Upload
dangthuy
View
215
Download
0
Embed Size (px)
Citation preview
Jim Toporski 1418079_TechMem_006_Rev1
Sasol Synfuels 7 April 2015
4/11
Tree and shrub screen, 15 m landfill height
Tree and shrub screen, 20 m landfill height
Figure 2: View from Charlie 1 Gate - tree and shrub combination screen
3.2 View from Graceland Casino At present the degree of visibility of the landfill from the Graceland Casino grounds is limited, due to the presence of existing trees located in the area in between.
The visual impact is also further reduced due to the distance between the landfill and the casino and as a result, only the western half of the landfill is exposed to view.
However the visibility of the landfill increases significantly when its height is increased, due to the fact that the Casino is located in a slightly elevated position in relation to the landfill. This occurrence will be more pronounced when viewed from the higher storeys of the casino hotel, as viewers would effectively look over the existing vegetation onto the landfill. While the existing vegetation still offers some degree of screening at a height of 5 m and 10 m, more than half of the facing landfill side slope will be visible at a height of 15 m and especially at 20 m.
By establishing a tree screen along the western half of the northern site boundary, the landfill can still be significantly screened from view at a landfill height of 5 m. This is no longer the case at a landfill height of 10 m as the upper half of the landfill is now visible above the existing trees in the left hand half of the view and also protrudes above the tree screen. The level of visibility of the landfill is especially higher at heights of 15 m and 20 m, as the tree screen is no longer expected to obscure the top half of the landfill. However, the distance between the landfill and the casino is expected to mitigate the visual impact to some extent, especially once the landfill has been re-profiled and vegetated. In addition, the landfill will effectively screen much of the Sasol infrastructure behind it as its heights increases.
These aspects are illustrated by Figure 3.
Jim Toporski 1418079_TechMem_006_Rev1
Sasol Synfuels 7 April 2015
5/11
Existing scenario
Tree screen and 5 m landfill height
Landfill extents
Landfill extents
Jim Toporski 1418079_TechMem_006_Rev1
Sasol Synfuels 7 April 2015
6/11
Tree screen and 10 m landfill height
Tree screen and 15 m landfill height
Landfill extents
Landfill extents
Jim Toporski 1418079_TechMem_006_Rev1
Sasol Synfuels 7 April 2015
7/11
Tree screen and 20 m landfill height Figure 3: View from Graceland Casino
3.3 View from Secunda Mall shopping Centre Similar to the Charlie 1 Gate, the visual impact of the landfill is at present significantly mitigated by the distance between the two areas and the presence of significant existing vegetation. In addition, the backdrop of the existing Sasol plant infrastructure and ash dams result in the landfill site not being visually intrusive.
This remains to be the case when the landfill is expanded to a height of 5 m, as the existing visual horizon backdrop or silhouette presented by Sasol is still “higher” than that of the landfill, effectively masking the landfill from view. By establishing a tree screen along the northern and eastern site boundary, the landfill is effectively completely screened from view. At a height of 10 m the topmost part of the dump protrudes above the tree screen but is still not expected to be visually prominent as it will likely be overshadowed by the infrastructure behind it.
Whilst the level of visibility of the landfill increases more significantly with a height increases to 15 m and 20 m, the resultant visual impact is still largely mitigated for the same reasons as stated above. The landfill is also not expected to significantly screen any of the existing Sasol infrastructure, at least not from elevated positions along the upper levels of the mall complex.
The above options are illustrated on Figure 4.
Landfill extents
Jim Toporski 1418079_TechMem_006_Rev1
Sasol Synfuels 7 April 2015
8/11
Existing scenario
Tree screen and 5 m dump height
Dump extents
Dump extents
Jim Toporski 1418079_TechMem_006_Rev1
Sasol Synfuels 7 April 2015
9/11
Tree screen and 10 m dump height
Tree screen and 15 m dump height
Dump extents
Dump extents
Jim Toporski 1418079_TechMem_006_Rev1
Sasol Synfuels 7 April 2015
10/11
Tree screen and 20 m dump height Figure 4: View from Secunda Mall shopping centre
4.0 DISCUSSION AND RECOMMENDATIONS Based on the findings of the visual modelling conducted the most sensitive visual receptor is expected to be Charlie 1 Gate, as it is located directly adjacent to the existing landfill and hence has the highest visual exposure to the proposed landfill expansion. However, it is expected that the visual impact can be significantly mitigated by planting a tree and shrub screen along the perimeter of the site, regardless of the final height of the landfill.
Conversely, the extent to which the landfill can be screened is somewhat limited from the other receptor locations, as in most instances the viewer will be able to see over a vegetative screen than is planted alongside the landfill, especially at a final height of 15 m or 20 m. However, the severity of the visual impact is reduced due to the distance between the landfill and these receptor locations; and is expected to be further mitigated once the landfill has been re-profiled and vegetated. In addition, the landfill will in some instances actually serve to screen parts of the Sasol complex from view. Given the above considerations, from a visual perspective a final height of up to 10 m is likely to be considered unobtrusive as the impact can be largely mitigated from Charlie 1 Gate; and is not expected to be especially significant from the other main receptors which are located some distance away.
In terms of plant species, poplar (Populus nigra) and Plumbago auriculata were used as screening tree and shrub species respectively, as both species are expected to grow in the local climate. A number of other species may also be suitable for this purpose, which will influence the degree of visual screening provided as well as overall appearance of the resultant scenery. However, suitable non-invasive tree species choices are limited as few relatively fast-growing species would be suited to the climate. Another tree species that may be considered is the Fever tree (Acacia xanthophloea), while additional shrub species could include Ehretia rigida and Buddleja salviifolia. It is recommended that a botanist be consulted to provide further guidance in this regard.
Furthermore it is recommended that Sasol further engage with potentially affected stakeholders regarding the expansion of Charlie 1 landfill, to ensure that potential dissatisfaction or tension in this regard is avoided.
