement and ownership of the BCP is developed at the business unit level. Trainingwas provided to the Senior Management Team as part of the BCP implementation. It will be theresponsibility of the various Senior Managers to ensure that the requirements of the BCP arecommunicated to all staff and that induction / training programs include reference to business continuity inthe context of sound risk management practices.
Managers should be familiar with key deliverables as detailed in the Critical Function Sub Plans andensure that staff are aware of their roles and responsibilities in the event of a business interruption event.
7
Validation and Testing
Business Continuity Management is a process, not an event. Once the BCP has been preparedcommitment to a pre-planned, annual test plan and maintenance schedule is required by Council toensure BCP procedures remain viable into the future.
The testing should include all aspects of the BCP, but not necessarily all in one year. Major components(Sub Plans) should be reviewed at least annually. Volatile information such as contact lists, or areas thatare constantly undergoing changes, should be validated more frequently.
In addition to the annual test and review of the BCP, any significant changes in the Alexandrina Council’soperations should also trigger a review of the BCP. Version control of the BCP should be co-ordinatedthrough the CMT – Coordinator.
Monitoring & review
Monitoring and review is an integral component of the BCP process. Council recognises and iscommitted to ensure the following monitoring and review strategy is implemented.
Activity for Review Accountability Timeframe
1 Business Continuity Plan (overarching plan) Continuity ManagementTeam via the CMTCoordinator
Monitor annually and actionas required
2 Business Continuity Plan Training Continuity ManagementTeam via the CMTCoordinator
Annual training brief orrefresher session
3 Business Continuity Plan Exercise Continuity ManagementTeam via the CMTCoordinator
Annual desk top exercise
Simulation exercise each 2years
Organisational and Culture
4 Critical Function Sub Plans Relevant Manager Annual Review
4a Non Critical Function Action Plans Annual Review
Infrastructure and Assets
5 Critical Function Sub Plans Relevant Manager Annual Review
5a Non Critical Function Action Plans Annual Review
Engineering and Environment
6 Critical Function Sub Plans Relevant Manager Annual Review
6a Non Critical Function Action Plans Annual Review
Overview of Business Function Criticality
Integral to the BCP is the determination of the Maximum Acceptable Outage (MAO) of a particularbusiness process. The loss of a critical business function for a period greater than the MAO will generally
8
result in the establishment of the Continuity Management Team to direct, oversee and support theemergency, continuity and recovery response phases.
The following table summarise the functions as identified as critical, the maximum acceptable outage forthat function and what Information Technology services are required to facilitate resumption.
Division/Group Organisation & Culture
Business Unit Critical Function Max Acceptable Outage
Human Resources Payroll processing 1-5 Days - shorten
Governance & Strategy Communications / Public Relations 1-2 hours
Library & Customer Service Service Centre – Call Centre 2 hours
Library & Customer Service Customer Service 2 hours
Division/Group Engineering & Environment
Business Unit Critical Function Max Acceptable Outage
CWMS Treatment Plant Operation 4 hours - 2 Weeks
CWMS Pump Station Operation 4 hours - 2 Weeks
CWMS Vacuum Operation 4 hours - 2 Weeks
Roads Road Services 1 – 20 days
Waste Management Waste Collection 2 Days
Environmental Health Food & Safety Regulation 1 day
Environmental Health Environmental Health & EmergencyManagement Activities
1 day
Division/Group Infrastructure & Assets
Business Unit Critical Function Max Acceptable Outage
IT Service Desk Internal 1-14 Days
IT IT Infrastructure Internal 1-14 Days
IT IT advisory – Service Desk 1-14 Days
IT IT advisory – ICT Infrastructure 1-14 Days
IT Information Management Immediate to 2 weeks
9
Scope
The object of the BCP is to ensure that appropriate structures and protocols are in place that enableseffective response to a business interruption event that has the potential to impact on council’s objectives.The BCP documents the processes and resources required by Council in the delivery of its criticalbusiness objectives.
In identifying business continuity risks, the focus is on the building of resilience and response capabilitieswithin business functions that have been identified as critical by the organisation. Treatment options fornon-critical functions are also identified and documented within the framework; this ensures that Councilhas a whole of organisation view when responding to interruption events, as the nature of these eventscan change rapidly.
The BCP does not cover requirements associated with a workplace emergency (safety) situation. Aseparate workplace emergency plan that is the responsibility of the Chief Warden / Emergency Servicesis to be implemented. In all cases of activation of the workplace emergency plan the Chief Warden willbrief the Director of the Continuity Management Team of any implications for business continuity as aresult of the emergency plan activation.
Risk Management Framework
Alexandrina Council
Business ContinuityPlan
Workplace Emergency &Evacuation Plan
Council EmergencyManagement Plan via
I-responda
Organisationand Culture
Engineeringand
Environment
Infrastructure &Assets
CriticalFunction Sub-
plans
Non CriticalFunction Action
Plans
Non CriticalFunction Action
Plans
Non CriticalFunction Action
Plans
CriticalFunction Sub-
plans
CriticalFunction Sub-
plans
IT Disaster Recovery Plan
10
MethodologyBusiness continuity encompasses the identification and risk management of Council’s businessprocesses. It involves a stepping process that seeks to identify, assess control and monitor Council’sbusiness functions. The plan has been developed with consideration given to AS/NZS 5050:2010Business continuity - Managing disruption-related risk, AS/NZS/ISO 3100:2009 Risk Management-Principles and guidelines and the ANAO Business Continuity Management guidelines – “Keep the wheelsin motion”, and Societal Security – Guidelines for incident preparedness and operational continuitymanagement (ISO N022: 2007).
Broadly, the steps in developing the Business Continuity Plan include:
1. Identify and Assess Business Processes and FunctionsIdentify business processes and functions within each individual business unit/section/division. Oncethe functions are identified an analysis at a whole of organisational level is conducted to determinewhich functions are critical and require further planning to ensure the ability to respond in the face ofa continuity interruption event.
2. Conduct the Business Impact Analysis (BIA)The BIA Is conducted on those functions identified as critical within the business processassessment. The BIA is intended to identify the impacts of the function loss on the business includingpenalties for non-delivery, functional interdependencies, organisational ownership, it also looks at theresources currently required to support the functions and assesses the minimum level of resourcesrequired to continue the availability. Importantly the BIA is the tool that is used to determine theMaximum Acceptable Outage (MAO).
3. Critical Function Sub Plan (CFSP) & Non Critical Function Action PlansThe CFSP identifies the agreed actions that a business process owner will undertake to manage theloss of the function through the emergency, continuity and recovery phases. The sub plan identifiesownership, failure scenarios, and criteria for invoking the plan, agreed courses of actions foremergency, continuity and recovery. The CFSP also allows for targeted messages to be developedfor specific function loss.
The Non Critical Function Action Plans are designed to assist the organisation in adopting a riskmanagement approach to the identification, assessment control and monitoring of those businessfunctions determined in the planning phase as non-critical.
4. Overarching Business Continuity Plan (BCP)The BCP identifies the responsibilities of key Managers, with particular emphasis on direction settingand effective and timely communication to stakeholders at an organisational level. It is important torecognise that this document provides a flexible framework in which the organisation can plan fordisruption of its critical functions. It does not attempt to identify and plan for every contingency oroutage that could occur, it provides a flexible framework for the process owners to identify, plan anddevelop redundancy for business processes.
5. Test and maintain the BCPThe BCP will be reviewed annually by the Executive, these actions are essential to ensure that itreflects the current practices of the organisation.
Testing of the Critical Function Sub plans and overarching plans will provide management assurancethat the plan(s) are effective. The testing regime is based on the following:
11
Desktop / paper audit to ensure that the appropriate documents are available and understood; forsub plans and overarching plan
Structured “walk through” where a business interruption scenario is played out through a mockrecovery; and a divisional or whole of organisation level, and
Frequency and actions to be undertaken are identified within the monitoring and review section ofthis document.
12
Continuity Management Team
Roles and Responsibilities CMT
The CMT is established to provide a management mechanism that can ensure reporting lines andresponsibilities are clear when the BCP is activated. The focus of the CMT is to manage the businessinterruption event from a corporate perspective while providing guidance and support to the Managers onsite. This process is facilitated by the development of pre-determined courses of actions (Sub plans) thusallowing the CMT to focus on the strategic or whole of business response to the business interruptionevent. Resilience within the CMT is the responsibility of the CMT. Each position is to have an alternatemember identified and trained in the role.
CMT – Structure
Mayor(Community
engagement)
CMT DirectorChief Executive
CMT MemberEngineering
andEnvironment
CMT MemberPlanning &
Development
CMT MemberLibrary &CustomerService
CMT MemberInformationTechnology
CMT MemberOrganisationand Culture
CMTCoordinator
ManagerGovernance &
Strategy
CMT SupportCMT
CommunicationsOfficer
13
CMT Position Staff Position Alternate Staff Position
CMT Director Chief Executive General Manager Infrastructure &Assets
CMT Member General Manager Engineering andEnvironment
General Manager Infrastructure &Assets
CMT Member Manager IT Services ICT Infrastructure & SecurityCoordinator
CMT Member Manager Planning and Development Manager Infrastructure
CMT Member Manager Library & Customer Service Coordinator, Customer Service
CMT Member General Manager Organisation and Culture Manager Human Resources
CMT Coordinator Manager Governance and Strategy Manager Health, Environment andCommunity Safety
CMTCommunications
Communications Officer Executive Assistant
CMT Support Planning & Development AdministrativeAssistant
Personal Assistant, Organisation &Culture
14
Notification – Declaration ProcessNotification
On first becoming aware of a possible business continuity event, the relevant function manager isrequired to assess the situation and if the event is likely to exceed the agreed “MAO timeframe”, then theCMT Director should be notified immediately by phone and where possible, with a follow-up email orpersonal briefing detailing the key issues including:
Nature of the incident – time informed etc.
Describe business elements impacted (Critical Functions)
Facility / equipment impacted
Staff
Any response actions implemented (Critical Function Sub Plan)
Any media involvement / interest
Any immediate support requirements.
