106
32 st Project Steering Committee Meeting ADB Funded Integrated Road Investment Program (iRoad 1) 29 October 2019 1

32st Project Steering Committee Meeting ADB Funded

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 32st Project Steering Committee Meeting ADB Funded

32st Project Steering Committee Meeting ADB Funded

Integrated Road Investment Program (iRoad 1)29 October 2019

1

Page 2: 32st Project Steering Committee Meeting ADB Funded

iRoad 1 Map

Page 3: 32st Project Steering Committee Meeting ADB Funded

Overall Status of Rural Road PackagesProvince No. of

packagesNo. of

packages completed

Km No. of km completed

Physical Progress as at

15 October 2019

Remarks

Planned (%)

Actual (%)

Southern 09 07 582 575 100.0 98.5 1 contract terminated. Court order for encashment.

Central 09 04 595 539 99.5 94.5 Court order for encashment for one contract & termination

Sabaragamuwa 06 01 472 345 99.8 78.8 3 contracts, court orders for encashment & termination

North Central 07 07 508 508 100.0 100.0 Completed. Statement at completion in progress

North Western 08 01 705 480 97 60 3 contract terminated... Court orders for encashment.. Retendering works completed and ready for awarding.

Kalutara 03 - 277 153 97.5 61 2 contracts terminated. Court orders for encashment..

Total 42 19 3,139 2,575 98.5 82.2

Page 4: 32st Project Steering Committee Meeting ADB Funded

4

Non-performing & Terminated Contracts

Cabinet decision received to complete the balance works of the terminated contracts through the local funds. Note to cabinet was sent to the cabinet for approval since the treasury finds difficulty in funding locally

Contractor Packages Status

K.D. Ebert G1 Terminated on 12/02/2019. challenged and obtained stay order for encashment of guarantees.

K.D. Ebert R1, R2, KE1 ADB concurrence for termination received. Contractor obtained stay order for termination and encashment of guarantees.

Ranken Railway KU3, KU5 Terminated on 12/02/2019. Encashment demanded from the BOC on 12/02/2019. retendering works completed and ready for awarding.

VVK KU4, PU2, PU3 PU2 – Terminated. Court order for encashment.KU4, PU3 - Poor progress. Contractual action is being taken for termination.

Olympus – Rani JV KL2, KL3 Terminated. Court order prevails for encashment.

Page 5: 32st Project Steering Committee Meeting ADB Funded

Expenditure – 2019 – iRoad 1 Program

No Description LKR (Mn)

1 Budget Allocation 7,687

2 Expenditure as at Oct 2019 7,687

3 % Financial achievement 100%

Page 6: 32st Project Steering Committee Meeting ADB Funded

Southern Province

6

Package No Contractor No.of RoadsRoad Length

(Km)Status

G1 K.D.Ebert & Sons Holdings (Pvt.) Ltd 15 64.6Terminated –76%

G2 K.D.A. Weerasinghe & Co (Pvt) Ltd 22 66.0 Completed

G3 K.D.A. Weerasinghe & Co (Pvt) Ltd 29 70.8 Completed

M1 CML-MTD Construction Ltd 22 97.5 Completed

M2 K.D.Ebert & Sons Holdings (Pvt.) Ltd 19 69.5 Completed

M3 K.D.Ebert & Sons Holdings (Pvt.) Ltd 25 53.4 Completed

H1 K.D.A. Weerasinghe & Co (Pvt) Ltd 19 67.1 Completed

H2 CML-MTD Construction Ltd 18 58.0 Completed

H3 R.R Construction. (Pvt.) Ltd 14 41.9 Completed

Total 183 588.8

Page 7: 32st Project Steering Committee Meeting ADB Funded

North Central Province

7

Pkg No. Contractor No. Of Roads/Length (km) Status

AP1 MAGA 17/85.09 Completed

AP2 MAGA 12/76.85 Completed

AP3 MAGA 12/82.66 Completed

AP4 MAGA 19/90.20 Completed

PO1 MAGA 18/50.76 Completed

PO2 MAGA 25/73.36 Completed

PO3 TISSA-AMSK JV 11/49.55 Completed

Page 8: 32st Project Steering Committee Meeting ADB Funded

8

Kalutara District

Page 9: 32st Project Steering Committee Meeting ADB Funded

Overall Physical Progress Summary –iROAD-Kalutara District /(up to 15th October2019)

9

Package No. ContractorNo. of Roads

Total Length / (km)

Physical Progress; Cumulative Status up to 15th October 2019 (%)

StatusTarget (Revised) Actual

KL 01 Maga 42 87.50 99.5 99.1%

Scheduled

completion

31st October

2019

KL 02 OCPL Jv RCPL 19 88.40 100 35.15% Terminated

KL 03 OCPL Jv RCPL 22 93.35 100 51.83% Terminated

Total / Avg. 83 269.25 100% 61.2%

Page 10: 32st Project Steering Committee Meeting ADB Funded

Photographs – KL 1

10

Asphalt concrete laying works at RD 59 (From Duwa Temple Road

Vilegoda Via Aluth Para)

Finishing works -Top soiling at RD 68 (Wilpatha Puhabugoda akkara

18 via Puhabugoda Road)

Page 11: 32st Project Steering Committee Meeting ADB Funded

Cost to Completion

11

• SAC is under preparation for KL1

• Valuation at Termination together with the employers claim being prepared.

Page 12: 32st Project Steering Committee Meeting ADB Funded

Road Management Contracts (RMC) Of National Roads

12

Page 13: 32st Project Steering Committee Meeting ADB Funded

Road Management Contracts MAPContract

No

Route No Road Length (km) Status

RMC SP1 B 248, B 454, B 303, B

139, B 129, B 429 & B156

Karapitiya – Labuduwa – Thawalama Road 52.0 Construction In

Progress

RMC 1 A 01 Colombo – Kandy Road from Ambepussa to

Kadugannawa

40.0 Expect to award in

June 2020RMC 3 A11 Maradankadawala - Thirikondiamadu Road from

Maradankadawala to Habarana 25.0Construction In

ProgressRMC 4 A18 Pelmadulla - Padalangala Road 66.0 Expect to award in

Dec 2019RMC 5 B 133,

B 212 & B 213

Thalawa - Kekirawa road, Kekirawa - Ganewalpola Road

& Ganewalpola - Dachchihalmillewa Road 90.0Expect to award in

May 2020RMC 6 A 03 Peliyagoda Puttalam Road section from Kochchikade

Bridge to Puttlam

88.0 Expect to award in

July 2020

RMC 7 A 02 Galle Road from Nallurwa Bridge to Benthota Bridge 21.0 Expect to award in

Aug 2020RMC 8 B 065 Bowaththa - Pandiwela Road 17.7 Expect to award in

Sep 2020B 244 Kuliyapitiya - Pandiwela Road

RMC 9 B364 Peradeniya – Deltota – Rikillagaskada Road 53.0 Expect to award in

Sep 2020Total 404.7

Page 14: 32st Project Steering Committee Meeting ADB Funded

Road Management Contracts MAP

Page 15: 32st Project Steering Committee Meeting ADB Funded

Project Profile (Awarded Contracts)

Funding AgencyAsian Development Bank

Contract No. RMC-03Maradankadawala - Habarana

RMC-SP1Karapitiya – Thawalama Road

Total Cost (SLR) 3,315,189,385.00 6,108,200,364.84

Cumulative Expenditure (SLR) 203,888,552.20 284,186,887.41

Cumulative Physical Progress 11.85% 1.04%

Total length 25.0 KM 51.7 KM

Location Anuradhapura District Galle District

Date of Commencement 16 April 2019 25 July 2019

Duration 6 years 5.5 years

Contractor Consulting Engineers & Contractors

Pvt Ltd (CEC)

K D A Weerasinghe & Company Pvt Ltd in JV with

Yunnan Construction (KDAW-YCIH JV)

Consultant Oriental Consultants Global Co Ltd (Japan) JV with Consulting Engineer’s and Architects

Associated Pvt Ltd

Page 16: 32st Project Steering Committee Meeting ADB Funded

Overall Physical Progress

Project Name Last Month %Cumulative

Reporting Month %Cumulative

Next Month Cumulative%

Target Actual Target Actual Target

RMC-03Maradankadawal

a - Habarana8.08% 8.50% 12.13% 11.85% 16.42%

SP 1Karapitiya –

Thawalama RoadContract’s Design and preliminary works in progress..

