3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

Embed Size (px)

Citation preview

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    1/146

    10

    00

    0-(31/80) 4000-PMT-1EG-000-Z

      PAGE 1 OF146

    PROJECT NO. 3538-200 3538-200-10-RT-045

    KHALDA PETROLUM COMPANY

    PRE-COMMISSIONING PROCEDURE

    FOR 

    QASR COMPRESSION PROECT

    !ESTERN DESERT " EGYPT

    1  21/05/2

    014  FINAL ISSUE A.S H.M W.E

    0 13/04/#014 ISSUED FOR APPRO$AL SM RK RK  

    REV DATE REVISIONS BY CH'D APPR

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    2/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 272 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    TA'LE OF CONTENTS

    1.0 INTRODUCTION…………………………….........................................................................4

    2.0 DEFINITIONS………………………….............................................................................5

    3.0 PRE-COMMISSIONING ORGANIZATION.....................................................................7

    4.0 ACTIVITIES BOARDER………………….........................................................................8

    5.0 SSTEMIZATION…………………...................................................................................!

    5.1 GENERA"………………………………………………………………………….. .!

    5.2 NUMBERING SSTEM............................................................................................!

    5.3 PRE-COMMISSIONING SSTEMS……………………………………………….10

    6.0 SSTEMSPERIORITIES……..………………………………………………………….14

    7.0 PRE-COMMISSIONING PROCEDURES.........................................................................16

    7.1 GENERA" PROCEDURE……………………………….........................................16

    7.2 SSTEM PROCEDURE…………………………...................................................17

    7.3 MAIN PRE-COMMISSIONING ACTIVITIES........................................................18

    7.4 MAIN PRE-COMMISSIONING C#EC$S..............................................................18

    7.5 SE%UENTIA" COMP"ETION F"O& C#ART......................................................47

    8.0 CONFORMIT C#EC$ OF T#E P"ANT'S E%UIPMENT.............................................4!

    !.0 SSTEM DOCUMENTS………………….......................................................................4!

    10.0 PROGRESS MONITORING……………........................................................................50

    11.0 PUNC# "ISTING………………....................................................................................50

    12.0 STEPS TO AC#IEVE MEC#ANICA" COMP"ETION AND MEC#ANICA"

    COMP"ETION CERTIFICATE (MCC)………….................................................................51

    13.0 #SE PROCEDURE………………..................................................................................53

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    3/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 372 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    14.0 SSTEMS COMPONENT "IST………..........................................................................54

    15.0 ATTAC#MENTS……………………...........................................................................140

    ATTAC#MENT 1 MAR$ED UP P*ID+,

    ATTAC#MENT 2 PRE-COMMISSIONING C#EC$ FORMS

    ATTAC#MENT 3 PUNC# "IST FORM

    ATTAC#MENT 4 MEC#ANICA" COMP"ETION CERTIFICATE

    ATTAC#MENT 5 CA"IBRATION CERTIFICATE

    ATTAC#MENT 6 "OOP C#EC$ S#EET

    ATTAC#MENT 7 TUBING TEST CERTIFICATE

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    4/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 472 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    1&0 INTRODUCTION

    T, P/-,, P// , 9 :/:/ 9; ENPPI  => :/?, ,== / ,?/?=; ? ?, ://, /

    ? :/-,, :, < ? :=?.

    T :/:, < ?, ? , ? ,/9 ? ,:

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    5/146

    1

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 572 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    #&0 DEFINITIONS

    P-*+,,..+

    M

    A,, :/, == M ? :/-

    ,, ?>?, &? == >=> :/?,

    ?= R; ,:/9= :/? < :=?=9=

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    6/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 672 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    R29 F+ C+,,..+

    T :=? / :/? ?/< , R; 9 :=?

    =; /?? : =,? / ? /

    ?=;.

    KI,, = :=? /?

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    7/146

    1

    KPC

    PLANT

    MANAGER 

    ENPPI

    CONSTRUCTION MANAGER 

    C+.*+ A...*

    T,

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 772 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    3&0 PRE-COMMISSIONING ORGANIZATION

    KPC

    OPERATION

    TEAM QA/QC

    ENGINEER  

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    8/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 872 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    4&0 ACTI$ITIES 'OARDER 

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    9/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE !72 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    :&0 SYSTEMIZATION

    :&1 G6

    T 9= ,? :=? < ? :/J? ? ?/ ?

    :/?= ,?, 9, ? / / 9,, ? =? 9/ ,;,? ?, ?

    >/ ? ?/= ?? , ? ,? ::/:/? 9 < ,? :=? , ? 9= ? / / ? 9 :=?,, ,?/? : ,@?= // , ?? ? ,?/?-: ,=

     :/? ?/?, 9 ?.

    T :=? , > ? ,;,?, , :/ ? =,? := /

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    10/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 1072 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    :&3 PRE-COMMISSIONING SYSTEMS

