17
Today 30-Mar Memorandum of Meeting. Date of Meeting: 12/08/2015 Location: Chilca UNO CCPP Attenders: Enersur Luis Zambrano Anibal Quezada Nilton Viera Cynthia Gutierrez Attenders: VOITH TURBO Eduardo Casanova General Subject Overhaul TC EL9YGTM 4,0 - 86 sn:8203463 July 2016 ItemTask Subject Description and Actions Responsible To Update To Close Date Comments 1 12-Aug 12-Aug 1 Spare Parts ### 6-Oct ### 31-Oct 2 7-Sep 30-Sep 3 General Tools (Workshop Tools) Eduardo Casanova (VOITH) ### 15-Jan ### 28-Feb 4 Eduardo Casanova (VOITH) ### 6-Nov ### 31-Jan [email protected] [email protected] [email protected] [email protected] [email protected] Overhaul TC-EL9YGTM 4,0-86 TG21 Extraction of Torque Converter from TG21. 1-) ENERSUR will reitre the Torque Converter from the Gen Train to enable it to be transported to the workshop (or designed site for the Overhaul). 2-) VOITH will start the Task with the Torque Converter retired from the Train. Luis Zambrano (ENERSUR) Anibal Quezada (ENERSUR) //// // /// /// According to EL9_SGANTT_89 Overhaul TC-EL9YGTM 4,0-86 TG21 1-) VOITH will sent the list of recommended Spare Parts for an Overhaul, identifying the additional items to complete actual stock in ENERSUR (warehouse). 2-) ENERSUR will sent a RFQ for the needed Spare Parts (codified in EL9_SP_01) 1-) VOITH will sent the Revised Offer for the RFQ from ENERSUR. 2-) ENERSUR will sent the P.O(Purchase order) as Eduardo Casanova (VOITH) Anibal Quezada (ENERSUR) Cynthia Gutierrez (ENERSUR) Estimated Delivery Time for Spare parts goes around 7 (SEVEN) months. Esimated date for Overhaul is shceduled for July 2016. Overhaul TC-EL9YGTM 4,0-86 TG22 VOITH Special Tools Multifunctional Special Tools 1-) VOITH will sent the list of VOITH Special Tools (codified as spare parts and only for Torque Converters) - EL9_SP_01 2-) VOITH will sent the list of Special Tools (Multinfunctional). - EL9_ST_01 3-) ENERSUR will confirm the avilability of all Eduardo Casanova (VOIHT) Anibal Quezada (ENERSUR) //// // /// /// Some special Tools could be bring by VOITH FSE, but the ENERPACK RCH-306 should be available on site due to its weight. The list must be bounded. Overhaul TC-EL9YGTM 4,0-86 TG23 1-) VOITH will sent the list of th egeneral Tools needed for an Overhaul. EL9_GT_01. 2-) ENERSUR will have the tools listed on EL9_GNTL_01 for OVH date. General Tools List contain all usual tools available in Workshop. To be reviewed 3 months before the OVH. Overhaul TC-EL9YGTM 4,0-86 TG24 Liability partner for operational support 1-) VOITH will confirm the possibility of presenting a proposal for the maintenance including operational support. This has to be evaluated internally because of suppliers validation.

2015-10-02 Voith Mom Enersur Uptooct-2015v1.0

Embed Size (px)

DESCRIPTION

2015-10-02 VOITH MoM ENERSUR UptoOct-2015v1.0.xls

Citation preview

Page 1: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0

Today 18-Apr

Memorandum of Meeting.

Date of Meeting: 12/08/2015Location: Chilca UNO CCPPAttenders: Enersur

Luis ZambranoAnibal QuezadaNilton VieraCynthia Gutierrez

Attenders: VOITH TURBOEduardo Casanova

General Subject Overhaul TC EL9YGTM 4,0 - 86 sn:8203463 July 2016

ItemTask Subject Description and Actions Responsible To Update To Close Date Comments STATUS

1 Extraction of Torque Converter from TG21.

//////

12-Aug

//////

12-Aug

CLOSED

1 Spare Parts

###

6-Oct

###

31-Oct

2

//////

7-Sep

//////

30-Sep

CLOSED

3 General Tools (Workshop Tools) Eduardo Casanova (VOITH)

###

15-Jan

###

28-Feb

OPEN

4 Liability partner for operational support Eduardo Casanova (VOITH)

###

6-Nov

###

31-Jan

[email protected]@[email protected]@enersur.com.pe

[email protected]

Overhaul TC-EL9YGTM 4,0-86 TG21

1-) ENERSUR will reitre the Torque Converter from the Gen Train to enable it to be transported to the workshop (or designed site for the Overhaul).2-) VOITH will start the Task with the Torque Converter retired from the Train.

