Upload
akhilesh-menon
View
215
Download
0
Embed Size (px)
Citation preview
7/30/2019 361-CH11Concise.ppt
1/35
11-1
CHAPTER 11 The Basics of Capital Budgeting
Should webuild this
plant?
7/30/2019 361-CH11Concise.ppt
2/35
11-2
What is capital budgeting? Analysis of potential additions tofixed assets investment analysis.
Long-term decisions; involve largeexpenditures (see p. 359-360).
Very important to firms future (see
Airbus, Boeing p. 357-358).
7/30/2019 361-CH11Concise.ppt
3/35
11-3
Steps to capital budgeting1. Estimate CFs (inflows & outflows).2. Assess riskiness of CFs.3. Determine the appropriate cost of capital
(%).4. Find NPV ($), IRR (%) and/or MIRR (%).5. Accept if NPV > 0 and/or IRR > WACC.
7/30/2019 361-CH11Concise.ppt
4/35
11-4
What is the difference betweenindependent and mutually
exclusive projects?Independent projects if the cash flowsof one are unaffected by the acceptanceof the other more than one projectmay be accepted.Mutually exclusive projects if the cashflows of one project can be adverselyimpacted by the acceptance of the other
accept one or the other.
7/30/2019 361-CH11Concise.ppt
5/35
11-5
An Example of MutuallyExclusive Projects
BRIDGE vs. BOAT to getproducts across a river.
7/30/2019 361-CH11Concise.ppt
6/35
11-6
What is the difference between normal
and nonnormal cash flow streams?Normal cash flow stream Cost (negativeCF) followed by a series of positive cash
inflows. One change of signs.Nonnormal cash flow stream Two ormore changes of signs. Most common:Cost (negative CF), then string of positiveCFs, then cost to close project. Nuclearpower plant, strip mine, etc.
7/30/2019 361-CH11Concise.ppt
7/35
11-7
Inflow (+) or Outflow (-) in Year
0 1 2 3 4 5 N NN
- + + + + + N- + + + + - NN
- - - + + + N
- - - + + + N
- + + - + - NN
7/30/2019 361-CH11Concise.ppt
8/35
11-8
Net Present Value (NPV)Sum of the PVs of all cash inflows andoutflows of a project:
N
0tt
t
)r1(CF
NPV
7/30/2019 361-CH11Concise.ppt
9/35
11-9
Calculating payback
Payback L = 2 + / = 2.375 years
CF t -100 10 60 100
Cumulative -100 -90 0 50
0 1 2 3
=
2.4
30 80
80
-30
Project L
Payback S = 1 + / = 1.6 years
CF t -100 70 100 20 Cumulative -100 0 20 40
0 1 2 3
=
1.6
30 50
50-30
Project S
7/30/2019 361-CH11Concise.ppt
10/35
11-10
What is Project Ls NPV @ 10%? Year CF t PV of CFt
0 -100 -$100
1 10 9.092 60 49.593 80 60.11
NPVL = $18.79
NPVS = $19.98 @ 10%
7/30/2019 361-CH11Concise.ppt
11/35
11-11
Solving for NPV:
Financial calculator solutionEnter CFs into the calculators CFjregister.
CF0 = -100CF1 = 10CF2 = 60CF
3= 80
Enter I/YR = 10, press NPV button toget NPV L = $18.78.
7/30/2019 361-CH11Concise.ppt
12/35
11-12
Rationale for the NPV methodNPV = PV of inflows Cost= Net gain in wealth
If projects are independent, accept if theproject NPV > 0.If projects are mutually exclusive, acceptprojects with the highest positive NPV,those that add the most value.In this example, accept S if mutuallyexclusive (NPV s > NPV L), and accept both
if independent.
7/30/2019 361-CH11Concise.ppt
13/35
11-13
Internal Rate of Return (IRR)IRR is the discount rate that forces PV of inflowsequal to cost, and the NPV = 0:
Solving for IRR with a financial calculator:Enter CFs in CFj register.Press IRR/YR ; IRR L = 18.13% and IRR S = 23.56%.