Page 17: 32st Project Steering Committee Meeting ADB Funded

Physical Progress-RMC 03

Ap

ril-

19

May

-19

Jun

e-1

9 July

-19

Au

gust

-1

9

Sep

tem

ber

-1

9 Oct

ob

er-1

9

No

vem

ber

-1

9

Dec

emb

er-1

9

Jan

uar

y-2

0

Feb

ruar

y-2

0 Mar

ch-2

0

No

vem

ber

-20

Oct

ob

er-2

0

Sep

tem

ber

-20

Au

gust

-20

Ap

ril-

20

May

-20

Jun

e-2

0

July

20

Dec

emb

er-2

0

Jan

uar

y-2

1

Feb

ruar

y-2

1 Mar

ch-2

1

Ap

ril-

21

Programme

Page 18: 32st Project Steering Committee Meeting ADB Funded

Physical Progress-SP 01

July

-19

Au

gust

-19

Sep

tem

ber

-19

Oct

ob

er-

19

No

vem

ber

-1

9 Dec

emb

er-1

9

Jan

uar

y-2

0

Feb

ruar

y-2

0

Mar

ch-2

0

Ap

ril-

20

May

-20

Jun

e-2

0

Feb

ruar

y-2

1

Jan

uar

y-2

1

Dec

emb

er-2

0

No

vem

ber

-2

0

July

-20

Au

gust

-20

Sep

tem

ber

-2

0 Oct

ob

er-2

0

Mar

ch-2

1

Ap

ril-

21

May

-21

Jun

e-2

1

July

-21

Page 19: 32st Project Steering Committee Meeting ADB Funded

Asphalt works at Ch 0+350km

PROJECT PHOTOS – RMC 03 CONTRACTMaradankadawala- Habarana Road

Traffic Management and Safety Measures at at Culvert No. 4/1

Page 20: 32st Project Steering Committee Meeting ADB Funded

GRC Meeting at Akmeemana Divisional Secretary’s Office 28th August 2019Routine Maintenance on Udugama Bus Stand to Hiniduma Road

PROJECT PHOTOS – SP 01 CONTRACT521.7 kms of B Class Roads in Galle District

Page 21: 32st Project Steering Committee Meeting ADB Funded

21

Progress of Civil Works Contracts up to

30th September 2019

ADB Funded Integrated Road Investment Program (I Road)

Rehabilitation/Improvement and Maintenance of Rural Roads in Central Province.

– PIC 03

Page 22: 32st Project Steering Committee Meeting ADB Funded

22

Project Location Map-Central Province

Page 23: 32st Project Steering Committee Meeting ADB Funded

Project Profile (Basic information)

Funding Agency : Asian Development Bank

Total cost : 15,666 Million

Total Length : 581.74 km

Location : Central Province (Kandy, Matale, Nuwaraeliya Districts)

Date of Commencement : 17th December 2015

Completion date : 16th December 2017

Consultant : Egis CEA Joint venture

23

Page 24: 32st Project Steering Committee Meeting ADB Funded

Overall Financial Progress of the Project

Last Month Reporting Month(September)

Allocation (Mn) Expenditure (Mn) Allocation (Mn) Expenditure (Mn)

15,093.49 13,729.33 15,384.71 13,745.52

24

Page 25: 32st Project Steering Committee Meeting ADB Funded

Overall Physical Progress of the Project

Last Month (%) Reporting Month (%)

Target Actual Target Actual

99.31 94.27 99.57 94.53

25

Page 26: 32st Project Steering Committee Meeting ADB Funded

Overall Physical Progress Summary –iROAD-Central Province /(up to 30 September 2019)

26

Package No. Contractor

Accepted Contract

Amount/ (Rs. Million)

No. of Roads

Actual Road Paving

Length / (km)

No. of Roads Civil Works in Progress

Total road pavement length

(asphalt+concrete) completed (km)

Physical Progress; Cumulative Status

up to 31 August 2019 (%)

Physical Progress; Cumulative Status up to 30 September 2019 (%)

Target (Revised) Actual

(A) Completed Contracts

NE 02 Sierra 1,242 14 36.21 0 36.21 100.00% 100.00% 100.00%

MA 02Edward and

Christie.1,249 14 55.55 0 55.55 100.00% 100.00% 100.00%

MA 03 CML-MTD 1,408 18 60.76 0 60.76 100.00% 100.00*(100.00)% 100.00%

KA 03Edward and

Christie.2,097 16 68.45 0 68.45 100.00% 100.00*(100.00)% 100.00%

(B) Performing Contracts

KA 01 Sierra 1,756 17 75.24 8 75.24 99.42% 100.00*(100.00)% 99.50%

KA 02 Sierra 1,924 17 72.48 5 72.48 100.00% 100.00*(100.00)% 100.00%

NE 01 Sierra 2,298 14 72.40 9 56.00 83.93% 100.00*(91.26)% 85.93%

NE 03 Sierra 2,070 15 65.53 9 64.50 98.61% 100.00*(100.00)% 98.89%

(C) Non-Performing Contracts

MA 01 KD Ebert 1,622 18 75.12 13 53.83 66.49% 100.00*(100.00)% 66.49%

Total / Avg. 15,666 143 581.74 44 543.02 94.27% 99.03% 94.53%

Page 27: 32st Project Steering Committee Meeting ADB Funded

27

Overall Physical Progress S curve –iROAD-Central Province /(up to 30 September 2019)

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19

Cum. Plan % 0.11% 0.54% 1.81% 4.69% 6.87% 10.67% 14.32% 18.99% 23.78% 29.29% 33.97% 38.68% 43.60% 49.46% 54.76% 60.59% 65.49% 71.84% 77.95% 83.74% 89.40% 94.31% 98.08% 99.57% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Rev. Plan 1 % 0.01% 0.29% 1.34% 3.29% 5.08% 8.15% 11.93% 16.57% 22.22% 27.38% 34.10% 39.32% 44.11% 49.37% 53.57% 58.51% 62.17% 65.83% 69.92% 73.61% 76.72% 79.45% 81.82% 83.10% 84.36% 85.90% 87.37% 89.08% 89.70% 91.49% 93.67% 96.04% 97.69% 97.97% 98.86% 99.64% 99.94% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Rev. Plan 2 % 0.01% 0.29% 1.34% 3.29% 5.08% 8.15% 11.93% 16.57% 22.22% 27.38% 34.10% 39.32% 44.11% 49.37% 53.57% 58.51% 62.17% 65.83% 69.92% 73.61% 76.72% 79.45% 81.82% 83.10% 84.36% 85.76% 87.08% 88.54% 89.11% 90.36% 91.57% 92.73% 93.63% 94.40% 95.19% 95.78% 96.06% 96.58% 96.84% 97.58% 98.01% 98.46% 98.76% 99.20% 99.31% 99.57% 99.78% 99.91% 100.00%

Cum. Actual % 0.03% 0.41% 1.41% 3.71% 5.73% 9.08% 13.07% 17.39% 22.62% 27.67% 33.82% 38.27% 43.00% 48.54% 53.20% 58.58% 61.84% 64.87% 69.04% 72.68% 75.74% 78.43% 80.51% 81.97% 83.41% 84.76% 86.10% 87.61% 88.28% 89.09% 89.69% 90.26% 90.76% 91.16% 91.60% 91.83% 92.11% 92.60% 92.72% 92.93% 93.02% 93.33% 93.65% 94.00% 94.27% 94.53%

Page 28: 32st Project Steering Committee Meeting ADB Funded

Package

No

Contractor

Accepted

Contract

Amount/ (Rs.

Million)

Total Certified Amount

(Mobilization Advance) /(Rs.

Million)

KA1 Sierra Construction (Pvt.) Ltd. 1,756 1,409.42 (55.01)

KA2 Sierra Construction (Pvt.) Ltd. 1,924 1,516.67 (65.38)

KA3 Edward and Christie. 2,097 1,711.09 (54.05)

MA1 KD Ebert and Sons Holdings(Pvt) Ltd. 1,622 937.16 (191.92)

MA2 Edward and Christie. 1,249 1,153.94 (0.00)

MA3 CML-MTD Construction limited 1,408 1,174.21 (9.04)

NE1 Sierra Construction (Pvt.) Ltd. 2,298 1,705.33 (138.66)

NE2 Sierra Construction (Pvt.) Ltd. 1,242 1,096.22 (0.00)

NE3 Sierra Construction (Pvt.) Ltd. 2,070 1,909.89 (0.00)

Total 15,666 12,613.93 (514.05)

Overall Financial Status –iROAD-Central Province /(up to 30 September 2019)

28

Page 29: 32st Project Steering Committee Meeting ADB Funded

Package wise Work Progress - Central Province

29

Page 30: 32st Project Steering Committee Meeting ADB Funded

Details of Contract Package – KA1

Contractor : Sierra Construction Ltd

Contract amount : Rs. 1,756 Millions

No of Roads : 17 Roads

Total Roads Length : 75.11 km

Start Date : 17th December 2015

Original Completion Date : 16th December 2017

EOT Granted : EOT 1-5 (Approved) EOT 6 (Under Evaluation)

Revised date of completion : 06 June 2018 30 September 2019

30

Page 31: 32st Project Steering Committee Meeting ADB Funded

31

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19

Cum. Plan % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 57.05% 62.45% 65.91% 70.52% 75.60% 80.65% 86.05% 91.77% 96.59% 99.81% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 1 % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 83.64% 86.90% 90.85% 93.15% 96.20% 98.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 2 % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 82.03% 85.45% 87.50% 90.35% 92.80% 95.40% 97.10% 98.70% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 3 % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 82.03% 84.10% 85.15% 86.70% 87.70% 89.00% 90.04% 93.30% 96.69% 98.89% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 4 % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 82.03% 84.10% 85.15% 86.70% 87.70% 89.00% 90.04% 90.56% 91.37% 92.02% 94.36% 95.10% 97.40% 99.10% 99.60% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 5 % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 82.03% 84.10% 85.15% 86.70% 87.70% 89.00% 90.04% 90.56% 91.37% 92.02% 94.36% 94.61% 95.00% 97.55% 97.72% 97.76% 97.77% 98.20% 98.36% 99.12% 99.62% 100.00%

Cum. Actual % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 82.03% 84.10% 85.15% 86.70% 87.70% 89.00% 90.04% 90.56% 91.37% 92.02% 94.36% 94.61% 95.00% 97.55% 97.72% 97.76% 97.80% 98.37% 98.78% 99.30% 99.42% 99.50%

