Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
1
2015 Snake River Salmon Recovery Board Project Application
Complete Application Checklist Summary:
Through the application process each of the following elements, depending on the project type, will need to be created and submitted at some point before the final application due date.
Local Snake River Salmon Recovery Board Application – this does not need to be submitted in PRISM, but is required and will assist in finalizing a complete application – may elements including the project title, description, property details, etc., can be copied and pasted throughout. The SRSRB Application includes this entire form, the pre-application, draft application, and final application sections.
The relevant Salmon Project Proposal (Appendix C, found in RCO Manual 18), which includes the response to the SRFB Review Panel comments if required.
Three maps: 1. a general vicinity map, 2. a detailed worksite map for planning and restoration projects or a parcel map for acquisitions, and 3. a map showing the project’s Area of Potential Effect with the section, township, and range identified.
A minimum of two site photographs in JPEG file format.
The proposed project design including plans, specifications, and a design report if available (for restoration projects only).
Detailed Cost Estimate.
Landowner Acknowledgement Form (Appendix F, found in RCO Manual 18).
Barrier Evaluation Form (fish passage construction and design projects only).
Correction Analysis Form (fish passage construction projects only).
Intensively Monitored Watershed Certification (when relevant).
Waiver of Retroactivity (for acquisition projects only).
Deliverables from prior phases of the project (when relevant).
Project partnership contribution form (when relevant, Appendix G, found in RCO Manual 18).
Complete required elements of PRISM Online Application: (https://secure.rco.wa.gov/Prism/Sponsor/Account/LogOn).
Please contact the Snake River Salmon Recovery Board Lead Entity office for questions or assistance with the application and application process at 509-382-4115 or [email protected].
https://secure.rco.wa.gov/Prism/Sponsor/Account/LogOn
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
2
Pre-Application Section (This section must also must be included as part of the Draft and Final Applications if you don’t submit a pre-application).
Project Title (less than 50 characters including spaces, please create a title that accurately reflects the project): Penawawa Creek: Instream Habitat Rehabilitation
Submitting Organization: Whitman Conservation District in partnership with Eco Logical Research, Inc.
Project Contact Information (Complete for each project contact)
Mr. Ms. First Name: Nancy Last Name: Hoobler
Address: 601 N. Main, Suite A City/Town: Colfax State: WA Zip: 99111
Telephone # (509) 288-4644 Cell # ( ) -
E-mail address: [email protected]
Project Location: Provide a brief description of the project location including watershed, stream
reach, position in watershed and if the project is within an major or minor spawning area (MSA or mSA)
and within a designated restoration or protection reach (according to the Funding Habitat Restoration
Projects for Salmon Recovery in the Snake River Region Booklet and Snake River Salmon Recovery
Plan (2011)).
Penawawa Creek is a mainstem tributary to the Snake River in southeast Washington and drains 122
km2 (47 mi2) of the Palouse Hills level 4 ecoregion (Omernik and Griffith, 2014). The project will be
located within the lower 1.5 km (1 mi) of the mainstem of Penawawa Creek. The lower 1.5 km (1 mi) is
within United States Army Corps of Engineers (USACE) land. All of the land upstream from the
confluence with the Snake River is privately owned, and will not be addressed in this proposal.
Maps: Provide both a map illustrating project vicinity and a site map. Map descriptions can be placed
in this section but maps should be attached as a separate page. (Contact SRSRB staff for assistance
if needed). Figures are located at the end of this document.
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
3
Figure 1. Proposed location of stream channel rehabilitation on the lower 1.5 km of Penawawa Creek
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
4
(green line). Post assisted log structures (PALS) will be implemented in the channel on United States
Army Corps of Engineer property.
Figure 2. Area of Potential Effect for the proposed stream rehabilitation on Penawawa Creek
represented by the green outline surrounding the channel. The influence of the proposed structures is
not expected to go beyond 20 meters on either side of the stream channel.
Figure 3. Overhead view of the proposed project area on Penawawa Creek within United States Army
Corps of Engineers property. The riparian zone in this section is in recovery, but instream habitat
complexity is low. Post Assisted Log Structures in this section will promote geomorphic and hydraulic
change to the channel that is beneficial to juvenile and adult steelhead.
Figure 4. A beaver dam upstream of the proposed project area on Penawawa Creek. At the time this
photo was taken, steelhead were witnessed spawning downstream of this beaver dam. Beaver Dam
Analogues mimic natural beaver dams to produce the same ecologic benefits as real ones.
Figure 5. The conceptual design and hypothesized effects of a bank attached Post Assisted Log
Structure. The structure increases hydraulic roughness and complexity which leads to predictable
geomorphic change in the channel during high flows.
Project Description
Must be less than 1,500 characters including spaces.
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
5
Important Note:
Many audiences, including the Salmon Recovery Funding Board (SRFB), SRFB’s Technical Review
Panel, media, legislators, and the public who may inquire about your project, use this description.
Provide as clear, succinct, and descriptive an overview of your project as possible – many will read
these 1-2 paragraphs! This project description will be used in your online PRISM application and
can be used in the Salmon Project Proposal, please take your time to craft a well written project
description.
Your description needs to include the following:
Who is sponsoring the project
Type of project (acquisition, restoration, development, design)
Location information
Overall specific goal to be achieved and why it is important to do at this time
Primary type of habitat to be protected or restored and to what extent the project will protect,
restore, and/or address salmon habitat
Priority species supported
Primary outdoor recreation opportunity to be provided if relevant
What will be acquired, restored, developed, and/or designed with grant funds
Example of a Project Description:
The Jones Nonprofit will use this grant to acquire approximately 20 acres to protect salmonid habitat. Five of
these acres will be restored. The property is located in B County, adjacent to Liquid Creek, east of Highway
1101. The acquisition will help conserve the ecological integrity and biological diversity of the Liquid Creek
watershed by protecting parcels containing critical riparian habitats and linking these parcels to existing public
lands. The primary habitat that will be protected is riparian and in‐stream habitat. Approximately 20 acres will
be acquired, 10 acres of riparian and wetland habitat and 10 acres of adjacent upland. Five of the riparian
acres will be restored by planting native vegetation. The primary species supported by these habitats are
Endangered Species Act listed anadromous fish including coho, summer and fall Chinook, chum, and
steelhead.
This acquisition has been identified as a high priority for B County, and the protection of functioning habitat is
the highest priority in the Northwestern chapter of the Salmon Recovery Plan. The Jones Non‐ Profit group has
worked closely with B County, the local school district and the Friends of Liquid Creek to secure funding and
other support for this project. The University of Fun Education has agreed to conduct the baseline study and
develop a restoration plan. This project builds upon the Land Trust’s adjacent land holdings and the Liquid
Creek Preserve which has already conserved 45 acres and 3,700 feet of Liquid Creek
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
6
The PRISM database limits project descriptions to 1500 characters (including spaces); any
excess text will be deleted. Additional detail should be provided in the project proposal!