N
0tt
t
)IRR 1(CF 0
7/30/2019 361-CH11Concise.ppt
14/35
11-14
How is a projects IRR similar
to a bonds YTM? They are the same thing.Think of a bond as a project. The
YTM on the bond would be the IRR of the bond project. EXAMPLE: Suppose a 10-year bond
with a 9% annual coupon and$1,000 par value sells for $1,134.20.Solve for IRR = YTM = 7.08%, theannual return for this project/bond.
7/30/2019 361-CH11Concise.ppt
15/35
11-15
Bond YTM = IRR
-1134.20 CF j90 CF j9 N j1090 CF jIRR/YR = ? 7.08%
---------------------------------------------------
N I PV PMT FV10 ? (-1134.2) 90 1000
7.08%
7/30/2019 361-CH11Concise.ppt
16/35
11-16
Rationale for the IRR methodIf IRR > WACC, the projects returnexceeds its costs and there is some returnleft over to boost stockholders returns.
If IRR > WACC, accept project.If IRR < WACC, reject project.
If projects are independent, accept bothprojects, as both IRR > WACC = 10%.If projects are mutually exclusive, accept S,because IRR s > IRR L.
7/30/2019 361-CH11Concise.ppt
17/35
11-17
NPV Profiles A graphical representation of project NPVs atvarious different costs of capital.
WACC NPVL NPVS 0 $50 $405 33 29
10 19 2015 7 1220 (4) 5
7/30/2019 361-CH11Concise.ppt
18/35
11-18
Drawing NPV profiles
-10
0
10
20
30
40
50
60
5 10 15 20 23.6
NPV($)
Discount Rate (%)
IRRL = 18.1%
IRRS = 23.6%
Crossover Point = 8.7%
SL
.
.
. ...
..
.. .
7/30/2019 361-CH11Concise.ppt
19/35
11-19
Comparing the NPV and IRR methods
If projects are independent, the twomethods always lead to the same
accept/reject decisions.If projects are mutually exclusive
If WACC > crossover rate, the methodslead to the same decision and there is noconflict.If WACC < crossover rate, the methodslead to different accept/reject decisions.
7/30/2019 361-CH11Concise.ppt
20/35
11-20
Reasons why NPV profiles cross
Size (scale) differences the smallerproject frees up funds at t = 0 for
investment. The higher the opportunitycost, the more valuable these funds, so ahigh WACC favors small projects.Timing differences the project with fasterpayback provides more CF in early yearsfor reinvestment. If WACC is high, early CFespecially good, NPV S > NPV L.
7/30/2019 361-CH11Concise.ppt
21/35
11-21
Reinvestment rate assumptionsNPV method assumes CFs are reinvestedat the WACC.IRR method assumes CFs are reinvestedat IRR.
Assuming CFs are reinvested at theopportunity cost of capital is morerealistic, so NPV method is the best. NPV
method should be used to choosebetween mutually exclusive projects.Perhaps a hybrid of the IRR that assumescost of capital reinvestment is needed.
7/30/2019 361-CH11Concise.ppt
22/35
11-22
Since managers prefer the IRR to the NPVmethod, is there a better IRR measure?
Yes, MIRR is the discount rate thatcauses the PV of a projects terminalvalue (TV) to equal the PV of costs. TVis found by compounding inflows atWACC.
MIRR assumes cash flows arereinvested at the WACC.