Elements of the BCP (Sub Plans) can be implemented at the local level, where appropriate to address animmediate response requirement even if the event is expected to be resolved within an acceptableperiod.
Assessment
On receipt of a notification that will impact business continuity the CMT Director will:
Formally note details
Notify the other members of the Continuity Management Team (CMT) (consider Telstra conferencecall)
Confirm the details of the incident and appropriate media strategies
Conduct preliminary impact assessment (facility and technology infrastructure)
Determine if a control centre needs to be opened.
Ensure that the Insurer has been formally notified (if appropriate)
Declaration
The CMT Director is to review the preliminary information and if considered necessary declare a BusinessInterruption Event.
The CMT Director is to facilitate the draft communications, both internal and external, for discussion at theinitial CMT meeting.
15
Control Centre
On the declaration of a business interruption event by the Director CMT and if deemed appropriate acontrol centre will be opened. The resourcing and opening of this centre is the responsibility of the CMTcoordinator. Given the variable nature of Business Continuity Events, the following sites have beenidentified and prioritised.
If the incident does not impact on the Alexandrina Council, Administration Building:
1. Council Chambers,
If the Council Chambers is uninhabitable then:
2. Goolwa Depot - meeting room.
3. Strathalbyn Council Office
Business Impact Analysis (BIA)
Central to ensuring the ongoing viability of the business in an interruption event is the identification ofcritical business functions, the processes and assets (people & property) that support the delivery ofthese critical functions and the impact of the loss of the functions on the business are analysed within aBusiness Impact Analysis. BIA’s have been completed for each of the identified critical functions and arecontained within the Critical Function Sub Plans.
Responsibility Statements
Responsibility Statement for each position in the CMT and supporting positions have been developed toensure there are clear and unambiguous directions available for each of the members of the CMT. Allresponsibility statements are to be approved by the CMT and this action is to be recorded on thestatement. On activation of the BCP these statements come into effect.
Business Continuity Instructions (BCI)
Upon declaration of an interruption event the following instructions have been developed to provideassistance. However, any restoration plan developed by the CMT will take precedence over therespective instruction.
Instruction Title
Emergency Contacts
CMT Sample Meeting Agenda
Staff Business Interruption Alert
Media Enquiry Record Form
Press Release
Telephone Redirection Authorisation
Business Continuity Coordination Centre Checklist
Pandemic Response Information Guide
16
Emergency Contacts
A list of Emergency Contacts has been prepared including all nominated members of the CMT, theirdesignated deputies as well as key external services.
A copy of this listing should be held off premises by respective CMT & members and identified alternatesto enable the listing to be referenced in the event that access is denied to the premises.
Initial CMT Meeting
The CMT Director is to call the initial CMT meeting to obtain more detailed information from the relevantbusiness areas impacted, including:
Staff
Any associated Emergency Services issues
Building facilities
Public relations/media
Damage/security, and
Salvage of building and/or IT equipment.
Salvage of records
Review and conformation of delegation of authorities for staff.
Ensure all team members understand their responsibilities and their assigned tasks.
During the meeting information will have been gathered by the various CMT members to produce anevaluation of the incident. A formal record of the meeting to be collated by CMT Support person withparticular emphasis on items to be actioned. This record needs to be regularly reviewed and updated asadditional information comes to hand.
The CMT Director to manage the restoration of business activities in line with the responsibilities definedin the BCP.
Communications - General
All communications will be coordinated through the Continuity Management Team
Due to the nature of the media, the timeliness of reporting in these circumstances is critical. Promptreporting to, and liaison with the Continuity Management Team is in the best interests in terms of allowingfor the preparation of an appropriate response.
The CE will develop the communications strategy that enables for:
News releases to the media Communications between council and the emergency management control agencies Communications to staff Communication to contractors and other external contractors
17
It is Alexandrina Council’s policy that no person other than the Chief Executive Officer (or delegatedGeneral Manager) and/or Mayor divulges any information to the media. This extends to contractors andother service providers and agencies and should be communicated in any site contractor agreements.
In the initial stages of an event the Continuity Management Team will schedule briefings at a designatedlocation. The Continuity Management Team will determine who will attend these meetings and if themeetings are in part or entirely, open to the media, members of the public and staff. Timing andfrequency of the briefing meetings will be matched to severity of the event.
Communications - Staff
In the event of a business interruption event which significantly impacts on the service delivery of Councilservices a staff message will be communicated by email, sms or UHF radio broadcast (BCI 3). Thismessage should be initiated as soon as possible to avoid high volume of traffic on the network regardingdetails of the event. A more formal staff briefing by the Chief Executive Officer, should be undertakenfollowing the Initial Meeting of the continuity Management Team.
Communications - Community
Alexandrina Council Communications Officer will be responsible for the delivery of communications andmedia actions on advice from the Continuity Management Team. The Communications Officer will:
Provide a focal point for media releases and statements to the media Schedule requests for media interviews with the Chief Executive Officer or Mayor Manage the operations and logistics of the media briefings, including time, location, facilities,
content and expectations Monitor and respond to rumours regarding the Council response and continuity management
actions Ensure staff are adequately informed
General Statement to Media in the event of a business interruption event
In the event of a major incident, particularly after-hours, there may be a period of time elapsed before thedesignated media spokesperson is in a position to respond to media enquiries. Should any staff memberbe approached by media representatives for a comment they are only authorised to make the followingstatement:
"I am sorry, but I am not authorised to make any statement at this time. The appropriatepersonnel are currently being briefed on the situation and a spokesperson will beavailable to talk to you shortly”
There is no such thing as an “off the record” comment.
If you cannot immediately refer the journalist to the CE, please complete the Media Enquiry Record Form.
Let the journalist know that someone will return their call promptly.
Provide the Manager Media and Communications with the journalist’s details as soon as possible. Alsoprovide any background and relevant information that you have about the event, including how thejournalist came to contact you.
19
Responsibility Statement – CMT Director
Position CMT Director Staff Position Chief Executive
During absence this role will be assumed by General Manager Infrastructure & Assets
Position Statement The CMT Director is responsible for declaring a business continuity eventand invoking the BCP.
The CMT Director is required to oversee and manage all resumptionactivities.
During a workplace emergency the Chief Warden has authority until theworkplace emergency is resolved and control is returned to the CE orCMT Director if the BCP is to be activated
Knowledge Requirements 1. High level of organisation activities and service delivery priorities
2. Community, Business and Regulatory contacts
Responsibilities The CMT Director must make decisions as to the best strategy for businessresumption based on information received by other CMT members. Thisstrategy is then translated into an action plan by the supporting teams.
Responsibilities include:
Maintain working knowledge of BCP & relevant Critical Function SubPlans
Participate in monitor and review activities
Participate in and ensure appropriate levels of training is undertaken
On Activation:
Activate the BCP
Notifying and liaising with stakeholders
Provide the focal point in communication to the staff, media and public
Establishing and chairing all CMT meetings (may delegate)
Authorisation of any detailed restoration plan
Delegate tasks and overseeing resumption activities
Monitor the gathering of business interruption event information
Promote the wellbeing and safety of all staff
Liaise with elected body via the Mayor
Date approved by CMT 25 July 2012
20
Responsibility Statement – CMT Member Engineering and Environment
Position CMT Member Staff Position General Manager Engineering andEnvironment
During absence this role will be assumed by General Manager Infrastructure & Assets
Position Statement A successful Continuity Management Team (CMT) relies on expertise fromwithin the organisation as they are the people that understand the businessprocesses and related risks. Accordingly, the Executive and Manager Teammembers are the designated members of the CMT and charged withimplementing the whole of organisation response. However they stillmaintain responsibility for the continuity and recovery actions of theirindividual business units. The business unit activities are undertaken by thefunction managers in accordance with agreed sub plans.
Knowledge Requirements 1. High level of group activities and service delivery priorities2. High level knowledge of group critical function sub plans
3. High level knowledge of overarching BCP
Responsibilities Responsibilities include:
Maintain working knowledge of BCP & relevant Critical Function SubPlans
Participate in monitor and review activities
Participate in and ensure appropriate levels of training are undertakenwith Critical Function Sub Plan Managers
On Activation:
Operate as a member of the CMT
Ascertain the impact on business unit activities and report to CMT
Co-ordination of business unit Critical Function Sub Plan implementationas required
Monitoring implementation against the Business Continuity Plan
Maintaining information and report on costs to CMT
Maintain communications with staff
Date approved by CMT 25 July 2012
21
Responsibility Statement – CMT Member IT Services
Position CMT Member Staff Position Manager IT Services
During absence this role will be assumed by ICT Infrastructure & Security Coordinator
Position Statement A successful Continuity Management Team (CMT) relies on expertise fromwithin the organisation as they are the people that understand the businessprocesses and related risks. Accordingly, the Executive and Manager Teammembers are the designated members of the CMT and charged withimplementing the whole of organisation response. However they stillmaintain responsibility for the continuity and recovery actions of theirindividual business units. The business unit activities are undertaken by thefunction managers in accordance with agreed sub plans.
Knowledge Requirements 1. High level of group activities and service delivery priorities2. High level knowledge of group critical function sub plans
3. High level knowledge of overarching BCP
Responsibilities Responsibilities include:
Maintain working knowledge of BCP & relevant Critical Function SubPlans
Participate in monitor and review activities
Participate in and ensure appropriate levels of training are undertakenwith Critical Function Sub Plan Managers
On Activation:
Operate as a member of the CMT
Ascertain the impact on business unit activities and report to CMT
Co-ordination of business unit Critical Function Sub Plan implementationas required
Monitoring implementation against the Business Continuity Plan
Maintaining information and report on costs to CMT
Maintain communications with staff
Date approved by CMT 25 July 2012
22
Responsibility Statement - CMT Member Planning & Development
Position CMT Member Staff Position Manager Planning andDevelopment
During absence this role will be assumed by Manager Infrastructure
Position Statement A successful Continuity Management Team (CMT) relies on expertise fromwithin the organisation as they are the people that understand the businessprocesses and related risks. Accordingly, the Executive and Manager Teammembers are the designated members of the CMT and charged withimplementing the whole of organisation response. However they stillmaintain responsibility for the continuity and recovery actions of theirindividual business units. The business unit activities are undertaken by thefunction managers in accordance with agreed sub plans.
