4
AbstractThis study examines previous literature on construction projects cost and schedule overruns, with the specific aim of identifying the causes and effects of cost schedule overruns in construction projects. This is because the concept of construction projects cost and schedule overruns has attracted much attention in recent years and that researchers and research bodies, be it corporate or government that try to formulate remedies to projects cost and schedule overruns should begin with an understanding of the causes of these overruns and their effects to the construction industry as a whole. The study is conducted with reference to existing theoretical literature, published and unpublished research. The study is mainly a literature review/survey on the causes and effects of construction project cost and schedule overruns. The primary findings emanating from the study revealed that empirical studies have identified a number of important factors which cause projects cost overruns, such as fluctuation of prices of material, cash flow and financial difficulties faced by the contractor, poor site management and supervision, lack of experience and schedule delay. The study further revealed that poor site management, delay in progress payments, poor communication and financial difficulties by the contractor are among the identified causes of construction projects schedule overruns by previous scholars. Literature also revealed that extension of project, additional cost, budget short fall, adversarial relationship between participants of the project, delayed payments to contractors, poor quality workmanship and dissatisfaction by project owners and consequently by end users as the major effects of cost overruns. Furthermore, it was observed that time overrun, cost overrun, arbitration, litigation, disputes and total abandonment of projects were the effects of construction projects schedule overruns. The study explores the causes and effects of construction projects cost and schedule overruns and presents a robust background on the theories of construction project cost and schedule overruns. KeywordsCost overruns, Schedule overruns, Construction Industry, Causes and effect of cost and schedule overruns. Mulenga. Mukuka is an MTech students with the Department of Construction Management and Quantity Surveying, University of Johannesburg, Johannesburg, 2028 South Africa (corresponding author to provide phone:+27 (0) 11 559 6398; fax:+27 (0) 11 559 6630; e-mail: [email protected]). Clinton. Aigbavboa is a Lecture with the Department of Construction Management and Quantity Surveying, University of Johannesburg, Johannesburg, 2028 South Africa (corresponding author to provide phone:+27 (0) 11 559 6398 ; fax:+27 (0) 11 559 6630; e- mail:[email protected]). Wellington. Thwala is a Professor with the Department of Construction Management and Quantity Surveying, University of Johannesburg, Johannesburg, 2028 South Africa (corresponding author to provide phone:+27 (0) 11 559 6048; fax:+27 (0) 11 559 6630; e-mail: [email protected]). I. INTRODUCTION OST and schedule overruns can occur for a wide variety of reasons on various types of projects which has led to the debate on how to minimise these construction projects cost and schedule overruns [1]. However, Memon, Rahman, Asmi, and Azis, [2] states that in order to find measures of minimising these overruns, the very first and most important step is to identify and understand the factors responsible for the overruns. Hence, this paper examines previous literature on causes and effects of construction projects cost and schedule overruns. II. CONSTRUCTION PROJECTS COST OVERRUNS Cost overruns are very common in the construction industry. Hardly few projects get completed within original costs [3]. Al-Najjar [4] defines cost overruns as the change in contract amount divided by the original contract award amount. However, Zhu and Lin [5] states that cost overrun can be defined as excess of actual cost over budget. Cost overrun is also sometimes called cost escalation, cost increase or budget overrun. Memon, Rahman and Abdul Azis [2] outlines that cost is among the major considerations throughout the project management life cycle and can be regarded as one of the most important parameters of a project and the driving force of project success. Olawale and Sun [6] states that despite the availability of various control techniques and project control software many construction projects still do not achieve their cost objectives. Hence, despite its proven importance it is not uncommon to see a construction project failing to achieve its objectives within the specified cost [2]. Park and Papadopoulou [7] states that construction cost overruns mean negative publicity for the design team and loss of client confidence. The repercussions for contractors are similar as they see their profit margins shrink. III. CONSTRUCTION PROJECTS SCHEDULE OVERRUNS Projects or construction works that are not delivered on time to the client are referred to as projects that have undergone schedule overruns. Hence, Mohamad [8] Defines schedule overruns as an act or event that extends the time to complete or perform an act under the contract. Also, Assaf and Al-Hejji [9], defined schedule overruns as the time overrun either beyond completion date specified in a contract, A Theoretical Review of the Causes and Effects of Construction Projects Cost and Schedule Overruns Mukuka M.J, Aigbavboa C.O., and Thwala W.D. C International Conference on Emerging Trends in Computer and Image Processing (ICETCIP'2014) Dec. 15-16, 2014 Pattaya (Thailand) 112