    :&3&1 TIE-IN SYSTEMS

    SYSTEM NO& DESCRIPTION

    .80.TI.001 EISTING PRODUCTION SEPARATOR TIE IN SSTEM %A-V-3002A

    .80. TI.002 EISTING PRODUCTION SEPARATOR TIE IN SSTEM %A-V-3002B

    .80. TI.003 EISTING PRODUCTION SEPARATOR TIE IN SSTEM %A-V-3002C

    .80. TI.004 EISTING PRODUCTION SEPARATOR TIE IN SSTEM %A-V-4002A

    .80. TI.005 EISTING PRODUCTION SEPARATOR TIE IN SSTEM %A-V-4002B

    .80. TI.006 P#ASE I GAS MANIFO"D TIE IN

    .80. TI.007 P#ASE II GAS MANIFO"D TIE IN

    .80. TI.008 BPASS B"O& DO&N "INES TIE IN SSTEM

    .80. TI.00! P#ASE I #P F"ARE $O DRUM %A-V-3002 TIE IN SATEM

    .80. TI.010 P#ASE I CO"D VENT TIE IN SSTEM

    .80. TI.011 P#ASE II CO"D VENT TIE IN SSTEM

    .80. TI.012 MET#ANO" AND DISTREBUTION TIE IN SSTEM

    .80. TI.013 P#ASE I INSTRUMENT AIR SSTEM

    .80. TI.014 P#ASE II B"AC$ START FUE" GAS TIE IN SSTEM

    .80. TI.015 P#ASE I B"AC$ START FUE" GAS TIE IN SSTEM

    .80. TI.016 P#ASE II #P F"ARE $O DRUM %A-V-4004 TIE IN SSTEM

    .80. TI.017 NE& MPU TIE IN SSTEM

    .80. TI.018 NE& DIESE" TRANSFER PUMP %A-P-8020

    .80. TI.01! TIE IN TO T#E EISTING 11 $V S&G %A-"-8004

    .80. TI.020 PMS TIE IN RE"ATED TO EISTING 11 $V S&G %A-"-8001

    :&3 PROCESS SYSTEMS

    SYSTEM NO& DESCRIPTION

    .80.P.001 COMPRESSOR IN"ET MANIFO"D

    .80.P.002 COMPRESSOR SUCTION DRUM TRAIN-A (%A-V-8001A) SSTEM

    .80.P.003 COMPRESSOR TRAIN-A (%A-$-8001A) SSTEM

    .80.P.004 COMPRESSOR DISC#ARE COO"ER TRAIN-A (%A-E-8001A) SSTEM

    .80.P.005 COMPRESSOR DISC#ARE DRUM TRAIN-A (%A-V-8002A) SSTEM.80.P.006 COMPRESSOR DISC#ARGE MANIFO"D SSTEM

    .80.P.007 COMPRESSOR SUCTION DRUM TRAIN-B (%A-V-8001B) SSTEM

    .80.P.008 COMPRESSOR TRAIN-B (%A-$-8001B) SSTEM

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    11/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 1172 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    .80.P.00! COMPRESSOR DISC#ARE COO"ER TRAIN-B (%A-E-8001B) SSTEM

    .80.P.010 COMPRESSOR DISC#ARE DRUM TRAIN-B (%A-V-8002B) SSTEM

    .80.P.011 COMPRESSOR SUCTION DRUM TRAIN-C (%A-V-8001C) SSTEM

    .80.P.012 COMPRESSOR TRAIN-C (%A-$-8001C) SSTEM

    .80.P.013 COMPRESSOR DISC#ARE COO"ER TRAIN-C (%A-E-8001C) SSTEM

    .80.P.014 COMPRESSOR DISC#ARE DRUM TRAIN-C (%A-V-8002C) SSTEM

    .80.P.015 COMPRESSOR SUCTION DRUM TRAIN-D (%A-V-8001D) SSTEM

    .80.P.016 COMPRESSOR TRAIN-D (%A-$-8001D) SSTEM

    .80.P.017 COMPRESSOR DISC#ARE COO"ER TRAIN-D (%A-E-8001D) SSTEM

    .80.P.018 COMPRESSOR DISC#ARE DRUM TRAIN-D (%A-V-8002D) SSTEM

    .80.P.01! CONDENSATE SUCTION MANIFO"D

    .80.P.020 CONDENSATE SUCTION DRUMS %A-V-8005A SSTEM AND PROCESS GAS BA"A

    .80.P.021 CONDENSATE SUCTION DRUMS %A-V-8005 B SSTEM

    .80.P.022 CONDENSATE EPOET PUMPS %A-P-8003 ABC SSTEM

    :&3&3 UTILITY SYSTEMS

    .80.U.001 AIR GENERATION PAC$AGE A%A-$-8002A SSTEM

    .80.U. 002 AIR GENERATION PAC$AGE A%A-$-8002B SSTEM

    .80.U. 003 AIR GENERATION PAC$AGE A%A-$-8002C SSTEM

    .80.U. 004 AIR DRER PAC$AGE %A-A-8005A SSTEM

    .80.U.005 AIR DRER PAC$AGE %A-A-8005B SSTEM

    .80.U.006 UTI"IT AIR RECEIVER %A-V-800! SSTEM

    .80.U.007 INSTRUMENT AIR RECEIVER %A-V-8010 SSTEM

    .80.U.008 UTI"IT STATION P"ANT AIR DISTRIBUTION SSTEM

    .80.U.00! INSTRUMENT AIR DISTRIBUTION SSTEM

    .80.U.010 NITROGEN GENERATION PAC$AGE %A-A-8003 SSTEM

    .80.U.011 NITROGEN DISTRIBUTION SSTEM

    .80.U.012 UTI"IT STATION P"ANT NITROGEN DISTRIBUTION SSTEM

    .80.U.013 NITROGEN RECIVER COMPRESSOR AND "ETDO&N PAC$AGE

    .80.U.014 #P FUE" F"AS# GAS PRE-#EATER FEED

    .80.U.015 #.P. FUE" GAS SSTEM

    .80.U.016 #.P FUE" GAS PRE-#EATER SSTEM

    .80.U.017 #.P FUE" GAS SUPER #EATER AND CONSUMERS

    .80.U.018 #.P FUE" GAS FI"TERS

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    12/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 1272 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    .80.U.01! ".P FUE" GAS BAC$-UP #EATER 

    .80.U.020 ".P FUE" GAS SCRUBBER 

    .80.U.021 #.P F"ARE CO""ECTION AND ".P SOURCE TO CO"D VENT

    .80.U.022 C"OSED DRAIN CO""ECTION

    .80.U.023 C"OSED DRAIN DRUM

    .80.U.024 C"OSED DRAIN DRUM PUMPS

    .80.U.025 C"OSED DRAIN TRANSFER PUMPS

    .80.U.026 NE& EMERGNC DEISE" GENERATOR 

    .80.U.027 POTAB"E &ATER SSTEM DISTRIBUTION SSTEM

    .80.U.028 POTAB"E &ATER SODIUM #POC#"ORITE INECTION PAC$AGE

    .80.U.02! SANITAR SE&AGE "IFTING PUMP AND CO""ECTION SUMP

    .80.U.030 SANITAR SE&AGE TREATMENT PAC$AGE

    .80.U.031 TREATED SANITAR &ATER 

    .80.U.032 FIRE&ATER SODIUM #POC#"ORITE INECTION PAC$AGE

    .80.U.033 FIRE&ATER STORAGE TAN$ 

    .80.U.034 FIRE&ATER OC$R PUMPS

    .80.U.035 FIRE&ATER DEISE" TAN$S AND PUMPS

    .80.U.036 FIRE&ATER NET&OR$ * E%UIPMENT

    .80.U.037 P#ASE I C"OSED DRAIN DRUM PUMP

    .80.U.038 P#ASE II C"OSED DRAIN DRUM PUMP

    -80-U-03! #VAC S;,?

    -80-U-040 GASEOUS ETINGUIS#ING SSTEM

    -80-U-041 SAFET E%UIPMENT SSTEM

    -80-U-042 CAT#ODIC PROTECTION SSTEM

    :&3&4 ELECTERICAL SYSTEMS

    SYSTEM NO&DESCRIPTION

    -80-U-043P/ T/,

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    13/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 1372 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    -80-U-046S== P/ D,?/9? P=

    -80-U-047"TG A S== P/ S;,?

    -80-U-048R;, A S::/?,

    -80-U-04!G/

    -80-U-050B??/; A B??/; C// A,,9=,

    -80-U-051U?//:?9= P/ S::=; ( UPS) S;,?

    -80-U-052"? S;,?