Your Project Description: The Whitman County Conservation District (WCD) in cooperation with Eco Logical Research, Inc. (ELR) will use this grant to install up to 50 Post Assisted Log Structures (PALS; e.g. Wheaton et al., 2012) on Penawawa Creek from the mouth to approximately 1.5 km (1 mi) upstream on USACE property. The limiting factors on Penawawa Creek were identified as excessive fine sediment, low stream flow, and poor habitat complexity related to a lack of large woody debris and poor riparian function (SRSB, 2013). The primary benefits to adding high densities of large woody debris using PALS are to (1) increase instream habitat complexity through the development of pools, bars, and structural refugia for juvenile salmonids, (2) temporarily store fine sediment around the installed structures, and (3) and back up water behind structures to encourage hyporheic exchange and provide localized floodplain access. Therefore, this project addresses the goals of SRSB Priority Protection reaches by addressing factors related to riparian function, instream flow, and water quality parameters. The project will primarily benefit ESA listed Snake River steelhead and is located in a designated priority protection reach in a minor spawning area as identified in the Salmon Recovery Plan for SE Washington and regional the three year work plan.
Pre-Application Cost Estimate: Note: Please only use this section for the Pre-Application – the Cost Estimate for the Draft and Final Applications must be more detailed and in a separate document or spreadsheet – please contact LE Staff for examples. List SRFB request, match, and total project costs.
Budget Items Cost/Unit Unit Matching
Funds SRFB
Request Total Project
Cost
Whitman Conservation District Admin 5,000 1 - 5,000 5,000
Watershed Assessment 2,000 1 - 2,000 2,000
Develop Restoration Plan 1,000 1 - 1,000 1,000
Project Management and Site Visits 3,000 1 1,000 2,000 3,000
Posts for construction of 60 structures 6,000 1 - 6,000 6,000
Large Woody Debris 7,000 1 7,000 - 7,000
Post Driver Rental 2,500 1 2,500 - 2,500
Construction labor 8,000 1 - 8,000 8,000
Implementation Monitoring 1,000 1 - 1,000 1,000
Acquisition of Permits 3,000 1 - 3,000 3,000
Cultural Resource Survey 3,000 1 - 3,000 3,000
Final Report 2,000 1 - 2,000 2,000
Total Matching $10,500
Total SRFB Request $33,000
Total Project Cost $43,500
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
7
Restoration Project Preliminary Design Requirements Starting in 2013, the SRFB changed the requirement for design review of restoration projects which exceed $250,000 in SRFB requested funds. If your grant request from the SRFB will exceed $250,000 you will be required to submit a preliminary design or equivalent with the final application. Check the SRFB Manual18 (Appendix D) for information of the Design Requirements or contact LE Staff. Please check the appropriate box below as to whether the design requirement can be met.
I have preliminary designs completed and have cross walked them w/ SRFB requirements
I am currently working on preliminary design and may be able to complete by final application deadline
I do not have preliminary designs and will not have them by the final application
Evidence that this project is part of the Snake River Salmon Recovery Plan: List the HWS project number and the title of the project as stated in the Snake river Salmon Recovery Region Provisional Work Plan 2013-2018. If project is not directly stated in the Work Plan, list the general project category your project pertains to and describe the correlation.
Work Plan Number(s): 35-00406 – Increase Habitat Complexity: Installation of high densities of large woody debris mimic natural processes that lead to the development of pools, structural refuge for juvenile salmonids, and sorted gravel bars for adult salmonid spawning areas. 35-00407 – Restore Floodplain Connectivity and Function: PALS and BDAs create constriction points in the channel that force water onto the floodplain during high flows.
35-00408 – Channel Length and Sinuosity: PALS increase thalweg sinuosity by disrupting uniform flow regimes in homogenous channels. Following high flow events, PALS also promote lateral stream movement and the development of bars which increase sinuosity of the channel at the reach level.
This is the end of the PRE-APPLICATION
When submitting your draft application, make sure to update the pre-application information where required as well as completing the following draft application. The pre-application will become part of the draft application to reduce redundant forms.
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
8
Draft Application Section (This section is in addition to the pre-application, please update sections above in the Pre-Application section where necessary).
Salmon Recovery Funding Board
Draft Application Information
Draft Date Submitted to SRSRB 4/29/2015
Vicinity / Site Maps & Photos Please submit photos as JPEG or other non PDF picture format. Maps and designs maybe submitted in photo or PDF format. If maps and photos were submitted with the pre-application, re-submit only if they have been updated.
Attached Vicinity Map
Detailed Worksite Map (planning and restoration projects) or parcel map (acquisition projects)
Map showing the project’s Area of Potential Effect (APE) with Section/Township/Range A minimum of two (2) Aerial or Site Specific Photos Attached Designs (conceptual, preliminary, or final) or Field Sketches
Salmon Project Proposal To complete this section download the Salmon Project Proposal template that fits your proposed project and attach as a separate document. Check appropriate box below. NOTE: This project proposal will be used primarily to evaluate your project and is the meat of the application. Please include appropriate metrics within the body of the text. The Salmon Project Proposal template documents listed below can be found at: http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ or in Appendix C of SRFB Manual 18.
Attached 1) Restoration, Acquisition, and Combination (Restoration & Acquisition) Project
2) Planning Projects (Assessment, Design, and Study) and Combination (Planning & Acquisition) Projects
3) Barrier Inventory Projects
Projects that address Imminent Threats – Population Effect Determination When the Lead Entity Committee reviews and evaluates project proposals, addressing an Imminent Threat to salmon and/or steelhead is taken into consideration Following the submission of the draft application, if your project addresses an Imminent Threat as identified in the Funding Habitat Restoration Projects for Salmon Recovery in the Snake River Region Application Booklet, the Snake River Salmon Recovery Board Regional Technical Team (RTT) will be consulted on the severity of Imminent Threats being proposed for restoration funding. The RTT will consider population level effects the project may have if the project is implement and provide a technical recommendation to the LE Committee either (I) large improvement on a population scale or (i) minimum impact on a population scale for project scoring and evaluation.
RTT Technical Opinion (Filled in by LE Staff)
Population Scale (I) OR Local Scale (i)
http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
9
Landowner Acknowledgment Forms To complete this section, download the landowner acknowledgment form (different from the landowner agreement form), have the landowner complete and sign the form, and submit a copy with the draft application. Draft applications without signed agreement forms may not be considered by the SRSRB for final scoring and ranking. Remember to complete a Landowner Acknowledgement form for each separate Landowner.