Luis Zambrano (ENERSUR)Anibal Quezada (ENERSUR)

According to EL9_SGANTT_89

Overhaul TC-EL9YGTM 4,0-86 TG21

1-) VOITH will sent the list of recommended Spare Parts for an Overhaul, identifying the additional items to complete actual stock in ENERSUR (warehouse).2-) ENERSUR will sent a RFQ for the needed Spare Parts (codified in EL9_SP_01)1-) VOITH will sent the Revised Offer for the RFQ from ENERSUR.2-) ENERSUR will sent the P.O(Purchase order) as confirmation to start the manufacturing process.

Eduardo Casanova (VOITH)Anibal Quezada (ENERSUR)

Cynthia Gutierrez (ENERSUR)

Estimated Delivery Time for Spare parts goes around 7 (SEVEN) months.Esimated date for Overhaul is shceduled for July 2016.

IN PROCESS

Overhaul TC-EL9YGTM 4,0-86 TG22

VOITH Special Tools Multifunctional Special Tools

1-) VOITH will sent the list of VOITH Special Tools (codified as spare parts and only for Torque Converters) - EL9_SP_012-) VOITH will sent the list of Special Tools (Multinfunctional). - EL9_ST_013-) ENERSUR will confirm the avilability of all Special Tools.

Eduardo Casanova (VOIHT)Anibal Quezada (ENERSUR)

Some special Tools could be bring by VOITH FSE, but the ENERPACK RCH-306 should be available on site due to its weight.The list must be bounded.

Overhaul TC-EL9YGTM 4,0-86 TG23

1-) VOITH will sent the list of th egeneral Tools needed for an Overhaul. EL9_GT_01.2-) ENERSUR will have the tools listed on EL9_GNTL_01 for OVH date.

General Tools List contain all usual tools available in Workshop.To be reviewed 3 months before the OVH.

Overhaul TC-EL9YGTM 4,0-86 TG24

1-) VOITH will confirm the possibility of presenting a proposal for the maintenance including operational support.

This has to be evaluated internally because of suppliers validation.

IN PROCESS

G23
Casanova, Eduardo: NEXT UPDATE
I24
Casanova, Eduardo: Close Date with clearances due to Delivery Time
I25
Casanova, Eduardo: Close Date with clearances due to Delivery Time
Page 2: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0

5

###

6-Nov

###

31-Jan

OPEN

6 Spare Unit for Gearbox

###

6-Oct

###

31-Oct

OPEN

7 Final Proposal for Service

###

6-Nov

###

31-Jan

OPEN

8 Starting Package Spare Unit for Motor Booster Pump Eduardo Casanova (VOITH)

###

6-Oct

###

31-Oct

OPEN

Maintenance Turning Gear TC-EL9YGTM 4,0-86 TG24

Inspection of the inner elements of Turning Gear. (Scope of maintenance)

1-) VOITH will evaluate the inclusion of the scope of maintenance/inspection of the Turning Gear in the Torque Converter programmed Overhaul.2-) ENERSUR should confirm the availability of the equipment for the new time scope.

Eduardo Casanova (VOITH)Anibal Quezada (ENERSUR)

This task could raise Total Time in approximately 2 days+

Maintenance Turning Gear TC-EL9YGTM 4,0-86 TG24

1-) VOITH will sent the proposal for an Spare Unit for the gearbox of the Turning Gear with its connecting minor parts.After ENERSUR presents the RFQ.- Parts list EL9_SP_01

Eduardo Casanova (VOITH) Estimated Delivery Time for Spare parts goes around 7 (SEVEN) months.

Overhaul TC-EL9YGTM 4,0-86 TG24

1-) VOITH will prepare the proposal for the service with the established agreements after 30-Sep.

Eduardo Casanova (VOITH) The service must be confirmed through a P.O, 3 months before due to FSE availability.