Dump extents
Jim Toporski 1418079_TechMem_006_Rev1
Sasol Synfuels 7 April 2015
11/11
5.0 ASSUMPTIONS AND QUALIFICATIONS The following assumptions and qualifications apply to the visual assessment and resultant findings:
Only fully mitigated options are presented i.e. assuming the landfill has been re-shaped, capped and vegetated and all vegetative screens have been fully established, as opposed to an operational situation, which will likely be visually less favourable;
The modelled options assumed that all screening vegetation will be planted at commencement of landfill expansion, in order to afford sufficient time for plants to grow. The degree of visual screening will be compromised if screening vegetation is only planted towards end of operations;
The visual assessment assumed that optimal growth of plant species as well as re-vegetation of the landfill itself will have taken place. Poor plant growth as a result of unfavourable conditions or inadequate maintenance or other unforeseen occurrences were not taken into consideration, and will compromise the degree of screening as well as visual quality of resultant scenery;
The images represented in this document are significantly reduced in scale and therefore likely “underplay” the likely actual appearance and resultant visual impact of the expanded landfill. Images at appropriate scale are therefore separately provided on an accompanying DVD, and should be printed to A2 paper size to provide reasonable representation of expected effects; and
The results of this visual assessment process are based on conceptual/preliminary landfill designs and screening vegetation placement arrangements; and should therefore be considered as indicative only in the event of notable landfill configuration changes with detailed design.
J Bothma SAP Brown Rehabilitation and Closure Rehabilitation and Closure JB/SAPB/jp g:\projects\1418079 - sasol charlie1cepsecunda\3.2 in -out info\1418079_techmem_006_charlie 1_visualmodelling_rev1_20150407.docx
CHARLIE 1 - FEASIBILITY ENGINEERING
June 2015 Report No. 1418079-13574-1
APPENDIX I Cost breakdown
Sasol Charlie 1 GAA - 1418079Feasibility EngineeringITEM NO DESCRIPTION AMOUNT
1 SECTION 1 - STORMWATER INTERCEPTION DRAINSREFERENCE DRAWINGS FOR THIS SECTION:1418079-0200-D (set)1418079-0501-D
1.1 SECTION 1.1: BULK EARTHWORKS
1.1.1 Clear and Grub site on alignment including removal of small trees, bushes, grass, roots, and waste and disposal on landfill.
R 250 000.00
1.1.2 Strip waste layer where applicable along toe of landfill and place within current waste despoition cell
R 600 000.00
1.1.3Excavation for channels. Excavated material to be placed along outside of channel to form berm with nominal compaction
R 560 000.00
1.1.4 Excavation for silt trap R 160 000.00
1.2 SECTION 1.2: DIVERSION BERM
1.2.1 Rip 150mm deep under diversion berm footprint and compact at 93% MOD aashto within 2% OMC
R 100 000.00
1.2.2 Construct berm in 300mm layers, compacted to 98% Proctor density at -1% to 2% OMC
R 100 000.00
1.3 SECTION 1.3: DRAINS
1.3.1 Restricted excavation (300x300mm) for geocell anchor trenches, including backfill and compaction
R 45 000.00
1.3.2 100mm thick geocells R 540 000.00
1.3.3 30MPa/19mm concrete infill R 1 350 000.00
1.4 SECTION 1.3: DRAIN-ROAD CROSSING
1.4.1 Structure, including brick headwalls and concrete pipes as per Drawing 0501
R 70 000.00
1.5 SECTION 1.4: SILT TRAP
1.5.1 Compact silt trap floor to 93% MOD AASHTO density at least 1m deep
R 40 000.00
1.5.2Load haul and fill of excavated material for ramp of silt trap
R 4 000.00
1.5.3 Concrete 25/19 , including shuttering R 525 000.00
1.5.4 Reinforcement for concrete R 420 000.00
1.5.5 Stainless steel safety escape ladder R 40 000.00
R 4 804 000.00TOTAL FOR SECTION 1 - CONTAMINATED
STORMWATER INTERCEPTION (Carried to Summary)
Sasol Charlie 1 GAA - 1418079Feasibility EngineeringITEM NO DESCRIPTION AMOUNT
2 SECTION 2 - LEACHATE INTERCEPTION DRAINS
REFERENCE DRAWINGS FOR THIS SECTION:1418079-0300-D (set)1418079-0502-D
2.1 SECTION 2.1: EARTHWORKS
2.1.1 Cut trench into in-situ material approximately 3m deep by 0.6m wide, and move to landfill
R 270 000.00
2.1.2 Extra over item 1.1.2 for hard excavation R 90 000.00
2.1.3 Backfill trench and apply 300mm layer to toe of landfill with washed riversand.
R 270 000.00
2.1.4 300mm thick cover soil layer over trench to landfill toe R 300 000.00
2.2 SECTION 2.2: SUPPLY AND INSTALL DRAIN COMPONENTS
2.2.1 DN 160 Wastex HDPE pipe attached with cable ties R 120 000.00
2.2.2 1mm LLDPE geomembrane liner wrapped around Wastex pipe at bottom of trench (lower 100mm)
R 40 000.00
2.2.3Geocomposite drain wrapped around pipe at bottom of trench, extended out of trench, including anchorage into waste body (Macdrain W1051 or Techdrain GTG512 or similar approved)
R 2 100 000.00
2.2.4 1.5mm LLDPE double textured geomembrane R 2 400 000.00
2.3 SECTION 2.3: SUPPLY AND INSTALL LEACHATE MANHOLE COMPONENTS (x13)
2.3.1 150mm thick concrete base slab, 30 MPa R 10 500.00
2.3.2 Mesh ref 395 R 10 000.00
2.3.3 20 Mpa concrete benching on manhole floor R 8 400.00
2.3.4 90 degree HDPE slip-on elbows R 6 500.00
2.3.5 450x450 coneret collars, grade 30/20 concrete R 26 000.00
2.3.6 1250 diameter precast concrete manhole rings with bituseal joints and step irons for access.
R 200 000.00
2.3.7 Bitumen coated grid manhole cover R 13 000.00
SUB-TOTAL CARRIED FORWARD R 5 864 400.00
R 5 864 400.002.4 SECTION 2.4: SUPPLY AND INSTALL LEACHATE
SUMP COMPONENTS
2.4.1 50mm blinding concrete (15 Mpa) applied to floor R 500.00
2.4.2 250mm thick concrete base slab, 30 MPa R 4 500.00
2.4.3 1500 diameter precast concrete manhole rings with bituseal joints and step irons for access.
R 27 000.00
2.4.4 1950 diameter precast concrete manhole rings with bituseal joints.