27 1214036

Embed Size (px)

DESCRIPTION

27 1214036

Citation preview

  • AbstractThis study examines previous literature on construction projects cost and schedule overruns, with the specific

    aim of identifying the causes and effects of cost schedule overruns in

    construction projects. This is because the concept of construction

    projects cost and schedule overruns has attracted much attention in

    recent years and that researchers and research bodies, be it corporate

    or government that try to formulate remedies to projects cost and

    schedule overruns should begin with an understanding of the causes

    of these overruns and their effects to the construction industry as a

    whole. The study is conducted with reference to existing theoretical

    literature, published and unpublished research. The study is mainly

    a literature review/survey on the causes and effects of construction

    project cost and schedule overruns. The primary findings emanating

    from the study revealed that empirical studies have identified a

    number of important factors which cause projects cost overruns,

    such as fluctuation of prices of material, cash flow and financial

    difficulties faced by the contractor, poor site management and

    supervision, lack of experience and schedule delay. The study

    further revealed that poor site management, delay in progress

    payments, poor communication and financial difficulties by the

    contractor are among the identified causes of construction projects

    schedule overruns by previous scholars. Literature also revealed that

    extension of project, additional cost, budget short fall, adversarial

    relationship between participants of the project, delayed payments to

    contractors, poor quality workmanship and dissatisfaction by project

    owners and consequently by end users as the major effects of cost

    overruns. Furthermore, it was observed that time overrun, cost

    overrun, arbitration, litigation, disputes and total abandonment of

    projects were the effects of construction projects schedule overruns.

    The study explores the causes and effects of construction projects

    cost and schedule overruns and presents a robust background on the

    theories of construction project cost and schedule overruns.

    KeywordsCost overruns, Schedule overruns, Construction Industry, Causes and effect of cost and schedule overruns.

    Mulenga. Mukuka is an MTech students with the Department of

    Construction Management and Quantity Surveying, University of Johannesburg,

    Johannesburg, 2028 South Africa (corresponding author to provide phone:+27

    (0) 11 559 6398; fax:+27 (0) 11 559 6630; e-mail: [email protected]).

    Clinton. Aigbavboa is a Lecture with the Department of Construction

    Management and Quantity Surveying, University of Johannesburg,

    Johannesburg, 2028 South Africa (corresponding author to provide phone:+27

    (0) 11 559 6398 ; fax:+27 (0) 11 559 6630; e-

    mail:[email protected]).

    Wellington. Thwala is a Professor with the Department of Construction

    Management and Quantity Surveying, University of Johannesburg,

    Johannesburg, 2028 South Africa (corresponding author to provide phone:+27

    (0) 11 559 6048; fax:+27 (0) 11 559 6630; e-mail: [email protected]).

    I. INTRODUCTION

    OST and schedule overruns can occur for a wide variety

    of reasons on various types of projects which has led to

    the debate on how to minimise these construction projects

    cost and schedule overruns [1]. However, Memon, Rahman,

    Asmi, and Azis, [2] states that in order to find measures of

    minimising these overruns, the very first and most important

    step is to identify and understand the factors responsible for

    the overruns. Hence, this paper examines previous literature

    on causes and effects of construction projects cost and

    schedule overruns.

    II. CONSTRUCTION PROJECTS COST OVERRUNS

    Cost overruns are very common in the construction

    industry. Hardly few projects get completed within original

    costs [3]. Al-Najjar [4] defines cost overruns as the change in

    contract amount divided by the original contract award

    amount. However, Zhu and Lin [5] states that cost overrun

    can be defined as excess of actual cost over budget. Cost

    overrun is also sometimes called cost escalation, cost increase

    or budget overrun. Memon, Rahman and Abdul Azis [2]

    outlines that cost is among the major considerations

    throughout the project management life cycle and can be

    regarded as one of the most important parameters of a project

    and the driving force of project success. Olawale and Sun [6]

    states that despite the availability of various control

    techniques and project control software many construction

    projects still do not achieve their cost objectives. Hence,

    despite its proven importance it is not uncommon to see a

    construction project failing to achieve its objectives within the

    specified cost [2]. Park and Papadopoulou [7] states that

    construction cost overruns mean negative publicity for the

    design team and loss of client confidence. The repercussions

    for contractors are similar as they see their profit margins

    shrink.