KnowledgeRequirements
1. High level of group activities and service delivery priorities2. High level knowledge of group critical function sub plans
3. High level knowledge of overarching BCP
Responsibilities Responsibilities include:
Maintain working knowledge of BCP & relevant Critical Function SubPlans
Participate in monitor and review activities
Participate in and ensure appropriate levels of training are undertakenwith Critical Function Sub Plan Managers
On Activation:
Operate as a member of the CMT
Ascertain the impact on business unit activities and report to CMT
Co-ordination of business unit Critical Function Sub Plan implementationas required
Monitoring implementation against the Business Continuity Plan
Maintaining information and report on costs to CMT
Maintain communications with staff
Date approved by CMT 25 July 2012
23
Responsibility Statement - CMT Member Library & Customer Service
Position CMT Member Staff Position Manager Library & CustomerService
During absence this role will be assumed by Coordinator, Customer Service
Position Statement A successful Continuity Management Team (CMT) relies on expertise fromwithin the organisation as they are the people that understand the businessprocesses and related risks. Accordingly, the Executive and Manager Teammembers are the designated members of the CMT and charged withimplementing the whole of organisation response. However they stillmaintain responsibility for the continuity and recovery actions of theirindividual business units. The business unit activities are undertaken by thefunction managers in accordance with agreed sub plans.
KnowledgeRequirements
1. High level of group activities and service delivery priorities2. High level knowledge of group critical function sub plans
3. High level knowledge of overarching BCP
Responsibilities Responsibilities include:
Maintain working knowledge of BCP & relevant Critical Function SubPlans
Participate in monitor and review activities
Participate in and ensure appropriate levels of training are undertakenwith Critical Function Sub Plan Managers
On Activation:
Operate as a member of the CMT
Ascertain the impact on business unit activities and report to CMT
Co-ordination of business unit Critical Function Sub Plan implementationas required
Monitoring implementation against the Business Continuity Plan
Maintaining information and report on costs to CMT
Maintain communications with staff
Date approved by CMT
24
Responsibility Statement - CMT Member General Manager Organisation & Culture
Position CMT Member Staff Position General Manager Organisationand Culture
During absence this role will be assumed by Manager Human Resources
Position Statement A successful Continuity Management Team (CMT) relies on expertise fromwithin the organisation as they are the people that understand the businessprocesses and related risks. Accordingly, the Executive and Manager Teammembers are the designated members of the CMT and charged withimplementing the whole of organisation response. However they stillmaintain responsibility for the continuity and recovery actions of theirindividual business units. The business unit activities are undertaken by thefunction managers in accordance with agreed sub plans.
KnowledgeRequirements
1. High level of group activities and service delivery priorities2. High level knowledge of group critical function sub plans
3. High level knowledge of overarching BCP
Responsibilities Responsibilities include:
Maintain working knowledge of BCP & relevant Critical Function SubPlans
Participate in monitor and review activities
Participate in and ensure appropriate levels of training are undertakenwith Critical Function Sub Plan Managers
On Activation:
Operate as a member of the CMT
Ascertain the impact on business unit activities and report to CMT
Co-ordination of business unit Critical Function Sub Plan implementationas required
Monitoring implementation against the Business Continuity Plan
Maintaining information and report on costs to CMT
Maintain communications with staff
Date approved by CMT 25 July 2012
25
Responsibility Statement – CMT Co-ordinator
Position CMT Co-ordinator Staff Position Manager Governance and Strategy
During absence this role will be assumed by Manager, Health Environment and Community Safety
Position Statement The CMT Co-ordinator is required to assist the CMT Director in themanagement of the business resumption activities. The CMT Co-ordinatormust be familiar with the business continuity plan, Critical function Sub Plansand team responsibilities.
Knowledge Requirements 1. High level knowledge of overarching BCP
2. Understanding of organisation activities and service deliverypriorities
3. High level of internal key contacts and accountabilities
Responsibilities The CMT Co-ordinator is required to report to the CMT on the currency ofindividual and business level continuity plans and activities.
Responsibilities include:
Pre event co-ordination of BCP and Sub plans with relevant owners
Co-ordination of training for CMT & CMT SG members
Co-ordination of testing for the Business Continuity Plan
Resourcing of Control Centre
On Activation:
Open Control Centre on direction of CMT Director
Assisting CMT Director as required
Notify Insurer and manage the insurance requirements
Date approved by CMT 25 July 2012
26
Responsibility Statement – CMT Communications
Position CMTCommunications
Staff Position Communications Officer
During absence this role will be assumed by Executive Assistant
Position Statement The CMT Communications is responsible for communicating messages ofthe Control Centre (if established).
Knowledge Requirements 1. High level of knowledge of organisation communications methods
2. High level of internal key contacts and resource knowledge
Responsibilities Responsibilities include:
Maintain working knowledge of BCP & relevant Critical Function Sub Plans
Maintain high level of communications skills
On Activation:
If required, assist with the crafting of communications messages of the ControlCentre
Assist the CMT Director and Mayor with media liaison
Distribute communications messages using key communications metholds
Date approved by CMT
27
Responsibility Statement – CMT Support
Position CMT Support Staff Position Planning & DevelopmentAdministration Officer
During absence this role will be assumed by Personal Assistant, Organisation and Culture
Position Statement The CMT Support is responsible for the smooth functioning of the ControlCentre (if established) and the administrative needs of the CMT.
Knowledge Requirements 1. High level of internal key contacts and resource knowledge
2. High level of administrative functions and arrangements
Responsibilities Responsibilities include:
Maintain working knowledge of BCP & relevant Critical Function Sub Plans
Maintain high level of administration skills
On Activation:
If required, assist with the setup of the Control Centre and arranging stationery,equipment etc.
Arrange resources to assist CMT members (if required)
Making arrangements for all CMT meetings
Provide general administrative support (including log of all events and actions,resumption status, CMT members’ movements etc.).
Create and maintain a chronological log of meetings and decisions made.
Date approved by CMT
28
BCI 1 Emergency Contacts ContinuityManagement Team
CMT Position Staff Position Contact Details Alternate StaffPosition
Contact Details
CMT Director Chief ExecutiveOfficer
Ph.: 08 8555 7023
H: 08 7324 2594M: 0409 699 [email protected]
General ManagerInfrastructure andAssets
Ph.: 08 8555 7019H: 08 8554 6572M: 0438 557 [email protected]
CMT Member General ManagerEngineering andEnvironment
Ph.: 08 8555 7057
H: 08 85541878M: 0419 864 130
040 769 [email protected]
General ManagerInfrastructure andAssets
Ph.: 08 8555 7019H: 08 8554 6572M: 0438 557 [email protected]
CMT Member Manager IT Services Ph.: 08 8555 7007
H: 8552 7957
M: 0407 716 [email protected]
ICT Infrastructureand SecurityCoordinator
Ph.: 08 8555 7060H: 08 8555 0214M: 0439 683 [email protected]
CMT Member Manager Planning &Development
Ph.: 08 8555 7002
H: 08 8537 0230M: 0437 911 [email protected]
ManagerInfrastructure
Ph: 08 8555 7097
H: 8555 2661
M: 0439 181 163
CMT Member Manager Library &Customer Services
Ph.: 08 8555 7091
H: 8596 7389M: 0409 860 162
Coordinator,Customer Service
Ph.: 08 8555 7087
H: 0437 818 121M: 0448 032 868
CMT Member General ManagerOrganisation &Culture
Ph.: 08 8555 7022
H: 08 8552 8773M: 0437 713 [email protected]
Manager HumanResources
Ph.: 08 8555 7095H: n/aM: 0427 208 [email protected]
CMT Coordinator Manager Governanceand Strategy
Ph.: 08 8555 7017
H: 0417 420 197M: 0439 700 [email protected]
Manager, Health,Environment andCommunity Safety
Ph.: 08 8555 7225H: 0403 220 562M: 0439 802 [email protected]
29
CMTCommunications
CommunicationsOfficer
Ph.: 08 8555 7084H: 0415 760 996M: 0488 555 [email protected]
ExecutiveAssistant
Ph.: 08 8555 7044H: 8555 2955
M: 0417 892 [email protected]
CMT Support Planning andDevelopmentAdministration Officer
Ph.: 08 8555 7096H: 8555 4034
PersonalAssistant,Organisation andCulture
Ph.: 08 8555 7032H: 8555 3464
M: 0407 187 [email protected]
30
BCI 2 Emergency Contacts External
Service Company Contact Details
Air Conditioning Westside Services 08 8347 7712
Electricity DS&R Electrical 0417 855 4500419 848 229
Plumbing Horseshoe Bay Plumbing 0407 600 588
Police Goolwa Police Station 08 8555 2018
Security Victor Harbour Security 0405 389 814
IT Computer Site Solutions/InterstateElectrical
Information Management Steamatic 1300 783 262
31
BCI 2. Continuity Management TeamMeeting Agenda
Initial CMT Meeting
The CMT Director is to call the initial CMT meeting to obtain more detailed information from the relevantbusiness areas impacted, including:
Staff
Any associated Emergency Services issues
Building facilities
Public relations/media
Damage/security,
Salvage of building and/or IT equipment, and
Salvage of records
During the meeting information will have been gathered by the various CMT members to produce anevaluation of the incident. A formal record of the meeting to be collated by CMT Support person withparticular emphasis on items to be actioned. This record needs to be regularly reviewed and updated asadditional information comes to hand.
Other Issues for consideration include
Scheduling of site visit
Identification of affected departments
Public notification
Schedule of staff meetings
Development of initial plan for operations (short term)
Allocation of temporary work locations.