14(17) Roads Handed Over

Page 32: 32st Project Steering Committee Meeting ADB Funded

PHOTOGRAPHS – KA 1

32

Shoulder construction work at Ch. 4+880 (RHS)Road No.02

Date : 15.09.2019

ABC Laying work at Ch. 4+520Road No.01

Date : 26.09.2019

Page 33: 32st Project Steering Committee Meeting ADB Funded

Details of Contract Package – KA2

Contractor : Sierra Construction Ltd

Contract amount : Rs. 1,924 Millions

No of Roads : 17 Roads

Total Roads Length : 72.35 km

Start Date : 17th December 2015

Original Completion Date : 16th December 2017

EOT Granted : EOT 1-6 (Approved) EOT 7 (Under Evaluation)

Revised date of completion : 19 Oct 2018 29 June 2019

33

Page 34: 32st Project Steering Committee Meeting ADB Funded

34

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19

Cum. Plan % 0.00% 0.08% 1.92% 4.10% 5.39% 9.89% 14.56% 19.69% 25.27% 32.82% 42.95% 49.74% 56.03% 63.76% 70.09% 74.36% 76.90% 81.07% 83.69% 87.15% 89.52% 92.58% 98.03% 99.78% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 1 % 0.00% 0.45% 2.22% 5.16% 7.25% 9.04% 16.09% 19.94% 26.12% 32.93% 40.00% 44.81% 49.82% 53.50% 57.50% 61.78% 65.01% 69.25% 74.21% 79.21% 84.22% 89.86% 95.31% 98.10% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 2 % 0.00% 0.45% 2.22% 5.16% 7.25% 9.04% 16.09% 19.94% 26.12% 32.93% 40.00% 44.81% 49.82% 53.50% 57.35% 61.60% 62.91% 68.42% 73.22% 78.13% 82.14% 86.64% 90.65% 92.01% 94.00% 95.00% 96.32% 96.34% 96.80% 97.20% 97.50% 97.90% 98.30% 98.70% 99.15% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Actual % 0.00% 0.45% 2.22% 5.16% 7.25% 9.04% 16.09% 19.94% 26.12% 32.93% 40.00% 44.81% 49.82% 53.50% 57.35% 61.60% 62.91% 68.42% 73.22% 78.13% 82.14% 86.64% 90.65% 92.01% 94.00% 95.00% 96.32% 96.34% 96.53% 97.10% 97.37% 98.55% 99.18% 99.20% 99.22% 99.25% 99.25% 99.35% 99.40% 99.45% 99.46% 99.47% 99.48% 99.51% 100.00% 100.00%

15(17) Roads Handed Over

Page 35: 32st Project Steering Committee Meeting ADB Funded

Details of Contract Package – KA3

Contractor : Edward & Christie Construction Ltd

Contract amount : Rs. 2,097 Millions

No of Roads : 16 Roads

Total Roads Length : 68.52 km

Start Date : 17th December 2015

Original Completion Date : 16th December 2017

EOT Granted : EOT 1 (Approved)

Revised date of completion : 31 March 2019

35

Page 36: 32st Project Steering Committee Meeting ADB Funded

36

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19

Cum. Initial Plan % 0.13% 0.39% 2.23% 5.08% 7.28% 10.87% 18.36% 26.21% 34.39% 42.69% 50.85% 58.66% 64.53% 69.75% 74.45% 79.18% 82.11% 85.11% 88.42% 91.53% 94.14% 96.56% 98.95% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 1 % 0.00% 0.05% 0.19% 1.02% 3.67% 8.18% 11.94% 16.34% 21.22% 27.16% 32.38% 36.20% 39.38% 44.33% 49.52% 54.88% 60.07% 66.43% 73.15% 80.10% 87.20% 93.01% 97.46% 99.47% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 2 % 0.00% 0.05% 0.19% 1.02% 3.67% 8.18% 11.83% 15.87% 19.68% 23.96% 30.15% 33.57% 38.21% 42.54% 47.17% 52.05% 54.74% 57.51% 60.62% 63.76% 67.21% 70.91% 74.50% 76.25% 79.00% 84.00% 88.00% 92.00% 94.00% 96.00% 98.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Actual % 0.00% 0.05% 0.19% 1.02% 3.67% 8.18% 11.83% 15.87% 19.68% 23.96% 30.15% 33.57% 38.21% 42.54% 47.17% 52.05% 54.74% 57.51% 60.62% 63.76% 67.21% 70.91% 74.50% 76.25% 78.90% 81.89% 83.98% 88.47% 90.54% 91.73% 93.40% 95.23% 96.20% 97.50% 98.10% 98.50% 98.70% 99.20% 99.30% 99.35% 99.50% 99.57% 99.80% 100.00% 100.00% 100.00%

16(16) Roads Handed Over

Page 37: 32st Project Steering Committee Meeting ADB Funded

Details of Contract Package – MA1

Contractor : K D Ebert and Sons Holding (pvt) Ltd

Contract amount : Rs. 1,622 Millions

No of Roads : 18 Roads

Total Roads Length : 75.12 km

Start Date : 17th December 2015

Original Completion Date : 16th December 2017

EOT Granted : EOT 1 (Approved)

Revised date of completion : 07 November 2018

37

Page 38: 32st Project Steering Committee Meeting ADB Funded

38

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19

Cum. Plan % 0.00% 0.12% 1.06% 6.15% 7.79% 11.53% 16.99% 23.27% 29.15% 34.24% 38.64% 45.01% 52.43% 59.08% 64.15% 70.87% 75.39% 80.73% 85.41% 90.58% 94.67% 97.38% 99.16% 99.98% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 1 % 0.00% 0.14% 1.17% 3.01% 5.10% 5.91% 10.97% 15.10% 19.18% 23.29% 28.57% 31.91% 35.33% 41.78% 48.56% 55.72% 61.24% 68.57% 75.92% 83.26% 89.79% 94.71% 98.02% 99.84% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 2 % 0.00% 0.14% 1.17% 3.01% 5.10% 5.91% 10.97% 15.10% 19.18% 23.29% 27.80% 31.07% 35.18% 38.72% 41.28% 48.73% 50.83% 53.48% 54.83% 54.93% 54.96% 54.99% 54.99% 54.99% 54.99% 56.30% 59.80% 63.80% 67.30% 72.30% 77.30% 82.30% 87.30% 92.30% 96.10% 99.30% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Actual % 0.00% 0.14% 1.17% 3.01% 5.10% 5.91% 10.97% 15.10% 19.18% 23.29% 27.80% 31.07% 35.18% 38.72% 41.28% 48.73% 50.83% 53.48% 54.83% 54.93% 54.96% 54.99% 54.99% 54.99% 54.99% 56.30% 58.72% 62.30% 62.88% 64.66% 65.77% 66.21% 66.21% 66.43% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49%

17.62 km Surfacing to be completed

Page 39: 32st Project Steering Committee Meeting ADB Funded

Details of Contract Package – MA2

Contractor : Edward & Christie Construction Ltd

Contract amount : Rs. 1,249 Millions

No of Roads : 17 Roads

Total Roads Length : 57.84 km

Start Date : 17th December 2015

Original Completion Date : 16th December 2017

EOT Granted : EOT 1 (Approved)

Revised date of completion : 21 May 2018

39

Page 40: 32st Project Steering Committee Meeting ADB Funded

40

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19

Cum. Plan % 0.00% 0.47% 1.84% 6.09% 7.24% 11.00% 12.70% 16.00% 19.15% 22.01% 26.00% 31.10% 35.85% 43.00% 50.20% 58.15% 66.80% 75.10% 81.94% 87.78% 93.58% 96.63% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Actual % 0.00% 0.19% 0.75% 1.57% 2.90% 6.50% 13.80% 19.94% 25.93% 32.45% 39.24% 43.40% 48.53% 51.10% 56.84% 63.05% 65.91% 70.06% 75.05% 80.47% 86.84% 90.74% 92.83% 95.90% 97.50% 98.20% 98.58% 99.50% 99.95% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

14(14) Roads Handed Over

Page 41: 32st Project Steering Committee Meeting ADB Funded

Details of Contract Package – MA3

Contractor : CML – MTD Construction Ltd

Contract amount : Rs. 1,408 Millions

No of Roads : 18 Roads

Total Roads Length : 59.92 km

Start Date : 17th December 2015

Original Completion Date : 16th December 2017

EOT Granted : EOT 1.6 (Approved) EOT 2 (Under Evaluation)

Revised date of completion : 31 August 2018 09 Feb 2019

41

Page 42: 32st Project Steering Committee Meeting ADB Funded

42

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19

Cum. Initial Plan % 0.00% 0.24% 1.28% 4.38% 5.88% 9.70% 14.21% 20.21% 27.66% 34.58% 38.76% 44.52% 47.82% 53.57% 58.68% 63.60% 66.68% 73.48% 83.93% 91.46% 95.28% 97.02% 99.66% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 1 % 0.00% 0.09% 0.93% 1.95% 2.79% 4.50% 9.52% 15.24% 23.18% 28.28% 32.17% 35.71% 39.37% 44.55% 51.11% 57.84% 62.03% 69.07% 76.08% 82.84% 89.60% 96.09% 99.73% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 2 % 0.00% 0.09% 0.93% 1.95% 2.79% 4.50% 9.52% 15.24% 23.18% 28.28% 32.17% 36.01% 40.27% 44.77% 51.00% 57.37% 62.15% 66.28% 72.10% 78.50% 82.40% 86.50% 90.10% 91.20% 92.80% 94.35% 95.50% 96.50% 97.40% 98.20% 99.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Actual % 0.00% 0.09% 0.93% 1.95% 2.79% 4.50% 9.52% 15.24% 23.18% 28.28% 32.17% 36.01% 40.27% 44.77% 51.00% 57.37% 62.15% 66.28% 72.10% 78.50% 82.40% 86.50% 90.10% 91.20% 92.80% 94.15% 96.68% 97.30% 98.20% 98.80% 99.30% 99.40% 99.50% 99.70% 99.70% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