R 30 000.00
2.4.5 Concrete infill between manhole rings, 30 Mpa R 12 000.00
2.4.6 Multibit 1702 corrosion resistant coating to internal walls R 1 800.00
2.4.7 550x550x250 concrete collar, grade 30/20 concrete R 3 000.00
2.4.8 Bitumen coated grid manhole cover R 1 000.00
2.5 SECTION 2.5: SUPPLY AND INSTALL LEACHATE SUMP PUMP COMPONENTS
2.5.1 1.6 kW submercible pump R 50 000.00
2.5.2 HDPE DN50 pipe R 20 000.00
2.5.3 Allowance for burying of pipe, pipe fittings, link to pond R 50 000.00
R 6 064 200.00
BROUGHT FORWARD
TOTAL FOR SECTION 2 - LEACHATE INTERCEPTION (Carried to Summary)
Sasol Charlie 1 GAA - 1418079Feasibility EngineeringITEM NO DESCRIPTION AMOUNT
3 SECTION 3 - CONTAMINATED STORMWATER POND
REFERENCE DRAWINGS FOR THIS SECTION:1418079-0200-D (set)1418079-0503-D
3.1 SECTION 3.1: EARTHWORKS
3.1.1 Clear and Grub pond footprint including removal of small trees, bushes, grass, and roots and disposal on landfill.
R 100 000.00
3.1.2 Excavate in all materials for boxcut, remove unsuitable material and construct main fill in layers not exceeding 300mm Compacted to 95% Proctor Density at OMC to OMC +2%(a) Cut R 1 200 000.00
(b) Fill R 350 000.00
Rip and recompact pond bases to a minimum depth of 150mm, grade to falls and recompact to 95% Proctor dry density at OMC to OMC +2%.
R 400 000.00
Lightly compact dam footprint area to form 150mm base preparation layer for liner application
R 600 000.00
3.2 SECTION 3.2: SUB-SOIL DRAINAGE
3.2.1 Place and compact 450mm washed river sand layer R 75 000.00
3.2.2 Drainex DN110 HDPE pipes, including joints and fittings R 60 000.00
3.3 SECTION 3.3: LINER SYSTEM SUPPLY AND INSTALLATION
3.3.1 200mm thick clay layer, compacted to 95% Proctor density at OMC to OMC +2%
R 280 000.00
3.3.2 1.5mm thick HDPE geomembrane liner R 990 000.00
3.3.3 Cuspated HDPE drainage sheet R 540 000.00
3.3.4 2mm thick HDPE geomembrane liner R 1 170 000.00
3.3.5 Excavation of anchor trenches for liners, including backfill and compaction
R 36 000.00
3.4 SECTION 3.3: SUMPS (x1)
3.4.1 Restricted excavation in all materials R 540.00
3.4.2 Non-woven geotextile, Bidim A8 R 1 750.00
3.4.3 19mm washed stone R 2 400.00
3.4.4 200mm diameter PE63 PN10 HDPE Class PN63 leakage drainage pipe
R 15 000.00
3.4.5 Liner penetration, including "boot" fitting with sealing R 5 000.00
3.4.6 Precast manhole monitoring sump, including excavation R 25 000.00
3.5 SECTION 3.5: SPILLWAY
3.5.1 Spillway structure as per drawing detail R 50 000.00
3.5.2 First flush structure as per detail R 15 000.00
3.6 SECTION 3.6: SAFETY
3.6.1 Safety rope with bouys as well as safety net and signage R 25 000.00
R 5 940 690.00TOTAL FOR SECTION 3 - CONTAMINATED STORMWATER POND (Carried to Summary)
Sasol Charlie 1 GAA - 1418079Feasibility EngineeringITEM NO DESCRIPTION AMOUNT
4 SECTION 4 - LEACHATE POND
REFERENCE DRAWINGS FOR THIS SECTION:1418079-0300-D (set)1418079-0504-D
4.1 SECTION 4.1: EARTHWORKS
4.1.1 Clear and Grub pond footprint including removal of small trees, bushes, grass, and roots and disposal on landfill.
R 60 000.00
4.1.2 Excavate in all materials for boxcut, remove unsuitable material and construct main fill in layers not exceeding 300mm Compacted to 95% Proctor Density at OMC to OMC +2%(a) Cut R 120 000.00
(b) Fill R 225 000.00
Rip and recompact pond bases to a minimum depth of 150mm, grade to falls and recompact to 95% Proctor dry density at OMC to OMC +2%.