32
BCI 3 Staff Business Interruption AlertSituation
At (insert time) on (insert date) the (insert Council) experienced (insert event) which has impacted on(insert impacts). The following services have been lost (insert losses). As a consequence the ChiefExecutive Officer has declared a Business Interruption Event and has opened the Business ContinuityCoordination Centre (BCCC) to allow the Continuity Management Team to restore Council’s criticalbusiness functions.
Plan
Council is now operating in a continuity management phase with normal operations temporary varied toensure Council can continue to provide key services to our customers. The continuity management teamis reassessing the allocation of personnel which may involve reassignment of staff to new roles with theorganisation.
Administration
The continuity management team is as follows:
CMT Director
CMT Team Members
CMT Coordinator
CMT Support
A staff briefing will be conducted at (insert time) at (insert location) to discuss Councils strategy and therole you will play in restoration. Meanwhile, all staff must ensure they have access to the followingresources (insert resources) and protective clothing (insert clothing requirements)
All continuity actions must be authorised by the CMT Director.
All staff must keep a personal log of actions and requests.
Communications
The BCCC can be contacted on (insert telephone number).
The primary mode of communication within the organisation will be (insert communication method). As aresult priority will be given to the following functions (insert functions).
Council’s business telephone number has been temporarily diverted to (insert location).
CMT Director
Insert Time
Insert Date
33
BCI 4 Media Enquiry Record FormTaken by:
Issue:
Date: Time of call:
Journalist name:
Contact numbers:
Media outlet:
Deadline:
Publication date:
Question:
Taken by:
Issue:
Response by:
Position in (Insert Client Name):
Response
Date: Time:
34
BCI 5 Press ReleaseOn (insert day and date) at approximately (insert time) Council experienced a business interruption event(describe event) as a result of this event the following services are currently impaired:
Rates
Water & Sewer
Roads
Community Services.
Services that are not impacted by the business interruption include:
Libraries
Swimming pools
Meals on wheels
Etc.
Workarounds are currently being put in place in line with Council’s Business Continuity Strategy.
Council will advise the community via the media once service delivery strategies have been confirmed
Councils contact number remains (insert number) ant will be manned from (insert times) until furthernotice
Issued by
Chief ExecutiveAlexandrina CouncilTimeDate
35
BCI 6 Telephone Redirection AuthorisationNote that telephone redirection has not been setup by LGRS. Indications from Telstra are that clientswill need to provide the following information to effect a redirection on phone numbers.
Company name
ABN
Billing Address
Redirection numbers.
Only Authorised council account holders will be able to authorise effect and will need to be preauthorised.
Emergency Redirections can be obtained with the above information by calling 13 22 55 TelstraCorporate Faults.
The following may be used to confirm your requirements with Telstra:
(Date)(Council)(Address)(Town State Post Code)
The ManagerTelephone Redirections
Dear Sir/Madam
(Insert Council Name) is in the process of activating its Business Continuity Plan in response to abusiness interruption event.
This fax is to request in writing Telstra immediately redirect the current (insert council name and number)to (insert alternate site name and number).
Council will inform Telstra again in writing when a change to this arrangement is required.
If you need clarification or to speak to a Council Representative please call (insert Mobile Number of CMTmember).
Issued by
Chief ExecutiveAlexandrina CouncilTimeDate
36
BCI 7 Business Continuity CoordinationCentre Checklist
Business Continuity Coordination Centre – Council Chambers
Element Issues to be addressed Actions Required
Location of BCCC The location of the Alexandrina Council CoordinationCentre is the Council Chambers within theadministration building providing that the building is notsubject to the interruption event
Alternate Location ofBCCC
1. Goolwa Depot meeting room
Diagram of BCCC
Provisions oftelecommunicationsfacilities
Mobile phonesFixed phones x 30 (Council Chambers)
Provision of internetfacilities
Internet available via fixed computers, laptop – remoteaccess and smart phones
Emergency powerrequirements forBCCC
UPS and cashiers and switchboard (1-2 hour use)Council Administration building has auto emergencypower for selected circuitsDepot has emergency power for centre building
Review dieselstorage at GoolwadepotReview Emergencypower circuit forchambers to ensurefunctionality
Management andStaffing
See Responsibility Statements for nominated positions
CMT Director
CCMT Member
CMT Coordinator
CMT Support Officer
Security Contracted proximity access for Administration buildingand depot
Media CE, Mayor and relevant General Managers ifunavailable Communications Officer
Initial level ofactivation
Stages of OperationActivation
Meeting or conference call to consider businessinterruption event and full team on declaration
37
Business Continuity Coordination Centre – Council Chambers
Information Displays Information Board required in BCCC
Current Operations Display Board, showing all taskscurrently being carried out
Contacts Display Board Used to display importantcontact telephone and fax numbers in regular use
Resources Allocation Board Showing resourceslocation, resources committed and resources available
Staff Rosters for longer or protracted use of the BCCC
Timing Details recording of Briefing, meetings SituationReport etc.
Media Releases Copies of publicly released materials
Plans and Documents Hard and soft copies of BCP, including Critical FunctionSub Plans
Administration Stationary Equipment list to be developed by the CMTcoordinator
Extended Operations Staff Roster to be developed if protracted use of theBCCC is expected
Briefing Sessions Suitable briefing timing sessions to be identified by theCMT
1. Staff
2. Media
3. Community
4. Elected Members
Stages of OperationStand down
Stand down of the BCCC will be at the discretion of theCMT Director
A stand down of the coordination centre may be agradual phasing down over a period of time or it may beimmediate cessation of the operation
Forms CMT Coordinator to identify suitable forms to be used tocollect and record information within the BCCC
Date approved byCMT
25 July 2012
38
BCI 8 Pandemic Response InformationGuide
If a pandemic of any description was to eventuate within any local government area, it is probable thatstate level disaster plans would be activated; these plans are separate to Business Continuity Plans andhave a community response focus.
Currently it is a requirement of the National Action Plan for Human Influenza Pandemic for all localgovernment authorities to have in place a Business Continuity Plan.
The Alexandrina Council BCP model places the importance on identifying what functions are critical to thebusiness in delivering it objectives, identifying likely failure scenarios (Pandemic, loss of IT etc.) for thosecritical business functions and then developing plans to ensure the continuity of those critical functions.
A pandemic event occurring may result in the failure scenario occurring “loss of critical staff”. It is theimpact of that loss scenario that the business continuity plan is design to respond to.
National, State & Local Pandemic Planning Matrix
National Action Planfor Human Influenza Pandemic
CommonwealthGovernment
Action Plan forInfluenzaPandemic
Australian HealthManagement Plan forPandemic Influenza
State and Territoryemergency
management plans
State and Territoryinfluenza pandemic
plans(including health
plans)
CommonwealthDisaster Response
Plan
Australian VeterinaryEmergency PlanNational Response Planfor Mass CasualtyIncidents InvolvingAustralians OverseasNational Food ChainContinuity Plan –Pandemic Othernational plans
OtherCommonwealth
Plans Other State andTerritory plans
District & Localemergency
managementplans
CouncilBusinessContinuity
Plan
CouncilBusiness IT
DisasterRecovery Plan
Local Government
Commonwealth
State/Territory
National
KEY
39
Phases of Human Influenza Pandemic
Globalphase
Australianphase
Description of phase AHMPPI 2008
REC
OVE
RY
PREV
ENTI
ON
AN
D P
REP
AR
EDN
ESS
AUS 0 No circulating animal influenza subtypes inAustralia that have caused human disease
Australian phases
1
Overseas1
Animal infection overseas: the risk of humaninfection or disease is considered low
AUS 1 Animal infection in Australia: the risk of humaninfection or disease is considered low
2
Overseas2
Animal infection overseas: substantial risk ofhuman disease
AUS 2 Animal infection in Australia: substantial risk ofhuman disease
3
Overseas3
Human infection overseas with new subtype/s butno human to human spread or at most rareinstances of spread to a close contact
ALERT
AUS 3Human infection in Australia with new subtype/sbut no human to human spread or at most rareinstances of spread to a close contact
RES
PON
SE
4
Overseas4
Human infection overseas: small cluster/sconsistent with limited human to humantransmission, spread highly localised, suggestingthe virus is not well adapted to humans
DELAY
AUS 4Human infection in Australia: small cluster/sconsistent with limited human to humantransmission, spread highly localised, suggestingthe virus is not well adapted to humans
5
Overseas5
Human infection overseas: larger cluster/s buthuman to human transmission still localised,suggesting the virus is becoming increasinglybetter adapted to humans, but may not yet be fullyadapted (substantial pandemic risk)
DELAY
AUS 5
Human infection in Australia: larger cluster/s buthuman to human transmission still localised,suggesting the virus is becoming increasinglybetter adapted to humans, but may not yet be fullyadapted (substantial pandemic risk)
6
Overseas6
Pandemic overseas: increased and sustainedtransmission in general population DELAY
AUS 6a Pandemic in Australia: localised (one area ofcountry) CONTAIN
AUS 6b Pandemic in Australia: widespread SUSTAIN
AUS 6c Pandemic in Australia: subsiding CONTROL
REC
OVE
R
AUS 6d Pandemic in Australia: next wave RECOVER
RECOVERY
Source: National Action Plan April 2009
40
Recommended Actions for Australian Businesses
AusPhase
Description of phase Recommended Actions for Australian Businesses
Aus 4 Human infection inAustralia: Smallercluster(s) consistent withlimited human to humantransmission, spreadhighly localised,suggesting the virus is notwell adapted to humans
Consider implementing remote work arrangements Consider suspending all overseas/interstate travel Purchase health and safety consumables such as disinfectant,
gloves and face masks Distribute hard copies of staff contact and supplier contact list Educate staff that if they get sick and recover, they should
return to work as they will be immune to the disease. If theybelieve they are unwell, they should not go to work.