18(18) Roads Handed Over

Page 43: 32st Project Steering Committee Meeting ADB Funded

Details of Contract Package – NE1

Contractor : Sierra Construction Ltd

Contract amount : Rs. 2,298 Millions

No of Roads : 14 Roads

Total Roads Length : 76.60 km

Start Date : 17th December 2015

Original Completion Date : 16th December 2017

EOT Granted : EOT 1&3 (Approved) EOT 4 (Under Evaluation)

Revised date of completion : 19 October 2018 20 December 2019

43

Page 44: 32st Project Steering Committee Meeting ADB Funded

44

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19

Cum. Plan % 0.00% 0.00% 0.10% 1.10% 4.20% 8.70% 12.20% 17.40% 19.70% 24.90% 30.10% 37.20% 42.00% 46.30% 50.10% 55.70% 60.50% 67.00% 75.30% 81.10% 86.20% 91.30% 95.20% 98.20% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 1 % 0.00% 0.00% 0.10% 1.30% 3.20% 5.30% 10.70% 14.00% 19.00% 23.00% 30.50% 36.40% 40.50% 45.20% 53.05% 57.10% 60.82% 67.75% 75.02% 81.43% 87.06% 92.95% 97.11% 99.38% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 2 % 0.00% 0.00% 0.10% 1.30% 3.20% 5.30% 10.70% 14.00% 19.00% 23.00% 30.50% 36.40% 40.50% 45.20% 51.34% 53.76% 56.40% 59.25% 65.00% 67.00% 69.00% 69.50% 70.20% 70.40% 75.57% 84.05% 88.70% 91.20% 93.90% 96.00% 98.20% 99.06% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 3 % 0.00% 0.00% 0.10% 1.30% 3.20% 5.30% 10.70% 14.00% 19.00% 23.00% 30.50% 36.40% 40.50% 45.20% 51.34% 53.76% 56.40% 59.25% 65.00% 67.00% 69.00% 69.50% 70.20% 70.40% 70.60% 71.05% 71.15% 71.75% 71.85% 76.35% 84.52% 92.12% 96.90% 98.31% 98.87% 99.72% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 4 % 0.00% 0.00% 0.10% 1.30% 3.20% 8.70% 12.20% 17.40% 19.70% 24.90% 30.10% 37.20% 42.00% 45.20% 51.34% 53.76% 56.40% 59.25% 65.00% 67.00% 69.00% 69.50% 70.20% 70.40% 70.60% 71.05% 71.15% 71.75% 71.85% 71.98% 72.05% 72.94% 73.57% 74.05% 74.29% 75.20% 76.10% 77.00% 77.81% 78.50% 78.80% 80.33% 81.53% 82.83% 85.93% 91.26% 96.07% 98.99% 100.00%

Cum. Actual % 0.00% 0.00% 0.10% 1.30% 3.20% 5.30% 10.70% 14.00% 19.00% 23.00% 30.50% 36.40% 40.50% 45.20% 51.34% 53.76% 56.40% 59.25% 65.00% 67.00% 69.00% 69.50% 70.20% 70.40% 70.60% 71.05% 71.15% 71.75% 71.85% 71.98% 72.05% 72.30% 73.57% 74.05% 74.29% 75.20% 76.10% 77.00% 77.81% 78.50% 78.80% 80.30% 81.53% 82.83% 83.93% 85.93%

6(14) Roads Handed Over

Page 45: 32st Project Steering Committee Meeting ADB Funded

PHOTOGRAPHS – NE 1

45

Asphalting at Ch. 3+550Road No. 04

ABC Compacting at Ch. 2+300Road No. 12

Asphalting at Ch. 1+900Road No. 05

Page 46: 32st Project Steering Committee Meeting ADB Funded

Details of Contract Package – NE2

Contractor : Sierra Construction Ltd

Contract amount : Rs. 1,242 Millions

No of Roads : 14 Roads

Total Roads Length : 36.21 km

Start Date : 17th December 2015

Original Completion Date : 16th December 2017

EOT Granted : EOT 1&3 (Approved) EOT 4 (Under Evaluation)

Revised date of completion : 22 June 2018 30 March 2019

46

Page 47: 32st Project Steering Committee Meeting ADB Funded

47

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19

Cum. Plan % 0.27% 1.60% 4.10% 7.81% 11.97% 16.75% 21.63% 26.42% 31.14% 36.26% 41.82% 47.79% 53.89% 59.74% 65.58% 72.12% 78.63% 84.66% 89.20% 92.34% 95.14% 97.82% 99.25% 99.62% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 1 % 0.10% 0.71% 3.79% 6.49% 9.22% 13.54% 16.08% 24.00% 32.10% 40.00% 51.00% 57.00% 63.00% 67.00% 69.00% 72.00% 75.00% 78.00% 80.00% 83.00% 86.00% 88.00% 89.00% 92.00% 94.00% 95.00% 96.00% 97.00% 97.00% 98.00% 99.00% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Actual % 0.10% 0.71% 3.79% 6.49% 9.22% 13.54% 16.08% 24.00% 32.10% 40.00% 51.00% 57.00% 63.00% 67.00% 69.00% 72.00% 75.00% 78.00% 80.00% 83.00% 86.00% 88.00% 89.00% 92.00% 94.00% 95.00% 96.00% 97.00% 97.00% 98.00% 98.10% 98.40% 98.70% 99.00% 99.40% 99.50% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

14(14) Roads Handed Over

Page 48: 32st Project Steering Committee Meeting ADB Funded

Details of Contract Package – NE3

Contractor : Sierra Construction Ltd

Contract amount : Rs. 2,070 Millions

No of Roads : 15 Roads

Total Roads Length : 65.53 km

Start Date : 17th December 2015

Original Completion Date : 16th December 2017

EOT Granted : EOT 1&3 (Approved) EOT 4 to 6(Under Evaluation)

Revised date of completion : 9 August 2018 30 September 2019

48

Page 49: 32st Project Steering Committee Meeting ADB Funded

49

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19

Cum. Initial Plan % 0.53% 1.51% 2.81% 4.00% 5.41% 6.73% 9.89% 14.97% 20.96% 26.65% 33.06% 39.76% 46.28% 53.00% 60.04% 67.26% 74.60% 81.85% 87.73% 92.68% 95.88% 97.49% 98.74% 99.73% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 1 % 0.00% 0.00% 0.09% 0.71% 2.23% 7.13% 12.02% 17.12% 22.67% 28.75% 34.87% 41.30% 47.68% 53.87% 60.25% 65.30% 68.87% 75.25% 80.48% 86.08% 91.95% 95.99% 99.23% 99.89% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 2 % 0.00% 0.00% 0.09% 0.71% 2.23% 3.81% 6.56% 12.60% 23.56% 30.56% 36.89% 44.00% 46.92% 53.81% 59.18% 64.17% 66.95% 68.98% 71.99% 77.12% 79.86% 81.93% 83.71% 84.79% 85.80% 88.34% 90.75% 93.93% 95.23% 96.37% 97.68% 98.96% 99.98% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 3 % 0.00% 0.00% 0.09% 0.71% 2.23% 3.81% 6.56% 12.60% 23.56% 30.56% 36.89% 44.00% 46.92% 53.81% 59.18% 64.17% 66.95% 68.98% 71.99% 77.12% 79.86% 81.93% 83.71% 84.79% 85.80% 87.08% 88.14% 89.15% 89.91% 90.52% 91.20% 91.71% 92.12% 93.52% 95.62% 97.92% 99.42% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 4 % - 31.01.2019 0.00% 0.00% 0.09% 0.71% 2.23% 3.81% 6.56% 12.60% 23.56% 30.56% 36.89% 44.00% 46.92% 53.81% 59.18% 64.17% 66.95% 68.98% 71.99% 77.12% 79.86% 81.93% 83.71% 84.79% 85.80% 87.08% 88.14% 89.15% 89.91% 90.52% 91.20% 91.71% 92.12% 92.52% 92.82% 93.13% 93.48% 94.46% 95.63% 96.80% 97.78% 98.69% 99.28% 99.67% 100.00% 100.00%

Cum. Revised Plan 5 % - 30.06.2019 0.00% 0.00% 0.09% 0.71% 2.23% 3.81% 6.56% 14.86% 23.56% 30.56% 36.89% 44.00% 46.92% 53.81% 59.18% 64.17% 66.95% 68.98% 74.00% 77.12% 79.86% 81.93% 83.71% 84.79% 85.80% 87.08% 88.14% 89.15% 89.91% 90.52% 91.20% 91.71% 92.12% 92.52% 92.82% 93.13% 93.48% 93.80% 94.17% 94.78% 95.14% 96.65% 97.77% 98.69% 99.47% 100.00%

