32st Project Steering Committee Meeting ADB Funded
Integrated Road Investment Program (iRoad 1)29 October 2019
1
iRoad 1 Map
Overall Status of Rural Road PackagesProvince No. of
packagesNo. of
packages completed
Km No. of km completed
Physical Progress as at
15 October 2019
Remarks
Planned (%)
Actual (%)
Southern 09 07 582 575 100.0 98.5 1 contract terminated. Court order for encashment.
Central 09 04 595 539 99.5 94.5 Court order for encashment for one contract & termination
Sabaragamuwa 06 01 472 345 99.8 78.8 3 contracts, court orders for encashment & termination
North Central 07 07 508 508 100.0 100.0 Completed. Statement at completion in progress
North Western 08 01 705 480 97 60 3 contract terminated... Court orders for encashment.. Retendering works completed and ready for awarding.
Kalutara 03 - 277 153 97.5 61 2 contracts terminated. Court orders for encashment..
Total 42 19 3,139 2,575 98.5 82.2
4
Non-performing & Terminated Contracts
Cabinet decision received to complete the balance works of the terminated contracts through the local funds. Note to cabinet was sent to the cabinet for approval since the treasury finds difficulty in funding locally
Contractor Packages Status
K.D. Ebert G1 Terminated on 12/02/2019. challenged and obtained stay order for encashment of guarantees.
K.D. Ebert R1, R2, KE1 ADB concurrence for termination received. Contractor obtained stay order for termination and encashment of guarantees.
Ranken Railway KU3, KU5 Terminated on 12/02/2019. Encashment demanded from the BOC on 12/02/2019. retendering works completed and ready for awarding.
VVK KU4, PU2, PU3 PU2 – Terminated. Court order for encashment.KU4, PU3 - Poor progress. Contractual action is being taken for termination.
Olympus – Rani JV KL2, KL3 Terminated. Court order prevails for encashment.
Expenditure – 2019 – iRoad 1 Program
No Description LKR (Mn)
1 Budget Allocation 7,687
2 Expenditure as at Oct 2019 7,687
3 % Financial achievement 100%
Southern Province
6
Package No Contractor No.of RoadsRoad Length
(Km)Status
G1 K.D.Ebert & Sons Holdings (Pvt.) Ltd 15 64.6Terminated –76%
G2 K.D.A. Weerasinghe & Co (Pvt) Ltd 22 66.0 Completed
G3 K.D.A. Weerasinghe & Co (Pvt) Ltd 29 70.8 Completed
M1 CML-MTD Construction Ltd 22 97.5 Completed
M2 K.D.Ebert & Sons Holdings (Pvt.) Ltd 19 69.5 Completed
M3 K.D.Ebert & Sons Holdings (Pvt.) Ltd 25 53.4 Completed
H1 K.D.A. Weerasinghe & Co (Pvt) Ltd 19 67.1 Completed
H2 CML-MTD Construction Ltd 18 58.0 Completed
H3 R.R Construction. (Pvt.) Ltd 14 41.9 Completed
Total 183 588.8
North Central Province
7
Pkg No. Contractor No. Of Roads/Length (km) Status
AP1 MAGA 17/85.09 Completed
AP2 MAGA 12/76.85 Completed
AP3 MAGA 12/82.66 Completed
AP4 MAGA 19/90.20 Completed
PO1 MAGA 18/50.76 Completed
PO2 MAGA 25/73.36 Completed
PO3 TISSA-AMSK JV 11/49.55 Completed
8
Kalutara District
Overall Physical Progress Summary –iROAD-Kalutara District /(up to 15th October2019)
9
Package No. ContractorNo. of Roads
Total Length / (km)
Physical Progress; Cumulative Status up to 15th October 2019 (%)
StatusTarget (Revised) Actual
KL 01 Maga 42 87.50 99.5 99.1%
Scheduled
completion
31st October
2019
KL 02 OCPL Jv RCPL 19 88.40 100 35.15% Terminated
KL 03 OCPL Jv RCPL 22 93.35 100 51.83% Terminated
Total / Avg. 83 269.25 100% 61.2%
Photographs – KL 1
10
Asphalt concrete laying works at RD 59 (From Duwa Temple Road
Vilegoda Via Aluth Para)
Finishing works -Top soiling at RD 68 (Wilpatha Puhabugoda akkara
18 via Puhabugoda Road)
Cost to Completion
11
• SAC is under preparation for KL1
• Valuation at Termination together with the employers claim being prepared.
Road Management Contracts (RMC) Of National Roads
12
Road Management Contracts MAPContract
No
Route No Road Length (km) Status
RMC SP1 B 248, B 454, B 303, B
139, B 129, B 429 & B156
Karapitiya – Labuduwa – Thawalama Road 52.0 Construction In
Progress
RMC 1 A 01 Colombo – Kandy Road from Ambepussa to
Kadugannawa
40.0 Expect to award in
June 2020RMC 3 A11 Maradankadawala - Thirikondiamadu Road from
Maradankadawala to Habarana 25.0Construction In
ProgressRMC 4 A18 Pelmadulla - Padalangala Road 66.0 Expect to award in
Dec 2019RMC 5 B 133,
B 212 & B 213
Thalawa - Kekirawa road, Kekirawa - Ganewalpola Road
& Ganewalpola - Dachchihalmillewa Road 90.0Expect to award in
May 2020RMC 6 A 03 Peliyagoda Puttalam Road section from Kochchikade
Bridge to Puttlam
88.0 Expect to award in
July 2020
RMC 7 A 02 Galle Road from Nallurwa Bridge to Benthota Bridge 21.0 Expect to award in
Aug 2020RMC 8 B 065 Bowaththa - Pandiwela Road 17.7 Expect to award in
Sep 2020B 244 Kuliyapitiya - Pandiwela Road
RMC 9 B364 Peradeniya – Deltota – Rikillagaskada Road 53.0 Expect to award in
Sep 2020Total 404.7
Road Management Contracts MAP
Project Profile (Awarded Contracts)
Funding AgencyAsian Development Bank
Contract No. RMC-03Maradankadawala - Habarana
RMC-SP1Karapitiya – Thawalama Road
Total Cost (SLR) 3,315,189,385.00 6,108,200,364.84
Cumulative Expenditure (SLR) 203,888,552.20 284,186,887.41
Cumulative Physical Progress 11.85% 1.04%
Total length 25.0 KM 51.7 KM
Location Anuradhapura District Galle District
Date of Commencement 16 April 2019 25 July 2019
Duration 6 years 5.5 years
Contractor Consulting Engineers & Contractors
Pvt Ltd (CEC)
K D A Weerasinghe & Company Pvt Ltd in JV with
Yunnan Construction (KDAW-YCIH JV)
Consultant Oriental Consultants Global Co Ltd (Japan) JV with Consulting Engineer’s and Architects
Associated Pvt Ltd
Overall Physical Progress
Project Name Last Month %Cumulative
Reporting Month %Cumulative
Next Month Cumulative%
Target Actual Target Actual Target
RMC-03Maradankadawal
a - Habarana8.08% 8.50% 12.13% 11.85% 16.42%
SP 1Karapitiya –
Thawalama RoadContract’s Design and preliminary works in progress..
Physical Progress-RMC 03
Ap
ril-
19
May
-19
Jun
e-1
9 July
-19
Au
gust
-1
9
Sep
tem
ber
-1
9 Oct
ob
er-1
9
No
vem
ber
-1
9
Dec
emb
er-1
9
Jan
uar
y-2
0
Feb
ruar
y-2
0 Mar
ch-2
0
No
vem
ber
-20
Oct
ob
er-2
0
Sep
tem
ber
-20
Au
gust
-20
Ap
ril-
20
May
-20
Jun
e-2
0
July
20
Dec
emb
er-2
0
Jan
uar
y-2
1
Feb
ruar
y-2
1 Mar
ch-2
1
Ap
ril-
21
Programme
Physical Progress-SP 01
July
-19
Au
gust
-19
Sep
tem
ber
-19
Oct
ob
er-
19
No
vem
ber
-1
9 Dec
emb
er-1
9
Jan
uar
y-2
0
Feb
ruar
y-2
0
Mar
ch-2
0
Ap
ril-
20
May
-20
Jun
e-2
0
Feb
ruar
y-2
1
Jan
uar
y-2
1
Dec
emb
er-2
0
No
vem
ber
-2
0
July
-20
Au
gust
-20
Sep
tem
ber
-2
0 Oct
ob
er-2
0
Mar
ch-2
1
Ap
ril-
21
May
-21
Jun
e-2
1
July
-21
Asphalt works at Ch 0+350km
PROJECT PHOTOS – RMC 03 CONTRACTMaradankadawala- Habarana Road
Traffic Management and Safety Measures at at Culvert No. 4/1
GRC Meeting at Akmeemana Divisional Secretary’s Office 28th August 2019Routine Maintenance on Udugama Bus Stand to Hiniduma Road
PROJECT PHOTOS – SP 01 CONTRACT521.7 kms of B Class Roads in Galle District
21
Progress of Civil Works Contracts up to
30th September 2019
ADB Funded Integrated Road Investment Program (I Road)
Rehabilitation/Improvement and Maintenance of Rural Roads in Central Province.