Prepare rosters that have no overlaps and include sufficienttime for disinfecting the area before the new shift arrives
Encourage staff to eat at their desks and stagger breaks toprevent groups meeting in the break rooms
Provide staff with details of the location of fever clinics,designated influenza hospitals, infection control guidelines, thehotline for influenza and other relevant information
Exercise the Business Continuity Plan examine how continuitywill be affected in an environment of high absenteeismincluding up to 50% absenteeism, when regions arequarantined, preventing staff and goods from leaving orarriving, and when schools are closed and other socialdistancing is introduced.
Plan to allow staff to work from home Plan for ways to increase social distancing in the workplace,
e.g. video conferencing Identify the conditions where all but the critical functions would
be suspended Update company succession plans in case the key staff
succumb Review insurance policies for pandemic coverage
Aus 5 Human infection inAustralia: largercluster(s) but human tohuman transmission stilllocalised, suggesting thevirus is becomingincreasingly betteradapted to humans, butmay not yet be fullyadapted
Activate remote work arrangements Implement social distancing at work Cancel all non-essential work Activate rosters that have no overlaps and include sufficient
time for disinfecting the area before the new shift arrives Maximise building ventilation Require staff to wear surgical masks, introduce cough
etiquette and other hygiene measures Undertake daily temperature checks of staff Clean phones and all touched surfaces between shifts
Aus 6a Pandemic in Australia:localised (one area ofcountry)
Maintain a register of staff who get sick but recover, as theyare immune to the disease.
Aus 6b Pandemic in Australia: Encourage immune staff to return to work
41
Widespread Maintain contact with all employees and provide situationalupdates
Aus 6c Pandemic in Australia:Subsided
When vaccine becomes available, organise for all non-immunestaff to be vaccinated as early as practical
Implement plan for the restoration of operations
Adapted from: National Security Briefing Notes May 2009
42
BCI 9 Immediate Actions GuideNotification
On first becoming aware of a possible business continuity event, the relevant local Manager is required toassess the situation and if the event is likely to exceed the agreed “MAO timeframe”, then the CMT Directorshould be notified immediately by phone and where possible, a follow-up personal briefing detailing the keyissues including;
Nature of the incident – time informed etc
Describe business elements impacted (Critical Functions)
Facility / equipment impacted
Staff
Any response actions implemented (Critical Function Sub Plan)
Any media involvement / interest
Any immediate support requirements.
Elements of the BCP (Sub Plans) can be implemented at the local level, where appropriate to address animmediate response requirement even if the event is expected to be resolved within an acceptable period.
Assessment by Director CMT
On receipt of a notification that will impactbusiness continuity the CMT Director will:
Formally note details
Conduct preliminary impactassessment (facility and technologyinfrastructure)
Notify the other members of theContinuity Management Team (CMT)
Confirm with the Mayor appropriatemedia strategies
Determine if a control centre needsto be opened.
Ensure that the Insurer has beenformally notified
Assemble & Brief CMT
Time of incident
Nature of incident
Location of incident
Staff involved
Facilities / equipment impacted
Community impact
Emergency Services involved
Initial indications of outage duration
Media involvement
Confirm responsibility statements
Declaration
The CMT Director to review the preliminary information and if considered necessary declare a BusinessContinuity Event and notify the Mayor. The CMT Director is responsible for all internal communications. Acontrol centre may also be required to be opened.
43
CMT Director
The CMT Director is to call the initial CMT meeting to obtain more detailed information from the relevant businessareas impacted, including:
• Review situation information to date & record
• Review business unit impact statements
• Review Media statements
• Ensure all CMT members understand their responsibilities
• Develop a whole of business “Business Impact Analysis
• Staff impacts
During the meeting information will have been gathered by the various CMT members to produce an evaluationof the incident. A formal record of the meeting to be collated by CMT Support person with particular emphasison items to be actioned. This record needs to be regularly reviewed and updated as additional information comesto hand.
Initial Meeting – Business Impact Assessment
CMT Member
Prior to undertaking the initial meeting each member of the CMT is to assess and document the impacts of thebusiness interruption event
At initial meeting each business unit is to report on
• Staff impacts
• Building / Facilities impacts
• Service Delivery impacts
• Media issues
• Other relevant issuesDevelopment and Implementation of Response Strategies
Response strategies will need to be developed to address the business interruption event.
Refer to Critical Function Sub Plans within the Business Continuity Plan for implementation strategies
Briefing Media/Staff/Community/Insurer
Due to the nature of the media, the timeliness of reporting in these circumstances are critical. Prompt reportingto, and liaison with CE and Mayor is in the best interests in terms of allowing for nomination of aspokesperson as well as preparation and appropriateness of response.
In a business continuity event, all communications with the media relative to the business of Council shallbe through the Director CMT or the Mayor for community impacts.
46
Payroll
Prepared by Manager Human Resources Date 8/9/2014
Sub Plan Owner This plan is owned by the Manager Human Resources who has overallresponsibility for this plan.
The routine management of the plan in delegated to the Payroll Officer who hasresponsibility for ensuring the accuracy and currency of the plan and advising theManager Human Resources of any changes required.
Identified Critical Business Functions
The preparation, processing & transport of council’s fortnightly payroll.
Overview of Functions (Context)
Council’s payroll is processed on a fortnightly basis with pay periods ending every second Tuesday andthe funds transferred to the bank electronically by 4pm on the Wednesday following the end of the payperiod. Payments are made to staff in accordance with Council’s Enterprise Agreements and Awardsand other relevant legislation.
Business Impact Analysis
Business Impact of FunctionLoss
Penalties for Non Delivery Functional Interdependencies
Staff do not receive pay
Staff complaint
Staff do no present to workfor industrial dispute
Staff may requestreimbursement of financialinstitution default charges
Industrial unrest
Timesheets and variations
IT platform and software.Ability to transfer data to thebank
Banking system to receiveand action data.
Current Resources Premises/Equipment/ Staff
Minimum Resources Required Alternate Manual Process orWork Around
IT access & equipment(Synergy, internet banking,emails)
1.8 Payroll officer
Payroll officer & payrollmanual
Cadell St Offices
Timesheet
1.5 Payroll Officer
Internet on Wednesday
Synergy Soft/IT Vision
Run last pay
Ask other Council’s,Yankalilla to processAlexandrina payroll or assistwith payroll.
47
Payroll
Disruption Scenario Max Allowable Outage
IT outage
Loss of staff (payroll)
Loss of utilities
Bank Failure
1 to 2 days (pay week)
5 days
4 days
2 days
Authority for Invoking Plan A standing authorisation is given to the plan owner to activate the planonce the outage exceeds that Maximum Allowable Outage as describedabove.
Key Decision Makers to be assembled
Manager Human Resources, payroll officer/s General Manager Organisation and Culture
Stakeholders other than process owner
Internal External
All employees ANZ
Pre Event Preparedness Current policies & procedures & access points required to deliver function
The current policy and procedures for this critical function can be located –
Electronic copies:
G:Drive / Payroll
Synergy Records
Hard copies:
Payroll cupboard
48
Payroll
Emergency Response Immediate actions required if function is lost.
On being advised of a business interruption event the following immediate responses should beconsidered:
The Manager Human Resources and Payroll staff to be informed immediately.
Source of Disruption to be identified where possible (i.e. internal IT system/external banking ortelecommunications infrastructure.
Identify possible downtime with key decision makers (IT, HR, finance)
Consult with stakeholders (i.e. let employees know of possible outcomes, liaise with bank, delay orvariation/standard/base pay
Implement emergency procedure
Document & review emergency process taken
Continuity Management Actions required to ensure continued availability of the function
In the event of a business interruption event occurring as identified within the disruption scenarioanalysis, that exceeds the identified MAO the following responses may be appropriate:
Consult with key decision makers on appropriate course of action i.e. when will IT access again beavailable / discuss options = bank
If deemed necessary, process standard hour pay run as per Emergency Procedure
Communicate with stakeholders
In the event of loss of staff the CMT to be informed to identify secondment or temp staff to assist inpayroll.
Communication Considerations
Internal External
Inform members of EMT
Provide all employees with up to dateinformation (may need to use alternatemethods if no emails)
Need emergency contact details if no ITavailable
Liaise with ANZ
o Local branch
o Business banking’s online
Notify applicable statutory bodies – super andchild support
Further Treatment/ Action Plans Actions required for continuous improvement
Treatment/ Action Plan Position Responsiblefor development
TargetDate
Emergency procedure to be reviewed and updated Payroll officer June 2015
49
Service Centre – Call Centre
Prepared by CS Manager Date 13.01.2016
Sub Plan Owner This plan is owned by the General Manager Organisation & Culture who hasoverall responsibility for this plan, including routine management andresponsibility for ensuring the accuracy and currency of the plan.
Identified Critical Business Functions
Call Centre
Overview of Functions (Context)
Focal point of communication between Community and Council. Becomes a critical function in times ofemergency.
Business Impact Analysis
Business Impact of FunctionLoss
Penalties for Non-Delivery Functional Independencies
Inability for Council to coordinatea response with community
Misinformation – potentiallitigation
Pressure on front office staff
Inputs required
CIS StaffSystems
IT platform and softwarePhone system , CRM, Telstra
DownstreamEnquires not reaching office
No feedback to or from CouncilOfficers
Current ResourcesPremises/Equipment/Staff
Minimum Resources Required Alternate Manual Process orWork Around
2 full time employees
Office space
Desk space
Phone stations (x3)
Cisco application
IT Network/backup
ISDN Connection
4 full time employees (increase)
Office space
Desk space
Phone stations (4)
Cisco application
IT Network/backup
ISDN Connection
Loss of Call Centre Software
Divert to Out of HoursEmergency servicesprovider
Initiaterepair/replacementwithin 24 hours
Longer than 24hours,reprogram system to useextensions in call group
50
Staff Training Staff Training Loss of System (including CallCentre)
Contact Telstra anddivert to After hours
Contact IT Serviceprovider forrepair/replace
Loss of Telstra Service
Divert to EmergencyAfter Hours contactTelstra immediately
Disruption Scenario Max Acceptable Outage
Loss of Call Centre Software Loss of System (including call centre) Loss of Telstra Service
2 Hours 2 Hours 2 Hours
Authority for Invoking Plan A standing authorisation is given to the plan owner to activate the planonce the outage exceeds the Maximum Acceptable Outage asdescribed above
Key Decision Makers to be assembled
General Manager, IT Manager, Manager Customer Services, Coordinator Customer Services
Stakeholders other than process owner
Internal External
Customer Service StaffAll Staff
Emergency After Hours providerTelstraIT Service provider
Pre Event Preparedness Current policies & procedures & access points required to deliver function
The current policy and procedures for this critical function can be located:
Electronic Copies G:/LCS/CustomerService
Hard copy: Copy of staff directory in phone room (updated quarterly)
Emergency Response Immediate actions required if function is lost.
