Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Contract Adjustments
2021 Contract Administration Workshop
June 7, 2021
2
We would like to know who is participating today.
3
Today’s
Agenda
• Supplemental Agreements
• Claims
• Closeouts
Contract Adjustments
But first, let’s talk about SAFETY!
Safety
• May 19, 2021
– Construction worker, on a private project in
Alexander County, was killed when the 10
ft. deep trench that he was working in
collapsed.
Excavation Hazards• Cave-ins are the greatest risk
• Other hazards include:
– Asphyxiation due to lack of oxygen
– Inhalation of toxic materials/fumes
– Water accumulation
– Machinery moving near edge of excavation
causing a collapse
– Severing underground utility lines
– Falls
Trenching & Excavation Safety• 5 feet or deeper require a protective
system
• A competent person must be on site
• 4 feet or deeper requires a means of
egress within 25 feet of all workers
• Surcharge loads must be at least 2
feet from trench edges
• Check for hazardous fumes and
toxic gases
Supplemental Agreements
8
What is an SA (Supplemental Agreement)?
• A Supplemental Agreement is a written
agreement between the Department and the
Contractor that amends the contract as
necessary to satisfactorily complete the
proposed construction. The modifications to the
contract may affect:
– The work requirements (104-3)
– Unit prices of an existing contract item (104-5)
– Addition of new work items (extra work) (104-7)
– Contract time(s)
– Other terms of the contract.
9
104-3 Alterations of Plans or
Details of Construction• The Contractor shall perform the modified
work at the original contract unit or lump
sum prices unless the character AND the
cost of performing the work materially
changed over that originally anticipated
and bid upon in the contract.
10
104-5 Overruns and Underruns of
Contract Quantities• (B) Overruns – Increase in Unit Price
– >15% Major Items and 100% Minor Item
• (C) Underruns – Increase in Unit Prices
– >15% on Major Items. Adjusted price would
be applicable for the entire quantity of the line
item that underruns. No revision for minor
items that underrun.
11
104-5 Overruns and Underruns of
Contract Quantities
• (D) Overruns/Underruns – Reduction in
Unit Prices
– The Engineer must make written request.
– This would only apply to work performed
AFTER execution of the agreement.
– If you know an item has a high unit price on a
small quantity, then execute the agreement
PRIOR to the work being performed so that
the item will be paid at the revised unit price
once the threshold has been reached.12
104-7 Extra Work
13
• Omission of necessary bid items from the
contract.
• Failure to include a basis of payment in
the contract for work necessary to be
performed under the terms of the contract.
• Necessary plan revisions
14
A supplemental agreement is not a contractually binding amendment to the contract.
Contractually binding…
15
16
https://connect.ncdot.gov/projects/construction/ConstManRefDocs/SUPPLEMENTAL%20AGREEMENT%20PRICING%20FORM.pdf
Approval
17
A Supplemental Agreement (SA) must be executed PRIOR to performing the affected work except as provided in Article 104-8(A). When the affected work is not within the limits established in Article 104-8(A)(1) and it is urgent that the work be begun, electronic copies of the agreement may be executed followed by the original agreement. If the Engineer and the Contractor do not agree to a modification to the terms of the contract prior to the performance of the affected work, neither compensation nor time can be granted by execution of a supplemental agreement.
Approval Authority Limits• Resident Engineer
– Up to $100K and 30 days
– Verbal Approval $25k or less
• Division Engineer
– Unlimited authority under all articles of the
specifications.
• Area Construction Engineer
– Review and make recommendation for all greater
than $100k and over 30 days
• State Construction Engineer
– Review and make recommendation for all greater
than $200k and over 90 days 18
Getting started…
• Ask Yourself- What is the scope of the
proposed work and is it needed to
satisfactorily complete the project?
19
20
Description of Work
• Detailed description - Narrative form –
What it is, What it includes, Where is it
located…
• First sentence should summarize the
change
• Include Specification reference(s) - Extra
Work, Additional Work, Altered Work, or
Other
21
Description• Remember- we are writing a “legally
binding contract” within a contract. Use
specification references where applicable.
Every item needs to be included here!