– PIC 03
22
Project Location Map-Central Province
Project Profile (Basic information)
Funding Agency : Asian Development Bank
Total cost : 15,666 Million
Total Length : 581.74 km
Location : Central Province (Kandy, Matale, Nuwaraeliya Districts)
Date of Commencement : 17th December 2015
Completion date : 16th December 2017
Consultant : Egis CEA Joint venture
23
Overall Financial Progress of the Project
Last Month Reporting Month(September)
Allocation (Mn) Expenditure (Mn) Allocation (Mn) Expenditure (Mn)
15,093.49 13,729.33 15,384.71 13,745.52
24
Overall Physical Progress of the Project
Last Month (%) Reporting Month (%)
Target Actual Target Actual
99.31 94.27 99.57 94.53
25
Overall Physical Progress Summary –iROAD-Central Province /(up to 30 September 2019)
26
Package No. Contractor
Accepted Contract
Amount/ (Rs. Million)
No. of Roads
Actual Road Paving
Length / (km)
No. of Roads Civil Works in Progress
Total road pavement length
(asphalt+concrete) completed (km)
Physical Progress; Cumulative Status
up to 31 August 2019 (%)
Physical Progress; Cumulative Status up to 30 September 2019 (%)
Target (Revised) Actual
(A) Completed Contracts
NE 02 Sierra 1,242 14 36.21 0 36.21 100.00% 100.00% 100.00%
MA 02Edward and
Christie.1,249 14 55.55 0 55.55 100.00% 100.00% 100.00%
MA 03 CML-MTD 1,408 18 60.76 0 60.76 100.00% 100.00*(100.00)% 100.00%
KA 03Edward and
Christie.2,097 16 68.45 0 68.45 100.00% 100.00*(100.00)% 100.00%
(B) Performing Contracts
KA 01 Sierra 1,756 17 75.24 8 75.24 99.42% 100.00*(100.00)% 99.50%
KA 02 Sierra 1,924 17 72.48 5 72.48 100.00% 100.00*(100.00)% 100.00%
NE 01 Sierra 2,298 14 72.40 9 56.00 83.93% 100.00*(91.26)% 85.93%
NE 03 Sierra 2,070 15 65.53 9 64.50 98.61% 100.00*(100.00)% 98.89%
(C) Non-Performing Contracts
MA 01 KD Ebert 1,622 18 75.12 13 53.83 66.49% 100.00*(100.00)% 66.49%
Total / Avg. 15,666 143 581.74 44 543.02 94.27% 99.03% 94.53%
27
Overall Physical Progress S curve –iROAD-Central Province /(up to 30 September 2019)
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19
Cum. Plan % 0.11% 0.54% 1.81% 4.69% 6.87% 10.67% 14.32% 18.99% 23.78% 29.29% 33.97% 38.68% 43.60% 49.46% 54.76% 60.59% 65.49% 71.84% 77.95% 83.74% 89.40% 94.31% 98.08% 99.57% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Rev. Plan 1 % 0.01% 0.29% 1.34% 3.29% 5.08% 8.15% 11.93% 16.57% 22.22% 27.38% 34.10% 39.32% 44.11% 49.37% 53.57% 58.51% 62.17% 65.83% 69.92% 73.61% 76.72% 79.45% 81.82% 83.10% 84.36% 85.90% 87.37% 89.08% 89.70% 91.49% 93.67% 96.04% 97.69% 97.97% 98.86% 99.64% 99.94% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Rev. Plan 2 % 0.01% 0.29% 1.34% 3.29% 5.08% 8.15% 11.93% 16.57% 22.22% 27.38% 34.10% 39.32% 44.11% 49.37% 53.57% 58.51% 62.17% 65.83% 69.92% 73.61% 76.72% 79.45% 81.82% 83.10% 84.36% 85.76% 87.08% 88.54% 89.11% 90.36% 91.57% 92.73% 93.63% 94.40% 95.19% 95.78% 96.06% 96.58% 96.84% 97.58% 98.01% 98.46% 98.76% 99.20% 99.31% 99.57% 99.78% 99.91% 100.00%
Cum. Actual % 0.03% 0.41% 1.41% 3.71% 5.73% 9.08% 13.07% 17.39% 22.62% 27.67% 33.82% 38.27% 43.00% 48.54% 53.20% 58.58% 61.84% 64.87% 69.04% 72.68% 75.74% 78.43% 80.51% 81.97% 83.41% 84.76% 86.10% 87.61% 88.28% 89.09% 89.69% 90.26% 90.76% 91.16% 91.60% 91.83% 92.11% 92.60% 92.72% 92.93% 93.02% 93.33% 93.65% 94.00% 94.27% 94.53%
Package
No
Contractor
Accepted
Contract
Amount/ (Rs.
Million)
Total Certified Amount
(Mobilization Advance) /(Rs.
Million)
KA1 Sierra Construction (Pvt.) Ltd. 1,756 1,409.42 (55.01)
KA2 Sierra Construction (Pvt.) Ltd. 1,924 1,516.67 (65.38)
KA3 Edward and Christie. 2,097 1,711.09 (54.05)
MA1 KD Ebert and Sons Holdings(Pvt) Ltd. 1,622 937.16 (191.92)
MA2 Edward and Christie. 1,249 1,153.94 (0.00)
MA3 CML-MTD Construction limited 1,408 1,174.21 (9.04)
NE1 Sierra Construction (Pvt.) Ltd. 2,298 1,705.33 (138.66)
NE2 Sierra Construction (Pvt.) Ltd. 1,242 1,096.22 (0.00)
NE3 Sierra Construction (Pvt.) Ltd. 2,070 1,909.89 (0.00)
Total 15,666 12,613.93 (514.05)
Overall Financial Status –iROAD-Central Province /(up to 30 September 2019)
28
Package wise Work Progress - Central Province
29
Details of Contract Package – KA1
Contractor : Sierra Construction Ltd
Contract amount : Rs. 1,756 Millions
No of Roads : 17 Roads
Total Roads Length : 75.11 km
Start Date : 17th December 2015
Original Completion Date : 16th December 2017
EOT Granted : EOT 1-5 (Approved) EOT 6 (Under Evaluation)
Revised date of completion : 06 June 2018 30 September 2019
30
31
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
Cum. Plan % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 57.05% 62.45% 65.91% 70.52% 75.60% 80.65% 86.05% 91.77% 96.59% 99.81% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 83.64% 86.90% 90.85% 93.15% 96.20% 98.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 82.03% 85.45% 87.50% 90.35% 92.80% 95.40% 97.10% 98.70% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 3 % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 82.03% 84.10% 85.15% 86.70% 87.70% 89.00% 90.04% 93.30% 96.69% 98.89% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 4 % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 82.03% 84.10% 85.15% 86.70% 87.70% 89.00% 90.04% 90.56% 91.37% 92.02% 94.36% 95.10% 97.40% 99.10% 99.60% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 5 % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 82.03% 84.10% 85.15% 86.70% 87.70% 89.00% 90.04% 90.56% 91.37% 92.02% 94.36% 94.61% 95.00% 97.55% 97.72% 97.76% 97.77% 98.20% 98.36% 99.12% 99.62% 100.00%
Cum. Actual % 0.03% 1.08% 1.98% 4.94% 6.91% 11.21% 14.46% 16.61% 18.91% 22.52% 29.47% 35.03% 41.03% 45.56% 55.45% 58.58% 61.67% 64.63% 68.57% 71.20% 73.22% 76.70% 78.60% 80.17% 82.03% 84.10% 85.15% 86.70% 87.70% 89.00% 90.04% 90.56% 91.37% 92.02% 94.36% 94.61% 95.00% 97.55% 97.72% 97.76% 97.80% 98.37% 98.78% 99.30% 99.42% 99.50%
14(17) Roads Handed Over
PHOTOGRAPHS – KA 1
32
Shoulder construction work at Ch. 4+880 (RHS)Road No.02
Date : 15.09.2019
ABC Laying work at Ch. 4+520Road No.01
Date : 26.09.2019
Details of Contract Package – KA2
Contractor : Sierra Construction Ltd
Contract amount : Rs. 1,924 Millions
No of Roads : 17 Roads
Total Roads Length : 72.35 km
Start Date : 17th December 2015
Original Completion Date : 16th December 2017
EOT Granted : EOT 1-6 (Approved) EOT 7 (Under Evaluation)
Revised date of completion : 19 Oct 2018 29 June 2019
33
34
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
