#AirportsTechnical
August 10-11, 2016
2016 ACC Airports Technical Workshop
#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC
EMAS Procurement Case Study
TF Green Airport
Providence, RI
Runway 5 Extension
#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC
Runway 5 Extension
• Runway 5 program
($87 million)
• Extension - $40 million
• Construction Safety and Phasing Plan including Safety Assessment
• ISI Envision Gold Award
• EMAS RSAEMAS
Runway Safety Area
#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC
Runway 5 Extension Timeline
#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC
Runway 5 Extension Timeline
#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC
FAA PGL for EMAS Procurement
• Acknowledges two manufacturers meeting FAA AC
• Required for AIP projects less than 30% design
• Buy American
• 1-Year warranty
• Sole-source requires FAA approval
• Competitive procurement process (RFI/RFP)
• Proposal requirements
• Involves maintenance costs (life-cycle)
#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC
How to select?
Stop at 70 knots
FAA PGL?
Maintenance
Sustainability
FAA ALSF-2
AIP vs. PFC
Buy American
New product?
Project constraints
How to evaluate?
How to contract?
Costs(Const,Life-Cycle)
#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC
Procurement by RIAC
• Designs approved by FAA by both manufacturers
• FAA Region concurrence
• Separate RFP from runway – two alternate bids for furnish and install
• Price proposal – first time cost only
• Successful EMAS assigned to runway general contract
#AirportsTechnical2016 ACC Airports Technical Workshop | August 10-11 | Washington, DC
Results
• Cardi construction (Runway 5 Extension contractor) submitted bid
• Bid both alternates (Zodiac and Runway Safe)
• Zodiac was lower price
• Saved more than $1 million from sole-source
• Construction progress currently on budget and ahead of schedule
• EMAS construction in 2017
#AirportsTechnical
Thank you
Matthew J. Wenham, PE, ENV SP
Manager, Aviation Engineering & Construction
Questions?