– General Description (What/Where/When)
– Construction Methods (How)
– Materials to be used
– Measurement and Payment
• Should be written so that those not familiar
with the project can understand it. It
should stand on its own. 22
Description
• Include references to Special Provisions,
Standard Specifications, Plan Revisions,
Attachments, etc.
• DOES NOT INCLUDE JUSTIFICATION!
23
Description
• TRUCK MOUNTED ATTENUATORS – This
supplemental agreement is written in accordance with
Article 104-7 of the 2018 Standard Specifications for
Roads and Structures. This agreement provides
compensation for the use of two (2) Truck Mounted
Attenuators (TMAs). All work shall be done in
accordance with Section 1165 of the 2018 Standard
Specifications for Roads and Structures and as directed
by the Engineer. The pricing includes mobilization,
installation, removal, materials, labor, and all other
incidentals necessary to complete the work.
24
Justification
• In order to install pedestrian safety fencing along the Old
Chapel Hill Road bridge over I-40 safely, lane closures
will be required to be installed on I-40, as well as, on Old
Chapel Hill Road. Truck mounted attenuators are one of
the required traffic control devices to be installed on
interstate lane closures. The contract did not provide
truck mounted attenuators as a line item.
25
Converting to plan quantity Earthwork
26
Before moving on past the description and
justification…
• Is the need for the change fully detailed?
• Is the article of the Specifications that allows the change
identified?
• Is the article of the Specifications that pertains to the
affected work identified?
• If the Specifications are not applicable to the work being
performed, has contractual language including
description, materials, construction methods, method of
measurement, and basis of payment been included as
part of the description?
• Have any special conditions pertaining to the agreement
been clearly identified?27
HiCAMS User Guide Resource
• https://connect.ncdot.gov/projects/construc
tion/HiCams/HiCAMS_03_06_Review_Su
pplemental_Agreements_V3.1.pdf
• Can’t remember that? Just google it…
ncdot hicams user guide supplemental
agreements
28
Line Items
• Could be new items or existing items
• May be a reduction/elimination of some
items
• RE should provide an estimate of
quantities to the contractor – may need to
work together
29
Time Considerations• Does the SA affect/delay the controlling
operations?
• How does it affect the completion date?
• Should seasonal limitations be
considered?
• Is there delay time that needs to be
considered independently of the time that
may be required to perform the
extra/altered work?
30
Types of Time Extensions to be
selected in HiCAMS• No additional time granted
• Time Considered upon Completion of
Work
• Pro Rata
• Set Amount (Time pertaining to performing
the work, NOT delay time)
31
Time Extensions
• Be sure to include time extensions on all
applicable ICT’s!
• How to Undo an incorrect Time
Extension?
32
Pricing
• RE should provide an estimate of
quantities to the contractor – may need to
work together.
• Prices may not be the same as at bid time
due to inflation, salary increases, materials
price increases.
• Average bid prices – are a good reference
and good place to start but may not be the
final resting place.
33
Pricing
• Consult with other units – Technical
Services, Roadway/Structure Design,
Geotech, Signing/Delineation,
Construction Unit, Other SA’s.
• Don’t hesitate to reach out to other
construction offices, as well as, your local
Area Construction Engineer for help
evaluating price proposals.
34
Pricing
• Consider Impacts to the schedule.
• Consider the risks involved – The more
information, the lower the risk, the
better the price.
35
Pricing
• Materials may be unique.
• Labor may be dedicated to another
project.
• Equipment may be specialized.
36
Cost Control
• How to lower the overall cost – look at the
quantities in relation to unit price.
• Contractor should submit the Standard
Pricing Form found in the CM.
• The bottom line- It costs to do
supplemental agreement work.
37
38
Allowable Mark Ups
• Labor Burden – Force Account typically
allows 35%
• Office Burden – Overhead – typically 5-
25%
• Profit – Typically 10%
39
Allowable Mark Ups
• Subcontractors will add markups and then
the Prime will add markups for
administration.
• This is part of doing business.
40
Executing the agreement• HiCAMS serves as the OFFICIAL approval
record for the contract change. All
approvals must be obtained prior to the
agreement being executed/signed, and the
work being performed.
• Docusign should be used to electronically
execute the agreement.
• The project teamsite should house the
executed agreement and ALL of the
backup documentation.41
Distribution of the SA
• The contractor can download their official copy
via DocuSign.