Cum. Plan % 0.00% 0.08% 1.92% 4.10% 5.39% 9.89% 14.56% 19.69% 25.27% 32.82% 42.95% 49.74% 56.03% 63.76% 70.09% 74.36% 76.90% 81.07% 83.69% 87.15% 89.52% 92.58% 98.03% 99.78% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.00% 0.45% 2.22% 5.16% 7.25% 9.04% 16.09% 19.94% 26.12% 32.93% 40.00% 44.81% 49.82% 53.50% 57.50% 61.78% 65.01% 69.25% 74.21% 79.21% 84.22% 89.86% 95.31% 98.10% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.00% 0.45% 2.22% 5.16% 7.25% 9.04% 16.09% 19.94% 26.12% 32.93% 40.00% 44.81% 49.82% 53.50% 57.35% 61.60% 62.91% 68.42% 73.22% 78.13% 82.14% 86.64% 90.65% 92.01% 94.00% 95.00% 96.32% 96.34% 96.80% 97.20% 97.50% 97.90% 98.30% 98.70% 99.15% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Actual % 0.00% 0.45% 2.22% 5.16% 7.25% 9.04% 16.09% 19.94% 26.12% 32.93% 40.00% 44.81% 49.82% 53.50% 57.35% 61.60% 62.91% 68.42% 73.22% 78.13% 82.14% 86.64% 90.65% 92.01% 94.00% 95.00% 96.32% 96.34% 96.53% 97.10% 97.37% 98.55% 99.18% 99.20% 99.22% 99.25% 99.25% 99.35% 99.40% 99.45% 99.46% 99.47% 99.48% 99.51% 100.00% 100.00%
15(17) Roads Handed Over
Details of Contract Package – KA3
Contractor : Edward & Christie Construction Ltd
Contract amount : Rs. 2,097 Millions
No of Roads : 16 Roads
Total Roads Length : 68.52 km
Start Date : 17th December 2015
Original Completion Date : 16th December 2017
EOT Granted : EOT 1 (Approved)
Revised date of completion : 31 March 2019
35
36
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
Cum. Initial Plan % 0.13% 0.39% 2.23% 5.08% 7.28% 10.87% 18.36% 26.21% 34.39% 42.69% 50.85% 58.66% 64.53% 69.75% 74.45% 79.18% 82.11% 85.11% 88.42% 91.53% 94.14% 96.56% 98.95% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.00% 0.05% 0.19% 1.02% 3.67% 8.18% 11.94% 16.34% 21.22% 27.16% 32.38% 36.20% 39.38% 44.33% 49.52% 54.88% 60.07% 66.43% 73.15% 80.10% 87.20% 93.01% 97.46% 99.47% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.00% 0.05% 0.19% 1.02% 3.67% 8.18% 11.83% 15.87% 19.68% 23.96% 30.15% 33.57% 38.21% 42.54% 47.17% 52.05% 54.74% 57.51% 60.62% 63.76% 67.21% 70.91% 74.50% 76.25% 79.00% 84.00% 88.00% 92.00% 94.00% 96.00% 98.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Actual % 0.00% 0.05% 0.19% 1.02% 3.67% 8.18% 11.83% 15.87% 19.68% 23.96% 30.15% 33.57% 38.21% 42.54% 47.17% 52.05% 54.74% 57.51% 60.62% 63.76% 67.21% 70.91% 74.50% 76.25% 78.90% 81.89% 83.98% 88.47% 90.54% 91.73% 93.40% 95.23% 96.20% 97.50% 98.10% 98.50% 98.70% 99.20% 99.30% 99.35% 99.50% 99.57% 99.80% 100.00% 100.00% 100.00%
16(16) Roads Handed Over
Details of Contract Package – MA1
Contractor : K D Ebert and Sons Holding (pvt) Ltd
Contract amount : Rs. 1,622 Millions
No of Roads : 18 Roads
Total Roads Length : 75.12 km
Start Date : 17th December 2015
Original Completion Date : 16th December 2017
EOT Granted : EOT 1 (Approved)
Revised date of completion : 07 November 2018
37
38
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
Cum. Plan % 0.00% 0.12% 1.06% 6.15% 7.79% 11.53% 16.99% 23.27% 29.15% 34.24% 38.64% 45.01% 52.43% 59.08% 64.15% 70.87% 75.39% 80.73% 85.41% 90.58% 94.67% 97.38% 99.16% 99.98% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.00% 0.14% 1.17% 3.01% 5.10% 5.91% 10.97% 15.10% 19.18% 23.29% 28.57% 31.91% 35.33% 41.78% 48.56% 55.72% 61.24% 68.57% 75.92% 83.26% 89.79% 94.71% 98.02% 99.84% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.00% 0.14% 1.17% 3.01% 5.10% 5.91% 10.97% 15.10% 19.18% 23.29% 27.80% 31.07% 35.18% 38.72% 41.28% 48.73% 50.83% 53.48% 54.83% 54.93% 54.96% 54.99% 54.99% 54.99% 54.99% 56.30% 59.80% 63.80% 67.30% 72.30% 77.30% 82.30% 87.30% 92.30% 96.10% 99.30% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Actual % 0.00% 0.14% 1.17% 3.01% 5.10% 5.91% 10.97% 15.10% 19.18% 23.29% 27.80% 31.07% 35.18% 38.72% 41.28% 48.73% 50.83% 53.48% 54.83% 54.93% 54.96% 54.99% 54.99% 54.99% 54.99% 56.30% 58.72% 62.30% 62.88% 64.66% 65.77% 66.21% 66.21% 66.43% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49% 66.49%
17.62 km Surfacing to be completed
Details of Contract Package – MA2
Contractor : Edward & Christie Construction Ltd
Contract amount : Rs. 1,249 Millions
No of Roads : 17 Roads
Total Roads Length : 57.84 km
Start Date : 17th December 2015
Original Completion Date : 16th December 2017
EOT Granted : EOT 1 (Approved)
Revised date of completion : 21 May 2018
39
40
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
Cum. Plan % 0.00% 0.47% 1.84% 6.09% 7.24% 11.00% 12.70% 16.00% 19.15% 22.01% 26.00% 31.10% 35.85% 43.00% 50.20% 58.15% 66.80% 75.10% 81.94% 87.78% 93.58% 96.63% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Actual % 0.00% 0.19% 0.75% 1.57% 2.90% 6.50% 13.80% 19.94% 25.93% 32.45% 39.24% 43.40% 48.53% 51.10% 56.84% 63.05% 65.91% 70.06% 75.05% 80.47% 86.84% 90.74% 92.83% 95.90% 97.50% 98.20% 98.58% 99.50% 99.95% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
14(14) Roads Handed Over
Details of Contract Package – MA3
Contractor : CML – MTD Construction Ltd
Contract amount : Rs. 1,408 Millions
No of Roads : 18 Roads
Total Roads Length : 59.92 km
Start Date : 17th December 2015
Original Completion Date : 16th December 2017
EOT Granted : EOT 1.6 (Approved) EOT 2 (Under Evaluation)
Revised date of completion : 31 August 2018 09 Feb 2019
41
42
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
Cum. Initial Plan % 0.00% 0.24% 1.28% 4.38% 5.88% 9.70% 14.21% 20.21% 27.66% 34.58% 38.76% 44.52% 47.82% 53.57% 58.68% 63.60% 66.68% 73.48% 83.93% 91.46% 95.28% 97.02% 99.66% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.00% 0.09% 0.93% 1.95% 2.79% 4.50% 9.52% 15.24% 23.18% 28.28% 32.17% 35.71% 39.37% 44.55% 51.11% 57.84% 62.03% 69.07% 76.08% 82.84% 89.60% 96.09% 99.73% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.00% 0.09% 0.93% 1.95% 2.79% 4.50% 9.52% 15.24% 23.18% 28.28% 32.17% 36.01% 40.27% 44.77% 51.00% 57.37% 62.15% 66.28% 72.10% 78.50% 82.40% 86.50% 90.10% 91.20% 92.80% 94.35% 95.50% 96.50% 97.40% 98.20% 99.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Actual % 0.00% 0.09% 0.93% 1.95% 2.79% 4.50% 9.52% 15.24% 23.18% 28.28% 32.17% 36.01% 40.27% 44.77% 51.00% 57.37% 62.15% 66.28% 72.10% 78.50% 82.40% 86.50% 90.10% 91.20% 92.80% 94.15% 96.68% 97.30% 98.20% 98.80% 99.30% 99.40% 99.50% 99.70% 99.70% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
18(18) Roads Handed Over
Details of Contract Package – NE1
Contractor : Sierra Construction Ltd
Contract amount : Rs. 2,298 Millions
No of Roads : 14 Roads