    -80-U-053E,? MV S?/ M?/ C?/= G/ 

    -80-U-054"V B, B/ T/

    -80-U-055MV B, B/ T/

    -80-U-056P/

    -80-U-058S:/>,/; D?= C?/= S;,? (SDCS)

    -80-U-05!11 V S?/ 

    :&3&: INSTRUMENTATION SYSTEMS

    SYSTEM NO&DESCRIPTION

    -80-U-060ESD SSTEM M C9=,

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    14/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 1472 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    -80-U-061DCS SSTEM M C9=, (PCS ,? < DCS)

    -80-U-062V9/? M?/ S;,? (VMS)

    -80-U-063F*G SSTEM M C9=,

    :&3&= TELECOMMUNICATION SYSTEMS

    SYSTEM NO&DESCRIPTION

    -80-U-064PAGE PART SSTEM

    -80-U-065PRIVET AUTOMATIC BRANC# EC#ANGE SSTEM (PAB)

    NOTES>

    1. T 9/; 9? ?=?; ,;,?, ,?/9? ,;,?, (.. ?=?; / / …?) ,

    =? ? ? =,? 9= >=> ? ,;,? P*ID.

    2. S::=/, :/-,, =,?, ?/ :/? =, ? 9 ,

    J? ? ENPPI :/-,, =,?,.

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    15/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 1572 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    =&0 SYSTEMS PRIORITIES

    T ,;,?, ,== 9 ://?H ? ?, ? :=? H ?

    ? /@/ ,/; ?= ?/= ,;,? (SDCS).

    17. C? :/?? ,;,?.

    #) I.,+ S9.,. P+.>

    1. ESD ,;,? 9=,.

    2. DCS ,;,? 9=, (PCS ,? < DCS).3. V9/? ?/ ,;,? (VMS).

    3) U6. 2 T-I. S9.,. P+.>

    1. N I,?/? * ?=?; / ,;,?

    2. E,? ,?/? / ,;,? ?-.

    3. N D,= ,;,?.

    4. ,? ,= ,;,? ?-.

    5. F/ &?/ S;,?

    6. F*G S;,?7. N #P"P

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    16/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 1672 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    11. N?/ /? ,?/9? ,;,?.

    12. C=, / ,;,?.

    13. E,? ?= ,;,? ?-.

    14. P?9= ?/ ,?/9? ,;,?.

    15. S?/; , ,;,?.

    16. P, I*II =, / / :: ,;,?.

    4) P+*.. 2 T-I. S9.,. P+.>

    1. E,? :/? ,:/?/, (P, III) ?-,

    2. P, III G,

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    17/146

    1

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 1772 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ?&0 PRE-COMMISSIONING PROCEDURES

    ?&1 G6 P+*2

    T :/-,, ?, == 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    18/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 1872 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ?&3 M P-C+,,..+ A*7.

     T G/= :/-,, ?>?, < ? ,;,? / ? 9=.

    •&?,, &?/ F=,

    •&?,, A/ B=

    •"9 O= F=,

    •P*ID', /, B C=9/?

    •I,?/? 9=, / ??; ,

    •E=?/= 9=, / ??; ,

    • E=?/= ::=, / (ACC ?/, :/,,/ ?/, /?/

    ?/, ?).

    •I,?/? ?/= =:,

    •E=?/= ,;,?, E/H? (SS 9??/; // UPS E/; :/

    ,::=;...?.)

    •T=? 9=, / ??; ,

    •F9/ :?, 9=  

    •S?? @:? E?/=?/= ,:? * 9 :

    •P/C=-=?

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    19/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 1!72 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ?&4 M P-C+,,..+ C*.

    ?&4&1 $..6.

     

    V/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    20/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 2072 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ?&4 P5

    V/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    21/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 2172 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ?&4&3 $ENDOR SKID INSTALLATION

    V/? ?/=.

    F?, = 9=?  .

    !C , , =>= * == (/ ::=9=).

    8C , /.

    "C 9??/; =? ?://; ?/=, ( / /@/ ? ?/=,

    R> ?://; 9=,

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    22/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 2272 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    8I,?== ?://; ,?//, 9;:,,, (&/ ::=9=).

    "C PSV', ,?== //?=; ?.

    10C =9 = ::, :: : //?=; (&/ ::=9=).

    11C =9 = =/ =

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    23/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 2372 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    1Refer to supplier operating and aintenan!e anual "#i!#

    in!lude all !opressor do!uents and dra"ings.

    2Ad$ust le%eling of t#e !opressor s&id "it# referen!e to t#e

    !on!rete foundation.

    3'#e!& t#e alignent of !oupling #u(s on !opressor and gear

    (o) output s#aft (efore and after t#e !onne!tion of pro!esspiping *as per supplier re!oendation+.

    4Pre!ision le%eling of t#e gas tur(ine and appli!ation of supplier

    instru!tion regarding an!#or (olt asse(l, installation and

    grouting.

    5Align t#e parallelis of t#e !oupling #u( fa!es *as per supplier

    re!oendation+.

    '#e!& t#e dire!tion of rotation of t#e otors for t#e !opressor

    pa!&age au)iliar,.

    !Perfor t#e oil -us#ing and !#e!& t#e !leanliness of oil s,ste

    *(,passing t#e (earing+.

    8'#arge t#e /rst /ll of lu(ri!ating oil.

    "'#e!& t#e set point of all alar and s#ut do"n s"it!#es.

    1

    0

    perfor t#e se0uen!e !#e!& of !ontrol s,ste *su!tiondis!#arge anti surge %al%es+

    1

    1'#e!& t#e fun!tion of ES pus# (utton on panel.

    1

    2'#e!& t#e fun!tion of lo" lu(e oil pressure s"it!#.

    1

    3

    Start grouting of !opressor (ase plate using nons#rin&ageepo), grout. All !on!rete top surfa!es ust (e !o%ered "it#

    grout2 e%en if not underneat# s&id.

    1

    4

    3u(e oil !ooler is ounted on steel stru!ture supplied loose to(e asse(led. A sall %ent pipe is !onne!ting top of !ooler to

    gas tur(ine reser%oir *as deeed ne!essar, (, t#e gas tur(ineanufa!turer+. lu(e oil !ooler fan otor asse(l, ust (e

    greased and free to rotate (, #and

    1

    5

    Ensure good alignent (et"een otor and fan pulle,s2 unlessfans are dire!tl, dri%en (, otor.

    1

    nstallation of seal air !ooler "it# inter!onne!ting piping andoisture drain pipe2 if appli!a(le.

    1

    !

    nstallation of !o(ustion air /lter2 eleents2 -e)i(le eleent2e)#aust fans to e)pel sand laden air25 et!.

    1

    8nstallation of en!losure %entilation s,ste.

    1"

    nstallation of /re/g#ting s,ste2 'O !,linders !a(inet2 piping2

    inside en!losure gas dete!tors on !opressor s&id ... Et!.nter!onne!ting 'O piping ust (e St.St. 784 or 716 as a

    iniu.