These forms can be found on the SRSRB web site at: http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ or in SRFB Manual 18.
Number of Landowners and Attached Landowner Forms Number: 1
Project Proposal Cost Estimate Please provide a detailed cost estimate to supplement the general cost information required by PRISM (it is easiest to align the cost estimate you create with the cost fields from PRISM). Applicants may use their own formats, but, in general, restoration and design project cost estimates should separate costs for individual construction, design, and project administration elements and tasks (e.g., survey, design, permits, cultural resources, materials, labor, and equipment). Acquisition projects should include costs for land, incidentals (including, as appropriate, appraisals, review appraisals, hazardous substance assessment, title reports and insurance, baseline documentation for conservation easements, closing, recording fees, wetland delineation, fencing, signing, taxes), boundary survey, cultural resources review, demolition, noxious weed control, relocation, stewardship plan, and project administration. Contingency costs should NOT be included as a separate line item in the attached cost estimate. For more information and eligible costs, see RCO Manual 18. For this section, you may use an existing example cost estimate which can be found on the SRSRB website at: http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ OR you may submit a detailed budget in your own format. Please check the appropriate project budget type below that you have completed.
Attached
Detailed Cost Estimate
Barrier Evaluation Form (Fish Passage construction and design projects only) This form is used to document fish passage barrier conditions. This form can be found on the SRSRB web site at: http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ or in SRFB Manual 18.
Attached
Barrier Evaluation From
http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
10
This is the END of the DRAFT APPLICATION.
Don’t forget to update the pre-project information to reflect
changes, if didn’t submit in the pre-application round fill out the pre-application information on your draft submittal.
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
11
Final Application Section (This section is in addition to the pre-application and draft application sections, please update sections above where necessary).
SRFB Final Application
In completing your final application make sure to update changes in your project on the sections listed under Pre-Application and Draft Application in track changes to aid in final review and comment of your project. It is also important to update previous sections to reduce replication in the final application.
Final Date Submitted to SRSRB
Non-profit Organizations must answer the following questions
Is your organization registered as a non-profit with the Washington Secretary of State? If so, what is your Unified Business Identifier (UBI) number?
No Yes, UBI #:
What date was your organization created?
How long has your organization been involved in salmon and habitat conservation?
Application Questionnaire All applicants must answer the following questions.
Property Details Enter a brief description (250 characters or less) of the Property and the work that you will complete there.
For acquisition projects please provide some basic information about the Property (acreage, acquisition type, site characteristics, etc…).
Driving Directions (provide directions that will enable staff to locate the project):
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
12
For any grants listed in the Summary of Funding Request and Match Contribution Section, are there any restrictions on the use of these grant funds (double click on box to select it)? No Yes
When and how long will the grant funds be available to this project?
Describe the type of donated labor (skilled and unskilled), donated equipment, and donated materials that will be used for this project, identified in the Summary of Funding Request and Match Contribution Section.
What is the current land use of the site, and its history? Describe past human uses and salmon habitat functions. Are there any structures on site?
Planning Questions These questions are specifically related to Cultural Resources. These questions must be answered, even if they are redundant or repetitive – i.e., please do not reference other sections of your application or state that they have previously been addressed. The response to these questions will be reviewed independently of the rest of your application.
Has the worksite been investigated for historical, archeological, or cultural resources? If yes, when did this occur and what agencies and tribes were consulted? Make sure to attach related documents (letters, surveys, agreements, etc.) to your project in PRISM.
What is the current land use of the site? Has there been ground disturbances historically, if so, what are/were those disturbances? Is there any fill where ground disturbance is proposed? If known, how deep is the fill?
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
13
Is the worksite(s) located within an existing park, wildlife refuge, natural area preserve, or other recreation or habitat site? If yes, name the area and specify if the land is owned by local, state or federal government.
Correction Analysis Form (Fish Passage construction projects only) This form is used to document how a fish passage barrier will be corrected. This form can be found on the SRSRB web site at: http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ or in SRFB Manual 18.
Attached
Correction Analysis From
Intensively Monitored Watershed Certification (when relevant) If the proposed project is in or near an intensively monitored watershed, attach a letter from the regional organization (Snake River Salmon Recovery Board) certifying that the proposed project contributes to and will not negatively affect ongoing data collection and salmon restoration efforts.
Attached
Intensively Monitored Watershed Certification
Waiver of Retroactivity (for acquisition projects) Required if a land acquisition will occur before project agreement. Waivers of Retroactivity are discussed in detail in SRFB Manual 18. Note that they must be secured before closing on the property
Attached
Waiver of Retroactivity
Deliverables from Prior Phases of the Project If you have received a planning or design grant from SRFB for your proposed restoration project, then you must submit completed design deliverables, at a minimum preliminary designs, from that grant as part of your final application.
Attached
Deliverables from Prior Phases
http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
14
Project Partnership Contribution Form State agencies are required to have a local partner and must attach a signed Partner Contribution Form. A Partner Contribution Form also is recommended, but not required, for other eligible applicants where a third party is providing a funding match. This form can be found on the SRSRB web site at: http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ or in SRFB Manual 18.
Attached
Project Partnership Contribution Form
Complete required elements of PRISM Online Application
Many of the questions and information that needs to be completed for the PRISM Online Application can be taken directly from this SRSRB application (and is designed to do so). Work with SRSRB Staff to complete. PRISM Online can be accessed here: https://secure.rco.wa.gov/Prism/Sponsor/Account/LogOn
Work with SRSRB Staff to complete the PRISM Online Application
http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/https://secure.rco.wa.gov/Prism/Sponsor/Account/LogOn
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
15
Permits
Please check the appropriate boxes to indicate required and/or anticipated permits. General permit information can be obtained at the Governor’s Office for Regulatory Innovation and Assistance by calling 1-800-917-0043 or on the web at: http://www.oria.wa.gov/site/alias__oria/347/default.aspx.
Permits Comments Regarding Permit Status
Aquatic Lands Use Authorization (Dept of Natural Resources)
Building Permit (City/County)
Clear & Grade Permit (City/County)
Cultural Assessment [Section 106] (CTED-OAHP)
Dredge/Fill Permit [Section 10/404 or 404] (US Army Corps of Engineers)
Endangered Species Act Compliance [ESA] (US Fish & Wildlife/NMFS*)
*(The SRFB has a permit programmatic with NMFS such that for a SRFB Funded project you just need a Self-Certification 4(d) Rule, Limit 8 Form signed and attached. Find the form at http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ or in SRFB Manual 18.