• RE staff should distribute an email .pdf and/or a
link to the project team site notifying internal staff
of the executed agreement, subsequently
loading it into SAP.
• This should be directed to the DCE/ACE. The
State Construction Engineer should only be
copied if they had specific input on the
agreement.
42
• What is a good resource to find valuable
information regarding supplemental
agreements?
43
Questions?
44
Construction Claims Process
Wiley W. Jones III, PE
Assistant State Construction Engineer – Eastern Region
June 7, 2021
Construction Claims
2021 Contract Administration Workshop
2
• Review of Basic Claim Situations
• Follow Current Procedures
• The Different Types of Construction Claims– Active Claim
– Final Claim
– Verified Claim
• Approval / Denial Authority Limits
• Expected Claim Response Timeframes
• Project Closeout Conferences
• Reducing Claim Exposure
Follow Current Procedures
Resident Engineer Record Reviews
• Are you doing what you said you were going to do?
– Review our Policies and Procedures
– Review Actual Case Studies
– Highlight or Draw Attention to Differences
– Provide Recommendations for Improvement
– Follow up to Ensure Improvement Occurred
3
Where do you find the Current
Procedures?• Construction Manual
• Reach out to your Area Construction Engineer
• Regional Bridge Construction Engineer
• FHWA Oversight Agreement
4
Active Claims
5
• Active Claims are the contractor's way of expressing entitlement while the
work of the contract is ongoing.
• Active Claims
– Additional Compensation
– Additional Contract Time
• Active Claims should not be viewed as personal attack on the Contract
Administrator or their staff, but rather a formal protection of Company’s
contractual interests.
Active Claims
Additional Compensation
6
Active Claims
7
• The Contractor is required to give written notice of intent to file a claim for
additional compensation under the provisions of Article 104-3 and Article
104-7.
• The provisions of Subarticle 104-8 – COMPENSATION AND RECORD
KEEPING shall be strictly adhered to.
• If the Contractor elects to file a written claim or requests an extension of
contract time, it shall be submitted on the Contractor Claim Submittal Form.
– Article 104-3 (Alterations of Plans or Details of Construction)
– Article 104-4 (Suspensions of Work Ordered by the Engineer)
– Article 104-7 (Extra Work)
Section 104 – Scope of Work
Article 104-3
• Change in cost and
character of work
• Contractor paid in
accordance with
Subarticle 104-8(A)– Supplemental
Agreement
– Force Account Notice
8
Section 104 – Scope of Work
Article 104-3
• Contractor believes
change in work
materially changes
character and cost of
performing the work.
• Notify Engineer before
performing such work.
9
Section 104 – Scope of Work
Article 104-3
• Engineer investigates
and notifies Contractor
of determination.
– Agree, write SA or FA
– No additional
compensation will be
provided.
10
Section 104 – Scope of Work
Article 104-3
• Contractor to notify
Engineer of intent to file
claim before performing
work.
• Engineer responds and
advises to 104-8(B)
strictly followed.
11
Section 104 – Scope of Work
Article 104-3
12
Questions?
Comment?13
Article 104-7
• Extra work ordered by the Engineer
14
Section 104 – Scope of Work
Article 104-7 (A)
• Extra Work
• Don’t begin until
authorized
• Engineer Agreed
additional compensation
is warranted
– Supplemental Agreement
– Force Account 15
Section 104 – Scope of Work
Article 104-7 (B)
• Contractor believes he
is required to perform
extra work
• Contractor notifies
Engineer in writing
before performing such
work.
16
Section 104 – Scope of Work
Article 104-7 (B)
• Engineer investigates
and notifies Contractor
in writing of
determination.
– Not Extra Work
17
Section 104 – Scope of Work
Article 104-7 (B)
• Contractor to notify
Engineer of Intent to File
claim in writing before
performing work.
• Engineer responds and
advises to 104-8(B)
strictly followed.
18
Section 104 – Scope of Work
Article 104-7 (B)
19
Questions?