    2

    0

    nstallation of fuel gas /lter9#eater *!onditioning+ s&id "it#inter!onne!ting piping.

    2

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    24/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 2472 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    !.4. TURBINE DRIVERS 

    :erif, and !#e!& t#e follo"ing;

    1Ad$ust le%eling of t#e tur(ine s&id "it# referen!e to t#e !on!retefoundation.

    2'#e!& t#e alignent of !oupling #u(s on tur(ine and gear (o)output s#aft (efore and after t#e !onne!tion of pro!ess piping

    *as per supplier re!oendation+.

    3Align t#e parallelis of t#e !oupling #u( fa!es *as per supplierre!oendation+.

    4'#e!& t#e dire!tion of rotation of t#e otors for t#e tur(inepa!&age au)iliar,.

    5'#e!& t#e set point of all alar and s#ut do"n s"it!#es

    Perfor t#e se0uen!e !#e!& of !ontrol s,ste *su!tion dis!#arge anti surge %al%es+

    !'#e!& t#e fun!tion of ES pus# (utton on panel.

    8'#e!& t#e fun!tion of all prote!tions of t#e tur(ine.

    ":erif, %endor site do!uentation is !oplete and atta!#ed.

    10'#e!& against dra"ings2 spe!s and data s#eets.

    11Reo%e preser%ation aterials *"#ere appli!a(le+.

    1#'#e!& lu(e 9seal oil reser%oirs are !lean < free fro de(ris.

    13Fill reser%oirs "it# -us#ing oil *Per %endors re!oendations+

    14nstall teporar, -us#ing strainers "#ere appli!a(le.

    1:Fill lu(e 9 seal oil s,stes "it# !orre!t oil after -us#ing *perlu(ri!ation s!#edule+

    1='#e!& lu(e 9 seal oil pups !orre!tl, piped up.

    1?'#e!& lu(e.9 seal oil !oolers free fro o(stru!tion

    18'#e!& #,drauli! oil pup piped up !orre!tl, *W#ere appli!a(le+.

    1B'#e!& #,drauli! oil !ooler !lean < free fro o(stru!tion *f appli!a(le+.

    #0'#e!& seal oil pups are piped up !orre!tl, *W#ere appli!a(le+.

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    25/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 2572 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    #1'#e!& seal oil !ooler !lean < free fro o(stru!tion *W#ereappli!a(le+

    ##'#e!& eergen!, lu(e 9 seal oil pup piped up !orre!tl, *"#ereappli!a(le+

    #3'#e!& eergen!, lu(e oil !ooler !lean < free fro o(stru!tion *f appli!a(le+

    #4'#e!& all lo!al instruents !orre!tl, installed.

    #:'#e!& fuel lines < %al%es are piped up !orre!tl,.

    #='#e!& starter gas lines < %al%es are piped up !orre!tl, *if appli!a(le+.

    #?'#e!& air inta&e /lters installed !orre!tl,.

    #8'#e!& en!losure fans and %ents free fro o(stru!tion.

    #B!#e!& /re 9 gas dete!tors installed !orre!tl,

    30!#e!& tur(ine en!losure installed !orre!tl,

    31!#ei!al !leaning of lu(e oil < F.G. piping !opleted

    3#Operation and aintenan!e a!!ess satisfa!tor,.

    ?&4&? INSTRUMENT / UTLITY AIR COMPRESSOR SYSTEM

    V/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    26/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 2672 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    I?/? ,=, 9? ? : P"C ? ICS , :/:/=;

    ?

    !C : ?, :=?,, ,? >/ ?,.

    V=>, ,?/?, ,? 9 ?.

    C =?/ :/ ?, ? ?/= := == ?/,.

    8C ? 9=?, ??

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    27/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 2772 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    N+ >

    &? / />/ , :/ 9; :/,,/ ?= ? , :/> >/; =. P: ? /;/

    / :/ :// ? ?? ? / ? /;/, /

    ?/ ?, / ? :// ? :/ ? ,?/? / /. &? / /

    ,== =, 9 :/ :// ? >= :/ < ,9 /,. T , ,== 9 ::=

    ? /; / ,9 ? ,9-,9 /, ? == >= ,/ ?- ?,.

    ?&4&8 DIESEL ENGINE

    V/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    28/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 2872 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    V/9= =>, ,=; ,,9= :/9= / ?

     ::.

    A,,9=?; < =/; :: ?/=,.

     NPS# /@/?,.

    B, :=? /? :=?

    P/ ,::=; ? :: ?/ , ,?==.

    C ?? ?/ /?? , //?.

    A@? , ? / :: , >=9=.

    P:, />/, = //?=;.

    C >=>, < :/:/ ?;: ,?== //? /?.A== : /,

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    29/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 2!72 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    V/? ?/=,.

    5A== /=< >=>, ,?==

    C = ?/= =/, (/ ::=9=)

    !C ,? * ,/ >=>, ,?== //?=; (/ ::=9=)

    8C ,? ,?// (,?== ?://; ,?// < /@/).

    "C ,/ /?/ >=> ,?== //?=; (/ ::=9=).

    10I,?== =9 = /?/ ? ? (/ ::=9=)

    1C / =, / 9,?/?

    1!C :=,? :/, ,?== (/ ::=9=).

    18C ,?/?, ,?==

    1"O:/? ? ,, ,?,

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    30/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 3072 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    2C / , ,?::

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    31/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 3172 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    5Filters !#e!& *(ag and Pre/lters+

    '#e!& t#e spa!e (et"een pa!&aged units as per anufa!ture

    !atalogue.

    !'#e!& t#e e%aporator !oil and /ns.

    8'#e!& t#e po"er and !ontrol !a(les as per anufa!turing "iring

    diagra.

    "'#e!& t#e du!t insulation and !ladding as per E=PP

    spe!i/!ations.

    10'#e!& t#e dire!tion of t#e rotation of t#e fan.

    ?&4&14 ACCUMULATORS PULSATION DAMPERS INSTALLATION

    V/? ?/=.

    5C >? = ,

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    32/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 3272 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    2C DBSE //? * //

    3C * =? ,

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    33/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 3372 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ?&4&1= $ 2 P.. R6@ 

    V/=>,.

    P/,,/ S, (PSV) 9 =9/? (P: ?,?)

    /,?/.

    T.S.O. =,,=>, ??,, ?,?.

    ?&4&1? I., 2 U69 A

    V/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    34/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 3472 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    2T? < 9= 9=?, 9= ?: =/ (? =,, ? >/

    /?, )

    3A=? < ?/ /> :==; ? 9=, / ? ?:/?/ ,.

    8A== ? ?9

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    35/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 3572 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    C9= //, / ? / ?,.

    C ,:? < ?/?, / ? /

    ?, S::=/ /?.

    #  

    ?&4&1B&3 GROUNDING (F+ ,+ 26. . 6**6 ,**6 *+,56+ 2 5-

    *+,,..+ **. @+ +2 EL-33 A)

    C ,:? ? / ,;,? ?,.

