Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
4/20/2020
1
© 2015 HDR, all rights reserved.
Project #EM 0295(45)130 PCN 020VApril 20, 2020
I-29 Exit 130 (20th Street S.) Interchange Project
Project Team(& private donors)
Purpose of the Presentation
1. Inform the public about the project•Background•Current Status•What’s next
2. Provide project schedule3. Identify project funding4. Request comments and questions
about the project (due by May 4)
Project Location
4/20/2020
2
Project andEnvironmentalStudy Area
• To relieve traffic congestion on other streets (both now and in the future)
• To better connect workers and places of employment
• To provide access for planned economic development.
Purpose of the Project
Feedback from the public is requested via the web site.
Traffic backups on 32nd Avenue at 6th Street(photo from before 2017 6th Street
reconstruction)
1. Studies from 2000 to 2018 identified the need for another street crossing of I-29.“An additional I-29 overpass or interchange will provide needed congestion relief on 6th Street and allow additional access to the industrial park. Of the alternatives considered, a new 20th Street S. interchange provides the greatest congestion relief.” 2013 Brookings Area Master Transportation Plan
2. Interchange grant funding application was submitted in July 2019.
3. Interchange grant funding was approved in November 2019.
Background
Traffic flows much better but delays at 6th Street
intersections may still be longer than desired.
4/20/2020
3
Existing 20th Street South(west of I-29)
1. SDDOT and City of Brookings hired the HDR/Banner team to complete:• Environmental and
interchange studies• Design plans for construction• Acquire permits and right-of-
way2. Public input is requested on the
project via web site and meetings with affected landowners.
Current Status
Existing I-29 @ 20th Street South
Existing 20th Street South(west of 22nd Avenue South)
1. Determine new 20th Street S section.
What’s Next?
New 20th Street S may look like this.
22nd Avenue S
4/20/2020
4
Interchange Options from 2016 Study
2. Refine interchange options from previous studies to:• Minimize adjacent property
impacts• Provide appropriate property
access
What’s Next?
Study Area for Interchange Analysis
3. Analyze traffic impacts of the new interchange to:• Adjacent I-29 interchanges• Other City streetsFor year 2023 (construction complete) and year 2045 traffic volumes.
What’s Next?
Existing 6th StreetInterchange
Existing 217th StreetInterchange
NewInterchange
3 miles
2 miles
20th Street S
6th Street
217th Street S
4/20/2020
5
Year 2045 Daily Traffic Without New Interchange
Traffic Comparison
30% increase from existing
22nd
Aven
ue
6th Street
Residential Areas
Employment Areas
34th
Aven
ue
From 2016 and 2018 traffic studies
Year 2045 Daily Traffic Without New Interchange
Traffic Comparison
22nd
Aven
ue
6th Street
Year 2045 Daily Traffic With New Interchange
Traffic volumes similar to today
or less
6th Street
32nd
Aven
ue32
ndAv
enue
4/20/2020
6
New interchange relieves traffic on
6th Street
20th Street S
Traffic Comparison
22nd
Aven
ueYear 2045 Daily Traffic With New Interchange
Traffic volumes similar to today
or less
6th Street
New Interchange at 20th Street S
32nd
Aven
ue
In process of updating traffic study
4. Analyze social, environmental, and economic impacts per National Environmental Policy Act of 1969 (NEPA)• Park and recreation facilities
(Section 4(f) and 6(f) properties)
What’s Next?
Edgebrook Golf Course
4/20/2020
7
4. Analyze social, environmental, and economic impacts per National Environmental Policy Act of 1969 (NEPA)• Traffic noise• Floodplain and wetlands• Cultural & historic resources• Threatened & endangered
species
What’s Next?
Western Estates Homes
Old Gravel Pit
4. Analyze social, environmental, and economic impacts per National Environmental Policy Act of 1969 (NEPA)• Land use• Right-of-way
What’s Next?
Interchange Options from 2016 Study
No way to build new interchange without impacting some property(s).Goals:• avoid, minimize, and/or mitigate impacts• select option with the least damaging
impacts
4/20/2020
8
4. Analyze social, environmental, and economic impacts per National Environmental Policy Act of 1969 (NEPA)• Economic Development
What’s Next?
Future Land Use Map(from grant application – on web site)
20th Street S
Better access with interchange can spur
development.
2019
• Funding grant application (July)• Funding grant award (November)• Site survey
Mar Apr2020
• Complete traffic counts (3/14/20)• Public information web site release and landowner meetings• Refine interchange options
May Jun 2020
• Update traffic study (Interchange Justification Report)• Analyze environmental impacts and update screening document• Recommend preferred option
Jul Aug2020
• Public meeting and landowner meetings• Complete draft Environmental Assessment• 30% design plans complete
Sep Oct2020
• Release draft Environmental Assessment at public meeting• 60% design plans complete• Finalize right-of-way acquisitions
Nov Dec2020
• Finalize Environmental Assessment• Obtain Finding of No Significant Impact (FONSI)
2021
• Finalize plans• Acquire right-of-way• Acquire permits
20222023
• Anticipated Construction
Schedule
Normally4 year
timeframe
Accelerated by funding
grantrequirements
4/20/2020
9
Better Utilizing Investments to Leverage DevelopmentCost and Funding
Western Estates Homes
From funding grant application
(subject to change during the project)
Embankment
Submit your comments andquestions by May 4 on the web site:
www.20thstinterchange.com
Additional contacts:Jackie Lanning, PECity of Brookings520 3rd Street, Suite 140Brookings, SD [email protected] Unruh, PEHDR Engineering, Inc.6300 S. Old Village Place, Suite 100Sioux Falls, SD [email protected]
Questions and Comments