Forest Practices Application [Forest & Fish] (Dept of Natural Resources)
Health Permit (Dept of Health/County)
Hydraulics Project Approval [HPA] (Dept of Fish & Wildlife)
NEPA (Federal Agencies)
SEPA (Local or State Agencies)
Shoreline Permit (City/County)
Water Quality Certification [Section 401] (County/Dept of Ecology)
Water Rights/Well Drilling Permit (Dept of Ecology)
Other Required Permits (identify)
None – No permits Required
http://www.oria.wa.gov/site/alias__oria/347/default.aspxhttp://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
16
This is the END of the FINAL APPLICATION.
Don’t forget to update the pre-project information to reflect changes, if didn’t submit in the pre-application round fill out the
pre-application information on your draft submittal. Please contact the Snake River Salmon Recovery Board Lead Entity office for questions or assistance with the application and application process at
509-382-4115 or [email protected].
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
17
Figure 1. Proposed location of stream channel rehabilitation on the lower 1.5 km of Penawawa Creek (green line). Post assisted log structures (PALS) will be implemented in the channel on United States Army Corps of Engineer property.
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
18
Figure 2. Area of Potential Effect for the proposed stream rehabilitation on Penawawa Creek
represented by the green outline surrounding the channel. The influence of the proposed structures is
not expected to go beyond 20 meters on either side of the stream channel.
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
19
Figure 3. Overhead view of the proposed project area on Penawawa Creek within United States
Army Corps of Engineers property. The riparian zone in this section is in recovery, but instream
habitat complexity is low. Post Assisted Log Structures in this section will promote geomorphic and
hydraulic change to the channel that is beneficial to juvenile and adult steelhead.
Figure 4. A beaver dam upstream of the proposed project area on Penawawa Creek. At the time this
photo was taken, steelhead were witnessed spawning downstream of this beaver dam. Beaver Dam
Analogues mimic natural beaver dams to produce the same ecologic benefits as real ones.
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
20
Figure 5. The conceptual design and hypothesized effects of a bank attached Post Assisted Log
Structure. The structure increases hydraulic roughness and complexity which leads to predictable
geomorphic change in the channel during high flows.
Pre-Application Due Date: April 2, 2015
Draft Application Due Date: April 29, 2015
Final Application Due Date: July 17, 2015
21
Literature Cited Omernik, J.M., Griffith, G.E., 2014. Ecoregions of the Conterminous United States: Evolution of a
Hierarchical Spatial Framework. Environ. Manage. 54, 1249–1266. doi:10.1007/s00267-014-
0364-1
SRSB, 2013. Snake River Salmon Recovery Region Provisional Work Plan 2013-2018. Snake River
Salmon Recovery Board, Dayton, WA.
Wheaton, J., Bennett, S., Bouwes, N., Camp, R., 2012. Asotin Creek Intensively Monitored Watershed:
Restoration Plan for Charley Creek, North Fork Asotin, & South Fork Asotin Creeks. (Restoration
Design). Snake River Salmon Recovery Board, Dayton, WA.
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 1
Restoration, Acquisition, and Combination Project Proposal
List all related projects previously funded or reviewed by RCO:
Project # or Name Status
Status of Prior Phase Deliverables and Relationship
to Current Proposal?
Asotin Creek IMW In progress Restoration phases are complete – effectiveness
monitoring will continue until 2019.
Pataha Creek:
Working with
Beaver to Restore
Salmon and
Steelhead Habitat
In progress Trial restoration to be completed in the summer of
2015.
If previous project was not funded, describe how the current proposal differs from the original.
1. Project Location.
Penawawa Creek is a mainstem tributary to the Snake River in southeast Washington and drains
122 km2 (47 mi2)of the Palouse Hills level 4 ecoregion (Omernik and Griffith, 2014). The project
will be located within the lower 1.5 km (1 mi) of the mainstem of Penawawa Creek. The lower 1.5
km (1 mi) is within United States Army Corps of Engineers (USACE) land. All of the land upstream
from the confluence with the Snake River is privately owned, and will not be addressed in this
proposal.
2. Brief Project Summary.
The Whitman County Conservation District (WCD) in cooperation with Eco Logical Research, Inc.
(ELR) will use this grant to install up to 50 Post Assisted Log Structures (PALS; e.g. Wheaton et
al., 2012) on Penawawa Creek from the mouth to approximately 1.5 km (1 mi) upstream on
USACE property. The limiting factors on Penawawa Creek were identified as excessive fine
sediment, low stream flow, and poor habitat complexity related to a lack of large woody debris
and poor riparian function (SRSB, 2013). The primary benefits to adding high densities of large
woody debris using PALS are to (1) increase instream habitat complexity through the
development of pools, bars, and structural refugia for juvenile salmonids, (2) temporarily store
fine sediment around the installed structures, and (3) and back up water behind structures to
encourage hyporheic exchange and provide localized floodplain access.
3. Problems Statement.
Project Number
Project Name Penawawa Creek: Instream Habitat Rehabilitation
Sponsor Whitman Conservation District
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 2
A. Describe the problem including the source and scale.
Penawawa Creek is listed on the Washington State Department of Ecology’s 303(d) list for
excessive water temperatures (WADOE, 2013). There is little available information for other
habitat parameters on Penawawa Creek, however, brief reports conducted by the Washington
Department of Fish and Wildlife (WDFW), indicate other potential problems in the watershed.
There may be excessive fine sediment in the channel from adjacent hillslopes, vegetation in the
riparian zone is sporadic, and there is an overall lack of shade in the channel from riparian
vegetation (Mendel et al., 2004). However, portions of the riparian appear to be in recovery, and
the riparian buffer generally widens moving downstream. Excessive fine sediment clogs
interstitial spaces between spawning gravels, reducing the number of suitable spawning
locations for adults salmonids. Additionally, the lack of shade on Penawawa Creek, likely
contributes to high water temperatures which have exceeded the lethal limit for salmonids.
Likewise, summer discharges on Penawawa Creek were very low (
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 3
Excessive fine sediment (egg life stage): fine sediments clog the interstitial spaces between the
gravels that adult salmonids target for spawning. Sufficient water flow through redds is required
to deliver oxygen to developing salmonid eggs and alevin.
Excessive water temperatures (all life stages): Steelhead are a cold water species, and require low
water temperatures to reach a metabolic optimum. The upper thermal limit (>25° C; Myrick and
Jr, 2005) is surpassed during the summer months on Penawawa Creek.
4. Project Goals and Objectives.
A. What are your project’s goals?
The goal of this project is to increase habitat diversity, reduce uniform fine sediment deposition,
improve riparian function, reconnect floodplain processes, and improve accessible habitat for
steelhead on Penawawa Creek. This project will focus primarily on the natural mitigation effects
of LWD to riparian and fluvial processes.
