Upload
nguyennhan
View
222
Download
9
Embed Size (px)
Citation preview
© 2015 HDR, Inc., all rights reserved.
Hastings Utilities Water Pollution Control Facility ImprovementsBrian Bakke , HDR
ASCE Environmental Conference
4/6/2017
Review Existing Facilities
Need for the Project
Study Phase
Design Phase
Construction Phase
Start-Up and Operation
01 Review Existing Facilities
Existing Facility Site Plan
Rotating Biological Contactors (not in operation)
Trickling Filter provides bulk of treatment
Existing Facility
02 Need for the project –Permit Limits
Existing permit (effective July 1, 2008) includes transition to final lower
ammonia limits
Permit Compliance Dates
January 31, 2012 – Submit Design for Upgrades
June 30, 2012 – Initiate Construction
April 2014 – Be in Compliance
Permit Limits - Ammonia
Condition 2003 Permit
2008 Permit
Interim
2008 Permit
Final
Fall and Winter Ave. 8.1 mg/l 8.7 mg/L 2.48 mg/L
Spring and Summer Ave. 8.5 mg/l 8.1 mg/L 1.88 mg/L
Residential growth projected at
0.5% per year. Same as Water
Master Plan
Study: Future Flows and Loadings
Year Population
2010 25,226
2015 25,862
2020 26,516
2025 27,185
2030 27,872
Prior to June 2009 Influent to PCF - 50-65% industrial wastewater
Since July 2009 two major industries have not been in operation.
New tenants plan on resuming operation in the near future.
Discussions with each industry helped establish projected flows and
loads when they resume operation. (60% of previous contributions)
Industrial reserve of built into planning numbers to account for potential
future industries.
Industrial Contributions
Projected Flows
Projected CBOD Loadings
Biochemical
Oxygen Demand
(BOD) removed
before ammonia
is removed.
High BOD load
does not leave
enough room for
ammonia removal
zone.
Existing Facility: Trickling Filter
BOD Removal
Zone
Ammonia
Removal Zone
Inflow
Outflow
Existing plant has capacity to meet interim permit with trickling filter
through 2015 with some reserve for industry
Existing plant does not have capacity to meet final permit limits, even at
current loadings.
Additional facilities are needed to achieve the new limits.
Existing Treatment Facility
What should be built and how much??
What other regulatory drivers should be considered??
Future Permit Limits
Future Permit Scenarios Considered:
• 10 mg/L TN and 1.0 mg/L TP (7-12 years)
• 5 mg/L TN and 0.5 mg/L TP (15-20 years)
• 3 mg/L TN and 0.3 mg/L TP (>20 years)
Recommended Improvements: Evaluation Methodology
Regulatory Timeline
Current
Limits
Lower Ammonia
Limits
10 mg/L TN
1 mg/L TP
5 mg/L TN
0.5 mg/L TP3 mg/L TN
0.3 mg/L TP
Long Term
Improvements
Short Term
Three options evaluated for existing final ammonia permit limits
Activated sludge lowest cost option
All options utilized the existing Trickling filter in a parallel mode
operation
Improvements to Meet Existing Ammonia Limits
Cost Component
Alternative 1 –
Activated Sludge
Alternative 2 -
IFAS
Alternative 3 -
MBBR
Estimated Capital Costs $8,680,000 $8,050,000 $10,250,000
Estimated Present Worth
O&M Costs$1,880,000 $2,890,000 $3,930,000
Total Present Worth Life
Cycle Costs$10,560,000 $10,940,000 $14,180,000
Proposed Site Plan for Recommended Improvements
03 Study Phase
Study Methodology
Regulatory Timeline
Current
Limits
Lower Ammonia
Limits
10 mg/L TN
1 mg/L TP
5 mg/L TN
0.5 mg/L TP3 mg/L TN
0.3 mg/L TP
Long Term
Improvements
Short Term
Evaluation of Future Limits(10 mg/l N and 1 mg/l P)
Cost Component
Alternative 1 –
Trickling Filters
with Activated
Sludge
Alternative 2 –