    C

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    36/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 3672 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ,: ?/ :/:/ /? ,??.

    C ? :, ,@ :=/?; < == @:?

    F?= < == ?/ ,?/?/, /? 9//,' /,

    ?

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    37/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 3772 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    38/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 3872 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ?&4 I.,+

    ?&4&1 E5, C* 

    I,?/? @:? ? 9 ,:? ? ,:

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    39/146

    1

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 3!72 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ?&4&3 P@+, L++5 C*.

    T :/:, < ?, , , ? ,/ ?? ? ,?/?, =>,...) / //?=; =9/? ? /,, ? ? PCS ESD ,;,?,.

    T = (/,==) 9? ? ,?/? ? PCS ESD / ,9-,;,? ==

     9 ,?9=, ? ?, :,. T ?,? , :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    40/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 4072 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ? /? ?? ,9J? ? ? = ?,?.

    P? = ?,? , 1.1 ?, ? , :/,,/.

    ?&4&? PS$ C6;+

    A== PSV', ,== 9 9 ?,? =9/? / ? ? /=>? API

    / ,. C:/,, / ,== 9 /==; , PSV , ,? / ?

    ,:

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    41/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 4172 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    S?=,, S?= ?9 ?, /

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    42/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 4272 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ": , / /@/ ? ,/ ?? ? :=? = :?, ? ,;,?

    ,? 9 ,?== .

    ?&4&4 I.66+ C* 

    C ?? == >, / ,?== / ? ? ,?==? / < ? ,;,?

    ,::=/.

    ?&4# TELECOM SYSTEM

    ?&4#&1 P / P9 S9.,

    ?&4# P/>? A?? B/ E S;,? (PAB)

    ?&4#&3 F9/ O:? C9=

    ?&4 CATHODIC PROTECTION SYSTEM

    C ?? ? //? >=,

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    43/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 4372 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ?&4 F6. O '6+ T P6

    I? , :/?? ? :=? ,= ? // == ? :/:/?/; :/?, ? -/? ?

    /, , ?? ?; :=; ? ? >/== ,, ,=.

     

    S== :, < == ,= = / ,?9, = ,:??/ ,=? ::/ ?/ 

    9/, / ,?, >9=; =

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    44/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 4472 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    - V,,=, ? -,?/, / ; ?/ ?/=, ,? 9

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    45/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 4572 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ?&4= P-*+,,..+ C* F+, L.&

    ?&4&11&1 EQUIPMENT CHECK FORMS

    DESCRIPTION CHECK LIST NO&

    C?/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    46/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 4672 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    EPANSION AND COMPRESSION TAN$S #V-11 A

    DAMPERS #V-12 A

    DUCT&OR$S #V-13 A

    AIR OUT"ETS #V-14 A

    FAN COI" UNITS #V-16 A

    PRIVET AUTOMATIC BRANC# EC#ANGE

    SSTEM TE-01-APUB"IC ADDRESS * GENERA" A"ARM

    SSTEMTE-02-A

    FIBER OPTICS CAB"E TE-04-A

    DATA COMMUNICATION SSTEM TE-0!-A

    C?/= V=>, * R=?/ IC-02-A

    S? * B= V=> IC-03-A

    ? B IC-04-A

    P/,,/ -F= -">=-T:/?/ T/,??/ IC-05-A

    O/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    47/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 4772 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ?&4&11 ELECTRICAL CHECK FORMS

    F/ P/-,, C F/, /

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    48/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 4872 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ?&: S6 C+,56+ F6+ C

     

    E@:?

    E/? *P:

    I,?==?

    P: F=,

    C=

    C?,

    S;,?, D,,/,

    C:=?

    M=

    C:=?

    C/?

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    49/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 4!72 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    8&0 CONFORMITY CHECK OF THE PLANTS EQUIPMENT

    E ,;,? < ? P=? == 9 ,:? ?, /@/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    50/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 5072 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    10&0 PROGRESS MONITORING

    F/ ://,, ,/? // ? ://?H ? ,?/? ?>?, ? >

    = :=? < ? ,;,?, ? =:

    A. #;/-?,? =: ,??,.

    B. ":, /,??? ,??,.

    C. S;,?, MC ,??,.

    D. I?/= P =,? ,??,.

    E. P/-,, /, ,?, < ? P/J? (.. C?/?/

     :/J? ,:? :/? ? =,, :/>? ?.).

    T G/= ,?/?/ < ? P ",? == ? ? .

    • I, D.*5+ B/< :=? < ? ?/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    51/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 5172 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    // ? / ?/, ? ? =/=; ? ? /,:,9=?; ==?

    T ?, ?/, ? ? ? P//?; /

    ? C,?/? M/ P/-,, /) == 9 ?/H ,   I?, /@/ ? 9 :=? 9

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    52/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 5272 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    U: :=? < == ? 9> = :=? /@/?, C,?/?

    C?/?/ ,== ,, ? M= C:=? /?

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    53/146

    1

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 5372 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    13&0 HSE PROCEDURES

    T /,:,9=?, /=?, // #SE ? ? ,?/?-,? / =/; ?, == 9 ? :/===. F/ ?,

    /, ,:= ??? ,= 9 : ? ?

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    54/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 5472 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    R, ,,,,?, ,== 9 :/:/ 9?, /

    ? ? ?=> ? ,?9=, ? :/?, ? 9

    ?.

    14&0 SYSTEMS COMPONENT LIST

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    55/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 5572 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    56/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 5672 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    INSTRUMENTS

    CONTRO" VA"VES 80-FV-012B

    S#UTDO&N VA"VE 80-ESDV-018

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A05 A0! A

    INSTRUMENT

    CAB"ESIC-23 A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    57/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 5772 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

      A& GENERAL

      R

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    58/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 5872 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A05 A0! A

    INSTRUMENT

    CAB"ESIC-23 A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    59/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 5!72 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    M :=? P*ID ? ??= ,;,? ? ,/ ?? ? ,?==? ,

    //? , :/ 9> ? P*ID.

    INSTRUMENTS

    F"O& 80-FIT-013

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-05 A 0! A 06 A

    INSTRUMENT

    CAB"ESIC-23 A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    60/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 6072 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    61/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 6172 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    T :/-,, ,== 9 :/ ? P*ID.

    INSTRUMENTS

    T:/?/ 80-TT-045

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    62/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 6272 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    P/,,/ 80-PT-045

    F= 80-FT-045

    O; =;H/ 80-AIT-004

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A05 A0! A

    INSTRUMENT

    CAB"ESIC-23 A

    A=;H/, IC-18-A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    63/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 6372 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    64/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 6472 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    CAB"ES

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    65/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 6572 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 06 A

    INSTRUMENT

    CAB"ESIC-23 A

    ? P*ID.