1-) ENERSUR wil send the information of the PLATE of the pump or the information regarding: Brand, Type and serial number.2-) VOITH will send the proposal for a spare unit for Motor Booster Pump of the Starting Package.

I30
Casanova, Eduardo: Close Date with clearances due to Delivery Time
I32
Casanova, Eduardo: Close Date with clearances due to Delivery Time
Page 3: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0
Page 4: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0
Page 5: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0
Page 6: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0

REF CÓDIGO POSICIÓN DESCRIPCIÓN

200 TCR41313420 2 0020/0380 breather filter300 TCR41901930 4 0010/0010/0030 weight-tol.screw M16X60301 TCR03100006 12 0010/0010/0060 washer303 TCR03049009 2 0010/0020/0060/0020 straight pin304 TCR41523760 60 0010/0020/0070 weight-tol.screw M10X20306 TCR41532690 6 0010/0020/0120 weight-tol.screw M8X20307 TCR03374021 1 0010/0030 tab washer308 TCR03372021 1 0010/0040 slotted nut309 TCR03645180 1 0010/0060 o-ring310 TCR03646099 1 0010/0080 o-ring311 TCR03501137 1 0010/0130 disc ring312 TCR03130042 1 0020/0055 roll pin313 TCR41526370 1 0020/0080 nozzle M 10 - 4D314 TCR03110012 58 0020/0100 spring washer315 TCR03644060 3.9 0020/0110 round cord316 TCR03645271 1 0020/0120 o-ring317 TCR03645265 1 0020/0125 o-ring318 TCR03646005 2 0020/0130 o-ring319 TCR03014065 6 0020/0180 socket head screw320 TCR03111084 6 0020/0190 spring washer 8,4X13,5X0,5322 H01229633 1 0020/0220 o ring323 TCR03645276 1 0020/0280 o-ring324 TCR03111105 40 0020/0295 spring washer325 TCR03014069 16 0020/0310 socket head screw326 TCR03110010 14 0020/0370 spring washer327 TCR03656022 2 0020/0390 seal ring328 H01002331 1 0020/0500 circlip329 TCR03658030 5 0020/0520 seal ring330 TCR03171024 1 0020/0550 circlip331 TCR03130075 1 0020/0560 spr.type str.pin332 TCR03656017 8 0020/0610 seal ring333 TCR03658017 6 0020/0670 seal ring334 TCR03000413 2 0020/0750 pipe clamp335 TCR03669999 0.04 0020/0760 elastic insert337 TCR03658022 2 0020/0900 seal ring338 TCR03645560 1 0020/1000 o-ring339 TCR03646013 1 0020/1010 o-ring341 TCR03111118 39 0020/1300 spring washer A17X25X1,2342 TCR03130076 3 0020/1400 roll pin343 TCR03130060 3 0020/1600 roll pin344 TCR03014062 32 0030/0030 socket head screw345 TCR03049060 64 0030/0040 straight pin346 H01000509 32 0030/0060 socket head screw347 TCR41583470 32 0030/0070 pin348 TCR03646021 32 0030/0075 o-ring350 TCR03017102 4 0030/0110 socket head screw351 TCR03094300 2 0030/0130 bush352 TCR03170030 2 0030/0150 circlip

Cantidad Requerida

Page 7: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0

353 TCR03645850 1 0040/0015 o-ring354 TCR03645685 1 0040/0020 o-ring357 TCR03210129 24 0040/0060 cyl.compr.spring358 TCR03683402 4 0040/0090 shaft seal ring359 TCR03683113 1 0040/0130 shaft seal ring360 TCR03172550 1 0040/0145 inner ring361 TCR03645203 2 0040/0150 o-ring362 TCR41566840 2 0040/0240 adjusting ring363 TCR03645020 2 0040/0250 o-ring364 TCR03646482 2 0040/0300 o-ring365 TCR41548550 2 0040/0340 seal366 TCR03110009 10 0040/0365 spring washer369 TCR03210182 1 0060/0020 cyl.compr.spring370 TCR03210181 1 0060/0030 cyl.compr.spring371 TCR41546510 1 0060/0050 seal372 TCR03093905 1 0060/0070 jig bush373 TCR41564160 1 0060/0080 pin374 TCR03646006 1 0060/0090 o-ring375 TCR03100908 1 0060/0100 lock washer376 TCR03210019 1 0060/0110 cyl.compr.spring378 TCR41546520 1 0060/0170 seal379 TCR03645007 5 0060/0190/ o-ring380 H01002339 1 0080/0090 circlip381 TCR41554600 1 0080/0110 bush 120/26X157,5382 TCR03687101 2 0100/0080 r-ring384 TCR03646291 1 0100/0170 o-ring385 TCR03645050 2 0100/0180 o-ring387 TCR49950065 1 0100/0290 hose clip388 TCR03670151 1 0100/0300 bellows389 TCR03000400 1 0100/0310 hose clip390 TCR03656020 1 0100/0385 seal ring391 TCR03130048 1 0100/0440 roll pin393 TCR41576900 1 0160/0030 seal394 TCR41530010 1 0160/0050 seal395 TCR41534230 2 0160/0070 seal396 TCR41583320 1 0030/0120 butt strap 60X20X167397 TCR03134009 1 0030/0140 pin398 TCR41539810 1 0040/0080 pin 9,9X25

