    PTD Telekit Meeting - Serco

    Date ofmeeting

    21/4/11 SupplierName:

    Serco

    Meeting Location:

    AttendeesDWP: redactedSerco: redacted

    Record ofdiscussion

    redacted provided an update on progress with amendments. A reviewhas been conducted on CPAs 15 and 17 to identify what amendmentsthey need to make. W2W Business Unit will not longer exist andreporting will now be to the Home Affairs Team. Information has beensent to the relevant work stream and redacted (Commercial Manager)will bring a table showing the changes to the meeting on 4th May to talk

    through it with us.

    redacted asked if we could see something in advance but redacted saidthat this was a significant piece of work that would need to be simplifiedand in view of the holidays it would be preferable to wait until the 4 th.redacted asked it they will be producing an addendum to the contractfollowing out meeting on the 4th and redacted confirmed this.

    redacted discussed changes to the IT system, a review of systems wasunderway and the team was already lined up to go on the agreed dateof 1/7. redacted said IT training needs had been agreed and theprogramme and rooms were arranged. redacted confirmed that therewere no other fundamental changes and that there was no indicationthat any of the subcontractors were not interested.

    redacted asked if we could have a revised implementation plan as theone we have for West Mids has a different go-live date. redacted agreedto provide one and some supporting narrative, and also gave asummary of where they were with premises/leases in the 2 CPAs noshowstoppers. Recruitment and training still on track, some datesidentified mid May and some in June. Current FND providers will need

    additional follow-on training as they will not be available to completeearlier training.

    redacted said some internal issues with IT but nothing that will impactgo-live. Impact training starts 23/5 and by 24/6 information will beloaded on the system in advance of 1/7.

    redacted also discussed the dashboard reporting and asked if he couldreplace our implementation highlight report with their morecomprehensive report, which covers, subcontractors, premises, Prap,comms and marketing, finance , TUPE and tops 5 risks. redacted to

    send us one to see if it meets our requirement. redacted said wecouldnt say whether this would be okay for redacted but that we are

    Generic inbox. DWP work progptdq&aSerco in Confidence

  • 8/3/2019 386. CPA17: Serco Ltd - PTD Telekit 21 April 2 -V2

    2/2

    happy to accept this format. This is updated weekly and discussedeach Friday. redacted agreed to send to us following this meeting, andnext Thursday.

    redacted asked in what format we wanted the risk log, 1 page copy orthe dashboard template. redacted said we want to see the top risks andwould be happy to accept an extract from their project managementsystem. redacted confirmed that he will send one over todayredacted asked for the questions from JCP in advance of the meeting on4th May. redacted outlined that they will not have sight of the bid but thatwhen we send the agenda we will ask them if they wish to see anythingspecifically covered at the meeting. Any responses will be sent throughto redacted Thursday 28/4.

    redacted also provided an update on Annex 7 Transparency Agendaand confirmed that she would be sending the proposals through directlyto redacted next week.

    Redacted said that we probably will not need a further meeting nextweek, and confirmed that following the meeting on 4th May she wouldget further advice if required regarding the amendments.

    Action Points redacted - To email JCP reps and provide any questions to redacted bynoon Thursday 28/4.

    redacted to send report and risk log through to redacted today andfurther report next Thursday.

    Action Point

    Owner

    Date(s) for

    Clearance

    Author redacted Date recorded 21/4/11

    Date Returnedto generic

    Inbox

    Generic inbox. DWP work progptdq&aSerco in Confidence