2014 Shutdown Schedule & UCN FY-2013 Resources
1
February 20, 2013
Upstream Section of BL1U 2
nEDMExperiment
Region
UCN Installation Schedule
N
2014 Shutdown4 months
3
2011 2015201420132012 2016 2017ACTIVITY
J A J OJ A J O J A J OJ A J O J A J OJ A J O J A
Schedule( 2010-2016 )2011 2015201420132012 2016 2017
Cleanup M11,1A/1B roof-beamDismantle PIENU & M13-DS
MESON HALL (& Vault):
Core M13 I-block
UCN APPARATUS:
Spallation Target & R/HUCN Source
BEAMLINE 1U:Kicker
SeptumDipoleBeamline (incl Quads, PS,…)
Design & Review Order/Fabricate/Deliver
Test
Mod/Fab/Assy
Order/Fabricate
Design & Review
Design & Review Order/Fabricate InstallTest
Specify/Conceptual design
Design/Fabricate InstallMove
COMMISSION @ TRIUMFBeamline Commissioning
HELIUM LIQUEFIER:
Upgrade He Liquefier System
He Liquefier SystemProcure
Install/Test & Run @ RCNP
Procure/Install
Install
Kicker Beamtube InstallDesign/Order Fabr
Install
Test
MILESTONES Shutdown Activities Activities Elsewhere(KEK, RCNP, CERN, Acsion)
Non-Shutdown Activities
Mod. 1VQ4/Q5; BL1V & Shld
Install
Dismantle M13-US, Mod.Shld
UCN Schedule (Draft)
Design/Order/Fabricate Test
Install
Install
Design/Fabr
Shielding Procure shielding blocksDesign & Review Install InstallInstall
4
2014 UCN Installation Schedule 5
UCN Installation 1 (Jan-May/2014): BL1U, Vault and Upstream Section
2014 S/D Schedule & Resources
UCN Installation 1 (Jan-May/2014): BL1U, Vault and Upstream Section
Late Dec/2013 Remove large shielding blocks outside (3 days) Start Jan.2/2014 Week 1 RPG survey & prepare for S/D work Week 2 Remove Warm blocks (layers A-D); Disconn.services; Remove 1A vault comp.’s Week 3 Cleanup/Layout BL1U; Specify location for coring of Immovable-block (and tx.) Week 4 1BVB2 mods (and 1B mods) Week 4 - 6 Install stands for kicker,septum,1UB2; Install & Align kicker-beamtube Week 7 Install & Align septum magnet Week 8 Install & Align 1UB2 magnet and 1UM6 Week 9 Reinstall 1A vault comp.’s; Install Notch-monitor; Install 1AUM5,1UBB2
Week 6 - 8 Install rough-in services (Electrical, Water, Air) Week 9 - 10 Finish Electrical (AC & DC), Water, Air services
Week 10 Finish all vacuum connections Week 11 Leak check & ready to pull vacuum Week 12 Pull vacuum & check-out vacuum controls Week 13 General check-out and ready to cover Week 14 - 15 Restore vault & 1A shielding and prepare for beam
Resources: 3 Beamlines techs (2 BL + Alignment), 13 weeks [39 person-weeks]1 Crane Operator + 2 Riggers, 7 weeks [21 person-weeks]Vacuum Group [6 person-weeks]Services: Outside Contractors, 5 weeks [6 person-weeks]
Mostly Contractors
Clo
se U
p
M
ain
Wor
k
Ope
n U
p2014 UCN Installation Schedule & Resources 6
Resource Requirements 7
Preparations for 2014 Shutdown: (Design, Procurement, Assembly of Subsystems)
Items/Subsystems Eng. DWGs Procurement Assy./Testing(needed Jan-2014) (incl Modeling)
Vault-BL1A Shielding Saf. / UCN DO UCN n/a
Septum Mods UCN UCN MS / UCN BL / UCNSeptum Vacuum Box UCN UCN MS / UCN BL / UCNSeptum Stand UCN UCN MS / UCN BL / UCN
1UAM5/1UBB2 Diag. DO MS /Diag. / ET ET / Diag.
