2016 Transportation Alternatives Project Requests
01-Dec-15 District: Bristol
Existing Projects
Project
Number: 16004
Name: Grayson County Trail
Sponsor: Grayson County
Applicant: Grayson County
Total Cost: $417,231
Current Request: $288,000
Description: Construction of a sidewalk and trail along Industrial Lane, Corporate Lane, and through a field area terminating at Grayson County Recreation Park.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $333,786
Project
Number: 16005
Name: Rural Retreat Community Sidewalk Improvements
Sponsor: Town of Rural Retreat
Applicant: Town of Rural Retreal
Total Cost: $550,575
Current Request: $440,640
Description: Construction of sidewalks along both sides of Railroad Avenue and along the east side of Church Street.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $440,640
Project
Number: 16033
Name: Heritage Walk
Sponsor: Town of Wytheville
Applicant: Town of Wytheville
Total Cost: $845,332
Current Request: $182,076
Description: Construction of a pedestrian walkway from Main Street thru Elizabeth Brown Park to Washington Street.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $676,265
1
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Bristol
Existing Projects
Project
Number: 16077
Name: Downtown to Hospital Pedestrian Sidewalk
Sponsor: Town of Pennington Gap
Applicant: Town of Pennington Gap
Total Cost: $556,106
Current Request: $444,885
Description: Construction of sidewalk from Cecil Street to North Edwards Street.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $444,885
Project
Number: 16083
Name: Powell River Trail
Sponsor: Town of Appalachia
Applicant: Town of Appalachia
Total Cost: $234,403
Current Request: $187,441
Description: Construction of a multi-use trail connecting the Town of Appalachia to the Town of Big Stone Gap.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $187,441
New Projects
Project
Number: 16035
Name: North 4th Street Sidewalk
Sponsor: Town of Wytheville
Applicant: Town of Wytheville
Total Cost: $1,052,225
Current Request: $841,780
Description: Construction of a sidewalk/walkway from the Northwind Apartments to the shopping center located at the intersection of North 4th Street and Tazewell Street.
Remarks:Average
Score
Total EN Funds
Anticipated: $841,780
2
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Bristol
New Projects
Project
Number: 16041
Name: Solon Street Sidewalk
Sponsor: Town of Gate City
Applicant: Town of Gate City
Total Cost: $316,585
Current Request: $253,268
Description: Rehabilitation of an existing sidewalk and construction of new sidewalk along Salon Street from Jackson Street to Bradford Street.
Remarks:Average
Score
Total EN Funds
Anticipated: $253,268
Project
Number: 16046
Name: Norton Riverwalk
Sponsor: City of Norton
Applicant: City of Norton
Total Cost: $771,992
Current Request: $617,954
Description: Construction of a trail along the Guest River in Norton.
Remarks:Average
Score
Total EN Funds
Anticipated: $617,954
Project
Number: 16053
Name: Rocky Gap Greenway
Sponsor: Bland County
Applicant: Bland County
Total Cost: $1,598,860
Current Request: $1,241,688
Description: Construction of a multi-use trail, trailhead, and rehabilitation of the historic Phoenix Bridge.
Remarks:Average
Score
Total EN Funds
Anticipated: $1,241,688
3
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Bristol
New Projects
Project
Number: 16078
Name: Norton Road Pedestrian Improvements
Sponsor: Town of Wise
Applicant: Town of Wise
Total Cost: $666,000
Current Request: $532,000
Description: Construction of sidewalks on both sides of Norton Road from Main Street to Cherry Street.
Remarks:Average
Score
Total EN Funds
Anticipated: $532,000
Project
Number: 16082
Name: Dungannon Streetscape
Sponsor: Town of Dungannon
Applicant: Town of Dungannon
Total Cost: $241,310
Current Request: $141,000
Description: Construction of a Greenway in the Town's Central Business District.
Remarks:Average
Score
Total EN Funds
Anticipated: $141,000
Project
Number: 16089
Name: Salt Trail Land Bridge Connector
Sponsor: Town of Saltville
Applicant: Town of Saltville
Total Cost: $300,000
Current Request: $240,000
Description: Construction of a trail and bridge to serve as a connection to the Salt Trail.
Remarks:Average
Score
Total EN Funds
Anticipated: $240,000
4
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Bristol
New Projects
Project
Number: 16097
Name: Back of the Dragon Scenic Overlook
Sponsor: Smyth County
Applicant: Smyth County
Total Cost: $920,000
Current Request: $736,000
Description: Rehabilitation of an existing overlook to improve it's safety and site amenities.