1000 20700161310 1 0080/0010 four lobe bearing1001 20700163110 1 0080/0020 four lobe bearing1002 TCR03305521 2 0080/0030 ang.con.ball bearing1003 TCR41526150 1 0080/0035 spacer ring BAUGRUPPE1004 20700110310 2 0080/0040 thrust bearing BGR. 355X175X50,81005 TCR03302245 1 0080/0050 dp.groove ball bearing1006 TCR03302246 1 0080/0060 dp.groove ball bearing1007 TCR03306123 1 0080/0070 cyl.roller bg.1008 TCR03306521 1 0080/0080 cyl.roller bg.1009 TCR03306588 1 0080/0100 taper roller bearing1500 TCR41552700 1 0060/0190 hydro direct.valve1501 TCR41559180 1 0100/0360 valve NACHARBEIT1700 20700111210 1 0010/0150 overrunning clutch

Page 8: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0

4000 TCR41566850 1 thrust spindle4001 TCR41569390 1 thrust spindle4002 TCR41565170 1 thrust spindle4003 2070010821 1 washer 255/37X254004 2070003851 1 spacer tube 114,3/85,5x2204005 2070010831 2 washer 150/25x204006 2070010841 1 washer 380/37x204007 2070003881 1 washer 170/60x204008 2070010851 1 spacer tube 121/100,5x1704009 2070010861 1 spacer tube 146/120,5x3004010 TCR41577390 3 spacer 25X65

Turning Gear101 20700101510 1 Gearbox102 TCR030442015 8 Stud103 TCR03072016 8 hexagon nut104 TCR41553390 1 Connecting Coupling

Page 9: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0

DELTA

2 08 4

24 124 2

73 1312 6

2 12 12 12 12 12 12 1

116 587.8 3.9

2 12 14 2

12 612 6

1 02 1

80 4012 -428 14

4 22 18 32 12 1

16 812 6

4 20.08 0.04

4 22 12 1

54 156 36 3

64 32128 64

64 3232 064 32

8 44 24 2

STOCK ENERSUR

G1
Casanova, Eduardo: La diferencia debe ser solicitada (<0) para el siguiente OVH
Page 10: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0

2 12 1

48 248 42 12 14 24 24 24 24 2

20 102 12 12 12 11 02 12 12 12 1

10 52 12 14 22 14 21 02 12 12 12 12 12 14 21 01 01 00 -10 -12 01 00 -21 01 01 00 -10 -10 -10 -10 -1

Page 11: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0

1 01 01 01 01 02 01 01 01 01 03 0

0 -10 -80 -80 -1

Page 12: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0

REF CÓDIGO CANT POSICIÓNDESCRIPCIÓN STOCK4000 TCR41566850 1 thrust spindle SI4001 TCR41569390 1 thrust spindle SI4002 TCR41565170 1 thrust spindle SI4003 2070010821 1 washer 255/37X25 SI4004 2070003851 1 spacer tube 114,3/85,5x220 SI4005 2070010831 2 washer 150/25x20 SI4006 2070010841 1 washer 380/37x20 SI4007 2070003881 1 washer 170/60x20 SI4008 2070010851 1 spacer tube 121/100,5x170 SI4009 2070010861 1 spacer tube 146/120,5x300 SI4010 TCR41577390 3 spacer 25X65 SI

La lista de Herramientas especiales será corroborada antes del servicio.