Cum. Actual % 0.00% 0.00% 0.09% 0.71% 2.23% 3.81% 6.56% 12.60% 23.56% 30.56% 36.89% 44.00% 46.92% 53.81% 59.18% 64.17% 66.95% 68.98% 71.99% 77.12% 79.86% 81.93% 83.71% 84.79% 85.80% 87.08% 88.14% 89.15% 89.91% 90.52% 91.20% 91.71% 92.12% 92.52% 92.82% 93.13% 93.48% 93.80% 94.17% 94.78% 95.14% 95.76% 96.81% 97.91% 98.61% 98.89%

9(15) Roads Handed Over

Page 50: 32st Project Steering Committee Meeting ADB Funded

Issues

• None performing contracts▪MA1 Package has identified as a none performing

contract

▪Contractor : KD Ebert and Sons Holding (pvt) Ltd.▪Present Physical Progress : 66.49%▪17.62 km Surfacing to be done (3.67 km Surfacing done

through other Contractors due to Public Complaints)

50

Page 51: 32st Project Steering Committee Meeting ADB Funded

Progress of Urgent Road Maintenance Work

51

Page 52: 32st Project Steering Committee Meeting ADB Funded

Progress of Urgent Road Maintenance Works of Non-Performing Contracts – PIC 03(September 2019)

52

NoNon-Performing

Contract Pkg

Road Maintenance

Works Undertaken

by Contract

No. of Roads to be

Maintained

No. of Roads In

Progress

1 MA 1 KA 3 18 17

Page 53: 32st Project Steering Committee Meeting ADB Funded

Performance Based Maintenance (PBM) Central Province

53

Page 54: 32st Project Steering Committee Meeting ADB Funded

Details of Handed Over Roads (Central Province / up to 30 September 2019)

54

District Package

No.Contractor

No. of Handed

Over Roads (Total

No. of Roads)

Handed Over Length

(Total Road Length) /

(km)

KA 01 Sierra Construction (Pvt.)Ltd. 14 (17) 57.00 (75.24)

KA 02 Sierra Construction (Pvt.)Ltd. 15 (17) 58.44 (72.48)

KA 03 Edward and Christie. 16 (16) 69.34 (69.34)

MA 02 Edward and Christie. 14 (14) 55.55 (55.55)

MA 03 CML-MTD Construction limited 18 (18) 60.76 (60.76)

NE 01 Sierra Construction (Pvt.)Ltd. 6 (14) 20.74 (72.40)

NE 02 Sierra Construction (Pvt.)Ltd. 14 (14) 36.96 (36.96)

NE 03 Sierra Construction (Pvt.)Ltd. 9 (15) 42.20 (66.12)

106 (125) 400.99 (508.26)

Kandy

Matale

Nuwara-Eliya

Total

Page 55: 32st Project Steering Committee Meeting ADB Funded

Cost of Accommodating Public Complaints - Central Province (up to 30 September 2019)

55

Dis

tric

t

Package No. Name of the ContractorTotal No. of Complaints

Accommodating Cost

Kan

dy

KA 01 Sierra Construction (Pvt.) Ltd. 665,886,351.54

KA 02 Sierra Construction (Pvt.) Ltd. 10921,974,212.33

KA 03 Edward and Christie. 697,736,637.00

Mat

ale

MA 01KD Ebert and Sons

Holdings(Pvt) Ltd.80

1,850,000.00

MA 02 Edward and Christie. 361,250,000.00

MA 03 CML-MTD Construction limited 452,425,000.00

Nu

war

a El

iya NE 01 Sierra Construction (Pvt.) Ltd. 239

-

NE 02 Sierra Construction (Pvt.) Ltd. 304,522,992.49

NE 03 Sierra Construction (Pvt.) Ltd. 1038,224,800.00

Total 77753,869,993.36

Page 56: 32st Project Steering Committee Meeting ADB Funded

Summary of Training Programmes / Workshops Conducted by iRoad-PIC 03 up to 30 September 2019

56

Male Female Total

1 Workshop on Environment and Social Consideration 4 63 22 85

2 Workshop on Contract Administration in Construction Supervision 1 68 12 80

3 Workshop on Road Investigation and Pavement Design 1 57 4 61

4 Workshop on Social Safeguard and Environment Progress, ADB Mission 2 106 19 125

5 Workshop on Social Safeguard Concept in iRoad Programme 1 67 14 81

6 Workshop on Calculation of Physical Progress using MS Project 2 39 46 85

7 Identification workshop on Co-operate Social Responsibility Programme 1 43 4 47

8 Awareness workshop on Environment and Social Safeguard 2 98 14 112

9 Awareness workshop for Local Government and Provincial Council Officers 6 447 75 522

10 Awareness Workshop on Road Safety for Drivers of PIU and PIC 2 108 - 108

11Workshop on Interpretation of FIDIC Contract Documents and Overview of

Contract Claims2 81 7 88

12 Workshop on Road Pavement Design 1 67 3 70

13 Workshop on Approval Process of Borrow Materials 1 72 13 85

14 Workshop on Preparation of Quality IPC 1 77 24 101

15Awareness workshop on monitoring environmental & safegurad activities using by

excel spread sheet and GIS package2 46 4 50

16 Workshop on Preparation of As Build Drawings 1 80 3 83

17 Workshop on PBM (CP, SG, Kandy,Matale & Nuwara Eliya Districts) 5 243 92 335

35 1762 356 2118

No. Name of the Programme

No. of

Programmes

held

Participants

Total

Page 57: 32st Project Steering Committee Meeting ADB Funded

Cost to Completion

57

• Cost to Completion (Revision 06) Prepared and forwarded to the Employer.

Statement at Completion (SAC)

• Statement at Completion for Contract MA2 have been completed.• Statement at Completion for Contract MA3 have being prepared by the

Engineer and will be completed in October 2019.• Statement at Completion for Contract KA3 have been submitted by the

Contractor and being checked by the Engineer.

Page 58: 32st Project Steering Committee Meeting ADB Funded

Environmental Safeguard activities

• Environmental field inspections and checking, environmental monitoring check lists have been conducted by Contractors, PIU and PIC Environmental and Social Safeguard Specialists, on all active sites.

Progress of Environmental Safeguard Activities (Sabaragamuwa & Central Provinces and Kalutara District)

58

Submission of the EMAP

• EMAPs were submitted and acceptation was given for these all 18 EMAPs by PIC up to the month

Submission of the EMC up to the month

• 340 EMCs at design and preconstruction stage

• 230 EMCs at 25% construction stage

• 167 EMCs at 50% construction stage

• 158 EMCs at 75% construction stage

• 93 EMCs at 100% construction stage

• 80 EMCs at post construction stage

Page 59: 32st Project Steering Committee Meeting ADB Funded

Details of Removal and Planting of Trees in all Contracts up to the end of September 2019

Package Contractor Total Trees Removed

Total Trees Planted

KA1 Sierra Construction (Pvt) Ltd 42 132

KA2 Sierra Construction (Pvt) Ltd 104 177

KA3 Edward and Christie (Pvt) Ltd 272 370

MA1 K D Ebert and Sons Holdings (Pvt) Ltd 23 109

MA2 Edward and Christie (Pvt) Ltd 10 50

MA3 CML-MTD Construction (Pvt) Ltd 100 586

NE1 Sierra Construction (Pvt) Ltd 63 213

NE2 Sierra Construction (Pvt) Ltd None 50

NE3 Sierra Construction (Pvt) Ltd 32 300Total 646 7964

• 646 trees were removed up to this month in all Packages

• 1,938 trees have to be planted for those removed trees.

• 1,987 trees have already planted by MA1(109), MA2(50), MA3 (586),KA1(132) KA2(177), KA3(370), NE1(213), NE2(50), NE3(300)

Page 60: 32st Project Steering Committee Meeting ADB Funded

GPS Points of Tree Planted Locations in Central Province

60

Page 61: 32st Project Steering Committee Meeting ADB Funded

61

Progress of Safeguard Social Consideration(Central Province)

Field visit with Project Director of Central Province & Team Leader in ADB Mission at Hitihegama- Polgahawatta - Minuwandeniya Road (Road ID. 33) on 23.09.2019 at NE3 Package in

Nuwaraeliya District

Page 62: 32st Project Steering Committee Meeting ADB Funded

62

Progress of the Safeguard Social ConsiderationEstablishment of Grievances Redressing Committees (GRCs) in

Divisional Secretariat & Grama Niladhari Levels – Central ProvinceP

rov

ince/

Dis

tric

t

Package

No.Name of the Contractor

Total No.

of DSDs

DSD LevelTotal No.

of GNDs

GND Level

EstablishedTo be

EstablishedEstablished

To be

Established

Cen

tral P

rov

inc

e

KA 01 Sierra Construction (Pvt.) Ltd. 6 6 0 57 57 0

KA 02 Sierra Construction (Pvt.) Ltd. 6 6 0 20 20 0

KA 03 Edward and Christie. 7 7 0 56 56 0

MA 01 KD Ebert and Sons Holdings(Pvt) Ltd. 3 3 0 34 34 0

MA 02 Edward and Christie. 3 3 0 29 29 0

MA 03 CML-MTD Construction limited 5 5 0 19 19 0

NE 01 Sierra Construction (Pvt.) Ltd. 2 2 0 14 14 0

NE 02 Sierra Construction (Pvt.) Ltd. 2 2 0 18 18 0

NE 03 Sierra Construction (Pvt.) Ltd. 2 2 0 15 15 0

Total 36 36 0 262 262 00

Grievance Redress Committees (GRC) formation completed in Central Province

Page 63: 32st Project Steering Committee Meeting ADB Funded

63

Progress of Civil Works Contracts

up to 30th September 2019

ASIAN DEVELOPMENT BANK FUNDED INTERGRATED ROAD INVESTMENT PROGRAM-1

SABARAGAMUWA PROVINCE

Page 64: 32st Project Steering Committee Meeting ADB Funded

64

Project Location Map-Sabaragamuwa Province

Package No. DistrictNo. of Roads

Road Length (km)

KE01

Kegalle.

