Upload
natyac
View
232
Download
0
Embed Size (px)
Citation preview
8/13/2019 3 Fulfillment of Grid Code
1/21
Fulfillment of Grid Code Requirements in
the area served by UCTE by Combined
Cycle Power Plants
Dieter Diegel,Steffen Eckstein
Ulrich Leuchs,Oldrich Zaviska
Siemens AG, Power Generation , Germany
Abstract:
The continental European power system is the result of synchronous interconnection of the
electricity networks of the separate transmission system operators (TSOs) involved. To
ensure smooth operation of the system and to enable grid disturbances to be controlled, a
number of technical rules and recommendations need to be followed in operation of this
system.
The rules and recommendations of the Union for the Coordination of Transmission of
Electricity (UCTE) form a common basis for this, providing minimum requirements to be
met for grid operation on this system which is operated in overall synchronism These rules
NextOptions
8/13/2019 3 Fulfillment of Grid Code
2/21
profitability for the system. For the TSOs to be able to meet their responsibilities,
transmission system users must comply with the technical minimum requirements and rulesspecified in the relevant Grid Codes.
The paper discusses the requirements of national Grid Codes for primary and secondary
control and the extent to which they can be fulfilled by combined cycle power plants
(CCPPs).
Examples are given of the restrictions that apply for modern gas turbines, and of the way in
which Grid Code or customer requirements can be met for combined cycle plants.
1. Introduction
In the past year, the UCTE and regional TSO associations responsible for national Grid Codes
have had very good reason to focus on compliance with and fulfillment of the requirements
that they have set forth.
There were the blackout events in Italy, Denmark/southern Sweden and the USA/Canada,
which resulted in major economic losses.
Even the variability of the causes involved illustrates that the complexity of a reliable energy
supply system presents ever greater challenges and requires more and more a coordinated
approach.
Not least of all, grid operators are being challenged to make ever larger power reserves
available, to achieve improved distribution of these power reserves within the interconnected
power system and to develop new and better load shedding concepts for response to
disturbances.
There are various reasons for the size and uniformity of the power reserves. On the one hand,
it is necessary for conventional power plants to provide control reserves corresponding to the
entire output supplied by energy producers which operate without any frequency-control
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
3/21
power system, which was originally envisioned primarily as a source of mutual assistance and
optimization, is more and more becoming a commercial marketplace.Not least of all, the expanded physical size of the interconnected power system and the
variability with which the interconnections mesh are also new challenges. Due to limited
transmission capacity, reliable provision of control power within the interconnected power
system requires uniform distribution of this control power over the generating units involved.
In the future, transmission system operators must pay even closer attention to compliance
with requirements when the generating units are connected and must also use test programs to
verify the necessary flexibility of these units for grid operation.
Power plant manufacturers are working intensively in close co-operation with companies that
operate the generating units to comply with these ever more intricate rules.
These companies have a vested interest in ensuring a reliable energy supply even in the event
of grid disturbances, especially if they are responsible for supplying power to large urban
areas with many industrial plants.
Back in the 1980s, the Power Generation Group of Siemens AG was already gaining vast
experience with special grid requirements, in particular relating to steam power plants.
As gas turbines have gone on-line in single or combined cycle (Siemens GUD) power plants,
which represent a growing market share, Siemens has been gaining worldwide experience
with these machines since the ending of the 1980s.
This experience also aids us in meeting the newly defined requirements for these types of
power plants.
2. Common Grid Requirements for Active Power control of CCPPs
Frequency Stability
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
4/21
If the power generation is greater than power demand, generators connected to the grid system
speed up.If the power generation is less than power demand, generators connected to the grid system
slow down. When power generation and power demand are back in balance, the frequency
stabilizes.
For correct operation of the transmission system it is necessary to hold the frequency within
defined narrow limits. Minor deviations from the frequency reference value (50/60Hz) or
absence of any such deviations show that there is a balance of generation and power demand.
Faults in the system resulting from loss of power plants, shutdown of loads, short circuits, etc.
result in deviations and gradients of varying magnitudes. These faults can result in instability
of the grid or even in grid outage. It is possible to distinguish:
- Faults within the anticipated range, controlled by provision of reserve power.
Those faults result in frequency fluctuations that remain within a control band defined by
the grid operator e.g. at UCTE = +/-200 mHz.
It must be possible to ride out loss of the largest generator in the system without frequency
moving outside the control band. This operation will be described in the subsection
Frequency Control.