BNR Activated
Sludge
Alternative 3 –
Hybrid Process
Number of Trickling Filters in
ServiceTwo Zero One
Estimated Capital Costs $16,430,000 $12,300,000 $10,420,000
Estimated Present Worth
O&M Costs$5,341,000 $2,827,000 $2,678,000
Total Present Worth Life
Cycle Costs$21,771,000 $15,127,000 $13,098,000
Plan developed for future more restrictive permits
Implementation Plan
Chosen Path Forward by the City
$10,420,000
Permit Limit
Existing Final
Ammonia
10 mg/L
Nitrogen
1 mg/L
Phosphorous
5 mg/L
Nitrogen
0.5 mg/L
Phosphorous
3 mg/L
Nitrogen
0.3 mg/L
Phosphorous
Estimated Timing Now 7-12 years 15-20 years >20 years
Estimated Capital Cost $8,680,000 $1,740,000 $2,500,000Increase in
Operational Cost
04 Design Phase
Design Criteria
Peak WW flow – 15 MGD
2030 Avg Annual Max Month Peak Day
Flow MGD 5.3 5.7 7.0
CBOD lbs/day 10,300 17,800 29,600
mg/l 234 377 508
TSS lbs/day 8,600 14,600 26,300
mg/l 195 309 450
NH3 lbs/day 930 1,370 4,470
mg/L 21 29 77
Design – Site Layout
Enhanced Nitrification BNR Activated Sludge - ENBNRAS
ScreenGrit Removal
Primary
Clarifiers
Lagoon
Storage
Land
Application
Secondary
Digestion
Primary
Digestion
Influent
Final EffluentAnoxic
A
BA
B
B
Anaerobic Aerobic
Secondary
Clarifiers
(14-FT SWD)
RAS
MLR
WAS
Nitrification Only
Nitrogen Removal
Full BNR Mode
Design – BNR Basin
Aeration
Basin
Effluent
Aerobic Anoxic Anaerobic
`Anoxic Anaerobic
Anoxic
Anoxic CS No. 8
PE Splitter
Aerobic
Design – BNR Basin
Aeration
Basin
Effluent
Aerobic Anoxic Anaerobic
`
To Inter.
Clar.
Anoxic Anaerobic
Anoxic
Anoxic CS No. 8
PE Splitter
MLR
MLR
MLR
MLR
Aerobic
Design – BNR Basin
Aeration
Basin
Effluent
Aerobic Anoxic Anaerobic
`
To Inter.
Clar.
Anoxic Anaerobic
Anoxic
Anoxic
CS No. 9 RAS SplitterCS No. 10 Trickling
Filter Effluent Splitter
CS No. 8
PE Splitter
MLR
MLR
MLR
MLR
Aerobic
Anaerobic, Anoxic and Aerobic zones
• 194’ length x 46’ width x 22’ tall concrete
tank
Fine Bubble Diffusers
• 9” Membrane Discs
Submersible Mixers (3 per train) – 10 HP
Mixed Liquor Recycle Pumps (2 per train)
• Anoxic to Anaerobic – 2,000 GPM, 10 HP
• Aerobic to Anoxic – 4,900 GPM, 40 HP
Design – BNR Basin
Design – BNR basin
4 RAS pumps – VTSH type
• 2,500 GPM, 40 HP
2 WAS Pumps – Self
Priming
• 250 GPM, 7.5 HP
2 ILS Pumps – VTSH Type
• 5,600 GPM, 40 HP
Design – Pump/Blower Building
4 High Speed Turbo Blowers
• 2,500 SCFM, 150 HP
• VFD
Stand by Generator
Electrical and Control Room
Design – Pump/Blower Building
Final Clarifier
• 80’ Diameter
• Stainless Steel
Mechanism
Design – Final Clarifier
Design – Site Layout
Lift
Station
Final
Clarifier
Aeration
Basin
Bid in April 2012
Four Bids
Project awarded to Eriksen Construction, Blair, NE
Engineers Estimate - $11.5 million
Design – Bid Results
Eriksen
Construction
John T Jones
Construction
PKG
Contracting
BRB
Contractors
$10,431,000 $10,970,000 $11,096,000 $11,782,000
05 Construction Phase
Contract Price:
Construction Timeline
June 2012
Eriksen issued
Notice to Proceed
2012 2013 2014
January 15, 2014
Substantial Completion
March 15, 2014
Final Completion
Mid-Late November
Startup activities begin
Contractual Dates
85-90% Complete
Bid:
$10,413,000
Final:
$10,487,000
Change Orders:
0.7%
Aeration Basin
Electrical Room MCC
Pump Room
Pipe Gallery – Dry well area
West Exterior View
Final Clarifier
06 Start-Up and Operation
Parallel Flow Process
Will be used at
startup
Allows staff to
become familiar
with AS
Operational cost
savings
Influent Loadings
Effluent Quality
Effluent Quality
Nitrogen Removal Performance
Effluent Phosphorus
Questions