55
© 2015 HDR, Inc., all rights reserved.

© 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Embed Size (px)

Citation preview

Page 1: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

© 2015 HDR, Inc., all rights reserved.

Page 2: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Hastings Utilities Water Pollution Control Facility ImprovementsBrian Bakke , HDR

ASCE Environmental Conference

4/6/2017

Page 3: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Review Existing Facilities

Need for the Project

Study Phase

Design Phase

Construction Phase

Start-Up and Operation

Page 4: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

01 Review Existing Facilities

Page 5: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Existing Facility Site Plan

Page 6: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Rotating Biological Contactors (not in operation)

Trickling Filter provides bulk of treatment

Existing Facility

Page 7: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

02 Need for the project –Permit Limits

Page 8: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Existing permit (effective July 1, 2008) includes transition to final lower

ammonia limits

Permit Compliance Dates

January 31, 2012 – Submit Design for Upgrades

June 30, 2012 – Initiate Construction

April 2014 – Be in Compliance

Permit Limits - Ammonia

Condition 2003 Permit

2008 Permit

Interim

2008 Permit

Final

Fall and Winter Ave. 8.1 mg/l 8.7 mg/L 2.48 mg/L

Spring and Summer Ave. 8.5 mg/l 8.1 mg/L 1.88 mg/L

Page 9: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Residential growth projected at

0.5% per year. Same as Water

Master Plan

Study: Future Flows and Loadings

Year Population

2010 25,226

2015 25,862

2020 26,516

2025 27,185

2030 27,872

Page 10: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Prior to June 2009 Influent to PCF - 50-65% industrial wastewater

Since July 2009 two major industries have not been in operation.

New tenants plan on resuming operation in the near future.

Discussions with each industry helped establish projected flows and

loads when they resume operation. (60% of previous contributions)

Industrial reserve of built into planning numbers to account for potential

future industries.

Industrial Contributions

Page 11: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Projected Flows

Page 12: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Projected CBOD Loadings

Page 13: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Biochemical

Oxygen Demand

(BOD) removed

before ammonia

is removed.

High BOD load

does not leave

enough room for

ammonia removal

zone.

Existing Facility: Trickling Filter

BOD Removal

Zone

Ammonia

Removal Zone

Inflow

Outflow

Page 14: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Existing plant has capacity to meet interim permit with trickling filter

through 2015 with some reserve for industry

Existing plant does not have capacity to meet final permit limits, even at

current loadings.

Additional facilities are needed to achieve the new limits.

Existing Treatment Facility

What should be built and how much??

What other regulatory drivers should be considered??

Page 15: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Future Permit Limits

Future Permit Scenarios Considered:

• 10 mg/L TN and 1.0 mg/L TP (7-12 years)

• 5 mg/L TN and 0.5 mg/L TP (15-20 years)

• 3 mg/L TN and 0.3 mg/L TP (>20 years)

Page 16: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Recommended Improvements: Evaluation Methodology

Regulatory Timeline

Current

Limits

Lower Ammonia

Limits

10 mg/L TN

1 mg/L TP

5 mg/L TN

0.5 mg/L TP3 mg/L TN

0.3 mg/L TP

Long Term

Improvements

Short Term

Page 17: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Three options evaluated for existing final ammonia permit limits

Activated sludge lowest cost option

All options utilized the existing Trickling filter in a parallel mode

operation

Improvements to Meet Existing Ammonia Limits

Cost Component

Alternative 1 –

Activated Sludge

Alternative 2 -

IFAS

Alternative 3 -

MBBR

Estimated Capital Costs $8,680,000 $8,050,000 $10,250,000

Estimated Present Worth

O&M Costs$1,880,000 $2,890,000 $3,930,000

Total Present Worth Life

Cycle Costs$10,560,000 $10,940,000 $14,180,000

Page 18: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Proposed Site Plan for Recommended Improvements

Page 19: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

03 Study Phase

Page 20: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Study Methodology

Regulatory Timeline

Current

Limits

Lower Ammonia

Limits

10 mg/L TN

1 mg/L TP

5 mg/L TN

0.5 mg/L TP3 mg/L TN

0.3 mg/L TP

Long Term

Improvements

Short Term

Page 21: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Evaluation of Future Limits(10 mg/l N and 1 mg/l P)

Cost Component

Alternative 1 –

Trickling Filters

with Activated

Sludge

Alternative 2 –

BNR Activated

Sludge

Alternative 3 –

Hybrid Process

Number of Trickling Filters in

ServiceTwo Zero One

Estimated Capital Costs $16,430,000 $12,300,000 $10,420,000

Estimated Present Worth

O&M Costs$5,341,000 $2,827,000 $2,678,000

Total Present Worth Life

Cycle Costs$21,771,000 $15,127,000 $13,098,000

Page 22: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Plan developed for future more restrictive permits