    III. CONSTRUCTION PROJECTS SCHEDULE OVERRUNS

    Projects or construction works that are not delivered on

    time to the client are referred to as projects that have

    undergone schedule overruns. Hence, Mohamad [8] Defines

    schedule overruns as an act or event that extends the time to

    complete or perform an act under the contract. Also, Assaf

    and Al-Hejji [9], defined schedule overruns as the time

    overrun either beyond completion date specified in a contract,

    A Theoretical Review of the Causes and Effects

    of Construction Projects Cost and Schedule

    Overruns

    Mukuka M.J, Aigbavboa C.O., and Thwala W.D.

    C

    International Conference on Emerging Trends in Computer and Image Processing (ICETCIP'2014) Dec. 15-16, 2014 Pattaya (Thailand)

    112

  • or beyond the date that the parties agreed upon for delivery of

    a project. It is basically a project slipping over its planned

    schedule and is considered as common problem in

    construction projects worldwide. Assaf and Al-Hejji [9]

    further illustrates that, to the owner, schedule overruns means

    loss of revenue through lack of production facilities and rent-

    able space or a dependence on present facilities. In some

    cases, to the contractor, schedule overruns means higher

    overhead costs because of longer working periods, higher

    material costs through inflation, and due to labour cost

    increases. Alkhathami [10] states that schedule overruns can

    be defined as extra time required to finish a given

    construction project beyond its original planned duration,

    whether compensated for or not.

    IV. CAUSES OF CONSTRUCTION PROJECTS COST OVERRUNS

    Cost overruns do not just occur naturally, there are a

    number of factors during the construction process that when

    not managed properly can lead to cost overruns. Al-Najjar [4]

    identified a total of 42 factors that cause cost overruns and

    ranked the top ten causes as follows: Technical incompetence,

    poor organizational structure, and failures of the enterprise,

    lack of cost reports during construction stage, inadequate

    project preparation, planning and implementation, delays in

    issuing information to the contractor during construction

    stage, lack of coordination at design phase, change in the

    scope of the project or in Government policies, Some

    tendering manoeuvres by contractors, such as front- loading

    of rates, incomplete design at the time of tender, bad

    allocation of labour inside the site and delays in decisions

    making by government were ranked the top ten causes of cost

    overruns.

    Eshofonie [11] revealed a total of 40 causes of cost

    overruns with the top ten causes being the following: cost of

    materials, incorrect planning, wrong method of estimation,

    contract management, fluctuation of prices of materials,

    previous experience of contractor, Absence of construction

    cost data, Additional cost and Project financing. However, the

    study of Ameh, Soyingbe and Odusami [12] identified factors

    that cause of cost overruns, these factors were then

    categorised in 5 categories namely: environmental factors,

    construction factors, construction Item Factors such as

    frequent design changes, Cost estimating factors and

    financing factors. Baloyi and Bekker [13] revealed that

    increase in material cost, inaccurate material estimates,

    shortage of skilled labour, clients late contract award, project

    complexity, increase in labour cost, inaccurate quantity take-

    off, difference between selected bid and the consultants

    estimate, change orders by client during construction and

    shortage of manpower.

    Rahman, Memon and Abd. Karim [14] identified the

    following as the top ten causes of cost overruns in large

    construction projects: fluctuation of prices of material, cash

    flow and financial difficulties faced by the contractor, poor

    site management and supervision, lack of experience,

    schedule delay, inadequate planning and scheduling,

    incompetent subcontractors, mistakes and errors in design,

    frequent design changes and poor financial control on site.

    These results were not in agreement with the results of

    Memon el al [15] where poor design and delays in design,

    unrealistic contract duration and requirements imposed, lack

    of experience, late delivery of materials and equipment,

    relationship between management and labour, delay in

    preparation and approval of drawings, inadequate planning

    and scheduling, poor site management and supervision,

    mistakes during construction and changes in material

    specification and type were identified as the top causes of cost

    overruns. Kasimu [16] identified five categories of causes of

    cost overruns which include: financial related factors, factors

    related to construction parties, factors related to construction

    items, environmental related factors and politics related

    factors.