On being advised of a business interruption event the following immediate responses should beconsidered:
Contact Emergency After Hours to act as back up
Notify CE and General Manager Organisation & Culture, Manager Customer Service, CoordinatorCustomer Service
51
Notify IT
If internal issue, Information Technology staff to advise on duration of outage. If outage is to belonger than identified MAO the continuity response to be enacted.
Continuity Management Actions required to ensure continued availability of the function
In the event of a business interruption event occurring as identified within the Disruption scenarioanalysis, that exceeds the identified MAO the following responses may be appropriate:
Loss of Call Centre Software
Divert to Emergency After Hours initiate repair/replacement within 2 hours Longer than 24hours
Loss of System (Including Call Centre)
Contact Telstra and divert to Emergency After Hours Contact service provider for repair/replace
Loss of Telstra Service
Divert to Emergency After Hours contact Telstra within 24 hours Arrange temporary connection from Telstra
Further Treatment/Action Plans Actions required for continuous improvement
Treatment/Action Plan PositionResponsible fordevelopment
Target Date
Reviewing existing after hours service provider Manager, CustomerService
2017
Review existing programming capacity of call centresoftware
Manager, CustomerService
2017
Communication Considerations
InternalAll staff including elected members
ExternalService providers including website.
Emergency notification message.
52
Customer Service
Prepared by Manager, Customer Service Date 13.01.2016
Sub Plan Owner This plan is owned by the General Manager Organisation and Culture who hasoverall responsibility for this plan, including routine management andresponsibility for ensuring the accuracy and currency of the plan.
Identified Critical Business Functions
Front Counter Service at two branches – Goolwa and Strathalbyn
Overview of Functions (Context)
Focal point of communication between Community and Council. Becomes a critical function in times ofemergency.
Business Impact Analysis
Business Impact of FunctionLoss
Penalties for Non-Delivery Functional Independencies
Cannot deliver payments,receipting, library, andtransactional dealings in general.
Misinformation
Pressure on front office staff
PR / reputational damage
Inputs requiredFront Counter trained operators
SystemsIT platform and softwarePhone system, Telstra
DownstreamEnquires not reaching office
No feedback from CouncilOfficers
Current ResourcesPremises/Equipment/Staff
Minimum Resources Required Alternate Manual Process orWork Around
3 full time employees 5 full time employees
Office space
Desk space
Phone station
Cisco application
IT Network/backup
ISDN Connection
Another location to becommunicatede.g. Strathalbyn or alternativevenue in Goolwa.
53
Staff Training
1 mobile
Front countertablet/desktop/laptop
Disruption Scenario Max Acceptable Outage
No access to buildings 2 Hours
Authority for Invoking Plan A standing authorisation is given to the plan owner to activate the planonce the outage exceeds the Maximum Acceptable Outage asdescribed above
Key Decision Makers to be assembled
General Manager Organisation Culture, Manager Customer Service, IT Manager, Manager CustomerServices, Coordinator Customer Service
Stakeholders other than process owner
Internal External
Customer Service & Library StaffElected members
All Staff
Community
Pre Event Preparedness Current policies & procedures & access points required to deliver function
Signage ready to be deployed on main entrance (if possible, if not an officer stationed at appropriatelocation)
Procedure for response, including script for customer enquiries
Emergency Response Immediate actions required if function is lost.
On being advised of a business interruption event the following immediate responses should beconsidered:
Signage and communications.
Continuity Management Actions required to ensure continued availability of the function
In the event of a business interruption event occurring as identified within the Disruption scenarioanalysis, that exceeds the identified MAO the following responses may be appropriate:
As above.
Further Treatment/Action Plans Actions required for continuous improvement
Treatment/Action Plan PositionResponsible for
Target Date
55
Communications
Prepared by General ManagerOrganisation & Culture Date 05.06.2012
Sub Plan Owner This plan is owned by the General Manager Organisation & Culture who hasoverall responsibility for this plan.
The routine management of the plan in delegated to Communications Officer whohas responsibility for ensuring the accuracy and currency of the plan and advisingthe General Manager Organisation Development of any changes required.
Identified Critical Business Functions
Public relations communication and internal communications
Overview of Functions (Context)
In the event of any significant disruption to business continuity the ability of Council to communicate toits staff and its community will be essential and this communication is often undertaken by means whichmay themselves be affected by the business continuity disruption
Business Impact Analysis
Business Impact of FunctionLoss
Penalties for Non-Delivery Functional Independencies
Unable to communicate thesituation with staff
Unable to communicate thesituation including what Councilsservice strategy is at the time
TelecommunicationsServer based
Information RelayServer based intranet/internet
Mobile Technologies
Contact detailsServer based
Current ResourcesPremises/Equipment/Staff
Minimum Resources Required Alternate Manual Process orWork Around
Main server – Goolwa Office
Backup – Goolwa works depot
Contact details/address books –electronic server based & paperbased
Mobile phones
1 Full time employeecommunications officer
IT system
1x mobile phone
Verbal briefings
Notice boards – white boards,pins
Paper based – contact list
Buildings – public announcementsystem
Disruption Scenario Max Allowable Outage
Interruption to Information Technology services 1 – 2 hours
56
Authority for Invoking Plan A standing authorisation is given to the plan owner to activate the planonce the outage exceeds the Maximum Allowable Outage as describedabove
Key Decision Makers to be assembled
Communications Officer, Team Leader, Library and Customer service, Manager Information Technologyservices, General Manager Organisation & Culture
Stakeholders other than process owner
Internal External
All staff All customers
Pre Event Preparedness Current policies & procedures & access points required to deliver function
The current policy and procedures for this critical function can be located:
Electronic Copies
Information Technology – Disaster Recovery Plan
Hard Copies
Manual Contact list – staff, key customer groups, media etc.
Emergency Response Immediate actions required if function is lost.
On being advised of a business interruption event the following immediate responses should beconsidered:
Key decision makers review situation
Source of disruption to be identified where possible (i.e. internal IT system / telecommunicationsinfrastructure)
Communicate with staff/public via briefing in building, public announcement system, signs,noticeboards, mobile phones, website, social media (Tourism), newspaper social media, radio
Disruption to service that exceeds MAO – communicate in local paper, remote access to website,erect notices in the community at local businesses. Visitor Information Centre used to provideadvice/information to the community, social media (Tourism)
Continuity Management Actions required to ensure continued availability of the function
In the event of a business interruption event occurring as identified within the Disruption scenarioanalysis, that exceeds the identified MAO the following responses may be appropriate:
Information Technology Disaster Recovery Plan
57
Further Treatment/Action Plans Actions required for continuous improvement
Treatment/Action Plan PositionResponsible fordevelopment
Target Date
Prepare a manual including media contact listensuring updated ¼
CommunicationsOfficer
31 July 2015
Communication Considerations
59
CWMS
Prepared by General ManagerEngineering andEnvironment
Date 29.06.14
Sub Plan Owner This plan is owned by the General Manager Engineering and Environment whohas overall responsibility for this plan.
The routine management of the plan in delegated to CWMS Coordinator who hasresponsibility for ensuring the accuracy and currency of the plan and advising theGeneral Manager Engineering and Environment of any changes required.
Identified Critical Business Functions
Community Wastewater Management Schemes
Overview of Functions (Context)
Alexandrina Council has over 6000 CWMS connections, four treatment plants, 58 pump stations
Business Impact Analysis
Business Impact of FunctionLoss
Penalties for Non-Delivery Functional Independencies
Inability to release and transportsewage into the environmentincluding waterways
Public Health concern/risksincreased
Litigation
Statutory Penalties includingfines from the EPA, loss oflicence from EPA
PR Issues
Inputs requiredMaintenance Staff
SystemsIT platform and softwarePlant – Public Infrastructure
Current ResourcesPremises/Equipment/Staff
Minimum Resources Required Alternate Manual Process orWork Around
7 staff including an electrician
3 backup generators
Depots including workshops atSouth Goolwa
3 light truck service units
3 Utes
Failure of alarms on all systems
7 staff including an electrician
3 backup generators
Depots including workshops atSouth Goolwa
3 light truck service units
3 Utes
Failure of alarms on all systems
Portable Generators
Rewire control panels to enablebasic operations can continue
Install /use standby pumps
60
Disruption Scenario Max Acceptable Outage
Power failure Flooding of Chambers Loss of staff Treatment Plant Failure
8 Hours 10 Hours 2 Weeks 4 Hours
Authority for Invoking Plan A standing authorisation is given to the CWMS Supervisor to activatethe plan once the outage exceeds the Maximum Acceptable Outage asdescribed above
Key Decision Makers to be assembled
CWMS Coordinator, CEMS Supervisor, Manager Engineering Services, Manager EnvironmentalHealth, GM Engineering
Stakeholders other than process owner
Internal External
Chief Executive EPA
Department of Health
Pre Event Preparedness Current policies & procedures & access points required to deliver function
The current policy and procedures for this critical function can be located:
Hard Copies
CWMS Maintenance – Operational Manual
Waste Water Treatment Plant Operation Manuals
Emergency Response Immediate actions required if function is lost.