Implementation Plan

Chosen Path Forward by the City

$10,420,000

Permit Limit

Existing Final

Ammonia

10 mg/L

Nitrogen

1 mg/L

Phosphorous

5 mg/L

Nitrogen

0.5 mg/L

Phosphorous

3 mg/L

Nitrogen

0.3 mg/L

Phosphorous

Estimated Timing Now 7-12 years 15-20 years >20 years

Estimated Capital Cost $8,680,000 $1,740,000 $2,500,000Increase in

Operational Cost

Page 23: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

04 Design Phase

Page 24: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Design Criteria

Peak WW flow – 15 MGD

2030 Avg Annual Max Month Peak Day

Flow MGD 5.3 5.7 7.0

CBOD lbs/day 10,300 17,800 29,600

mg/l 234 377 508

TSS lbs/day 8,600 14,600 26,300

mg/l 195 309 450

NH3 lbs/day 930 1,370 4,470

mg/L 21 29 77

Page 25: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Design – Site Layout

Page 26: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Enhanced Nitrification BNR Activated Sludge - ENBNRAS

ScreenGrit Removal

Primary

Clarifiers

Lagoon

Storage

Land

Application

Secondary

Digestion

Primary

Digestion

Influent

Final EffluentAnoxic

A

BA

B

B

Anaerobic Aerobic

Secondary

Clarifiers

(14-FT SWD)

RAS

MLR

WAS

Page 27: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Nitrification Only

Page 28: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Nitrogen Removal

Page 29: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Full BNR Mode

Page 30: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Design – BNR Basin

Aeration

Basin

Effluent

Aerobic Anoxic Anaerobic

`Anoxic Anaerobic

Anoxic

Anoxic CS No. 8

PE Splitter

Aerobic

Page 31: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Design – BNR Basin

Aeration

Basin

Effluent

Aerobic Anoxic Anaerobic

`

To Inter.

Clar.

Anoxic Anaerobic

Anoxic

Anoxic CS No. 8

PE Splitter

MLR

MLR

MLR

MLR

Aerobic

Page 32: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Design – BNR Basin

Aeration

Basin

Effluent

Aerobic Anoxic Anaerobic

`

To Inter.

Clar.

Anoxic Anaerobic

Anoxic

Anoxic

CS No. 9 RAS SplitterCS No. 10 Trickling

Filter Effluent Splitter

CS No. 8

PE Splitter

MLR

MLR

MLR

MLR

Aerobic

Page 33: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Anaerobic, Anoxic and Aerobic zones

• 194’ length x 46’ width x 22’ tall concrete

tank

Fine Bubble Diffusers

• 9” Membrane Discs

Submersible Mixers (3 per train) – 10 HP

Mixed Liquor Recycle Pumps (2 per train)

• Anoxic to Anaerobic – 2,000 GPM, 10 HP

• Aerobic to Anoxic – 4,900 GPM, 40 HP

Design – BNR Basin

Page 34: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Design – BNR basin

Page 35: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

4 RAS pumps – VTSH type

• 2,500 GPM, 40 HP

2 WAS Pumps – Self

Priming

• 250 GPM, 7.5 HP

2 ILS Pumps – VTSH Type

• 5,600 GPM, 40 HP

Design – Pump/Blower Building

4 High Speed Turbo Blowers

• 2,500 SCFM, 150 HP

• VFD

Stand by Generator

Electrical and Control Room

Page 36: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Design – Pump/Blower Building

Page 37: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Final Clarifier

• 80’ Diameter

• Stainless Steel

Mechanism

Design – Final Clarifier

Page 38: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Design – Site Layout

Lift

Station

Final

Clarifier

Aeration

Basin

Page 39: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Bid in April 2012

Four Bids

Project awarded to Eriksen Construction, Blair, NE

Engineers Estimate - $11.5 million

Design – Bid Results

Eriksen

Construction

John T Jones

Construction

PKG

Contracting

BRB

Contractors

$10,431,000 $10,970,000 $11,096,000 $11,782,000

Page 40: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

05 Construction Phase

Page 41: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Contract Price:

Construction Timeline

June 2012

Eriksen issued

Notice to Proceed

2012 2013 2014

January 15, 2014

Substantial Completion

March 15, 2014

Final Completion

Mid-Late November

Startup activities begin

Contractual Dates

85-90% Complete

Bid:

$10,413,000

Final:

$10,487,000

Change Orders:

0.7%

Page 42: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Aeration Basin

Page 43: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Electrical Room MCC

Page 44: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Pump Room

Page 45: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Pipe Gallery – Dry well area

Page 46: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

West Exterior View

Page 47: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Final Clarifier

Page 48: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

06 Start-Up and Operation

Page 49: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Parallel Flow Process

Will be used at

startup

Allows staff to

become familiar

with AS

Operational cost

savings

Page 50: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Influent Loadings

Page 51: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Effluent Quality

Page 52: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Effluent Quality

Page 53: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Nitrogen Removal Performance

Page 54: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Effluent Phosphorus

Page 55: © 2015 HDR, Inc., all rights reserved. - Iowa State University 2013 2014 January 15, 2014 Substantial Completion March 15, 2014 Final Completion Mid-Late November Startup activities

Questions