F1
Casanova, Eduardo: Stock de Enersur
Page 13: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0
Page 14: 2015-10-02 Voith Mom Enersur Uptooct-2015v1.0

Horario 8 9 ######################## 8 9 ######################## 8 9 ##################### 8 9 ##################### 8 9 ##################### 8 9 ##################### 8 9 ######################## 8 9 ##################### 8 9 ######Día N Día N+1 Día N+2 Día N+3 Día N+4 Día N+5 Día N+6 Día N+7 Día N+8

1 2 3 4 5 6 7 8 9 ##################################################################################################################################################################################################################

Start End

Inspección de Taller 1 8:00 9:00 1Inspección y preparación de las herramientas y dispositivos de transporte 1 9:00 10:00 1Coordinación con el equipo de apoyo 1 10:00 11:00 1Desconexión de los ejes del motor y máquina accionada, bridas de las tuberias y pines de fijación 1 11:00 12:00 1Almuerzo 1 12:00 13:00 1Desconexión de los ejes del motor y máquina accionada, bridas de las tuberias y pines de fijación 3 13:00 16:00 1 1 1Retirada de la caseta 2 16:00 18:00 1 1Transporte y condicionamiento en el taller 2 8:00 10:00 1 1Desmontaje del acoplamiento del eje de entrada con la bomba de lubricación de aceite. 1 10:00 11:00 1Desmontaje del sistema de Giro Lento (embrague, carcasa y pistones) 1 11:00 12:00 1Almuerzo 1 12:00 13:00 1Desmontaje del sistema de Giro Lento (embrague, carcasa y pistones) 3 13:00 16:00 1 1 1Abertura de la carcaza del reductor y retirada de los engranes 2 16:00 18:00 1 1Desmontaje del convertidor de Torque 1 4 8:00 12:00 1 1 1 1Almuerzo 1 12:00 13:00 1Desmontaje del convertidor de Torque 2 4 13:00 17:00 1 1 1 1Inspección de las piezas 4 10:00 12:00 1 1 1 1Almuerzo 1 12:00 13:00 1Análisis y medición de los componentes 3 13:00 16:00 1 1 1Ensamble del convertidor de Torque 1 16:00 17:00 1Ensamble del convertidor de Torque 4 8:00 12:00 1 1 1 1Almuerzo 1 12:00 13:00 1Ensamble del convertidor de Torque 3 13:00 16:00 1 1 1Montaje del reductor y ajuste de los parámetros de los rodamientos cónicos en el eje de salida. 1 16:00 17:00 1Montaje del reductor y ajuste de los parámetros de los rodamientos cónicos en el eje de salida. 3 8:00 11:00 1 1 1Montaje del sistema de Giro Lento 1 11:00 12:00 1Almuerzo 1 12:00 13:00 1Montaje del sistema de Giro Lento 3 13:00 16:00 1 1 1Montaje del acoplamiento del eje de entrada 1 16:00 17:00 1Transporte a sitio (skid) 1 8:00 9:00 1Alineamiento 3 9:00 12:00 1 1 1Almuerzo 1 12:00 13:00 1Alineamiento 5 13:00 18:00 1 1 1 1 1Ensamble caja de accesorios y tuberias de aceite 4 8:00 12:00 1 1 1 1Almuerzo 1 12:00 13:00 1Reinstalación de los instrumentos y cableado eléctrico 2 13:00 15:00 1 1Pruebas 2 15:00 17:00 1 1Pruebas 4 8:00 12:00 1 1 1 1TOTAL 79

Día N - Día de arranque en los trabajos

El tiempo establecido es un aproximado teniendo en cuenta condiciones ideales de trabajoPara el día N+1, en caso de existir, la caseta puede estar fuera del skid para reducir tiempos de trabajoLa disponibilidad de repuestos de inspección y herramientas especiales es imprescindible en todo momento.El programa esta establecido bajo condiciones de apoyo operativo continuo Tiempo estimado de trabajo: 79 hrs* El alcance de la reparación es relativo al análisis realizado en el equipo (Los tiempos pueden variar considerablemente)El trabajo directo se realizará en aproximadamente 8 - 9 días.Los procesos de Alineamiento y pruebas dependen de la programación del mantenimiento global del cliente.

Mantenimiento Mayor (OVH) Convertidor de Torque EL9YGTMGantt view with 1 Shift / 8 - 9 Hours Time

(hrs)