12 74.75

KE 02 21 78.25

KE 03 25 64.00

R 01

Ratnapura

12 82.95

R 02 14 91.70

R 03 17 80.35

Total 101 472.00

Page 65: 32st Project Steering Committee Meeting ADB Funded

65

Project Profile-Sabaragamuwa Province

Funding Agency Asian Development Bank (ADB)

Total Cost 11,849 Million

Cumulative Expenditure 7,123 Million

Cumulative Physical Progress 78.24%

Total Length 472.00 km

Location Sabaragamuwa Province ( Kegalle and Rathnapura Districts)

Contract Packages 06 Nos (Only 3 Nos are performing)

Consultant Egis-CEA Joint Venture

Page 66: 32st Project Steering Committee Meeting ADB Funded

66

Overall Financial Progress

Last Month

31-August-2019 (Rs. Mn.)

Reporting Month

30-September-2019 (Rs. Mn.)

Allocation Actual Allocation Actual

11,762.11 7,067.34 11,841.30 7,122.83

Page 67: 32st Project Steering Committee Meeting ADB Funded

67

Overall Physical Progress

Last Month %

(August-2019)

Reporting Month %

(September-2019)

Next Month %

(October 2019)

Target Actual Target Actual Target

99.5 78.06 99.86 78.24 100.00

Page 68: 32st Project Steering Committee Meeting ADB Funded

List of the Packages under the Project

68

Package No. Contractor

Accepted Contract

Amount/ (Rs. Million)

No. of Roads

Actual Road Paving Length

(km)Remarks

KE 01 KD Ebert 1,973 17 74.65

Works suspended by the contractor

KE 02 Nawaloka 1,817 21 78.09 In Progress

KE 03 Nawaloka 1,632 25 67.62 In Progress

R 01 KD Ebert 2,022 12 80.63Works suspended by the

contractor

R 02 KD Ebert 2,384 14 92.24Works suspended by the

contractor

R 03 R. R. Construction 1,973 17 74.65 100% Completed

Total / Avg. 11,849 101 474.24 78.24%

Page 69: 32st Project Steering Committee Meeting ADB Funded

Overall Physical Progress Summary - Sabaragamuwa Province/(up to 30 September 2019)

69

Package No. Contractor

Accepted Contract

Amount/ (Rs. Million)

No. of Roads

Actual Road Paving Length

/ (km)

Cumulative Physical Progress up to 31 August 2019 (%)

Cumulative Physical Progressup to 30 September 2019 (%)

Target (Revised) Actual

KE 01 KD Ebert 1,973 17 74.65 53.18% 100.00*(100.00)% 53.18%

KE 02 Nawaloka 1,817 21 78.09 98.60% 100.00*(100.00)% 98.71%

KE 03 Nawaloka 1,632 25 67.62 93.83% 100.00*(99.18)% 94.85%

R 01 KD Ebert 2,022 12 80.63 64.54% 100.00*(100.00)% 64.54%

R 02 KD Ebert 2,384 14 92.24 58.18% 100.00*(100.00)% 58.18%

R 03 R.R. Const. 2,021 12 81.01 100.00% 100.00*(100.00)% 100.00%

Total / Avg. 11,849 101 474.24 78.06% 99.86% 78.24%**

** - By considering non-performing contracts. Without considering them, the value is 96.78%

Page 70: 32st Project Steering Committee Meeting ADB Funded

70

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19

Cum. Plan % 0.02% 0.09% 0.23% 0.85% 2.59% 5.43% 9.28% 13.77% 17.94% 21.95% 23.66% 26.14% 32.42% 39.52% 45.92% 52.71% 56.07% 62.48% 68.95% 75.01% 81.67% 87.46% 92.35% 95.76% 97.73% 99.02% 99.58% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Rev. Plan 1% 0.02% 0.08% 0.34% 0.83% 1.50% 2.56% 4.51% 7.84% 10.71% 14.01% 18.86% 24.33% 29.11% 35.65% 39.89% 44.46% 46.74% 49.22% 50.82% 52.29% 53.13% 54.01% 54.69% 55.24% 56.27% 58.16% 60.89% 64.37% 67.57% 71.40% 75.15% 79.02% 83.00% 87.17% 90.91% 94.16% 96.77% 98.23% 99.40% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Rev. Plan 2% 0.02% 0.08% 0.34% 0.83% 1.50% 2.56% 4.51% 7.84% 10.71% 14.01% 18.86% 24.33% 29.11% 35.65% 39.89% 44.46% 46.74% 49.22% 50.82% 52.29% 53.13% 54.01% 54.69% 55.24% 56.27% 58.16% 60.89% 64.37% 67.57% 71.40% 75.15% 79.02% 83.00% 85.97% 88.58% 90.97% 92.94% 93.88% 94.81% 95.81% 96.55% 97.39% 98.11% 98.77% 99.50% 99.86% 100.00%

Cum. Actual % 0.02% 0.08% 0.34% 0.83% 1.50% 2.56% 4.51% 7.84% 10.71% 14.01% 18.86% 24.15% 28.90% 35.00% 40.07% 44.55% 46.65% 49.22% 50.83% 52.29% 53.13% 54.01% 54.69% 55.24% 56.27% 58.00% 60.11% 62.49% 63.40% 65.13% 66.58% 67.55% 68.43% 69.50% 70.31% 71.24% 72.26% 73.20% 74.03% 75.12% 75.55% 76.44% 77.22% 77.75% 78.06% 78.24%

Page 71: 32st Project Steering Committee Meeting ADB Funded

Package wise Progress-KE1

• Start Date : 17.12.2015

• End Date : 16.12.2017

• Contract Amount : Rs. 1,973 Millions

• Contractor : KD Ebert and Sons Holdings (Pvt.) Limited

• Cumulative Physical progress : 53.18%

• EOT Granted : Up to 20th May 2018

EOT-1 – 8 days, EOT-2 -06 days

• Present Status : Work suspended due to internal cash flow issue of the

Contractor.

Page 72: 32st Project Steering Committee Meeting ADB Funded

72

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19

Cum. Plan % 0.00% 0.00% 0.41% 1.74% 4.30% 8.74% 13.50% 18.27% 23.13% 28.26% 33.39% 38.52% 43.65% 48.78% 53.91% 59.04% 64.17% 69.30% 74.43% 79.56% 84.64% 89.47% 94.23% 98.23% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan % 0.00% 0.00% 0.12% 0.66% 1.41% 2.01% 4.21% 7.81% 11.91% 15.11% 21.42% 27.87% 33.07% 39.96% 46.84% 53.72% 58.92% 65.80% 72.68% 79.56% 84.64% 89.47% 94.23% 98.23% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan 2 % -

07.03.20180.00% 0.00% 0.12% 0.66% 1.41% 2.01% 4.21% 7.81% 11.91% 15.11% 20.24% 24.78% 29.39% 35.04% 40.20% 43.26% 45.43% 47.10% 47.74% 47.89% 47.89% 47.89% 47.99% 47.99% 47.99% 49.01% 51.32% 55.23% 58.04% 62.56% 67.99% 74.18% 80.59% 86.96% 92.91% 96.95% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Actual % 0.00% 0.00% 0.12% 0.66% 1.41% 2.01% 4.21% 7.81% 11.91% 15.11% 20.24% 24.78% 29.39% 35.04% 40.20% 43.26% 45.43% 47.10% 47.74% 47.89% 47.89% 47.89% 47.99% 47.99% 47.99% 48.87% 49.85% 50.97% 51.26% 52.10% 52.88% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18%

Page 73: 32st Project Steering Committee Meeting ADB Funded

Reasons for Delay - KE1

Delay of work due to cash flow issues of the Contractor.

Contract amount : Rs. 1,973 M

Balance works to be done : Rs. 1,008 M

The Engineer has given recommendation to terminate the Contractor.