B. What are your project’s objectives?
The specific objectives of this project are to:
1. Assess the current habitat conditions in the treatment area by estimating the density of
pools, bars, and LWD, and mean embeddedness.
2. Add up to 50 Post Assisted Log Structures (PALS) comprised of 200 qualifying LWD
pieces (>10 cm diameter, >1 m long) to the active channel by 2017.
3. Increase pool density to 5 pools/100 m within 5 years of funding.
4. Decrease mean embeddedness in the active channel by 1 ranking on the Platts et al.
(1983) method within 5 years of funding.
5. Test viable methods for removing water hemlock within a small portion of the project
area.
C. What are the assumptions and constraints that could impact whether you
achieve your objectives?
The geomorphic effectiveness of PALS are dependent on peak discharge. However, the
immediate hydraulic effects of PALS are still beneficial for steelhead in all life stages. We have
received support from the USACE for this project on the lower 1.5 km (1 mi) of Penawawa Creek.
We would like this project to act as a demonstration site for potential future projects in the
Whitman Conservation District.
5. Project Details.
A. Provide a narrative description of your proposed project.
Prior to performing restoration, we will perform a habitat assessment survey of the project area
to calculate pool, bar, and LWD density. In addition, we will quantify mean embeddedness by
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 4
geomorphic unit, using the Platts et al. (1983) ranking method. We will also perform of a
desktop assessment of watershed controls including climate, geology, and hydrology that might
affect the project design. We will use this data to identify priority locations for individual PALS
when developing the restoration design. In addition, this data will act as a baseline for assessing
our success at reaching the project objectives. In the year following implementation, we will
repeat the survey to monitor changes to those habitat attributes.
We propose to use a method of restoration extensively tested on the Asotin Creek Intensively
Monitored Watershed project (IMW; Wheaton et al., 2012), using Post Assisted Log Structures
(PALS) to increase habitat diversity and reconnect floodplain processes. Penawawa Creek is
similar in many was to the study streams with the IMW, as have wild steelhead populations and
both are affected by poor riparian function. Our approach will be to drive wooden fence posts
into the stream bed spanning 80-90% of the active channel. The posts will support 3-5 pieces of
LWD, keeping the LWD in place for 5-10 years while the riparian zone continues to recover. Each
post is installed 40-70 cm (1-3 feet) into the channel bed, and extend slightly above the active
flood height. Because the structures are not fully channel spanning, steelhead migration will not
be impeded. The initial effects of altering the uniform flow regime in Penawawa Creek will
provide more suitable habitat for steelhead by creating multiple feeding lanes and slow-water
resting areas. Additionally, the specific design of each PALS will lead to predictable geomorphic
effects following high flows. These geomorphic effects include the development of pools and
bars, increased floodplain sediment deposits, and better sediment sorting. The influence of PALS
on sediment sorting leads to distinct, similarly sized grain patches within the channel; therefore
fine sediment is collected within eddys, rather than uniformly distributed throughout the active
channel.
Water hemlock is an invasive plant that is poisonous when ingested by humans and livestock
and is currently found within the proposed project area. Although difficult to control, water
hemlock is easiest to remove in early spring when the soil in which it grows is soft, allowing the
full removal of the plant’s roots. We propose to explore methods for reducing the threat of
water hemlock through manual removal. Prior to structure implementation in 2016, we will
remove water hemlock plants and roots within the top 100 m (~325 feet) of the project area to
determine the feasibility of this method.
B. Provide a scope of work.
Deliverable Description Completion Date Completed by
Project management Project area
assessment,
restoration planning,
construction,
implementation,
project reporting
December 31, 2017 ELR
Permitting Complete and apply July 15, 2016 ELR
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 5
for all necessary
permits
Develop restoration
plan
Based on the project
area assessment,
develop a plan for
constructing PALS
July 15, 2016 ELR
Install up to 50 PALS PALS will be
constructed using
wooden fence posts
and LWD, based on
the restoration plan
August 30, 2016 ELR
Implementation
monitoring
Describe each as-
built structure using
the HDLWD
Effectiveness App
September 30, 2016 ELR
Water hemlock
removal trial
Manually remove
water hemlock within
the top 100 m of the
project area
June 1st, 2016 ELR
C. Explain how you determined your cost estimates.
Detailed budget is attached.
The proposed costs are largely based off of ELR’s previous projects that are similar in size and
scope. Labor costs are based on competitive prevailing wage rates. Materials costs are based on
estimate matches from participating agencies, and quotes from the material providers.
D. Describe the design or acquisition alternatives that you considered to
achieve your project’s objectives.
We considered two other alternatives. 1) Do nothing. This option assumes that the current
condition of the project area is not degraded, or is exhibiting a rate of recovery that could not
be enhanced through intervention. Based on the history of the Palouse Hills ecoregion, land use
practices, and the best available data, we believe that Penawawa Creek is degraded compared to
its historic condition. 2) Riparian planting. This option would address one of our project
objectives (improve riparian function) over the long term; however, it does not provide short
term improvement to instream habitat that would be beneficial for steelhead. Therefore, we
settled on our preferred option, to implement PALS, because their hydraulic and geomorphic
benefits have been well documented within the Asotin IMW project (Camp, 2015), as well as
others in southeast Washington. Likewise, the long term benefits of reconnecting floodplain
processes through the use of PALS will likely improve riparian function.
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 6
E. How have lessons learned from completed projects or monitoring studies
informed your project?
ELR has been developing many low-cost restoration alternatives throughout the Northwest
United States. In particular, they have completed three years of PALS implementation on three
different streams in the Asotin Creek watershed. Within an adaptive management framework,
ELR improved structure designs and placement with each subsequent year. The effects and
potential uses for PALS are well documented in Camp (2015). This project with benefit further
from monitoring the effects of PALS on Penawawa Creek, including changes to instream habitat,
riparian structure, temperature, and discharge.
F. Describe the long-term stewardship and maintenance obligations for the
project or acquired land.
There are no expected maintenance responsibilities for any landowners involved in the project.
The grantee will maintain or repair the PALS, when necessary, throughout the life of the project.
However, PALS are designed to be dynamic and work in concert with each other and, therefore,
no maintenance is required. All of the materials used are biodegradable.
6. Context within the Local Recovery Plan.
A. Discuss how this project fits within your regional recovery plan and/or local
lead entity’s strategy to restore or protect salmonid habitat
This project addresses ESA listed steelhead habitat in a priority protection reach. The general
project categories for a priority protection reach in the 2013-2018 Snake River Salmon Recovery
Region Provisional Work Plan include: protecting floodplain and riparian function, reducing fine
sediments, and maintaining instream flow. PALS reconnect instream process with riparian and
floodplain processes by mimicking trees that have fallen into the channel. The riparian zone in
the project area appears to be in recovery, but because of the homogenous age structure of the
trees, there is little to no LWD recruitment to the channel. Structural elements in streams, such
as LWD, increase hydraulic roughness which leads to sorted patches of sediment grains.