    V. CAUSES OF CONSTRUCTION PROJECTS SCHEDULE OVERRUNS

    Causes of schedule overruns are factors that lead to

    construction projects not being finished according to the

    planned scheduled time at the inception of project. Ade-ojo

    and Babalola [17] states that there are 6 major causes that

    would lead to schedule overruns, the identified causes were

    ranked as follows: design error, poor site condition, delay in

    payment, financial incapability of client, financial

    incapability of contractor and non-availability of

    subcontractor and supplier. Further, Akinsiku and Akinsulire

    [18] show that, financial or cash flow difficulties, financial

    difficulties faced by contractors and public agencies, frequent

    change order and design, failure to pay for completed works,

    shortages of resources, considerable additional work,

    escalations of material prices, increases in the scope of work,

    delay in design work and late delivery of materials are the top

    ten causes of schedule overruns on construction projects.

    However, Ali, Smith, Pitt and Choon [19] shows that

    labour Shortage, contractors financial difficulties,

    construction mistakes and defective works, coordination

    problem, material shortage and poor Site management are the

    major factors that contribute to schedule overruns con

    construction projects in Malaysia. Furthermore, Memon et al.

    [20] revealed that design and documentation issues, financial

    resource management, project management and contract

    administration, contractors site management, information and

    communication technology, material and machinery resource,

    labour (human) resource and external factors as the major

    factors affecting time performance on construction projects.

    The study of Pourrostam and Ismail [21] shows the following

    as the top ten causes of schedule overruns: poor site

    management, delay in progress payments by client, change

    orders by client during construction, ineffective planning and

    scheduling of project by contractor, financial difficulties by

    contractor, slowness in decision making process by client,

    delays in producing design documents, late in reviewing and

    approving design documents by client, poor contract

    management by consultant and problems with subcontractors.

    International Conference on Emerging Trends in Computer and Image Processing (ICETCIP'2014) Dec. 15-16, 2014 Pattaya (Thailand)

    113

  • VI. EFFECTS OF COST OVERRUNS

    Effects are the consequences that will be encountered when

    cost overruns occur on a construction project. Nega [22] states

    that cost overruns have obvious effects for the key

    stakeholders in particular, and on the construction industry in

    general. To the client, cost overrun implies added costs over

    and above those initially agreed upon at the onset, resulting in

    less returns on investment. To the end user, the added costs

    are passed on as higher rental or lease costs or prices. To the

    professionals, cost overrun implies inability to deliver value

    for money and could well tarnish their reputations and result

    in loss of confidence reposed in them by clients. To the

    contractor, it implies loss of profit for non-completion, and

    defamation that could jeopardize his or her chances of

    winning further jobs, if at fault. To the industry as a whole,

    cost overruns could bring about project abandonment and a

    drop in building activities, bad reputation, and inability to

    secure project finance or securing it at higher costs due to

    added risks [22].

    The study of Nega [22] further identified the following

    as the major effects of cost overruns: delays during

    construction, supplementary agreement, additional cost,

    budget short fall, adversarial relationship between

    participants of the project, loss of reputation to the consultant,

    the consultant will be viewed as incompetent by project

    owners, high cost of supervision and contract administration

    for consultants, delayed payments to contractors, the

    contractor will suffer from budget short fall of the client and

    poor quality workmanship. However, Eshofonie [11]

    identifies four effects of cost overruns as follows: company or

    firm liability to insolvency and liability of the companies or

    firms to bad debt, under-utilization of man-power resources,

    plants and equipment, increased project cost due to extension

    of time: Longer project duration means that more resources

    will need to be allocated to the project, which then increases

    the project costs and project abandonment.

    VII. EFFECTS OF SCHEDULE OVERRUNS

    Effects of schedule overruns are the consequences that will

    occur when the causes of these schedule overruns are not

    identified and worked on effectively. The study of Pourrostam

    and Ismail [21] identifies and ranks the effects of construction

    delays as follows, time overrun, cost overrun, dispute,

    arbitration, litigation, and total abandonment of projects.

    These findings are in general agreement with other studies as

    carried out by Aibinu and Jagboro [23] and Motaleb and

    Kishk [24]. However, the study of Baki [25] brings in the

    aspect of claims as one of the effects of delays in construction

    projects.

