1
WINDOW HEIGHT 1173 MM WALL THICKNESS 191 MM CUPBOARD FUSE BOARD TILE FLOOR CHIMNEY WALL THICKNESS 319 MM ARCHWING OVER THE DOORS 5400 6646 850 1650 KITCHEN CUPBOARD VELUX WINDOW KITCHEN CUPBOARD ISLAND STEEL BEAM WINDOW BATHROOM NEW SLIDING GLAZED DOOR WALL THICKNESS 300 MM CUPBOARD CUPBOARD CORNER BOILER FLEW TROUGH ATIC CHIMNEY BREAST CHIMNEY BREAST PVC DOUBLE WINDOW BRICK LINE BRICK CLADING ROOF BRICK LINE WINDOW WITH DIAMONT LEADED WATER GUTTER PIPE (50MM) +0000 +3200 +7657 GUTTER+ FUSION BOARD MARLEY ROOF TILE PITCH ROOF VELUX WINDOW STEP OBSCURE GLADED WINDOW +2400 +5000 6646 +0000 +7157 +5000 +7657 +0000 +2400 5095 2611 +0000 +1840 +420 +1840 +0000 Garden level Rear entry level (lower than garden level) +0000 +2310 5400 +0000 +2400 +0000 +2400 5400 6095 4286 +0000 +2310 +3310 +420 +1840 +0000 Garden level Rear entry level (lower than garden level) +2840 +0000 +1840 +2840 +420 +1840 +0000 Garden level Rear entry level (lower than garden level) +2840 Revision A 15/09/15 M.C.P. Dimensions and notes added onto drawing sheet Project title 31 TORBAY ROAD Drg title Plans and Elevations The Drawing Desk, Coventry Drawn M C P Checked P S B Date 30/07/2015 Scale 1:100 Project No. 2015/03 Drg No. 02 Revision B Existing Floor Plan Rear Elevation Existing Rear Elevation Existing Elevation Existing Ground Floor Plan Existing+ Proposed First Floor Plan Proposed Ground Floor Plan Extension Elevation Existing+ Proposed Elevation Existing Rear Elevation Existing Side Elevation 1 (29) Existing Side Elevation (33) Proposed Side Elevation (29) Proposed Side Elevation (33) Proposed Floor Plan Proposed Rear Elevation Proposed Side Elevation Proposed Side Elevation Proposed Front Elevation Notes All new bricks and roof tiles to match existing All new drainage to connect into existing Garage hip roof will have minimum 150mm overhang on all sides Revision B 05/10/15 M.C.P. Garage roof revised to suit planner comments

31 TORBAY ROAD-Revision B

Embed Size (px)

Citation preview

Page 1: 31 TORBAY ROAD-Revision B

WINDOW HEIGHT 1173 MM

WALL THICKNESS 191 MM

CUPBOARD

FUSE BOARD

TILE FLOOR

CHIMNEY

WALL THICKNESS 319 MM

ARCHWING OVER THE DOORS

5400

6646

850

1650

KITCHEN CUPBOARD

VELUX WINDOW

KITCHEN CUPBOARD ISLAND

STEEL BEAM

WINDOW

BATHROOM

NEW SLIDING GLAZED DOOR

WALL THICKNESS 300 MM

CUPBOARD

CUPBOARD

CORNER

BOILER FLEW TROUGH ATIC

CHIMNEY BREAST

CHIMNEY BREAST

PVC DOUBLE WINDOW

BRICK LINE

BRICK CLADING

ROOF

BRICK LINE

WINDOW WITH DIAMONT LEADED

WATER GUTTER PIPE (50MM)

+0000

+3200

+7657

GUTTER+ FUSION BOARD

MARLEY ROOF TILE

PITCH ROOF

VELUX WINDOW

STEP

OBSCURE GLADED WINDOW

+2400

+5000

6646

+0000

+7157

+5000

+7657

+0000

+2400

5095

2611

+0000

+1840

+420

+1840

+0000

Garden

level

Rear entry level

(lower than

garden level)

+0000

+2310

5400

+0000

+2400

+0000

+2400

5400

6095

4286

+0000

+2310

+3310

+420

+1840

+0000

Garden

level

Rear entry level

(lower than

garden level)

+2840

+0000

+1840

+2840

+420

+1840

+0000

Garden

level

Rear entry level

(lower than

garden level)

+2840

Revision A 15/09/15 M.C.P. Dimensions and notes

added onto drawing sheet

Project

title

31 TORBAY ROAD

Drg

title

Plans and

Elevations

The Drawing Desk, Coventry

Drawn M C P

Checked P S B

Date

30/07/2015

Scale

1:100

Project No.

2015/03

Drg No.

02

Revision

B

Existing Floor Plan Rear Elevation Existing Rear Elevation Existing Elevation

Existing Ground Floor

Plan

Existing+ Proposed First Floor

Plan

Proposed Ground Floor Plan

Extension Elevation

Existing+ Proposed Elevation Existing Rear Elevation

Existing Side Elevation 1 (29)

Existing Side Elevation (33) Proposed Side Elevation (29) Proposed Side Elevation (33)

Proposed Floor

Plan

Proposed Rear

Elevation

Proposed Side

Elevation

Proposed Side

Elevation

Proposed Front

Elevation

Notes

All new bricks and roof tiles to match

existing

All new drainage to connect into existing

Garage hip roof will have minimum

150mm overhang on all sides

Revision B 05/10/15 M.C.P. Garage roof revised to

suit planner comments