Upload
muriel-ross
View
215
Download
0
Tags:
Embed Size (px)
Citation preview
27/Aug./2015 KAGRA f2f meeting
N. KIMURAHigh Energy Accelerator Research Organization, KEK
Progress status of Cryogenic Progress status of Cryogenic System System
at KAGRA siteat KAGRA site
27/Aug./2015 KAGRA f2f meeting2
Outline
Over View of KAGRA Cryogenics
Components of the Cryogenics
Construction of Cryostat
Proposed Work Schedule
Summary
3 333
14 m
Vacuum ducts along laser beam
Vibration isolation system(room
temperature)
Clean booth
Design drawing with tunnel and cross section
Cryostat(Here is a mirror)
2nd floor
Shaft
A. Hagiwara
Structure of vibration isolation and cryostat
Progress status of assembling the cryostats;
•EXC & EYC were assembled as vacuum vessels
without duct shields and cryo-coolers
from the end of 2014.11 to the end of 2015.1.
•IYC & IXC were assembled with all of components
such as duct shields and cryo-cooler units
from the end of 2015.2 to the mid of 2015.4.
EYC
EXCIXC
IYC
• Duct Shield
• 12 mL vacuum duct
• 6 mL +6 mL vacuum
duct
• Cryostat
• Gate Valve
BS
3 km
3 km
Cryo-cooler unit installation
BS
3 km
3 km
IXC
IYC
EYC
EXC
View of Assembled Cryostats
Reached pressurein the Y-front cryostat3.7x10-7 kPa
27/Aug./2015 KAGRA f2f meeting
X&Y-end cryostats •Leak test were cleared based on KAGRA requirement
< 1x10-10 Pa*m3/sec•No excess leak found above the background
(~1x10-12 Pa*m3/sec)
X&Y-front cryostats•At leak test,
two small leak spots < 1x10-9 Pa*m3/sec were founded by the reason of malfunction of gaskets.•It should be replace until mid of September 2015.
Leak test
27/Aug./2015 KAGRA f2f meeting
Proposed Proposed Future Plans of KAGRA Future Plans of KAGRA CryogenicsCryogenics
2015 2016
Jan./’16
We are hereJuly, 23rd
Re-align position of EXC&EYC,and connect cross tube between cryostat and vacuum vessel for VIS.
Operation of iKAGRA
Connect cryo-coolers and duct shields to EXC&EYC
Performance test with confirming vibrationin the cryostat
Connect compressors, flexible horse and cables to cryostat
Jan./’17June/’16 June/’17
up grade work to bKAGRA
Apr./’16~May/’16
June/’16~July/’16
Aug./’16~Oct./’16
We have already proposed above schedule to SEO.We would like to complete KAGRA cryogenic system for next year.
27/Aug./2015 KAGRA f2f meeting
SummarySummary
8
• Completed assembling X&Y-end cryostats without cryo-
coolers
and cleared leak tests based on KAGRA requirement
• Completed assembling X&Y-front cryostat including
connection of 11 cryo-cooler units and 4 duct shields.
• At leak test of the front,
two small leak spots < 1x10-9 Pa*m3/sec were founded
by the reason of malfunction of gaskets.
• It should be replace until mid of September 2015.
• A plan for connection of cryo-cooler units and duct shields at
X&Y-end cryostat were proposed and accepted by SEO.
It should be launched at mid of March 2016.
9
KAGRA Cryogenics Group
Toshikazu SUZUKI EO and SEO member KEK, Senior Fellow
Nobuhiro KIMURA Cryostat sub-chief KEK, Assoc. Prof.
Kazuhiro YAMAMOTO Cryo-Payload sub-chief ICRR, Project Assist. Prof.
Takayuki TOMARU Chief KEK, Assoc. Prof.
Tatsuya KUME Surveying, Alignment KEK, Assoc. Prof.