Total Roads Length : 76.60 km
Start Date : 17th December 2015
Original Completion Date : 16th December 2017
EOT Granted : EOT 1&3 (Approved) EOT 4 (Under Evaluation)
Revised date of completion : 19 October 2018 20 December 2019
43
44
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19
Cum. Plan % 0.00% 0.00% 0.10% 1.10% 4.20% 8.70% 12.20% 17.40% 19.70% 24.90% 30.10% 37.20% 42.00% 46.30% 50.10% 55.70% 60.50% 67.00% 75.30% 81.10% 86.20% 91.30% 95.20% 98.20% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.00% 0.00% 0.10% 1.30% 3.20% 5.30% 10.70% 14.00% 19.00% 23.00% 30.50% 36.40% 40.50% 45.20% 53.05% 57.10% 60.82% 67.75% 75.02% 81.43% 87.06% 92.95% 97.11% 99.38% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.00% 0.00% 0.10% 1.30% 3.20% 5.30% 10.70% 14.00% 19.00% 23.00% 30.50% 36.40% 40.50% 45.20% 51.34% 53.76% 56.40% 59.25% 65.00% 67.00% 69.00% 69.50% 70.20% 70.40% 75.57% 84.05% 88.70% 91.20% 93.90% 96.00% 98.20% 99.06% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 3 % 0.00% 0.00% 0.10% 1.30% 3.20% 5.30% 10.70% 14.00% 19.00% 23.00% 30.50% 36.40% 40.50% 45.20% 51.34% 53.76% 56.40% 59.25% 65.00% 67.00% 69.00% 69.50% 70.20% 70.40% 70.60% 71.05% 71.15% 71.75% 71.85% 76.35% 84.52% 92.12% 96.90% 98.31% 98.87% 99.72% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 4 % 0.00% 0.00% 0.10% 1.30% 3.20% 8.70% 12.20% 17.40% 19.70% 24.90% 30.10% 37.20% 42.00% 45.20% 51.34% 53.76% 56.40% 59.25% 65.00% 67.00% 69.00% 69.50% 70.20% 70.40% 70.60% 71.05% 71.15% 71.75% 71.85% 71.98% 72.05% 72.94% 73.57% 74.05% 74.29% 75.20% 76.10% 77.00% 77.81% 78.50% 78.80% 80.33% 81.53% 82.83% 85.93% 91.26% 96.07% 98.99% 100.00%
Cum. Actual % 0.00% 0.00% 0.10% 1.30% 3.20% 5.30% 10.70% 14.00% 19.00% 23.00% 30.50% 36.40% 40.50% 45.20% 51.34% 53.76% 56.40% 59.25% 65.00% 67.00% 69.00% 69.50% 70.20% 70.40% 70.60% 71.05% 71.15% 71.75% 71.85% 71.98% 72.05% 72.30% 73.57% 74.05% 74.29% 75.20% 76.10% 77.00% 77.81% 78.50% 78.80% 80.30% 81.53% 82.83% 83.93% 85.93%
6(14) Roads Handed Over
PHOTOGRAPHS – NE 1
45
Asphalting at Ch. 3+550Road No. 04
ABC Compacting at Ch. 2+300Road No. 12
Asphalting at Ch. 1+900Road No. 05
Details of Contract Package – NE2
Contractor : Sierra Construction Ltd
Contract amount : Rs. 1,242 Millions
No of Roads : 14 Roads
Total Roads Length : 36.21 km
Start Date : 17th December 2015
Original Completion Date : 16th December 2017
EOT Granted : EOT 1&3 (Approved) EOT 4 (Under Evaluation)
Revised date of completion : 22 June 2018 30 March 2019
46
47
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
Cum. Plan % 0.27% 1.60% 4.10% 7.81% 11.97% 16.75% 21.63% 26.42% 31.14% 36.26% 41.82% 47.79% 53.89% 59.74% 65.58% 72.12% 78.63% 84.66% 89.20% 92.34% 95.14% 97.82% 99.25% 99.62% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.10% 0.71% 3.79% 6.49% 9.22% 13.54% 16.08% 24.00% 32.10% 40.00% 51.00% 57.00% 63.00% 67.00% 69.00% 72.00% 75.00% 78.00% 80.00% 83.00% 86.00% 88.00% 89.00% 92.00% 94.00% 95.00% 96.00% 97.00% 97.00% 98.00% 99.00% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Actual % 0.10% 0.71% 3.79% 6.49% 9.22% 13.54% 16.08% 24.00% 32.10% 40.00% 51.00% 57.00% 63.00% 67.00% 69.00% 72.00% 75.00% 78.00% 80.00% 83.00% 86.00% 88.00% 89.00% 92.00% 94.00% 95.00% 96.00% 97.00% 97.00% 98.00% 98.10% 98.40% 98.70% 99.00% 99.40% 99.50% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
14(14) Roads Handed Over
Details of Contract Package – NE3
Contractor : Sierra Construction Ltd
Contract amount : Rs. 2,070 Millions
No of Roads : 15 Roads
Total Roads Length : 65.53 km
Start Date : 17th December 2015
Original Completion Date : 16th December 2017
EOT Granted : EOT 1&3 (Approved) EOT 4 to 6(Under Evaluation)
Revised date of completion : 9 August 2018 30 September 2019
48
49
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
Cum. Initial Plan % 0.53% 1.51% 2.81% 4.00% 5.41% 6.73% 9.89% 14.97% 20.96% 26.65% 33.06% 39.76% 46.28% 53.00% 60.04% 67.26% 74.60% 81.85% 87.73% 92.68% 95.88% 97.49% 98.74% 99.73% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 1 % 0.00% 0.00% 0.09% 0.71% 2.23% 7.13% 12.02% 17.12% 22.67% 28.75% 34.87% 41.30% 47.68% 53.87% 60.25% 65.30% 68.87% 75.25% 80.48% 86.08% 91.95% 95.99% 99.23% 99.89% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % 0.00% 0.00% 0.09% 0.71% 2.23% 3.81% 6.56% 12.60% 23.56% 30.56% 36.89% 44.00% 46.92% 53.81% 59.18% 64.17% 66.95% 68.98% 71.99% 77.12% 79.86% 81.93% 83.71% 84.79% 85.80% 88.34% 90.75% 93.93% 95.23% 96.37% 97.68% 98.96% 99.98% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 3 % 0.00% 0.00% 0.09% 0.71% 2.23% 3.81% 6.56% 12.60% 23.56% 30.56% 36.89% 44.00% 46.92% 53.81% 59.18% 64.17% 66.95% 68.98% 71.99% 77.12% 79.86% 81.93% 83.71% 84.79% 85.80% 87.08% 88.14% 89.15% 89.91% 90.52% 91.20% 91.71% 92.12% 93.52% 95.62% 97.92% 99.42% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 4 % - 31.01.2019 0.00% 0.00% 0.09% 0.71% 2.23% 3.81% 6.56% 12.60% 23.56% 30.56% 36.89% 44.00% 46.92% 53.81% 59.18% 64.17% 66.95% 68.98% 71.99% 77.12% 79.86% 81.93% 83.71% 84.79% 85.80% 87.08% 88.14% 89.15% 89.91% 90.52% 91.20% 91.71% 92.12% 92.52% 92.82% 93.13% 93.48% 94.46% 95.63% 96.80% 97.78% 98.69% 99.28% 99.67% 100.00% 100.00%
Cum. Revised Plan 5 % - 30.06.2019 0.00% 0.00% 0.09% 0.71% 2.23% 3.81% 6.56% 14.86% 23.56% 30.56% 36.89% 44.00% 46.92% 53.81% 59.18% 64.17% 66.95% 68.98% 74.00% 77.12% 79.86% 81.93% 83.71% 84.79% 85.80% 87.08% 88.14% 89.15% 89.91% 90.52% 91.20% 91.71% 92.12% 92.52% 92.82% 93.13% 93.48% 93.80% 94.17% 94.78% 95.14% 96.65% 97.77% 98.69% 99.47% 100.00%
Cum. Actual % 0.00% 0.00% 0.09% 0.71% 2.23% 3.81% 6.56% 12.60% 23.56% 30.56% 36.89% 44.00% 46.92% 53.81% 59.18% 64.17% 66.95% 68.98% 71.99% 77.12% 79.86% 81.93% 83.71% 84.79% 85.80% 87.08% 88.14% 89.15% 89.91% 90.52% 91.20% 91.71% 92.12% 92.52% 92.82% 93.13% 93.48% 93.80% 94.17% 94.78% 95.14% 95.76% 96.81% 97.91% 98.61% 98.89%
9(15) Roads Handed Over
Issues
• None performing contracts▪MA1 Package has identified as a none performing
contract
▪Contractor : KD Ebert and Sons Holding (pvt) Ltd.▪Present Physical Progress : 66.49%▪17.62 km Surfacing to be done (3.67 km Surfacing done
through other Contractors due to Public Complaints)
50
Progress of Urgent Road Maintenance Work
51
Progress of Urgent Road Maintenance Works of Non-Performing Contracts – PIC 03(September 2019)
52
NoNon-Performing
Contract Pkg
Road Maintenance
Works Undertaken
by Contract
No. of Roads to be