R 240 000.00
Lightly compact dam footprint area to form 150mm base preparation layer for liner application
R 360 000.00
4.2 SECTION 4.2: SUB-SOIL DRAINAGE
4.2.1 Place and compact 450mm washed river sand layer R 50 000.00
4.2.2 Drainex DN110 HDPE pipes, including joints and fittings R 30 000.00
4.3 SECTION 4.3: LINER SYSTEM SUPPLY AND INSTALLATION
4.3.1 200mm thick clay layer, compacted to 95% Proctor density at OMC to OMC +2%
R 175 000.00
4.3.2 1.5mm thick HDPE geomembrane liner R 1 023 000.00
4.3.3 Cuspated HDPE drainage sheet R 558 000.00
4.3.4 2mm thick HDPE geomembrane liner R 604 500.00
4.3.5 Excavation of anchor trenches for liners, including backfill and compaction
R 24 000.00
4.4 SECTION 4.3: SUMPS (x2)
4.4.1 Restricted excavation in all materials R 1 080.00
4.4.2 Non-woven geotextile, Bidim A8 R 3 500.00
4.4.3 19mm washed stone R 4 800.00
4.4.4 200mm diameter PE63 PN10 HDPE Class PN63 leakage drainage pipe
R 30 000.00
4.4.5 Liner penetration, including "boot" fitting with sealing R 10 000.00
4.4.6 Precast manhole monitoring sump, including excavation R 50 000.00
4.5 SECTION 4.5: SPILLWAY
4.5.1 Spillway structure as per drawing detail R 50 000.00
4.5.2 First flush structure as per detail R 15 000.00
4.6 SECTION 4.6: SAFETY
4.6.1 Safety rope with bouys as well as safety net and signage R 20 000.00
R 3 653 880.00TOTAL FOR SECTION 4 - LEACHATE POND (Carried to
Summary)
Sasol Charlie 1 GAA - 1418079Feasibility EngineeringITEM NO DESCRIPTION AMOUNT
5 SECTION 5 - EVAPORATION AND ABSTRACTION SYSTEMS
REFERENCE DRAWINGS FOR THIS SECTION:1418079-0401-D
5.1 SECTION 5.1: STORMWATER ENHANCED EVAPORATIVE SYSTEM
5.1.1 Whirljet hollow cone nozzles R 19 200.00
5.1.2 PVC spray header (accomodates 3 nozzles). Includes isolation valve, flexible hose, fittings and swage nipples
R 112 000.00
5.1.3 Vertical multistage centrifugal 5.5 kW pump R 60 000.00
5.1.4 Pump station, including manifolds, gauges, isolation valves, suction line and foot valve, as well as control panel
R 40 000.00
5.1.5 HDPE piping (PN16 PE100 SDR26) R 35 000.00
5.1.6 Auto flush strainer bank R 35 000.00
5.1.7 Fittings and accessories R 40 000.00
5.1.8 Installation of system R 60 000.00
5.2 SECTION 5.1: LEACHATE ENHANCED EVAPORATIVE SYSTEM
5.2.1 Whirljet hollow cone nozzles R 9 600.00
5.2.2 PVC spray header (accomodates 3 nozzles). Includes isolation valve, flexible hose, fittings and swage nipples
R 56 000.00
5.2.3 Vertical multistage centrifugal 3 kW pump R 45 000.00
5.2.4 Pump station, including manifolds, gauges, isolation valves, suction line and foot valve, as well as control panel
R 40 000.00
5.2.5 HDPE piping (PN16 PE100 SDR26) R 15 000.00
5.2.6 Auto flush strainer bank R 35 000.00
5.2.7 Fittings and accessories R 30 000.00
5.2.8 Installation of system R 50 000.00
5.3 SECTION 5.3: ABSTRACTION
5.3.1 Vertical multistage centrifugal 2.2 kW pump R 12 000.00
5.3.2 Gooseneck structure as per drawing detail (0506) R 75 000.00
5.3.3 HDPE piping from ponds to gooseneck R 40 000.00
R 808 800.00TOTAL FOR SECTION 5 - EVAPORATION AND ABSTRACTION SYSTEMS (Carried to Summary)
Sasol Charlie 1 GAA - 1418079Feasibility EngineeringITEM NO DESCRIPTION AMOUNT
6 SECTION 6 - MISCELLANEOUS
REFERENCE DRAWINGS FOR THIS SECTION:-
6.1 SECTION 6.1: VEGETATIVE SCREEN
6.1.1 Tree screen (populus nigra, or similar approved) R 100 000.00
6.1.2 Shrub screen (plumbago auriculata, or similar approved) R 40 000.00
6.1.3 Topsoil (100mm) applied to planted areas R 400 000.00
6.1.4 Compost (50mm) R 350 000.00
6.2 SECTION 6.2: FENCING
6.2.1 Galvanised razor mesh fencing, 1.8m high, as per Drawing 0507
R 280 000.00
6.2.2 Double swing gate in galvanised razor mesh security fence complete as per detail drawing 0507
R 10 000.00
6.3 SECTION 6.3: WEATHER STATION
Weather station for automation of evaporative systems, site monitoring, etc
R 25 000.00
R 1 205 000.00TOTAL FOR SECTION 6 - MISCELLANEOUS
(Carried to Summary)
Sasol Charlie 1 GAA - 1418079Feasibility EngineeringITEM NO DESCRIPTION AMOUNT
7 SECTION 7 - INITIAL LANDFILL SHAPING
REFERENCE DRAWINGS FOR THIS SECTION:1418079-0600-D (set)
7.1 SECTION 7.1: SHAPING
7.1.1 Cut to fill for Area A R 910 000.00
7.1.2 Cut to fill for Area B R 770 000.00
7.1.3 Cut to fill for Area C R 805 000.00
7.2 SECTION 7.2: INTERIM COVER
7.2.1 Apply 300mm interim cover to Area A and compact, material sourced on site
R 850 000.00
Apply 300mm interim cover to Area B and compact, material sourced on site
R 850 000.00
Apply 300mm interim cover to Area C and compact, material sourced on site
R 500 000.00
R 4 685 000.00TOTAL FOR SECTION 8 - INITIAL LANDFILL SHAPING
(Carried to Summary)
Sasol Charlie 1 GAA - 1418079Feasibility Engineering
DESCRIPTION AMOUNT
SECTION 1 - SW INTECEPTION R 4 804 000.00
SECTION 2 - LEACHATE INTERCEPTION R 6 064 200.00
SECTION 3 - SW POND R 5 940 690.00
SECTION 4 - LEACHATE POND R 3 653 880.00
SECTION 5 - EVAPORATION AND ABSTRACTION SYSTEMS R 808 800.00
SECTION 6 - MISCELLANEOUS R 1 205 000.00
SECTION 7 - INITIAL LANDFILL SHAPING R 4 685 000.00
SUB-TOTAL R 27 161 570.00
PRELIMINARY AND GENERAL (25%) R 6 790 392.50
SUB-TOTAL R 33 951 962.50
CONTINGENCIES (15%) R 5 092 794.38
TOTAL R 39 044 756.88
SUMMARY OF SECTIONS
CHARLIE 1 - FEASIBILITY ENGINEERING
June 2015 Report No. 1418079-13574-1
APPENDIX J Waste Stream Volumes
WASTE INVENTORY
2014Month Builder Rubble(m3) Cover Material(m3) Domestic Waste(m3) Garden Waste(m3) Insulation Waste(m3) Spent Catalyst(m3) Total(m3)
July 459 4806 5034 82 797 702 11880August 115 4103 5151 120 522 50 10061September 471 4214 4879 149 500 340 10553October 1156 6554 6458 232 736 470 15606November 201 2691 4051 97 324 340 7704December 133 2160 3620 201 322 290 6726
2012Month Builders Cover Domestic Garden Insulation Sandblast Spent Total
Rubble Material Waste Waste Waste Grit Catalyst
Jan-12 654 2226 5458 440 136 0 140 9054Feb-12 1265 2852 4520 527 519 0 190 9873Mar-12 859 5952 5185 669 735 0 90 13490Apr-12 367 3332 4946 560 596 0 60 9861
May-12 843 7654 5705 819 471 8 110 15610Jun-12 690 17728 5266 446 348 0 440 24918Jul-12 1119 11853 6078 440 402 0 470 20362
Aug-12 1001 10666 6642 500 477 0 290 19576Sep-12 1604 8862 7015 551 443 0 0 18475Oct-12 1130 7146 4702 723 351 0 710 14762Nov-12 1866 10167 4997 488 498 0 290 18306Dec-12 940 3090 2896 391 307 264 330 8218
12338 91528 63410 6554 5283 272 3120
CHARLIE 1 - FEASIBILITY ENGINEERING
June 2015 Report No. 1418079-13574-1
APPENDIX K Drawings
www.golder.com
025
mm
1 31
PRETORIA1204 PARK STREETHATFIELD, 0028SOUTH AFRICA[+27] (0) 12 364 4000A 2015-05-08 FIRST DRAFT FOR REVIEW GDGD SAPB SAPB 800395
B 2015-05-28 FINAL DRAFT GDGD SAPB SAPB 800395
1418079CONTROL0000
DRAWING
0000B
SASOL CHARLIE 1 LANDFILLSTORMWATER AND LEACHATE MANAGEMENTFEASIBILITY ENGINEERING PACKAGE
SASOL SYNFUELS
COVER PAGE
REV. DESCRIPTIONYYYY-MM-DDof
PREPARED REVIEWED APPROVEDDESIGNED
CONSULTANT TITLE
PROJECT NO. REV.