On being advised of a business interruption event the following immediate responses should beconsidered:
• CWMS Maintenance – Operational Manual
• Waste Water Treatment Plant Operation Manuals
Continuity Management Actions required to ensure continued availability of the function
In the event of a business interruption event occurring as identified within the Disruption scenarioanalysis, that exceeds the identified MAO the following responses may be appropriate:
Risk assessment conducted by key decision makers in relation to specific nature of outage
61
Further Treatment/Action Plans Actions required for continuous improvement
Treatment/Action Plan PositionResponsible fordevelopment
Target Date
Ongoing maintenance CWMS Supervisor Bi-annual
Communication Considerations
Internal
CE
External
EPA, Department of Health
62
Waste Management
Prepared by General ManagerEngineering andEnvironment
Date 29.06.2014
Sub Plan Owner This plan is owned by the General Manager Engineering and Environment whohas overall responsibility for this plan, including routine management andresponsibility for ensuring the accuracy and currency of the plan.
Identified Critical Business Functions
Waste Management – Operation of Waste transfer stations, including collection of kerbside waste.
Overview of Functions (Context)
Alexandrina Council is a member of a local Government Subsidiary “Fleurieu Regional Waste Authority”who operates Councils waste transfer facility including the collection of kerbside waste and recyclables.
Business Impact Analysis
Business Impact of FunctionLoss
Penalties for Non-Delivery Functional Independencies
An increase of waste within thecommunity
Public Health Risk
Adverse public reaction
Loss of integrity / reputation
Potential litigation Staff, plant and equipment fromother organisations.
Current ResourcesPremises/Equipment/Staff
Minimum Resources Required Alternate Manual Process orWork Around
8 Trucks and 2 back up trucks
Contract trucks can be sources ifrequired
15 staff for WTF and 9 staff forcollection trucks.
6 trucks can be used for a shorttime
Hire additional trucks
Re allocate resources / stafffrom WTF’d
Re prioritise tasks
Disruption Scenario Max Acceptable Outage
Plant breakdown that requires other trucks to be sourced Staff unavailability that requires reallocation of tasks for Waste
Transfer Facility staff
2 Days 2 Days & ½ day for WTF
closure
63
Disposal location (landfill) closes due to unforeseencircumstances
Nil
Authority for Invoking Plan A standing authorisation is given to the Fleurieu Regional WasteAuthority (FRWA) Executive Officer to activate the plan once the outageexceeds the Maximum Acceptable Outage as described above. FRWAdoes not have its own business continuity plan.
Key Decision Makers to be assembled
Executive Officer – FRWA, Operations Manager - FRWA
Stakeholders other than process owner
Internal External
CE
Pre Event Preparedness Current policies & procedures & access points required to deliver function
The current policy and procedures for this critical function can be located:
Electronic Copies
FRWA internal systems
Hard Copies
FRWA internal systems
Emergency Response Immediate actions required if function is lost.
Notify EPA that there has been a suspension of services
Notify internally of interruption event
Ensure communication of interruption is disseminated through Councils communication channels
Initiate contact with FRWA due ascertain duration of outage
Continuity Management Actions required to ensure continued availability of the function
Maintain communications with FRWA to ensure contract obligations are maintained
Consider closure of waste transfer station and diversion to alternative site
Consider use of alternative contractor in the event that rubbish cannot be collected
Further Treatment/Action Plans Actions required for continuous improvement
Treatment/Action Plan PositionResponsible fordevelopment
Target Date
Liaise with FRWA to gain an understanding of theircontingencies to deal with business interruptions.
General ManagerEngineering
Jan 2015
65
Road Services
Prepared by General ManagerEngineering andEnvironment
Date 13/7/2014
Sub Plan Owner This plan is owned by the GM Engineering and Environment who has overallresponsibility for this plan.
The routine management of the plan in delegated to Manager Field Services whohas responsibility for ensuring the accuracy and currency of the plan and advisingthe General Manager Engineering and Environment of any changes required.
Identified Critical Business Functions
Road Services
Overview of Functions (Context)
Overall maintenance of Councils public roads and associated infrastructure.
Business Impact Analysis
Business Impact of FunctionLoss
Penalties for Non Delivery Functional Independencies
Inability for residents to accessareas safely
Disruption to Councilmaintenance schedule
Access for emergency services
Potential Litigation Inputs requiredStaff, Heavy Equipment,availability of raw materials,contractors
SystemsIT platform and softwarePhone
Current ResourcesPremises/Equipment/Staff
Minimum Resources Required Alternate Manual Process orWork Around
Staff
Plant
Contractors
2 staff
2 utes
Possibly grader (1) and/or otherheavy machinery depending ontype of business interruption.
Contract labour / machinery
Seek assistance fromneighbouring Councils
Disruption Scenario Max Allowable Outage
Inability for residents to access properties Heavy plant breakdown Disruption to Council maintenance schedule Inability for emergency services to access properties Contractors not available
1 Day 20 Days 20 Days 1 Day 1 Week.
66
Authority for Invoking Plan A standing authorisation is given to the plan owner to activate the planonce the outage exceeds the Maximum Allowable Outage as describedabove
Key Decision Makers to be assembled
Engineering Services Manager, Supervisors (civil and construction) and GM.
Stakeholders other than process owner
Internal External
CE General Public
Emergency Services
Contractors
Pre Event Preparedness Current policies & procedures & access points required to deliver function
The current policy and procedures for this critical function can be located:
Electronic Copies
Various SOP’s – Intranet
Plans
Hard Copies
Various SOP’s – Depots
Emergency Response Immediate actions required if function is lost.
On being advised of a business interruption event the following immediate responses should beconsidered:
Contact Engineering Services Manager, Supervisors (civil and construction) and GM.
Continuity Management Actions required to ensure continued availability of the function
In the event of a business interruption event occurring as identified within the Disruption scenarioanalysis, that exceeds the identified MAO the following responses may be appropriate:
Liaise with Engineering Services Manager, Supervisors (civil and construction) and GM.
Liaise with Communications Officer to arrange media release(s) as appropriate
Make direct contact with affected residents
67
Further Treatment/Action Plans Actions required for continuous improvement
Treatment/Action Plan PositionResponsible fordevelopment
Target Date
Communication Considerations
68
Food Safety Regulations
Prepared by Manager Health,Environment and CommunitySafety
Date 14.07.2014
Sub Plan Owner This plan is owned by the Manager Health, Environment and Community Safetywho has overall responsibility for this plan, including routine management andresponsibility for ensuring the accuracy and currency of the plan
Identified Critical Business Functions
Food Safety Regulation
Overview of Functions (Context)
Emergency situations relating to food safety i.e. outbreaks of food-borne disease.
Business Impact Analysis
Business Impact of FunctionLoss
Penalties for Non Delivery Functional Independencies
Staff do not present for work
Failure to fulfil legislativerequirements
Poor reception bymedia/community
Illness/deaths in community
Information unavailable
Ombudsman/Ministerintervention
Liability to CE
Inputs requiredAssistance to Department ofHealth
SystemsIT platform and software (Healthmodule)
DownstreamSA Health to receive relevantinformation
Current ResourcesPremises/Equipment/Staff
Minimum Resources Required Alternate Manual Process orWork Around
Access to car/transport
2 full time employee EHO’s1 full time employee EnvironmentHealth Support Officer1full time employee ManagerHealth, Environment andCommunity SafetyOffice spaceDesk spaceLaptops/terminal serverTelephonesIT system – synergy healthmoduleThermometers
2 full time employee EHO’s + 1
FTE support officer
Thermometers (3)Australian Food SafetyAssessment (AFSA) -electronically or paper version
Car / Transport
Use AFSA inspection pads andcarbon copy
Use taxis or private vehicles
69
Disruption Scenario Max Acceptable Outage
loss of key staff Interruption to Information Technology services Loss of vehicle access (if inspections are scheduled – i.e.
prohibition order being lifted)
1 day 2 days 1 day
Authority for Invoking Plan A standing authorisation is given to the plan owner to activate the planonce the outage exceeds the Maximum Acceptable Outage asdescribed above
Key Decision Makers to be assembled
Manager Health, Environment and Community Safety, Environmental Health Officers, GeneralManager Environmental and Development, Environmental Health Support Officer
Stakeholders other than process owner
Internal External
EHO’s (Environmental health Officers)
EH Support Officer
Department of HealthAlexandrina CommunityBusiness implicated in outbreak
Pre Event Preparedness Current policies & procedures & access points required to deliver function
The current policy and procedures for this critical function can be located:
Electronic Copies
SOP’s on Connect Intranet Workspace for Environmental Health team
Hard Copies
No hard copies available or required – Department of Health is the lead agency for foodborne illnessoutbreak
Emergency Response Immediate actions required if function is lost.
On being advised of a business interruption event the following immediate responses should beconsidered:
Manager Health, Environment and Community Safety informed immediately
Identify if resources are adequate and second staff from other Councils if required
Ensure AFSA available and food inspection kits ready source top ups if required.
70
Continuity Management Actions required to ensure continued availability of the function
In the event of a business interruption event occurring as identified within the Disruption scenarioanalysis, that exceeds the identified MAO the following responses may be appropriate:
Use manual AFSA if required
Second extra staff EHO’s from other Councils if needed
Further Treatment/Action Plans Actions required for continuous improvement
Treatment/Action Plan PositionResponsible fordevelopment
Target Date
Ongoing dialogue with adjoining councils to supportof a reciprocal arrangement could be reached
Emergency Kits including AFSA available andstocked
Manager Health,Environment andCommunity Safety
Annual
Annual
Communication Considerations
InternalInform all staff that EHO’s are unavailable until further notice, due to emergency or direct regularenquires to an agreed point.