    INSTRUMENTS

    F"O& 80-FI-024 AB

    TEMPRETURE 80-TIT-028

    PRESSURE 80-PIT-!02

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 06 A

    INSTRUMENT

    CAB"ESIC-23 A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    66/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 6672 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    T :/-,, ,== 9 :/ ? P*ID.

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    67/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 6772 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    C& CHECK FORMS

    PIPING MCRS-P*P-70070!711712

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    68/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 6872 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    C& CHECK FORMS

    "V SEITC#GEAR AND

    CONTRO" MOTOR

    CONTRO" CENTER 

    E"-04 A

     

    .04

    3538-200-$$D-12221 R>.04

    3538-200-$$D-12224 R>.04

    3538-200-$$D-12231 R>.04

    3538-200-$$D-12234 R>.04 3538-200-$$D-12241 R>.04

    3538-200-$$D-12244 R>.04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    69/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 6!72 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    80-TI-048

    PRESSURE 80-PG-!15

    80-PIT-0!1 AB

    80-PDIT-!06

    80-PDIT-!07

    RESTRICTED ORFICE 80-RO-013

    80-RO-018

    S#UTDO&N VA"VE 80-ESDV-030 AB

    80-ESDV-031 AB

    B"O&DO&N VA"VE 80-BDV-0010

    80-BDV-0010

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 0! A 06 A

    INSTRUMENT

    CAB"ESIC-23 A

    .04

    3538-200-$$D-12221 R>.04

    3538-200-$$D-12231 R>.04

    3538-200-$$D-12241 R>.04

    3538-200-$$D-12250 R>.05

    3538-200-$$D-12254 R>.05

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    70/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 7072 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    M :=? P*ID+, ? ??= ,;,? ? ,/ ?? ? ,?==? ,

    //? , :/ 9> ? P*ID+,.

    INSTRUMENTS

    TEMPERATURE 80-TIT-101

    80-TG-105

    80-TG-111

    PRESSURE 80-PDIT-101

    80-PDIT-121

    80-PG-103

    80-PG-106

    80-PG-107

    80-PG-103

    80-PDIT-108

    80-PIT-10!

    80-PIT-110

    "EVE" 80-"IT-101

    80-"IT-102

    80-"IT-107

    80-"G-103

    F"O& 80-FIT-102

    CONTRO" VA"VE 80-"V-102

    80-PV-123

    S#UTDO&N VA"VE 80-ESDV-101 AB

    80-ESDV-103

    SAFET VA"VES 80-PSV-105 AB

    C& CHECK FORMSPIPING PI-03-A 04-A

    INSTRUMENTSIC-03-A 05-A 0!-A 02-A 06-

    A

    INSTRUMENT

    CAB"ESIC-23-A

    VESSE" PV-06-A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    71/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 7172 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    .02

    3538-200-$$D-12213 R>.04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    72/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 7272 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    "EVE" 80-"G-102

    80-"IT-108

    80-"IT-10!

    80-"IT-110

    S#UTDO&N VA"VE 80-ESDV-10!

    CONTRO" VA"VES 80-"V-108

    80-AV-5167 TRAIN A

    SAFET VA"VES 80-PSV-114 AB

    F"AME ARRESTOR 80-FA-2121 TRAIN A

    80-FA-5177 TRAIN A

    80-FA-3270 TRAIN A

    B"O&DO&N VA"VE 80-BDV-101

    EQUIPMENT

    COMPRESSOR %A-$-8001A

    TURBINE %A-GT$-8001A

    COA"ESCING FI"TER F-2100FI"TER F-2106

    CO2 ETINGUIS#ING AS-6600 6601

    SEA" GAS TREATMENT

    S$ID

    "UBE OI" COO"ER 

    VENT SEPARATOR F-2370

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 0! A 02 A 06-A

    INSTRUMENT IC-23 A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    73/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 7372 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    CAB"ES

    VESSE" PV-06-A

    FI"TER PV-01-A

    E"ECTRIC #EATER PR-05-A

    F"AME ARRESTOR PR-11-A

    CENTRIFUGA" TURBO

    COMPRESSOR ME-08-A

    .04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    74/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 7472 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 0! A 02 A

    INSTRUMENT

    CAB"ESIC-23 A

    AIR COO"ER PR-18-A

    MOTOR E"-22-A

     .04

    3538-200-$$D-12234 R>.04

    3538-200-$$D-12244 R>.04

    3538-200-$$D-12221 R>.04

    3538-200-$$D-12241 R>.04

    3538-200-$$D-12312 R>.04

    3538-200-$$D-1235! R>.04

    3538-200-$$D-12360 R>.04

    3538-200-$$D-12361 R>.04

    3538-200-$$D-12362 R>.04

    3538-200-$$D-12363 R>.04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    75/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 7572 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    80-PDIT-122

    80-PG-117

    80-PG-11!

    80-PIT-064

    "EVE" 80-"IT-104 AB

    80-"IT-105

    80-"G-106

    CONTRO" VA"VES 80-FV-103

    80-"V-105

    S#UTDO&N VA"VE 80-ESDV-102 AB

    80-ESDV-104

    SAFET VA"VES 80-PSV-118 AB

    EQUIPMENT

    DISC#ARGE DRUM

    TRAIN A%A-V-8002A

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 0! A 02 A

    INSTRUMENT CAB"ES IC-23 A

    VESSE" PV-06-A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    76/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 7672 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    3538-200-$$D-12234 REV.04

    3538-200-$$D-12244 REV.04

    3538-200-$$D-12353 REV.04

    3538-200-$$D-12244 REV.04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    77/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 7772 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

      A& GENERAL

      R.04

    3538-200-$$D-12222 R>.04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    78/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 7872 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    S#UTDO&N VA"VE 80-ESDV-201 AB

    80-ESDV-203

    SAFET VA"VES 80-PSV-205 AB

    C& CHECK FORMS

    .02

    3538-200-$$D-12223 R>.04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    79/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 7!72 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    80-PT-5167 TRAIN B

    F"O& 80-FT-2108 TRAIN B

    RESTRECTION ORFICE 80-RO-201

    80-RO-203

    "EVE" 80-"G-202

    80-"IT-208

    80-"IT-20!

    80-"IT-210

    SPEED 80-SIT-201

    VIBRATION 80-VIT-201

    S#UTDO&N VA"VE 80-ESDV-20!