Page 74: 32st Project Steering Committee Meeting ADB Funded

Package wise Progress-KE2

• Start Date : 29.03.2016

• End Date : 28.03.2018

• Contract Amount : Rs. 1,816,999,270.80

• Cumulative Physical progress : 98.71%

• Contractor : Nawaloka Construction Co. (Pvt) Ltd

• EOT : Up to 30th September 2019

EOT-1 – 150 days, EOT-2 -413 days

Page 75: 32st Project Steering Committee Meeting ADB Funded

Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19

Cum. Plan % 0.00% 1.00% 1.00% 2.00% 4.00% 7.00% 12.00% 17.00% 24.00% 31.00% 38.00% 44.00% 51.00% 56.00% 61.00% 67.00% 72.00% 78.00% 84.00% 89.00% 94.00% 96.00% 97.00% 98.00% 99.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised - 1 % 0.00% 0.00% 0.00% 1.00% 2.00% 3.00% 4.40% 8.80% 14.14% 18.90% 25.60% 31.10% 37.20% 42.27% 47.62% 53.60% 61.38% 69.56% 77.69% 85.45% 90.78% 94.60% 97.49% 98.88% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised - 2 % 0.00% 0.00% 0.00% 1.00% 2.00% 2.70% 4.40% 8.80% 14.14% 17.73% 22.22% 26.19% 29.33% 30.44% 34.00% 35.94% 37.69% 39.54% 41.66% 45.69% 51.56% 58.47% 66.43% 73.25% 80.17% 86.48% 92.69% 96.95% 99.23% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised - 3 % 0.00% 0.00% 0.00% 1.00% 2.00% 2.70% 4.40% 8.80% 14.14% 17.73% 22.22% 26.19% 29.33% 30.44% 34.00% 35.94% 37.69% 39.54% 41.66% 43.36% 44.44% 46.14% 49.32% 53.35% 57.48% 60.39% 64.21% 67.55% 70.56% 75.45% 80.45% 85.68% 90.02% 93.76% 96.35% 98.10% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised - 4 % 0.00% 0.00% 0.00% 1.00% 2.00% 2.70% 4.40% 8.80% 14.14% 17.73% 22.22% 26.19% 29.33% 30.44% 34.00% 35.94% 37.69% 39.54% 41.66% 43.36% 44.44% 46.14% 49.32% 53.35% 57.48% 60.39% 64.21% 67.55% 70.56% 73.56% 77.04% 79.89% 83.22% 85.92% 88.72% 91.34% 93.94% 96.23% 97.63% 98.39% 98.99% 99.23% 100.00%

Cum. Actual % 0.00% 0.00% 0.00% 1.00% 2.00% 2.70% 4.40% 8.80% 14.14% 17.73% 22.22% 26.19% 29.33% 30.44% 34.00% 35.94% 37.69% 39.54% 41.66% 43.36% 44.44% 46.14% 49.32% 53.35% 57.48% 60.39% 64.21% 67.55% 70.56% 73.56% 77.04% 79.89% 83.22% 85.92% 88.72% 91.07% 93.94% 95.34% 97.07% 98.16% 98.44% 98.60% 98.71%

Page 76: 32st Project Steering Committee Meeting ADB Funded

Package wise Progress-KE3

• Start Date : 29.03.2016

• End Date : 28.03.2018

• Contract Amount : Rs. 1,632,455,502.54

• Cumulative Physical progress : 94.85%

• Contractor : Nawaloka Construction Co. (Pvt) Ltd

EOT-1 – 174 days, EOT-2 -384 days

• EOT : Up to 31st October 2019

Page 77: 32st Project Steering Committee Meeting ADB Funded

77

Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19

Cum. Initial Plan % 0.00% 0.00% 1.00% 2.00% 2.00% 4.00% 8.00% 13.00% 18.00% 23.00% 29.00% 35.00% 40.00% 46.00% 52.00% 58.00% 63.00% 69.00% 75.00% 80.00% 86.00% 91.00% 94.00% 97.00% 98.00% 99.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan -1 % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 3.00% 7.51% 12.83% 17.76% 22.11% 27.60% 31.02% 35.60% 40.81% 46.08% 52.10% 58.31% 65.47% 72.97% 80.04% 86.86% 91.77% 96.64% 98.61% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan -2 % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 2.50% 3.80% 6.10% 11.40% 15.70% 21.93% 26.10% 30.00% 30.76% 32.26% 32.88% 34.50% 36.18% 37.60% 41.18% 47.10% 53.70% 60.87% 66.68% 73.11% 79.58% 85.50% 91.26% 96.45% 99.70% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan -3 % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 2.50% 3.80% 6.10% 11.40% 15.70% 21.93% 26.10% 30.00% 30.76% 32.26% 32.88% 34.50% 36.19% 37.60% 39.19% 40.83% 42.45% 45.09% 47.91% 50.88% 51.78% 54.18% 56.41% 58.88% 61.13% 67.87% 74.25% 80.60% 86.85% 93.03% 98.28% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised Plan -4 % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 2.50% 3.80% 6.10% 11.40% 15.70% 21.93% 26.10% 30.00% 30.76% 32.26% 32.88% 34.50% 36.19% 37.60% 39.19% 40.83% 42.45% 45.09% 47.91% 50.88% 51.78% 54.18% 56.41% 58.88% 61.13% 64.05% 66.05% 68.29% 71.72% 74.57% 77.53% 80.90% 84.05% 87.33% 90.59% 93.78% 96.96% 100.00% 100.00%

Cum. Revised Plan -5 % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 2.50% 3.80% 6.10% 11.40% 15.70% 21.93% 26.10% 30.00% 30.76% 32.26% 32.88% 34.50% 36.18% 37.60% 39.19% 40.83% 42.45% 45.09% 47.91% 50.88% 51.78% 54.18% 56.41% 58.88% 61.13% 64.05% 66.05% 68.29% 71.72% 74.57% 77.53% 80.90% 83.07% 86.68% 90.28% 93.61% 97.76% 99.18% 100.00%

Cum. Actual % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 2.50% 3.80% 6.10% 11.40% 15.70% 21.93% 26.10% 30.00% 30.76% 32.26% 32.88% 34.50% 36.18% 37.60% 39.19% 40.83% 42.45% 45.09% 47.91% 50.88% 51.78% 54.18% 56.41% 58.88% 61.13% 64.05% 66.05% 68.29% 71.72% 74.57% 77.53% 80.90% 82.07% 85.65% 89.26% 92.18% 93.83% 94.85%

Page 78: 32st Project Steering Committee Meeting ADB Funded

Package wise Progress-R1

• Start Date : 17.12.2015

• End Date : 16.12.2017

• Contract Amount : Rs. 2,022 Millions

• Cumulative Physical progress : 64.54%

• Contractor : KD Ebert and Sons Holdings (Pvt.) Limited

• EOT : Up to 04th January 2019

• EOT-1 – 384 days

• Present Status : Work suspended due to internal cash flow issue of the Contractor.

Page 79: 32st Project Steering Committee Meeting ADB Funded

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19

Cum. Plan % 0.06% 0.30% 0.71% 1.36% 4.55% 8.65% 14.42% 19.81% 24.42% 29.06% 34.22% 40.47% 46.48% 53.52% 61.10% 68.28% 74.87% 80.97% 86.50% 90.93% 94.23% 97.27% 99.34% 99.95% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised - 1 % 0.06% 0.30% 0.87% 1.86% 2.69% 4.12% 5.94% 9.62% 11.33% 15.58% 21.01% 27.38% 33.77% 39.69% 45.20% 52.63% 58.14% 64.77% 72.19% 79.45% 86.37% 92.39% 96.64% 99.39% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised - 2 % 0.06% 0.30% 0.87% 1.86% 2.69% 4.12% 5.94% 9.62% 11.33% 17.02% 22.78% 27.45% 31.60% 38.88% 44.37% 49.04% 50.45% 53.96% 55.01% 55.51% 55.51% 55.51% 55.51% 55.51% 55.51% 58.64% 61.75% 65.90% 70.63% 75.32% 79.63% 83.42% 86.76% 89.51% 92.83% 97.36% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Actual % 0.06% 0.30% 0.87% 1.86% 2.69% 4.12% 5.94% 9.62% 11.33% 17.02% 22.78% 27.45% 31.60% 38.88% 44.37% 49.04% 50.45% 53.96% 55.01% 55.51% 55.51% 55.51% 55.51% 55.51% 55.51% 57.80% 61.23% 62.79% 63.02% 64.00% 64.52% 64.53% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54%

Page 80: 32st Project Steering Committee Meeting ADB Funded

Reasons for Delay - R1

Delay of work due to cash flow issues of the Contractor.

Contract amount : Rs. 2,022 M

Balance works to be done : Rs. 1,006 M

The Engineer has given recommendation to terminate the Contractor.

Page 81: 32st Project Steering Committee Meeting ADB Funded

Package wise Progress-R2

• Start Date : 17.12.2015

• End Date : 16.12.2017

• Contract Amount : Rs. 2,384 Millions

• Cumulative Physical progress : 58.18%

• Contractor : KD Ebert and Sons Holdings (Pvt.) Limited

• EOT : Up to 03rd September 2019

EOT-1 – 358 days

• Present Status : Work suspended due to internal cash flow issue of the Contractor.

Page 82: 32st Project Steering Committee Meeting ADB Funded

Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19

Cum. Initial Plan % 0.00% 0.00% 0.00% 0.54% 1.64% 4.73% 10.54% 16.98% 23.04% 29.84% 36.12% 41.99% 48.89% 56.30% 61.56% 67.00% 71.16% 77.29% 82.67% 87.81% 93.60% 97.32% 99.42% 99.99% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised - 1 % 0.00% 0.00% 0.50% 0.92% 1.08% 1.32% 3.36% 7.43% 11.10% 15.13% 19.54% 24.14% 28.97% 35.49% 42.07% 51.24% 56.87% 64.64% 72.18% 79.38% 87.14% 94.04% 98.25% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Revised - 2 % 0.00% 0.00% 0.50% 0.92% 1.08% 1.32% 3.36% 7.43% 11.10% 15.13% 18.58% 23.51% 27.10% 31.35% 35.16% 40.49% 43.41% 45.68% 46.53% 46.66% 46.66% 46.66% 46.86% 46.86% 46.86% 47.24% 51.26% 56.89% 64.66% 72.20% 79.39% 87.14% 94.04% 98.25% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Cum. Actual % 0.00% 0.00% 0.50% 0.92% 1.08% 1.32% 3.36% 7.43% 11.10% 15.13% 18.58% 23.51% 27.10% 31.35% 35.16% 40.49% 43.41% 45.68% 46.53% 46.66% 46.66% 46.66% 46.86% 46.86% 46.86% 47.24% 48.55% 52.95% 54.04% 56.35% 58.17% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18%

Page 83: 32st Project Steering Committee Meeting ADB Funded

Reasons for Delay – R2

Delay of work due to cash flow issues of the Contractor.