ExternalMedia release potentially required to highlight what is being done. Must be very careful as investigationon going
71
Environmental Health Emergency Management
Prepared by Manager Health,Environment and CommunitySafety
Date 05.06.2012
Sub Plan Owner This plan is owned by the Manager Health, Environment and Community Safetywho has overall responsibility for this plan, including routine management andresponsibility for ensuring the accuracy and currency of the plan
Identified Critical Business Functions
Environmental Health Emergency Management
Overview of Functions (Context)
Emergency Management in the event of a natural disaster where the SA Department of Health is thelead agency
Business Impact Analysis
Business Impact of FunctionLoss
Penalties for Non-Delivery Functional Independencies
Availability of Staff& Contractorsto perform all business functions
Poor perception in thecommunity
Illness / Death
Failure to meet statutoryresponsibilities / MOUagreements
Poor media perception
Inputs requiredAssistance to Department of
Health, Essential Safetyequipment including vehicles
SystemsIT platform and software
Current ResourcesPremises/Equipment/Staff
Minimum Resources Required Alternate Manual Process orWork Around
EHO’s/Manager/ EH SupportOfficerOffice spaceDesk spacePhonesIT SystemsLaptops/terminal/servicesImmunisation Contractors
EHO’s/staffTelephonesEmergency Management Kitincluding alcohol gel,information, inspection sheetsVehicleImmunisation Contractors
Use of private vehicles / taxis
Disruption Scenario Max Acceptable Outage
loss of key staff Interruption to Information Technology services No available vehicles
1 day 1 day 1 day
72
Authority for Invoking Plan A standing authorisation is given to the plan owner to activate the planonce the outage exceeds the Maximum Acceptable Outage asdescribed above
Key Decision Makers to be assembled
Environmental Health Manager, General Manager, EHO’s
Stakeholders other than process owner
Internal External
Staff
Elected Members
General PublicDepartment of HealthPolice and Emergency ServicesOther Government Agencies
Pre Event Preparedness Current policies & procedures & access points required to deliver function
The current policy and procedures for this critical function can be located:
Electronic Copies
Intranet
Hard Copies
Fact sheets in office
Emergency Response Immediate actions required if function is lost.
On being advised of a business interruption event the following immediate responses should beconsidered:
Get kits and vehicle ready and await direction from Department of Health.
Continuity Management Actions required to ensure continued availability of the function
In the event of a business interruption event occurring as identified within the Disruption scenarioanalysis, that exceeds the identified MAO the following responses may be appropriate:
Ongoing dialogue to other Councils for usage of staff to assist
Further Treatment/Action Plans Actions required for continuous improvement
Treatment/Action Plan PositionResponsible fordevelopment
Target Date
Routine Check of Emergency Management Kits
Ensure EHO’s are emergency management trained –
EHO’s December 2015
73
ongoing as required. Annual
Communication Considerations
InternalInform Customer Service staff of what is occurring and how to contact EHO’s and what service level willbe during this emergency
ExternalDepartment of Health, Other Councils, Media.
75
Information Management – Vital Records
Prepared by Team Leader InformationManagement Date 26/08/2014
Sub Plan Owner This plan is owned by the General Manager Infrastructure & Assets who hasoverall responsibility for this plan, including routine management and responsibilityfor ensuring the accuracy and currency of the plan
Identified Critical Business Functions
Information Management
Overview of Functions (Context)
Manage life cycle of documents for council, manage information and to meet legislative requirements(e.g. FOI)
Business Impact Analysis
Business Impact of FunctionLoss
Penalties for Non-Delivery Functional Independencies
Cannot meet legislativerequirements
Cannot access information forCouncil operations
Legislative provisions for fines Inputs requiredIT system
Hard copy storage
Current ResourcesPremises/Equipment/Staff
Minimum Resources Required Alternate Manual Process orWork Around
1 Co-ord
3 FTE
Local Govt Software
Scanners (3)
7 computers
Onsite
1 bunker
1 container (depot)
Offsite (contracted)
4 staff (FTE)
3 Computers
1 Scanner
Secure onsite storage
1 bunker
1 container (depot)
Offsite (contracted)
Incoming mail
Building plans
Excel recording
Access to photocopier orscanner
76
Disruption Scenario Max Acceptable Outage
IT LossLoss of records (fire)No access to Principal OfficeNo access to bunkerNo access to temporary storage providerLoss of 1 or more key staff
1 Day Immediate 2 Days 2 Days 2 Days 1 Week
Authority for Invoking Plan Plan Owner
Key Decision Makers to be assembled
CE, 3 GM’s, Manager IT Services, Coordinator Information Management
Stakeholders other than process owner
Internal External
All staff
Elected members
State Records
Affected stakeholders
Pre Event Preparedness Current policies & procedures & access points required to deliver function
All of council and internal team policies & procedures
State Records audits
Emergency Response Immediate actions required if function is lost.
On being advised of a business interruption event the following immediate responses should beconsidered:
Identify issue
Understand timeframes
Develop plan for situation - schematic
Continuity Management Actions required to ensure continued availability of the function
In the event of a business interruption event occurring as identified within the Disruption scenarioanalysis, that exceeds the identified MAO the following responses may be appropriate:
Source alternative premises (Strathalbyn or work from home) to deal with IT flow
Site must have bare minimum resources
77
Further Treatment/Action Plans Actions required for continuous improvement
Treatment/Action Plan PositionResponsible fordevelopment
Target Date
Development of Vital Records Plan (in Draft) Aug 2015
Communication Considerations
InternalAll staff
Elected Members
ExternalApplicable members of public
Legislated stakeholders
78
IT Services – Service Desk
Prepared by Manager IT Service Date 26.08.2012
Sub Plan Owner This plan is owned by the Manager IT Services who has overall responsibility forthis plan, including routine management and responsibility for ensuring theaccuracy and currency of the plan.
Identified Critical Business Functions
Service Desk Internal / IT Advisory including contracted services.
Overview of Functions (Context)
Council’s service desk provides support to internal staff in the operation of IT systems and equipment.
Business Impact Analysis
Business Impact of FunctionLoss
Penalties for Non-Delivery Functional Independencies
Inability for staff to conduct theirduties impacting on Counciloperations
Staff complaint
Breach of contract (IT Advisory) SystemsIT platform and software
Current ResourcesPremises/Equipment/Staff
Minimum Resources Required Alternate Manual Process orWork Around
2 full time employee service deskofficer
One office space
Desk space
IT Systems
Telephone
3 full time employee (internal)
IT system
Telephone (1 mobile)
Infrastructure team to fill in
Third party contractor maybeengaged
Extend service time frames
Divert phone
Disruption Scenario Max Acceptable Outage
Loss of Service Desk 4 hours
Authority for Invoking Plan A standing authorisation is given to the plan owner to activate the planonce the outage exceeds the Maximum Acceptable Outage asdescribed above
Key Decision Makers to be assembled
79
Manager IT Services, Service Desk Coordinator
Stakeholders other than process owner
Internal External
Staff
Elected Members
Partner Organisations (KI and Fleurieu Regional waste)
Contractors
Public
Pre Event Preparedness Current policies & procedures & access points required to deliver function
The current policy and procedures for this critical function can be located:
Electronic Copies
1:\procedures
Emergency Response Immediate actions required if function is lost.
On being advised of a business interruption event the following immediate responses should beconsidered:
Continuity Management Actions required to ensure continued availability of the function
In the event of a business interruption event occurring as identified within the Disruption scenarioanalysis, that exceeds the identified MAO the following responses may be appropriate:
Third party contractors to be engaged
Further Treatment/Action Plans Actions required for continuous improvement
Treatment/Action Plan PositionResponsible fordevelopment
Target Date
Ongoing maintenance of DRP IT Mgr Aug 2015
Communication Considerations
InternalLink to communications plan ensuring staff including elected membersExternalLink to communication plan to advise Partner Organisations, public
80
IT Services Infrastructure
Prepared by Manager IT Services Date 26.08.2014
Sub Plan Owner This plan is owned by the Manger IT Services who have overall responsibility forthis plan, including routine management and responsibility for ensuring theaccuracy and currency of the plan.
Identified Critical Business Functions
IT Infrastructure / IT Advisory including contracted services
Overview of Functions (Context)
The IT Infrastructure provides the underlying communication and business systems for Council.
Business Impact Analysis
Business Impact of FunctionLoss
Penalties for Non-Delivery Functional Independencies
Inability for staff to perform corebusiness
Inability for core functions to beundertaken
Breach of contract
Breach of legislativerequirements
SystemsIT Infrastructure and software,Utilities, power, comms, air-conditioning
Current ResourcesPremises/Equipment/Staff
Minimum Resources Required Alternate Manual Process orWork Around
2 full time employeesInfrastructure Staff
Office space
Data centre space
IT Infrastructure
Telephone
Utilities
2 full time employeesInfrastructure staff
Data centre space
IT Infrastructure
Utilities
Engage third party
Disruption Scenario Max Acceptable Outage
Denial of access to the site loss of key staff (Infrastructure and Security Coordinator) loss of key staff (network systems admin) Interruption to Information Technology services
14 Days 1-2 Days 14 Days 12 Hours
81
Authority for Invoking Plan A standing authorisation is given to the plan owner to activate the planonce the outage exceeds the Maximum Acceptable Outage asdescribed above
Key Decision Makers to be assembled
Manager IT Services, Infrastructure and Security Coordinator, General Manager Corporate andCommunity Services
Stakeholders other than process owner
Internal External
StaffEM’s
Partner OrganisationsContractorsPublic
Pre Event Preparedness Current policies & procedures & access points required to deliver function
The current policy and procedures for this critical function can be located:
Electronic Copies
Password Manager I:\Passwords
Procedures I:\Procedures
Emergency Response Immediate actions required if function is lost.
On being advised of a business interruption event the following immediate responses should beconsidered:
Source of disruption to be identified where possible (i.e. internal IT system / telecommunicationsinfrastructure)
Determine duration
If outage is to be longer than identified MAO the continuity response to be enacted.
Continuity Management Actions required to ensure continued availability of the function
In the event of a business interruption event occurring as identified within the Disruption scenarioanalysis, that exceeds the identified MAO the following responses may be appropriate:
Restore some backups to external location provided by a third party
Further Treatment/Action Plans Actions required for continuous improvement
Treatment/Action Plan PositionResponsible fordevelopment
Target Date
82
Review IT Infrastructure DRP Manager IT Services Aug 2015
Communication Considerations
InternalLink to Communication Plan to critical function plan including advising staff and elected member