PROJECTCLIENT
Path
: \\p
re1-
v-fs
1\ga
adat
a\Pr
ojec
ts\1
4180
79 -
Saso
l Cha
rlie1
CEP
Secu
nda\
5.2
Dra
win
gs -
imag
es\D
RAW
ING
S\R
evB_
2015
0527
\ |
File
Nam
e: 1
4180
79-0
00-0
00-D
Cov
er P
age_
2015
0528
.dw
g
IF T
HIS
MEA
SUR
EMEN
T D
OES
NO
T M
ATC
H W
HAT
IS S
HO
WN
, TH
E SH
EET
SIZE
HAS
BEE
N M
OD
IFIE
D F
RO
M: I
SO A
1
SASOL CHARLIE 1 LANDFILLSTORMWATER AND LEACHATE MANAGEMENT
FEASIBILITY ENGINEERING PACKAGE
NOTES
1. THESE NOTES APPLY TO ALL PROJECT DRAWINGS IN THE SET UNLESS NOTEDOTHERWISE AND SHALL BE READ IN CONJUNCTION WITH THE SPECIFICATION.
2. ALL CO-ORDINATES ARE IN METERS TO LO 29 WITH SOUTH AFRICAN SURVEY GRIDWGS84 DATUM 28 TO 30 DEG EAST.
3. ALL DIMENSIONS ARE IN METERS UNLESS NOTED OTHERWISE.4. DIMENSIONS AND LOCATION OF EXISTING STRUCTURES SHALL BE CONFIRMED ON SITE
BY THE CONTRACTOR PRIOR TO COMMENCEMENT OF WORKS.5. LOCATION AND DEPTH OF ALL SERVICES TO BE VERIFIED BY THE CONTRACTOR PRIOR
TO COMMENCEMENT OF WORKS.6. DIMENSIONS SHALL NOT BE SCALED OFF DRAWINGS.
DRAFTNOT FOR CONSTRUCTION
1 2
3
4
5
6
7
8
-2 935 200 X -2 935 200 X
17 2
00 Y
17 2
00 Y
-2 935 600 X -2 935 600 X
16 8
00 Y
16 8
00 Y
16 4
00 Y
16 4
00 Y
17 6
00 Y
17 6
00 Y
SETOUT TABLE
POINT No.
1
2
3
4
5
6
7
8
EASTING (m)
16495.90
17177.30
17051.55
16764.49
16814.65
16708.29
16674.34
16384.44
NORTHING (m)
-2935178.36
-2935183.49
-2935527.78
-2935740.11
-2935787.46
-2935866.83
-2935837.13
-2935643.00
www.golder.com
025
mm
2 31
PRETORIA1204 PARK STREETHATFIELD, 0028SOUTH AFRICA[+27] (0) 12 364 4000A 2015-05-08 FIRST DRAFT FOR REVIEW GDGD SAPB SAPB 800395
B 2015-05-28 FINAL DRAFT GDGD SAPB SAPB 800395
1418079CONTROL0100
DRAWING
0101B
SASOL CHARLIE 1 LANDFILLSTORMWATER AND LEACHATE MANAGEMENTFEASIBILITY ENGINEERING PACKAGE
SASOL SYNFUELS
GENERAL ARRANGEMENT
REV. DESCRIPTIONYYYY-MM-DDof
PREPARED REVIEWED APPROVEDDESIGNED
CONSULTANT TITLE
PROJECT NO. REV.
PROJECTCLIENT
Path
: \\p
re1-
v-fs
1\ga
adat
a\Pr
ojec
ts\1
4180
79 -
Saso
l Cha
rlie1
CEP
Secu
nda\
5.2
Dra
win
gs -
imag
es\D
RAW
ING
S\R
evB_
2015
0527
\ |
File
Nam
e: 1
4180
79-0
101-
D-E
xist
ing
Layo
ut_2
0150
528.
dwg
IF T
HIS
MEA
SUR
EMEN
T D
OES
NO
T M
ATC
H W
HAT
IS S
HO
WN
, TH
E SH
EET
SIZE
HAS
BEE
N M
OD
IFIE
D F
RO
M: I
SO A
1
1. THESE NOTES APPLY TO ALL PROJECT DRAWINGS IN THE SET UNLESS NOTEDOTHERWISE AND SHALL BE READ IN CONJUNCTION WITH THE SPECIFICATION.