Remarks:Average
Score
Total EN Funds
Anticipated: $736,000
Cost : $8,470,619
Amount Requested : $6,146,732
Subtotal: Projects13
5
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Salem
Existing Projects
Project
Number: 16006
Name: Mayo River Rail Trail
Sponsor: Patrick County
Applicant: Patrick County
Total Cost: $499,050
Current Request: $399,240
Description: Phase III construction of the Mayo River Rail Trail to include a bridge crossing of the Mayo River and trailheads at each end.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $399,240
Project
Number: 16011
Name: Dick and Willie Passage
Sponsor: Henry County
Applicant: Henry County
Total Cost: $1,556,157
Current Request: $400,000
Description: Construction of a multi-use trail connecting the exisiting Dick & Willie Trail to the Henry County Soccer Complex.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $1,244,928
Project
Number: 16024
Name: Boones Mill Rail Depot Restoration
Sponsor: Town of Boones Mill
Applicant: Town of Boones Mill
Total Cost: $250,000
Current Request: $200,000
Description: Restoration of the Depot to serve as a living museum and community meeting place.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $200,000
6
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Salem
Existing Projects
Project
Number: 16051
Name: Christiansburg Downtown Streetscaping
Sponsor: Town of Christiansburg
Applicant: Town of Christiansburg
Total Cost: $1,406,000
Current Request: $250,000
Description: Construction of streetscaping improvements in the Downtown Central Business District.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $1,124,800
Project
Number: 16052
Name: Huckleberry Trail Extension
Sponsor: Montgomery County
Applicant: Montgomery County
Total Cost: $801,000
Current Request: $250,000
Description: Construction of a trail extension that will connect the Huckleberry Trail to the North Franklin Street sidewalk at Independence Boulevard.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $640,800
Project
Number: 16084
Name: Rich Creek Downtown Improvements
Sponsor: Town of Rich Creek
Applicant: Town of Rich Creek
Total Cost: $816,117
Current Request: $225,000
Description: Sidewalk replacement and other improvements in downtown Rich Creek.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $652,893
New Projects
7
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Salem
New Projects
Project
Number: 16007
Name: Historic Gauge Dock Restoration
Sponsor: Town of Buchanan
Applicant: Town of Buchanan
Total Cost: $242,800
Current Request: $192,240
Description: Excavation and testing for the Buchanan Gauge Dock Restoration.
Remarks:Average
Score
Total EN Funds
Anticipated: $192,240
Project
Number: 16031
Name: Radford University Sidewalk Interconnectivity
Sponsor: City of Radford
Applicant: City of Radford
Total Cost: $814,977
Current Request: $651,902
Description: Construction of sidewalk along one side of Clement Street and Downey Street from Jefferson Street to Burlington Street.
Remarks:Average
Score
Total EN Funds
Anticipated: $651,902
Project
Number: 16045
Name: Colonial Avenue Boulevard
Sponsor: City of Roanoke
Applicant: Virginia Western Community College
Total Cost: $573,518
Current Request: $458,814
Description: Construction of inroad buffered bike lanes, sidwalks, pedestrian crosswalks, and intersection improvements at Overland Road, McNeil Road, and Winding Way Road.
Remarks:Average
Score
Total EN Funds
Anticipated: $458,814
8
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Salem
New Projects
Project
Number: 16074
Name: Downtown Salem Streetscape and Intersection Improvements
Sponsor: City of Salem
Applicant: City of Salem
Total Cost: $600,000
Current Request: $480,000
Description: Reconstruction of sidewalks on Main Street from the intersection of Broad Street to InterWhite Oak Alley.
Remarks:Average
Score
Total EN Funds
Anticipated:$480,000
Project
Number: 16075
Name: Glade Creek Greenway
Sponsor: Town of Vinton
Applicant: Town of Vinton
Total Cost: $526,210
Current Request: $417,710
Description: Construction of the Glade Creek Greenway from Walnut Avenue to Gus Nicks Boulevard.
Remarks:Average
Score
Total EN Funds
Anticipated: $417,710
Project
Number: 16094
Name: Friensdship Lane/Carvins Creek Bridge Replacement
Sponsor: Roanoke County
Applicant: Roanoke County
Total Cost: $170,619
Current Request: $136,495
Description: Replacement of a pedestrian bridge allowing the next segment of the Tinker Creek Trail to be constructed.
Remarks:Average
Score
Total EN Funds
Anticipated: $136,495
Cost : $8,256,448
Amount Requested : $4,061,401
Subtotal: Projects12
9
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Lynchburg
Existing Projects
Project
Number: 16010
Name: Appomattox Heritage Trail
Sponsor: Appomattox County
Applicant: Appomattox County
Total Cost: $546,442
Current Request: $218,577
Description: Phase 2 Multi-Use Trail construction.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $437,154
Project
Number: 16030
Name: Blue Ridge Crozet Tunnel Rehabilitation and Trail
Sponsor: Nelson County
Applicant: Nelson County
Total Cost: $1,142,825
Current Request: $949,920
Description: Construction of the western trailhead and parking area, the western trail, and the western portal work.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $949,920
Project
Number: 16062
Name: Route 43 Downtown Gateway
Sponsor: Town of Altavista
Applicant: Town of Altavista
Total Cost: $220,000
Current Request: $176,000
Description: Upgrade of the cabinets/conduits at the intersection of Bedford Avenue and 7th Street, and Bedford Avenue and Main Street to accomidate pedestrian signals.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $176,000
10
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Lynchburg
Existing Projects
Project
Number: 16063
Name: Buffalo Creek Pedestrian/Bicycle Bridge and Trail Connections
Sponsor: Town of Farmville
Applicant: Town of Farmville
Total Cost: $820,000
Current Request: $306,454
Description: Construction of the Buffalo Creek Pedestrian/Bicycle Bridge and trail connections to the existing Dogwood Trail, Sarah Terry Trail, and the Buffalo Creek Blueway.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated:$652,000
Project
Number: 16096
Name: Banister River Gateway
Sponsor: Town of Halifax
Applicant: Town of Halifax
Total Cost: $291,164
Current Request: $232,931
Description: Completion of the Banister River Gateway.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $232,931
New Projects
Project
Number: 16018
Name: Route 645 (Evergreen Road) Sidewalk
Sponsor: Town of Charlotte Courthouse
Applicant: Town of Charlotte Court House
Total Cost: $314,820
Current Request: $251,856
Description: Construction of new sidewalks along Route 645 from the entrance to the Randolph-Henry High School parking lot to intersection with Route 1106.
Remarks:Average
Score
Total EN Funds
Anticipated: $251,856
11
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Lynchburg
New Projects
Project
Number: 16023
Name: Danville Multi-Use Connector Trail
Sponsor: City of Danville
Applicant: City of Danville
Total Cost: $319,824
Current Request: $239,868
Description: Construction of a trail that will tie into the existing northside trail that ends on Stinson Street and terminate at Danville Regional Airport.
Remarks:Average
Score
Total EN Funds
Anticipated: $239,868
Project
Number: 16044
Name: Dearington Elementary SRTS
Sponsor: City of Lynchburg
Applicant: City of Lynchburg
Total Cost: $210,305
Current Request: $168,244
Description: Construction of a sidewalk along Stoneridge Street.
Remarks:Average
Score
Total EN Funds
Anticipated: $168,244
Project
Number: 16095
Name: Tobacco Heritage Trail - Halifax County Extension
Sponsor: Halifax County
Applicant: Halifax County
Total Cost: $428,000
Current Request: $342,400
Description: Construction of a trail from the current Tobacco Heritage Trail at Berry Hill Plantation to Mirey Creek.
Remarks:Average
Score
Total EN Funds
Anticipated: $342,400
Cost : $4,293,380
Amount Requested : $2,886,250
Subtotal: Projects9
12
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Richmond
Existing Projects
Project
Number: 16013
Name: Belvidere Street Gateway
Sponsor: City of Richmond
Applicant: City of Richmond
Total Cost: $486,000
Current Request: $388,800
Description: Construction of pedestrian and access improvements along Belvidere Street at the intersection of Idlewood Avenue, Spring Street, and Rowe Street.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $388,800
Project
Number: 16017
Name: South Hill Downtown Revitalization
Sponsor: Town of South Hill
Applicant: Town of South Hill
Total Cost: $158,231
Current Request: $126,585
Description: Construction of sidewalks and other pedestrian improvements that will complete this downtown streetscaping project.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $126,585
Project
Number: 16055
Name: Appomattox River Greenway Trail
Sponsor: City of Colonial Heights
Applicant: City of Colonial Heights
Total Cost: $90,000
Current Request: $72,000
Description: Construction of a trail along the Appomattox River from Roslyn Landing Park to Jennick Drive.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $72,000
13
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Richmond
Existing Projects
Project
Number: 16090
Name: South Side Depot Rehabilitation
Sponsor: City of Petersburg
Applicant: City of Petersburg
Total Cost: $450,000
Current Request: $360,000
Description: Phase II rehabilitation of the Southside Depot.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $360,000
New Projects
Project
Number: 16012
Name: 1st and 2nd Street Buffered Bike Lanes
Sponsor: City of Richmond
Applicant: City of Richmond
Total Cost: $300,000
Current Request: $240,000
Description: Construction of a buffered bike lane along the one-way couplet of 1st Street and 2nd Street.
Remarks:Average
Score
Total EN Funds
Anticipated: $240,000
Project
Number: 16014
Name: Church Hill/29th Street Bike-Walk Boulevard
Sponsor: City of Richmond
Applicant: City of Richmond
Total Cost: $650,000
Current Request: $520,000
Description: Conversion of North 29th Street into a bike-walk boulevard.
Remarks:Average
Score
Total EN Funds
Anticipated: $520,000
14
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Richmond
New Projects
Project
Number: 16015
Name: Maymont Neighborhood Sidewalks
Sponsor: City of Richmond
Applicant: City of Richmond
Total Cost: $800,000
Current Request: $640,000
Description: Construction of sidewalks in the Maymont Neighborhood.
Remarks:Average
Score
Total EN Funds
Anticipated: $640,000
Project
Number: 16016
Name: James River Branch Trail
Sponsor: City of Richmond
Applicant: City of Richmond
Total Cost: $450,000
Current Request: $360,000
Description: Conversion of an abandoned rail corridor into a trail.
Remarks:Average
Score
Total EN Funds
Anticipated: $360,000
Project
Number: 16019
Name: Brodnax Depot Renovation
Sponsor: Town of Brodnax
Applicant: Town of Broadnax
Total Cost: $438,275
Current Request: $315,245
Description: Renovation of the Brodnax Depot to serve as a trailhead facility on the Tobacco Heritage Trail.
Remarks:Average
Score
Total EN Funds
Anticipated: $315,245
15
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Richmond
New Projects
Project
Number: 16020
Name: North Main Street Sidewalks
Sponsor: Town of Lawrenceville
Applicant: Town of Lawrenceville
Total Cost: $384,283
Current Request: $307,426
Description: Reconstruction of sidewalks along both sides of North Main Street from the Railroad Street Bridge to Hicks Street.
Remarks:Average
Score
Total EN Funds
Anticipated: $307,426
Project
Number: 16048
Name: Short Pump Park
Sponsor: Henrico County
Applicant: Henrico County
Total Cost: $310,215
Current Request: $248,172
Description: Construction of shared-use paths that will provide connectivity to/from West Broad Village mixed-use community.
Remarks:Average
Score
Total EN Funds
Anticipated: $248,172
Project
Number: 16060
Name: Boulevard Pedestrian Safety
Sponsor: City of Colonial Heights
Applicant: City of Colonial Heights
Total Cost: $120,000
Current Request: $96,000
Description: Right-of-way acquisition and design of pedestrian safety amenities along both sides of the Boulevard from A Avenue to Temple Avenue.
Remarks:Average
Score
Total EN Funds
Anticipated: $96,000
16
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Richmond
New Projects
Project
Number: 16070
Name: Bailey Bridge Road Sidewalk
Sponsor: Chesterfield County
Applicant: Chesterfield County
Total Cost: $900,000
Current Request: $720,000
Description: Construction of a sidewalk along Bailey Bridge Road from Battlecreek Drive to Manchester High School.
Remarks:Average
Score
Total EN Funds
Anticipated: $720,000
Project
Number: 16073
Name: Spring Run Road Sidewalk
Sponsor: Chesterfield County
Applicant: Chesterfield County
Total Cost: $126,000
Current Request: $100,800
Description: Construction of a sidewalk on Spring Run Road from Brocket Drive to Spring Run Elementary School.
Remarks:Average
Score
Total EN Funds
Anticipated: $100,800
Project
Number: 16079
Name: Blackstone Sidewalk Improvements
Sponsor: Town of Blackstone
Applicant: Town of Blackstone
Total Cost: $983,238
Current Request: $786,590
Description: Sidewalk and access improvements to the Park and Blackstone Primary School.
Remarks:Average
Score
Total EN Funds
Anticipated: $786,590
17
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Richmond
New Projects
Project
Number: 16085
Name: Petersburg SRTS
Sponsor: City of Petersburg
Applicant: City of Petersburg
Total Cost: $125,000
Current Request: $100,000
Description: Construction of sidewalk and crosswalk improvements at various school locations.
Remarks:Average
Score
Total EN Funds
Anticipated: $100,000
Cost : $6,771,242
Amount Requested : $5,381,618
Subtotal: Projects16
18
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Hampton Roads
Existing Projects
Project
Number: 16001
Name: Cape Charles Community Trail
Sponsor: Town of Cape Charles
Applicant: Town of Cape Charles
Total Cost: $1,021,469
Current Request: $204,294
Description: Construction of Phase 2B trail section on the east end of Washington Avenue from Peach Street to Fig Street.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $817,175
Project
Number: 16022
Name: Chesapeake Avenue Bike Trail
Sponsor: City of Chesapeake
Applicant: City of Chesapeake
Total Cost: $1,000,000
Current Request: $400,000
Description: Construction of a bike trail and separate pedestrian promenade walkway along the Chesapeake Avenue seawall.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $800,000
Project
Number: 16057
Name: Hwy 301 North Sidewalk
Sponsor: Greensville County
Applicant: Greensville County
Total Cost: $564,100
Current Request: $132,108
Description: Construction of a sidewalk along US Hwy 301 North from Crescent Road to Greensville County Elementary School.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $451,280
19
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Hampton Roads
Existing Projects
Project
Number: 16065
Name: Pine Chapel Road Pedestrian/Bicycle Trail
Sponsor: City of Hampton
Applicant: City of Hampton
Total Cost: $2,254,377
Current Request: $509,072
Description: Construction of a pedestrian/bicycle trail along the north side of Pine Chapel Road from Coliseum Drive to Power Plant Parkway.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $1,803,502
New Projects
Project
Number: 16021
Name: Washington Avenue Streetscape
Sponsor: City of Newport News
Applicant: City of Newport News
Total Cost: $500,000
Current Request: $400,000
Description: Construction of pedestrian accommodations on four city blocks of Washington Avenue.
Remarks:Average
Score
Total EN Funds
Anticipated: $400,000
Project
Number: 16026
Name: Independence Boulevard and Baxter Road Sidewalk
Sponsor: City of Virginia Beach
Applicant: City of Virginia Beach
Total Cost: $1,151,416
Current Request: $794,477
Description: Construction of a sidewalk along the west side of Independence Boulevard from the I-264 on-ramp to Baxter Road, and on the north side of Baxter Road from Independence Boulevard to Alicia Drive.
Remarks:Average
Score
Total EN Funds
Anticipated: $794,477
20
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Hampton Roads
New Projects
Project
Number: 16027
Name: Providence Road Sidewalk
Sponsor: City of Virginia Beach
Applicant: City of Virginia Beach
Total Cost: $924,880
Current Request: $638,168
Description: Construction of a sidewalk along the south side of Providence Road from east of Kempsville Road to the intersection of Indian Lakes Boulevard and Churchill Drive.
Remarks:Average
Score
Total EN Funds
Anticipated: $638,168
Project
Number: 16028
Name: Salem Road Sidewalk
Sponsor: City of Virginia Beach
Applicant: City of Virginia Beach
Total Cost: $484,821
Current Request: $334,527
Description: Construction of a sidewalk along the east side of Salem Road from Salem Lakes Boulevard to Rock Lake Loop.
Remarks:Average
Score
Total EN Funds
Anticipated: $334,527
Project
Number: 16029
Name: West Great Neck Sidewalk
Sponsor: City of Virginia Beach
Applicant: City of Virginia Beach
Total Cost: $860,047
Current Request: $593,432
Description: Construction of a sidewalk along the west side of West Great Neck Road from Adam Keeling Road to the southern side of the bridge over Long Creek.
Remarks:Average
Score
Total EN Funds
Anticipated: $593,432
21
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Hampton Roads
New Projects
Project
Number: 16037
Name: Complete Streets Initiative
Sponsor: City of Norfolk
Applicant: City of Norfok
Total Cost: $400,000
Current Request: $320,000
Description: Pedestrian safety improvements along the Tidewater Drive corridor.
Remarks:Average
Score
Total EN Funds
Anticipated: $320,000
Project
Number: 16049
Name: Granby Street Bike Lane
Sponsor: City of Norfolk
Applicant: City of Norfok
Total Cost: $710,000
Current Request: $568,000
Description: Construction of bicycle improvements along Granby Street from Willow Wood Drive to Admiral Taussig Boulevard.
Remarks:Average
Score
Total EN Funds
Anticipated: $568,000
Project
Number: 16050
Name: Elizabeth River Trail - Fort Norfolk Segment
Sponsor: City of Norfolk
Applicant: City of Norfok
Total Cost: $530,000
Current Request: $424,000
Description: Reconstruction of sidewalk from the Smith Creek Bridge to Front Street. Construction of a multi-modal path on Front Street from Second Street to Colley Avenue. Rehabilitation of the sidewalk on Colley Avenue from Front Street to Southampton Avenue.
Remarks:Average
Score
Total EN Funds
Anticipated: $424,000
22
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Hampton Roads
New Projects
Project
Number: 16056
Name: Monticello Avenue Multi-Use Trail
Sponsor: City of Williamsburg
Applicant: City of Williamsburg
Total Cost: $1,250,000
Current Request: $1,000,000
Description: Construction of a trail along Monticello Avenue from Trayburn Drive to Ironbound Road.
Remarks:Average
Score
Total EN Funds
Anticipated: $1,000,000
Project
Number: 16066
Name: Suburban Pedestrian Connector
Sponsor: City of Suffolk
Applicant: City of Suffolk
Total Cost: $1,185,108
Current Request: $948,086
Description: Construction of a sidewalk from the Oakdale and Pierce Park communities to Portsmouth Boulevard.
Remarks:Average
Score
Total EN Funds
Anticipated: $948,086
Project
Number: 16086
Name: Bypass Road Sidewalk Rehabilitation
Sponsor: York County
Applicant: York County
Total Cost: $700,000
Current Request: $560,000
Description: Replacement of a pedestrian/bike path along Bypass Road from west of Waller Mill Road to the Williamsburg City Limits.
Remarks:Average
Score
Total EN Funds
Anticipated: $560,000
23
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Hampton Roads
New Projects
Project
Number: 16091
Name: Low Ground Road Sidewalk
Sponsor: Greensville County
Applicant: Greensville County
Total Cost: $315,932
Current Request: $252,746
Description: Construction of a sidewalk from the Spring Hill Village Mobile Home Park to the Emporia City Limits.
Remarks:Average
Score
Total EN Funds
Anticipated: $252,746
Project
Number: 16093
Name: Lake Hampton Pedestrian/Bicycle Trail
Sponsor: City of Hampton
Applicant: City of Hampton
Total Cost: $1,870,000
Current Request: $1,000,000
Description: Construction of a trail from the Greenman property on Freeman Drive to the North Armistead Avenue intersection.
Remarks:Average
Score
Total EN Funds
Anticipated: $1,496,000
Cost : $15,722,150
Amount Requested : $9,078,910
Subtotal: Projects17
24
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Fredericksburg
Existing Projects
Project
Number: 16059
Name: Mine Road Sidewalk
Sponsor: Stafford County
Applicant: Stafford County
Total Cost: $820,000
Current Request: $492,785
Description: Construction of a sidewalk along Mine Road from Cathedral Lane to Highpointe Boulevard.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $656,000
New Projects
Project
Number: 16008
Name: Prince Street Sidewalks
Sponsor: Town of Tappahannock
Applicant: Town of Tappahannock
Total Cost: $361,330
Current Request: $266,130
Description: Reconstruction of sidewalks on Prince Street from Church Lane to the River.
Remarks:Average
Score
Total EN Funds
Anticipated: $266,130
Project
Number: 16025
Name: King William Courthouse Trail System
Sponsor: King William County
Applicant: King William County
Total Cost: $250,000
Current Request: $200,000
Description: Construction of pedestrian facilities that will facilitate access to the County's historic administrative/judical complex.
Remarks:Average
Score
Total EN Funds
Anticipated: $200,000
Cost : $1,431,330
Amount Requested : $958,915
Subtotal: Projects3
25
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Culpeper
Existing Projects
Project
Number: 16002
Name: Marshall Streetscape
Sponsor: Fauquier County
Applicant: Fauquier County
Total Cost: $4,511,975
Current Request: $392,000
Description: Construction of sidewalks, crosswalks, landscaping, lighting and other improvements along the north and south sides of Main Street (Route 55) in the village of Marshall.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $3,609,580
New Projects
Project
Number: 16036
Name: Water Street Shared Use Path
Sponsor: City of Charlottesville
Applicant: City of Charlottesville
Total Cost: $353,672
Current Request: $254,984
Description: Construction of a shared-use path along Water Street from the Coal Tower and Meade Avenue Trails to the downtown maill.
Remarks:Average
Score
Total EN Funds
Anticipated: $254,984
Project
Number: 16042
Name: Timber Fence Trail
Sponsor: Town of Warrenton
Applicant: Town of Warrenton
Total Cost: $918,756
Current Request: $735,005
Description: Construction of a trail connecting a park through adjacent neighborhoods to a high school.
Remarks:Average
Score
Total EN Funds
Anticipated: $735,005
26
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Culpeper
New Projects
Project
Number: 16076
Name: 5th Street Node and Bicycle Connections
Sponsor: City of Charlottesville
Applicant: Thomas Jefferson Planning District Commission
Total Cost: $612,880
Current Request: $412,880
Description: Construction to include "nodes" for bicyclists at connecting points on the trail, trail construction from Bent Creek Road south along Moore's Creek, bridge construction over Biscuit Run, trail construction along Biscut Run and Moore's Creek.
Remarks:Average
Score
Total EN Funds
Anticipated: $412,880
Cost : $6,397,283
Amount Requested : $1,794,869
Subtotal: Projects4
27
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Staunton
Existing Projects
Project
Number: 16009
Name: Strasburg Downtown Streetscaping
Sponsor: Town of Strasburg
Applicant: Town of Strasburg
Total Cost: $2,185,444
Current Request: $613,413
Description: Streetscaping improvements along King Street.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $1,748,355
Project
Number: 16040
Name: Appalachian Trail Connector
Sponsor: Warren County
Applicant: Warren County
Total Cost: $1,299,137
Current Request: $340,941
Description: Construction of a path along Route 522 that will connect the Town of Front Royal with the Appalachian Trail.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $1,039,309
Project
Number: 16064
Name: Sidewalk Improvements
Sponsor: Town of Mt Jackson
Applicant: Town of Mount Jackson
Total Cost: $450,120
Current Request: $360,096
Description: Construction of sidewalks along Main Street and Conicville Boulevard from Tripplett Tech School to Avondale Avenue.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $360,096
28
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Staunton
Existing Projects
Project
Number: 16067
Name: Lifecore Drive Shared-Use Path
Sponsor: Augusta County
Applicant: Augusta County
Total Cost: $1,067,100
Current Request: $580,640
Description: Construction of a shared-use path from west of the intersection of Tinkling Spring Road and Lifecore Road to the intersection of Village Creek Drive and Lifecore Drive.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $853,680
New Projects
Project
Number: 16080
Name: Blue Ridge Road Shared-Use Path
Sponsor: Town of Glasgow
Applicant: Town of Glasgow
Total Cost: $294,400
Current Request: $235,520
Description: Construction of a shared-use path along Blue Ridge Road from Powhatan Street to Fitzlee Street.
Remarks:Average
Score
Total EN Funds
Anticipated: $235,520
Project
Number: 16081
Name: Bessie Weller Elementary School SRTS
Sponsor: City of Staunton
Applicant: City of Staunton
Total Cost: $378,798
Current Request: $278,798
Description: Construction of sidewalk, crosswalks, and lighting.
Remarks:Average
Score
Total EN Funds
Anticipated: $278,798
29
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Staunton
New Projects
Project
Number: 16088
Name: Chessie Trail Bridge Connection
Sponsor: Town of Buena Vista
Applicant: City of Buena Vista
Total Cost: $231,619
Current Request: $176,031
Description: Construction of a walkway that will connect the existing Chessie trail to the City sidewalk along Route 60.
Remarks:Average
Score
Total EN Funds
Anticipated: $176,031
Project
Number: 16092
Name: Spotswood Elementary School SRTS
Sponsor: City of Harrisonburg
Applicant: City of Harrisonburg
Total Cost: $189,900
Current Request: $151,984
Description: Construction of a sidewalk, crossing location, and flashing zone lights on Reservoir Street between Hawkins Street and Kenmore Street.
Remarks:Average
Score
Total EN Funds
Anticipated: $151,984
Cost : $6,096,518
Amount Requested : $2,737,423
Subtotal: Projects8
30
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Northern Virginia
Existing Projects
Project
Number: 16043
Name: Round Hill Pedestrian Improvements
Sponsor: Town of Round Hill
Applicant: Town of Round Hill
Total Cost: $2,419,565
Current Request: $1,175,162
Description: Construction of sidewalks along Main Street from Loudoun Street to just north of High Street.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $1,935,652
Project
Number: 16047
Name: Colonial Highway Sidewalks
Sponsor: Town of Hamilton
Applicant: Town of Hamilton
Total Cost: $372,100
Current Request: $297,680
Description: Replacement, reconstruction, and upgrade of existing sidewalks in the Town of Hamilton.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $297,680
Project
Number: 16054
Name: Van Buren Street Multi-Modal Improvements
Sponsor: Town of Herndon
Applicant: Town of Herndon
Total Cost: $636,383
Current Request: $509,106
Description: Construction of "complete street" design facilities on Van Buren Street from Herndon Parkway to Alabama Drive.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $509,106
31
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Northern Virginia
Existing Projects
Project
Number: 16061
Name: Cinder Bed Bikeway
Sponsor: Fairfax County
Applicant: Fairfax County
Total Cost: $4,000,000
Current Request: $400,000
Description: Construction of a bikeway from Fort Belvoir to Franconia-Springfield Metrorail Station.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $2,000,000
Project
Number: 16087
Name: McKinley Road/North Ohio Street SRTS
Sponsor: Arlington County
Applicant: Arlington County
Total Cost: $1,109,280
Current Request: $400,000
Description: Construction of raised medians, pedestrian curb extensions, and buffered bike lanes on McKinley Road/North Ohio Street from Wilson Boulevard to 11th Street North.
Remarks:Average
Score
Priority
Ranking0
Total EN Funds
Anticipated: $840,000
New Projects
Project
Number: 16003
Name: Melody Lane Safe Routes to School Sidewalk
Sponsor: Town of Vienna
Applicant: Town of Vienna
Total Cost: $350,000
Current Request: $280,000
Description: Construction of a sidewalk on Melody Lane SW from DeSale Street to Lullaby Lane.
Remarks:Average
Score
Total EN Funds
Anticipated: $280,000
32
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Northern Virginia
New Projects
Project
Number: 16032
Name: Horner Road Sidewalk
Sponsor: Prince William County
Applicant: Prince William County
Total Cost: $462,357
Current Request: $369,886
Description: Construction of a sidewalk along Horner Road from the intersection of Forest Glen Road to the Kilby Elementary School.
Remarks:Average
Score
Total EN Funds
Anticipated: $369,886
Project
Number: 16034
Name: Innovation Drive Asphalt Trail
Sponsor: Prince William County
Applicant: Prince William County
Total Cost: $1,067,000
Current Request: $853,600
Description: Construction of a trail on one side of Innovation Drive from George Mason Drive to the end of Innovation Drive.
Remarks:Average
Score
Total EN Funds
Anticipated: $853,600
Project
Number: 16038
Name: Opitz Boulevard Sidewalk
Sponsor: Prince William County
Applicant: Prince William County
Total Cost: $1,254,120
Current Request: $1,003,296
Description: Construction of a sidewalk along the south side of Opitz Boulevard from an existing sidewalk on Potomac Center Boulevard to an existing sidewalk on Opitz Boulevard at Potomac Library.
Remarks:Average
Score
Total EN Funds
Anticipated: $1,003,296
33
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Northern Virginia
New Projects
Project
Number: 16039
Name: Dumfries Road Sidewalk
Sponsor: Prince William County
Applicant: Prince William County
Total Cost: $686,648
Current Request: $514,986
Description: Construction of sidewalk on the east side of Dumfries Road between Counselor Road and Tayloe Drive.
Remarks:Average
Score
Total EN Funds
Anticipated: $514,986
Project
Number: 16058
Name: Mount Vernon Trail Bridge Replacement
Sponsor: City of Alexandria
Applicant: National Park Service
Total Cost: $1,275,000
Current Request: $800,000
Description: Removal of an existing bridge and construction of a new bridge on the Mount Vernon Trail.
Remarks:Average
Score
Total EN Funds
Anticipated: $800,000
Project
Number: 16068
Name: Van Dorn Street Pedestrian and Bicycle Access Improvements
Sponsor: Fairfax County
Applicant: Fairfax County
Total Cost: $1,500,000
Current Request: $400,000
Description: Construction of a shared-use path from South Van Dorn Street/Oakwood Road Intersection to Fairfax County Line.
Remarks:Average
Score
Total EN Funds
Anticipated:$1,200,000
34
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Northern Virginia
New Projects
Project
Number: 16069
Name: Reston Bike Share
Sponsor: Fairfax County
Applicant: Fairfax County
Total Cost: $766,000
Current Request: $400,000
Description: Purchase of bikeshare stations and bicycles to launch a bikeshare system in Reston, Va.
Remarks:Average
Score
Total EN Funds
Anticipated: $400,000
Project
Number: 16071
Name: W&OD Trail Plaza and Crossing Improvements
Sponsor: City of Falls Church
Applicant: City of Falls Church
Total Cost: $900,000
Current Request: $160,000
Description: Improvement of 6 at-grade crossings and construction of several trail plazas that will provide bicycle repair, access to restrooms, historical information, and wayfinding information.
Remarks:Average
Score
Total EN Funds
Anticipated: $720,000
Project
Number: 16072
Name: Park Avenue Great Streets
Sponsor: City of Falls Church
Applicant: City of Falls Church
Total Cost: $3,300,000
Current Request: $240,000
Description: Rehabilitate existing sidewwalks to comply with ADA standards and improve pedestrian access.
Remarks:Average
Score
Total EN Funds
Anticipated: $2,640,000
35
2016 Transportation Alternatives Project Requests
01-Dec-15 District: Northern Virginia
New Projects
Project
Number: 16098
Name: Historic Stone Bridge Rehabilitation
Sponsor: City of Manassas
Applicant: National Park Service
Total Cost: $575,000
Current Request: $460,000
Description: Preservation and rehabilitation of the historic Stone Bridge over Bull Run.
Remarks:Average
Score
Total EN Funds
Anticipated: $460,000
Cost : $20,673,453
Amount Requested : $8,263,716
Subtotal: Projects16
Cost : $78,112,423
Amount Requested : $41,309,834
Grand Total: Projects98
36