    CONTRO" VA"VES 80-"V-208

    80-AV-5167 TRAIN B

    SAFET VA"VES 80-PSV-214 AB

    B"O&DO&N VA"VE 80-BDV-201

    F"AME ARRESTOR 80-FA-2121 TRAIN A

    80-FA-5177 TRAIN A

    80-FA-3270 TRAIN A

    EQUIPMENT

    COMPRESSOR %A-$-8001B

    TURBINE %A-GT$-8001BCOA"ESCING FI"TER F-2100

    FI"TER F-2106

    CO2 ETINGUIS#ING AS-6600 6601

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    80/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 8072 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    SEA" GAS TREATMENT

    S$ID

    "UBE OI" COO"ER 

    VENT SEPARATOR F-2370

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 0! A 02 A 06-A

    INSTRUMENT

    CAB"ESIC-23 A

    VESSE" PV-06-A

    FI"TER PV-01-A

    E"ECTRIC #EATER PR-05-A

    F"AME ARRESTOR PR-11-A

    CENTRIFUGA" TURBO

    COMPRESSOR ME-08-A

    ? P*ID+,.

    INSTRUMENTS

    TEMPERATURE 80-TG-206 AB

    80-TIT-207

    80-TIT-208 ABC80-TIT-213A

    CONTRO" VA"VE 80-FV-204

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    81/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 8172 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    S&ITC# 80-VS##-202 ABCD

    E%UIPMENTS

    AIR COO"ER %A-E-8001B

    MOTOR 80-EM-8001BABBBCBD

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 0! A 02 A

    INSTRUMENT

    CAB"ESIC-23 A

    AIR COO"ER PR-18-A

    MOTOR E"-22-A

     

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    82/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 8272 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    "EVE" 80-"IT-204 AB

    80-"IT-205

    80-"G-206

    CONTRO" VA"VES 80-FV-203

    80-"V-205

    S#UTDO&N VA"VE 80-ESDV-202 AB

    80-ESDV-204

    SAFET VA"VES 80-PSV-218 AB

    EQUIPMENT

    DISC#ARGE DRUM

    TRAIN B%A-V-8002B

    C& CHECK FORMS

    PIPING PI-03-A 04-A

    INSTRUMENTSIC-03-A 05-A 0!-A 02-A 06-

    A

    INSTRUMENT

    CAB"ESIC-23-A

    VESSE" PV-06-A

    .04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    83/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 8372 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    INSTRUMENTS

    TEMPERATURE 80-TIT-301

    80-TG-305

    80-TG-311

    PRESSURE 80-PDIT-301

    80-PDIT-321

    80-PG-303

    80-PG-306

    80-PG-307

    80-PG-303

    80-PDIT-308

    80-PIT-30!

    80-PIT-310

    "EVE" 80-"IT-301

    80-"IT-302

    80-"IT-307

    80-"G-303

    F"O& 80-FIT-302

    CONTRO" VA"VE 80-"V-302

    80-PV-323

    S#UTDO&N VA"VE 80-ESDV-301 AB

    80-ESDV-303

    SAFET VA"VES 80-PSV-305 AB

    C& CHECK FORMS

    PIPING PI-03-A 04-A

    INSTRUMENTSIC-03-A 05-A 0!-A 02-A 06-

    A

    INSTRUMENT

    CAB"ESIC-23-A

    VESSE" PV-06-A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    84/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 8472 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    .02

    3538-200-$$D-12233 R>.04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    85/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 8572 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    VIBRATION 80-VIT-301

    S#UTDO&N VA"VE 80-ESDV-30!

    CONTRO" VA"VES 80-"V-308

    80-AV-5167 TRAIN C

    SAFET VA"VES 80-PSV-314 AB

    B"O&DO&N VA"VE 80-BDV-301

    F"AME ARRESTOR 80-FA-2121 TRAIN C

    80-FA-5177 TRAIN C

    80-FA-3270 TRAIN C

    EQUIPMENT

    COMPRESSOR %A-$-8001C

    TURBINE %A-GT$-8001C

    COA"ESCING FI"TER F-2100

    FI"TER F-2106

    CO2 ETINGUIS#ING AS-6600 6601

    SEA" GAS TREATMENT

    S$ID"UBE OI" COO"ER 

    VENT SEPARATOR F-2370

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 0! A 02 A 06-A

    INSTRUMENT

    CAB"ESIC-23 A

    VESSE" PV-06-A

    FI"TER PV-01-A

    E"ECTRIC #EATER PR-05-A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    86/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 8672 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    F"AME ARRESTOR PR-11-A

    CENTRIFUGA" TURBO

    COMPRESSOR ME-08-A

    .04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    87/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 8772 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    AIR COO"ER PR-18-A

    MOTOR E"-22-A

     

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    88/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 8872 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    DISC#ARGE DRUM

    TRAIN C%A-V-8002C

    C& CHECK FORMS

    PIPING PI-03-A 04-A

    INSTRUMENTSIC-03-A 05-A 0!-A 02-A 06-

    AINSTRUMENT

    CAB"ESIC-23-A

    VESSE" PV-06-A

    .04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    89/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 8!72 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    "EVE" 80-"IT-401

    80-"IT-402

    80-"IT-407

    80-"G-403

    F"O& 80-FIT-402

    CONTRO" VA"VE 80-"V-402 AB

    80-PV-423

    S#UTDO&N VA"VE 80-ESDV-401 AB

    80-ESDV-403

    SAFET VA"VES 80-PSV-405 AB

    C& CHECK FORMS

    .02

    3538-200-$$D-12243 R>.04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    90/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE !072 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    INSTRUMENTS

    TEMPERATURE 80-TIT-402

    80-TIT-403

    80-TIT-411

    80-TIT-410

    80-TG-404

    PRESSURE 80-PIT-411

    80-PIT-412

    80-PG-413

    80-PG-415

    80-PT-5167 TRAIN D

    F"O& 80-FT-2108 TRAIN D

    RESTRICTED ORFICE 80-RO-40180-RO-403

    "EVE" 80-"G-402

    80-"IT-408

    80-"IT-40!

    80-"IT-410

    SPEED 80-SIT-401

    VIBRATION 80-VIT-401

    S#UTDO&N VA"VE 80-ESDV-20!

    CONTRO" VA"VES 80-"V-408

    80-AV-5167

    SAFET VA"VES 80-PSV-414 AB

    B"O&DO&N VA"VE 80-BDV-401

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    91/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE !172 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    EQUIPMENT

    COMPRESSOR %A-$-8001D

    TURBINE %A-GT$-8001D

    COA"ESCING FI"TER F-2100

    FI"TER F-2106

    CO2 ETINGUIS#ING AS-6600 6601

    SEA" GAS TREATMENT

    S$ID

    "UBE OI" COO"ER 

    VENT SEPARATOR F-2370

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 0! A 02 A 06-A

    INSTRUMENT

    CAB"ES

    IC-23 A

    VESSE" PV-06-A

    FI"TER PV-01-A

    E"ECTRIC #EATER PR-05-A

    F"AME ARRESTOR PR-11-A

    CENTRIFUGA" TURBO

    COMPRESSOR ME-08-A

    .04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    92/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE !272 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    TEMPERATURE 80-TG-406 AB

    80-TIT-407

    80-TIT-408 ABC

    80-TIT-413A

    CONTRO" VA"VE 80-FV-404

    S&ITC# 80-VS##-402 ABCD

    E%UIPMENTS

    AIR COO"ER %A-E-8001D

    MOTOR %A-EM-8001 DADBDCDD

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 0! A 02 A

    INSTRUMENT

    CAB"ESIC-23 A

    AIR COO"ER PR-18-A

    MOTOR E"-22-A

     

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    93/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE !372 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    PRESSURE 80-PDG-408

    80-PDIT-402

    80-PDIT-422

    80-PG-417

    80-PG-41!