2. ALL CO-ORDINATES ARE IN METERS TO LO 29 WITH SOUTH AFRICAN SURVEY GRIDWGS84 DATUM 28 TO 30 DEG EAST.
3. ALL DIMENSIONS ARE IN METERS UNLESS NOTED OTHERWISE.4. DIMENSIONS AND LOCATION OF EXISTING STRUCTURES SHALL BE CONFIRMED ON SITE
BY THE CONTRACTOR PRIOR TO COMMENCEMENT OF WORKS.5. LOCATION AND DEPTH OF ALL SERVICES TO BE VERIFIED BY THE CONTRACTOR PRIOR
TO COMMENCEMENT OF WORKS.6. DIMENSIONS SHALL NOT BE SCALED OFF DRAWINGS.
NOTES
PERMIT AREA 35.3 Ha
LANDFILL AREA 30.2 Ha
1:2,000
2000
METRES
100
DRAFT30
CHARLIE 1 GATE
SITE ENTRANCE
GATEHOUSEABLUTION FACILITIES
VEHICLE MAINTENANCE SHED
RECYCLING AREA
EXISTING FENCE
+2 935 200 X +2 935 200 X
-16
400
Y
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
Y0605
SCALE 1:10 CAPPING DETAIL
Z0601
SCALE 1:50 STORMWATER DIVERSION STRUCTURE DETAIL
ofwww.golder.com
Rev. DESCRIPTIONYYYY-MM-DD DESIGN REVIEW APPROVEDPREPARED
CONSULTANT TITLE
PROJECT No. Rev.
PROJECTCLIENT
31 31
PRETORIA1204 PARK STREETHATFIELD, 0028SOUTH AFRICA[+27] (0) 12 364 4000A 2015-05-08 FIRST DRAFT FOR REVIEW GD GD SAPB SAPB 800395
B 2015-05-28 FINAL DRAFT GD GD SAPB SAPB 800395
1418079CONTROL0600
DRAWING
0605BPR ENG No.
SASOL CHARLIE 1 LANDFILLSTORMWATER AND LEACHATE MANAGEMENTFEASIBILITY ENGINEERING PACKAGE
SASOL SYNFUELS
PROPOSED FINAL LANDFORM AND DETAILS
FINAL LANDFORMSCALE 1:2000
ABLUTIONFACILITIES
MAINTENANCE SHED
LEACHATE POND
STO
RM
WAT
ER P
ON
D
SITE ENTRANCE
PERMIT AREA
PERMIT AREA
1625
1620
1:4
1:4
1:4
1:4
1:4
AIRSPACE SUMMARY:PHASE 1: 269 412m³PHASE 2: 199 848m³PHASE 3: 107 270m³PHASE 4: 202 663m³PHASE 5: 327 980m³PHASE 6: 367 148m³PHASE 7: 296 347m³PHASE 8: 433 420m³PHASE 9: 315 075m³
TOTAL AIRSPACE USED: 2 519 163m³
FLOWFLOW
FLOW
PERMANENT BRICK WALLS,1.0m HIGH
PERMANENT BRICK WALLS,1.0m HIGH
TEMPORARY BRICKWALLS, 1.0m HIGH
CONCRETE / GEOCELLSSTORMWATER V-DRAIN
STORMWATER EARTH V-DRAINTO DAYLIGHT TO ENVIRONMENT
CONCRETE / GEOCELLSSTORMWATER V-DRAIN
DRAIN FLOOR TO BE FLAT
EARTH
CONCRETE
150mm TOP SOIL, GRASSED
3 x 150mm COMPACTED CLAYEY SOIL
DN75 DRAINEXPIPE FOR GAS
DRAINAGE
SURFACE OF WASTE TO BESHAPED AND LEVELLING LAYER OFSOIL APPLIED WHERE NECESSARY
GEOCOMPOSITE DRAIN (MACDRAINW1051 OR POZIDRAIN)
WASTE
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
ofwww.golder.com
Rev. DESCRIPTIONYYYY-MM-DD DESIGN REVIEW APPROVEDPREPARED
CONSULTANT TITLE
PROJECT No. Rev.
PROJECTCLIENT
30 31
PRETORIA1204 PARK STREETHATFIELD, 0028SOUTH AFRICA[+27] (0) 12 364 4000A 2015-05-08 FIRST DRAFT FOR REVIEW GD GD SAPB SAPB 800395
B 2015-05-28 FINAL DRAFT GD GD SAPB SAPB 800395
1418079CONTROL0600
DRAWING
0604BPR ENG No.
SASOL CHARLIE 1 LANDFILLSTORMWATER AND LEACHATE MANAGEMENTFEASIBILITY ENGINEERING PACKAGE
SASOL SYNFUELS
DEVELOPMENT PLAN PHASES 6 TO 9
PHASE 6AIRSPACE USED = 367 148m³
SCALE 1:3000
LEACHATE POND
STO
RM
WAT
ER P
ON
D
NOTES: APPLY FINAL CAPPING TO AREA B. CLOSE STORMWATER DRAIN OUTLET AT
SOUTHERN CORNER TO ALLOWCONTAMINATED WATER TO FLOW TO POND.
LANDFILL OPERATIONS TO CONTINUE INAREA A.
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
SITE ENTRANCE
PHASE 7AIRSPACE USED = 296 347m³
SCALE 1:3000
LEACHATE POND
STO
RM
WAT
ER P
ON
D
NOTES: APPLY FINAL CAPPING TO AREA A. OPEN STORMWATER DRAIN ALONG SOUTHERN
& WESTERN SIDES TO DISCHARGE CLEANWATER TO ENVIRONMENT.
CLOSE STORMWATER DRAIN OUTLET ALONGNORTHERN BOUNDARY TO ALLOWCONTAMINATED WATER TO FLOW TO POND.
LANDFILL OPERATIONS TO CONTINUE IN AREA 1.
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
SITE ENTRANCE
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
PHASE 8AIRSPACE USED = 433 420m³
SCALE 1:3000
LEACHATE POND
STO
RM
WAT
ER P
ON
D
NOTES: APPLY FINAL CAPPING TO AREA 1. OPEN STORMWATER DRAIN ALONG NORTHERN
BOUNDARY TO DISCHARGE CLEAN WATER TOENVIRONMENT.
LANDFILL OPERATIONS TO CONTINUE IN AREA 2.
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
SITE ENTRANCE
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
PHASE 9AIRSPACE USED = 315 075m³
SCALE 1:3000
LEACHATE POND
STO
RM
WAT
ER P
ON
D
NOTES: APPLY FINAL CAPPING TO AREA 2. OPEN STORMWATER DRAIN ALONG NORTHERN
BOUNDARY TO DISCHARGE CLEAN WATER TOENVIRONMENT.