Comment?20
Section 104 – Scope of Work
• Subarticle 104-8 (A)
Compensation for Articles
104-3 or 104-7
– Supplemental Agreement
– Force Account Notice
21
Subarticle 104-8(B) Claim for Additional Compensation
Articles 104-3 and 104-7
• Contractor must provide:
– Written notice of Intent to File Claim for additional
compensation
– Cost records in accordance with Article 109-3 (Force Account)
– Weekly cost records and supporting data of disputed work to
Engineer for review
– Separate the cost of any work for which payment has been
made
– Submit Weekly cost records to the Engineer within 7 calendar
days after the end of a given weekly period.22
Subarticle 104-8(B) Claim for Additional Compensation
Articles 104-3 and 104-7
• Contractor must decide whether to submit a Written Claim
for Additional Compensation within 120 calendar days of
completion of disputed work.
23
Section 104 – Scope of Work
• Subarticle 104-8(B) Claim
for Additional Compensation
– Articles 104-3 and 104-7
– Intent to file claim must be in
writing
– Keep accurate records in
accordance with Article 109-3
– Prepared and submitted
weekly
24
Article 104-8 Compensation and Record Keeping
– Clearly indicate the cost of
performing work in dispute
– Separate the cost of any
work for which payment
has been made
– Engineer given opportunity
to review records
25
Article 104-8 Compensation and Record Keeping
– Cost records prepared
weekly for each written
intent
– Cost Records given to
Engineer within 7 days
after end of weekly period
26
Subarticle 104-8 (B)
Claim for Additional Compensation
• Subarticle 104-8 (B)
Claim for Additional
Compensation
– Once disputed work is
complete, submit written
claim within 120 days after
completion of the disputed
work.
– Summarize cost records
27
Subarticle 104-8 (B)
Claim for Additional Compensation
• Subarticle 104-8 (B)
Claim for Additional
Compensation
– Describe justification for
adjustment in
compensation under terms
of contract.
28
Section 104 – Scope of Work
• Subarticle 104-8 (B)
Claim for Additional
Compensation
– Certified true and accurate
by officer of company or
person authorized to
execute SA.
29
Article 104-4
• Suspension of work ordered by the Engineer
– Should be made in writing
– Describe the operation being suspended
– Should be lifted in writing once available again
• Alleged Suspensions
– When suspension are not made in writing by Engineer
– Not caused by weather
30
Article 104-4
• No adjustment in compensation is allowed when
– Duration is < 24 hours
– Performance would have been suspended by other cause
– Suspension is due to fault or negligence of Contractor
31
Subarticle 104-8(C) Compensation for Article 104-4
(Suspension of Work Ordered by Engineer)
• Contractor must provide:
– written notice of Intent to File Claim for additional compensation
within 7 calendar days after Engineer suspends work
– written notice of Intent to File Claim for additional compensation
for alleged suspension of work.
– Detailed records of alleged idle equipment and idle labor.
– Weekly cost records to Engineer for review for each notice of
intent
32
Subarticle 104-8(C) Compensation for Article 104-4
(Suspension of Work Ordered by Engineer)
• Contractor must:
– Decide whether to submit a Written Claim for Additional
Compensation within 14 calendar days of notice to resume
work.
– Summarize previously submitted cost records and
– Clearly describe the justification for adjustment in
compensation under terms of the contract.
33
Subarticle 104-8(C) Compensation for Article 104-4
(Suspension of Work Ordered by Engineer)
• Resident Engineer will:
– Evaluate the Contractor’s Request
• If agree, make adjustment on actual verified cost
– Idle equipment
– Idle labor
• If not in agreement,
– Notify the Contractor in writing of determination
– Within 120 days after receiving complete request.
34
Subarticle 104-8(C)
(Article104-4 Suspension of Work)The Contractor shall:
• Provide Notice of Intent
to File Claim must be in
writing within 7 days of
suspension
• Keep accurate records
– Idle Equipment
– Idle Labor
35
Subarticle 104-8(C)
(Article104-4 Suspension of Work)The Contractor shall:
• Justification why idle
equipment/ labor cannot
be absorbed into
unaffected work
• Engineer ability to review
• Prepared weekly
• Submitted weekly
36
Subarticle 104-8(C)
(Article104-4 Suspension of Work)Once suspension is lifted,
submit written claim within
14 calendar days
– Summarize previously
submitted cost records
– Justify adjustment under
terms of the contract
37
Subarticle 104-8(C)
(Article104-4 Suspension of Work)• Evaluate the claim
– Was the cost of work
directly associated with
suspension
– Not caused by weather
– No profit included in cost
– Paid verified actual costs
of idle equipment and idle
labor
38
Time Extensions
To be a valid cause for an extension of the completion date, there
are four basic criteria which must be met.
1. The current controlling operation must have been delayed
2. The delay to the controlling operation must have developed from
circumstances originating from the work required under the
contract.
3. The Contractor must have pursued the work (Article 108-1)
4. Any delay must have been caused by circumstances beyond the
Contractor’s control and without his fault or negligence.
39
Subarticle 108-10(B)
Time Extensions1. Pro-rata extensions
2. Extensions Allowed by Supplemental Agreements
3. Delays to the Controlling Operation
4. Changes in time due to elimination of work.
5. Winter weather extensions
*When all work is complete except for items precluded by
seasonal limitations, the engineer may waive assessment of
liquidated damages.
40
What should you do when you receive a
Notice of Intent to File a Claim?• Review the validity of the Contractor’s request.
• Respond in writing acknowledging receipt of the notice of
intent to file a claim
– Highlight to the contractor the numbered items which shall be a
bar to recovery if not followed.
– Examples letters can be found in the Construction Manual
• Advise the inspection staff to properly document
equipment, labor, and materials for the disputed operation
41
How should a Contractor file a claim?
• Claims for additional compensation have to be in writing
before the work is performed.
• They shall use the Contractor Claim Submission Form
42
Contractor Claim Submittal Form
43
Contractor Claim Submittal Form
44
Contractor Claim Submittal Form
• Enter project
information
• Identify what
they are seeking
– Time
– Compensation
– Both
45
Contractor Claim Submittal Form
• Signed by
Authorized
Representative
who has
authority to sign
supplemental
agreements for
the Contractor.
46
Contractor Claim Submittal Form
Controlling Operation
• Any operation or
operations, as
determined by the
Engineer, that if
delayed would delay
the completion of the
project.
47
Contractor Claim Submittal Form
Example : Department
added extra work to
the contract via
supplemental
agreement. Time to be
Considered upon
completion of work.
48
Contractor Claim Submittal Form
If any of the boxes are
marked “No”, then a
case could be made
that there is a bar to
recovery of the
additional
compensation.
49
Contractor Claim Submittal Form
• 1(a) Suspensions
ordered by Engineer
• 1(b) Alleged
Suspensions
• Notice the
timeframes are
slightly different than
for Article 104-3.
50
Contractor Claim Submittal Form
• 1(a) Suspensions
ordered by Engineer
• 1(b) Alleged
Suspensions
• Notice the
timeframes are
slightly different than
for Article 104-3.
51
Contractor Claim Submittal Form
Engineer requests to
remove or uncover portions
of the finished work as
directed.
If found to be acceptable,
the cost for uncovering or
removing, and replacing of
the covering or making
good of the parts removed.
52
What should you do when you receive a
notice of intent to file a claim?• Respond in writing and inform the Contractor to follow
Article 104-8(B) or 104-8(C)
• Example letter is in the Construction Manuals
53
What should you do when you receive a
notice of intent to file a claim?• Refer them to the Contractor Claim Submittal Form
• Check the weekly records
– Notify them of any deficiencies.
– Notify them if they are late.
– Just receiving them does not mean we agree with their position
54
Subarticle 104-8(B)
• Claim for Additional Compensation
• Contractor’s notice of intent to file a claim for additional
compensation under 104-3 and 104-7 shall be given to
Engineer in writing.