- Serious system faults that are counteracted by disconnection from the interconnected
system and measures such as load shedding.
Fast decreases in frequency in the case of serious system faults can not be counteractedsolely by measures on the generating side. Protection devices are implemented which
switch off loads (load shedding) in case of a specific underfrequency.
In the case of fast decreases in frequency where the frequency remains above a
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
5/21
Primary control is the automatic, stabilizing action of active power controls for the turbine-
generators interconnected in the synchronous three-phase grid. This type of control acts in the
time frame of seconds using turbine speed control.
Secondary controltakes effect after about 30 seconds and acts in the time frame of minutes.
The local Grid Codes in each country generally specify minimum requirements.
Purchaser-specific requirements that go beyond the respective Grid Codes are, however, often
specified in order to achieve competitive advantages on deregulated power trading markets.
Specifications :
For example: England/ Wales: NGC Grid Code, Connection Conditions, Appendix 3
(minimum requirements):
Plant Operating Ranges:
If there is a contractual agreement with the TSO, frequency control takes place above a
minimum generation MG of 65% registered capacity. In case of grid disturbances with
increasing frequency the control must be able to reduce the generation dynamically down
to a designed minimum operating level DMLO of 55%.
For example: Spain : RED ELCTRICA DE ESPAA, P.O.7.1.
Frequency control band !P = +/- 1.5 % of registered capacity
The required frequency dependent load change is to be demonstrated 10 seconds after the
start of a frequency simulation ramp of +/- 0.2 Hz per 30 seconds.
(It should be noted that these requirements apply to the overall power plant. In combined-
cycle plants, the ST does not participate in frequency regulation, so the GT has to provide
1.5 times the response).
Operating frequency demanded by the grid system
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
6/21
The regulator must guarantee stable operation of the unit for an indefinite time, for any
frequency between 47.5 Hz and 51.5 Hz and any load between the load of the auxiliary
service and the maximum power that can be generated by the unit .
Allowable power dip on rising/falling system frequency
Requirement:
Many Grid Codes contain a requirement to avoid excessive active power dips on fallingsystem frequency. Gas turbines, in particular, tend to respond to frequency reductions with
pronounced output changes that depend on the ambient temperature.
Specifications:
For example: Greece : RAE, CC7.3.1.1.1.
operate continuously at normal rated output at transmission system frequencies in the range
49.5 Hz to 50.5 Hz
Load rejection / island operation
Requirement :
In many Grid Codes the requirements above are compulsory.
Load rejection
Various electrical causes such as frequency under a minimum limit, stability problems and too
low grid voltage can cause the circuit breaker to open and disconnect the power plant from the
grid during operation. After opening of the circuit breaker house load is still supplied (about 5
to 10 MW). This is called load rejection to house load. If opening of the generator breaker
takes place in response to a system fault there is then a load rejection to 0 MW
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
7/21
A blanket requirement for stable operation of a single generator in all possible island
configurations cannot be met. If there is a requirement for the generating unit to continue in
stable operation, a purchaser-specific automation concept must be drawn up. For this purpose
detailed information and technical data on the purchaser's requirements and the possible
configurations of the island system are necessary.
Specifications :
German Transmission Code 2003
1. Load rejection on house load
The generating unit must be designed to control the load rejection to house load .
from each permissible operating point.
2. (Grid) island operation capability
Each generating unit must be capable of controlling the frequency under the condition
that the respective generation shortage is not more than the primary operating reserve.
In case of generating surplus the generating unit must be able to reduce output down
to minimum generation.
Control of a short circuit close to the power plant
Requirement :
The short circuit clearance protection will control failures in the system in a time frame of
approximately 100 ms. If this is unsuccessful, a back-up protection feature then acts in a time
frame of 100 to 250ms to maintain stable and undisturbed load operation. The requirement to
overcome a short circuit in the system applies both to the generator voltage control and to the
turbine frequency/load control.
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
8/21
Even though the UCTE has developed a number of technical and organizational rules printed
in the UCTE Operation Handbook, the responsibility of the national TSOs must still bedetermined in their own guidelines.
Because grid structures vary in different countries (e.g., in the distribution of generating units
over the area of the country) and due to the way in which the interfaces to the other
transmission systems are defined and thus to the way in which energy is exchanged with these
other systems over the interconnected power lines, it is necessary to define specificrequirements.