LANDFILL OPERATIONS TO CONTINUE IN AREA 3. ONCE OPERATIONS IN AREA 3 IS COMPLETE,
FINAL CAPPING MUST BE APPLIED.
SITE ENTRANCE
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
1615
1:4
1:4
1:4
1610
1620
1:4
1616
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
1625
1:4
1625
1:4
1:4
1:4
1610
1620
1:4
1616
1625
1:4
1625
1:4
1:4
1:4
1610
1620
1:4
1616
1625
1:4
1620
1625
1:4
1:4
1:4
1620
1:4
1616
1625
1:4
1620
1:4
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
DIVERT CLEAN RUNOFF
DIVERT CLEAN RUNOFF
DIVERT CLEAN RUNOFF
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
ofwww.golder.com
Rev. DESCRIPTIONYYYY-MM-DD DESIGN REVIEW APPROVEDPREPARED
CONSULTANT TITLE
PROJECT No. Rev.
PROJECTCLIENT
29 31
PRETORIA1204 PARK STREETHATFIELD, 0028SOUTH AFRICA[+27] (0) 12 364 4000A 2015-05-08 FIRST DRAFT FOR REVIEW GD GD SAPB SAPB 800395
B 2015-05-28 FINAL DRAFT GD GD SAPB SAPB 800395
1418079CONTROL0600
DRAWING
0603BPR ENG No.
SASOL CHARLIE 1 LANDFILLSTORMWATER AND LEACHATE MANAGEMENTFEASIBILITY ENGINEERING PACKAGE
SASOL SYNFUELS
DEVELOPMENT PLAN PHASES 3 TO 5
PHASE 3BAIRSPACE USED = 107 270m³
SCALE 1:3000
ABLUTIONFACILITIES
MAINTENANCE SHED
LEACHATE POND
STO
RM
WAT
ER P
ON
D
2% FALL
2% FALL
1615
NOTES: APPLY TEMPORARY SOIL COVER TO AREA C. OPEN STORMWATER DRAIN ALONG WESTERN
SIDE TO DISCHARGE CLEAN WATER TOENVIRONMENT.
LANDFILL OPERATIONS TO CONTINUE INAREA 3.CLEAN STORMWATER
TO DISCHARGE TOENVIRONMENT
1615
PHASE 3ASCALE 1:3000
ABLUTIONFACILITIES
LEACHATE POND
STO
RM
WAT
ER P
ON
D
2% FALL
2% FALL
1615
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
1615
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
MAINTENANCE SHED
NOTES: RECYCLING AREA TO BE RELOCATED. AREA C TO BE RESHAPED TO BE FREE DRAINING
AND SLOPING TOWARDS STORMWATER DRAIN. APPLY TEMPORARY SOIL COVER TO AREA 2. OPEN STORMWATER DRAIN ALONG NORTHERN
BOUNDARY TO DISCHARGE CLEAN WATER TOENVIRONMENT.
LANDFILL OPERATIONS TO CONTINUE IN AREA 3.
SITE ENTRANCE
2% FALL
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
SITE ENTRANCE
2% FALL
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
PHASE 4AIRSPACE USED = 202 663m³
SCALE 1:3000
LEACHATE POND
STO
RM
WAT
ER P
ON
D
2% FALL
2% FALL
1615
NOTES: APPLY TEMPORARY SOIL COVER TO AREA 3. CLOSE STORMWATER DRAIN OUTLET ALONG
WESTERN SIDE TO ALLOW CONTAMINATEDWATER TO FLOW TO POND.
LANDFILL OPERATIONS TO CONTINUE INAREA C.CLEAN STORMWATER
TO DISCHARGE TOENVIRONMENT
1615
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
SITE ENTRANCE
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
1620
PHASE 5AIRSPACE USED = 327 980m³
SCALE 1:3000
LEACHATE POND
STO
RM
WAT
ER P
ON
D
NOTES: APPLY FINAL CAPPING TO AREA C. CLOSE STORMWATER DRAIN OUTLET AT
SOUTH WESTERN CORNER TO ALLOWCONTAMINATED WATER TO FLOW TO POND.
LANDFILL OPERATIONS TO CONTINUE INAREA B.CLEAN STORMWATER
TO DISCHARGE TOENVIRONMENT
1615
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
SITE ENTRANCE
1610
1610
1610
1610
2% FALL 2% FALL
2% FALL
1610
1:4
1:4
1:4
1:4
1:4
1:4
1:4
1:4
1:4
1:41:4 1:4
1:4 1:4
1:4
1605
1:4
1616
1610 1610
1620
1:4
1616
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
DIVERT CLEAN RUNOFF
+2 935 200 X +2 935 200 X
-16
400
Y
+2 935 400 X +2 935 400 X
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
+2 935 200 X +2 935 200 X
-16
400
Y
+2 935 400 X +2 935 400 X
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
+2 935 200 X +2 935 200 X
-16
400
Y
+2 935 400 X +2 935 400 X
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
+2 935 200 X +2 935 200 X
-16
400
Y
+2 935 400 X +2 935 400 X
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
ofwww.golder.com
Rev. DESCRIPTIONYYYY-MM-DD DESIGN REVIEW APPROVEDPREPARED
CONSULTANT TITLE
PROJECT No. Rev.
PROJECTCLIENT
28 31
PRETORIA1204 PARK STREETHATFIELD, 0028SOUTH AFRICA[+27] (0) 12 364 4000A 2015-05-08 FIRST DRAFT FOR REVIEW GD GD SAPB SAPB 800395
B 2015-05-28 FINAL DRAFT GD GD SAPB SAPB 800395
1418079CONTROL0600
DRAWING
0602BPR ENG No.
SASOL CHARLIE 1 LANDFILLSTORMWATER AND LEACHATE MANAGEMENTFEASIBILITY ENGINEERING PACKAGE
SASOL SYNFUELS
DEVELOPMENT PLAN PHASE 1 AND 2
PHASE 1ASCALE 1:3000
NOTES: AREA A TO BE RESHAPED TO BE FREE
DRAINING AND SLOPING TOWARDSSTORMWATER DRAIN.
LANDFILL OPERATIONS TO CONTINUE INAREA 1.