Maintained
No. of Roads In
Progress
1 MA 1 KA 3 18 17
Performance Based Maintenance (PBM) Central Province
53
Details of Handed Over Roads (Central Province / up to 30 September 2019)
54
District Package
No.Contractor
No. of Handed
Over Roads (Total
No. of Roads)
Handed Over Length
(Total Road Length) /
(km)
KA 01 Sierra Construction (Pvt.)Ltd. 14 (17) 57.00 (75.24)
KA 02 Sierra Construction (Pvt.)Ltd. 15 (17) 58.44 (72.48)
KA 03 Edward and Christie. 16 (16) 69.34 (69.34)
MA 02 Edward and Christie. 14 (14) 55.55 (55.55)
MA 03 CML-MTD Construction limited 18 (18) 60.76 (60.76)
NE 01 Sierra Construction (Pvt.)Ltd. 6 (14) 20.74 (72.40)
NE 02 Sierra Construction (Pvt.)Ltd. 14 (14) 36.96 (36.96)
NE 03 Sierra Construction (Pvt.)Ltd. 9 (15) 42.20 (66.12)
106 (125) 400.99 (508.26)
Kandy
Matale
Nuwara-Eliya
Total
Cost of Accommodating Public Complaints - Central Province (up to 30 September 2019)
55
Dis
tric
t
Package No. Name of the ContractorTotal No. of Complaints
Accommodating Cost
Kan
dy
KA 01 Sierra Construction (Pvt.) Ltd. 665,886,351.54
KA 02 Sierra Construction (Pvt.) Ltd. 10921,974,212.33
KA 03 Edward and Christie. 697,736,637.00
Mat
ale
MA 01KD Ebert and Sons
Holdings(Pvt) Ltd.80
1,850,000.00
MA 02 Edward and Christie. 361,250,000.00
MA 03 CML-MTD Construction limited 452,425,000.00
Nu
war
a El
iya NE 01 Sierra Construction (Pvt.) Ltd. 239
-
NE 02 Sierra Construction (Pvt.) Ltd. 304,522,992.49
NE 03 Sierra Construction (Pvt.) Ltd. 1038,224,800.00
Total 77753,869,993.36
Summary of Training Programmes / Workshops Conducted by iRoad-PIC 03 up to 30 September 2019
56
Male Female Total
1 Workshop on Environment and Social Consideration 4 63 22 85
2 Workshop on Contract Administration in Construction Supervision 1 68 12 80
3 Workshop on Road Investigation and Pavement Design 1 57 4 61
4 Workshop on Social Safeguard and Environment Progress, ADB Mission 2 106 19 125
5 Workshop on Social Safeguard Concept in iRoad Programme 1 67 14 81
6 Workshop on Calculation of Physical Progress using MS Project 2 39 46 85
7 Identification workshop on Co-operate Social Responsibility Programme 1 43 4 47
8 Awareness workshop on Environment and Social Safeguard 2 98 14 112
9 Awareness workshop for Local Government and Provincial Council Officers 6 447 75 522
10 Awareness Workshop on Road Safety for Drivers of PIU and PIC 2 108 - 108
11Workshop on Interpretation of FIDIC Contract Documents and Overview of
Contract Claims2 81 7 88
12 Workshop on Road Pavement Design 1 67 3 70
13 Workshop on Approval Process of Borrow Materials 1 72 13 85
14 Workshop on Preparation of Quality IPC 1 77 24 101
15Awareness workshop on monitoring environmental & safegurad activities using by
excel spread sheet and GIS package2 46 4 50
16 Workshop on Preparation of As Build Drawings 1 80 3 83
17 Workshop on PBM (CP, SG, Kandy,Matale & Nuwara Eliya Districts) 5 243 92 335
35 1762 356 2118
No. Name of the Programme
No. of
Programmes
held
Participants
Total
Cost to Completion
57
• Cost to Completion (Revision 06) Prepared and forwarded to the Employer.
Statement at Completion (SAC)
• Statement at Completion for Contract MA2 have been completed.• Statement at Completion for Contract MA3 have being prepared by the
Engineer and will be completed in October 2019.• Statement at Completion for Contract KA3 have been submitted by the
Contractor and being checked by the Engineer.
Environmental Safeguard activities
• Environmental field inspections and checking, environmental monitoring check lists have been conducted by Contractors, PIU and PIC Environmental and Social Safeguard Specialists, on all active sites.
Progress of Environmental Safeguard Activities (Sabaragamuwa & Central Provinces and Kalutara District)
58
Submission of the EMAP
• EMAPs were submitted and acceptation was given for these all 18 EMAPs by PIC up to the month
Submission of the EMC up to the month
• 340 EMCs at design and preconstruction stage
• 230 EMCs at 25% construction stage
• 167 EMCs at 50% construction stage
• 158 EMCs at 75% construction stage
• 93 EMCs at 100% construction stage
• 80 EMCs at post construction stage
Details of Removal and Planting of Trees in all Contracts up to the end of September 2019
Package Contractor Total Trees Removed
Total Trees Planted
KA1 Sierra Construction (Pvt) Ltd 42 132
KA2 Sierra Construction (Pvt) Ltd 104 177
KA3 Edward and Christie (Pvt) Ltd 272 370
MA1 K D Ebert and Sons Holdings (Pvt) Ltd 23 109
MA2 Edward and Christie (Pvt) Ltd 10 50
MA3 CML-MTD Construction (Pvt) Ltd 100 586
NE1 Sierra Construction (Pvt) Ltd 63 213
NE2 Sierra Construction (Pvt) Ltd None 50
NE3 Sierra Construction (Pvt) Ltd 32 300Total 646 7964
• 646 trees were removed up to this month in all Packages
• 1,938 trees have to be planted for those removed trees.
• 1,987 trees have already planted by MA1(109), MA2(50), MA3 (586),KA1(132) KA2(177), KA3(370), NE1(213), NE2(50), NE3(300)
GPS Points of Tree Planted Locations in Central Province
60
61
Progress of Safeguard Social Consideration(Central Province)
Field visit with Project Director of Central Province & Team Leader in ADB Mission at Hitihegama- Polgahawatta - Minuwandeniya Road (Road ID. 33) on 23.09.2019 at NE3 Package in
Nuwaraeliya District
62
Progress of the Safeguard Social ConsiderationEstablishment of Grievances Redressing Committees (GRCs) in
Divisional Secretariat & Grama Niladhari Levels – Central ProvinceP
rov
ince/
Dis
tric
t
Package
No.Name of the Contractor
Total No.
of DSDs
DSD LevelTotal No.
of GNDs
GND Level
EstablishedTo be
EstablishedEstablished
To be
Established
Cen
tral P
rov
inc
e
KA 01 Sierra Construction (Pvt.) Ltd. 6 6 0 57 57 0
KA 02 Sierra Construction (Pvt.) Ltd. 6 6 0 20 20 0
KA 03 Edward and Christie. 7 7 0 56 56 0
MA 01 KD Ebert and Sons Holdings(Pvt) Ltd. 3 3 0 34 34 0
MA 02 Edward and Christie. 3 3 0 29 29 0
MA 03 CML-MTD Construction limited 5 5 0 19 19 0
NE 01 Sierra Construction (Pvt.) Ltd. 2 2 0 14 14 0
NE 02 Sierra Construction (Pvt.) Ltd. 2 2 0 18 18 0
NE 03 Sierra Construction (Pvt.) Ltd. 2 2 0 15 15 0
Total 36 36 0 262 262 00
Grievance Redress Committees (GRC) formation completed in Central Province
63
Progress of Civil Works Contracts
up to 30th September 2019
ASIAN DEVELOPMENT BANK FUNDED INTERGRATED ROAD INVESTMENT PROGRAM-1
SABARAGAMUWA PROVINCE
64
Project Location Map-Sabaragamuwa Province
Package No. DistrictNo. of Roads
Road Length (km)
KE01
Kegalle.