Rahul KUMAR Simulation, Payload KEK, PD
Ayako HAGIWARA CAD KEK, Technical Staff
Shinichi TERASHIMA Machining KEK, Technical Staff
Iwao MURAKAMI Welding, Assembly KEK, Technical Staff
Hiroki TANAKA Cryo-Payload, Q ICRR, Grad. Student
Takahiro MIYAMOTO Cryo-Payload ICRR, Grad. Student
Suguru TAKADA Cryogenics NIFS, Assist. Prof.
2015.Jul.25
By T. Tomaru(Revised by K. Yamamoto)
27/Aug./2015 KAGRA f2f meeting
Conceptual Design Conceptual Design of the Cryogenicsof the Cryogenics
Four 4K cryocooler units per one cryostat Baffles against wide scattering is cooled via 8K shield.
Main Beam
Cooling 8K shield
Cooling Cryo-Payload
Duct Shield
400kW4W?
~1W
Cryostat80K shield
8K shield
two units
80K PTC withVibration reduction
4K PTC withVibration reduction
two units
2 units for cool cryo-payload2 units cool for 8K shield4 units cool for 80K shield
Low vibration in U. H. VacuumStop propagation of 300K radiationPrevent heating by scattered beam
300K Radiation
Baffles
27/Aug./2015 KAGRA f2f meeting
Gate valve Gate valve
Connection Port to SASMirror a cryostat
Location of Four Mirror Cryostats in Kamioka MineConstructed at the position of 1 km in depth.
Mozumi-End Atotsu-End
X-Front RoomY-Front Room
L=5 m
L=5 m
Vacuum duct800 with radiation shield
Vacuum duct800 with radiation shield
27/Aug./2015 KAGRA f2f meeting
Structure of KAGRA CryostatStructure of KAGRA Cryostat
Seismic Attenuation System (SAS)
Duct Shield
Four Cryocooler Units
Main Laser Beam
Radia
tion S
hie
lds
4.3
m
2.6m
Cryogenic Payload
Sapphire Mirror(-alumina crystal)
S.Koike
View Ports
Stainless steel t=20mmDiameter 2.4 mHeight ~4.3 mM ~ 12 tonCold Mass:8K shield ~455 kg80 K shield ~590 kg
CryocoolersPulse tube, 60Hz0.9 W at 4K (2nd)36 W at 50K (1st)
27/Aug./2015 KAGRA f2f meeting
Recommendation 18: The basic performance test/inspection, especially leak tests, should be completed before the beam tube installation. The current plan to do this by the coming January should be kept. Suzuki: The leak test of Cryostat in X-end was performed in January 2015. The top flange of the cryostat with a diameter of 2400 mm was fastened using a metal gasket. This part will never be able to open after constructing a clean booth. No excess leak was found on the background level of 1x10^-12 Pa*m^3 /sec. This result satisfied the requirement of KAGRA vacuum system that specify a leak less than 1x10^-10 Pa*m^3 /sec. Assembling other three cryostats in Y-end and XY-front is in progress. Leak test for those cryostats will finish until April 2015.
Recommendation: Vibration measurements with the cryo-cooler in operation should be repeated at appropriate locations corresponding to the final design configuration, to more accurately assess vibration transfer. If the resulting spectrum remains as serious as was presented from the preliminary measurements shown, more understanding anddevelopment of mitigation techniques will be necessary. This may have radical impact on the cryogenic plant and/or payload designs.Comment: All the cryocoolers have been delivered to the KAGRA site, but cryocoolers have not all been integrated with the end cryostats. Although the cooling time for the radiation shield and vibration levels at the shield have been measured at Toshiba facility, it is highly desirable to demonstrate the cooling and vibration levels inside the realcryostat at the KAGRA site as soon as possible to alleviate remaining uncertainties about the cryogenic operation of KAGRA. If isolation of cryocooler vibration should be insufficient, it could render the vibration isolation achieved by super-attenuators useless.Recommendation: The cryocoolers should be integrated with at least one end cryostat and vibration isolation system, so that both cooling and vibration isolation can be tested as soon as possible. This will also afford VIS and CRY teams an opportunity to work together on integration of their systems.
2014 PAB
2015 External Review