1BVB2 Stand Mod. Eng.Div. DO MS BL
Dipole Vacuum Box UCN UCN MS BL
1AM4(ToF)/1AM4.5 Diag. UCN Diag. / UCN Diag. / UCN
Kicker Beamtube UCN UCN UCN BL Kicker Stand UCN UCN MS / UCN BL
Preparations for 2014 Shutdown: [ Time Estimate in Person-Weeks ]
Items/Subsystems Eng. DWGs Procurement Assy./Testing(needed Jan-2014) (incl Modeling)
Vault-BL1A Shielding Saf.[3]/UCN[4] DO [7] UCN [3] n/a
Septum Mods UCN [8] UCN [4] MS [2] / UCN [1] BL [10] / UCN [2]Septum Vacuum Box UCN [3.5] UCN [6] MS [6] / UCN [1] BL [6] / UCN [3]Septum Stand UCN [3.5] UCN [6] MS [5] / UCN [1] BL [4] / UCN [2]
1UAM5/1UBB2 Diag. [8] DO [7] MS[6]/Diag.[2]/ET[4] ET [3] / Diag. [7]
1BVB2 Stand Mod. Eng.Div. DO MS BL [0.5]
Dipole Vacuum Box UCN [1] UCN [6] MS [8] BL [1]
1AM4(ToF)/1AM4.5 Diag. [3] Stu. [3] Diag. [2] / Stu. [5] Diag. [2] / Stu. [6]
Kicker Beamtube UCN [3.5] UCN [5.5] UCN [3.5] BL [2.5]Kicker Stand UCN [3.5] UCN [6.5] MS [5] / UCN [2.5] BL [4]
Resource Requirements 8
Summary: Resource Requirements 9
[ Time Estimate in Person-Weeks ]
Meson-Hall Cleanup 2013 (+ 2014 non-S/D?)
M11 Platform (2013 ) 2013 non-S/D CleanupPG [12] PG [70]BL [4] BL [34]
EL [16]
Preparations for 2014 S/D (2013)
Safety [3] DO [14] MS [32]BL [28]Diag. [24]ET [7]
UCN.Eng [46]UCN.Des [34]UCN.Stu [14]
2014 S/D (UCN Installation)PG [21]BL [39]Vac [6]Con.[6]
FINIS
10
List of Major Milestones
2013 – May UCN Beamline Review
2014 – May BL1U US-section (Kicker beamtube, Septum, Dipole) Installed.
2014 – Aug UCN/nEDM RCNP phase completed.Begin Uninstall for transport to TRIUMF.
2015 – Apr UCN Source received at TRIUMF.(Unpack and Begin Cold Tests of UCN Source)
2015 – July BL1U DS-section Installed.
2016 – July Commission UCN Facility using low intensity beam.
11
Summary: (Reference Scenario)
1. Vault mods: Cleanup issues; BL1B & Vault mods
Jan.2-Mar.29 Rewire Vault Quads for Steering Capability Work Estimate 2 weeks; 1 BL, 1 Contractor (Electrician)
2. Cleanup: M11 experiment area and above 1A/1B shielding blocks
Jan.2-Feb.28 M11 Platform Work Estimate 4 weeks; 1 crane operator, 2 riggers, 1 BL
Mar.1-Aug.30 Cleanup M11 expt area and above 1A/1B shielding blocks Work Estimate 12 weeks; 1 crane operator, 2 riggers, 1 BL
3. Dismantle: M13 expt area (PIENU,Q6,Q7) and Infrastructure/Services
Finish Mar.29 PIENU BG/Calib and remove detectors (PIENU personnel)
Apr.1-Jun.30 Remove PIENU and clear M13 floor area Work Estimate 6 weeks; 1 crane operator, 2 riggers, 1 BL
Jul.1-Sep.30 Remove PIENU-M13 infrastructure & services Work Estimate 8 weeks; 1 crane operator, 1 rigger, 2 BL, 2 EL
Person-Week Sums Shutdown & Meson-Hall Cleanup 2013 [ Time Estimate in Person-Weeks]
2013 Shutdown M11 Platform (2013 ) 2013 non-ShutdownBL [2] PG [12] PG [70]Contr [2] BL [4] BL [34]
EL [16]
Any possible storage solutions left on-site?