Non-UCTE nations (such as Ireland) are second to none in terms of the requirements placed
Fig. 1 : UCTE members
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
9/21
4. Control Strategy of SIEMENS Combined Cycle Power Plants
The range within which a GUDpower plant can contribute to grid frequency regulation is a
function of the power plant operating mode and the associated overall conditions. Interaction
between the operating modes of all of the relevant components, such as the gas turbine, heat-
recovery steam generator and steam turbine, must be taken into account, especially where
dynamic processes are involved.
In the GUDprocess, Siemens gas turbines should operate within the largest possible load
range with nearly constant turbine outlet temperatures, with NOX requirements taken into
account here. The turbine outlet temperature controller regulates the compressor air mass flow
to a specified fuel/air ratio. In other words, the air mass flow rate through the compressor
must be adjusted according to the flow of fuel entering through the control valves. An
adjustable row of inlet guide vanes, driven by an actuator, is located at the compressor inlet.
OTC temp. IGV position
1
0.5
11
0 5
1
HP steam press.HP valve opening
Valve
Temp.IGV
Speed-/Admiss.controller
ST controller
GT controller
Speed/Load &OTC temp. lim.controller
OTC temp.(IGV)controller
Gas turbineHRSG Steam turbine
Generator
IGV
G
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
10/21
8/13/2019 3 Fulfillment of Grid Code
11/21
In order to hold back a required control reserve, a GUDpower plant must operate in the
part-load range. The gas turbine is then operated under load-controlled with a subordinate
speed controller. The unit is controlled based on a specified unit load setpoint. As soon as the
grid frequency goes outside of a set insensitivity band, the frequency influence then acts on
the unit power setpoint, changing this and the speed controller corrects the lift setpoint (for
the fuel valves and inlet guide vanes). Unit output is regulated to correspond to the new
requirement. In the event of overfrequency the load is reduced and in the event of
underfrequency the load is increased.
With these dynamic processes, the speed/load controller of the gas turbine provides for an
optimum and stable combustion process.
5. The Excellence of SIEMENS CCPPs in Frequency Response
Now that an explanation has been provided as to the general conditions and the requirements
of the transmission system operators on the one hand and the Siemens power plant control
strategy on the other hand, the results of a number of tests will be used to illustrate how
Siemens GUDpower plants respond to particular events during grid operation.
The following points will be explored on the basis of tests:
Primary control in the event of underfrequency
Primary control in the event of overfrequency
Load rejection by a gas turbine from base load to house load
Load rejection by a gas turbine to islanding mode
Fig. 3 : GT Control, Speed(Frequency)/ Load Controller Principle
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
12/21
N tP iO ti
8/13/2019 3 Fulfillment of Grid Code
13/21
Primary control in the event of overfrequency
In response to overfrequency simulated by a ramp function of +0.2 Hz within 10 seconds, the
GUD reduces the power output.
Load rejection by a gas turbine from base load to house load
Riding out a load rejection from base load to house load using a gas turbine entails holding
speed below the overspeed trip limit without throttling the fuel valves so far that flameout
occurs.
Fig. 5 : Primary Frequency Response on Overfrequency
-14
-12
-10
-8
-6
-4
-2
0
-5 0 5 10 15 20 25 30 35
0
0,05
0,1
0,15
0,2
0,25
Measured power response
UCTE / Spain requirement
Greece requirement
England requirement
Frequency injection
Frequency deviation [Hz]
Time [s]
Power response [% on RC]
NextPreviousOptions
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
14/21
Fig. 6 shows load rejection to house load initiated by opening the circuit breaker at a plant
located in Italy.
Load rejection by a gas turbine to islanding mode
Load rejection to islanding mode is gaining in significance. This is a trend that has become
more apparent since the blackout events of last year. Fig. 17 shows load and frequency curves
for plant in Germany during load rejection from part load to islanding mode.
6. Participation of ST in Primary Control
It was primarily contractual agreements that led to the realization that only by involving the
steam turbine could the power output requirements be met.
Fig. 7 : Load Rejection to Island
20
40
60
80
100
120
140
160
-1,00 0,00 1,00 2,00 3,00 4,00 5,00 6,00 7,00 8,00
Time [s]
49,9
50
50,1
50,2
50,3
50,4
50,5
50,6
GT power
GT frequency
Frequency [Hz]Power [MW]
opening of circuit breaker for island operation
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
15/21
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
16/21
The block diagram of the new control module is shown in Fig. 9. The charging of thermal
storage is initiated by switching from natural variable-pressure mode to modified variable-
pressure mode. This changes the setpoints in the unit control module such that the turbine
inlet valves begin to throttle accordingly. At the end of the throttling process the storage has
been charged and the steam section is operating in modified variable-pressure mode, ready for
the steam turbine to participate in primary control.