Contract amount : Rs. 2,384 M

Balance works to be done : Rs. 1,229 M

The Engineer has given recommendation to terminate the Contractor.

Page 84: 32st Project Steering Committee Meeting ADB Funded

Package wise Progress-R3

• Start Date : 17th December 2015

• End Date : 16th December 2017

• Contract Amount : Rs. 2,021 Millions

• Contractor : R.R. Construction(Pvt) Ltd

• EOT : Up to 8th October 2018

Construction works Completed

Page 85: 32st Project Steering Committee Meeting ADB Funded

Package NoContractor

Accepted Contract Amount

(Rs. Million)

Total Certified Amount (Mobilization Advance)

(Rs. Million)

R 01 KD Ebert and Sons Holdings(Pvt) Ltd. 2,022 1,016.11 (327.65)

R 02 KD Ebert and Sons Holdings(Pvt) Ltd. 2,384 1,154.65 (419.02)

R 03 R.R. Construction (Pvt) Ltd. 2,021 1,997.12(0.00)

KE 01 KD Ebert and Sons Holdings(Pvt) Ltd. 1,973 964.67 (334. 50)

KE 02 Nawaloka Construction Co. (Pvt) Ltd. 1,817 1,523.88 (10.81)

KE 03 Nawaloka Construction Co. (Pvt) Ltd. 1,632 1,203.55 (104.00)

Total 11,849 7,860.08 (1,195.97)

Overall Financial Status –iROAD-Sabaragamuwa Province /(up to 30 September 2019)

Page 86: 32st Project Steering Committee Meeting ADB Funded

ISSUES

• Urgent maintenance works of roads in nonperforming Contracts, KE1, R1 and R2, are done by Contractors of R3, KE2 and KE3

• Due to the prevailing rainy weather in last two months, work progress was reduced and couldn’t achieve set targets of KE2 & KE3.

• KE2 and KE3 Contractor faced cash flow issues. Therefore, ESCROW accounts have been opened for those two packages.

Page 87: 32st Project Steering Committee Meeting ADB Funded

Performance Based Maintenance (PBM) Sabaragamuwa Province

87

Page 88: 32st Project Steering Committee Meeting ADB Funded

Details of Handed Over Roads to Provincial Director RDA, Sabaragamuwa Province(up to 30 September 2019)

88

District Package

No.Contractor

No. of Handed Over

Roads (Total No. of

Roads)

Handed Over Length

(Total Road Length) /

(km)

Ratnapura R3 R R Construction (Pvt.)Ltd. 12 (12) 81.01 (81.01)

KE2Nawaloka Construction Co. (Pvt)

Ltd.9(21) 22.47 (78.10)

KE3Nawaloka Construction Co. (Pvt)

Ltd.5 (25) 8.64 (67.74)

26(58) 112.12 (226.85)Total

Kegalle

Page 89: 32st Project Steering Committee Meeting ADB Funded

iRoad - North Western ProvinceProject Steering Committee Meeting No.32

29th October 2019

Page 90: 32st Project Steering Committee Meeting ADB Funded

Overall Physical Progress of the Project

Last Month (%) Reporting Month (%) Next Month (%)

Target Actual Target Actual Target

3.56 1.51 1.68 0.10 -

(Program of the total packages)

Page 91: 32st Project Steering Committee Meeting ADB Funded

Overall Financial Progress of the Project

Last Month (Rs.) Reporting Month (Rs.)

Allocation Expenditure Allocation Expenditure

- 83,968,809.61 - 87,491,546.07

Page 92: 32st Project Steering Committee Meeting ADB Funded

List of the packages under the project Contra

ct Packag

e

Contractor Remarks

KU 01 Maga Engineering 100% Completed. PBM under operation through Provincial Director – NWP.

KU 02 K.D.A. Weerasinghe – BMG Joint Venture

100% Completed. PBM under operation through Provincial Director - NWP.

KU 03 Terminated w.e.f. 2019.02.26, A case filed for guarantee encashment. Rebidding process in progress.

KU 04 V.V. Karunarathne & CompanyAwaiting ADB’s concurrence for Employer’s Termination.

KU 05 Terminated w.e.f. 2019.02.26, A case filed for guarantee encashment. Rebidding process in progress.

PU 01 Ranken Railway Constructions Finishing works are in progress.

PU 02 Terminated w.e.f. 2019.08.02 – Cabinet decision has to be revoked for rebidding.

PU 03 V.V. Karunarathne & CompanyAwaiting ADB’s concurrence for Employer’s Termination.

Page 93: 32st Project Steering Committee Meeting ADB Funded

Progress

Contract Package

Financial (%) Physical (%)

Planned Achieved Planned Achieved

KU 02 0.60 0.93 0.01 0.01

KU 04 4.68 0.00 4.63 0.00

PU 01 0.49 0.31 0.4 0.3

PU 03 - - - -

Page 94: 32st Project Steering Committee Meeting ADB Funded

Package wise Program

• Package No :- KU1

• Start Date :- 01.08.2016

• End Date :- 31.01.2019

• Contract Amount :- Rs. 2,005,790,082.72

• Contractor :- Maga Engineering (Pvt) Ltd

• EOT :- EOT 1 – 6 months

Page 95: 32st Project Steering Committee Meeting ADB Funded

Package wise Program

• Package No :- KU2

• Start Date :- 01.08.2016

• End Date :- 15.09.2019

• Contract Amount :- Rs. 2,124,166,266.00

• Contractor :- KDA Weerasinghe – BMG Joint Venture

• Cumulative Physical Progress :- 100%

• EOT :- EOT 1 - 241 Calendar days

EOT 2 - 39.5 Calendar days

EOT 3 - 130 Calendar days

Page 96: 32st Project Steering Committee Meeting ADB Funded

Package wise Program

• Package No :- KU4

• Start Date :- 01.08.2016

• End Date :- 30.09.2019

• Contract Amount :- Rs. 2,091,174,540.00

• Contractor :- VV Karunarathna & Co.

• Cumulative Physical progress :- 55.2%

• EOT :- EOT 1 – 14 months.

All sites are abandoned since April 2019

Page 97: 32st Project Steering Committee Meeting ADB Funded

Reasons for delay

KU4 – VVK

Delay of work due to cash flow issues of the Contractor.

Contract amount :- Rs. 2,091,174,540.00

Balance works to be done :- Rs. 1,146,447,391.82

Page 98: 32st Project Steering Committee Meeting ADB Funded

Package wise Program• Package No :- PU1

• Start Date :- 01.08.2016

• End Date :- 29.10.2019

• Contract Amount :- Rs. 1,706,320,523.61

• Contractor :- Ranken Railway Constructions.

• Cumulative Physical progress :- 98.2%

• EOT :- EOT 1 - 273 Calendar days

EOT 2 - 88 Calendar days

EOT 3 - 94 Calendar days

Delay in finishing works and handing over roads

Page 99: 32st Project Steering Committee Meeting ADB Funded

Package wise Program• Package No :- PU3

• Start Date :- 01.08.2016

• End Date :- 29.05.2019

• Contract Amount :- Rs. 1,210,355,904.00

• Contractor :- VV Karunarathna & Co

• Cumulative Physical progress :- 60.0%

• EOT :- EOT 1 - 184 Calendar days

EOT 2 - 118 Calendar days

All sites are abandoned since April 2019

Page 100: 32st Project Steering Committee Meeting ADB Funded

Reasons for delay

PU3 – VVK

Delay of work due to cash flow issues.

Contract amount :- Rs. 1,210,355,904.00

Balance work to be done :- Rs. 376,484,682.47

Page 101: 32st Project Steering Committee Meeting ADB Funded

ISSUES• Emergency works in terminated Contract PU2 are to be attended by the

Contractor of PU1.

• Attending emergency works and safety requirements in Contract Packages KU4 & PU3 are to be attended by the contractor of PU1.

• Routine maintenance and making roads motorable in Contract Packages KU4,PU2 & PU3 are still unsolved.

• Some of the emergency works in KU4 has to be done with the help of Pradeshiya Sabha and Public.

Page 102: 32st Project Steering Committee Meeting ADB Funded

Abandoned causeway construction

Ihalagama Junction to Nochchiya across Wannikudawewa Road – RD ID 07

Page 103: 32st Project Steering Committee Meeting ADB Funded

After temporary reinstatement

Ihalagama Junction to Nochchiya across Wannikudawewa Road – RD ID 07

Page 104: 32st Project Steering Committee Meeting ADB Funded

Abandoned culvert construction

Palugolla Iginimitiya Road (Aluthgama Kotawehera Road ) – RD ID 27

Page 105: 32st Project Steering Committee Meeting ADB Funded

After temporary reinstatement

Palugolla Iginimitiya Road (Aluthgama Kotawehera Road) – RD ID 27

Page 106: 32st Project Steering Committee Meeting ADB Funded

Thank You…

106