MOB
ISAC II
ISAC I
RH
M.S.
Construction
ARIEL
A
D.O./StoresPlant Grp.
Hh
Ff
Constr.
He Fac
Cycl
MH
PH
Gg
Comments:
4. UCN Installation 1 (Jan-May/2014): BL1U, Vault and Upstream Section
Comments:
4. UCN Installation 1 (Jan-May/2014): BL1U, Vault and Upstream Section
Late Dec/2013 Remove large shielding blocks outside (3 days) Start Jan.2/2014 Week 1 RPG survey & prepare for S/D work Week 2 Remove Warm blocks (layers A-D); Disconn.services; Remove 1A vault comp.’s Week 3 Cleanup/Layout BL1U; Specify location for coring of Immovable-block (and tx.) Week 4 - 5 1BVB2 mods (and 1B mods) Week 5 - 7 Install stands for kicker,septum,1UB2; Install & Align kicker-beamtube Week 8 Install & Align septum magnet Week 9 Install & Align 1UB2 magnet and 1UM6 Week 10 Reinstall 1A vault comp.’s; Install Notch-monitor; Install 1AUM5/1UBB2
Week 7 - 9 Install rough-in services (Electrical, Water, Air) Week 10 - 11 Finish Electrical (AC & DC), Water, Air services
Week 11 Finish all vacuum connections Week 12 Leak check & ready to pull vacuum Week 13 Pull vacuum & check-out vacuum controls Week 14 General check-out and ready to cover Week 15 - 16 Restore vault & 1A shielding and prepare for beam
Resources: 3 Beamlines techs (2 BL + Alignment), 13 weeks [39 person-weeks]1 Crane Operator + 2 Riggers, 7 weeks [21 person-weeks]Vacuum Group [6 person-weeks]Services: Outside Contractors, 5 weeks [6 person-weeks]
Mostly Contractors (?)
Clo
se U
p
M
ain
Wor
k
Ope
n U
p
Preparations for 2014 Shutdown: (Design, Procurement, Assembly of Subsystems)
Items/Subsystems Eng. DWGs Procurement Assy./Testing(needed Jan-2014) (incl Modeling)
Vault-BL1A Shielding Saf. / UCN DO UCN n/a
Septum Mods UCN UCN MS / UCN BL / UCNSeptum Vacuum Box UCN UCN MS / UCN BL / UCNSeptum Stand UCN UCN MS / UCN BL / UCN
1UAM5/1UBB2 Diag. DO MS /Diag. / ET ET / Diag.
1BVB2 Stand Mod. Eng.Div. DO MS BL
Dipole Vacuum Box UCN UCN MS BL
1AM4(ToF)/1AM4.5 Diag. UCN Diag. / UCN Diag. / UCN
Kicker Beamtube UCN UCN UCN BL Kicker Stand UCN UCN MS / UCN BL
SEM for BL1B Diag. D.O. Diag. Diag.(M.Trinczek)
Preparations for 2014 Shutdown: [ Time Estimate in Person-Weeks ]
Items/Subsystems Eng. DWGs Procurement Assy./Testing(needed Jan-2014) (incl Modeling)
Vault-BL1A Shielding Saf.[3]/UCN[4] DO [7] UCN [3] n/a
Septum Mods UCN [8] UCN [4] MS [2] / UCN [1] BL [10] / UCN [2]Septum Vacuum Box UCN [3.5] UCN [6] MS [6] / UCN [1] BL [6] / UCN [3]Septum Stand UCN [3.5] UCN [6] MS [5] / UCN [1] BL [4] / UCN [2]
1UAM5/1UBB2 Diag. [8] DO [7] MS[6]/Diag.[2]/ET[4] ET [3] / Diag. [7]
1BVB2 Stand Mod. Eng.Div. [1.5] DO [3] MS [2] BL [2]
Dipole Vacuum Box UCN [1] UCN [6] MS [8] BL [1]
1AM4(ToF)/1AM4.5 Diag. [3] UCN [6] Diag. [2] / UCN [5] Diag. [2] / UCN [6]
Kicker Beamtube UCN [3.5] UCN [5.5] UCN [3.5] BL [2.5]Kicker Stand UCN [3.5] UCN [6.5] MS [5] / UCN [2.5] BL [4]