The grid frequency is compared to a frequency setpoint, with the frequency deviation (f)
used to generate a frequency-dependent setpoint component (SETP) and perform a dynamic
analysis (SETP_DYN). The SETP_DYNparameter is used to generate control signals in the
unit coordination control system, with static weighting applied for the steam turbine control
system. The statically weighted signals are used to correct the steam turbine setpoints and the
control deviations, causing the desired release of reserve capacity within seconds via the
control valves.
500
470
460
450
PUNIT(MW)
PUNIT
PGT(MW)
PGT
PST
PGT = P UNIT
operation with active STbase load 450 MW
50
40
30
20
10
0
50
40
30
20
10
NextPreviousOptions
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
17/21
reserve capacity. Once the reserve capacity has been made available, the steam section is
automatically returned to modified variable-pressure mode.
Shifting part of the primary control power to the steam turbine provides two important
advantages over the concept used previously:
The desired level of primary control power can be held ready at higher base load (by reducing
the gas turbine contribution by the magnitude of the steam turbine contribution).
Simultaneously, the dynamic characteristics of the unit are improved through temporary
activation of the steam process (increases in steam turbine output can be implemented at the
fast positioning speed that is a feature of the turbine inlet valves).
A comparison of the two concepts for releasing reserve capacity is shown in Fig. 10.
At present, a control concept is being developed for primary control using the ST in the range
of small frequency deviations (up to about 50 mHz). The gas turbine in this case is called
upon for large frequency dips and for secondary control. This concept will mobilize the
advantages to be gained by shifting a part of the primary control reserve to the steam turbine.
Controlled access to the ST control power contribution in the range of small frequency
deviations substantially improves the dynamic characteristics of the unit and ensures a gas
turbine operating mode that minimizes life-limiting effects.
7. Conclusion
Over its many years of experience in the power plant business, the Siemens Power Generation
Group has kept pace with the new demands for involving the generating units in frequency
control within the interconnected power system.
A steady stream of new and innovative approaches to existing and proven control concepts
helps us meet the requirements of the transmission system operators. The complexity of a
NextPreviousOptions
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
18/21
8. References
Activating the steam side increases base load capacity. Modern Power Systems,
January 2002
Advanced primary control with combine cycle power plants. Proceeding of the 3rd
International Conference Electric Power Quality and Supply Reliability, Sept. 4-6,
2002, Haapsalu, Estonia
Einsatz der Dampfturbine eines GUD-Kraftwerkes zur Primrregelung. EPE
Electric Power Engineering 2003, 5thInternational Scientific Conference, Jan 28-29,
2003, Visalaje, Czech Republic
ESB Grid Code / requirement, Ireland
Frequency Response Capability of Combined-Cycle Power Plants 12th Conference
of the Electric Power Supply Industry Cepsi 02-06 November 1998
GRTN, TRANSMISSION AND DISPATCHING CODE / requirement, Italy
NGT Grid Code / requirement, England/Wales
RAE Grid Code / requirement, Greece
RED ELCTRICA DE ESPAA Grid Code / requirement, Spain
Siemens Power Journal 2/2000
Siemens Power Journal online May 2002
Transmission Code 2003 / requirement, Germany
UCTE Operation Handbook, www.ucte.org
UNE Grid Code / requirement, Morocco
NextPreviousOptions
NextPreviousOptions
http://www.ucte.org/http://www.ucte.org/http://www.ucte.org/http://www.ucte.org/8/13/2019 3 Fulfillment of Grid Code
19/21
Page 19 of 21
Appendix 1, Requirements of various TSOs
UCTE Members RC= registered capacity
Country / Grid Code Primary Control
Controlband/Deadband/Dynamics
Secondary Control
Controlband / Dynamics
Additionals
UCTE OpHB
Policy 1
Load frequency
control(final draft 1.9E,
31.12.2003)
based on
UCPTE*-Ground
Rules
of 01.06.98
Primary control bandaccording to the control zone.
Deadband < 10 mHz Dynamics: primary operating
reserve / 30 s linear according
to control zone.
At !f = -0.2 Hz provision offull primary operating reserve
Value of 8%/min for oil / gaspower plants will be used as
an aid and are not required. The tracking-speed can be
set from 50 to 200 s.
Germany
Transmission
Code 2003
Primary control band +/-2%of RC
Fully available at !f = 200mHz after 30 s for 15 min.
