9
24 April 2015 FY 2016 Budget Request to Congress for DOE’s Office of Science Dr. Patricia M. Dehmer Acting Director, Office of Science http://science.energy.gov/sc-2/presentations- and-testimony /

24 April 2015 FY 2016 Budget Request to Congress for DOE’s Office of Science Dr. Patricia M. Dehmer Acting Director, Office of Science

Embed Size (px)

Citation preview

24 April 2015

FY 2016 Budget Request to Congressfor DOE’s Office of Science

Dr. Patricia M. DehmerActing Director, Office of Science

http://science.energy.gov/sc-2/presentations-and-testimony/

Office of ScienceBy the numbers

Shown is a portion of SLAC's two-mile-long linear accelerator (or linac), which provides the electron beam for the new Linac Coherent Light Source (LCLS) – the world’s first hard x-ray, free-electron laser. For nearly 50 years, SLAC's linac had produced high-energy electrons for physics experiments. Now researchers use the very intense X-ray pulses (more than a billion times brighter than the most powerful existing sources) much like a high-speed camera to take stop-motion pictures of atoms and molecules in motion, examining fundamental processes on femtosecond timescales.

SC delivers scientific discoveries and tools to transform our understanding of nature and advance the energy, economic, and national security of the U.S.

Research Support for 47% of the U.S. Federal support of basic

research in the physical sciences; ~22,000 Ph.D. scientists, grad students, engineers, and

support staff at >300 institutions, including all 17 DOE labs; U.S. and world leadership in high-performance computing

and computational sciences; Major U.S. supporter of physics, chemistry, materials

sciences, and biology for discovery and for energy sciences.

Scientific User Facilities

The world’s largest collection of scientific user facilities (aka research infrastructure) operated by a single organization in the world, used by 31,000 researchers each year. 2

Support for basic research in the physical sciences by agency.

Source: NSF Science and Engineering Indicators 2012

3

Office of Science FY 2016 Budget Request to Congress(Dollars in thousands)

4

Office of Science FY 2016 Budget Request to Congress(Dollars in thousands)

FY 2016 SC Budget Request by CategoryDollars in Thousands

Research$2,099,93

139%

Facility Operations$1,995,56

537%

Construction$591,310

11%

MIEs$144,901

3%

Other* $364,747

7%

SBIR/STTR$143,340

3%

*Other includes GPP/GPE amounts for BES, GPP for FES, Other (DOE/SC/Fermi/Lawrence) for NP, WDTS, SLI non-construction funding, S&S, and Program Direction.

Construction BES: Linac Coherent Light Source-II continues

and is in its peak funding year ($200,300K). FES: ITER – support for the USIPO, IO, and

hardware fabrication continues ($150,000K). HEP: Long Baseline Neutrino Facility

($20,000K for PED); Muon to Electron Conversion ($40,100K).

NP: FRIB continues and is at the peak of its funding profile ($100,000K); accelerator commissioning and detector construction of the CEBAF 12 GeV upgrade continue ($12,000K).

SLI: Materials Design Lab at ANL ($23,910K); Photon Science Lab Building at SLAC ($25,000K); Integrative Genomics Building at LBNL ($20,000K).

Also in SLI: “Infrastructure Support” increases by $31,100K for top priorities identified as part of the Campus Strategy discussions, for electrical upgrades at ANL and SLAC and for facility improvements at FNAL.

Major Items of Equipment BES: Advanced Photon Source Upgrade

(APS-U) ($20,000K) and NSLS-II Experimental Tools (NEXT) (15,500K).

HEP: LHC Detector Upgrades (ATLAS and CMS) ($9,500K each); Large Synoptic Survey Telescope camera (LSSTcam) ($40,800K); Muon g-2 ($10,200K); LUX-ZEPLIN ($9,000K); SuperCDMS-SNOLab ($2,000K); Dark Energy Spectroscopic Instrument (DESI) ($5,300K).

Research ASCR: There is a significant increase for the

exascale initiative to support for HPC vendors to design and develop exascale node technologies and systems. (Δ = +$86,895K).

Also in ASCR: The Computational Science Graduate Fellowship is restored at $10,000K to fully fund a new cohort!

BES: Increases for EFRCs (Δ = +$10,000K), Computational Materials Sciences (Δ = +$4,000K), and mid-scale instrumentation for ultrafast electron scattering (Δ = +$5,000K).

BER: Increases for Climate and Earth System Modeling with largest increase for Climate Model Development & Validation and Integrated Assessment. (Δ = +$18,730K). Some decreases offset the increases.

FES: Research continues in all areas. Increase for GPP for PPPL in support of NSTX-U operations. HEDLP is reduced, but the Matter in Extreme Conditions end station at LCLS remains fully funded.

HEP: Research funding is nearly flat with FY 2015 and supports scientific results from operating experiments and R&D for future projects.

NP: Research increases by more than 8% to support high-priority work.

Facility Operations ASCR, BER, BES, HEP: Facilities operate at or

near to optimal, >98%. FES: NSTX resumes operations for 14 weeks;

DIII-D operates for 12 weeks until shutdown for installation of upgrades; Alcator C-Mod operates for 5 weeks prior to final shutdown at the end of FY 2016.

NP: RHIC operates 22 weeks, same as in FY 2015 and has funding for capital equipment and spares; ATLAS operates 37 weeks; CEBAF is supported for continued machine development and commissioning of beam to Halls B and C.

5

Research

6

Facility Operations

7

Construction

8

Major Items of Equipment

9