    VIII. RESEARCH METHODOLOGY

    The research was conducted with reference to existing

    theoretical literature, published and unpublished literatures.

    The study is mainly a literature survey/review and looks at the

    literatures relating to construction project cost and schedule

    overruns. This is because the concept of projects cost and

    schedule overruns has attracted much attention in recent

    years and that researchers and research bodies, be it corporate

    or government that try to formulate remedies to construction

    projects cost and schedule overruns should begin with an

    understanding of the causes and their effects. The current

    methodology falls within the qualitative research

    methodology.

    IX. LESSONS LEARNT FROM LITERATURE REVIEW

    Literature reviewed showed that the major causes of cost

    overruns include: cost of materials, incorrect planning, wrong

    method of estimation, contract management, and fluctuation

    of prices of materials [11]. Other causes identified through

    literature include, environmental factors, construction factors,

    construction Item Factors such as frequent design changes,

    Cost estimating factors and financing factors [12].

    Furthermore, literature showed that the major causes of

    schedule overruns include: design error, poor site condition,

    delay in payment, financial incapability of client, financial

    incapability of contractor and non-availability of

    subcontractor and supplier [17]. Other causes of schedule

    overruns included: financial or cash flow difficulties,

    financial difficulties faced by contractors and public agencies,

    frequent change order and design, failure to pay for

    completed works, shortages of resources, considerable

    additional work, escalations of material prices, increases in

    the scope of work, delay in design work and late delivery of

    materials [18].

    Literature further identified the following as the major

    effects of cost overruns, delays during construction,

    supplementary agreement, additional cost, budget short fall,

    adversarial relationship between participants of the project,

    loss of reputation to the consultant, the consultant will be

    viewed as incompetent by project owners, high cost of

    supervision and contract administration for consultants,

    delayed payments to contractors, the contractor will suffer

    from budget short fall of the client and poor quality

    workmanship [22]. Furthermore, literature showed the major

    effects of schedule overruns to be time overrun, cost overrun,

    dispute, arbitration, litigation, and total abandonment of

    projects [21].

    X. CONCLUSION

    This article has examined literature relating to construction

    project cost and schedule overruns. Literature review showed

    that the causes of cost and schedule overruns range from

    those caused by poor construction management to those that

    are caused by other external factors like poor weather

    conditions. Further, literature revealed that there are

    corresponding negative effects of construction project cost

    and schedule overruns that can eventually lead to total project

    abandonment.

    REFERENCES

    [1] Alinaitwe, H., Apolot, R. and Tindiwensi, D. 2013, Investigation into the Causes of Delays and Cost Overruns in Uganda's Public Sector

    Construction Projects: Journal of Construction in Developing Countries,

    18(2), 3347, 2013. [2] Memon, A.H., Rahman, I.A., Asmi, A. and Azis, A., 2010, Factors

    Affecting Construction Cost in Mara Large Construction Project:

    International Conference on Emerging Trends in Computer and Image Processing (ICETCIP'2014) Dec. 15-16, 2014 Pattaya (Thailand)

    114

  • Perspective of Project Management Consultant: International Journal of

    Sustainable Construction Engineering & Technology: Vol 1, No 2,

    December 2010.

    [3] Subramani, T., Sruthi, P. S. and Kavitha, M. 2014, Causes of Cost Overrun In Construction: IOSR Journal of Engineering (IOSRJEN): ISSN

    (e): 2250-3021, ISSN (p): 2278-8719: Vol. 04, Issue 06 (June. 2014),

    ||V3|| PP 01-07.

    [4] Al-Najjar, J.M., 2002, Factors Influencing Time and Cost Overruns on Construction Projects in the Gaza Strip: Masters Thesis: The Islamic University of Gaza.

    [5] Zhu, K. and Lin, L., 2004, A stage by stage factor control frame work for cost estimation of construction projects, Owners Driving Innovation:

    International Conference. http:/ flybjerg. Plan.aau.dk / JAPAASPUBLISH.

    [6] Olawale, Y. A, and Sun M., 2010, Cost and time control of construction projects: Inhibiting factors and mitigating measures in practice.

    Construction Management and Economics, 28 (5), 509 526. [7] Park, Y-III and Papadopoulou, T. C. 2012, Causes of cost overruns in

    transport infrastructure projects in Asia; Their significance and relationship

    with project size: Built Environment Project and Asset Management, Vol.