SEM for BL1B Diag. [2] D.O. [2] Diag. [3] Diag. [3](M.Trinczek)
UCN Designer (need to hire)
Person-Week Sums: Summary [ Time Estimate in Person-Weeks ]
Shutdown & Meson-Hall Cleanup 2013 & 2014
2013 S/D M11 Platform (2013 ) 2013 non-S/DBL [4] PG [12] PG [70]
BL [4] BL [34]EL [16]
2014 S/DPG [21]BL [39]Vac [6]Con.[6]
Preparations for 2014 S/D (2012,2013)
Safety [3] Eng.Div [1.5]DO [19] MS [34]BL [29.5]Diag. [32]ET [7]
UCN.Eng [46]UCN.Des [34]UCN.Stu [17]
Preparations for 2014 Shutdown: [ Time Estimate in Person-Weeks ]
(Deferral Options - Prioritized)
Items/Subsystems Eng. DWGs Procurement Assy./Testing(needed Jan-2014) (incl Modeling)
Vault-BL1A Shielding Saf.[3]/UCN[4] DO [7] UCN [3] n/a
Septum Mods UCN [8] UCN [4] MS [2] / UCN [1] BL [10] / UCN [2]Septum Vacuum Box UCN [3.5] UCN [6] MS [6] / UCN [1] BL [6] / UCN [3]Septum Stand UCN [3.5] UCN [6] MS [5] / UCN [1] BL [4] / UCN [2]
1UAM5/1UBB2 Diag. [8] DO [7] MS[6]/Diag.[2]/ET[4] ET [3] / Diag. [7]
1BVB2 Stand Mod. Eng.Div. [1.5] DO [3] MS [2] BL [2]
Dipole Vacuum Box UCN [1] UCN [6] MS [8] BL [1]
1AM4(ToF)/1AM4.5 Diag. [3] UCN [6] Diag. [2] / UCN [5] Diag. [2] / UCN [6]
Kicker Beamtube UCN [3.5] UCN [5.5] UCN [3.5] BL [2.5]Kicker Stand UCN [3.5] UCN [6.5] MS [5] / UCN [2.5] BL [4]
SEM for BL1B Diag. [2] D.O. [2] Diag. [3] Diag. [3](M.Trinczek)
JOA J
2012
JOA J
2013
JOA J
2014
A J O
2015
Oct. 17, 2012
Major TasksJ A J O
2016
ARIEL & Shutdown Plan (2012-2016) - DRAFT
Install Kicker, UCN Beam line, Services & Controls
Complete Shielding & Commissioning Tests
Mod Vault Quads (rem. Steerers), 1BVB2, and BL1A/1B
Install Kicker Ceramic beam Tube & Services
Install Base Layer of UCN Shielding to Run BL/1A
Core through M13 Block
2012
/ 2
013
2014
2015
Complete M20 Front end & M9A Front end work
Install Septum & Dipole (with services, where possible)
Remove & Store M13 Front end, Hot Blocks & Crumbling Blocks
Install UCN Spallation Target & R/Handling System, & UCN Source
Install UCN Shielding
Legend:
Shutdown Jobs
Non Shutdown Jobs
Reconfigure Vault-to-1A Shld, and beamline Shld to run 1A
Cleanup (incl M11 Expt area, above 1A/1B shielding blocks)
ARIEL & E-Linac MilestonesTunnel &Bldg Avail
LC (50Kw)e-Beam
100Kwe-Beam
E-HallAvailable
Construction
Install & Connect ELBT & EINJ-2 in E-Hall
Cryogenic Plant (delivery & operational)
Test & Commission High Power RF System (Klystron & HVPS)
Install EHBT from ACM to Target Hall
Install & Connect EACA, Test & Comm Beam in E-Hall (50kW & 100kW)
AR
IEL
& E
-Lin
acS
hu
tdo
wn
s
Complete IRIS
Complete EMMA
Hel liquefier system (and UCN upgrade) Procure & InstDsgn
2016
Procure & Inst Upgrades
Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services
Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods