Agenda for the 86th
Meeting of PCSC scheduled to be held on 4
th September, 2019 Page 1
SOUTHERN REGIONAL POWER COMMITTEE BENGALURU
Agenda for the 86th Meeting of Protection Coordination Sub-Committee of SRPC to be held on 4th September, 2019
1. Introduction
2. Confirmation of Minutes of last PCSC meeting
Confirmation of minutes of 85th Protection Coordination Sub-Committee meeting held on 31st July 2019.
3. Grid Occurrences
3.1 Grid Disturbances (GD), Grid Incidences (GI), trippings due to failure of Auto-reclosing
(A/R) and mal-operation of PLCC equipment that occurred during the period July - August, 2019, given at Annexure-I, would be discussed in the PCSC meeting.
Constituents are requested to furnish the following information in respect of the above grid occurrences to have fruitful discussions:
(a) Single line diagram of the station with switching devices, CT, PT and relay details.
(b) Cause of the tripping & Remedial Action taken
(c) Relay setting details
Constituents are requested to furnish/bring full particulars of the tripping events pertaining to their system.
3.2 In compliance of Regulations 5.2 (r) of IEGC, the Constituents are required to furnish
the following information in respect of Grid Occurrences within 24 hr. of occurrence of the same to SRLDC/ SRPC: (a) First Information Report (FIR) (b) Event Logger (EL) output (c) Disturbance Recorder (DR) output (d) Trip event analysis report (with pre and post fault system conditions) Non-furnishing of tripping details (FIR/DR/EL/TR) for the period 01.07.2019 – 15.08.2019 had been brought to Constituents’ notice vide letters (i) No. SRPC/ SE-III/ PCSC/ 2019/ 4624-34 dated 19.07.2019, (ii) No. SRPC/ SE-III/ PCSC/ 2019/ 4957-69 dated 07.08.2019 and (iii) No. SRPC/ SE-III/ PCSC/ 2019/5157-72 dated 20.08.2019. Non-compliance in this regard would be discussed in the meeting.
4. Submission of Reports/ Compliance by Constituents
4.1 Status of implementation of Recommendations Protection Coordination
Sub-Committee (PCSC), which are pending
The status of implementation of PCSC recommendations (up to 85th PCSC meeting), which are pending is given at Annexure-II. The latest status on the same may please be sent latest by 28.08.2019.
Agenda for the 86th
Meeting of PCSC scheduled to be held on 4
th September, 2019 Page 2
4.2 Remedial measures for "Transmission Elements under Forced Outage"
The Constituents are requested to furnish the remedial measures/ actions taken by them for the tripping events as circulated vide this office emails. (Annexure-III)
The tripping events are based on the daily reports at SRLDC website http://srldc.in/Reports.aspx under the menu: Reports->Daily-> "TL under Forced Outage").
4.3 Certificate for Healthiness of Batteries
As per the MoP direction, given in pursuant to recommendations of the Enquiry Committee (NEW grid disturbance on 30th & 31st July, 2012), the monthly certificate for healthiness of batteries, installed at 220 KV and above voltage level Substations (for power supply to Relays, RTUs and PLCC equipment) are required to be obtained by RPC’s from their respective Constituents and furnish the same to CEA/ MoP.
With reference to above, the Constituents have been requested to submit the certificate on healthiness of batteries on monthly basis (i.e. status for a month shall be sent by the 7th day of the following month) to SRPC Secretariat.
The sought status for the month of July, 2019 is awaited from the following SR-Constituents:
KPTCL, TANGEDCO, PGCIL (SR-1), NLCIL, NTECL 5. Nominations of Nodal Officers for Conduction of Protection Audit of various 220 kV
& above Stations in Southern Region
As per the discussions of PCSC-80 conduction of protection audit of various 220 kV & above Stations in Southern Region was approved in 35th SRPC meeting. Nominations in this regard were sought from all Utilities vide SRPC letter No. SRPC/SE-III/ PA/ 2019/3589-3618 dated 19.06.2019. NLCIL is requested to urgently furnish nominations in this regard.
Based on analysis of past tripping data nearly 80 stations have been identified as part of the audit. Schedule of the same will be discussed during the meeting.
6. Updating of Protection Audit format
All SR constituents were requested to share their suggestions/ modifications/ deletions required in the protection audit format vide SRPC mail dated 02.08.2019, so as to update the same as per recent trends followed in industry. All constituents are requested to furnish the inputs in this regard before 28.08.2019 for compiling and further discussion in forthcoming PCSC meeting.
7. Report of Standing Committee of experts on failure of 220kV & above voltage class substation equipments
CEA standing Committee of experts on failure of 220kV & above voltage class substation equipments have published their report of failure analysis of 220kV & above voltage class substation equipment for the period January 2017 to March 2018 on CEA website (http://www.cea.nic.in/reports/committee/failure_equipment/failure_1718.pdf) .
This is for the kind information of all constituents.
Agenda for the 86th
Meeting of PCSC scheduled to be held on 4
th September, 2019 Page 3
8. Other Protection Issues, if any, with the permission of the Chair
9. Sending Agenda items for the PCSC meetings
As per the Guidelines of CEA/MOP, it has been decided to conduct the PCSC meetings on monthly basis. It is requested that Agenda Items for the PCSC meetings, if any, may please be sent latest by 5th working day of the month to SRPC Secretariat to compile and circulate the same so as to have fruitful discussions in the PCSC meetings.
10. Date of next PCSC meeting
The tentative date of 87th meeting of PCSC is 23rd October 2019.
*****
Grid Occurrences to be discussed in the 86thMeeting of PCSC scheduled to be held on 4th September, 2019 1/4
Grid Occurrences - 86
For all tripping events involving failure of substation equipment, Constituents are requested to kindly furnish the SLD or equivalent pictorial representation showing (i) Location of the fault, and (ii) Bus-bar arrangement/ Configuration of feeders and other connected equipment with proper CB positions (OPEN/ CLOSE) at the time of occurrence of the fault.
I. Details of Grid Disturbances:
Sl. No.
Details of Event Date &Time Reason Remarks Category
1
Complete outage of 220kV Kadakola, Hootagally, Vajramangala, TK Halli, Madhuvanahalli and Chamrajnagar stations of KPTCL
25-07-2019 at 12:58hrs
Bus bar protection operated at 220kV Kadakola station due to fault created by arcing in isolator resulting in tripping of all connected elements. 220kV Kadakola station was on single bus operation. There was also complete loss of supply at 220kV Hootagally, 220kV Vajramangala, 220kV TK Halli, 220kV Madhuvanahalliand 220kV Chamrajnagar substations
Load loss –
350MW GD-1
2
Complete Outage of 400kV KTPS VII Generating Station of TSGENCO
04-08-2019 at 18:01hrs
and 06-08-2019 at 23:50hrs
Connected lines got tripped on operation of over voltage protection which in turn lead to de-energization of 400kV Bus-1 & 2.
GD-1
3
Complete outage of 220kV/132kV Paravada SS of APTRANSCO
08-08-2019 at 11:34 hrs
Triggering incident was failure of Y-ph LA of 220kV Paravada- VSS(Vizag Switching Station) line at Paravada end.
Load loss – 84 MW
GD-1
II. Details of Grid Incidents:
Sl. No. Details of Event Date &Time Reason Category
1 Tripping of 400kV Krishnapatnam-Nellore-1
01-07-2019 at 03:40 hrs, 03-07-2019 at 3:42 hrs, 19-07-2019 at 2:25 hrs, 21-07-2019 at 2:27 hrs, 28-07-2019 at 1:40 hrs, 28-07-2019 at 23:39 hrs
Line tripped on operation of over voltage stg-1 protection at Krishnapatnam and direct trip was received at Nellore. The Y –phase CVT voltage at Krishnapatnam end was observed to be 8 to 10 kV higher than the R & B phase voltages.
GI-2
Annexure-I
Grid Occurrences to be discussed in the 86thMeeting of PCSC scheduled to be held on 4th September, 2019 2/4
2 Tripping of 400kv Kalpakka-Asupaka line-1
01-07-2019 at 15:59 hrs; 20-07-2019 at 21:00 hrs
Line tripped on operation of over voltage stg-1 protection at Asupaka and direct trip was received at Kalpakka. 8 to 10 kV voltage difference was observed between R, Y & B phase voltages.
GI-2
3 Tripping of 400kV Guttur-Hiryur line-1
01-07-2019 at 18:02 hrs; 02-07-2019 at 1:20 hrs
Line tripped on operation of over voltage stg-1 protection at Guttur and direct trip was received at Hiryur. However, over-voltage stg-1 operation could not be validated from DR of Guttur end as the volatges were less than O/V pick up
GI-2
4 Tripping of ICT-1&2 at 400/220kV Hoody Substation
01-07-2019 at 09:20 hrs
ICT’s got tripped on operation of back up earth fault protection. CB failure occurred during charging of 220kV Hoody-HSR line at Hoody end. Delayed clearance of fault observed from DR and PMU data.
GI-2
5 Tripping of 400kV Raichur TPS - Bellary TPS line
03-07-2019 at 4:39 hrs, 08-07-2019 at 5:20 hrs
Line tripped on operation of overvoltage stage-1 protection at Bellary TPS end and DT received at Raichur TPS end. From BTPS end. Difference in phase voltages observed from BTPS end DR (Vr-259kV, Vy-245kV and Vb-238kV)
GI-2
6 Tripping of 400kV BTPS-JSW line
08-07-2019 at 2:43hrs
Line tripped on operation of overvoltage stage-1 protection at Bellary TPS end and DT received at JSW. Difference in phase voltages observed at Bellary TPS from DR (Vr-241kV, Vy-257kV and Vb-225kV)
GI-2
7 Tripping of 220kV KTPS - Lower Sileru-1
08-07-2019 at 10:45 hrs
Line tripped on B-phase to earth fault. As per FIR, there was zone-2 operation at KTPS
GI-1
8 Tripping of 400kV Srisailam-Dindi line-2
11-07-2019 at 15:35 hrs
Line tripped on OV St-1 protection operation at Srisailam end and DT was received at Dindi end. From DR of Srisailam end,B phase voltage is observed to be higher than other two phases (Vr-243kV, Vy-244kV and Vb-253kV)
GI-2
9 Tripping of 400kV Nelamangala-Mysore line-2
15-07-2019 at 2:02 hrs
line tripped on operation of OV st-1 protection at Neelamangala end and DT was received at Mysore end. DR of Nelamangala end was not available for validation of OV protection operation
GI-2
10 Outage of Bus-2 at 400kV RYTPP station of APGENCO
18-07-2019 at 3:30 hrs
Bus bar protection of 400kV Bus-2 operated due to malfunctioning of CT supervisory circuit. All elements connected to Bus-2 tripped.
GI-2
11 Tripping of 400/110kV ICT-3&4 at S.V.Chatram S/s of TANTRANSCO
26-07-2019 at 14:07hrs
110kV Bus fault resulted in tripping of ICT-3&4
GI-2
12 Triping of 400KV/220KV JulurupaduICT-1&2
27-07-2019 at 2:31 hrs
ICT’s got tripped on operation of over flux protection
GI-2
Annexure-I
Grid Occurrences to be discussed in the 86thMeeting of PCSC scheduled to be held on 4th September, 2019 3/4
13 Tripping of 400/220 kV ICT-2 at Talaguppa
27-07-2019 at 16:27 hrs
ICT tripped due to mal-operation of OCR relay
GI-2
14 Tripping of 400kV Tippapur-Jangaon line-2
30-07-2019 at 12:23 ; 31-07-2019 at 19:00 hrs; 01-08-2019 at 21:58 hrs
Line tripped on operation of Over voltage stage-1 protection at Tippapur end and Direct trip received at Jangaon. As observed from DR of Tippapur R phase voltage was higher when compared to Y & B phases (Vr-253kV, Vy-231kV, Vb-239kV)
GI-2
15
Tripping of 400kV Krishnapatnam-Nellore line-1 and Unit -2 of Krishnapatnam
01-08-2019 at 21:49 hrs
Triggering incident was R phase to Y phase fault in the line. Unit -2 of SDSTPS also got tripped during the incident.
GI-2
16 Tripping of 400kV KTPS(VII)-Khammam line
01-08-2019 at 23:34hrs; 05-08-2019 at 1:07 hrs
Line tripped on operation of OV st-1 protection at KTPS end and DT receive at Khammam end. From DR of KTPS end, voltages observed are: Vr-249kV, Vy-244kV and Vb-244kV. R-phase voltage 5kV higher than Y & b phase voltage
GI-2
17 Tripping of 400kV Kalpakka-Vemagiri line-1
02-08-2019 at 07:06 hrs
Line tripped due to operation of LBB protection at Kalpaka end
GI-2
18 Tripping of 400/220kV Udumalpet ICT-3
04-08-2019 at 10:34 hrs
Udumalpet ICT-3 HV side and LV side CB tripped due to operation of Over-flux relay at LV side.
GI-2
19
Tripping of 400kV Simhadiri-Kalpakka line-1,2&3; 400kV Kalpakka-Asupaka line-1 & 400kV Kalpakka-Gazuwaka line-2
05-08-2019 at 13:37 hrs
Triggering incident was failure of R-phase LA in 400kV Kalpakka-Asupaka line.
GI-2
20 Tripping of 400kV Suryapet-Kethyreddipalli line-2
05-08-2019 at 21:15 hrs
Line tripped on operation of OV Stg-1 protection at Suryapet end and DT received at Kethyreddipalli. From DR of Suryapet Y phase is observed to be higher than R&B phase (Vr-238kV, Vy-253kV and Vb-241kV)
GI-2
21 400 kV Ramagundam – Hyderabad line-3
08-08-2019 at 3:50 hrs
Line tripped on operation of over voltage protection at Ramagundam. Direct trip was not received at Hyderabad and line was holding. Difference in R, Y and B phase voltage at Ramagundam was observed from DR (Vr-243kV, Vy-254kV, 239kV)
GI-2
22 Tripping of 400/110kV Kamuthi ICT-3
10-08-2019 at 11:00 hrs
ICT tripped due to operation of 110kV Bus bar protection
GI-2
23 Tripping of 400/220kV ICT-1,2,3&4 at N.P.Kunta
12-08-2019 at 12:08 hrs
ICT’s got tripped due to operation of 220kV Bus bar protection
GI-2
Annexure-I
Grid Occurrences to be discussed in the 86thMeeting of PCSC scheduled to be held on 4th September, 2019 4/4
III. Details of Trippings due to Failure or Non-operation of Auto-Reclose:
Sl. No. Element Date & Time Reason
1 Tripping of 220kV Chilakallu-Suryapet line-1
11-07-2019 at 00:33hrs
R phase to Earth fault in the line. At Suryapet end, fault was detected in Zone-1 and at Chillakallu end, fault was detected in Zone-2. A/r not operated at both the ends
2 Tripping of Kaiga-Gutur line -2
22-07-2019 at 17:47hrs
Line tripped on B-phase to earth fault. Line did not auto-reclose.
IV. Details of Trippings due to PLCC mal-operation:
Sl. No. Element Date & Time Reason
1 Tripping of 400kV Nellore-Sriperambadur line-2
01-07-2019 at 03:40 hrs; 28-07-2019 at 3:20 hrs
Direct trip received at both ends.
2 Tripping of 400kV Nizamabad-Dichipally line-2
25-07-2019 at 14:19 hrs
Line tripped on DT receive at Dichipally and line was holding from Nizamabad.
3 Tripping of 400kV Srisailam-Dindi line-2 and 400kV Satenapalli-Srisailam line-2
09-08-2019 at 05:00 hrs
400kV Srisailam-Dindi line-2 tripped on DT receive at Dindi and line was holding from Srisailam. 400kV Satenapalli-Srisailam line-2 on DT receive at both ends
Annexure-I
Meeting
No /
Index
Details of Event Date & Time Reason PCSC Recommendations Utility responsible for
Implementation
Status of Implementation of PCSC Recommendations Remarks Latest Status
(To be filled up by the Constituent)
PGCIL (SR-I) mail received on 27-04-2016:
1. The firmware of REL670 is being upgraded. ------- Completed.
2. The recording of events in msec interval is being taken up with OEM. Henceforth,
for analysis purpose, we will provide larm list which has msec time stamp. --------
Completed.
3. End to end testing of PLCC code transmision and tuning of channels carried out. ----
--- Completed.
4. Procurement of differential protection for 400kV NPS-NLR D/C and 400kV RCR-
RTPS-D/C is under tendering. The legends modified in Event/alarm list. Provision of
diff. relay for all short lines emanating from NPS is being taken up with our
corporate.
----- Pending.
PGCIL(SR-I) RVMD 14-07-2016:
4. The proposal for procurement of Line differential Protections for 400kV Raichur -
RTPS-1 & 2 and 400kV Nellore - NPS - 1 & 2 lines has been approved and tender is
Status of Pending Implementation of PCSC Recommendations as on 19.08.2019 (up to 85th Meeting)
KPTCL Mail dated 27-05-2015:
1. KPTCL has taken action to provide bus bar protection to 220kV buses. --- Pending
2. Over current relay Settings of ICTs to be reviewed by PGCIL.
--- Pending
3. --- Pending
KPTCL Mail dated 29-07-2015:
1. Initial Tendering stage. --- Pending
2. --- Pending
3. --- Pending
KPTCL Mail dated on 23-01-2016:
1. Detailed estimate prepared for taking up the work. CEE, Transmission Zone,
Gulbarga will take up necessary procurement and further execution. --- Pending
2. --- Pending with PGCIL (SR-I).
3. --- Pending
PGCIL (SR-I) Mail dated 14.07.2016:
2. Relay settings of all the stations in SRTS-1 were derived as per Ramakrishna
Commettee recomendations and implemented" --- Completed.
KPTCL Mail dated 16.12.2017:
1) & 3). DPR is approved. Tender is to be called by CEE,TZ Kalaburgi --- Pending
Review Meeting dated 19.12.2017:
1. KPTCL informed that Tenders for providing BBP would be called in Jan-Feb,
2018; Supply of the same is targeted by September, 2018; Erection & Commissioning
is targeted by January, 2019
--- Pending
3. PGCIL (SR-I) informed that time-synchronization of 220 kV side is in place. ---
Completed.
KPTCL mail dated 19.12.2018:
1. DPR preapared for the work of providing Bus Bar Protection to 220kV buses at
Guddadahally is approved. Tender is to be invited by CEE,TZ .
Review Meeting dated 20.12.2018:
1. Tender would be floated in January 2019. Works would be completed in 6 months
16-07-201434/I/6 400/220 kV ICT-1 & 2 at
Munirabad
As reported directional over current relay of ICT’s
operated due to snapping of line jumper in 220kV
Lingapur line.
1. Bus bar protection shall be provided by asset
owner ( i.e KPTCL).
2. Settings for main distance protection &
Overcurrent protection shall be examined and
reviewed.
3. Time synchronization of the Substation shall be
ensured.
KPTCL/
PGCIL (SR-I)
Pending
(with KPTCL)
Multi-Utilities
Complete outage of TPCIL
power station
PendingPGCIL (SR-I),
MEPL, SEL, TPCIL,
NCC
Running units at Thermal Powertech power Station
tripped due to tripping of 400kV Nellore pooling
station (NPS)-TPCIL line and 400kV Nellore pooling
station (NPS)-NCC line
30-12-2015 at
06:02hrs
50/I/2 1.PGCIL (SR-I) to furnish Action Taken Report on the
findings of OEM on relay mal-operation at NPS end
on 400 kV NPS – NCC line to PCSC forum.
2. PGCIL (SR-I) to appropriately configure Station
Event Logger at NPS to record events at msec interval.
3. PGCIL (SR-I) to carry out PLCC end-to-end testing
in coordination with TPCIL for 400 kV NPS –TPCIL
line.
4.PGCIL (SR-I), MEPL, SEL, TPCIL & NCC to take
steps to provide line differential protection at their
respective ends on all 400 kV lines (except Gooty line)
emanating from Nellore Pooling Station, and furnish
an action plan to implement the same.
Annexure-II
Page 1 of 48
PGCIL (SR-I) Mail dated 15.12.2017:
4. LDP relays procurement is under process. Procurement will be completed by Feb-
2018. TPCIL has to give written confirmation for LDP relay procurement. For want
of written confirmation from TPCIL, PGCIL approving authority has withheld the
LDP proposal.
Review Meeting dated 19.12.2017:
4. PGCIL (SR-I) informed that they are waiting for written confirmation from TPCIL
to complete procurement of LDP relays. To this, PCSC forum asked TPCIL to submit
written confirmation to PGCIL (SR-I) by 29.12.2017. PGCIL (SR-I) assured that
with receipt of above confirmation from TPCIL by Dec, 2017, they would be able to
complete the work by FEbruary, 2018.
APTRANSCO informed that they would be able to implement LDP from their &
APGENCO side by April, 2018.
In this regard, PCSC forum made it clear that the recommendation is about providing
LDP as both Main-I & Main-II relays on all stated lines in Nellore Complex, ans
PGCIL (SR-I) mail dated 20.06.2018:
PGCI(SR1) procuring LDP relays for retrofitting of Main-1&2 distance relays.
Tenders are invited from bidders & tender floated. Technical bid opening in this
week.
PGCIL (SR-I) mail dated 10.12.2018:
PO placed on M/s GE & TD India Ltd on 24.09.2018. Supply of relays will be
completed by Jan'2019 and commissioning by Mar'19.
PGCIL (SR-I) mail dated 07.06.2019:
4. PGCIL-SR1: LDP relays (Main-1) commissioned in 400kV NPS-TPCIL-1 Line
during opportunity shutdown. NPS-NCC D/C & NPS-TPCIl D/C lines LDP relay
retrofitting planned in June & July -2019.
In 154th OCC meeting SRLDC/SRPC has advised to re-schedule LDP
commissioning tentatively to Sep/Oct’2019.
Complete outage of TPCIL
power station
PendingPGCIL (SR-I),
MEPL, SEL, TPCIL,
NCC
Running units at Thermal Powertech power Station
tripped due to tripping of 400kV Nellore pooling
station (NPS)-TPCIL line and 400kV Nellore pooling
station (NPS)-NCC line
30-12-2015 at
06:02hrs
50/I/2 1.PGCIL (SR-I) to furnish Action Taken Report on the
findings of OEM on relay mal-operation at NPS end
on 400 kV NPS – NCC line to PCSC forum.
2. PGCIL (SR-I) to appropriately configure Station
Event Logger at NPS to record events at msec interval.
3. PGCIL (SR-I) to carry out PLCC end-to-end testing
in coordination with TPCIL for 400 kV NPS –TPCIL
line.
4.PGCIL (SR-I), MEPL, SEL, TPCIL & NCC to take
steps to provide line differential protection at their
respective ends on all 400 kV lines (except Gooty line)
emanating from Nellore Pooling Station, and furnish
an action plan to implement the same.
57/II/9 Tripping of 400 kV Nellore
(PG) - NPS line-1, 400 kV
Krishnapatnam-Nellore (AP)
lines -1&2 and 400kV NPS -
MEPL line
18-07-2016
at 19:05 hrs
APTRANSCO mail dated on 20-12-2016:
Issue was addressed to the concerned for necessary action.
APTRANSCO mail dated on 24-05-2017:
Meeting was conducted and the relays procurement for all the loctions is under
progress.
APTRANSCO mail dated on 20-10-2017 & 22.11.2017:
Relays procurement for all the locations is under progress.
APTRANSCO Mail dated 15.12.2017:
Technical bids opened. PQ evaluation under progress . Price bids expected to open in
next week.
PGCIL (SR-I) Mail dated 15.12.2017:
LDP relays procurement is under process. Procurement will be completed by Feb-
2018. TPCIL has to give written confirmation for LDP relay procurement. For want
of written confirmation from TPCIL, PGCIL approving authority has withheld the
LDP proposal.
Review Meeting dated 19.12.2017:
PGCIL (SR-I) informed that they are waiting for written confirmation from TPCIL to
complete procurement of LDP relays. To this, PCSC forum asked TPCIL to submit
written confirmation to PGCIL (SR-I) by 29.12.2017. PGCIL (SR-I) assured that
with receipt of above confirmation from TPCIL by Dec, 2017, they would be able to
complete the work by FEbruary, 2018.
APTRANSCO informed that they would be able to implement LDP from their &
APGENCO side by April, 2018.
In this regard, PCSC forum made it clear that the recommendation is about providing
LDP as both Main-I & Main-II relays on all stated lines in Nellore Complex, ans
asked all stakeholders to ensure & comply with the same.
Triggering incident was snapping of Y phase conductor
in 400kV Nellore (PG) - NPS line-1. Distance relay at
Krishnapatnam end over-reached in Zone-1, and
resulted in tripping of 400kV Krishnapatnam – Nellore
(AP) lines - 1&2 from Krishnapatnam end. Distance
relay at MEPL over-reached and resulted in tripping of
MEPL-NPS line from MEPL end.
PGCIL (SR-I), TPCIL, MEPL, SEL, SGPL,
APTRANSCO, APGENCO and SDSTPS to
implement line differential protection on all 400 kV
transmission lines (of length less than 50 km)
emanating from Nellore PS, Nellore (PG) SS, and
Nellore (AP) SS. [It may be noted here that the cut-off
length of 50 km has been specified with a view to
exclude only long transmission lines].
APGENCO/
PGCIL(SR-I)/
TPCIL/MEPL/SEL/
SGPL/ APTRANSCO
Pending
Annexure-II
Page 2 of 48
APTRANSCO Mail Dated 24.04.2018:
ABB make LDP relays inspection is completed. SNEIDER make LDP relays
inspection yet to be completed. Delivery of relays expected in the 1st weak of May-
2018.
APTRANSCO Mail Dated 24.05.2018:
SNEIDER make LDP relays inspection yet to be completed.Delivery of relays
expected in the month of june 2018.
PGCIL (SR-I) mail dated 20.06.2018:
PGCI(SR1) procuring LDP relays for retrofitting of Main-1&2 distance relays.
Tenders are invited from bidders & tender floated. Technical bid opening in this
week.
APTRANSCO Mail Dated 26.06.2018:
ABB make LDP relays are delivered. Schneider make LDP relays inspection to be
offered by the company.
APTRANSCO Mail Dated 25.07.2018:APTRANSCO Mail Dated 25.09.2018:
ABB make LDP relays for Main-1 protection were delivered earlier and schneider
make LDP relays for Main-2 protection are delivered in this week.
APTRANSCO Mail Dated 18.12.2018:
ABB & SCHNEIDER Relays are drawn and available at site. To be commissioned
in coordination with the Alstom (Area) engineers who implemented SAS.
PGCIL (SR-I) mail dated 10.12.2018:
PGCIL(SR-1): PO placed on M/s GE & TD India Ltd on 24.09.2018. Supply of
relays will be completed by Jan'2019 and commissioning by Mar'19
APTRANSCO MAIL DATED 22.01.2019:
The relays are yet to be commissioned.
APTRANSCO mail dated 15.03.2019:
Commissioning of LDP relays scheduled in the month of April 2019.
APTRANSCO mail dated 13.05.2019:
Schnider make P546 LDP relays commissioned in place of Main-1 relays at Nellore
end for 400KV Krishnapatnam feeder on 26/03/19 and for feeder-2 on 27/03/19.
ABB make RED670 relays yet to be commissined in place of Main-2 relays.
PGCIL (SR-I) mail dated 07.06.2019:
PGCIL-SR1: LDP relays (Main-1) commissioned in 400kV NPS-TPCIL-1 Line
during opportunity shutdown. NPS-NCC D/C & NPS-TPCIl D/C lines LDP relay
retrofitting planned in June & July -2019.
In 154th OCC meeting SRLDC/SRPC has advised to re-schedule LDP
commissioning tentatively to Sep/Oct’2019.
APTRANSCO mail dated 19.06.2019:
ABB make RED670 relays testing is under process and will be commissioned in
place of Main-2 relays for Krishnapatnam-1&2 feeders by 30.06.2019 at 400KV
Manubolu SS.
APTRANSCO mail dated 30.07.2019:
ABB make RED670 type LDP relays commissioned in place of Main-2 relays at
Nellore end for 400KV Krishnapatnam feeder-1 on 17/07/19 and for feeder-2 on
15/07/19. The 400KV Krishanapatnam line-2 main-2 relay is in service in
Differential mode. But due to non availability of suitable patch cards, Main-1 of KP-
1 & Main-1&2 of KP-2 feeders are not in differential mode but in Distance mode.
The diffential mode of operation will be kept in service by after purchasing suitable
patch cards.
57/II/9 Tripping of 400 kV Nellore
(PG) - NPS line-1, 400 kV
Krishnapatnam-Nellore (AP)
lines -1&2 and 400kV NPS -
MEPL line
18-07-2016
at 19:05 hrs
Triggering incident was snapping of Y phase conductor
in 400kV Nellore (PG) - NPS line-1. Distance relay at
Krishnapatnam end over-reached in Zone-1, and
resulted in tripping of 400kV Krishnapatnam – Nellore
(AP) lines - 1&2 from Krishnapatnam end. Distance
relay at MEPL over-reached and resulted in tripping of
MEPL-NPS line from MEPL end.
PGCIL (SR-I), TPCIL, MEPL, SEL, SGPL,
APTRANSCO, APGENCO and SDSTPS to
implement line differential protection on all 400 kV
transmission lines (of length less than 50 km)
emanating from Nellore PS, Nellore (PG) SS, and
Nellore (AP) SS. [It may be noted here that the cut-off
length of 50 km has been specified with a view to
exclude only long transmission lines].
APGENCO/
PGCIL(SR-I)/
TPCIL/MEPL/SEL/
SGPL/ APTRANSCO
Pending
Annexure-II
Page 3 of 48
NTPC mail dated 07.12.2017:
1. High set DEFR on 220 KV lines is disabled ----Completed
2. ---- Pending
Review Meeting dated 19.12.2017:
TSTRANSCO informed that the works are under progress, and are targeted to be
completed in 3 months time.
TSTRANSCO MAIL DATED 20.01.2018:
Line Differential Protection will be provided within 3 months i.e., by end of March,
2018.
TSTRANSCO MAIL DATED 20.04.2018:
Line Differential Protection relays are under procurement and will be provided by end
of May, 2018.
TSTRANSCO MAIL DATED 17.05.2018:
Line Differential relays will be supplied to site by manufacturer by end of May, 2018
and erection will be completed by end of June, 2018.
TSTRANSCO MAIL DATED 12.10.2018:
Inspection of the relays is completed and the relays are received at stores. Relays are
to be drawn and commissioned. Work is expected to be completed by end of
TSTRANSCO MAIL DATED 22.01.2019:
Relays will be commissioned by end of February, 2019.
TSTRANSCO MAIL DATED 22.01.2019:
Replacement of porcelain insulators with Polymer insulator for 4 Km radius ( in
Chennai area) from NCTPS.2 in 400kV SVCM & Alamathy feeders were completed.
TSTRANSCO mail dated 22.06.2019:
2. Relay erection work is under progress and will be completed by end of July, 2019.
NTPC-Ramagundam/
TSTRANSCO
Pending66/ II/ 10 Tripping of 400/ 220 kV
ICT’s – 3 & 4 at
Ramagundam STPS
11-06-2017
at 19:46hrs
Triggering incident was failure of 220 kV
B-phase LA in ICT-3 LV extension feeder (220KV
line-2) at Malayalapalli substation
1. NTPC to disable high-set of DEFR on the 220 kV
lines emanating from their Ramagundam STPS.
2. NTPC/ TSTRANSCO to provide Line Differential
Protection (with or without pilot) on 220 kV
Ramagundam – Malayalapalli lines – 1 & 2 & 3.
Annexure-II
Page 4 of 48
69/I/2 Complete outage of 400kV
TPCIL station
30-10-2017 at
21:37 hrs
400kV TPCIL - Nellore line-1 got tripped at TPCIL
end during failure of LA of Station Transformer-2 at
TPCIL. Running Units at TPCIL got tripped due to loss
of evacuating line. 400kV TPCIL - Nellore PS line-2
was under emergency shutdown
1. TPCIL to configure DEF protection such that it
remains in blocked condition as long as Distance
Protection is active, and becomes active only when
distance protection does not pickup.
2.PGCIL (SR-I) to ensure healthiness of Carrier
communication, and the set PUP mode of carrier aided
scheme operates reliably on TPCIL lines 1 & 2.
TPCIL/
PGCIL (SR-I)
Review Meeting dated 19.12.2017:
PGCIL (SR-I) informed that they are waiting for written confirmation from TPCIL to
complete procurement of LDP relays. To this, PCSC forum asked TPCIL to submit
written confirmation to PGCIL (SR-I) by 29.12.2017. PGCIL (SR-I) assured that
with receipt of above confirmation from TPCIL by Dec, 2017, they would be able to
complete the work by February, 2018.
APTRANSCO informed that they would be able to implement LDP from their &
APGENCO side by April, 2018.
In this regard, PCSC forum made it clear that the recommendation is about providing
LDP as both Main-I & Main-II relays on all stated lines in Nellore Complex, ans
asked all stakeholders to ensure & comply with the same.
PGCIL (SR-I) mail dated 20.06.2018:
2. PGCI(SR1) procuring LDP relays for retrofitting of Main-1&2 distance relays.
Tenders are invited from bidders & tender floated. Technical bid opening in this
week.
PGCIL (SR-I) mail dated 10.12.2018:
2. PO placed on M/s GE & TD India Ltd on 24.09.2018. Supply of relays will be
completed by Jan'2019 and commissioning by Mar'19.
Review Meeting on 20.12.2018 & 27.06.2019:
Pending
APTRANSCO maild ated 30.01.2018:
1. Pending...
2.A/R scheme on 400kV Kurnool (PGCIL) feeder-2 will be checked after getting LC.
APTRANSCO maild ated 24.04.2018 & 24.05.2018 & 26.06.2018:
1. Pending...
2. B Ph auxilary trip relay is found defective. The same is to be replaced by M/S
PGCIL. Ii) PD relay event is configured in the EL as per the recommendation.
PGCIL (SR-I) mail dated 20.06.2018:
1. ---Pending
2. PGCIl(SR-1): B-Ph auxiliary relay problem rectified at Narnoor end by replacing
relay contact. ---Completed
APTRANSCO Mail Dated 18.12.2018:
1) Bays and lines pertains to PGCIL .
2) ---Completed.
PGCIL (SR-I) mail dated 20.12.2018:
1) PO placed on M/s GE & TD India Ltd on 24.09.2018. Supply of relays will be
completed by Jan'2019.
APTRANSCO MAIL DATED 22.01.2019:
Pending [with PGCIL (SR-I)]
PGCIL (SR-I) mail dated 07.06.2019:
PGCIL(SR-1):
This issue of retrofitiing of distance relays with LDP relays in Kurnool(PG) –
Kurnool(AP) D/C lines has been discussed with our management. Our management is
seeking approval for the same. You are requested to takeup this LDP issue in next
TCC meeting.
Tripping of 400 kV
Kurnool(PG) – Kurnool(AP)
line-2
Pending [with
PGCIL (SR-I)]
APTRANSCO/
PGCIL (SR-I)
69/III/3 02-10-2017 at
02:03 hrs
1) PGCIL (SR-I) and APTRANSCO to provide for
Line Differential Protection as both the Main
protections on 400 kV Kurnool (AP) – Kurnool (PG)
lines 1 & 2 lines.
2) APTRANSCO to furnish an action taken report
w.r.t. resolving A/R non-operation at Kurnool-AP end
for the subject trippings and configure EL for capturing
PDR operation at their 400 kV Kurnool-AP SS.
Line tripped on B-ph to ground fault. A/R was
unsuccessful at both Kurnool (AP) and Kurnool (PG)
ends.
Annexure-II
Page 5 of 48
APTRANSCO maild ated 15.12.2017:
APTRANSCO would extend support and requirements if any ,for the rectification
proposed by KPTCL.
Review Meeting dated 19.12.2017:
It was noted that the original Gooty - Lingapur line got LILOed at BTPS, Alipura,
and Ragulapadu. It was also noted that Phase Discrepancy is being observed in
Ragulapadu - Alipira section only. When enquired about the same, KPTCL informed
that they would examine the issue in detail, and would inform the action lan proposed
by next PCSC-71 meeting. On this, APTRANSCO was also asked to render all help
required from their side to KPTCL.
APTRANSCO maild dated 30.01.2018:
APTransco world extend required support .
APTRANSCO maild dated 24.04.2018 & 24.05.2018 & 26.06.2018:
AP Transco would extend required support for attending, phase discrepancy issue in
ragulapadu-Alipura line by KPTCL.
APTRANSCO Mail Dated 25.07.2018:
To be attended by KPTCL as discussed in 75th PCSC meeting.
KPTCL mail dated 19.12.2018:
Phase mis match issue is to be sorted out jointly by KPTCL/ APTRANSCO/ KPCL.
Review Meeting on 20.12.2018:
PCSC forum decided that concrete action in this respect to be initiated in 2 months by
KPTCL alongwith APTRANSCO.
APTRANSCO MAIL DATED 22.01.2019:
Pending [with KPTCL ]
Review Meeting on 27.06.2019:
KPTCL informed that the work is expected to be completed by August 2019.
1) TANTRANSCO to provide double-bus operation at
their 230 kV Thiruvalam SS.
2) APTRANSCO to replace the existing static relays
with suitable numerical relays for various line
protections at their 220 kV Chittoor SS.
Pending
[with KPTCL ]
Tripping of 230 kV
Thiruvalam - Chittoor line
76/II/9 1) TANTRANSCO Mail dated 29.08.2018 & 11.09.2018:
Material supplied and work to be taken up ---Pending
2) APTRANSCO Mail dated 24.09.2018:
The static relays were replaced with Numerical relay on all 220 kV feeders at 220 kV
SS chittoor.---Completed
TANTRANSCO Mail dated 11.12.2018:
Due to space constraint, the equipments could not be erected.
Review Meeting on 20.12.2018:
In view of Tiruvalam being inter-state sustation, TANTRANSCO was asked to
prvodie double-bus operation at their 230 kV Tiruvalam SS.
APTRANSCO MAIL DATED 22.01.2019:
Pending [with TANTRANSCO]
TANTRANSCO MAIL DATED 23.01.2019 & 19.03.2019:
Feasibility for providing hybrid breaker / shifting of bays will be studied & action
will be taken. Time upto Sep 2019
TANTRANSCO MAIL DATED 13.06.2019:
1. Bus segregation will be ensured by providing bus coupler bay by extending the
existing Bus.Time line 31.12.2019.
TANTRANSCO mail dated 18.07.2019 & 26.07.2019:
1. Bus segregation will be ensured by providing bus coupler bay by extending the
existing Bus.Time line 31.12.2019.
Pending [with
TANTRANSCO]
TANTRANSCO/
APTRANSCO
13-06-2018 at
18:55hrs
Y-phase to earth fault occurred in line. At 230 kV
Tiruvalam end, breaker was under lockout leading to
operation of LBB protection.
69/III/7 Tripping of 220 kV
Ragulapadu – Alipura line
12-10-2017 at
01:30 hrs
KPTCL and APTRANSCO to sort out issues relating
to incongruence in denoting R, Y, B phases of the
electric supply on their respective sides.
APTRANSCO/ KPTCLLine tripped on B-Ph to earth fault. A/R was successful
at Regulapadu and breakers at Alipura end got tripped.
Annexure-II
Page 6 of 48
KPTCL mail dated 19.12.2018:
3). Nagzari-Bidnal PLCC link is healthy --- Completed.
1.--- Pending
2. --- Pending
Review Meeting on 20.12.2018:
1. & 3. Completed
2. Pending
KPCL mail dated 24-12-2018:
1) --- Completed
2) Proposal will be taken up for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850 shortly, after availing
necessary admnistrative approval...Pending
3) Completed
KPCL mail dated 23.01.2019:
1. Completed
2. Letter addressed to site to take up the proposal for replacement of PZ1000 line
distance relays.KPCL mail dated 23.03.2019:
1). COMPLETED
2) Proposal will be taken up for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Prepration of
specification is under progress.
3) COMPLETED
KPCL mail dated 13.05.2019:
1) & 3) Completed
2) Budgetary offer obtained for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Preparation of estimation
and specification is under progress.
KPCL mail dated 25.06.2019:
1) & 3) Completed
2) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval of
NLDC for DPR is awaited. Further, availing administrative approval for issue of NIT
for replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 and preparation of estimation and specification is
under progress.
Review Meeting on 27.06.2019:KPCL mail dated 16.07.2019:
1) & 3) Completed
2) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval of
NLDC for DPR is awaited. However, administrative approval for issue of NIT for
replacement of existing PZ1000 relays with new version Numerical Line protection
relays having IEC61850 obtained. Preparation of technical specification is under
progress.
17-09-2018 at
14:37hrs
Complete outage of 220 kV
Nagjheri PH and 220/110 kV
Ambewadi Substation.
78/I/2 PendingKPCL/ KPTCL1. SLDC/KPTCL to be pro-active in issuing necessary
directions that help in expeditious restoration of the
tripped lines based on the prevailing conditions and
grid security.
2.KPCL to implement A/R enabled on all 220 kV lines
emanating from their 220 kV Nagjheri PH, with the
help of KPTCL, by December, 2018. In the event of
non-amenability of the existing PZ1000 relays in
providing A/R feature, KPCL shall take steps to
retrofit them with suitable relays that support A/R.
3. KPTCL to restore PLCC carrier communication on
220 kV Nagjheri – Bidnal line at the earliest
220kV lines connected to Nagjheri PH got tripped due
to successive transient faults. Running Units #3 and #4
at Nagjheri got tripped on over frequency protection
operation due to loss of evacuating lines resulting in
complete outage of 220 kV Nagjheri. 220 kV Nagjheri
being the only source to 220kV Ambewadi station,
since 220kV Ambewadi Narendra line 1&2 were under
shutdown during antecedent condition, tripping of
Units at 220 kV Nagjheri resulted in the loss of supply
to 220 kV Ambewadi SS.
Annexure-II
Page 7 of 48
Review Meeting on 20.12.2018:
1. KPTCL I formed that SPS scheme finalisation shall be completed in one month
time --- Pending
KPCL mail dated 24-12-2018:
2) Time delay of operation is not changed. However, the external NCT is used for
REF protection against earlier internal NCT for REF, to avoid tripping due to
malopration --- Completed.
KPCL mail dated 23.01.2019:
1) It shall be reviewd and Implemented by KPCL in coordination with KPTCL.
2)....Completed.
KPCL mail dated 23.01.2019:
1) It shall be reviewd and Implemented by KPTCL in coordination with KPCL.
KPCL mail dated 10.05.2019 & 25.06.2019:
1) Letter addressed to KPTCL RT dated: 25.03.2019 for review and implementation
of SPS at NPH. Reply is awaited.
Review Meeting on 27.06.2019:
1. KPTCL informed that Nagjheri SPS has to be studied in the event of configuration
changes and outcome of the same will be intimated soon .KPCL mail dated 16.07.2019:
1) Letter addressed to KPTCL RT dated: 25.03.2019 for review and implementation
of SPS at NPH. Reply from KPTCL is awaited.
2)Completed.
TANTRANSCO Mail dated 11.12.2018:
1. TANTRANSCO: Estimate sanctioned for replacement of defective isolator status
feedback. Work under progress. ......Pending
2.Earth value of 110kV earthmat has been improved & 230kV side earthmat work
under progress. Lightning mask earthing renovation under execution............Pending
3.......Pending
APTRANSCO Mail Dated 18.12.2018:
Relays settings reviewed and need to be revised due to change of line length DR &
EL's of Main-1 (P444) relay configured properly. Main-2 (D60) relay to be
configured.
Review Meeting on 20.12.2018:
1 & 2). TANTRANSCO informed that Work will be completed by March 2019.
3. APTRANSCO informed that work will be completed by February 2019.
APTRANSCO MAIL DATED 22.01.2019:
Collecting the details of adjacent feeders connected to Gummadipudi for computing
revised relay settings.
TANTRANSCO MAIL DATED 23.01.2019:
Isolator status will be ensured by March 2019
TANTRANSCO/
APTRANSCO
05-10-2018 at
00:42 hrs
Complete outage of 230/ 110
kV Gummidipoondi
Substation
78/II/16
1) TANTRANSCO to take steps to implement multi-
bus, multi-zone operation (Double-bus operation) at
their 230 kV Gummidipooindi SS by December,
22018.
2) TANTRANSCO to check if the Gummidipoondi
substation is adequately protected from lightning-
strokes by providing requisite no. of lightning masts
and/ or earth-wire caging.
3) APTRANSCO was asked to verify & correct the
settings employed for distance protection at Sullurpeta
and configure DR’s & EL’s of all Protection Relays at
their Supllurpet SS properly for recording only the
mandated protections & digital signals.
Pending [with
TANTRANSCO]
KPTCL/ KPCL1)KPTCL to examine the reasons for tripping of more
than one Unit (Units – 3 & 6) on SPS operation at
Nagjheri PH during subject trippings, and furnish a
report on the same along with remedial action taken to
PCSC forum.
2)KPCL to employ a suitable time delay of 50 – 60
msec in operation of REF protection for the GT of Unit-
2 at their Nagjheri PH.
Triggering incident was B-E fault in 220 kV Nagjheri -
Ambewadi line-1. As per the information received,
after tripping of 220 kV Naghjeri - Ambewadi line-1,
220 kV Naghjeri Ambewadi line#2 got overloaded.
This resulted in the tripping of Nagjheri Generating
Units #3 and 6 on SPS operation. At the same time,
Unit #2 got tripped on REF operation.
PendingMultiple trippings at 220kV
Nagjheri PH
Triggering incident was B-phase fault at 230kV
Gummidipoondi Substation due to which 230kV Bus-1
Bus-bar protection operated. 230kV Gummidipoondi
Station was under single bus operation, hence
operation of Bus-bar protection resulted in tripping of
all connected elements.
31-08-2018
at 11:49 hrs
79/I/2
Annexure-II
Page 8 of 48
APTRANSCO mail dated 15.03.2019:
3. Revised relay settings were implemented on 16/02/2019 ---Completed
TANTRANSCO MAIL DATED 19.03.2019:
New 230kV isolators have been allotted for replacement of defective isolators. Hence
time line requested upto June.2019.
TANTRANSCO MAIL DATED 13.06.2019:
1. New 230kV isolators have been allotted for replacement of defective isolators.
Hence time line requested upto Sep.2019.
Review Meeting on 27.06.2019:
1. New 230kV isolators have been allotted for replacement of defective isolators.
Hence time line requested upto Sep.2019.
2. & 3. Completed
TANTRANSCO mail dated 18.07.2019 & 26.07.2019:
1. 1New 230kV isolators have been allotted for replacement of defective isolators.
Hence time line requested upto Sep.2019
81/IV/3 Tripping of 400 kV
Warangal - Bhoopalapalli
line-2
15-12-2018 at
20:42 hrs
Line tripped at Bhoopalapalli end only and was holding
from warangal s/s. FIR, DR and EL of Bhoopalapally
were not furnished.
For the line under consideration, the following shall be
carried out by TSGENCO in coordination with PGCIL
(SR-I):
(i) End-to-end communication for DT/ permissive &
other signals may be ensured by testing at both the
ends.
(ii) Healthiness of PLCC system components
(hardware and software) at both ends shall be checked
and faulty components shall be repaired/ replaced.
TSGENCO/ PGCIL (SR-
I)
PGCIL (SR-I) mail dated 07.06.2019:
PGCIL-SR1: Presently WGL-Bhopalapalli-2 line PLCC Ch-1 is unhealthy same was
informed to TSGENCO for rectification. The Ch-1 is out of service from last 50 days
onwards. Both ends PLCC belongs to TSGENCO
TSGENCO mail dated 24.06.2019:
TSGENCO is cordinating with TSTRANSCO for testing of End-to-End
communication for DT/permissive & other signals; checking of Healthiness of PLCC
system components and also for replacing of faulty components .
Review Meeting on 27.06.2019:
TSGENCO informed that PLCC has to be replaced and will be done by December
2019.
Pending [with
TSGENCO]
83/I/1 Complete outage of 230kV
Veeranam substation of
TANTRANSCO
11-03-2019
at 00:55Hrs
Triggering incident was Y-phase CT blast in 230kV
Tirunelvelli (Abhishekpatty) – Veeranam Ckt-1.
230kV Trirunelvelli – Veeranam Ckt-1 and 2 tripped.
Two faults were observed from the PMU plot. During
the second fault, delayed fault clearance of 400ms was
observed. As reported, other connected feeders 230kV
Veeranam – Kodikur ckt-1&2 and 230kV Veeranam –
Kayathar tripped on Zone -2 protection.
1. TANTRANSCO is recommended to submit action
plan to provide Multi-Bus operation/ Hybrid breakers
at 230kV Veeranam SS with clear timelines.
2. TANTRANSCO to revise the distance zone settings
at Tiruneveli SS for 230kV Veeranam – Tirunelveli
line to overcome the problem of relay overreach and
share the same with SRPC.
3. TANTRANSCO to take definite measures ensure
the time synchronization of relays at Tirunelveli end.
4. TANTRANSCO to submit equipment failure report
of the failed CT to CEA.
TANTRANSCO TANTRANSCO MAIL DATED 13.06.2019:
1.Provision of bus coupler breaker is not feasible due to space constaint.
2&3. Tirunelveli end maintained by PGCIL.
4. Report will be sent.
Review meeting on 27.06.2019:
1.Provision of bus coupler breaker is not feasible due to space constaint.
2. Will be informed
3. Time synchronisation will be ensured.
4. Report will be sent.
TANTRANSCO mail dated 19.07.2019:
1.Provision of bus coupler breaker is not feasible due to space constaint.
2&3. Tirunelveli end maintained by PGCIL.
4. Report sent to CEA.
Pending[PGCIL-
SR-II]
TANTRANSCO/
APTRANSCO
05-10-2018 at
00:42 hrs
Complete outage of 230/ 110
kV Gummidipoondi
Substation
1) TANTRANSCO to take steps to implement multi-
bus, multi-zone operation (Double-bus operation) at
their 230 kV Gummidipooindi SS by December,
22018.
2) TANTRANSCO to check if the Gummidipoondi
substation is adequately protected from lightning-
strokes by providing requisite no. of lightning masts
and/ or earth-wire caging.
3) APTRANSCO was asked to verify & correct the
settings employed for distance protection at Sullurpeta
and configure DR’s & EL’s of all Protection Relays at
their Supllurpet SS properly for recording only the
mandated protections & digital signals.
Pending [with
TANTRANSCO]
Triggering incident was B-phase fault at 230kV
Gummidipoondi Substation due to which 230kV Bus-1
Bus-bar protection operated. 230kV Gummidipoondi
Station was under single bus operation, hence
operation of Bus-bar protection resulted in tripping of
all connected elements.
79/I/2
Annexure-II
Page 9 of 48
83/I/6 Complete outage of 220kV
Hubli substation of KPTCL
and 220kV
Nagjheri Power station of
KPCL
10-04-2019
at 18:09Hrs
Y and B-phase earth isolator switch blades of 220kV
Hubli-Bidnal ckt-1, got closed due to failure of locking
mechanism during heavy wind and rain
conditionsresulting in bus fault. Bus bar protection
operated and all connected elements tripped. There was
complete loss of supply at 220kV Hubli station since
the station was on single bus operation. At thesame
time, 220kV Nagjheri-Ambewadi ckt-1 and 220kV
Nagjheri – Bidnal tripped on overcurrent
protection. Since 220kV Nagjheri – Ambewadi ckt-2
and 220kV Nagjheri-Kodasalli ckt-1 &2 wereunder
shutdown in the antecedent due to maintenance,
running units #1,4,5 and 6 tripped due to
loss of evacuating lines. This resulted in complete loss
of supply at 220kv Nagjheri station.
1. KPTCL is recommended to revise the SPS at
Nagjheri, (to accommodate a new condition with high
flow and low time delay) in consultation with SRPC
and SRLDC.
2. KPCL in coordination with KPTCL is recommended
to provide at least one main protection as carrier aided
three zone distance protection on the 220kV lines
emanating from Nagjheri GS.
KPTCL/ KPCL KPCL mail dated 25.06.2019:
2) Carrier aided protection is enabled on all 220kV lines emanating from NPH
___Completed
Review Meeting on 27.06.2019:
1. KPTCL informed that Nagjheri SPS has to be studied in the event of configuration
changes and outcome of the same will be intimated soon
KPCL mail dated 16.07.2019:
1. under progress
2. Completed
Pending
83/II/9 Tripping of 400 kV
GUTTUR - NARENDRA -1
10-03-2019 at
18:03hrs
Line tripped on operation of overvoltage stage-1
protection at Guttur end and DT received at Narendra
end. Voltages at Guttur end: Vr-254kV, Vy-252kV,
Vb-246kV. As per voltage grading, 400kV Guttur
Narendra line-2 should trip first.
PGCIL (SR-II) to submit action plan regarding
replacement of CT’s for 400Kv Guttur Narendra line -
1 at Guttur end. PGCIL (SR-II) to sort out the time
sync issues in DR and EL at Narendra end.
PGCIL (SR-II)/ KPTCL PGCIL (SR-I) mail dated 07.06.2019:
Line belongs to PGCIL(SR-2)
Review meeting on 27.06.2019:
PGCIL(SR-II) informed that R & Y ph CVT replaced on 25.05.2019. Time
syncronisation has to be attended by KPTCL.
Pending
23-03-2019 at
04:41 hrs
24-03-2019 at
02:32 hrs
25-03-2019 at
01:19 hrs
84/I/1 Complete outage of 230kV
NCTPS Generating Station
of TANGEDCO
18-05-2019 at
04:39 hr.
Triggering incident was Y phase to Earth fault in 220
kV NCTPS Tondiarpet line-2. Due to mal-operation of
LBB protection (of Tondiarpet line-2) at NCTPS end,
all the connected elements of bus zone-3 got tripped.
Due to loss of evacuating lines, running units at
NCTPS unit#1 and 2 got tripped.
1.TANTRANSCO may take immediate measures to
attend the problem in LBB wiring that is extending trip
during A/R within one month.
2. TANTRANSCO is recommended to send a detailed
report regarding the A/R status (availability
/enabling)on all lines emanating from 230kV NCTPS
GS and enable A/R in all lines emanating from 230kV
NCTPS GS.
3.TANGEDCO in coordination with TANTRANSCO
may take definite measures to ensure time
synchronization of all relays with GPS signal at
NCTPS end and remote ends at the earliest.
4. It was also suggested that possibility of backing
down of generation, in the event of unavailability of
many feeders, in particular when radial feeders only
are in service, may be looked at.
TANGEDCO/
TANTRANSCO
TANTRANSCO mail dated 26.07.2019:
1 & 2.Inbuilt LBB function will be enabled in the new distance relays.
3. will be ensured.
4.230kV Kilpauk was operated radially for avoid overloading in the adjacent feeders
due to cable fault in the area.Normally all feeders are operated as grid feeders.
Pending
APGENCO/
APTRANSCO
APTRANSCO mail dated 19.06.2019:
3. Line Insulator stacks were replaced with SRC insulators at location Nos.4,5,6 for
Krishanpatnam-1 on 26/03/2019 and Krishanpatnam-2 on 27/03/2019.--------------
Completed.
Review Meeting on 27.06.2019:
1. APGENCO representative did not attend the meeting. APGENCO is requested to
furnish the status at the earliest.
83/II/17 Pending [ with
APGENCO]
Tripping of 400kV
Krishnapatnam – Nellore ckt-
1
Feeder tripped due to severe tracking on line insulator
stacks.
1. APGENCO to inform PCSC forum the following:
Status of A/R in 400kV Krishnapattnam – Nellore
line-1 at Krishnapattanam end, if A/R is not enabled
APGENCO shall implement 1-ph ‘lead-follow’ A/R
scheme at Krishnapattanam.
The reason for tripping of Unit-2, along with the line
tripping on 24.03.2019.
2. APGENCO in consultation with APTRANSCO to
explore the possibility of providing Line Differential
Protection (LDP) for the line.
3. APTRANSCO is recommended to replace the
insulators of the line with polymer insulators.
Annexure-II
Page 10 of 48
84/I/2 Complete outage of 230kV
NCTPS Generating Station
of TANGEDCO
19-05-2019 at
22:44 hr.
230kV lines connected to NCTPS got tripped due to
fault in lines. Running units#1,2 and 3 at 230kV
NCTPS also got tripped due to loss of evacuating lines.
1. TANGEDCO in coordination with TANTRANSCO
to take definite measures to ensure time
synchronization of all relays with GPS signal at
NCTPS end and remote ends at the earliest.
2.The PCSC noted frequent jumper cut/conductor snap
instances in the area, of late; accordingly, it was
suggested to have adequate condition monitoring and
preventive maintenance measures.
3.TANTRANSCO to communicate
(i) the schedule of replacement of balance porcelain
insulators with polymer insulators in evacuation lines
from NCTPS.
(ii) schedule of insulator washing
4.NCTPS /TANGEDCO to inform regarding house
load operation capability of Generators at NCTPS.
TANGEDCO/
TANTRANSCO
TANTRANSCO mail dated 26.07.2019:
2& 3.wedge connector have been provided in order to avoid jumbercut.
4. Replacement of porcelain insulators by polymer insulatos in all 230kV & 400kV
feeders in North Chennai area has been completed
Pending
84/II/4 Tripping of 230kV Sulurupet-
Gumudipoondi line
11-04-2019 at
16:05 hr.
Triggering incident was B-N fault in 230kV
Gummudipoondi-NCTPS line. 230kV Sulurupet -
Gummudipoondi line tripped on operation of zone-2
distance protection at Sulurpet end and reverse zone
protection at Gummudipoondi end.
1.TANTRANSCO to check the resistive and reactive
reach settings of 230kV Gummudipoondi-NCTPS line
at Gummidipoondi end.
2. APTRANSCO to ensure time synchronization of
DR and EL at Sulurupet end. Also in coordination with
TANTRANSCO sort out the time synchronization
issue in 230kV Sulurupet-Gumudipoondi line.
3. TANTRANSCO to check the SOTF settings at
Gummidipoondi end for 230kV Gummudipoondi-
NCTPS line .
TANTRANSCO/
APTRANSCO
APTRANSCO mail dated 30.07.2019:
2. GPS not available at 220KV Sullurpet SS.Manually set the timing on 29/07/2019 -
- Completed
TANTRANSCO mail dated 26.07.2019:
1. & 3. Will be reviewed
Pending [ with
TANTRANSCO]
84/II/19 Tripping of 400/220 kV ICT-
1 atCuddapah
03-05-2019 at
23:39 hr.
ICT-1 Tripped on operation of APTRANSCO 220 kV
Bus Bar relay (96 trip relay). Fault reported in 220 kV
Cudappah-Renigunta line
1. PGCIL (SR-I) to submit the high set settings of
ICT’s at Cuddapah. Since the static relay in which
high set is enabled has no provision to provide time
delay, ICT high set shall be enabled from numeric
relay and sufficient time delay shall be provided for
highset operation.
2.APTRANSCO to check the Busbar operation at 220
kV Cuddapah SS and submit a report regarding the
same.
3. PGCIl (SR-I) to inform the methodology adopted for
calculating high set settings of ICT’s. Also due to
changes in system configuration at Cuddapah in recent
future revision of set points shall be taken up.
PGCIL (SR-I)/
APTRANSCO
APTRANSCO mail dated 30.07.2019:
2. The 220KV GE make B90 type Bus Bar relays tested on 23/07/19 and found
healthy. The report submitted vide mail dated 29.07.2019 - Completed
Pending [ with
PGCIL (Sr-1)
84/II/22 Tripping of 400kV
Khammam-Mamidapalli line-
1
09-05-2019 at
02:40 hr.
Line tripped on mal-operation of Reactor differential
protection and DT sent to Khammam.
TSTRANSCO in coordination with PGCIL (SR-I) to
ensure time synchronization of relays at Mamidapalli
end with Khammam end in 6 months’ time.
TSTRANSCO/ PGCIL
(SR-I)
Yet to be informed Pending
Annexure-II
Page 11 of 48
84/II/29 Frequent tripping of 220 kV
KTPS –Lower Sileru line
01-05-2019 at
16:04 hr.
04-05-2019 at
14:48 hr.
05-05-2019 at
11:29 hr.
06-05-2019 at
13:14 hr.
09-05-2019
at13:58 hr.
12-05-2019
at11:10 hr.
15-05-2019
at21:05 hr.
26-05-2019
at15:36 hr.
29-05-2019
at21:26 hr.
B-N FAULT
B-N FAULT
B-N FAULT
B-N FAULT
R-N FAULT
R-B FAULT
R-B FAULT
B-N FAULT
R-B FAULT
It was noted that no representative of APGENCO
attended the meeting.
For the subject line, the following shall be carried out
by TSGENCO in co-ordination with APGENCO:
(i) End-to-end communication for DT/ permissive &
other signals may be ensured by testing at boththe
ends.
(ii) Healthiness of PLCC system components
(hardware and software) at both ends shall be checked
and faulty components shall be repaired/ replaced.
APGENCO in coordination with TSGENCO to
ensure frequent patrolling and proper maintenance of
ROW by attending all tree clearance issues.
APGENCO/
TSGENCO
Yet to be informed Pending
85/II/3 Tripping of 400kV Kurnool-
Srisailam line
17-05-2019 at
14:10 hrs
line tripped only at Srisailam end on Zone-3 distance
protection operation during Y phase to B phase fault in
220kV NarnoorSomayajulapalli line-1
1. TSGENCO is recommended to modify the PSL
logic (Srisailam end to trip for faults occurring in Zone-
2 and Zone-3 with respective time delays except for
PUR scheme if adopted ) in 1 month time to avoid
occurrence of any such unwarranted trippings in future.
2. APTRANSCO to ensure time synchronization of
relays at 220kV Somayajulapalli SS.
TSGENCO/
APTRANSCO
Yet to be informed Pending
85/II/14 Tripping of 230kV Theni-
Sabarigiri line
29-05-2019 at
18:39 hrs
3 phase to earth fault occurred in line. Tripped on
ground over current protection 67N at Sabarigiri and
Zone-2 at Theni end.
For the subject line, the following shall be carried out
by TANTRANSCO in coordination with KSEBL:
(i) End-to-end testing for DT/ permissive & other
signals may be ensured by testing at both the ends.
(ii) Healthiness of PLCC system components (
hardware and software) at both the ends shall be
checked and faulty components shall be repaired/
replaced .
TANTRANSCO/
KSEBL
Yet to be informed Pending
85/II/17 400 kV Ghani – Narnoor line-
1, 400 KV Jamalamadugu-
Kurnool line-1, 765/400 kV
ICT-1&2 at Kurnool
30-05-2019 at
00:48 hrs
Triggering incident was Y-ph to B-ph fault in the
400kV NarnoorJammalamadugu line-1 & 2 due to
falling of Y-ph CVT jumper on B-ph during heavy
wind. At the same time, 400kV GhaniNarnoor tripped
only at Ghani end on operation of Zone-1 distance
protection. 765/400 kV ICT-1 & 2 at Kurnool PG also
got tripped on HV side Directional Overcurrent (DOC)
protection.
1. APTRANSCO is recommended to sort out the issues
with their distance protection relay (7SA522) which
maloperated and caused unwarranted tripping of
400kV Ghani – Narnoor line-1. The time
synchronization of relays at Ghani end also shall be
ensured.
2.PGCIL (Sr-1) is recommended to submit a detailed
report regarding operation of ICT Buchholz relay for
through fault conditions along-with remedial measures
suggested by OEM.
APTRANSCO/ PGCIL
(SR-1)
Yet to be informed Pending
85/II/20 Tripping of 220kV Idukki-
Udumalpet line
05-06-2019 at
15:13 hrs
Triggering incident was R-Y-Earth fault in the
line. Carrier aided protection not operated at
Udumalpet end.
For the subject line, the following shall be carried out
by TANTRANSCO in coordination with KSEBL:
(iii) End-to-end testing for DT/ permissive & other
signals may be ensured by testing at both the ends.
(iv) Healthiness of PLCC system components (
hardware and software) at both the ends shall be
checked and faulty components shall be repaired/
replaced .
KSEBL/
TANTRANSCO
Yet to be informed Pending
85/II/26 Tripping of 400kV Vemagiri-
GMR line-1&2
14-06-2019 at
09:33 hrs
Line-1 tripped on Y-Phase to earth fault due to Y-
Phase LA failure at Vemagiri end. Line-2 tripped at
GMR end only
1. APTRANSCO is recommended to submit
Equipment failure report (LA failure) to CEA.
2.GMR is recommended to submit a report regarding
tripping of 400kV Vemagiri-GMR line-2 at GMR end
along-with the related tripping files.
APTRANSCO/ GMR Yet to be informed Pending
Annexure-II
Page 12 of 48
02-06-2019
at 15:30 hrs
R-phase to earth fault occurred in line. Auto-reclose
was successful at Lower sileru end. A/r is not enabled
at KTPS.
02-06-2019 at
15:30 hrs
R-phase to earth fault occurred in line. Auto-reclose
was successful at Lower sileru end. A/r is not enabled
at KTPS.
09-06-2019 at
11:58 hrs
B-phase to earth fault occurred in line. Zone-2
operated at KTPS and Earth fault at Lower sileru.
Suspected high resistance fault.
12-06-2019 at
14:23 hrs
Y-phase to earth fault occurred in line. Auto-reclose
was successful at Lower Sileru end. A/r is not enabled
at KTPS
85/IV/2 Tripping of 400kV
Khammam-Mamidapally line-
1
27-05-2019 at
18:16 hrs
Line tripped only at Mamidapally end due to suspected
PLCC maloperation
For the subject line, the following shall be carried out
by TSTRANSCO in coordination with PGCIL(SR-I):
(i)End-to-end testing for DT/ permissive & other
signals may be ensured by testing at both the ends.
(ii)Healthiness of PLCC system components (
hardware and software) at both the ends shall be
checked and faulty components shall be repaired/
replaced .
TSTRANSCO/ PGCIL
(SR-I)
Yet to be informed Pending
85/IV/5 Tripping of 400kV Warangal-
Bhoopalapalli line-1
&BoopalppalliChandlapur
line-1
08-06-2019 at
1:35 hrs
400kV Warangal-Bhoopalapalli line-1 line tripped
only at Boopalappalli end on OV st-1 protection
operation and DT was not sent to Warangal end due to
failure of both PLCC channels. 400kV
BoopalppalliChandlapur line-1 tripped at Boopalpalli
end due to DT Receive
For the subject line, the following shall be carried out
by TSTRANSCO in coordination with TSGENCO
(i)End-to-end testing for DT/ permissive & other
signals may be ensured by testing at both the ends.
(ii)Healthiness of PLCC system components (
hardware and software) at both the ends shall be
checked and faulty components shall be repaired/
replaced .
TSGENCO/
TSTRANSCO
Yet to be informed Pending
ATRANSCO in coordination with TSTRANSCO to
ensure frequent patrolling and proper maintenance of
ROW by attending all tree clearance issues.
APTRANSCO/
TSTRANSCO
Yet to be informed Pending85/II/32
Andhra Pradesh
220kV Lower Sileru-KTPS
line
Annexure-II
Page 13 of 48
57/II/9 Tripping of 400 kV Nellore
(PG) - NPS line-1, 400 kV
Krishnapatnam-Nellore (AP)
lines -1&2 and 400kV NPS -
MEPL line
18-07-2016
at 19:05 hrs
Triggering incident was snapping of Y phase conductor
in 400kV Nellore (PG) - NPS line-1. Distance relay at
Krishnapatnam end over-reached in Zone-1, and
resulted in tripping of 400kV Krishnapatnam – Nellore
(AP) lines - 1&2 from Krishnapatnam end. Distance
APGENCO to furnish a report on the remedial action
implemented w.r.t. overreaching of Krishnapatnam end
distance relays during the tripping of 400 kV Nellore
(PG) - NPS line-1
APGENCO Review Meeting dated 19.12.2017:
It was noted that no APGENCO representative had come to attend the meeting.
APGENCO Mail dated 19.12.2017:
Procurement of relays is under progress
Pending
82/III/8 Tripping of 400kV VTPS-
SURYAPET-1
10-02-2019
at 13:20 hrs
B-phase to earth fault occurred in line. Auto-reclose
was successful at Suryapet and breakers got tripped at
VTPS end
It was noted that no representative of APGENCO
attended PCSC-82 meeting. APGENCO to furnish a
detailed report on tripping event bringing out reasons
for A/R non-operation at VTPS end along with
remedial action taken to PCSC forum.
APGENCO Review Meeting on 27.06.2019:
1. APGENCO representative did not attend the meeting. APGENCO is requested to
furnish the status at the earliest.
Pending
82/III/9 Tripping of 400kV VTPS-
SURYAPET-1
15-02-2019
at 14:36 hrs
B-phase to earth fault occurred in line. Auto-reclose
was successful at Suryapet and breakers got tripped at
VTPS end
It was noted that no representative of APGENCO
attended PCSC-82 meeting. APGENCO to furnish a
detailed report on tripping event bringing out reasons
for A/R non-operation at VTPS end along with
remedial action taken to PCSC forum.
APGENCO Review Meeting on 27.06.2019:
1. APGENCO representative did not attend the meeting. APGENCO is requested to
furnish the status at the earliest.
Pending
83/II/20 Tripping of 220kV VTS-
Talapalli ckt-3 and
Generating Units#1,2,3,4,5
& 6 at VTS.
01-04-2019 at
22:58hrs
220kV VTS – Talapalli ckt-4 was under maintenance.
While restoring the feeder, 220kV VTS – Talapalli ckt-
3 tripped on Zone-1 distance protection due to B-N
fault. At the same tine VTS unit# 1 & 2 tripped on
Loss of fuel and Generators 3,4,5&6 tripped on
Generator Negative phase sequence protection.
1. APGENCO is recommended to revise the time
delay of Negative Phase sequence protection operation
in consultation with OEM.
2. APGENCO is also recommended to look into the
Overcurrent Protection settings of Buscoupler, so as to
reduce its time delay of operation in case of faults on
Transfer Bus.
APGENCO Review Meeting on 27.06.2019:
1. APGENCO representative did not attend the meeting. APGENCO is requested to
furnish the status at the earliest.
Pending
83/III/8 Tripping of 400 kV VTPS -
Nellore
24-03-2019 at
12:46hrs
Feeder tripped on Y -N Fault. Auto reclose operated at
Nellore end but not operated at VTPS end.
APGENCO is recommended to submit a detailed
report regarding the reason for A/R being kept
disabled and the Remedial Measure taken for the same.
APGENCO Review Meeting on 27.06.2019:
1. APGENCO representative did not attend the meeting. APGENCO is requested to
furnish the status at the earliest.
Pending
84/II/9 Tripping of 220kV Bus 2 and
connected elements at 220kV
Gazuawaka Substation.
17-04-2019 at 5:40 hr.Triggering incident was Y-phase to earth fault in
220kV Gazuwaka Bus-2. This resulted in tripping of
220 kV elements and 400/220 kV ICT-2
1. APTRANSCO to submit a detailed report
regarding the subject tripping at 220 kV Gazuawaka
Substation along with the remedial measures taken.
2. For all lines emanating from Gazuwaka SS, RTV
coating shall be taken up.
APTRANSCO APTRANSCO mail dated 30.07.2019:
1. The report submitted vide mail dated 29.07.2019 -- Completed
2. Pending
Pending
85/II/6 Tripping of 400/220 kV ICT-
2 at Ghani substation
21-05-2019 at
15:13 hrs
ICT-2 tripped on LV Earth fault protection. 400kV
Ghani-Narnoor line-1 had tripped on B-phase to earth
fault.
APTRANSCO is recommended to send a detailed
report regarding non-availability of Main CB (Main
CB was already in tripped condition in antecedent
condition) during the tripping and non-attempt of auto-
reclosure by Tie CB at Ghani end.
APTRANSCO Yet to be informed Pending
85/II/27 Multiple tripping at 220kV
Nunna substation
16-06-2019 at
06:16 hrs
Triggering incident was failure R phase CT of
220/132kV transformer (connected to 220kV Bus-2) in
220kV Nunna station. Bus-2 bus bar protection
operated resulting in tripping of elements connected to
220kV Bus-2. 2.63 Seconds later a 2nd fault occurred
in Bus-1 due to fault getting extended from Bus-2 CT
failure which inturn resulted in tripping of elements
connected to 220kV Bus-1
1.APTRANSCO is recommended to submit Equipment
Failure Report regarding the failed CT to CEA.
2.APTRANSCO to sort out time synchronization
issues in 220kV Nunna SS.
APTRANSCO Yet to be informed Pending
Annexure-II
Page 14 of 48
85/III/1 Tripping of 400kV Ghani-
Narnoor line-1
21-05-2019 at
15:11 hrs
B-phase to earth fault occurred in line. Auto-reclose
was not successful as fault was persistent in nature.
Fault was cleared in zone-2 time during A/r attempt
APTRANSCO is recommended to send a detailed
report regarding non-availability of Main CB (Main
CB was already in tripped condition in antecedent
condition) during the tripping and non-attempt of auto-
reclosure by Tie CB at Ghani end.
APTRANSCO Yet to be informed Pending
85/III/4 Tripping of 400kV
Talarichevu - Jamalamadugu
ckt-1
22-05-2019 at
19:21 hrs
R phase to Earth fault in the line. At Jammalamadugu
end A/r operated and line tripped due to persistent
fault. Main CB A/r not attempted at Talarichevu
APTRANSCO is recommended to submit a report
regarding non-attempt of A/R by Main CB at
Talarichevu end of 400kV Talarichevu -
Jamalamadugu ckt-1.
APTRANSCO Yet to be informed Pending
Annexure-II
Page 15 of 48
82/II/1 Tripping of 400kV KTPS VI-
KTPS VII
05-01-2019
at 10:17hrs
Line tripped at KTPS VI end due to suspected mal-
operation of over-voltage protection. Line was in
service from KTPS VII., BUS CVT secondary R
PHASE got grounded at KTPS VI
1) TSGENCO to configure OVR_start and
OVR_tripin EL at KTPS-VI end and sent a report after
completion of works related to DT communication
channel between KTPS-VI and KTPS-VII
TSGENCO TSGENCO mail dated 24.06.2019:
The issue is referred to M/s BHEL ( EPC vendor ) and the study on feasibility for
providing the communication with the existing available system is under process and
will be completed during the availability of next shutdown.
Review meeting on 27.06.2019:
TSGENCO informed that the recommendations will be completed in September 2019
Pending
83/III/6 Tripping of 400kV Julurpadu
- Manuguru line-2
14-03-2019 at
06:10:00
Triggering incident was R-ph fault in the line. At
Julurpadu end, fault was sensed in Zone-2 and carrier
was received but due to DT Receive from manuguru
end, A/r not operated and line got tripped. FIR, DR and
EL of Manuguru end are not available.
It was noted that no representative of TSGENCO
attended the meeting. TSGENCO is recommended to
submit a report on the tripping and to furnish
equipment failure report to CEA.
TSGENCO TSGENCO mail dated 24.06.2019:
FIR, DR and EL was uploaded in SRLDC website.Trip Report was also submitted.
Review meeting on 27.06.2019:
TSGENCO informed that Equipment failure report will be sent to CEA.
Pending
84/II/28 Frequent tripping of 220 kV
KTPS –Nunna line
05-04-2019 at
12:55 hr. B-N
FAULT
15-04-2019 at
13:20 hr. Y-N
FAULT
16-04-2019 at
14:04 hr. B-N
FAULT
22-04-2019 at
14:13 hr. R-N
FAULT
23-04-2019 at
13:31 hr. R-N
FAULT
04-05-2019 at
14:40 hr. B-N
FAULT
09-05-2019 at
14:31 hr. B-N
FAULT
05-05-2019 at
13:03 hr. B-N
In 155thOCC meeting of SRPC, APTRANSCO
informed that the tripping was due to clearance issues
in the ROW caused by mango tree. It was cleared and
issue was rectified. However, frequent tripping of line
is still persistent.
1. TSGENCO to check the non-operation of carrier
aided trip, when fault is detected at KTPS end in Z-2
and carrier is also received, and submit a report
regarding the same.
2. TSGENCO and APTRANSCO to ensure that
ROW is cleared periodically.
3.APTRANSCO & TSGENCO may consider raising
the height of towers if the line is planned to be used in
future.
4.TSGENCO to consider replacement of old
pneumatic CB’s at KTPS if 220kV KTPS- Nunna line
is planned to be used in future.
TSGENCO Yet to be informed Pending
Telangana
Annexure-II
Page 16 of 48
74/II/8 Tripping of 400/220 kV ICT-
2 at Gajwel
11-04-2018 at
5:50 hrs
400/220 kV ICT-2 at Gajwel tripped on mal-operation
of Buchholtz relay.
1). TSTRANSCO was asked to keep the ICT and its
mechanical protections under observation for detecting
any slippages.
2). TSTRANSCO was also asked to configure
capturing of mechanical protections of ICT’s in the
respective relay’s/ station’s event logger.
TSTRANSCO TSTRANSCO mail dated 20.06.2018:
1. Mechanical protections of ICTs is under observation. --- Completed
2.New relays are available at site and will be commissioned by 2nd week of August-
2018. The mechanical protection of ICTs will be configured in the new relays ----
Pending
TSTRANSCO MAIL DATED 20.10.2018:
2. New relays will be commissioned by end of November-2018 and the Over Voltage
settings will be implemented after commissioning in new relays ----Pending
TSTRANSCO MAIL DATED 06.12.2018:
2. New relays will be commissioned by end of January-2019 and the mechanical
protections of ICTs will be configured in the new relays ----Pending
Pending
84/II/1 Tripping of 400kV Srisailam-
Dindi line-1 and 400kV
Mamidapalli-Dindi line-1
06-04-2019 at
17:39 hr.
400kV Mamidapally Dindi line-1 tripped on R-phase
to earth fault. 400kV Srisailam-Dindi line-1 tripped on
operation of cable differential protection at Srisailam
and direct trip was sent to Dindi.
1.TSTRANSCO to ensure time synchronization of DR
and EL at Mamidapalli end and Dindi end. Also in
coordination with TSGENCO sort out the time
synchronization issue in 400kV Srisailam – Dindi line-
1. 2.TSTRANSCO to ensure that A/R dead-time
is maintained as 1 sec uniformly at all Stations.
TSTRANSCO Yet to be informed Pending
84/II/14 Tripping of 400/220 kV ICT-
2 and 3 at Dichipalli
Substation
22-04-2019 at
17:22 hr.
ICT#2 and 3 got tripped on suspected mal-operation of
LV earth fault relay during fault in 220 kV Dichpally-
Medaram feeder
1 .TSTRANSCO to ensure directional settings for ICT
earth fault protection and to ensure coordination
between line and ICT DEF protection.
2.TSTRANSCO to investigate the reason for non-
operation of LBB protection of 220 kVDichpally-
Medaram line while breaker lockout at Dichipalli SS
occurred.
3. TSTRANSCO to perform condition monitoring of
CB’s regularly to ensure sufficient air pressure for
proper CB operation.
TSTRANSCO Yet to be informed Pending
84/II/27 Multiple tripping at 220 kV
Ghanapur station
27-05-2019 at
02:04 hr.
Triggering incident was failure of B-phase CT of bus
coupler of Bus-2. Bus bar protection of 220 kV Bus-2
operated resulting in tripping of all elements connected
to Bus-2.
1.TSTRANSCO is recommended to submit
Equipment failure report to CEA regarding the blast
CT.
2.TSTRANSCO to inform if any old CTs exist in
Ghanapur SS and ensure healthiness of the same to
TSTRANSCO Yet to be informed Pending
84/III/4 Tripping of 400kV
Uravakonda - Veltoor ckt-1
13-04-2019 at
18:36 hr.
Y-phase to ground fault. Auto reclose didnot operate at
Veltoor end due to maloperation of STUB protection
1. TSTRANSCO to submit a report regarding the error
in PSL logic that led to the subject tripping along with
Remedial Measures taken.
2. TSTRANSCO to submit a report after checking mal-
operation of STUB protection on P444 relay.
TSTRANSCO Yet to be informed Pending
85/II/7 Tripping of 400/220 kV ICT-
3at Mamidapalli
21-05-2019 at
20:43 hrs
ICT tripped on PRV-1 indications due to ingress of
moisture into the relay
TSTRANSCO is recommended to ensure proper
sealing of PRV by providing suitable canopy to
prevent spurious operation of the same due to ingress
of moisture.
TSTRANSCO Yet to be informed Pending
85/II/25 Tripping of 400kV KTPS-
VII - Julurupadu Line-2 &
tripping of 400/220kV ICT-
1&2 at Julurupadu substation
10-06-2019 at
8:22 hrs
Y-phase to earth fault occurred in 400kV KTPS-VII -
Julurupadu Line-2. Operation of over-voltage stg-2
resulted in tripping of line. 400/220kV ICT-1&2 at
Julurupadu on operation of over flux protection.
1.TSTRANSCO is recommended to check the v/f
settings of ICT-2 at Julurupadu since ICT-1 & 2
tripped at different time ( 3mins difference).
2.DGA analysis of ICT-2 shall be carried out to ensure
healthiness of ICT owing to very high voltage and the
tap position of ICT-2 also to be checked.
TSTRANSCO Yet to be informed Pending
Annexure-II
Page 17 of 48
85/III/12 Tripping of 400KV-
Maheshwaram PG-
Mahbubnagar line-1
06-06-2019 at
19:18 hrs
Y phase to Earth fault in the line. A/r not operated at
Mahbubnagar
TSTRANSCO is recommended to submit a report
regarding non-attempt of A/R at Mehaboobnagar with
Remedial measures taken
TSTRANSCO Yet to be informed Pending
Annexure-II
Page 18 of 48
Mail received on 21-10-2015:
1) Anti-pumping contactors of all the nine 220KV Lines are in circuit and tested
periodically during AOH works of lines along with other protections.
2) Completed.
3) Possibility to use both the 220kV buses as main bus under normal operation is
under review.
Mail recieved on 23-11-2015:
1) Completed
3) Two bus operation for 220kV buses : In place of existing CT switching relays,
High speed manual heavy duty change over switch of sufficient current capacity will
be retrofitted to all feeders at 220kV station and same will be operated manually
during changeover of feeder by one bus to the other and this arrangement may Status received vide KPCL mail dated 14.12.2017:
3) DPR for implementation of Two Bus operation for 220kV bus system has been
prepared and proposal is placed for funds from PSDF. After the approval of the DPR,
the work is proposed to be taken up.
Review Meeting dated 19.12.2017:
3) KPCL informed that DPR for implementation of Two Bus operation for 220kV bus
system has been prepared and proposal is placed for funds from PSDF. After the
approval of the DPR, the work is proposed to be taken up. Time frame requested for
is 2 yrs.
KPCL mail dated 19.12.2018:
3) Work proposed to be taken up under PSDF. Approval from Nodal agency is
awaited. However, arrangements have been made to issue NIT.
Review Meeting on 21.12.2018:
KPCL informed that Tender would be floated in 1 month and work would be
completed in 2 years.
KPCL mail dated 23.01.2019:
Tender would be floated in 1 month and work would be completed in 2 years.
KPCL mail dated 23.03.2019:
Arrangements have been made to issue NIT and Tender for the work proposed to be
floated during May- 2019.
KPCL mail dated 10.05.2019:
NIT will be issued during May- 2019.
KPCL mail dated 25.06.2019:
1. & 2. Completed
3) Preparation of technical specification is in progress. NIT will be issued during July-
2019.
Review meeting on 27.06.2019:
KPCL informed that timeline for completion of work is December 2019.
KPCL mail dated 16.07.2019:
1. & 2. Completed
3) Preparation of technical specification is in progress. NIT will be issued during July-
2019. timeline for completion of work is December 2019.
46/II/21 Trippings at 220kV Raichur
TPS
07-06-2015 at
01:35 hrs
1. KPCL to check the operation of anti-pumping relay
on 220 kV side and keep it in healthy condition.
2. KPCL to provide manual reset to the 220 kV side
master trip relay.
3. KPCL to use both the 220 kV buses as main buses
under normal operation, and should go for single bus
operation only during emergencies.
KPCL Pending
Karnataka
Annexure-II
Page 19 of 48
Status received vide KPCL mail dated 10.07.2017:
1. (ii) Hot line water washing stopped and off line water washing is carried out
whenever the 400 KV Unit or line is under tripped condition / Shutdown condition. ---
Completed
1. (iii) Silicon coating for Unit#8 main & tie breakers carried out in Sep'16 and same
is under observation. Till today in order and good condition. For remaining breakers,
since it is big order, approval for the same is under process. --- Pending
2. Static / Electromechanical relays are existing in all 1 to 7 units. Breaker flash over
protection feature will be enabled (if available) in the numerical relays which will be
retrofitted in phased manner during R&M works.
Status received vide KPCL mail dated 14.12.2017:
1.(i) --- Pending
1. (ii) Hot line water washing stopped and off line water washing is carried out
whenever the 400 KV Unit or line is under tripped condition / Shutdown condition. ---
Completed
1. (iii) Silicon coating for Unit#8 main & tie breakers carried out in Sep'16 and same
is under observation. Till today in order and good condition. For remaining breakers,
since it is big order, approval for the same is under process --- PendingReview Meeting dated 19.12.2017:
1 (iii) As upgradation of 400kV switchyard equip's to be taken under PSDF funds,
Silicon rubber coating for breakers is deffered till then. --- Pending
2. Replacement by Num relay for Units - 5,6 & 7 completed in the month of Oct-
2017. Main-I is Seimens make and Main-II is ABB make. --- Pending
KPCL mail dated 19.01.2018:
2. Replacement of Numerical relays for Units-5, 6 & 7 have been completed.
Referred to OEM for providing the Breaker flashover protection for all the breakers.KPCL mail dated 23.03.2019:
1) (i) & (iii)- Arrangements have been made to issue NIT and Tender for the work
proposed to be floated during May- 2019.
2) Reply is awaiting from OEM to implement the Breaker flash over protection in the
Numerical relays in 400KV station. & Being discussed with other utilities.
It is requested to furnish Necessary logic and settings to implement the breaker
flashover protection
KPCL mail dated 10.05.2019:
1) (i) & (iii)- NIT floated on 01.03.2019
2) Reply is awaiting from OEM to implement the Breaker flash over protection in the
Numerical relays in 400KV station. & Being discussed with other utilities.
It is requested that SRPC may suggest/furnish reference of necessary logic and
settings to implement the breaker flashover protection.
KPCL mail dated 25.06.2019:
1) (i) & (iii)- NIT floated on 01.03.2019. Cover-I opened. Technical evaluation is in
progress. Approval from Nodal Agency is awaited.
2) Reply is awaiting from OEM to implement the Breaker flash over protection in the
Numerical relays in 400KV station. & Being discussed with other utilities.
It is requested that SRPC may suggest/furnish referenc of necessary logic and Review meeting on 27.06.2019:
SRPC informed that referenc of necessary logic and settings to implement the breaker
flashover protection will be shared soon.
KPCL mail dated 16.07.2019:
1) (i) & (iii)- NIT floated on 01.03.2019. Cover-I opened. Technical evaluation is in
progress. Approval from Nodal Agency for PSDF funds is awaited.
2) As confirmed during 84th PCSC meeting, SRPC may suggest/furnish referenc of
necessary logic and settings to implement the breaker flashover protection. reply in
this regard is awaited.
54/II/9 PendingKPCL 1.KPCL to undertake the following remedial measures
to avoid breaker flashovers:
(i) Replacing all porcelain insulators with composite
insulators
(ii) Carrying out hot-line water washing of all
insulators on regular basis.
(iii) Applying Room Temperature Vulcanizing (RTV)
Silicone high voltage insulator coatings to all bus-
connected ceramic insulators of equipment like CT,
PT, CB, Isolators etc.
2.KPCL to take steps to provide dedicated breaker
flashover protection to all breakers at Raichur TPS at
the earliest.
Y-ph Pole of Tie-breaker of Unit-4 at RTPS failed.
Unit-4 got tripped on operation of Generator
Differential, Reverse power & LBB protection.
Operation of LBB protection led to tripping of BUS-2
at RTPS
13-04-2016 at
21:12 hrs
Tripping of 400kV Raichur
TPS
Bus-2
Annexure-II
Page 20 of 48
Status received vide KPCL mail dated 10.07.2017 & 14.12.2017:
Two Bus operation for 220kV bus is being carried out whenever required. However
scheme for tripping of one bus during LBB/fault and maintaining the other bus intact
by tripping B/C breaker will be taken up in R&M works.
Review Meeting dated 19.12.2017:
3) KPCL informed that DPR for implementation of Two Bus operation for 220kV bus
system has been prepared and proposal is placed for funds from PSDF. After the
approval of the DPR, the work is proposed to be taken up. Time frame requested is 2
yrs.
KPCL mail dated 20.12.2018 & 23.01.2019:
Work proposed to be taken up under PSDF. Approval from Nodal agency is awaited.
However, arrangements have been made to issue NIT.
KPCL mail dated 10.05.2019:
NIT will be issued during May- 2019.
KPCL mail dated 25.06.2019:
Preparation of technical specification is in progress.
NIT will be issued during June/July- 2019.
Review meeting on 27.06.2019:KPCL mail dated 16.07.2019:
NIT will be issued during July- 2019. Time line for completion of work is Dec-2020.
Tripping of Units at 220 kV
Raichur TPS
54/II/13 PendingKPCL In view of the availability of two buses along with
healthy bus-coupler at 220 kV RTPS, KPCL is
recommended to put in service the double-bus
operation at 220 kV RTPS by suitably distributing
loads within 15 days.
During testing of retrofitted distance protection in
400kV Raichur-2 feeder, LBB protection trip DC got
extended to Bus trip. This resulted in tripping of 220kV
bus at RTPS and all connected 220 kV elements. Unit-
4 which is connected to 400 kV Bus got tripped due to
tripping of Station Utility Transformer that is
connected 220 kV bus
Timeline?15-04-2016 at
15:36 hrs
Annexure-II
Page 21 of 48
Status received vide KPCL mail dated 14.06.2017:
1. All logics checked and found normal. LBB timing checked and found 200msec as
per KPTCL MRT recommendation. - Completed
2. Work Under Progress ---- Pending
3. New GPS System commissioned along with new numerical and synchronised with
GPS system - Complied
4. Work Under Progress ---- Pending
Status received vide mail dated 14.12.2017:
1),3),4) Completed
2. Auto Start of DG set is taken up --- Pending
Review Meeting dated 19.12.2017:
2. KPCL informed that for AMF of DG, Scheme prepared & material procurement
under process. The AMF scheme will be implemented in January 2018. --- Pending
3. The GPS system commissioned on Nov 2016 & all the numarical relay time
synchronised with GPS ---- Completed
Status received vide mail dated 25.07.2018:
AMF panel procurement under progress.
KPCL mail dated 20.1.2.2018:
2. AMF scheme implementation is included in the work ''Replacement common
auxiliary panel with latest technology SCADA compatibility system'' . Availing Review Meeting on 21.12.2018:
KPCL informed that Tender for the work would be floated by January 2019 and work
would be completed in 1 year.
KPCL mail dated 23.01.2019:
1) Completed.
2) Tender for the work would be floated by February 2019 and work would be
completed in 1 year....Pending
3) Completed.
4) Tender for the work would be floated by Feb, 2019, and work would be completed
in 1 year....Pending
KPCL mail dated 23.03.2019:Review meeting on 27.06.2019:
.1 & 3) Completed.
4) Tender published on 21.06.2019 and time line in June 2020.
2. tender has to be issued. Timeline requested upto December 2020.
KPCL mail dated 16.07.2019:
1 & 3) Completed.
2 ) NIT will be issued during Aug-2019.
4) Tender published on 21.06.2019. Time line for completion of Work is Dec-2020.
Status received vide mail dated 25.07.2018:
Numerical Generator protection relay replacement proposed to be taken up alongwith
SCADA work.
KPCL mail dated 20.12.2018:
Will be taken up along with SCADA work. NIT to be issued on Jan-2019
Review Meeting on 21.12.2018:
KPCL informed that Tender for the work would be floated by March, 2019, and work
would be completed in 1 year.
KPCL mail dated 23.01.2019:
Tender for the work would be floated by February-2019 and work would be
completed in 1 year.
KPCL mail dated 23.03.2019:
Tender for the work proposed to be floated during May- 2019 after model code of
conduct and work would be completed in 1 year
KPCL mail dated 10.05.2019:
Tender will be floated during 3rd week of May- 2019.
KPCL mail dated 25.06.2019:
Tender published on 21.06.2019.
Review meeting on 27.06.2019:
69/II/8 PendingKPCLKPCL to take steps to replace the existing static
protection relays for Generator Units and Generating
Transformers (GT’s) with suitable Numerical relays at
their 220 kV Kadra PH.
While de-synchronising of Unit-2, B-phase pole of
GCB did not open and pole descrepancy relay
operated. Hence all 220KV lines CB hand tripped.
PendingKPCL1) KPCL to check settings of LBB protection in all
relays from which it was implemented, and ensure that
their configuration, logic, and timing are in order at
their 220 kV Kadra PH.
2) KPCL to furnish details regarding the existing LT
auxiliary supply arrangement at their 220 kV Kadra
PH, and take steps to provide a suitable Auto-Main-
Fail (AMF) panel for DG set to effect its auto-starting
in case of failure of LT supply.
3) KPCL to ensure time-sync of all relays (DR’s &
EL’s) with GPS at their 220 kV Kadra PH.
4) KPCL to provide stand-alone Event Logger at their
220 kV Nagjheri PH.
LBB of 220kV Kodasalli breaker at Kadra end got
operated which resulted in tripping of Bus at Kadra
and in turn led to tripping of all elements
06-09-2016
at 14:40 hrs
Complete outage of 220 kV
Kadra power station of
KPCL
58/I/3
(GD)
06-10-2017 at
22:22 hrs
Tripping of 220 kV Kaiga-
Kadra line-1
Annexure-II
Page 22 of 48
KPCL mail dated 16.07.2019:
Tender published on 21.06.2019. Time line for completion of Work is Dec-2020.
72/I/4 Complete outage of 220kV
Sedam, Shahapur, Shahabad,
Kapanoor, Humnabad and
Halabarga Stations of
KPTCL
01-02-2018
at 17:46 hrs
High resistance fault occurred in 110kV Sedam-
Chittapur line near Sedam end. Line DEF operated and
backup OC protection of 100MVA transformer
operated at Sedam end. But line breaker and
transformer HV breaker didn’t open due to problem in
trip circuit. This resulted in cascade tripping of
upstream feeders and power supply was lost to six
220kV stations of KPTCL.
KPCL to disable GFC protection on all lines
emanating from their generating stations.
KPCL Review Meeting on 21.12.2018
KPCL informed that compliance w.r.t. Implementing the recommendation would be
furnished soon.
KPCL mail dated 23.03.2019:
'GFC protection will be disabled in all lines in coordination with M/s.KPTCL
KPCL mail dated 10.05.2019 & 25.06.2019:
Letter addressed to CE, RT, KPTCL dated: 10.04.2019 to disable GFC protection
in all 220kV lines . Reply is awaited.
KPCL mail dated 16.07.2019:
Letter addressed to CE, RT, KPTCL dated: 10.04.2019 to disable GFC protection
in all 220kV lines . Reply is awaited.
Pending
73/I/5 Complete outage of 220kV
Varahi power station
15-03-2018 at
22:36 hrs
There was Y-phase to ground fault on 220 kV Varahi -
Shimoga line-2. Consequent to persisting fault in ‘Y’
phase, the breaker failure protection operated resulting
in operation of 220KV bus bar protection at Varahi,
tripping all the connected lines and Varahi running
units.
KPCL to take steps to put double-bus operation into
service at their 220 kV Varahi PH.
KPCL Status received vide mail dated 25.07.2018:
Under Implementation.
KPCL mail dated 20.12.2018 & 23.01.2019 & 23.03.2019:
Retrofitting of 220kV Bus Isolators is under progress. Proposed to be in service after
April-2019
KPCL mail dated 10.05.2019:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted. Remaining
bays will be completed after Concurrence of LC from LDC
KPCL mail dated 25.06.2019 & 16.07.2019:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted. Remaining
bay will be completed after monsoon season i.e during November -2019
Pending
78/I/1 Complete Outage of 220 kV
Varahi UGPH.
24-08-2018 at
11:00 hrs
Due to suspected mal-operation of 220KV bus bar
protection at Varahi, all the connected lines and Varahi
running Units got tripped. (6 nos 220kV lines and 4
nos Varahi generating station running Units). This
resulted in complete outage of 220kV Varahi UGPH
1. KPCL to take steps to put double-bus operation into
service at their 220 kV Varahi UGPH by December,
2018.
2. KPCL to employ correct operational practices like
keeping DC fuses of B/C CB intact during bus
changeover works, disabling back-up protections of
B/C CB during bus changeover works & enabling
them with proper settings only when it is used as Main-
CB of the grid elements.
KPCL KPCL mail dated 20.12.2018 & 23.01.2019:
1. Retrofitting of 220kV Bus Isolators is under progress. Proposed to be in service
after April-2019 --- Pending
2. ---- Completed.
KPCL mail dated 23.03.2019:
1) Retrofitting of 220kV Bus Isolators is under progress. Proposed to be in service
after April-2019
KPCL mail dated 10.05.2019:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted. Remaining
bays will be completed after Concurrence of LC from LDC.
KPCL mail dated 25.06.2019 & 16.07.2019:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted. Remaining
bay will be completed after monsoon season i.e during November -2019
Pending
69/II/8 PendingKPCLKPCL to take steps to replace the existing static
protection relays for Generator Units and Generating
Transformers (GT’s) with suitable Numerical relays at
their 220 kV Kadra PH.
While de-synchronising of Unit-2, B-phase pole of
GCB did not open and pole descrepancy relay
operated. Hence all 220KV lines CB hand tripped.
06-10-2017 at
22:22 hrs
Tripping of 220 kV Kaiga-
Kadra line-1
Annexure-II
Page 23 of 48
KPCL mail dated 10.03.2019:
1) Preparation of technical specification is completed. Tender will be floated during
3rd week of May- 2019 for control & protection system along with SCADA.
2) English Electric make static type relay is used for NPS protection system at Unit
no.2. The detailed report shall be furnished shortly.
KPCL mail dated 25.06.2019:
1) Preparation of technical specification is completed. Tender will be floated during
1st week of July 2019 for control & protection system along with SCADA.
2) Existing relays are English Electric Static type
@ GT -2 side, Unit breaker opened at 3MW, HV side current is
0.045A(CTR:200/1A), Since LBB setting I= 0.2A, t=0.2sec, Hence LBB is not
operated.
at the same time,@Generator-2 side ,current is 0.9A(CTR-4000/5A, I2s=7.5% of
secondary current i.e alarm=80% of I2s(i.e 0.3A pickup value), since R pole of
breaker closed condition till manual opening of all 4lines, Due to continous
current(>0.3A), However, NPS operated.
Review meeting on 27.06.2019:
1. Timeline for completion of work July 2020.
2. PCSC confirmed the correctness of NPS relay settings adopted at Kadra. --
Completed.
KPCL mail dated 16.07.2019:
1) Tender published on 21.06.2019. Time line for completion of Work is Dec-2020.
2) Completed.
Mail received on 28-04-2015:
1. In view of operating 220kV Ambewadi SS in split bus mode, action is being taken
up by KPTCL. Problem in the 220kV bus coupler breaker is attended and isolator
overhauling work is under progress. Spilt bus operation at Ambewadi will be made
possible at the earliest. --- Pending
2. ICT Protection system at Ambewadi and trippings occured at Supa GS during the
instance is checked up and remedial measures already furnished in this regard.
---- Completed
Mail recieved on 29-07-2015:KPTCL Mail dated 16.12.2017 & Review Meeting dated 19.12.2017:
1. Recommended works at Ambewadi have not been taken up due to various problems
faced due to poor response from the turn key agency M/s ERL. A site meeting is
planned during this month to discuss about further plan of action for attending SRPC
recommendations pertaining to the Sub station.
The issue was discussed in the review meeting. Considering the importance of the
substation and delay in executing the works, it was decided to escalate all pending
issues relating to Ambewadi SS to KPTCL top Management for early completion.
KPTCL mail dated 20.12.2018:Mail received on 28-04-2015:
Procurement of Bus bar and LBB protection is in the final tendering stage. 2. Action
is being taken to restore the carrier protection for 220kV Sedam-Tandoor line. AR
will be enabled.
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final tendering stage. KPTCL Mail dated 16.12.2017:
1 & 2) Replacement of Bus Bar Protection is included under R&U project. Awarded
to M/s GE Ltd. Panels have alredy been supplied by the Agency. The work will be
taken up on top priority.
Review Meeting dated 19.12.2017:
PendingKPTCLTriggering incident was B-phase to earth fault in
220kV Ambewadi- Nagzari line-1. B-pole of breaker
did not open at Ambewadi end. LBB protection not
available at Ambewadi end. All elements tripped on
Zone-2 from remote ends.
1. Till the completion of R&M works for bus bar and
LBB protection, KPTCL shall explore the possibility
of having split bus operation at Ambewadi and submit
the details of the same to PCSC forum.
2. KPTCL shall provide the details of the tripping of
Supa hydro station connected downstream from 110
kV bus.
1. Status? 1. KPTCL to provide Bus bar and LBB
protections for 220 kV bus at Sedam S/s.
2. KPTCL to implement A/R feature on 220 kV
Sedam-Tandur inter-state line.
27-01-2015 at
8.00 hrs
40/I/1 22-12-2014
at 21:22 hrs
Complete outage at 220kV
Sedam Substation of KPTCL
(GD-1)
KPTCL
PendingKPCL
GD-1 at 220kV Ambewadi
Station of KPTCL
1) KPCL to ensure that DR and EL for all events are
made available. If Static relays with no DR are present
in Station, standalone Disturbance recorder and Event
logger should be provided.
2) KPCL to investigate the operation of Negative
sequence relay and report to SRPC since the operation
of Negative sequence relay due to stuck breaker
condition is not proper as per protection philisophy
During de-synchronising of Kadra unit#2, R-pole
didn’t open due to struck breaker condition. Pole
Discrepancy operated. All the connected 220kV lines
at Kadra end were hand tripped.
04-02-2019 at
20:19 hrs
Complete Outage of 220kV
Kadra Power House of
KPCL & 220kV Karwar SS
of KPTCL
82/I/3
R-Phase to ground fault occurred on 220kV Sedam-
Shahpur line. Fault not cleared from Sedam end due to
stuck-breaker condition. While the Sedam- Sahapur
line tripped from Shahapur end in Zone-1, the other
220 kv lines from Sedam tripped at remote ends in
Zone-2. This caused complete outage of 220kV Sedam
substation.
41/I/4 Pending
Annexure-II
Page 24 of 48
Mail received on 27-05-2015:
1. Bus Bar protection will be provded under R&U.
2. A/R yet to be enabled.
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final tendering stage.
2. Action is being taken to restore the carrier protection for 220kV Sedam-Tandoor
line. AR will be enabled after restoration of PLCC.
KPTCL Mail Recieved dated 22-11-2017:
Bus Bar Protection panel and required Wave traps are supplied under R&U. Wave
trap to be commisioned in Tandoor line and PLCC to be restored.Once PLCC is
restored AR will be enabled.
KPTCL Mail dated 16.12.2017:
1. Replacement of Bus Bar Protection is included under R&U project. Awarded to
M/s GE Ltd. Panels have alredy been supplied by the Agency. The work will be taken
up on top priority.
2. AR feature will be enabled during retrofitting of Main-2 relays.
Review Meeting dated 19.12.2017:
1 & 2) KPTCL informed that the works are under progress and are targeted to be
completed by February, 2018. Review meeting on 27.06.2019:
1. Timeline - September 2019
2. Completed
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final tendering stage.
2. Action is being taken to restore the carrier protection for 220kV Sedam-Tandoor
line. AR will be enabled after restoration of PLCC.
KPTCL Mail Recieved dated 22-11-2017 & 16.12.2017:
1.Enabling the AR feature was discussed during PCSC meetings and since Ambewadi-
Ponda and Ambewadi-Xeldom lines are radial lines, it was decided that enabling AR
KPTCL mail dated 20.12.2018:
The protection issues pertaining to Ambewadi was appraised to the management
and proposal for construction of new GIS SUb stations has been approved by KPTCL
management. Further as per SRPC directions and in view of attending protection audit
recommendations pertaining to Ambewadi SS without linking with new Station
proposal, action has been taken to include the works in extended scope of R&U
project awarded to M/s GE T&D India Limited. Addition materials required are yet to
be supplied by M/s GE. work expecnted to be completed in 5 months.
Review meeting on 27.06.2019:
1. Since 220kV Ambewadi -Ponda line is radial, this recommendation is dropped.
2. Timeline will be in timated by KPTCL
15-02-2015
at 14:24 hrs
42/I/2
(GD)
1. KPTCL to provide Bus Bar protection and LBB
protection at Sedam S/s and furnish the status of their
implementation to PCSC forum.
2. KPTCL to implement A/R feature on 220 kV Sedam-
Tandur inter-state line.
Fault occurred in 220kV Sedam-Shahpur line42/I/1 Pending
Fault in 220kV Ambewadi-Nagjheri line-2Complete outage of 220 kV
Ambewadi substation of
KPTCL
PendingKPTCL1. KPTCL shall provide A/R feature on Ambewadi –
Ponda 220 kV D/C inter-state line.
2. Till the completion of R&M works for bus bar and
LBB protection, KPTCL shall explore the possibility
of having split bus operation at Ambewadi and submit
the details of the same to PCSC forum.
KPTCL
12-03-2015 at
7:51 hrs
Complete outage of 220kV
Sedam substation of KPTCL
Annexure-II
Page 25 of 48
KPTCL mail received on 23-01-2016:
Will be complied in a months time.
KPTCL Mail Recieved dated 22-11-2017:
Enabling the AR feature was discussed during PCSC meetings and since Ambewadi-
Ponda and Ambewadi-Xeldom lines are radial lines, it was decided that enabling AR
is not required. To clear the faults in the abovelines early, the timings of the Zone 2
was reduced to 150mS and the Back Up EFR timings have been reducedto 150mS.
KPTCL Mail dated 16.12.2017:
Enabling the AR feature was discussed during PCSC meetings and since Ambewadi-
Ponda and Ambewadi-Xeldom lines are radial lines, it was decided that enabling AR
is not required. To clear the faults in the abovelines early, the timings of the Zone 2
was reduced to 150mS and the Back Up EFR timings have been reduced to 150mS.
In view of the above, it is requested to drop the issue from this list.
Review Meeting dated 19.12.2017:
KPTCL informed that AR would be enabled at Ambewadi end for lines other than
Ponda and Xeldom lines during retrofitting of Back Up protection by Distance
protection relay at Ambewadi.
KPTCL mail dated 20.12.2018:
The protection issues pertaining to Ambewadi was appraised to the management
and proposal for construction of new GIS SUb stations has been approved by KPTCL
management. Further as per SRPC directions and in view of attending protection audit
recommendations pertaining to Ambewadi SS without linking with new Station
proposal, action has been taken to include the works in extended scope of R&U
project awarded to M/s GE T&D India Limited. Addition materials required are yet to
be supplied by M/s GE. work will be completed in 5 months
Review meeting on 27.06.2019:
1. Work order plced. Timeline requested December 2019.
Status?48/I/3 PendingKPTCL KPTCL to fast-track providing A/R on all 220 kV
lines emanating from Ambewadi SS to prevent Station
shut-down on temporary faults.
220kV Ambewadi-Nagjheri line-2 tripped on B-phase
to earth fault. This resulted in loss of supply to 220kV
Ambewadi bus. 220kV Ambewadi-Ponda line-1&2
were hand tripped after deenergization of bus at
Ambewadi.
30-09-2015 at
10:41 hrs
Outage of 220kV Ambewadi
station in Karnataka
Annexure-II
Page 26 of 48
KPTCL Mail received dated 25-04-2017:
Replacement of existing BBP by new BBP with 4 zone protection is being taken up
under R&U.
KPTCL Mail Recieved dated 22-11-2017:
GE Ltd has already supplied the necessary Bus Bar protection panels for replacement
of the existing static type BBP by new numerical BBP with 4 zone protection under
R&U project. The work of commissioning the same will be taken up shortly.
KPTCL Mail dated 16.12.2017:
Due to operational constraints two/ multi bus operation is not being implemented.
Review Meeting dated 19.12.2017:
It was noted that Shimoga SS is having required configuration for providing double-
bus operation. However, due to large no. of feeders (15 in no) with variable gneration
at certain remote ends like Varahi, the flows on these lines are bound to vary. As such
it is necessary to zero in on appropriate arrangement of feeders on different buses so
that bus-isolators of the feeders are not overloaded.
The issue was discussed. KPTCL was asked to try out multi-bus operation on trial
basis to arrive at suitable arrangement of feeders.
KPTCL mail dated 20.12.2018:
Bus sectionaliser breakers have to be provided for operating Shimoga in multi bus
mode. Estimates have to be prepared by CEE,TZ,Hassan. Work expected to be
completed in 1 year.
KPTCL Mail Recieved dated 22-11-2017:
1. The necessary Bus Bar protection panels are already supplied to Chikkodi under
R&U project. Presently R&U works at sub stations subjected to audit are taken up.
After completion of PAR works, the baove works are planned.
--- Pending
2. --- Pending
3. --- Pending
KPTCL mail dated 16.12.2017:
1.The necessary Bus Bar protection panels are already supplied to Chikkodi under
R&U project. Control cables have to be supplied. Presently R&U works at sub
stations subjected to audit are taken up. After completion of PAR works at 26 Sub
stations, remaining works will be taken up through M/s GE.
--- Pending.
2. --- Pending
3. --- Pending
Review Meeting dated 19.12.2017:
1. KPTCL informed that BBP would be provided by April, 2018.
---- PendingKPTCL mail dated 20.12.2018:
1). Bus Bar Protection work is included under R&U. work expected to be completed
in 3 months ---- Pending
2). Major equipment failure reports are being sent to CEA regularly ----
Completed.
Review Meeting on 27.06.2019:
1. Timeline for completion of work is September 2019
2. Completed
220kV Bus Bar protection operated during failure of R
phase CT in DVG-2 line bay.
22-02-2016 at
15:03 hrs
57/II/1 PendingTriggering incident was failure of B-ph PT of 220kV
Bus-2 (western bus) at 220KV Chikkodi substation.
220KV Chikodi- Belgaum-I line tripped on DEFR
(Inst), 220KV Chikkodi-Kudachi line tripped on
Distance protection and also 100MVA transformer-2
tripped on E/F protection.
KPTCL1.KPTCL to take steps to provide busbar protection at
their 220 kV Chikkodi inter-regional substation, and
furnish a time-line for the same.
2.KPTCL to review distance protection settings for
220 kV Chikkodi – Kudachi line.
3.KPTCL to furnish equipment failure report of the
current incident to PSE&TD Division of CEA with a
copy marked to SRPC.
KPTCLKPTCL to operate 220 kV Shimoga on multi-bus
operation under normal conditions, and put it on single-
bus operation only under emergency conditions.
Complete outage of 220 kV
Shimoga substation
Tripping of 220 kV Chikkodi-
Mudshingi and 220 kV
Chikkodi-Talandage lines
01-07-2016 at
03:03 hrs
Pending52/I/3
Annexure-II
Page 27 of 48
KPTCL mail received dated 25.04.2017:
Numerical BBP is being provided under R&M works.
KPTCL mail dated 20.12.2018:
1). The R&M work of 220kV Hoody SS is under progress and expected to be
comleted before the end of August 2019. Providing Bus Bar Protection to 220kV
buses is a part of R&M work at Hoody ----- Pending
62/II/5 Tripping of 220 kV South
Bus and connected elements
(220kV HSR, 220kV
Nagnathpura, 220 kV
Harohalli, 220 kV
Subramanyapura, 220 kV
20-01-2017 at
14:34 hrs
Triggering incident was fault in 66 kV Somanahalli -
Bannerghatta line and fault was cleared by operation of
Back-up OCR at Somanahalli end.
KPTCL to provide numerical Busbar Protection at
their 220 kV Somanahalli SS at the earliest.
KPTCL KPTCL mail received dated 25.04.2017:
Numerical BBP is being provided under R&M works
KPTCL Mail Recieved dated 22-11-2017:
Tesing & Commissioning of numerical BBP at Somanahalli is under progress. There
was some technical issue wth BBP scheme supplied to Somanahally which is being
Pending
74/I/2 Complete outage of 220 kV
Ambewadi station
02-04-2018 at
13:46hrs
Loss of supply occurred to 220 kV Ambewadi station
due to tripping of 220kV Nagzhari-Ambewadi line-2
(Source) from Nagzhari power station. After bus dead,
Ambewadi-Ponda lines – 1 & 2 were hand-tripped. In
antecedent conditions, 220kV Ambewadi - Nagjheri
ckt-1, 220kV Ambewadi-Narendra Ckt-1 &2 were out
of service.
1). KPTCL to review operation of SPS at NPH for
proper functionality and changed network conditions
(reduction of generation with tripping of evacuating
lines) and put it into service at the earliest.
2). KPTCL to furnish equipment failure report of the
current incident (R-phase CT in Nagjheri – 1 bay at
KPTCL KPTCL mail dated 20.12.2018:
1). To be reviewed. Expected to be completed in 1 month.---- Pending
2), Being followed ----- Pending
Review meeting on 27.06.2019:
1. Nagjheri SPS shall be studied in view of changed system configuration
Pending
74/II15 Multiple Trippings at
400/220kV Guttur station
21-04-2018 at
12:50 hrs
Triggering incident was fault in 220 kV Davanagare -
Shimoga line. Bus bar protection operated at Guttur
resulting in tripping of all the connected elements. 220
kV Guttur was on single bus operation due to CVT
problem in Bus-2.
KPTCL to put double-bus operation at their 220 kV
Guttur substations by attending to Bus-2 CVT
problem.
KPTCL KPTCL mail dated 20.12.2018:
Bus-2 CVT problem is attended. However due to breaker replacement works, 220kV
side operated in single bus mode.
Review Meeting dated 20.12.2018:
KPTCL informed that double-bus operation at their 220 kV Guttur would be provided
within two months.
Pending
79/III/9 Tripping of 400 kV JSWEL
–Guttur line
29-09-2018
at 11:30 hrs
R-phase to earth fault occurred in line. Auto-reclose
was not attempted at JSWEL due to DT receive. At
Guttur end auto-reclose could not be validated with
DR/EL.
KPTCL to furnish a detailed report on tripping event
bringing out reasons for DT sending from Guttur end
to JSWEL on 400 kV Guttur - JSWEL line along with
remedial action taken to PCSC forum.
KPTCL Review Meeting on 21.12.2018:
KPTCL was aksed to furnish status of implementation of the recommendation given
at the earliest.
Review meeting on 27.06.2019:
Pending
80/II/7 Tripping of 400 kV JSWEL-
Guttur line
17-10-2018 at
02:04 Hrs
Triggering incident was R-phase to earth fault in line.
At Guttur end there was operation of pole discrepancy
and resulted on tripping of Y & B pole after a duration
of 2 seconds from the occurrence of fault. FIR, DR &
EL of Guttur end were not furnished.
KPTCL to examine the reasons for sending of DT from
Guttur end to JSWEL end, and furnish an action taken
report including remedial measures taken to rectify the
same.
KPTCL Review meeting on 27.06.2019:
report will be submitted by KPTCL
Pending
82/I/4 Complete Outage of 220kV
Ambewadi Station of
KPTCL
06-02-2019 at
14:51hrs
Fault occurred while test charging of 220kV
Ambewadi – Nagjheri Line -2 from Ambewadi end.
Suspected stuck breaker condition at Ambewadi end)
led to clearing of fault by tripping of remote end
breaker in Zone-2. LBB protection is not active at
220kV Ambewadi station.
KPTCL to investigate the reason for non-tripping of
220kV Ambewadi - Nagjheri line-2 on operation of
SOTF and submit a report regarding the same to
SRPC. Also KPTCL to take necessary measures in
order to ensure healthiness of breaker before
testcharging of any line.
KPTCL Review meeting on 27.06.2019:
report will be submitted by KPTCL
Pending
Tripping of 220 kV Bus 2
and connected elements
(220kV HAL #1 and 2,
400/220 kV ICT- 1, 2 and
220/66 kV ICT-2) at
400/220 kV Hoody
substation of KPTCL (Load
loss : 590 MW)
62/II/3 1. KPTCL to provide Busbar protection at their 220
kV Hoody SS at the earliest.
2. KPTCL to furnish an Equipment Failure Report on
CT failure to CEA with a copy marked to SRPC.
Failure of R-phase CT of 220/ 66 kV transformer-2 at
220kV Hoody end resulted in a bus fault in 220kV Bus-
2. Fault was cleared by backup protection of ICT's
(220kV lines were being radially operated) due to
absence of busbar protection
KPTCL Pending09-01-2017
at 23:06 hrs
Annexure-II
Page 28 of 48
82/I/8 Complete outage of 220kV
Alipura substation
20-02-2019 at
12:45 hrs
As informed by KPTCL, Suspected delayed clearance
of fault in 220 kV BTPS-Lingapur line from BTPS end
resulted in tripping of lines from Alipura S/s.
1) KPTCL is recommended to furnish detailed report
regarding spurious operation of DEF at Alipur SSand
check the directionality of DEF on all lines.
2) KPTCL is requested to share the revised zone
settings for Distance protection at BTPS end.
KPTCL Review meeting on 27.06.2019:
report will be submitted by KPTCL
Pending
82/II/12 Tripping of 400kV Kaiga-
Guttur line-1&2
07-02-2019
at 11:49 hrs
Line-1 tripped due to insulator flashover. Line-2
tripped due to zone-3 operation at Kaiga and Direct
trip receive at Guttur
KPTCL is recommended to take necessary measures to
ensure that Main-I and Main-II at Guttur end shall be
of different types (make and model) coherent with the
general protection philosophy followed in SR region.
KPTCL Review meeting on 27.06.2019:
KPTCL informed that the recommendation has been included as part of R & M work.
Timeline will be informed
Pending
84/II/12 Tripping of 400kV DHONI
GUTTUR line- 1
18-04-2019 at
18:59 hr.
Triggering incident was failure of B-ph CB of 400kV
Dhoni-Guttur line at Dhoni end. This resulted in the
operation of LBB of bus-1 and DT was sent to Guttur
end
1. KPTCL to send equipment failure report,
corresponding to the failed CB at Dhoni SS, to CEA.
2. KPTCL to ensure time synchronization at Guttur
end.
KPTCL Yet to be informed Pending
84/II/16 Tripping of 400 kV
Nelamangala-Mysore line-2
01-05-2019 at 02:29 hr.Line tripped on operation of over voltage stg-2 at
Nelamangala end
KPTCL to ensure time synchronization of DR and
EL with GPS signal at Nelamangala end.
KPTCL Yet to be informed Pending
84/II/24 Tripping of 400/220 kV ICT-
1&3 at Hoody Substation
13-05-2019 at
15:35 hr.
ICT-3 tripped on operation of 59N neutral
displacement relay. ICT-1 tripped on OCR.
KPTCL to inform PCSC forum regarding the changes
implemented in Hoody ICT SPS and to ensure time
synchronization of relays at Hoody SS.
KPTCL Yet to be informed Pending
85/I/4 Tripping of 220kV Sedam-RTPS
line-1&2 and 220kV Sedam-
Tandur line
14-06-2019
at 02:00 hrs
Tripped on Directional Earth Fault indications in Main-
2 relay at Tandur end for fault at Raichur end. Sedam
end details not furnished.
1. KPTCL is recommended to enable A/R on all lines
emanating from 220kV Sedam SS.
2.KPTCL is recommended to commission BBP at
220kV Sedam SS immediately.
KPTCL Yet to be informed Pending
85/II/5 Tripping of 400/220 kV ICT-3 at
Nelamangala substation19-05-2019
at 16:11 hrs
As per FIR, ICT-3 got tripped on operation of High Set
Over current trip on 400kV side
1. KPTCL is recommended to enable auto-reclosure
on all lines emanating from 400/ 220kv Neelamangala
SS and to ensure time synchronization of relays at
Neelamangala SS.
KPTCL Yet to be informed Pending
85/II/11 Tripping of 400kV Hoody-
Yelahanka line-125-05-2019
at 20:41 hrs
Line tripped at Hoody end only and was holding from
Yelahanka.
KPTCL is recommended to check the spurious
operation of SOTF protection at Hoody SS and submit
a report to SRPC regarding the same .
KPTCL Yet to be informed Pending
Annexure-II
Page 29 of 48
85/II/12 Tripping of 400/220 kV ICT-1at
Guttur Substation26-05-2019
at 10:00 hrs
LV side of 400kV/220kV 315MVA ICT#1 Guttur got
tripped due to CB lockout (B phase)because of low
SF6 gas in the CB
1. KPTCL is recommended to submit a report to SRPC
after the CB pressure leakage problem is attended by
OEM.
2.. KPTCL to ensure that during recharging of Circuit
breakers, cylinders with Non-return valve only are
used to prevent sudden pressure drop in Circuit
breakers.
KPTCL Yet to be informed Pending
85/II/22 Tripping of 400kV Dhoni-
Munirabad line06-06-2019
at 02:01 hrs
Line got tripped at Dhoni end. From DR Zone-3 start,
PSB and A/r block was observed.
KPTCL is recommended to submit a report regarding
PSB maloperation along-with the RM suggested by
OEM. Proper legends shall be ensured for digital
signals at Doni end.
KPTCL Yet to be informed Pending
85/II/27 Tripping of 400/220kV ICT-2 at
Hoody substation16-06-2019
at 19:20 hrs
ICT-2 got tripped on operation of over-flux protection KPTCL is recommended to adopt v/f settings as per
manufacture suggested curve.
v/f setting for alarm: 1.1 time Vnominal; Time delay
10 seconds;
v/f trip setting : v/f is 1.2 time Vnominal;Time delay
60 seconds
KPTCL Yet to be informed Pending
85/II/29 Tripping of 400kV Hiriyur-
Nelamangala line-1 and 400kV
Gooty-Nelamangala line
22-06-2019 at
04:06hrs
400kV Hiryur-Nelamangala line-1 : 'Y' phase bushing
of Hiriyur line-1 reactor failed at Nelamangala end
resuting in a R-Y phase fault. Direct trip was sent to
Hiryur.
400kV Gooty-Nelamangalaline : Line tripped at
Nelamangala end only due to mal-operation of Main-2
distance protection relay (THR).
KPTCL is recommended to submit equipment failure
report to CEA regarding the reactor bushing failure
and also to sort out time synchronization issues of
400kV Hiriyur-Nelamangala line.
KPTCL Yet to be informed Pending
85/II/30 Tripping of 400/220kV ICT-1&2
at Munirabad substation24-06-2019
at 20:50 hrs
400/220kV ICT-1&2 at Munirabad end got tripped due
to operation of High set of backup earth fault relay
during failure of Y phase CT in 220kV Munirabad-
Kalyani steel feeder at Kalyani steel end
KPTCL is recommended to submit equipment failure
report to CEA regarding the CT and PT failure.
KPTCL Yet to be informed Pending
Annexure-II
Page 30 of 48
KPTCL Mail Recieved dated 22-11-2017:
1. coordination of KPCL has been requested for enabling AR lines terminated to
Nagajari.
2. AR will be enabled at Ambewadi end for lines other than Ponda and Xeldom lines
during retrofitting of Back Up protection by Distance protection relay at Ambewadi.
KPTCL Mail dadted 16.12.2017 & Review Meeting dated 19.12.2017:
1. KPTCL informed that Coordination of KPCL has been requested for enabling AR
lines terminated to Nagajari.
--- Pending
2. KPTCL informed that AR would be enabled at Ambewadi end for lines other than
Ponda and Xeldom lines during retrofitting of Back Up protection by Distance
protection relay at Ambewadi. -- Pending
KPTCL mail dated 20.12.2018:
2). Readiness from KPTCL for implementing AR is already confirmed to KPCL. KPCL mail dated 23.03.2019:
1) Proposal will be taken up for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Prepration of
specification is under progress.
KPCL mail dated 13.05.2019:
1) Budgetary offer obtained for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Preparation of estimation
and specification is under progress.
KPCL mail dated 25.05.2019 & 16.07.2019:
1) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval of
NLDC for DPR is awaited. Further, availing administrative approval for issue of NIT
for replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 and preparation of estimation and specification is
under progress. Timeline for completion of work is July 2020.
Status informed during Special Meeting held on 03.06.2016:
1. KPTCL informed that the matter had been taken up with concerned Line Operation
and Maintenance wing to carry out corridor clearance and maintenance as per
schedule to avoid frequent line faults in this corridor. A letter had also been addressed
to Chief Engineer, Bhagalkot zone, to ensure lines in & around Kali complex are
maintained in healthy condition. --- Completed
2. KPTCL assurd that the final modified SPS would be implemented at Nagjheri PH
at the earliest. ------ Pending
3. KPCL informed that Nagjhari- Kodasalli Lines 1 & 2 had been kept in service
since 23.05.2016 @ 08.06hrs.
--- Completed
KPTCL Mail received dated 28-06-2016:
2. Modifications to be carried in Nagzari SPS logic is submitted to SRLDC/SRPC
for verification and approval
Status received vide KPCL mail dated 14.06.2017:
1. Will be reviewed in consultation with EE(RT), KPTCL, Hubli.
3. Both the lines are in charged condition.
KPTCL Mail Recieved dated 22-11-2017:
1) & 3) --- Completed
2). Proposed revision in existing SPS scheme is already submitted to SRLDC/SRPC.,
Yet to be discussed and approved by the SRPC forum. --- Pending
Pending
PendingKPCL/ KPTCL 1. To avoid tripping of transmission lines on transient
faults, KPCL/ KPTCL is recommended to carry out
periodic patrolling of lines, and ensure their proper
maintenance by carrying out jungle/ bushing clearance
and trimming of tree branches within the RoW of
transmission lines as per the SRPC transmission line
patrolling guidelines (available under the menu item
"All Uploads/ Operation/ Miscellaneous/ Transmission
Line Patrolling Protocol / Guidelines for Southern
Region" on SRPC website).
2. KPCL/ KPTCL to review operation of SPS at NPH
for functionality (reduction of generation with tripping
of evacuating lines) and healthiness.
3. KPCL to put 220 kV Kodasalli - Nagjheri D/C lines
into service if more than 200 MW generation from
Kali Complex (with Nagheri Contribution not less than
50 MW) is ensured on sustained basis.
220kV lines from Nagjheri power house started
tripping from 11:00 hrs due to fault in lines. The
sequence of tripping is shown in SOE list. At 12:33
hrs, 220kV Narendra-Ambewadi lines-1&2 got tripped
which resulted in loss of evacuation path to Nagjheri
station resulting in tripping of running Units and
complete outage at Nagjhheri power station. 220kV
Ambewadi station also got de-energized due to tripping
of source feeders i.e. 220kV Narendra-Ambewadi-1&2
and 220kV Nagjheri-Ambewadi-1&2.
22-02-2016 at
12:36 hrs
Complete outage of 220 kV
Nagjheri power station and
220 kV Ambewadi
substation of KPTCL
51/I/3
49/I/3 1. KPCL to provide A/R on all 220 kV lines emanating
from Nagjheri PH.
2. KPTCL to provide A/R on all 220 kV lines
emanating from Ambewadi SS.
KPCL/ KPTCL220kV Nagjheri-Ambewadi line-1 tripped at 13:33 hrs
due to B phase to earth fault. Ambewadi was radially
fed from Nagjheri power station through 220kV
Nagjheri-Ambewadi line-2. Tripping of this line
caused 220kV Bus shut down at Ambewadi and
remaining lines and transformers were hand tripped
Complete outage of 220kV
Ambewadi Substation of
KPTCL
29.10.2015 at
14:34 hrs
Annexure-II
Page 31 of 48
KPTCL Mail dated 16.12.2017:
1) & 3). --- Completed.
2). Proposed revision in existing SPS scheme is already submitted to SRLDC/SRPC.,
yet to be discussed and approved by the SRPC forum --- Pending
Review Meeting dated 19.12.2017:
2. The SPS proposed by KPTCL was discussed and the PCSC forum suggested
certain changes for suitable incorporation. KPTCL agreed to look into the same and
assured that the modified SPS would be furnished by January, 2018.
Review Meeting on 21.12.2018:
2. KPTCL informed that Nagjheri SPS shall be finalised in 1 month.
KPCL mail dated 23.01.2019 & 23.03.2019:
1) .....Completed
2) It shall be reviewd and Implemented by KPCL in coordination with KPTCL.
3) .....Completed
KPCL mail dated 13.05.2019 & 25.06.2019
1. 3. Completed
2) Letter addressed to KPTCL RT dated: 25.03.2019 for review and implementation
of SPS at NPH. Reply is awaited.
Review meeting on 27.06.2019:
2. KPTCL informed that Naghjeri SPS need to be revisited in view of changes in KPCL mail dated 16.07.2019:
1 & 3) Completed.
2) Letter addressed to KPTCL RT dated: 25.03.2019 for review and implementation
of SPS at NPH. Reply from KPTCL is awaited.
PendingKPCL/ KPTCL 1. To avoid tripping of transmission lines on transient
faults, KPCL/ KPTCL is recommended to carry out
periodic patrolling of lines, and ensure their proper
maintenance by carrying out jungle/ bushing clearance
and trimming of tree branches within the RoW of
transmission lines as per the SRPC transmission line
patrolling guidelines (available under the menu item
"All Uploads/ Operation/ Miscellaneous/ Transmission
Line Patrolling Protocol / Guidelines for Southern
Region" on SRPC website).
2. KPCL/ KPTCL to review operation of SPS at NPH
for functionality (reduction of generation with tripping
of evacuating lines) and healthiness.
3. KPCL to put 220 kV Kodasalli - Nagjheri D/C lines
into service if more than 200 MW generation from
Kali Complex (with Nagheri Contribution not less than
50 MW) is ensured on sustained basis.
220kV lines from Nagjheri power house started
tripping from 11:00 hrs due to fault in lines. The
sequence of tripping is shown in SOE list. At 12:33
hrs, 220kV Narendra-Ambewadi lines-1&2 got tripped
which resulted in loss of evacuation path to Nagjheri
station resulting in tripping of running Units and
complete outage at Nagjhheri power station. 220kV
Ambewadi station also got de-energized due to tripping
of source feeders i.e. 220kV Narendra-Ambewadi-1&2
and 220kV Nagjheri-Ambewadi-1&2.
22-02-2016 at
12:36 hrs
Complete outage of 220 kV
Nagjheri power station and
220 kV Ambewadi
substation of KPTCL
51/I/3
Annexure-II
Page 32 of 48
KPCL mail dated 23.01.2019 & 23.03.2019:
1) …Completed.
2) It shall be reviewd and Implemented by KPCL in coordination with KPTCL.
3) …Completed.
KPCL mail dated 10.05.2019 & 25.06.2019:
1. & 3. Completed
2) Letter addressed to KPTCL RT dated: 25.03.2019 for review and implementation
of SPS at NPH. Reply is awaited.
Review meeting on 27.06.2019:
2. KPTCL informed that Naghjeri SPS need to be revisited in view of changes in
system configuration.
KPCL mail dated 16.07.2019:
1 & 3) Completed.
2) Letter addressed to KPTCL RT dated: 25.03.2019 for review and implementation
of SPS at NPH. Reply from KPTCL is awaited.
KPTCL Mail received dated 28-06-2016:
Modifications to be carried in Nagzari SPS logic is submitted to SRLDC/SRPC for
verification and approval
Status received vide KPCL mail dated 14.06.2017:
1. Tripped since there was evacuation problem and there were only two lines NA-1
and NA-2 ---- Completed
2. Will be reviewed in consultation with EE(RT), KPTCL, Hubli. --- Pending
3. Both the lines are in charged condition. --- Completed.
KPTCL Mail Recieved dated 22-11-2017:
2. Proposed revision in existing SPS scheme is already submitted to SRLDC/SRPC.,
yet to be discussed and approved by the SRPC forum. --- Pending
KPTCL Mail dated 16.12.2017:
1) & 3). --- Completed.
2). Proposed revision in existing SPS scheme is already submitted to SRLDC/SRPC.,
yet to be discussed and approved by the SRPC forum --- Pending
Review Meeting dated 19.12.2017:
2. The SPS proposed by KPTCL was discussed and the PCSC forum suggested
certain changes for suitable incorporation. KPTCL agreed to look into the same and
assured that the modified SPS would be furnished by January, 2018.
Review Meeting on 21.12.2018:
KPTCL informed that Nagjheri SPS shall be finalised in 1 month.
53/I/3 1. KPCL to furnish a report on the reasons for Unit-6
tripping at Nagjheri PH.
2. KPCL/ KPTCL to modify suitably the SPS at
Nagjheri Power House such that it would also factor in
the over loading of Ambewadi-Narendra lines.
3. KPCL to put 220 kV Kodasalli - Nagjheri D/C lines
into service if more than 200 MW generation from
Kali Complex (with Nagheri Contribution not less than
50 MW) is ensured on sustained basis.
PendingKPCL/ KPTCLAmbewadi Narendra line-2 tripped on fault and 220kV
ambewadi Narendra line-1 tripped due to over-loading.
Running Units at Nagjheri also tripped during the event
due to tripping of evacuating lines
Tamil Nadu
Complete outage of 220kV
Ambewadi station of
KPTCL and 220kV Nagjheri
of KPCL
18-03-2016 at
14:40 hrs
Annexure-II
Page 33 of 48
Mail dated 18.07.2019
2) Tender has been lodged two times. New indent was reaised on 06.07.19. and
tender floating is expected by August 2019. 3) Tender has been
lodged on 15.07.19 and new indent would be raised for the same shortly.
TANTRANSCO Mail received on 19-02-2016 and 24-03-2016:
Revision of Bus Bar Protection setting was carried out. The stabilizing voltage
setting was raised from 410 to 450 volts. After completing the necessary test, the bus
bar protection put in to service on 29.12.2015.
Mail Received on 27-04-2016 ,16-06-2016,25-07-2016 & 24-09-2016:
Revision of Bus Bar Protection setting was carried out. After completing the
necessary test, the bus bar protection put in to service on 29.12.2015.
Mail received on 10-11-2016 & 20.12.2016:
Provision of Bus Coupler bay arrangement was included in the Upgradation works
proposed and the same was sanctioned by MoP through PSDF.
Numerical relay allotted and being commissioned.
Mail received on 20-02-2017:
Numerical BBP relay was commissioned on 02.02.2017
Status received vide mail dated 12.04.2017 & 01.06.2017 & 15-06-2017:
Numerical BBP relay was commissioned on 02.02.2017.
Provision of Bus Coupler bay arrangement was included in the Upgradation works
proposed and the same was sanctioned by MoP through PSDF.
Status received vide mail dated 04.08.2017:
Numerical BBP relay was commissioned on 02.02.2017.
PendingTANGEDCO1. TANGEDCO to replace existing Check-Zone relay
with a new one possessing required performance.
2. TANGEDCO to take steps to provide numerical
busbar protection at their 220 kV Tuticorin TPS.
TANGEDCO may also explore providing dual CT’s
(on either side) for all B/S breaakers at the time of
commissioning of numerical BBP, if there were no
space constraints.
3. TANGEDCO to take steps to provide for standalone
Event Logger (EL) and standalone Disturbance
Recorder (DR) with automatic downloading facility to
a centralized server.
Failure of Bus Section-I Y-ph CT resulted in operation
of bus-bar protection for Bus Sections -I & II. Running
Units#1, 4 and 5, 230 kV Kayathar, 230kV
Kudankulam, 230kV Sterlite, Station Transformer-1, 2
& 3 got tripped during the incident. Unit – 2 & 3 were
not in service.
25-01-2017 at
22:36 hrs
Tripping of running Units &
230kV feeders at Tuticorin
TPS of TANGEDCO
(Gen Loss: 640 MW)
62/II/7
Busbar protection got operated for a fault in 230kV
Mywadi-Anaikadavu line
TANTRANSCO to examine the feasibility of
providing two main-zone operation for bus bar
protection by exploring various alternatives like
replacing existing bus-coupler CB with a hybrid bus-
coupler CB that comes with inbuilt CT, replacing
existing BBP relay with another suitable relay that
supports two main-zone operation, and implement the
same.
TANGEDCO mail dated 15.04.2017:
1) New Relay is tested and ready for replacement.Now all 5 units are in service.The
relay will be replaced when lesser units are in service. --- Pending
2.a)Steps are taken to renovate & mordernization of all the control panel into
Numerical based control panels. --- Pending
2.b) Since 230 KV indoor switchyard has no spare space providing dual CT`s is not
fessible. -- Completed
3) Procurement of EL & DR is under progress. --- Pending
TANGEDCO mail dated 26.04.2017:
1) Check zone New Relay is replaced on 17.04.2017 -- Completed.
2. --- Pending
3. --- Pending
TANGEDCO mail dated 13.12.2017:
2).P & C wing gives clearance to TTPS to procure the Bus bar protection relays and
protection relays and SER / DR system vide
Lr.CE/P&C/SE/D/EEPC4/AEE3/F.TECH/D.27/17 Dated: 05.10.2017. To get
administrative approval budgetary offer has bar protection relay from various
companies ----Pending
3). SRPC vide Lr: SRPC/SE- III/CEA/2017/6450/DT:27.10.2017 gives features of
SER/DR. Budgetary offer will be called for SER / DR having above features. ---
Penidng
Review Meeting dated 19.12.2017:
2) & 3) The issue was discussed and TANGEDCO was asked to provide time-line for
implementing the recommendations.
Mail dated 29.01.2018:
Procurement work is under progress and will be completed by December 2018.
Review Meeting on 21.12.2018:
TANTRANSCO informed that Tender would be floated by January 2019 and
Procurement is expected by APril 2019. Works would be completed by December
2019.
Review meeting on 27.06.2019:
2. Tender issued. Timline- July 2020.
3. Tender has to be issued. Timline- July 2020.
21-12-2015 at
6:28 hrs
50/I/3 Complete outage of 230kV
Mywadi station of
TANTRANSCO
PendingTANTRANSCO
Status?
Annexure-II
Page 34 of 48
Status received vide mail dated 18-09-2017 & 31-20-2017:
Numerical BBP relay was commissioned on 02.02.2017. Provision of CT in Bus
Coupler bay is arranged and zone segregation will be provided.
Status received vid email dated 12-12-2017:
Numerical BBP relay was commissioned on 02.02.2017. Provision of CT in Bus
Coupler bay has been allotted. Zone segregation will be provided after commissioning
of CT.
Review Meeting dated 19.12.2017:
TANTRANSCO informed that the recommendation would be complied with by
March, 2018.
TANTRANSCO Mail received on 25-01-2018:
Provision of CT in Bus Coupler bay is arranged and zone segregation will be
provided. Timeline: March-2018.
Status received vid email dated 11-12-2018:
Civil work completed & CT will be commissioned after strengthening Bus .2
conductor jumpers.Awaiting Bus LC Time line before January 2019.
TANTRANSCO MAIL DATED 23.01.2019:
Erection under progress will be completed before 31.01.2019
TANTRANSCO MAIL DATED 19.03.2019:
Buscoupler bay will be commissioned by June 2019
TANTRANSCO MAIL DATED 13.06.2019:
Buscoupler bay configuation in BBP will be completed by June 2019. Bus
segregation will be ensured by 31.12.2019 after attending Isolator status feedback.
TANTRANSCO MAIL DATED 18.07.2019:
Buscoupler bay configuation in BBP will be completed by June 2019. Bus
segregation will be ensured by 31.12.2019 after attending Isolator status feedback.
Mail recieved on 25-07-2016 & 24-09-2016:
TANTRANSCO: Auto Transformer-2 HV side Bus isolator 'C'-phase support
insulator of 230kV Southern Bus was replaced and Bus Bar Protection scheme was
restored on 12.05.2016.
Status received vide mails received on 10-11-2016 & 20.12.2016 & 12.04.2017
& 01.06.2017 & 15-06-2017 & 04.08.2017 & 18.09.2017:
CT is not available in the Bus Coupler bay for zone segregation. CT latch relay is to
be provided for all bays for zone segregation.
Status received vide mails received on 31-10-2017 & 12-12-2017:
Numerical Bus bar protection panel allotted and will be commissioned with zone
segregation..
Review Meeting dated 19.12.2017:
TANTRANSCO informed that Numerical BBP would be commissioned by March,
2018.
TANTRANSCO MAIL DATED 22.05.2018 & 08.06.2018:
Numerical Busbar protection relay commissioned on 14.05.2018
TANTRANSCO MAIL DATED 23.07.2018:
Control & Status of isolator feedeback to be provided by replacement of Drive
Mechanism box.
TANTRANSCO MAIL DATED 29.08.2018:
Control & Status of isolator feedeback to be provided by replacement of Drive
Mechanism box.
TANTRANSCO MAIL DATED 11.09.2018:
Control & Status of isolator feedeback to be provided by replacement of Drive
Mechanism box. Timeline requested upto Dec 2018.
Status received vid email dated 11-12-2018:
1. TANTRANSCO: Estimate sanctioned for replacement of defective isolator status
feedback. Work under progress. Lightning mask work under progress will be
completed within three days.
Review Meeting on 21.12.2018:
TANTRANSCO informed that Double bus operation would be provided by March,
Pending55/I/1
(GD)
Complete outage of 230 kV
Gummidipoondi Station of
TANTRANSCO
12-05-2016 at
12:15 hrs
Flashover of Auto Transformer- 2 HV
B-phase Isolator supporting insulator of 230kV
Southern Bus occurred at Gummidipoondi station. At
the time of fault, Bus bar protection relay was not in
service for pre-commissioning testing of Auto
Transformer-2. All feeders got tripped due to operation
of zone-2 protection from remote ends.
Busbar protection got operated for a fault in 230kV
Mywadi-Anaikadavu line
TANTRANSCO to examine the feasibility of
providing two main-zone operation for bus bar
protection by exploring various alternatives like
replacing existing bus-coupler CB with a hybrid bus-
coupler CB that comes with inbuilt CT, replacing
existing BBP relay with another suitable relay that
supports two main-zone operation, and implement the
same.
TANTRANSCO TANTRANSCO to take steps to provide double-bus
operation at their 230 kV Gummidipoondi SS.
21-12-2015 at
6:28 hrs
50/I/3 Complete outage of 230kV
Mywadi station of
TANTRANSCO
PendingTANTRANSCO
Annexure-II
Page 35 of 48
TANTRANSCO MAIL DATED 19.03.2019:
New 230kV isolators have been allotted for replacement of defective isolators. Hence
time line requested upto June.2019.
TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
New 230kV isolators have been allotted for replacement of defective isolators. Hence
time line requested uptoSep.2019
Pending55/I/1
(GD)
Complete outage of 230 kV
Gummidipoondi Station of
TANTRANSCO
12-05-2016 at
12:15 hrs
Flashover of Auto Transformer- 2 HV
B-phase Isolator supporting insulator of 230kV
Southern Bus occurred at Gummidipoondi station. At
the time of fault, Bus bar protection relay was not in
service for pre-commissioning testing of Auto
Transformer-2. All feeders got tripped due to operation
of zone-2 protection from remote ends.
TANTRANSCO TANTRANSCO to take steps to provide double-bus
operation at their 230 kV Gummidipoondi SS.
Annexure-II
Page 36 of 48
The issue was discussed in PCSC-58 meeting held on 18.10.2016, when PCSC forum
agreed to de-link the implementation of the Item from the scope of Protection Audit
Recommendations (PAR), and pursue it as part of PCSC Recommendations.
Status received vide mails dated 10.01.2017 & 12.04.2017 & 01.06.2017 &15-06-
2017 & 04.08.2017 & 18.09.2017 & 31-10-2017& 12-12-2017:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram
end in a phased manner.
TANTRANSCO MAIL DATED 22.05.2018:
TANTRANSCO informed that the recommended works of providing different make
Relays for Main-I & Main-II are targeted to be completed by September, 2018.
TANTRANSCO MAIL DATED 08.06.2018:
provision of Different make Relays for Main-I & Main-II will be completed by
September, 2018.
TANTRANSCO MAIL DATED 23.07.2018:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram
end in a phased manner. Timeline: September-2018.
TANTRANSCO MAIL DATED 29.08.2018 & 11.09.2018:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram
end in a phased manner. Timeline: September-2019.
TANTRANSCO MAIL DATED 11-12-2018:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram TANTRANSCO MAIL DATED 23.01.2019:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram
end in a phased manner. Timeline: September-2019.
TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram
end in a phased manner. Timeline: September-2019
14-09-2016 at
11:13Hrs
Bus Bar Protection (Zone-2) of 230 kV Bus-B got
operated at Alamathy Station during fault in 230 kV
Alamathy-Korattur feeder.
1. TANTRANSCO to check the healthiness of BBP
relay by conducting stability test, and take appropriate
remedial action like increasing voltage settings,
ensuring the healthiness of CT’s, using CT’s with
similar characteristics (equal saturation effects &
equal winding resistances) etc. at their 230 kV
Alamathy SS.
2. TANTRANSCO to replace the existing high-
impedance BBP relay with its low-impedance/
numerical variant so as to accommodate variation in
CT characteristics at their 230 kV Alamathy SS.
58/II/17 Multiple tripping at 230 kV
Alamathy Station
TANTRANSCO Pending
Mail received on 10-11-2016 & 20.12.2016:
1. The Bus Bar Protection scheme will be tested for healthiness including the CT
circuits.
2. High impedance BBP relay will be replaced by Numerical relay.
Status received vide mails dated 10.01.2017 & 12.04.2017 & 01.06.2017 & 15-06-
2017:
1. The Bus Bar Protection scheme was tested for healthiness including the CT
circuits. AREVA make CTs in Alamathy SS are having different kneepoint voltage
for the cores. CT cores of higher knee point voltage has been choosen for BBP in
230kV Korattur, 230kV OPG-1 & 230kV OPG-2 feeders on 29.11.2016. ----
Completed.
2. High impedance BBP relay will be replaced by Numerical relay. --- Pending,
Status received vide mails dated 04.08.2017 & 18.09.2017 & 31-10-2017 & 12-
12-2017.
1. ---- Completed
2. High impedance BBP relay will be replaced by Numerical relay. --- Pending
Review Meeting dated 19.12.2017:
2) TANTRANSCO informed that Numerical BBP would be provided by April, 2018
--- Pending
TANTRANSCO mail received on 25-01-2018:
1. --- Complied.
2. High impedance BBP relay will be replaced by Numerical relay. Timeline: April-
2018.
TANTRANSCO MAIL DATED 22.05.2018 & 08.06.2018 & 23.07.2018:
2.Numerical BBP relay will be provided. Timeline: Sep-2018.
TANTRANSCO MAIL DATED 29.08.2018 & 11.09.2018:
1. Complied
2.Numerical BBP relay will be provided. Timeline: Sep-2018.
PendingTANTRANSCO
Different type and Make of distance protection relays to be provided for Main-I & Main-II protection for 230kV feeders at 400 kV Sunguvarchathiram & 230 kV
Sunguvarchathiram Substation [Carry-Over from Protection Audit Recommendations]
58
Annexure-II
Page 37 of 48
TANTRANSCO MAIL DATED 11-12-2018:
Numerical BBP relay to procured. Timeline: Sep-2019.
TANTRANSCO MAIL DATED 23.01.2019:
Numerical BBP relay to be procured. Timeline: Sep-2019.
TANTRANSCO MAIL DATED 19.03.2019 & 13.06.2019 & 18.07.2019:
Numerical BBP relay to be procured. Timeline: Sep-2019.
Review meeting on 27.06.2019:
1. TANTRANSCO to check the healthiness of BBP
relay by conducting stability test, and take appropriate
remedial action like increasing voltage settings,
ensuring the healthiness of CT’s, using CT’s with
similar characteristics (equal saturation effects &
equal winding resistances) etc. at their 230 kV
Alamathy SS.
2. TANTRANSCO to replace the existing high-
impedance BBP relay with its low-impedance/
numerical variant so as to accommodate variation in
CT characteristics at their 230 kV Alamathy SS.
58/II/17 Multiple tripping at 230 kV
Alamathy Station
Mail received on 10-11-2016 & 20.12.2016:
1. The Bus Bar Protection scheme will be tested for healthiness including the CT
circuits.
2. High impedance BBP relay will be replaced by Numerical relay.
Status received vide mails dated 10.01.2017 & 12.04.2017 & 01.06.2017 & 15-06-
2017:
1. The Bus Bar Protection scheme was tested for healthiness including the CT
circuits. AREVA make CTs in Alamathy SS are having different kneepoint voltage
for the cores. CT cores of higher knee point voltage has been choosen for BBP in
230kV Korattur, 230kV OPG-1 & 230kV OPG-2 feeders on 29.11.2016. ----
Completed.
2. High impedance BBP relay will be replaced by Numerical relay. --- Pending,
Status received vide mails dated 04.08.2017 & 18.09.2017 & 31-10-2017 & 12-
12-2017.
1. ---- Completed
2. High impedance BBP relay will be replaced by Numerical relay. --- Pending
Review Meeting dated 19.12.2017:
2) TANTRANSCO informed that Numerical BBP would be provided by April, 2018
--- Pending
TANTRANSCO mail received on 25-01-2018:
1. --- Complied.
2. High impedance BBP relay will be replaced by Numerical relay. Timeline: April-
2018.
TANTRANSCO MAIL DATED 22.05.2018 & 08.06.2018 & 23.07.2018:
2.Numerical BBP relay will be provided. Timeline: Sep-2018.
TANTRANSCO MAIL DATED 29.08.2018 & 11.09.2018:
1. Complied
2.Numerical BBP relay will be provided. Timeline: Sep-2018.
Pending
15-09-2016 at
22:14 hrs
Bus Bar Protection (Zone1) of 230kV Bus-A got
operated at Alamathy Station during fault in 230 kV
Alamathy-OPG-1 feeder.
TANTRANSCO
Annexure-II
Page 38 of 48
64/1/4 Complete outage of North
Chennai TPS STG-1
26-03-2017
at 23:14hrs
Tripping of evacuating lines due to fault led to tripping
of running Unit at NCTPS Stg-1
1. TANTRANSCO to take steps to complete insulator
replacement works on the 230 kV lines owned by them
in NCTPS area within 6 months.
2. TANTRANSCO to take steps to implement A/R on
all 230 kV lines emanating from NCTPS-I at the
earliest.
TANTRANSCO Status received vide mails dated 04.08.2017 & 18.09.2017 & 31-10-2017:
1. All the Porcelain insulators were replaced with Polymer insulators in 230kV
NCTPS-I - Tondiarpet feeders - 1 & 2.
---- Completed
2. AR will be implemented on all 230kV lines emanating from NCTPS-I. --- Pending
Status received vid email dated 12-12-2017:
1. Completed
2. The scheme needs modification to enable AR, since AR was not envisaged for this
station during commissioning. AR will be implemented on all 230kV lines emanating
from NCTPS-I within six months. --- Pending
Review Meeting dated 19.12.2017:
2) TANTRANSCO informed that A/R would be implemented on all 230 kV lines
emanating from NCTPS-I by June, 2018.
TANTRANSCO mail received on 25-01-2018:
1. Complied.
2. The scheme needs modification to enable AR, since AR was not envisaged for this
station during commissioning. AR will be implemented on all 230kV lines emanating
from NCTPS-I within six months. Timeline:June-2018.
Pending
TANTRANSCO MAIL DATED 22.05.2018:
2. The scheme needs modification to enable AR, since AR was not envisaged for this
station during commissioning. AR will be implemented on all 230kV lines emanating
from NCTPS-I Timeline:Sep -2018.
TANTRANSCO mail received on 08-06-2018:
1. Complied.
2. The scheme needs modification to enable AR, since AR was not envisaged for this TANTRANSCO MAIL DATED 11-12-2018:
2. Enabling AR pending for 3 feeders. ( Sriperumpudhur end breaker problem,
Tondiarpet & Alamathy feeder . static relay to be replaced. Timeline - 1 year
TANTRANSCO MAIL DATED 23.01.2019:
Enabling AR pending for 3 feeders. ( Sriperumpudhur end breaker problem,
Tondiarpet & Alamathy feeder . static relay to be replaced. Timeline -Sep 2019
TANTRANSCO MAIL DATED 19.03.2019 & 13.06.2019 & 18.07.2019:
Enabling AR pending for 3 feeders. ( Sriperumpudhur end breaker problem,
Tondiarpet & Alamathy feeder . static relay to be replaced. Timeline -Sep 2019
77/II/9 Multiple trippings at
400 kV Manali Substation
TANTRANSCO to refer the issue of selective tripping
of 400 kV side breakers, and non-tripping of 230 kV
side breakers due to operation of Densimeters on low
pressure in the instant case to their OEM, and share
OEM’s advice/ remedy in this regard.
TANTRANSCO mail dated 11.09.2018:
OEM will be referred
Review Meeting on 21.12.2018:
TANTRANSCO was asked to update the status.
TANTRANSCO MAIL DATED 23.01.2019, 19.03.2019 & 13.06.2019:
The issue was referred with OEM & reply awaited.
Review meeting on 27.06.2019:
OEM reply shall be communicated by end of July 2019
TANTRANSCO mail dated 18.07.2019:
The issue was referred with OEM & reply awaited
Pending
Annexure-II
Page 39 of 48
79/I/3 Complete outage of 230 kV
Thiruvalam Substation
05-10-2018 at
14:32 hrs
Bus-1 got tripped at 230 kV Thiruvalam substation due
to spurious LBB relay (independent) operation of
230kV Thiruvalam Chittoor line. 230kV Thiruvalam
substation was under single bus operation; hence
operation of LBB protection resulted in tripping of all
connected elements resulting in the complete outage
TANTRANSCO to take steps to implement multi-bus,
multi-zone operation (Double-bus operation) at their
230 kV Thiruvalam SS by December, 2018.
TANTRANSCO TANTRANSCO MAIL DATED 11-12-2018:
Due to space constraint, the equipments could not be erected.
Review Meeting on 21.12.2018:
It was noted that the station was on a single (Main) bus and there was not even
transfer bus. In view of the importance of 230 kV Thiruvalam SS, TANTRANSCO
was asked to take steps to provide dobule-bus operation at their 230 kV Tiruvalam
SS.
TANTRANSCO MAIL DATED 23.01.2019 & 19.03.2019:
Feasibility for providing hybrid breaker / shifting of bays will be studied & action
will be taken. Time upto Sep 2019
TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
Bus segregation will be ensured by providing bus coupler bay by extending the
existing Bus.Time line 31.12.2019.
Pending
80/II/12 Tripping of all elements
connected to 230 kV
Anaikadavu SS
06-11-2018 at
21:35 Hrs
Triggering incident was failure of R-ph PT of 230 kV
Anaikadavu Bus-1. 230 kV Bus bar protection of bus-
1 operated resulting in tripping of all the connected
elements. 230 kV Anaikadavu was on single bus
operation due to failure of Bus-2 PT during antecedent
conditions.
1) TANTRANSCO to adopt recommended OVR,
Stage-I and OVR, Stage-II protections at their 400 kV
Anaikadavu and 400 kV Rasipalayam stations, and to
ensure that OVR-I_START signal is configured for
triggering corresponding Event Logger (EL), and OVR-
I_TRIP is configured for triggering corresponding
Event Logger (EL) and Disturbance Recorder (DR).
2) TANTRANSCO to take steps to restore multi-bus,
multi-zone operation at their 230 kV Anaikadavu SS at
the earliest.
TANTRANSCO TANTRANSCO MAIL DATED 23.01.2019 & 19.03.2019:
1……Complied
2.Bus PT is to be supplied by the Turnkey contractor will be replaced by 31.03.2019
TANTRANSCO MAIL DATED 13.06.2019:
Bus PT is to be supplied by the Turnkey contractor
Review meeting on 27.06.2019:
Timeline requested upto December 2019.
TANTRANSCO mail dated 18.07.2019:
Bus PT is to be supplied by the Turnkey contracto
Pending
82/I/1 Complete outage of 400kV
Sriperumbudur station
28-01-2019
at 01:15 Hrs
Failure of ‘R-phase’ HV side Current transformer (CT)
of 315MVA 400/230kV ICT-3 at 400kV
Sriperumbudur substation (400kV TANTRANSCO
switchyard).
1) TANTRANSCO to ensure proper legends for DR
Digital signals and all required events(including CB
status, Type of protection operated) are captured in
Event logger.
2) TANTRANSCO to extend BBP trip from BusBar
relay to 86A (with source-1 DC) in addition to 86B
(with source-2 DC), or to provide Common trip relay
96 with redundant DC supply.
3) TANTRANSCO to inform the action plan with
timelines for providing Numerical BBP at
Sriperumbdur SS .
4) TANTRANSCO to check the healthiness of all
CT’s in the stationand submit a report regarding the
same to SRPC to prevent any such occurrence in
future.
TANTRANSCO TANTRANSCO MAIL DATED 13.06.2019:
1. At present Duobias relay avaiable I/O configuration could not be carried out.after
changing the relay Digital signals will be configured
2.COMPLIED
3.Provision of Numerical BBP relay covered under R&M work. Tender under
progress.
4.out of 30 CTs, 21 No CTs have been replaced with new one.
Review meeting on 27.06.2019:
1. , 3. Timeline requested upto July 2020.
2. Complied
4. Timeline requested upto September 2019.
TANTRANSCO mail dated 18.07.2019:
1. At present Duobias relay avaiable I/O configuration could not be carried out.after
changing the relay Digital signals will be configured
2.COMPLIED
3.Provision of Numerical BBP relay covered under R&M work. Tender under
progress.
4.out of 30 CTs, 21 No CTs have been replaced with new one.
Pending
83/I/7 Complete outage of
230kV/110kV KR Thoppur
Substation of
TANTRANSCO
11-04-2019
at 13:16Hrs
Triggering incident was failure of Y-ph CT of Bus
Coupler at 230kV KR Thoppur(Salem) SS. Bus bar
protection of Bus-1 and Bus-2 operated resulting in the
tripping of all the connected elements at 230kV KR
Thoppur SS. 400kV/230kV ICT#1 and 2 at Salem also
got tripped during this event.
1.TANTRANSCO informed that replacement of
mechanical relay by Numerical relay is under progress
and it is recommended to submit the action plan
regarding the same with proper time-lines.
2.TANTRANSCO is also recommended to send
equipment failure report to CEA regarding failure of
Bus coupler CT.
TANTRANSCO TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
1. Replacement of numerical relay under progress
2.Equipment failure report will be sent
Pending
Annexure-II
Page 40 of 48
83/II/13 230kV Bus dead at 230/110
kV Pugalur
14-03-2019 at
13:24 hrs
Triggering incident was R-phase breaker failure in
230kV Pugalur end of Budansandhai feeder. LBB
operated resulting in tripping of all connected elements.
As reported, 230kV side was on single bus operation
since bus sectionalizer provision is not there. 110kV
side connected feeders did not trip.
TANTRANSCO is recommended to furnish
equipment failure report to CEA regarding failure of
CB.
TANTRANSCO TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
Equipment failure report will be sent
Pending
85/II/1 Tripping of 400/230kV
MANALI ICT-3
13-05-2019 at
2:42 hrs
ICT-3 got tripped on the activation of HV REF
protection. During test charging of 110 kV Manali-
ETPS -1 , the 110 kV ETPS -1 got tripped on the
activation of Back up relay and Distance relay failed to
act
1. TANTRANCO is recommended to sort out the
malfunctioning of ICT Ref protection in consultation
with OEM and submit a detailed report regarding the
same in 1 month time.
2. TANTRANSCO is recommended to ensure proper
labelling of all digital signals in Disturbance recorders
of lines and ICTs at Manali SS.
TANTRANSCO Yet to be informed Pending
85/III/6 400 KV Thiruvelam – Palavadi
line-1
28-05-2019 at 18:04
hrs
B-phase to earth fault. A/r attempt could not be validated. TANTRANSCO is recommended to check sending of DT from
Palvadi end during 3-ph trip at Palvadi. The time
synchronization issues between Thiruvalem and Palvadi shall
also be rectified.
TANTRANSCO Yet to be informed Pending
85/IV/6 Tripping of 400kV Kayathar-
Kanarpatty line-1 & 2
10-06-2019 at 12:22
hrs
Line-1 & 2 tripped at Kanarpatty end due to spurious DT sent
from kayathar end. Feeder did not trip at Kayathar end
TANTRANSCO is recommended to submit a report regarding
the problem with PLCC panel at Kayathar along-with
Remedial Measures suggested by OEM.
TANTRANSCO Yet to be informed Pending
Annexure-II
Page 41 of 48
KSEB Mail received vide dated 17.01.2017:
1. 110 kV bus bar protection progressing ----Pending
2. Connection of 220kV earth mat and 110 kV plate earthing system completed.----
Completed
3. Redundancy of 110V DC system in progress. Complete independent redundancy is
not practical for the time being. 48 V DC redundancy was already there. ----
Pending
4. Instead of stand alone event logger, SCADA system of 110 kV feeder is expected
to be completed by the end of 2017. SCADA system of 220kV side will be taken up
Status received vide mail dated 12-12-2017:
1. Detailed engineering of the scheme has been completed. Material procurement is in
progress. ---Pending
2.,3. ---- Completed
4. The SOE and DR are available with time stamping from the numerical relays.
Hence stand alone event logger is not necessary ----- Completed
Status received vide mail dated 11-12-2018:
Work has been already tendered. It is expected that purchase process will completed
Status received vide mail dated 03.05.2019:
Sanction to issue purchase order in progress. Time Frame is January 2020 .
Review meeting on 27.06.2019.
1. BBP will be commissioned by December 2019.
2.,3.,4. Completed
79/I/1 Complete Outage of 220 kV
Idukki Power Station
01-10-2018 at
04:16 hrs
Triggering incident was R-Ph fault in 220kV Idukki-
Kalamassery line-2. R-phase pole of breaker didn’t
open at Idukki end. LBB of Bus-2 operated resulting in
tripping of all connected elements along with running
Unit#4 at Idukki and 50MVA station transformer. At
the same time, 220kV Idukki Kalamassery line-1 also
got tripped at Idukki end. Subsequently running Units 1
and 2 also tripped on Governor oil Low Pressure due to
loss of AC supply. This resulted in complete outage of
1). KSEBL to check & correct the LBB time setting
employed at their Idukki PH to 200 msec.
2). KSEBL o ensure that DR’s & EL’s of all
Protection Relays (PR’s) at their Idukki PH are
configured for recording all mandated protections &
signals.
KSEBL Status received vide mail dated 11-12-2018:
1) Present setting is 180ms.OEM(ABB) suggests that it will give around 200ms
delay as it is having inherent delay is of around 20ms(ie, 180ms +20ms
=200ms).With this setting the fault clearence is found after 220ms.So further revision
may be carried out after discussion.
2)Breaker status will be ready only after completing the GOOSE network as part of
renovation of all feeder panels and Idukki first stage units by June 2019 .
Pending
80/II/5 Multiple trippings at 220 kV
Madakathra station
15-10-2018 at
08:57 Hrs
Triggering incident was Y-phase to ground fault in
220kV Madakathra – Palakkad_KL (Ellapully) line
due to flashover of pilot insulator string. Auto-reclose
was successful at Madakathra end. At the same time
bus differential relay Zone-C mal-operated resulting in
tripping of all elements connected to the bus.
KSEBL to take steps to replace the existing static
(high impedance type) 220 kV BBP with numerical
Busbar protection at their 220 kV Madakathara SS.
KSEBL Status received vide mail dated 11-12-2018:
In progress
Status received vide mail dated 19.03.2019:
Status as on 18.03.2019: Estimate sanctioned by CE(Transmission North ) and have
prepared the technical specifications.Tendering procedures are yet to get started.
Status received vide mail dated 03.05.2019:
Pending
Kerala
PED
Triggering incident was conductor snapping in 110 kV
Kalamassery- Kaloor feeder
1. Time-frame?58/I/1
(GD)
KSEB to take steps to provide the following at their
220/ 110 kV Kalamassery SS:
1. Busbar protection at 110 kV level
2. Connecting 220 kV and 110 kV sides on to a
common earthmat
3. Redundant DC supply for both protection (220 V)
and communication (48 V) applications
4. Stand-alone Event Logger
KSEB Pending23-08-2016
at 11:20 hrs
Complete outage of 220 kV
Kalamassery Substation
Annexure-II
Page 42 of 48
82/I/5 Complete Outage of 220kV
Bhramapuram substation of
KSEB
08-02-2019 at
10:28 hrs
Complete outage of 220kV Brahmapuram SS occurred
due to suspected mal operation of Bus Bar protection.
1) KSEBL to furnish detailed report regarding the
healthiness of BBP operation at 220kV Brahmapuram
after testing of the same on 12th April 2019.
2) KSEBL to submit the action plan regarding
(i) Replacing of the Static High impedance BBP
(using CRM relays) with Numerical BBP.
(ii) Replacement of CRM relays and relays with no
Disturbance recording facilitites.
KSEBL Status received vide mail dated 03.05.2019:
1) Detailed report sent on 02.05.2019…..Completed.
2) As reported earlier in this regard, the permanent solution to this problem is to
replace the existing high impedance static relay with a low impedance numerical
relay. The station authorities have already initiated action to implement the same by
June 2020.
Pending
84/I/3 Complete outage of 220 kV
Edamon SS of KSEB
27-05-2019 at
12:30 hr.
Triggering incident was three phase to earth fault in
220 kV Edamon Bus 1 and 2. Bus 1 and 2 Bus bar
protection operated resulting in the tripping of all
connected elements.
1.KSEBL may develop proper operational code for
procedures to be followed while performing operations
in switchyard and sensitize their operators to reduce
operational errors. 2.ksEBL to ensure time
synchronization of relays at 220 kV Edamon SS.
KSEBL KSEBL mail dated 30.07.2019:
1. proper operrational code is avilalable in 220kV SS Edamon
2. All 220KV relays of Edamon substation are synchronized with GPS clock . Out of
this, 3 relays are having hardware issues with time synchronisation switch . This
problem will be resolved by August 2019 itself.
Pending
85/I/2 Complete outage of 220kV
Pothenkode Substation of
KSEB
04-07-2019
at 01:18 hrs
Triggering incident was failure of suspension insulator
of 220kV Pothenkode – Trivendrum ckt-2. Bus bar
protection of Bus-1 and Bus -2 operated resulting in
tripping of all connected elements.
1. KSEBL is recommended to investigate the non-
operation of zone selective Busbar Operation at 220/
110kV Pothencode SS and submit detailed report
regarding reasons for the same alongwith remedial
measures taken.
2. KSEBL is recommended to ensure time
synchronization of relays at 220/ 110kV Pothencode
SS.
KSEBL Yet to informed Pending
85/II/9 Tripping of 220KV Sabarigiri-
Theni line23-05-2019
at 16:12 hrs
Line tripped on operation of DEF at Theni end KSEBL is recommended to configure in DR and EL
the pick up and operation of relevant distance
protection zones in the event of distance protection
operation.
KSEBL Yet to informed Pending
82/II/6 Tripping of 400/220 kV ICT-
1 at Khammam
27-01-2019
at 14:33hrs
ICT-1 at Khammam tripped on operation of IV side
non directional Over-current high set during failure of
L.A in 220kV Khammam (Budhidampadu)-Suryapet
line-2
PGCIL (SR-I) to immediately take necessary actions
to raise the Highset pick up current setting as per
protection standards since unwarranted tripping of ICT
for fault on 220kV line compromises the reliability of
Power system. In any case the transformer protection
should not encroach into protection zone of nearby
protection element.
PGCIL (SR-I) Review meeting on 27.06.2019:
PGCIL (SR-I) informed that the ICT high set settings have been sent by mail
Pending
84/II/3 Tripping of 400kV KTPS-
Khammam line
11-04-2019 at 13:59 hr.Line tripped on operation of overvoltage stage-1
protection at KTPS end and DT received at Khammam
end. Phase voltages at KTPS end could not be verified
from the DR furnished.
PGCIL (SR-I) to ensure time synchronization of DR
and EL at Khammam end.
PGCIl (SR-I) Yet to be informed Pending
80/II/9 Tripping of 400/220 kV ICT-
2 at Bangalore (Somanahalli)
26-10-2018 at
12:10 Hrs
400/220 kV ICT-2 at Bengaluru (Sonamahalli) tripped
due to operation of LV side over flux protection which
in turn was due to suspected 220 kV CVT problem.
PGCIL (SR-II) to configure DR’s & EL’s all
protection relays at their 400/ 220 kV Somanahally SS
for all mandated protections and signals.
PGCIL (SR-II) Review meetinmg on 27.06.2019:
PGCIL (SR-II) was asked to furnish the status of implementation of the
recommendation at the earliest.
Pending
84/II/2 Tripping of 400kV
Somanahalli-Dharmapuri
line-2
07-04-2019 at
18:02 hr.
Line tripped on operation of over voltage stage-1
protection at Somanahalli. Somanahalli end DR: Vr-
240kV, Vy-253kV, Vb-241kV. Y-phase voltage was
higher than R and B phase
1. PGCIL (SR-II) to configure OVR start and OVR
trip signal in Event logger to facilitate verification of
adopted OVR grading.
2.PGCIL (SR-II) to ensure time synchronization of
DR and EL at Somanahalli end and Dharmapuri end.
PGCIL (SR-II) Yet to be informed Pending
84/II/15 Tripping of 400kV Bus-1
and connected elements at
400kV Bidadi substation
25-04-2019 at 08:01 hr.Triggering incident was failure of R-ph CB of bus
reactor at 400kV Bidadi. Bus bar protection of Bus-1
operated resulting in the tripping of all elements
connected to Bus-1
1. PGCIL (SR-II) was requested to send the
equipment failure report to CEA.
2.PGCIL (SR-II) is recommended to share the
feedback of OEM regarding decomposition of SF6 gas.
PGCIL (SR-II) Yet to be informed Pending
PGCIL (SR-I) & PGCIL (SR-II)
Annexure-II
Page 43 of 48
85/II/8 Tripping of 765/400kV ICT-
1 and 2 at Kurnool
substation
21-05-2019 at
18:11 hrs
ICT 1 and 2 got tripped due to maloperation of
Bucholz relays during the charging of 400KV Kurnool-
Nanoor line 1 which tripped on SOTF
PGCIL (SR-I) is recommended to submit a detailed
report regarding operation of Buchholz relay of 765/
400kV ICT 1& 2 during through fault after
consultation with OEM along-with the remedial
measures taken to prevent occurrence of any such
incidence in future.
PGCIL (SR-I) Yet to be informed Pending
85/II/16 Tripping of 400kV Tumkur-
Bidadi line-1&2, 400kV
Tumkur-Cuddapah line-2,
400kV Tumkur-Pavagada
line-2
29-05-2019 at
6:11 hrs
Lines tripped due to Y-N & Y-B phase to earth fault PGCIL (SR-2) is recommended to submit Equipment
failure report to CEA regarding the failed LA.
PGCIL (SR-II) Yet to be informed Pending
85/II/18 Tripping of 765/400kV ICT-
2 at Kurnool
02-06-2019 at
17:41 hrs
ICT-2 got tripped on operation of Back up directional
over current due to through fault (Y-B phase fault).
PGCIL (SR-1) is requested to check the operation of
ICT HV side High set O/C protection for through fault
and submit a report regarding the same.
PGCIL (SR-I) Yet to be informed Pending
85/III/7 Tripping of 400kV Pugalur-
Karaikudi line-1
31-05-2019 at
17:44 hrs
R-phase to earth fault occurred in line. Auto-reclose
was successful at Karaikudi, At Pugalur end there was
3-phase trip
PGCIL (SR-2) is recommended to ensure proper
condition monitoring of their CB’s such as sufficient
air pressure.
PGCIL (SR-II) Yet to be informed Pending
Others
Annexure-II
Page 44 of 48
69/I/1 Complete outage of 400kV
TPCIL station
25-10-2017 at
19:33 hrs
400 kV TPCIL-Nellore PS line-1 got tripped from
TPCIL end during fault in 400kV Nellore-Nellore PS
line-2. Running units at TPCIL got tripped due to loss
of evacuating line. 400kV Nellore PG - Nellore PS line-
2 and 400kV TPCIL - Nellore PS line-1 were under
shutdown.
TPCIL to configure DEF protection such that it
remains in blocked condition as long as Distance
Protection is active, and becomes active only when
distance protection does not pickup.
TPCIL Review Meeting on 21.12.2018:
It was noted that no TPCIL representatives had come to attend the meeting
Review meetinmg on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit status
regrading the recommendation at athe earliest.
Pending
02-04-2016 at
17:08 hrs
54/I/1 Complete outage of 230 kV
S.P.Koil Station of
TANTRANSCO
PendingNPCIL (MAPS) Status revided vide MAPS mail dated 06.12.2016;
1. The settings given by M/s TANTRANSCO were adopted for Main –I & Main- II
relays for both the lines. The same settings were verified to be same. Subsequently
calibrated was done and no drift was observed. --- Completed
2. From May 2016 onwards, the DR, EL and trip report are being sent by mail to
SRLDC, Bengaluru by MAPS. --- Completed
B-phase CT failure occurred in 230 kV S.P.Koil -
MAPS line-1. Busbar protection got operated at
SP.Koil station. All elements except 230kV Oragadam
and 230kV Kalivandapattu got tripped at 230kV
S.P.Koil station. ‘Y’ phase CT and support insulators
also got damaged.
1.MAPS to furnish a detailed report on the tripping of
SP Koil – MAPS lines 1 & 2 at MAPS end with focus
on the correctness of the settings of Main-I & Main-II
relays (for primary & back-up protections) on both the
lines.
2.MAPS to take steps to provide down-loading facility
Annexure-II
Page 45 of 48
78/II/2 Tripping of 400 kV Neyveli
TS2Exp -Pugalur line
01-08-2018
at 11:56 hrs
Triggering incident was failure of R-ph tension
insulator string/ flashover in 400 kV Bus-1 at NLC
TS2Exp end. Busbar protection had operated resulting
in tripping of all main breakers connected to 400kV
Bus-1 at Neyveli TS2 Exp. In 400kV NLC TS2Exp -
Pugalur line, fault was sensed in Zone-1, R-N at
Pugalur end resulting in a single phase trip. Direct Trip
was received at Pugalur end due to operation of over
voltage Stg-2 at NLC TS2Exp.
1. NLCIL to furnish a report along with a suitable
SLD on the tripping event explaining the observed
discrepancies [DPR, Z1 operation, instantaneous
operation of OVR-II operation], and remedial action
taken to attend the same.
2. NLCIL to configure DR’s & EL’s of all protection
relays at their NLC TS-IIExp station for all mandated
protections & signals.
NLCIL Review Meeting on 21.12.2018:
NLCIL was asked to furnish the status of implementation of the recommendation
given at the earliest.
Review meetinmg on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit status
regrading the recommendation at athe earliest.
Pending
79/II/8 Tripping of 400 kV NLC TS-
2 (Exp) – Pugalur line
10-09-2018 at
20:57 hrs
Line tripped on B-N fault. Auto-reclose was not
attempted at Pugalur end due to DT receipt from NLC
TS2Exp end. At NLC TS2Exp end, V>2 trip was
observed in DR. Analog voltages recorded in DR were
observed to be less than that required for O/V Stage-II
operation.
NLCIL to furnish a detailed report on tripping event
explaining the observed discrepancies , and proper
reasons for tripping of the line considering both the
Main-relays including remedial action taken w.r.t.
healthiness/ replacement of Main protection relays on
400 kV NLC TS2Exp–Pugalur line.
NLCIL Review Meeting on 21.12.2018:
NLCIL was asked to furnish the status of implementation of the recommendation
given at the earliest.
Review meetinmg on 27.06.2019:
it is requested to submit status regrading the recommendation at athe earliest.
Pending
80/II/17 Tripping of 400 kV Nellore
PS – SGPL line-1
14-11-2018 at
20:20 hrs
Y- ph to earth fault occurred in line due to snapping of
GIS to Air bushing conductor at SGPL switchyard.
The conductor got grounded such that the fault was
being fed by NPS bus and there was earth fault and
broken conductor start at SGPL end. NPS end got
tripped in Zone-2 due to non-receipt of carrier resulting
in a 3-ph trip at NPS. After 500ms, earth fault
occurred at SGPL end resulting in Zone-1 operation
and 3 phase trip. A/R was not attempted at SGPL end
SGPL to examine the reasons for no-operation / failure
of Auto-reclosure from their end for the subject
tripping, and furnish an action taken report detailing
remedial measures taken to PCSC forum.
SGPL Review meetinmg on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit status
regrading the recommendation at athe earliest.
Pending
80/III/6 Tripping of 400 kV Neyvelli
TS2 (Exp) - Pugalur line
07-11-2018 at
05:50 Hrs
400 kV Neyvelli TS2Exp - Pugalur tripped on
B-phase to ground fault due to DPR, Z1 operation.
Auto-reclose was successful at Pugalur end and the
line tripped at Neyveli TS2Exp end only. Auto-reclose
was not attempted at Neyveli TS-2(Exp) end
NLCIL to furnish a detailed report on the reasons for
A/R non-operation for the subject tripping at their
NLCTS2Exp station including remedial measures
taken to PCSC forum.
NLCIL Review meetinmg on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit status
regrading the recommendation at athe earliest.
Pending
83/III/1 Tripping of 220 kV
Kayamkulam –Punnapura-2
24-02-2019 at
03:05hrs
Line tripped on B-phase to earth fault. Auto-reclose
was successful at Punnapura. A/r was not attempted at
Kayamkulam and there was pole discrepancy operation
resulting in tripping of R and Y pole of CB.
It was noted that no representative of NTPC attended
the meeting.
NTPC (Kayamkulam) to furnish detailed report
regarding failure of Auto-reclosure at Kayamkulam
end for Kayamkulam –Punnapura line-2.
NTPC (KYKLM) Review meeting on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit status
regrading the recommendation at athe earliest.
NTPC mail dated 13.05.2019:
Trip report for Tripping of 220 kV Kayamkulam –Punnapura-2 submitted , but for
submitting detailed report for Auto-reclosure at Kayamkulam end not operating for
Kayamkulam –Punnapura line-2 , half day shutdown of Kayamkulam –Punnapura
line is required to check reason for failure . May please approve half day outage of
Kayamkulam –Punnapura line and intimate us atleast one day in advance.
Pending
83/III/2 Tripping of 220 kV
Kayamkulam –Punnapura-2
05-03-2019 at
00:30hrs
220kV Kayamkulam-Punnapura -2 tripped on Zone-1
distance protection due to R-N fault. Auto reclose
operated and successful at Punnapara end but didnot
operate at Kayamkulam end.
It was noted that no representative of NTPC attended
the meeting.
NTPC (Kayamkulam) to furnish detailed report
regarding failure of Auto-reclosure at Kayamkulam
end for Kayamkulam –Punnapura line-2.
NTPC (KYKLM) Review meeting on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit status
regrading the recommendation at athe earliest.
NTPC mail dated 13.05.2019:
Trip report for Tripping of 220 kV Kayamkulam –Punnapura-2 submitted , but for
submitting detailed report for Auto-reclosure at Kayamkulam end not operating for
Kayamkulam –Punnapura line-2 , half day shutdown of Kayamkulam –Punnapura
line is required to check reason for failure . May please approve half day outage of
Kayamkulam –Punnapura line and intimate us atleast one day in advance.
Pending
Annexure-II
Page 46 of 48
84/I/5 Complete outage of 400kV
NLC1
Expansion(NLC1EXP)
05-06-2019at 18:51 hr.Triggering incident was failure of Y-phase CT of GT-1 (Generator Transformer) at 400kV NLC1EXP. Bus-1 Bus bar protection operated resulting in the tripping of NLC1EXP U#1 and 400kV NLC1EXP- Nagapattinam line 1. NLCIL to check the healthiness of R & B ph CT of
Unit-1 at NLC TS1(Exp) and if found unhealthy
replace the same alongwith replacement of Y-ph CT.
CT replacement plan and timeframe shall be informed
to SRPC.
2.NLCIL in coordination with PGCIL(SR-II) to
resolve the time syncronisation issues in 230kV NLC
TS1(Exp) – Nagapattinam line.
3. NLCIL was also requested to investigate the reason
of unwarranted DT sent to NLC TS1 (Exp) end from
NLC TS2 end and resolve the same.
NLCIL NLCIL mail dated 09.07.2019:
AT TS2 Side Siemens 7SA52 & Micromho relay are used for distance protection.
During the incident Micromho has sensed the CT blast as a Zone-1 fault and tripped
the feeder. Adt signal was send to TS1 Exp end. The relay will be tested during the
next shut down.
Pending
84/II/7 Tripping of 400 kV
Dichipally–Ramagundam
line
20-04-2019 at
18:09 hr.
Y phase to Earth fault in the line. Line did not auto-
reclose at Ramagundam end
1. It was noted that no representative of NTPC
(Ramagundam) attended the meeting.
2. NTPC (Ramagundam) to submit a detailed report
regarding non-operation of A/R at Ramagundam end
and Remedial measures taken for the same
NTPC (RMGDM) Yet to be informed Pending
84/II/20 Tripping of 400kV Neyveli
TS2- Neyveli TS-I (EXP)
and 400/230 kV ICT-1
atNeyvli
07-05-2019 at 20:56 hr.400kV/230kV ICT-1 got tripped on Differential
protection due to failure of R phase bushing on the HV
side. For 400kV Neyveli TS2- Neyveli TS-I (EXP), R
pole breaker at TS1Expgot tripped. TS2 End breaker
tripped on trip command received from TS1 EXP
1. NLCIL to measure the earth resistance of Neyveli
TS-2 SS and submit the same to PCSC forum. NLCIL
to check the healthiness of LAs of ICTs and confirm
proper earthing.
2.It is also recommended to furnish a report on
adequacy of ground wire shielding of switchyard.
3. NLCIL to ensure Time synchronization of relays at
Neyveli TS-2 SS.
NLCIL NLCIL mail dated 09.07.2019:
1) The earth pit resistance of the ICT1 LA was measured as follows.
400 kV side was measured on29-03-19
Rphase - 0.61 ῼ , Y phase - 0.76ῼ , B phase - 0.58 ῼ
230 kV side was measured on 29-03-2019
Rphase - 0.47 ῼ , Y phase - 0.86ῼ , B phase - 0.68ῼ
The resistive leakage current for the LA's was also measured and the readings are as
follows.
400kV side was measured on 29-03-2019 and the values are as follows .
R phase - 73 μA , Y phase 90 μA , B phase - 92 μA .
230kV side was measured on 22-03-2019 and the values are as follows
R phase - 238 μA , Y phase - 330 μA , B phase 401 μA.
After the incident on 07-05-19 the resistive leaksge current was again measured on
13-05-2019 and the values are as follows.
400kV Side
R phase - 91 μA , Y phase - 116 μA , B phase - 105 μA
230 kV side
R phase - 297 μA , Y phase - 318 μA , B phase - 385 μA
2) Time synchronization of one series of relays completed. The time synchronization
of balance relays will be completed by August 2019.
Pending
84/III/12 Tripping of 400 kV Simhadri-
Kalpakka line-3
12-05-2019 at
18:33 hr.
R-phase to earth fault. Line did not attempt auto-
reclose
1. It was noted that no representative of NTPC
(Simhadri) attended the meeting.
2.NTPC (Simhadri) to submit a detailed report
regarding non-operation of A/R at Simhadri end and
Remedial measures taken for the same.
NTPC(Simhadri) Yet to be informed Pending
85/II/19 Tripping of 400kV JSW-
Guttur line
02-06-2019 at
18:17 hrs
Line tripped due to OV St-1 protection operation at
JSW end and DT was sent to Guttur end. At Guttur
end B ph voltage was observed to be lesser comparing
to R ph and Y ph(Vr-249kV, Vy-255kV and Vb-
230kV).
JSWEL is recommended to monitor the B-ph CVT of
400kV JSWEL-Guttur line (due to lower B-ph voltage
compared to other two phases). The same shall be
replaced if the issue persists.
JSWEL Yet to be informed Pending
85/II/21 Tripping of 400kV JSW -
Guttur line and 400 kV
Kaiga - Guttur line-2
05-06-2019 at
18:27 hrs
Y-phase to earth fault occurred in 400kV Kaiga-Guttur
line-2. A/r was successful at Guttur end. At Kaiga end
A/r was not attempted and breakers got tripped due to
operation of Pole discrepancy (1.65 Sec). 400kV JSW-
Guttur line tripped on operation of over-voltage at
Guttur and direct trip was received at JSW. From DR
of Guttur, it is observed that there was swell in R & Y
phase voltage for few cycles
1. NPCIL (KGS) is recommended to identify the issue
related to unsuccessful A/R attempt of 400kV Kaiga –
Guttur line and non-opening of R-pole CB. It is
recommended to check the healthiness of all breakers
including breaker timing.
2. Time synchronization of DR and EL at Kaiga end
shall be ensured.
NPCIL (KGS) Yet to be informed Pending
Annexure-II
Page 47 of 48
85/III/14 Tripping of 400kV Kaiga-
Guttur line-2
16-06-2019 at
19:20 hrs
R-phase to earth fault. Auto-reclose attempt at Guttur
end was not successful as fault was persistent in
nature. Attempt for A/r could not be established from
Kaiga end EL
1. NPCIL (KGS) is recommended to identify the issue
related to unsuccessful A/R attempt of 400kV Kaiga –
Guttur line and non-opening of R-pole CB. It is
recommended to check the healthiness of all breakers
including breaker timing.
2. Time synchronization of DR and EL at Kaiga end
shall be ensured.
NPCIL (KGS) Yet to be informed Pending
85/IV/7 Tripping of 400kV
Ramadugu-Singareni line
11-06-2019 at
08:24 hrs
Line tripped due to Direct Trip receive at Ramadugu
end
Singareni STPP is recommended to submit a detailed
report regarding sending of DT from singareni end that
resulted in tripping of 400kV Ramadugu-Singareni
line.
Singareni TPP Yet to be informed Pending
Annexure-II
Page 48 of 48
Sl.No. Element Name Outage date/time Revival date/time Reason for outage Sender/ ReceiverRemedial Measures/ Actions
takenRemarks
1 400KV-BPS-TUMKUR-2 17-03-2019/16:17:00 R-Y FAULT KPTCL To-be-discussed
2 400KV/220KV RAMAGUNDAM-ICT-2 05-04-2019/19:56:00 05-04-2019/23:26:00BUS BAR PROTECTION
OPERATEDNTPC To-be-discussed
3 220kV Dindi-Srisailam line-2 17-05-2019/11:44:00 17-05-2019/16:33:00 TRIPPED ON R-N FAULT TSGENCO/ TSTRANSCO
"TSTRANSCO:
It is 220kV Dindi-Srisailam-2
feeder.
A/R successful at Dindi end."
4 400KV-BTPS-HIRIYUR-2 02-06-2019/18:16:00 TRIPPED ON Y-N FAULTKPCL/ KPTCL
[ Pending with KPTCL]
"KPCL: Line tripped on Zone-2,
""C"" phase to earth.
Remedial Measures: Line Charged
on 03.06.2019 at 09:47Hrs from
BTPS end
"
Status of A/R in the
line?
5 400KV-TALGUPPA-HASSAN-1 05-06-2019/23:59:00 06-06-2019/00:32:00R Phase distance
protection operatedKPTCL/ PGCIL (SR-II) To-be-discussed
6 132KV-KONAJE-MANJESWAR-1 06-06-2019/05:45:00EARTH FAULT RELAY
OPERATEDKPTCL/ KSEBL
KSEBL:
Feeder not trippped at
Manjeswar end
7 400KV-KUDGI_PG-NARENDRA-1 07-06-2019/22:47:00 07-06-2019/23:00:00 Y-N FAULT PGCIL(SR-II) To-be-discussed
8 400KV-DONI-GUTTUR-1 11-06-2019/17:24:00 11-06-2019/18:01:00BUS BAR PROTECTION
OPERATEDKPTCL To-be-discussed
9 400KV-GUTTUR-JINDAL-1 11-06-2019/17:24:00 11-06-2019/19:00:00BUS BAR PROTECTION
OPERATEDKPTCL/ JSWEL To-be-discussed
10 400KV-KAIGA-GUTTUR-1 11-06-2019/17:24:00 11-06-2019/20:13:00BUS BAR PROTECTION
OPERATEDNPCIL (KGS)/ KPTCL To-be-discussed
11 400KV-GUTTUR-HIRIYUR-1 11-06-2019/17:24:00 11-06-2019/18:35:00BUS BAR PROTECTION
OPERATEDKPTCL/ PGCIL (Sr-II) To-be-discussed
12 400KV-GUTTUR-HIRIYUR-2 11-06-2019/17:24:00 11-06-2019/18:42:00BUS BAR PROTECTION
OPERATEDKPTCL/ PGCIL (SR-II) To-be-discussed
Pending Remedial Measures/ Actions taken for the Critical Tripping Incidents (as on 19.08.2019)
Annexure-III
Page 1 of 5
13 400KV/220KV GUTTUR-ICT-1 11-06-2019/17:24:00 11-06-2019/18:10:00BUS BAR PROTECTION
OPERATEDKPTCL To-be-discussed
14 400KV/220KV GUTTUR-ICT-2 11-06-2019/17:24:00 11-06-2019/19:04:00BUS BAR PROTECTION
OPERATEDKPTCL
On 11.06.19 at 17:23 hrs 400KV
Kaiga-Guttur-1(Line-1) tripped at
Kaiga end on receipt of DT from
Guttur end. As per KPTCL
information, during ground fault
testing in bus bar panel at Guttur
end, trip command was extended
to bus bar protection and all
connected elements were
tripped. Direct trip was extended
to Kaiga end CB. No event is
recorded at Kaiga end. Kaiga-
Guttur-1 (Line-1) was taken into
service on 11.06.2019 at 20:13hrs
vide CPCC-06/234 and SRLDC -
06/627.
Issue is belonging to KPTCL
15 400KV-NELAMANGALA-TALGUPPA-1 12-06-2019/18:24:00 12-06-2019/20:44:00 EMERGENCY WORK KPTCL To-be-discussed
16 400KV-TALGUPPA-HASSAN-1 12-06-2019/14:38:00 12-06-2019/21:31:00INSULATOR FLASH
OVERKPTCL/ PGCIL (SR-II) To-be-discussed
17 400KV-GUTTUR-HIRIYUR-1 12-06-2019/17:00:00 12-06-2019/17:19:00DT received from
GutturKPTCL/ PGCIL (SR-II) To-be-discussed
18 400KV/220KV HOODY-ICT-2 16-06-2019/19:20:00 16-06-2019/20:51:00
OVER FLUX
PROTECTION RELAY
OPERATED
KPTCL To-be-discussed
19 400KV-KAIGA-GUTTUR-2 18-06-2019/02:53:00 R-N FAULT NPCIL(KGS)/ KPTCL To-be-discussed
20 220KV-AMBEWADI-XELDEM 23-06-2019/16:09:00 TRIPPED ON C-N FAULT KPTCL To-be-discussed
Annexure-III
Page 2 of 5
21 220KV-CHILLAKALLU-PULICHINTHALA-1 25-06-2019/17:17:00 25-06-2019/17:34:00 TRIPPED ON R-N FAULTAPTRANSCO/ TSGENCO
[ Pending with TSGENCO]
APTRANSCO: Feeder tripped on R-
Phase to ground, Zone-2 fault.
Line charged after taking
permission from SLDC. Fault
distance of 81.68KM falls in
TSTRANSCO juridiction.
TSTRANSCO: Line Patrolling done
and no fault found. Substation
belongs to TSGENCO
What protection
operated at TSGENCO
end?
22 400KV-BHADRAVATHI-RAMAGUNDAM-1 26-06-2019/16:29:00 26-06-2019/18:35:00 RELAY MALOPERATION NTPC (RMGD)/ WR To-be-discussed
23 400KV-SALEM-DHARMAPURI-1 29-06-2019/15:43:00 29-06-2019/17:03:00 phase to phase fault PGCIL (SR-II) To-be-discussed
24 220KV-Talapalli-NAGARJUNASAGAR TS 30-06-2019/11:03:00 30-06-2019/11:36:00 TRIPPED ON B-N FAULTAPTRANSCO/ TSGENCO
[ Pending with TSGENCO]
APTRANSCO: Feeder not tripped
at Tallapalli end.
APTRANSCO: The feeder
"Nagarjuna sagar-AP" may be
changed as "Tallapalli".
2.Feeder not tripped at Tallapalli
end.No carrier received from
Nagarjuna Sagar -TS end due to
PLCC problem at TSGENCO end.
25 132KV-KONAJE-MANJESWAR-1 07-07-2019/12:49:00 DISTANCE PROTECTION KPTCL/ KSEBLKSEBL: Supply failed at 110kV
Manjeswar substaion
26 400KV/110KV SHOLINGANALLUR-ICT-1 09-07-2019/14:47:00 09-07-2019/20:25:00TRIPPED ON BUCCHOLZ
RELAY OPERATIONTANTRANSCO To-be-discussed
27 132KV-KONAJE-MANJESWAR-1 14-07-2019/10:25:00 14-07-2019/10:49:00 TRIPPED ON B-N FAULT KPTCL/ KSEBL To-be-discussed
28 400KV-KAIGA-GUTTUR-2 22-07-2019/17:47:00TRIPPED DUE TO B-N
LINE FAULTNPCIL (KGS)/ KPTCL To-be-discussed
29 400KV-YELHANKA-NELAMANGALA-1 23-07-2019/12:09:00operation of gas
chamber protectionKPTCL/ PGCIL (Sr-2) To-be-discussed
30 220KV-KADAKOLA-KANIYAMPETTA 23-07-2019/10:49:00 23-07-2019/12:26:00 RELAY MALOPERATION KSEBL/ KPTCL To-be-discussed
31 400KV-HOODY-YELHANKA-1 23-07-2019/12:09:00operation of gas
chamber protectionKPTCL/ PGCIL (Sr-2) To-be-discussed
Annexure-III
Page 3 of 5
32400KV/110KV SUNGAVARACHATRAM-ICT-
326-07-2019/14:07:00 26-07-2019/15:15:00
EXTERNAL PROTECTION
TRIPTANTRANSCO To-be-discussed
33400KV/110KV SUNGAVARACHATRAM-ICT-
426-07-2019/14:10:00 26-07-2019/16:30:00
EXTERNAL PROTECTION
TRIPTANTRANSCO To-be-discussed
34 220KV-THENI-MOOZIYAR-1 27-07-2019/12:24:00 27-07-2019/12:47:00TRIPPED ON SINGLE
PHASE TO GND FAULTKSEBL/ TANTRANSCO To-be-discussed
35 400KV/220KV TALGUPPA-ICT-2 27-07-2019/16:27:00 27-07-2019/17:16:00MALFUNCTIONING OF
OCRKPTCL To-be-discussed
36 132KV-KONAJE-MANJESWAR-1 28-07-2019/10:29:00 28-07-2019/14:26:00 DISTANCE PROTECTION KSEBL/ KPTCL To-be-discussed
37 400KV-KRISHNAPATNAM-NELLORE_AP-1 01-08-2019/21:49:00 TRIPPED ON R-Y FAULT APGENCO/ APTRANSCO To-be-discussed
38 220KV-AMBEWADI-PONDA-2 02-08-2019/00:18:00 DISTANCE PROTECTION KPTCL/ GED To-be-discussed
39 400KV-NCTPS_STAGE_II-VALLUR-1 04-08-2019/22:19:00TRIPPED ON SINGLE
PHASE TO GND FAULTTANGEDCO/ NTECL To-be-discussed
40 400KV/230KV UDUMALPET-ICT-3 04-08-2019/10:34:00 04-08-2019/11:57:00
OVER FLUX
PROTECTION RELAY
OPERATED
PGCIL (SR-II) To-be-discussed
41 400KV-KALPAKKA-ASUPAKA-1 05-08-2019/13:37:00LA blast of Kalpaka -
Asupaka Line @KalpakaAPTRANSCO/ TSTRANSCO To-be-discussed
42 HVDC 500KV KOLAR_DC Pole 05-08-2019/10:14:00 05-08-2019/13:20:00EXTERNAL PROTECTION
TRIPPGCIl (Sr-II) To-be-discussed
43 400KV-GAZUWAKA-KALPAKKA-1 05-08-2019/13:37:00 05-08-2019/14:54:00LA blast of Kalpaka -
Asupaka Line @KalpakaPGCIL (SR-1)/ APTRANSCO To-be-discussed
44 400KV-KALPAKKA-SIMHADRI_STG1-2 05-08-2019/13:37:00 05-08-2019/14:38:00LA blast of Kalpaka -
Asupaka Line @Kalpaka
APTRANSCO/ NTPC
(SIMHADRI)To-be-discussed
45 400KV-KALPAKKA-SIMHADRI_STG1-1 05-08-2019/13:37:00 05-08-2019/14:20:00LA blast of Kalpaka -
Asupaka Line @Kalpaka
APTRANSCO/ NTPC
(SIMHADRI)To-be-discussed
46 220KV-ELAPULLY-PALAKKAD(KL)-3 05-08-2019/06:41:00 05-08-2019/18:33:00TRIPPED ON DISTANCE
PROTECTIONKSEBL To-be-discussed
47 400KV-KALPAKKA-SIMHADRI_STG1-3 05-08-2019/13:37:00 05-08-2019/14:47:00LA blast of Kalpaka -
Asupaka Line @Kalpaka
APTRANSCO/ NTPC
(SIMHADRI)To-be-discussed
48 400KV-NELAMANGALA-TALGUPPA-1 07-08-2019/19:31:00 220KV SIDE PROBLEM KPTCL To-be-discussed
49 132KV-KONAJE-MANJESWAR-1 08-08-2019/03:29:00 08-08-2019/03:49:00 Main supply failure KSEBL/ KPTCL To-be-discussed
Annexure-III
Page 4 of 5
50 132KV-KONAJE-MANJESWAR-1 09-08-2019/21:42:00 09-08-2019/22:37:00 transient fault KSEBL/ KPTCL To-be-discussed
51400KV-NCTPS_STAGE_II-
SUNGAVARACHATRAM10-08-2019/16:45:00 TRIPPED ON C-N FAULT TANGEDCO/ TANTRANSCO To-be-discussed
52 132KV-KONAJE-MANJESWAR-1 10-08-2019/10:47:00 10-08-2019/14:55:00 DISTANCE PROTECTION KPTCL/ KSEBL To-be-discussed
53 400KV/220KV NP_KUNTA-ICT-3 12-08-2019/12:08:00 12-08-2019/14:14:00Due to fault in 220KV
Galiveedu PS1 Line-2PGCIL (SR-1) To-be-discussed
54 400KV/220KV NP_KUNTA-ICT-2 12-08-2019/12:08:00 12-08-2019/14:25:00Due to fault in 220KV
Galiveedu PS1 Line-2PGCIL (SR-1) To-be-discussed
55 400KV/220KV NP_KUNTA-ICT-1 12-08-2019/12:08:00 12-08-2019/13:39:00Due to fault in 220KV
Galiveedu PS1 Line-2PGCIL (SR-1) To-be-discussed
56 400KV/220KV NP_KUNTA-ICT-4 12-08-2019/12:08:00 12-08-2019/13:43:00Due to fault in 220KV
Galiveedu PS1 Line-2PGCIL (SR-1) To-be-discussed
57 400KV/230KV KARAIKUDI-ICT-3 15-08-2019/06:57:00 15-08-2019/08:58:00OIL SURGE RELAY
ACTEDPGCIl (Sr-II) To-be-discussed
58220KV-KOTHAGUDEM_TPS-
LOWER_SILERU-115-08-2019/13:04:00 15-08-2019/13:36:00 TRIPPED ON Y-N FAULT TSGENCO/ APGENCO To-be-discussed
59 220KV-CHILLAKALLU-NARKETPALLI-1 16-08-2019/22:57:00 16-08-2019/23:17:00 TRIPPED ON R-N FAULT APTRANSCO/ TSGENCO To-be-discussed
60 400KV-GOOTY-NELAMANGALA-1 17-08-2019/06:10:00 17-08-2019/06:47:00 DISTANCE PROTECTION PGCIL (SR-1)/ KPTCL To-be-discussed
61 230KV-NEYVELI_TS_II-KARAIKAL-1 17-08-2019/00:28:00 17-08-2019/02:03:00 DISTANCE PROTECTION NLCIL/ PGCIL (SR-2) To-be-discussed
Annexure-III
Page 5 of 5