Similarly, fine sediment is stored upstream of PALS, and within the eddys they create; therefore,
concentrating the amount of fines deposited to predictable locations, rather than uniformly
throughout the channel. Some PALS significantly backup water upstream, thereby increasing
water depth and helping to maintain instream flow. Additionally, the hydraulic and geomorphic
effects of PALS increase habitat complexity, presumably creating more suitable habitat for ESA
listed steelhead.
B. Explain why it is important to do this project now instead of later.
Penawawa Creek was not immune to the last 100+ years of land use practices in the Palouse
Hills ecoregion. While some of the upland management practices have improved, the stream is
still degraded and may not recover by itself, or may take many decades to do so without
assistance. There do not appear to be any imminent threats on Penawawa Creek. Instream
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 7
actions appear to be the next necessary step to rehabilitate Penawawa Creek by promoting the
natural processes that lead to improved fish habitat. At the time this proposal was written, a
total of 236 steelhead (188 wild, 55 hatchery) were collected at an adult weir near the mouth of
Penawawa Creek (J. Trump, WDFW, personal communication, April 24, 2015). In contrast, 33
steelhead (27 wild, 6 hatchery) were captured in 2014 (Trump and Gembala, 2015), and 71
steelhead (24 wild, 47 hatchery) were captured in 2013 (Trump et al., 2014). This current year
may be anomaly; however, considering the limited years of data, there is still much more to be
learned about steelhead use in Penawawa Creek. Additionally, the current numbers suggest that
Penawawa Creek may be an important component of the Middle and Lower Snake River
steelhead metapopulation.
C. If your project is a part of a larger overall project or strategy, describe the
goal of the overall strategy, explain individual sequencing steps, and which
of these steps is included in this application for funding.
NA
7. Project Proponents and Partners.
A. Describe your experience managing this type of project.
The Whitman Conservation District has effectively coordinated landowner operations to
establish best management practices to their region. Additionally, landowners within the district
develop, test, and implement their own strategies for improving land management practices.
The district also holds regular meetings to discuss projects and management goals with
stakeholders and producers in the region. A team of board members for the WCD coordinate
with other agencies to address resource problems and prioritize solutions for addressing local
land use issues.
Eco Logical Research Inc. with assistance from Utah State University will be providing technical
support and some project management and implementation duties as required. The primary
people involved are Dr. Nick Bouwes, Dr. Joe Wheaton, and Dr. Stephen Bennett. The project
team has managed dozens of restoration and monitoring projects related to stream habitat
restoration and fisheries research. Dr. Bouwes and Dr. Bennett are currently managing two IMWs
where restoration activities have already been implemented that are similar to those proposed
in this application. Specifically, in Bridge Creek, a tributary to the John Day River, Dr. Bouwes was
part of a team that developed a method to drive posts into the stream bottom to create starter
dams for beaver as part of the Bridge Creek IMW. Additionally, Dr. Bennett is currently
managing the Asotin Creek IMW, which used PALS as the primary restoration method. As
manager and president of Eco Logical Research Inc. Dr. Bouwes has managed numerous projects
for Bonneville Power Administration and National Oceanic and Atmospheric Administration
including the development and implementation of the Columbia Basin Habitat Monitoring
Protocol and the John Day portion of ISEMP. Dr. Bennett has been an environmental consultant
since 1990 and has managed several large restoration and habitat assessment projects for
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 8
salmon and inland trout. Dr. Wheaton is the Director of Ecogeomorphology & Topographic
Analysis Lab at Utah State and the Co‐Director of Intermountain Center for River Rehabilitation
& Restoration and as such manages numerous large scale river restoration, assessment, and
monitoring projects.
B. List all landowner names.
United States Army Corps of Engineers
C. List project partners and their role and contribution to the project.
Whitman Conservation District will cover project administration tasks.
Eco Logical Research, Inc. will implement, manage, and report on the restoration actions.
D. Stakeholder Outreach.
We are currently contacting local landowners for project support and outreach; however, the
proposed actions would not occur on private land. Within the WCD, there are many citizen
stakeholders that are supportive of best management practices. We will meet with landowners
and the WCD board to discuss the project in detail. We will implement this project in a manner
that is satisfactory to all of the involved stakeholders. Ideally, this project would serve as a
demonstration to encourage landowner participation in future projects.
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 9
Supplemental Questions
Restoration Project Supplemental Questions
Answer the following supplemental questions:
A. Will you complete, or have you already completed, a preliminary design, final
design, and design report (per Appendix D) before construction?
Yes
1. If no, please describe your design process and list all pre-construction
deliverables you will submit to RCO for review.
B. Will your project be designed by a licensed professional engineer?
No
1. If not, please describe the qualifications of your design team.
The Whitman Conservation District will team up with Eco Logical Research Inc., (ELR), to
complete the implementation portion of this project. ELR focuses on process-based restoration
approaches. Many of our projects are related to using low cost, minimal disturbance approaches
to adding large woody debris to streams. We also believe in understanding the processes in a
watershed before conducting any restoration. As such, we promote watershed assessments and
developing a clear understanding of the ecological concerns and disrupted processes within a
watershed. An example of the kind of watershed assessment we promote can be seen in (Pollock
et al. 2012, Wheaton 2012, Portugal et al. 2015). We have over a decade of experience managing
restoration projects. The ELR staff that will be working on this project and their qualifications are
listed below.
Dr. Nicolaas Bouwes
Dr. Bouwes has a strong foundation in biometric and data analyses, modeling, experimental and
monitoring design, fisheries research and aquatic ecology and has detailed knowledge of the
salmon, steelhead, and bulltrout issues in the Columbia River Basin. Nick is the owner of Eco
Logical Research, Inc. Nick is also an adjunct professor at the Watershed Sciences Department,
Utah State University, Logan UT. Projects he is currently working on include: Asotin Creek
Intensively Monitored Watershed (IMW) Project in southeast Washington and the Integrated
Status and Effectiveness Monitoring Program to developed standardized status, trend, and
effectiveness monitoring programs for salmon and steelhead in the Columbia River Basin. Nick
has been the lead manager of the Bridge Creek IMW that focuses on using beaver dam analogs
to restore steelhead habitat and also been a lead in developing restoration plans for the Asotin
Creek IMW as well as numerous smaller beaver restoration projects in Oregon and Utah. Nick
was the co-developer of the Columbia Habitat Monitoring Protocol (CHaMP) for the Bonneville
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 10
Power Administration. Nick received a BS in zoology from the University of WI, Madison, and a
MS and PhD in aquatic ecology from Utah State University, Logan UT.