ABLUTIONFACILITIES
MAINTENANCE SHEDSITE ENTRANCE
LEACHATE POND
STO
RM
WAT
ER P
ON
D
RECYCLINGAREA
2% FALL
2% FALL
1615
PHASE 1BAIRSPACE USED = 269 412m³
SCALE 1:3000
ABLUTIONFACILITIES
MAINTENANCE SHEDSITE ENTRANCE
LEACHATE POND
STO
RM
WAT
ER P
ON
D
RECYCLINGAREA
2% FALL
2% FALL
1615
NOTES: APPLY TEMPORARY SOIL COVER TO AREA A. OPEN STORMWATER DRAIN AT SOUTHERN
CORNER TO DISCHARGE CLEAN WATER TOENVIRONMENT.
LANDFILL OPERATIONS TO CONTINUE INAREA 1.CLEAN STORMWATER
TO DISCHARGE TOENVIRONMENT
1615
1610
PHASE 2ASCALE 1:3000
ABLUTIONFACILITIES
MAINTENANCE SHEDSITE ENTRANCE
LEACHATE POND
STO
RM
WAT
ER P
ON
D
RECYCLINGAREA
2% FALL
2% FALL
1615
NOTES: AREA B TO BE RESHAPED TO BE FREE DRAINING
AND SLOPING TOWARDS STORMWATER DRAIN. APPLY TEMPORARY SOIL COVER TO AREA 1. OPEN STORMWATER DRAIN ALONG NORTHERN
BOUNDARY TO DISCHARGE CLEAN WATER TOENVIRONMENT.
LANDFILL OPERATIONS TO CONTINUE IN AREA 2.CLEAN STORMWATER
TO DISCHARGE TOENVIRONMENT
1615
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
2% FALL
PHASE 2BAIRSPACE USED = 199 848m³
SCALE 1:3000
ABLUTIONFACILITIES
MAINTENANCE SHEDSITE ENTRANCE
LEACHATE POND
STO
RM
WAT
ER P
ON
D
RECYCLINGAREA
2% FALL
2% FALL
1615
NOTES: APPLY TEMPORARY SOIL COVER TO AREA B. OPEN STORMWATER DRAIN AT SOUTH WESTERN
CORNER TO DISCHARGE CLEAN WATER TOENVIRONMENT.
LANDFILL OPERATIONS TO CONTINUE IN AREA 2.
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
1615
CLEAN STORMWATERTO DISCHARGE TOENVIRONMENT
CLEAN STORMWATERTO DISCHARGE TO
ENVIRONMENT
2% FALL
1:4
1:4 1:4
1:4
1:4
1:4
1:4
1:4 1:4
1610
1610
XX
XX
XX
XX
XX
-2 935 200 X -2 935 200 X
17 2
00 Y
17 2
00 Y
-2 935 600 X -2 935 600 X
16 8
00 Y
16 8
00 Y
16 4
00 Y
16 4
00 Y
17 6
00 Y
17 6
00 Y
SETOUT TABLE
POINT No.
1
2
3
4
5
6
7
8
EASTING (m)
16729.20
16950.95
16448.43
16724.10
16889.72
17055.46
16408.57
16670.43
NORTHING (m)
-2935185.34
-2935187.65
-2935414.90
-2935465.03
-2935495.16
-2935525.33
-2935632.18
-2935809.33
www.golder.com
025
mm
27 31
PRETORIA1204 PARK STREETHATFIELD, 0028SOUTH AFRICA[+27] (0) 12 364 4000A 2015-05-08 FIRST DRAFT FOR REVIEW GDGD SAPB SAPB 800395
B 2015-05-28 FINAL DRAFT GDGD SAPB SAPB 800395
1418079CONTROL0600
DRAWING
0601B
SASOL CHARLIE 1 LANDFILLSTORMWATER AND LEACHATE MANAGEMENTFEASIBILITY ENGINEERING PACKAGE
SASOL SYNFUELS
DEVELOPMENT PLAN
REV. DESCRIPTIONYYYY-MM-DDof
PREPARED REVIEWED APPROVEDDESIGNED
CONSULTANT TITLE
PROJECT NO. REV.
PROJECTCLIENT
Path
: \\p
re1-
v-fs
1\ga
adat
a\Pr
ojec
ts\1
4180
79 -
Saso
l Cha
rlie1
CEP
Secu
nda\
5.2
Dra
win
gs -
imag
es\D
RAW
ING
S\R
evB_
2015
0527
\ |
File
Nam
e: 1
4180
79-0
601-
D-D
evel
opm
ent P
lan
Layo
ut_2
0150
527.
dwg
IF T
HIS
MEA
SUR
EMEN
T D
OES
NO
T M
ATC
H W
HAT
IS S
HO
WN
, TH
E SH
EET
SIZE
HAS
BEE
N M
OD
IFIE
D F
RO
M: I
SO A
1
AREA "1"
AREA "2"AREA "3"
AREA "A"
AREA "B"
AREA "C"
1. THESE NOTES APPLY TO ALL PROJECT DRAWINGS IN THE SET UNLESS NOTEDOTHERWISE AND SHALL BE READ IN CONJUNCTION WITH THE SPECIFICATION.
2. ALL CO-ORDINATES ARE IN METERS TO LO 29 WITH SOUTH AFRICAN SURVEY GRIDWGS84 DATUM 28 TO 30 DEG EAST.
3. ALL DIMENSIONS ARE IN METERS UNLESS NOTED OTHERWISE.4. DIMENSIONS AND LOCATION OF EXISTING STRUCTURES SHALL BE CONFIRMED ON SITE
BY THE CONTRACTOR PRIOR TO COMMENCEMENT OF WORKS.5. LOCATION AND DEPTH OF ALL SERVICES TO BE VERIFIED BY THE CONTRACTOR PRIOR
TO COMMENCEMENT OF WORKS.6. DIMENSIONS SHALL NOT BE SCALED OFF DRAWINGS.
NOTES
SITE ENTRANCE
1:2,000
2000
METRES
100
DRAFTISSUED FOR INFORMATION
Z0605
STORMWATER DIVERSION STRUCTURE
STORMWATER DIVERSION STRUCTURESTORMWATER DIVERSION STRUCTURES
STORMWATER DIVERSION STRUCTURES