Gradient 2% / 3 0s Deadband < +/-10 mHz
Not a must
Right to participate insecondary frequency control
after compliance with
prequalification
Load rejection to house load supply must be controlled. Primary reserve additional to speed of load change and
secondary reserve
Grid Island Mode:control band: increase !P = +1.5%
load decrease until minimum load reached
details must be discussed between
grid and plant operators Load dip due to falling frequency restricted according
to Figures 2.1 und 2.2
p
NextPreviousOptions
8/13/2019 3 Fulfillment of Grid Code
20/21
Page 20 of 21
Country / Grid Code Primary Control
Controlband/Deadband/Dynamics
Secondary Control
Controlband / Dynamics
Additionals
Spain
RED Grid Code Primary control band +/-1.5%
of RC
Fully available at !f = 200mHz after 30s for 15 min.
Deadband < +/-10 mHz Droop must be adjustable
Not a must:
A condition for participationin secondary control by
generators is a respective
Qualification of OS
Italy
GRTN GridCode
CA, CC und
11
StandardCEI 11-32
Primary control band +/-3% oRC
Fully available at !f = 200mHz after 30s for 15 min.
Deadband < +/-10 mHz Droop 2 8%, must be
adjustable
Specific agreement
SC-band = +/-6% of theactive plant power with 8%
/min of the GT part of the
combined cycle
The primary and secondary control windows areindependent from each other. The overall control
window is the sum value of the two.
Islanded Mode: correct operation in an islanded grid.... restore the frequency on the island at rated value of
+/-0.25%..
Greece
RAE
Grid Code
Primary control band +/-3%of RC in the load range of 50
97% RC, then linear
decrease.
Fully available at !f = 200
mHz after 30 s for 15 min. Deadband < +/-10 mHz Droop must be adjustable
according to the requirements
of HTSO
Secondary operating reservenot less than 3% of RC in a
load range of 50 97% RC,
then linear decrease
Remain synchronized with the grid at frequency 47.5 to49.5 Hz and 51.5 to 52.5 Hz for a duration of 60
minutes
Remain synchronized with the grid at frequency 52.5 to53 Hz for a duration of 5 s.
Minimum load not greater than 35% RC Load dip due to falling frequency:
Supply of rated load in the frequency range of 49.5
50.5 Hz.
p
PreviousOptions
8/13/2019 3 Fulfillment of Grid Code
21/21
Page 21 of 21
Non UCTE Members,
Country / Grid Code Primary ControlControlband/Deadband/Dynamics
Secundary ControlControlband / Dynamics
Additionals
Morocco UNE
Techn. rules for
the operation of the
connection grid
Spain Morocco
Primary control band +/-2.5%of RC (expotential Ta = 10s)
at !f = 200 mHz
Deadband < +/-10 mHz Droop 2 6%
The COMELEC operatingzone must be equipped with a
grid operation system.
Morocco is a COMELEC-member. COMELEC isbeing represented within UCTE by REE (Spain). For
COMELEC the technical rules of UCTE are valid.
England / Wales
NGT Grid Code Min. requirement +/-10% RC
10s after start of frequency
ramp of -0.5Hz / 10 s the
frequency response must be
10% RC.
Deadband < +/-15 mHz. Limited frequency control in
case of f > 50.4Hz
Droop 3 5% NGT normallyrequires 4%.
Min. requirement +/-10% RC30 s after start of frequency
ramp of 0.5Hz / 10 s the
frequency response must be
10% RC.
No load decrease on frequency fall of up to 49 Hz. Target frequency correction with +/-100 mHz must be
possible.
Islanded ModeThere must be the ability to control an island formation
between 55% and 100% RC.
Load dip due to falling frequency:In the range 50.5 to 49.5 Hz continuous active power !
In the range 49.5 to 47 Hz linear decrease in active
power by not more than 5%.
Ireland
ESB Grid Code
Primary operation reserve +/-
5% RC in the load range 50 95% RC, then linear decrease
allowed
Fully available in real time atfrequency nadir between 5
15 s
Secondary operating reserve
not less than 5% of RC in theload range 50 95% RC,
with linear decrease then
allowed.
Fully available in the timerange of 15 90 s
Remain synchronized with the grid at frequency 47.5 to
52.5 Hz for a duration of 60 min Remain synchronized with the grid at frequency 47.5 -
47 Hz for a duration of 20s.
No load increase in the range of 49.5 50.5 Hz Minimum load not < 50% RC for CC and not < 35%
RC for steam turbine plant.