Dr. Stephen N. Bennett
Dr. Bennett has been working for Eco Logical Research, Inc. since 2007 as the project
coordinator of the Asotin Creek Intensively Monitored Watershed Project in southeast
Washington. Stephen’s focus in the last eight years has been on developing and implementing
restoration and monitoring programs in southeast Washington with a focus on building
structures similar to BDAs (called post-assisted log structures). Stephen is familiar with the
permitting and regulatory requirements of working with the Salmon Recovery Funding Board
and works closely with the Snake River Salmon Recovery Board on several projects including
monitoring restoration effectiveness in the Tucannon River. Stephen has also worked to aid in
the development and assessment of regional salmonid monitoring programs. Stephen
completed a PhD in Fisheries Biology in 2007 at the Watershed Sciences Department at Utah
State University, Logan, Utah. Prior to starting his PhD Stephen was a biological consultant for
12 years working on a variety of fisheries issues including fish inventory, fish passage
assessment, watershed analysis, habitat monitoring, impact assessments, and salmonid
enhancement projects. Stephen also has a Masters in Resource and Environmental Management
(M.R.M.) from Simon Fraser University, Canada, and a Wildlife Biology (B.Sc. Honors), University
of Montana.
Dr. Joseph Wheaton
Dr. Wheaton is an Assistant Professor at Utah State University and a fluvial geomorphologist
with over a decade of experience in river restoration, including working with beaver in
restoration. Joe runs the Ecogeomorphology & Topographic Analysis Lab at Utah State
University and is a leader in the monitoring and modeling of riverine habitats and watersheds.
He has worked to develop monitoring protocols for the USFS, NOAA, USGS and National Park
Service and he and his lab have produced software for monitoring applications and simulation
modeling. He is the co-director of the Intermountain Center for River Rehabilitation &
Restoration. He worked four years in consulting engineering before completing his B.S. in
Hydrology (2003, UC Davis), M.S. and Ph.D. in Hydrologic Sciences (2003, UC Davis; 2008, U. of
Southampton, UK). He has worked as a lecturer (U. of Wales 2006-08), Research Assistant
Professor (Idaho State U. 2008-09) and is an Assistant Professor at Utah State U. (2009-present)
where he teaches courses on GIS, Fluvial Hydraulics and Ecohydraulics as well as workshops on
'Restoration Monitoring: Geomorphic Change Detection', 'Partnering with Beaver in Restoration
Design', and 'Geomorphology and Sediment Transport in Channel Design'. Joe works regularly
with Eco Logical Research on projects including: Asotin Creek Intensively Monitored Watershed
Project in southeast Washington, Intercomparing Monitoring Methods in the Lemhi Watershed
of Idaho for the Integrated Status and Effectiveness Monitoring Program, Bridge Creek
Intensively Monitored Watershed restoration project in Central Oregon, developing a Big River
Monitoring Protocol for the National Park Service, working on sediment budgeting in the Grand
Canyon with the USGS Grand Canyon Monitoring & Research Center.
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 11
Reid Camp
Reid has eight years of experience monitoring wild salmonid populations, and conducting
stream restoration effectiveness monitoring in southeast Washington and throughout Idaho. He
began working for ELR in 2009 on the Asotin Creek Intensively Monitored Watershed where he
is currently coordinating field operations on Asotin Creek and other ELR projects in southeast
Washington. Reid has substantial technical experience collecting, organizing, and analyzing
fisheries and stream data, is proficient in many software packages including Access, FileMaker,
ArcGIS, R, and is a certified Microsoft Office User Specialist. He has helped to develop multiple
protocols and mobile device applications for facilitating rapid, low-cost monitoring methods
that are currently being used by public and private entities in WA, ID, UT, and MT. Reid received
a B.S. in Fishery Resources from the University of Idaho in Moscow, ID and a M.S. in Watershed
Science from Utah State University in Logan, UT. Pertinent to this project, Reid’s M.S. thesis
primarily assessed the geomorphic effectiveness of low-cost stream restoration structures (PALS
on the Asotin IMW, specifically), at increasing habitat diversity that is beneficial for steelhead.
C. If this project includes measures to stabilize an eroding streambank, explain why
bank stabilization there is necessary to accomplish habitat recovery.
NA
D. Describe the steps you will take to minimize the introduction and spread of
invasive species during construction and restoration.
We will use locally sourced wood and non-treated fence posts for the construction of each
restoration structure to reduce the potential of introducing new invasive species to the project
area. Our methods are very low impact to the surrounding riparian vegetation, and cause little
disturbance to the stream bed and floodplain. We do not anticipate that our actions will
contribute to the spread of invasive species currently found within the Penawawa watershed.
Although water hemlock is present within the project area, we will test viable options for its
removal.
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 12
Comments
Use this section to respond to the comments you will receive after your initial site visits, and
then again after you submit your final application.
Response to Site Visit Comments
Please describe how you’ve responded to the review panel’s initial site visit comments. We
recommend that you list each of the review panel’s comments and questions and identify how you
have responded. You alsomay use this space to respond directly to their comments.
Response to Post-Application Comments
Please describe how you’ve responded to the review panel’s post-application comments. We
recommend that you list each of the review panel’s comments and questions and identify how you
have responded. You alsomay use this space to respond directly to their comments.
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 13
Literature Cited
Camp, R., 2015. Short Term Effectiveness of High Density Large Woody Debris, a Cheap and
Cheerful Restoration Action, in Asotin Creek (Thesis). Utah State University, Logan, UT.
Fausch, K.D., 1993. Experimental Analysis of Microhabitat Selection by Juvenile Steelhead
(Oncorhynchus mykiss) and Coho Salmon (O. kisutch) in a British Columbia Stream. Can.
J. Fish. Aquat. Sci. 50, 1198–1207. doi:10.1139/f93-136
Mendel, G., Trump, J., Fulton, C., Gembala, M., 2004. Brief Assessment of Salmonids and Stream
Habitat Conditions in Snake River Tributaries of Asotin, Whitman and Garfield Counties
in Washington: March 2001-June 2003. Washington Department of Fish and Wildlife,
Olympia, WA.
Myrick, C.A., Jr, J.J.C., 2005. Effects of Temperature on the Growth, Food Consumption, and
Thermal Tolerance of Age-0 Nimbus-Strain Steelhead. North Am. J. Aquac. 67, 324–330.
doi:10.1577/A04-050.1
Omernik, J.M., Griffith, G.E., 2014. Ecoregions of the Conterminous United States: Evolution of a
Hierarchical Spatial Framework. Environ. Manage. 54, 1249–1266. doi:10.1007/s00267-
014-0364-1
Platts, W.S., Megahan, W.F., Minshall, G.W., 1983. Methods for evaluating stream, riparian, and
biotic conditions.