12 74.75
KE 02 21 78.25
KE 03 25 64.00
R 01
Ratnapura
12 82.95
R 02 14 91.70
R 03 17 80.35
Total 101 472.00
65
Project Profile-Sabaragamuwa Province
Funding Agency Asian Development Bank (ADB)
Total Cost 11,849 Million
Cumulative Expenditure 7,123 Million
Cumulative Physical Progress 78.24%
Total Length 472.00 km
Location Sabaragamuwa Province ( Kegalle and Rathnapura Districts)
Contract Packages 06 Nos (Only 3 Nos are performing)
Consultant Egis-CEA Joint Venture
66
Overall Financial Progress
Last Month
31-August-2019 (Rs. Mn.)
Reporting Month
30-September-2019 (Rs. Mn.)
Allocation Actual Allocation Actual
11,762.11 7,067.34 11,841.30 7,122.83
67
Overall Physical Progress
Last Month %
(August-2019)
Reporting Month %
(September-2019)
Next Month %
(October 2019)
Target Actual Target Actual Target
99.5 78.06 99.86 78.24 100.00
List of the Packages under the Project
68
Package No. Contractor
Accepted Contract
Amount/ (Rs. Million)
No. of Roads
Actual Road Paving Length
(km)Remarks
KE 01 KD Ebert 1,973 17 74.65
Works suspended by the contractor
KE 02 Nawaloka 1,817 21 78.09 In Progress
KE 03 Nawaloka 1,632 25 67.62 In Progress
R 01 KD Ebert 2,022 12 80.63Works suspended by the
contractor
R 02 KD Ebert 2,384 14 92.24Works suspended by the
contractor
R 03 R. R. Construction 1,973 17 74.65 100% Completed
Total / Avg. 11,849 101 474.24 78.24%
Overall Physical Progress Summary - Sabaragamuwa Province/(up to 30 September 2019)
69
Package No. Contractor
Accepted Contract
Amount/ (Rs. Million)
No. of Roads
Actual Road Paving Length
/ (km)
Cumulative Physical Progress up to 31 August 2019 (%)
Cumulative Physical Progressup to 30 September 2019 (%)
Target (Revised) Actual
KE 01 KD Ebert 1,973 17 74.65 53.18% 100.00*(100.00)% 53.18%
KE 02 Nawaloka 1,817 21 78.09 98.60% 100.00*(100.00)% 98.71%
KE 03 Nawaloka 1,632 25 67.62 93.83% 100.00*(99.18)% 94.85%
R 01 KD Ebert 2,022 12 80.63 64.54% 100.00*(100.00)% 64.54%
R 02 KD Ebert 2,384 14 92.24 58.18% 100.00*(100.00)% 58.18%
R 03 R.R. Const. 2,021 12 81.01 100.00% 100.00*(100.00)% 100.00%
Total / Avg. 11,849 101 474.24 78.06% 99.86% 78.24%**
** - By considering non-performing contracts. Without considering them, the value is 96.78%
70
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19
Cum. Plan % 0.02% 0.09% 0.23% 0.85% 2.59% 5.43% 9.28% 13.77% 17.94% 21.95% 23.66% 26.14% 32.42% 39.52% 45.92% 52.71% 56.07% 62.48% 68.95% 75.01% 81.67% 87.46% 92.35% 95.76% 97.73% 99.02% 99.58% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Rev. Plan 1% 0.02% 0.08% 0.34% 0.83% 1.50% 2.56% 4.51% 7.84% 10.71% 14.01% 18.86% 24.33% 29.11% 35.65% 39.89% 44.46% 46.74% 49.22% 50.82% 52.29% 53.13% 54.01% 54.69% 55.24% 56.27% 58.16% 60.89% 64.37% 67.57% 71.40% 75.15% 79.02% 83.00% 87.17% 90.91% 94.16% 96.77% 98.23% 99.40% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Rev. Plan 2% 0.02% 0.08% 0.34% 0.83% 1.50% 2.56% 4.51% 7.84% 10.71% 14.01% 18.86% 24.33% 29.11% 35.65% 39.89% 44.46% 46.74% 49.22% 50.82% 52.29% 53.13% 54.01% 54.69% 55.24% 56.27% 58.16% 60.89% 64.37% 67.57% 71.40% 75.15% 79.02% 83.00% 85.97% 88.58% 90.97% 92.94% 93.88% 94.81% 95.81% 96.55% 97.39% 98.11% 98.77% 99.50% 99.86% 100.00%
Cum. Actual % 0.02% 0.08% 0.34% 0.83% 1.50% 2.56% 4.51% 7.84% 10.71% 14.01% 18.86% 24.15% 28.90% 35.00% 40.07% 44.55% 46.65% 49.22% 50.83% 52.29% 53.13% 54.01% 54.69% 55.24% 56.27% 58.00% 60.11% 62.49% 63.40% 65.13% 66.58% 67.55% 68.43% 69.50% 70.31% 71.24% 72.26% 73.20% 74.03% 75.12% 75.55% 76.44% 77.22% 77.75% 78.06% 78.24%
Package wise Progress-KE1
• Start Date : 17.12.2015
• End Date : 16.12.2017
• Contract Amount : Rs. 1,973 Millions
• Contractor : KD Ebert and Sons Holdings (Pvt.) Limited
• Cumulative Physical progress : 53.18%
• EOT Granted : Up to 20th May 2018
EOT-1 – 8 days, EOT-2 -06 days
• Present Status : Work suspended due to internal cash flow issue of the
Contractor.
72
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
Cum. Plan % 0.00% 0.00% 0.41% 1.74% 4.30% 8.74% 13.50% 18.27% 23.13% 28.26% 33.39% 38.52% 43.65% 48.78% 53.91% 59.04% 64.17% 69.30% 74.43% 79.56% 84.64% 89.47% 94.23% 98.23% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan % 0.00% 0.00% 0.12% 0.66% 1.41% 2.01% 4.21% 7.81% 11.91% 15.11% 21.42% 27.87% 33.07% 39.96% 46.84% 53.72% 58.92% 65.80% 72.68% 79.56% 84.64% 89.47% 94.23% 98.23% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan 2 % -
07.03.20180.00% 0.00% 0.12% 0.66% 1.41% 2.01% 4.21% 7.81% 11.91% 15.11% 20.24% 24.78% 29.39% 35.04% 40.20% 43.26% 45.43% 47.10% 47.74% 47.89% 47.89% 47.89% 47.99% 47.99% 47.99% 49.01% 51.32% 55.23% 58.04% 62.56% 67.99% 74.18% 80.59% 86.96% 92.91% 96.95% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Actual % 0.00% 0.00% 0.12% 0.66% 1.41% 2.01% 4.21% 7.81% 11.91% 15.11% 20.24% 24.78% 29.39% 35.04% 40.20% 43.26% 45.43% 47.10% 47.74% 47.89% 47.89% 47.89% 47.99% 47.99% 47.99% 48.87% 49.85% 50.97% 51.26% 52.10% 52.88% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18% 53.18%
Reasons for Delay - KE1
Delay of work due to cash flow issues of the Contractor.
Contract amount : Rs. 1,973 M
Balance works to be done : Rs. 1,008 M
The Engineer has given recommendation to terminate the Contractor.