• Records kept in accordance with Article 109-3
• Must be checked by Engineer
55
Claim Approval/Denial Authority Limits
Active Claims
• Resident Engineer
– $100,000 and 30 days under all Articles of Specifications
– Cannot deny any active claim
• Division Engineer or delegate
– Unlimited under all Articles of Specifications
• Area Construction Engineer
– Review all active claims over $100,000 or 30 days
• State Construction Engineer
– Review all active claims over $200,000 or 90 days56
Expected Claim Response Time Frames
Active Claims up to $100,000 or 30 days
• Resident Engineer review – If approved, within 10 Days
– If recommends denial, forward to Division Engineer within 10 Days
• Division Engineer– Reviews recommendation of RE, and approves or denies the claim within
10 days
Overall process complete within 1 Month
57
Expected Claim Response Time Frames
Active Claims between $100,000 and $200,00 or up to 90 days
• Resident Engineer– Reviews and sends recommendation to Area Construction Engineer within 20 Days
• Area Construction Engineer
– Reviews and forwards to Division Engineer with comments within 5 days
• Division Engineer– Reviews recommendations and approves or denies the claim within 5 days
Overall process complete within 6 Weeks
58
Expected Claim Response Time Frames
Active Claims over $200,00 or over 90 days
• Resident Engineer– Reviews and sends recommendation to Area Construction Engineer within 30 Days
• Area Construction Engineer and State Construction Engineer – Reviews and forwards to Division Engineer with comments within 10 days
• Division Engineer– Reviews recommendations and approves or denies the claim within 10 days
Overall process complete within 2 ½ Months 59
Closeout Conferences
• Scheduled after the contractor has had time to review the
final quantities letter
• Opportunity to verbally discuss any previously denied
active claims.
• Opportunity to reach an agreement to closeout the
project.
60
Closeout Conference
• Area Construction Engineer leads the discussion for
Centrally Let projects
– Explanation of purpose of meeting
– Notify Contractor of next steps in the closeout process
– Discuss any pay record quantity disputes
– Give Contractor opportunity to verbalize his positions on
entitlement for additional contract time and/or additional
compensation
– Division and Construction Unit have to be in agreement before
any settlement closeout offer is made. 61
Closeout Conference
If agreement is not reached, contractor to submit Final Claim to the State
Construction Engineer, detailing all requests for additional contract time
and additional compensation, as if any offer extended to reach
settlement during the closeout conference did not occur.
• If satisfaction not received in Final Claim, then contractor can pursue
Verified Claim by submitting to Chief Engineers office
62
What are Contractor’s next steps if an agreement
cannot be reached at the Closeout Conference?
• Contractor will need to submit a Final Claim to the State Construction
Engineer, detailing all requests for additional contract time and
additional compensation, as if any offer extended to reach settlement
during the closeout conference did not occur.
• If satisfaction not received in Final Claim Process, then contractor may
submit a written and Verified Claim in accordance with Article 107-24
and NCGS 136-29, to the Chief Engineer within 60 days of payment of
the final estimate. (Lawyers are involved at this level)
• If unsatisfied at Verified Claim Process, then Contractor may institute a
civil action
• Court Ordered Mediation
• Civil action in Superior Court, tried by the judge, without a jury.63
Final Claims
64
• Central Let Projects
– Submitted from the Contractor directly to the State Construction Engineer
– State Construction Engineer will review and respond as part of the Final Estimate
Process
• Division Let Projects
– Submitted from the Contractor directly to the Division Engineer
• For claims > $100,000 or 30 days, Division Engineer should forward recommendation to the Area
Construction Engineer.
• For claims > $200,000 or 90 days, Division Engineer should forward recommendation to the State
Construction Engineer.
– Division Engineer, after consultation, will respond to the Contractor as part of the Final
Estimate Processing
Verified Claims
Article 107-24 – Right of the Contractor to File Verified Claim
• When Contractor fails to receive settlement as he claims to be
entitled to under the terms and provisions of the contract
• Submit a written and verified claim for such amounts he deems
himself or subcontractor entitled
• Written notice of intent to file a claim, keeping and submission of
cost records and the initial submission within the specified time
period.
• Submitted to the Chief Engineer within 60 calendar days from the
time the Contractor receives the final estimate as defined by
Section 101 and submitted in accordance with NCGS 136-29. 65
Reducing Claim Exposure
• Utility Workgroup
• Railroad Work Group
66
Reducing Claim Exposure
• Keep Lines of Communication Open
• Timely Responses to Issues
– Forced Acceleration
• Engage Area Construction Engineers
67
Reducing Claim Exposure
• Public Record Requests
– Use Technical Writing Skills
– Project Diary Entries
– Email Correspondence
• Documentation can assist
– Pictures
– Correspondence showing engaged
68
Questions?
Comment?69