Roni, P., Quinn, T.P., 2001. Density and size of juvenile salmonids in response to placement of
large woody debris in western Oregon and Washington streams. Can. J. Fish. Aquat. Sci.
58, 282–292. doi:10.1139/f00-246
SRSB, 2013. Snake River Salmon Recovery Region Provisional Work Plan 2013-2018. Snake River
Salmon Recovery Board, Dayton, WA.
Trump, J., Gembala, M., 2015. Estimate Adult Steelhead Abundance in Small Streams Associated
with the Tucannon and Asotin Populations. Washington Department of Fish and Wildlife,
Dayton, WA.
Trump, J., Mendel, G., Gembala, M., 2014. Estimate Adult Steelhead Abundance in Small Streams
Associated with the Tucannon and Asotin Populations. Washington Department of Fish
and Wildlife, Dayton, WA.
WADOE, 2013. 2012 Water Quality Assessment - 305(b) Report. Washington State Department
of Ecology, Olympia, WA.
Wheaton, J., Bennett, S., Bouwes, N., Camp, R., 2012. Asotin Creek Intensively Monitored
Watershed: Restoration Plan for Charley Creek, North Fork Asotin, & South Fork Asotin
Creeks. (Restoration Design). Snake River Salmon Recovery Board, Dayton, WA.
Restoration, Acquisition, or Combination Project Proposal May 1, 2015
Page 14
Zalewski, M., Lapinska, M., Bayley, P., 2003. Fish relationships with wood in large rivers, in: The
Ecology and Management of Wood in World Rivers. American Fisheries Society,
Bethesda, pp. 195–211.
RESTORATION
OVERALL
PROJECT GRANT REQUEST MATCH
Budget must
account for all
costs to
complete the
project
Enter only the
amount of the
grant request
Qty Rate Amount Amount Match in PRISM
Funding not reported
in PRISM
Source (Grant,
Cash, Materials,
Labor, Volunteers,
etc)
Match Type
(federal, state,
local)
Construction
Category (choose one) Task Description
Construction supervision Implementation monitoring 30.00 40.56$ 1,217$ 1,217$ -$ -$
Construction supervision Project management and
site visits
70.00 40.56$ 2,839$ 2,000$ 839$ -$ Labor Local
Materials Non-treated wood posts 400.00 10.00$ 4,000$ 4,000$ -$ -$
Equipment and equipment use Post driver rental 1.00 2,500.00$ 2,500$ -$ 2,500$ -$ Equipment Local
Construction labor Crew of 4 biologists for 7
days to implement
structures
200.00 40.56$ 8,112$ 8,112$ -$ -$
Permits Shoreline, HPA, JARPA 70.00 40.56$ 2,839$ 2,839$ -$ -$
Permits Army Corps of Engineers 1.00 5,000.00$ 5,000$ 5,000$ -$ -$
Cultural resources Cultural resources
consultation
1.00 4,000.00$ 4,000$ 4,000$ -$ -$
Materials Large woody debris pieces 220.00 30.00$ 6,600$ -$ 6,600$ -$ Materials Federal
Materials Large wood debris felling
and delivery
1.00 2,000.00$ 2,000$ 2,000$ -$ -$
Construction labor 1 biologist for 2 days to test
viable options for water
hemlock removal
20.00 40.56$ 811$ 811$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
STotal 39,918$ 29,979$ 9,939$ -$
Administrative, Architechtural &
Engineering
Category Task Description
Final design Develop restoration plan 30.00 40.56$ 1,216.80$ 1,217$ -$ -$
Assessments (geologic, hydraulic, etc.) Watershed assessment 65.00 40.56$ 2,636.40$ 2,636$ -$ -$
Administrative Whitman Conservation
District administration
1.00 5,000.00$ 5,000.00$ 5,000$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
-$ -$ -$ -$ -$
Stotal $ 8,853.20 $ 8,853.20 $ - -$
GTOTAL 48,772$ 38,832$ 9,939$ -$
A&EPRISM Project
Total
$ 48,771
A&E maximum allowed in PRISM $ 11,975.40 RCO Percentage Match Percentage
A&E validation 3,122 0.796211699 0.203788301
The Grant Request and Match should equal the total project cost and Budget
Check cell should be 0. Sponsors must account for all sources and types of match
need to complete the project.
See SRFB Manual 5 for additional information regarding allowable costs.
Lower Columbia Habitat Project Application Detailed Cost Estimate 2/1/2013
Appendix F: Landowner Acknowledgement Form
Manual 18, Salmon Recovery Grants January 2015
Appendix F:
Landowner
Acknowledgement Form
Landowner Information
Name of Landowner: United States of America, U.S. Army Corps of Engineers
Landowner Contact Information:
Mr. Ms. Title: Chief of Real Estate
First Name:Rodney Last Name: Huffman
Contact Mailing Address: 201 North Third Avenue, Walla Walla, WA 99362
Contact E-Mail Address:[email protected]
Property Address or Location: Penawawa Creek, Little Goose Lock and Dam Project
1. The United States of America (Landowner or Organization) is the legal owner of property
described in this grant application.
2. I am aware that the project is being proposed on my property.
3. If the grant is successfully awarded, I will be contacted and asked to engage in negotiations.
4. My signature does not represent authorization of project implementation.
April 24, 2015
Landowner Signature Date
Project Sponsor Information
Project Name:
Project Applicant Contact Information:
Mr. Ms. Title
First Name: Last Name:
Mailing Address:
E-Mail Address:
Appendix G: Project Partner Contribution Form
Manual 18, Salmon Recovery Grants January 2015
Appendix G: Project Partner Contribution Form
Project Partner: Eco Logical Research, Inc.
Partner Address: 456 S 100 W, Logan, UT 84321
Contact Person:
Mr. Ms. Title:
First Name: Reid Last Name: Camp
Mailing Address: 1493 Northwood Dr. #104, Moscow, ID 83843
E-Mail Address: [email protected]
Description of contribution to project:
Eco Logical Research, Inc. will assist with restoraiton implementation, management,
and reporting.
Estimated value to be contributed: $30,000
4/27/2015
X Reid CampReid Camp
Research Biologist, ELR
Signed by: Reid Camp 04/27/2015_
Partner’s signature Date
1 DraftApplication_PenawawaCreek_1504292 Appendix_C_PenawawaProposal_ELR_1504294 SRFB_Cost_Estimate_PenawawaCreek_1504275 Appendix_F_Landowner_Ack_Form_USACE6 Appendix_G_Proj_Partner_Contribution_Form_ELR7 Penawawa_USACE_letter of support