7/30/2019 361-CH11Concise.ppt
23/35
11-23
Calculating MIRR
66.012.1
10%10%
-100.0 10.0 60.0 80.0
0 1 2 310%
PV outflows
-100.0 $100
MIRR = 16.5% 158.1
TV inflows
MIRRL = 16.5%
$158.1(1 + MIRR L)3
=
7/30/2019 361-CH11Concise.ppt
24/35
11-24
Calculator Solution for MIRR
1. Solve for PV of future CFs, using thereinvestment rate to discount
(set CF 0 = 0)2. Solve for the FV of these CFs (usingreinvestment rate) = Terminal Value =
Future Value (FV)3. Use CF0 as PV, N = # years, Terminal Value as FV, solve for I/YR = MIRR
7/30/2019 361-CH11Concise.ppt
25/35
11-25
Keystrokes for MIRR
CF j = 0, 10, 60, 80
I = 10%, solve for NPV = $118.78
PV = 118.78, n = 3, solve for FV = -158.10
PV = 100, solve for I/YR = 16.50% = MIRR
7/30/2019 361-CH11Concise.ppt
26/35
11-26
Keystrokes for MIRR, p. 372
CF j = 0, 500, 400, 300, 100
I = 10%, solve for NPV = $1078.82
PV = 1078.82, n = 4, solve for FV = -1579.50
PV = 1000, solve for I/YR = 12.11% = MIRR
7/30/2019 361-CH11Concise.ppt
27/35
11-27
Why use MIRR versus IRR?
MIRR assumes reinvestment at theopportunity cost = WACC. MIRR alsoavoids the multiple IRR problem.Managers like rate of returncomparisons, and MIRR is better for
this than IRR.
7/30/2019 361-CH11Concise.ppt
28/35
11-28
What is the payback period?
The number of years required torecover a projects cost, or How longdoes it take to get our money back? Calculated by adding projects cashinflows to its cost until the cumulative
cash flow for the project turns positive.
7/30/2019 361-CH11Concise.ppt
29/35
11-29
Calculating payback
Payback L = 2 + / = 2.375 years
CF t -100 10 60 100
Cumulative -100 -90 0 50
0 1 2 3
=
2.4
30 80
80
-30
Project L
Payback S = 1 + / = 1.6 years
CF t -100 70 100 20 Cumulative -100 0 20 40
0 1 2 3
=
1.6
30 50
50-30
Project S
7/30/2019 361-CH11Concise.ppt
30/35
11-30
Strengths and weaknesses of payback
StrengthsProvides an indication of a projects risk and liquidity.Easy to calculate and understand.
Weaknesses
Ignores the time value of money.Ignores CFs occurring after the payback period.
7/30/2019 361-CH11Concise.ppt
31/35
11-31
Discounted payback period
Uses discounted cash flows rather thanraw CFs.
Disc Payback L = 2 + / = 2.7 years
CF t -100 10 60 80
Cumulative -100 -90.91 18.79
0 1 2 3
=
60.11
-41.32
PV of CF t -100 9.09 49.59
41.32 60.11
10%
7/30/2019 361-CH11Concise.ppt
32/35
11-32
Project P has cash flows (in 000s): CF 0 =-$0.8 million, CF 1 = $5 million, and CF 2 =
-$5 million. Find Project Ps NPV and IRR.
Enter CFs into calculator CFLO register.
Enter I/YR = 10.NPV = -$386.78.IRR = ERROR Why?
-800 5,000 -5,000
0 1 2WACC = 10%
7/30/2019 361-CH11Concise.ppt
33/35
11-33
Multiple IRRs
450
-800
0 400100
IRR2 = 400%
IRR1 = 25%
WACC
NPV
7/30/2019 361-CH11Concise.ppt
34/35
11-34
Why are there multiple IRRs?
At very low discount rates, the PV of CF 2 islarge & negative, so NPV < 0.
At very high discount rates, the PV of bothCF1 and CF 2 are low, so CF 0 dominates andagain NPV < 0.In between, the discount rate hits CF 2 harder than CF 1, so NPV > 0.Result: 2 IRRs.
7/30/2019 361-CH11Concise.ppt
35/35
11 35
When to use the MIRR insteadof the IRR? Accept Project P?
When there are nonnormal CFs andmore than one IRR, use MIRR.
PV of outflows @ 10% = -$4,932.2314.TV of inflows @ 10% = $5,500.MIRR = 5.6%.
Do not accept Project P.NPV = -$386.78 < 0.MIRR = 5.6% < WACC = 10%.