    "EVE" 80-"IT-404 AB

    80-"IT-405

    80-"G-406

    CONTRO" VA"VES 80-FV-403

    80-"V-405

    S#UTDO&N VA"VE 80-ESDV-402 AB

    80-ESDV-404

    SAFET VA"VES 80-PSV-418 AB

    EQUIPMENT

    DISC#ARGE DRUM

    TRAIN D%A-V-8002D

    C& CHECK FORMS

    PIPING PI-03-A 04-A

    INSTRUMENTSIC-03-A 05-A 0!-A 02-A 06-

    A

    INSTRUMENT

    CAB"ESIC-23-A

    VESSE" PV-06-A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    94/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE !472 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

      R.4

    3538-200-$$D-12250 R>.5

    3538-200-$$D-12254 R>.5

    3538-200-$$D-12353 R>.4

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    95/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE !572 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

      A& GENERAL

      R.5

    3538-200-$$D-12215 R>.4

    3538-200-$$D-12250 R>.5

    3538-200-$$D-12251 R>.5

    3538-200-$$D-12254 R>.5

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    96/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE !672 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    S#UTDO&N VA"VES 80-ESDV-001A

    80-ESDV-00! A

    80-ESDV-011 A

    80-ESDV-026 A

    B"O&DO&N VA"VES 80-BDV-001 A

    SAFET VA"VES 80-PSV-007 AB

    E%UIPMENT

    CONDENSATE

    SUCTION DRUM%A-V-8005 A

    D& CHECK FORMS

    PIPING PI-03-A 04-A

    INSTRUMENTSIC-03-A 05-A 0!-A 02-A 06-

    AINSTRUMENT

    CAB"ESIC-23-A

    VESSE" PV-06-A

    ? P*ID+,.

    INSTRUMENTS

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    97/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE !772 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    TEMPERATURE 80-TIT-001 B

    PRESSURE 80-PIT-002 B

    80-PG-001 B

    80-PG-005 B

    RESTRICTION ORFICE 80-R0-001 B

    "EVE" 80-"IT-001 B

    80-"IT-003 B

    80-"IT-016 B

    80-"IT-021 B

    80-"G-003 B

    80-"G-004 B

    CONTRO" VA"VES 80-"V-016 B

    S#UTDO&N VA"VES 80-ESDV-001 B

    80-ESDV-00! B

    80-ESDV-011 B

    80-ESDV-026 B

    B"O&DO&N VA"VES 80-BDV-001 B

    SAFET VA"VES 80-PSV-008 AB

    E%UIPMENT

    CONDENSATE

    SUCTION DRUM%A-V-8005 B

    C& CHECK FORMS

    PIPING PI-03-A 04-A

    INSTRUMENTSIC-03-A 05-A 0!-A 02-A 06-

    A

    INSTRUMENT

    CAB"ESIC-23-A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    98/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE !872 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    VESSE" PV-06-A

    ? P*ID.

    INSTRUMENTS

    PRESSURE 80-PIT-008ABC

    80-PIT-012ABC

    80-PIT-!18ABC

    80-PDIT-00!ABC

    80-PG-011ABC80-PG-!28

    80-PIT-

    TEMPERATURE 80-TIT-016ABC

    F"O& 80-FIT-001ABC

    80-FIT-01!ABC

    80-FIT-011AB

    VIBRATION 80-VT-002ABC

    80-VT-003ABC

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    99/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE !!72 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    SPEED 80-SIT-002ABC

    ON-OFF VA"VES 80-V-027ABC

    SAFET VA"VES 80-PSV-0!3ABC

    80-PSV-014

    CONTRO" VA"VES 80-FV-001ABC

    S#UTDO&N VA"VES 80-ESDV-014

    80-ESDV-036A

    80-ESDV-037A

    E%UIPMENT

    CONDENSATE EPORT

    PUMPS%A-P-8003ABC

    AUTOMATIC TOP UPUNIT

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 06 A

    INSTRUMENT

    CAB"ESIC-23 A

    PUMP ME-01 A

    VMS PANE"CABINET CONSO"

    IC-15 A

    MOTOR E"-22 A

    4&3 UTILITY SYSTEMS

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    100/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 10072 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    '& PIDS MECHANICAL CHECK 

    M :=? P*ID ? ??= ,;,? ? ,/ ?? ? ,?==? ,

    //? , :/ 9> ? P*ID.

    EQUIPMENT

    AIR GENERATION

    PAC$AGE%A-$-8002A

    F/ I*U A/ C:/,,/ (%A-$-8002A) : :/-,, ://

    /, :=, / ? P*ID.

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    101/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 10172 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    EQUIPMENT

    AIR GENERATION

    PAC$AGE%A-$-8002C

    F/ I*U A/ C:/,,/ (%A-$-8002C) : :/-,, ://

    /, :=, / ? P*ID.

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    102/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 10272 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    EQUIPMENT

    AIR DRER PAC$AGE 80-A-8005B

    F/ A/ D/;/ (80-A-8005B) : :/-,, :// /,

     :=, /

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    103/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 10372 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    CAB"ES

    VESSE" PV-06 A

    .04

    T :/-,, ,== 9 :/

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    104/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 10472 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    ? P*ID+,.

    INSTRUMENTS

    PRESSURE 80-PIT-06!

    S#UTDO&N VA"VE 80-ESDV-015

    C& CHECK FORMS

    PIPING PI 03 A04 A

    INSTRUMENTS IC-03 A 05 A 0! A

    INSTRUMENT

    CAB"ES

    IC-23 A

  • 8/18/2019 3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1

    105/146

       1   0   0   0   0  -   Z  -   0   0   0  -   G   E   1  -   T   M   P  -   0   0   0   4

       (   0   8   /   1   3   )

      PAGE 10572 OF146145

    KPCQASR COMPRESSION PROECT

    PRE-COMMISSIONING PROCEDURE

    3538-200-10-RT-045

    !ESTERN DESERTMAY #1% #014

    EGYPTRE$&1

    3538-200-$$D-12357 R>.04

    3538-200-$$D-12213 R>.04

    3538-200-$$D-12223 R>.04

    3538-200-$$D-12233 R>.04

    3538-200-$$D-12243 R>.04

    3538-200-$$D-12251 R>.05

    3538-200-$$D-12320 R>.02

    3538-200-$$D-12364 R>.04

    T :/-,, ,== 9