3A3 FWH Turbine Floor Wall Wall Boilermakers weld lifting lugs to old shell. The lugs are designed to match the connection style of the new heater shell lugs. Prepared By Steven Cooper

#3 Heater Rigging concept Rev 2

Embed Size (px)

Citation preview

Page 1: #3 Heater Rigging concept  Rev 2

3A3 FWH

Turbine Floor

WallWall

Boilermakers weld lifting lugs to old shell. The lugs are designed to match the connection style of the new heater shell lugs.

Prepared BySteven Cooper

Page 2: #3 Heater Rigging concept  Rev 2

3A3 FWH

Boilermakers weld temporary attachments to heater shell in 4 locations over the cut line (If required). Supports are designed to allow the cutting head to travel through the support.

Turbine Floor

WallWall

The crane is released while Tri-Tool installs the cutter and performs the entire cut to the shell. The shell is supported by the walls (temporary supports if required) saving 72 hours of crane time through removal and installation of the new shell.

The Boilermakers rig the lifting device to the crane. The lifting device is then set on the heater room walls and attached to the new lugs previously welded to the heater shell.

Tri-Tool removes cutting equipment and the crane is re-attached to the lifting device and the heater shell.

Prepared BySteven Cooper

Page 3: #3 Heater Rigging concept  Rev 2

3A3 FWH

Attachments are cut by torch at the top of the attachment before the heater shell is lifted out by the crane. Bottom welds will be removed by grinding after the lift.

The crane then lifts the old heater shell out of the room to be set on cribbing on the turbine deck or truck bay.

Turbine Floor

WallWallPrepared By

Steven Cooper

Page 4: #3 Heater Rigging concept  Rev 2

The lifting device is detached from the heater shell and carried to a staging location. The heater shell can then be rigged with nylon slings and laid horizontal in the Sea / Land.

3A3 FWH

Turbine Floor

WallWall

3A3 FWH