    2 No. 2, 2012: pp. 195-216: Emerald Group Publishing Limited.

    Available at www.emeraldinsight.com/2044-124X.htm.

    [8] Mohamad, M.R.B. 2010, The factors and effect of delay in government Construction project, Case study in kuantan: University Malaysia Pahang.

    [9] Assaf, S.A. & Al-Hejji, S. 2006, Causes of delay in large construction projects: International Journal of Project Management, 24 (2006): 349357.

    [10] Alkhathami, M.M. 2004, Examination of the correlation of critical success and delay Factors in construction projects in the kingdom of Saudi Arabia:

    Doctor of Philosophy Thesis: University of Pittsburgh.

    [11] Eshofonie, F.P., 2008, Factors affecting cost of construction in Nigeria: Masters in construction management thesis: University of Lagos akoka,

    Lagos.

    [12] Ameh, O.J., Soyingbe, A.A. and Odusami, K.T., 2010, Significant Factors Causing Cost Overruns in Telecommunication Projects in Nigeria: Journal

    of Construction in Developing Countries, Vol. 15(2), 4967, 2010. [13] Baloyi, L. and Bekker, M., 2011, Causes of construction cost and time

    overruns: The 2010 FIFA World Cup stadia in South Africa: Acta

    Structilia 2011: 18(1).

    [14] Rahman, I.A., Memon, A.H and Abd. Karim, A. T., 2013, Significant Factors Causing Cost Overruns in Large Construction Projects in

    Malaysia: Journal of Applied Sciences 13 (2): 286-293, 2013.

    [15] Memon, A. H., Rahman, I. A. and Abdul Azis, A. A. 2011, Preliminary Study on Causative Factors Leading to Construction Cost Overrun:

    International Journal of Sustainable Construction Engineering &

    Technology Vol 2, Issue 1, June 201.

    [16] Kasimu, M. A., 2012, Significant factors that causes cost overruns in building construction project in Nigeria. Interdisciplinary journal of

    contemporary research in business: March 2012, VOL 3, NO 11.

    [17] Ade-Ojo, C. O. and Babalola, A. A. 2013, Cost and Time performance of construction projects under the due process reform in Nigeria. Research

    Inventy: International Journal Of Engineering And Science: Vol.3, Issue 6

    (Aug 2013), PP 01-06: Issn(e): 2278-4721, Issn(p):2319-6483,

    Www.Researchinventy.Com.

    [18] Akinsiku, O. E and Akinsulire, A. 2012, Stakeholders Perception of the Causes and Effects of Construction Delays on Project Delivery. KICEM

    Journal of Construction Engineering and Project Management: Online

    ISSN 2233-9582.

    [19] Ali, A. S. Smith, A. Pitt, M. and Choon, C. H. 2012, Contractors perception of factors contributing to project delay: case studies of

    commercial projects in klang valley, Malaysia.

    [20] Memon, A.H., Rahman, I.A. and Azis A.A.A. 2012, Time and Cost Performance in Construction Projects in Southern and Central Regions of

    Peninsular Malaysia: International Journal of Advances in Applied

    Sciences (IJAAS): Vol.1, No.1, March 2012, pp. 45-52.

    [21] Pourrostam, T. & Ismail, A. 2011, Significant Factors Causing and Effects of Delay in Iranian Construction Projects: Australian Journal of Basic and

    Applied Sciences, 5(7): 450-456.

    [22] Nega, F., 2008, Causes and effects of cost overrun on public building construction projects in Ethiopia: Master of Science thesis: Addis Ababa

    University.

    [23] Aibinu, A.A. & Jagboro, G.O. 2012, The effects of construction delays on project delivery in Nigerian construction industry: International Journal of

    Project Management, 20 (2002): 593599. [24] Motaleb, O. & Kishk, M. 2010, An investigation into causes and effects of

    construction delays in UAE: Robert Gordon University.

    [25] Baki, M.A. 1999, Delay Claims Management in Construction-A Step-By-Step Approach: ProQuest Dissertations & Theses Full Text: pg. 36-38.

    International Conference on Emerging Trends in Computer and Image Processing (ICETCIP'2014) Dec. 15-16, 2014 Pattaya (Thailand)

    115