Package wise Progress-KE2
• Start Date : 29.03.2016
• End Date : 28.03.2018
• Contract Amount : Rs. 1,816,999,270.80
• Cumulative Physical progress : 98.71%
• Contractor : Nawaloka Construction Co. (Pvt) Ltd
• EOT : Up to 30th September 2019
EOT-1 – 150 days, EOT-2 -413 days
Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
Cum. Plan % 0.00% 1.00% 1.00% 2.00% 4.00% 7.00% 12.00% 17.00% 24.00% 31.00% 38.00% 44.00% 51.00% 56.00% 61.00% 67.00% 72.00% 78.00% 84.00% 89.00% 94.00% 96.00% 97.00% 98.00% 99.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 1 % 0.00% 0.00% 0.00% 1.00% 2.00% 3.00% 4.40% 8.80% 14.14% 18.90% 25.60% 31.10% 37.20% 42.27% 47.62% 53.60% 61.38% 69.56% 77.69% 85.45% 90.78% 94.60% 97.49% 98.88% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 2 % 0.00% 0.00% 0.00% 1.00% 2.00% 2.70% 4.40% 8.80% 14.14% 17.73% 22.22% 26.19% 29.33% 30.44% 34.00% 35.94% 37.69% 39.54% 41.66% 45.69% 51.56% 58.47% 66.43% 73.25% 80.17% 86.48% 92.69% 96.95% 99.23% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 3 % 0.00% 0.00% 0.00% 1.00% 2.00% 2.70% 4.40% 8.80% 14.14% 17.73% 22.22% 26.19% 29.33% 30.44% 34.00% 35.94% 37.69% 39.54% 41.66% 43.36% 44.44% 46.14% 49.32% 53.35% 57.48% 60.39% 64.21% 67.55% 70.56% 75.45% 80.45% 85.68% 90.02% 93.76% 96.35% 98.10% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 4 % 0.00% 0.00% 0.00% 1.00% 2.00% 2.70% 4.40% 8.80% 14.14% 17.73% 22.22% 26.19% 29.33% 30.44% 34.00% 35.94% 37.69% 39.54% 41.66% 43.36% 44.44% 46.14% 49.32% 53.35% 57.48% 60.39% 64.21% 67.55% 70.56% 73.56% 77.04% 79.89% 83.22% 85.92% 88.72% 91.34% 93.94% 96.23% 97.63% 98.39% 98.99% 99.23% 100.00%
Cum. Actual % 0.00% 0.00% 0.00% 1.00% 2.00% 2.70% 4.40% 8.80% 14.14% 17.73% 22.22% 26.19% 29.33% 30.44% 34.00% 35.94% 37.69% 39.54% 41.66% 43.36% 44.44% 46.14% 49.32% 53.35% 57.48% 60.39% 64.21% 67.55% 70.56% 73.56% 77.04% 79.89% 83.22% 85.92% 88.72% 91.07% 93.94% 95.34% 97.07% 98.16% 98.44% 98.60% 98.71%
Package wise Progress-KE3
• Start Date : 29.03.2016
• End Date : 28.03.2018
• Contract Amount : Rs. 1,632,455,502.54
• Cumulative Physical progress : 94.85%
• Contractor : Nawaloka Construction Co. (Pvt) Ltd
EOT-1 – 174 days, EOT-2 -384 days
• EOT : Up to 31st October 2019
77
Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19
Cum. Initial Plan % 0.00% 0.00% 1.00% 2.00% 2.00% 4.00% 8.00% 13.00% 18.00% 23.00% 29.00% 35.00% 40.00% 46.00% 52.00% 58.00% 63.00% 69.00% 75.00% 80.00% 86.00% 91.00% 94.00% 97.00% 98.00% 99.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan -1 % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 3.00% 7.51% 12.83% 17.76% 22.11% 27.60% 31.02% 35.60% 40.81% 46.08% 52.10% 58.31% 65.47% 72.97% 80.04% 86.86% 91.77% 96.64% 98.61% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan -2 % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 2.50% 3.80% 6.10% 11.40% 15.70% 21.93% 26.10% 30.00% 30.76% 32.26% 32.88% 34.50% 36.18% 37.60% 41.18% 47.10% 53.70% 60.87% 66.68% 73.11% 79.58% 85.50% 91.26% 96.45% 99.70% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan -3 % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 2.50% 3.80% 6.10% 11.40% 15.70% 21.93% 26.10% 30.00% 30.76% 32.26% 32.88% 34.50% 36.19% 37.60% 39.19% 40.83% 42.45% 45.09% 47.91% 50.88% 51.78% 54.18% 56.41% 58.88% 61.13% 67.87% 74.25% 80.60% 86.85% 93.03% 98.28% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised Plan -4 % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 2.50% 3.80% 6.10% 11.40% 15.70% 21.93% 26.10% 30.00% 30.76% 32.26% 32.88% 34.50% 36.19% 37.60% 39.19% 40.83% 42.45% 45.09% 47.91% 50.88% 51.78% 54.18% 56.41% 58.88% 61.13% 64.05% 66.05% 68.29% 71.72% 74.57% 77.53% 80.90% 84.05% 87.33% 90.59% 93.78% 96.96% 100.00% 100.00%
Cum. Revised Plan -5 % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 2.50% 3.80% 6.10% 11.40% 15.70% 21.93% 26.10% 30.00% 30.76% 32.26% 32.88% 34.50% 36.18% 37.60% 39.19% 40.83% 42.45% 45.09% 47.91% 50.88% 51.78% 54.18% 56.41% 58.88% 61.13% 64.05% 66.05% 68.29% 71.72% 74.57% 77.53% 80.90% 83.07% 86.68% 90.28% 93.61% 97.76% 99.18% 100.00%
Cum. Actual % 0.00% 0.00% 0.00% 0.00% 1.00% 2.00% 2.50% 3.80% 6.10% 11.40% 15.70% 21.93% 26.10% 30.00% 30.76% 32.26% 32.88% 34.50% 36.18% 37.60% 39.19% 40.83% 42.45% 45.09% 47.91% 50.88% 51.78% 54.18% 56.41% 58.88% 61.13% 64.05% 66.05% 68.29% 71.72% 74.57% 77.53% 80.90% 82.07% 85.65% 89.26% 92.18% 93.83% 94.85%
Package wise Progress-R1
• Start Date : 17.12.2015
• End Date : 16.12.2017
• Contract Amount : Rs. 2,022 Millions
• Cumulative Physical progress : 64.54%
• Contractor : KD Ebert and Sons Holdings (Pvt.) Limited
• EOT : Up to 04th January 2019
• EOT-1 – 384 days
• Present Status : Work suspended due to internal cash flow issue of the Contractor.
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
Cum. Plan % 0.06% 0.30% 0.71% 1.36% 4.55% 8.65% 14.42% 19.81% 24.42% 29.06% 34.22% 40.47% 46.48% 53.52% 61.10% 68.28% 74.87% 80.97% 86.50% 90.93% 94.23% 97.27% 99.34% 99.95% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 1 % 0.06% 0.30% 0.87% 1.86% 2.69% 4.12% 5.94% 9.62% 11.33% 15.58% 21.01% 27.38% 33.77% 39.69% 45.20% 52.63% 58.14% 64.77% 72.19% 79.45% 86.37% 92.39% 96.64% 99.39% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 2 % 0.06% 0.30% 0.87% 1.86% 2.69% 4.12% 5.94% 9.62% 11.33% 17.02% 22.78% 27.45% 31.60% 38.88% 44.37% 49.04% 50.45% 53.96% 55.01% 55.51% 55.51% 55.51% 55.51% 55.51% 55.51% 58.64% 61.75% 65.90% 70.63% 75.32% 79.63% 83.42% 86.76% 89.51% 92.83% 97.36% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Actual % 0.06% 0.30% 0.87% 1.86% 2.69% 4.12% 5.94% 9.62% 11.33% 17.02% 22.78% 27.45% 31.60% 38.88% 44.37% 49.04% 50.45% 53.96% 55.01% 55.51% 55.51% 55.51% 55.51% 55.51% 55.51% 57.80% 61.23% 62.79% 63.02% 64.00% 64.52% 64.53% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54% 64.54%
Reasons for Delay - R1
Delay of work due to cash flow issues of the Contractor.
Contract amount : Rs. 2,022 M
Balance works to be done : Rs. 1,006 M
The Engineer has given recommendation to terminate the Contractor.
Package wise Progress-R2
• Start Date : 17.12.2015
• End Date : 16.12.2017
• Contract Amount : Rs. 2,384 Millions
• Cumulative Physical progress : 58.18%
• Contractor : KD Ebert and Sons Holdings (Pvt.) Limited
• EOT : Up to 03rd September 2019
EOT-1 – 358 days
• Present Status : Work suspended due to internal cash flow issue of the Contractor.
Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
Cum. Initial Plan % 0.00% 0.00% 0.00% 0.54% 1.64% 4.73% 10.54% 16.98% 23.04% 29.84% 36.12% 41.99% 48.89% 56.30% 61.56% 67.00% 71.16% 77.29% 82.67% 87.81% 93.60% 97.32% 99.42% 99.99% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 1 % 0.00% 0.00% 0.50% 0.92% 1.08% 1.32% 3.36% 7.43% 11.10% 15.13% 19.54% 24.14% 28.97% 35.49% 42.07% 51.24% 56.87% 64.64% 72.18% 79.38% 87.14% 94.04% 98.25% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Revised - 2 % 0.00% 0.00% 0.50% 0.92% 1.08% 1.32% 3.36% 7.43% 11.10% 15.13% 18.58% 23.51% 27.10% 31.35% 35.16% 40.49% 43.41% 45.68% 46.53% 46.66% 46.66% 46.66% 46.86% 46.86% 46.86% 47.24% 51.26% 56.89% 64.66% 72.20% 79.39% 87.14% 94.04% 98.25% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Cum. Actual % 0.00% 0.00% 0.50% 0.92% 1.08% 1.32% 3.36% 7.43% 11.10% 15.13% 18.58% 23.51% 27.10% 31.35% 35.16% 40.49% 43.41% 45.68% 46.53% 46.66% 46.66% 46.66% 46.86% 46.86% 46.86% 47.24% 48.55% 52.95% 54.04% 56.35% 58.17% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18% 58.18%
Reasons for Delay – R2
Delay of work due to cash flow issues of the Contractor.
Contract amount : Rs. 2,384 M
Balance works to be done : Rs. 1,229 M
The Engineer has given recommendation to terminate the Contractor.
Package wise Progress-R3
• Start Date : 17th December 2015
• End Date : 16th December 2017
• Contract Amount : Rs. 2,021 Millions
• Contractor : R.R. Construction(Pvt) Ltd
• EOT : Up to 8th October 2018
Construction works Completed
Package NoContractor
Accepted Contract Amount
(Rs. Million)
Total Certified Amount (Mobilization Advance)
(Rs. Million)
R 01 KD Ebert and Sons Holdings(Pvt) Ltd. 2,022 1,016.11 (327.65)
R 02 KD Ebert and Sons Holdings(Pvt) Ltd. 2,384 1,154.65 (419.02)
R 03 R.R. Construction (Pvt) Ltd. 2,021 1,997.12(0.00)
KE 01 KD Ebert and Sons Holdings(Pvt) Ltd. 1,973 964.67 (334. 50)
KE 02 Nawaloka Construction Co. (Pvt) Ltd. 1,817 1,523.88 (10.81)
KE 03 Nawaloka Construction Co. (Pvt) Ltd. 1,632 1,203.55 (104.00)
Total 11,849 7,860.08 (1,195.97)
Overall Financial Status –iROAD-Sabaragamuwa Province /(up to 30 September 2019)
ISSUES
• Urgent maintenance works of roads in nonperforming Contracts, KE1, R1 and R2, are done by Contractors of R3, KE2 and KE3
• Due to the prevailing rainy weather in last two months, work progress was reduced and couldn’t achieve set targets of KE2 & KE3.
• KE2 and KE3 Contractor faced cash flow issues. Therefore, ESCROW accounts have been opened for those two packages.
Performance Based Maintenance (PBM) Sabaragamuwa Province
87
Details of Handed Over Roads to Provincial Director RDA, Sabaragamuwa Province(up to 30 September 2019)
88
District Package
No.Contractor
No. of Handed Over
Roads (Total No. of
Roads)
Handed Over Length
(Total Road Length) /
(km)
Ratnapura R3 R R Construction (Pvt.)Ltd. 12 (12) 81.01 (81.01)
KE2Nawaloka Construction Co. (Pvt)
Ltd.9(21) 22.47 (78.10)
KE3Nawaloka Construction Co. (Pvt)
Ltd.5 (25) 8.64 (67.74)
26(58) 112.12 (226.85)Total
Kegalle
iRoad - North Western ProvinceProject Steering Committee Meeting No.32
29th October 2019
Overall Physical Progress of the Project
Last Month (%) Reporting Month (%) Next Month (%)
Target Actual Target Actual Target
3.56 1.51 1.68 0.10 -
(Program of the total packages)
Overall Financial Progress of the Project
Last Month (Rs.) Reporting Month (Rs.)
Allocation Expenditure Allocation Expenditure
- 83,968,809.61 - 87,491,546.07
List of the packages under the project Contra
ct Packag
e
Contractor Remarks
KU 01 Maga Engineering 100% Completed. PBM under operation through Provincial Director – NWP.
KU 02 K.D.A. Weerasinghe – BMG Joint Venture
100% Completed. PBM under operation through Provincial Director - NWP.
KU 03 Terminated w.e.f. 2019.02.26, A case filed for guarantee encashment. Rebidding process in progress.
KU 04 V.V. Karunarathne & CompanyAwaiting ADB’s concurrence for Employer’s Termination.
KU 05 Terminated w.e.f. 2019.02.26, A case filed for guarantee encashment. Rebidding process in progress.
PU 01 Ranken Railway Constructions Finishing works are in progress.
PU 02 Terminated w.e.f. 2019.08.02 – Cabinet decision has to be revoked for rebidding.
PU 03 V.V. Karunarathne & CompanyAwaiting ADB’s concurrence for Employer’s Termination.
Progress
Contract Package
Financial (%) Physical (%)
Planned Achieved Planned Achieved
KU 02 0.60 0.93 0.01 0.01
KU 04 4.68 0.00 4.63 0.00
PU 01 0.49 0.31 0.4 0.3
PU 03 - - - -
Package wise Program
• Package No :- KU1
• Start Date :- 01.08.2016
• End Date :- 31.01.2019
• Contract Amount :- Rs. 2,005,790,082.72
• Contractor :- Maga Engineering (Pvt) Ltd
• EOT :- EOT 1 – 6 months
Package wise Program
• Package No :- KU2
• Start Date :- 01.08.2016
• End Date :- 15.09.2019
• Contract Amount :- Rs. 2,124,166,266.00
• Contractor :- KDA Weerasinghe – BMG Joint Venture
• Cumulative Physical Progress :- 100%
• EOT :- EOT 1 - 241 Calendar days
EOT 2 - 39.5 Calendar days
EOT 3 - 130 Calendar days
Package wise Program
• Package No :- KU4
• Start Date :- 01.08.2016
• End Date :- 30.09.2019
• Contract Amount :- Rs. 2,091,174,540.00
• Contractor :- VV Karunarathna & Co.
• Cumulative Physical progress :- 55.2%
• EOT :- EOT 1 – 14 months.
All sites are abandoned since April 2019
Reasons for delay
KU4 – VVK
Delay of work due to cash flow issues of the Contractor.
Contract amount :- Rs. 2,091,174,540.00
Balance works to be done :- Rs. 1,146,447,391.82
Package wise Program• Package No :- PU1
• Start Date :- 01.08.2016
• End Date :- 29.10.2019
• Contract Amount :- Rs. 1,706,320,523.61
• Contractor :- Ranken Railway Constructions.
• Cumulative Physical progress :- 98.2%
• EOT :- EOT 1 - 273 Calendar days
EOT 2 - 88 Calendar days
EOT 3 - 94 Calendar days
Delay in finishing works and handing over roads
Package wise Program• Package No :- PU3
• Start Date :- 01.08.2016
• End Date :- 29.05.2019
• Contract Amount :- Rs. 1,210,355,904.00
• Contractor :- VV Karunarathna & Co
• Cumulative Physical progress :- 60.0%
• EOT :- EOT 1 - 184 Calendar days
EOT 2 - 118 Calendar days
All sites are abandoned since April 2019
Reasons for delay
PU3 – VVK
Delay of work due to cash flow issues.
Contract amount :- Rs. 1,210,355,904.00
Balance work to be done :- Rs. 376,484,682.47
ISSUES• Emergency works in terminated Contract PU2 are to be attended by the
Contractor of PU1.
• Attending emergency works and safety requirements in Contract Packages KU4 & PU3 are to be attended by the contractor of PU1.
• Routine maintenance and making roads motorable in Contract Packages KU4,PU2 & PU3 are still unsolved.
• Some of the emergency works in KU4 has to be done with the help of Pradeshiya Sabha and Public.
Abandoned causeway construction
Ihalagama Junction to Nochchiya across Wannikudawewa Road – RD ID 07
After temporary reinstatement
Ihalagama Junction to Nochchiya across Wannikudawewa Road – RD ID 07
Abandoned culvert construction
Palugolla Iginimitiya Road (Aluthgama Kotawehera Road ) – RD ID 27
After temporary reinstatement
Palugolla Iginimitiya Road (Aluthgama Kotawehera Road) – RD ID 27
Thank You…