3G New Site Integration Process
This document is designed to cover the process of what is to be done when a tech calls in tointegrate a 3G Site.
Firstly locate the Transmission Datafill for the site so you can determine what RNC the site isbuilt on and obtain the TRS & BTS IP Addresses. Then launch Application Launcher to login tothe relevant RNC.
8/7/2019 3G Site Integration
http://slidepdf.com/reader/full/3g-site-integration 2/9
2/9 Document Type
Author
Unit/Dept.
Document Title
Date, VersionFor internal use
Once Application Launcher is up then double click on the RNC RNW Object Browser to viewthe sites on the RNC
Once opened then scroll down through the list of sites to locate the site you will integrate toestablish the status of the site whether it is unlocked & on air or yet to be unlocked. As shownbelow the site WBTS1770 is currently Blocked User.
8/7/2019 3G Site Integration
http://slidepdf.com/reader/full/3g-site-integration 3/9
3/9 Document Type
Author
Unit/Dept.
Document Title
Date, VersionFor internal use
You will then need to check the status of the CoCo for the site. This can be down by againscrolling down thru the Object Browser till you find the relevant CoCo Id. It will as a standard bethe same Id as the WBTS Id. In the case below the CoCo is in a Blocked state. Therefore theTransmission is most likely down or the CoCo has been created incorrectly. This would then betroubleshot with the Tech to establish where the fault may lie and if needed delete & recreate
the CoCo. When resolved the CoCo will show in the CNBAP & DNBAP columns1/27/33,WO,20 & 1/37/34/WO,20 for the site below.
8/7/2019 3G Site Integration
http://slidepdf.com/reader/full/3g-site-integration 4/9
4/9 Document Type
Author
Unit/Dept.
Document Title
Date, VersionFor internal use
As part of the process you will refer to the Transmission Datafill to obtain the Transmission IPaddress. As illustrated below ping the IP address to ensure that all is ok. Timeouts will showthere are still issues with the TRS and will need to be checked.
8/7/2019 3G Site Integration
http://slidepdf.com/reader/full/3g-site-integration 5/9
5/9 Document Type
Author
Unit/Dept.
Document Title
Date, VersionFor internal use
Once the CoCo is up and working proceed to unlock the site. This is done by clicking on theWCDMA Cells tab for the site. Highlight the cells to be unlocked, right click and select UnlockWCEL. This will then unlock the Cells for use.
8/7/2019 3G Site Integration
http://slidepdf.com/reader/full/3g-site-integration 6/9
6/9 Document Type
Author
Unit/Dept.
Document Title
Date, VersionFor internal use
Once unlocked and the cells are on air the State will change to “Working” Then ensure that thetech is not connected locally to the WBTS so you can check to ensure you can connect to theWBTS to check if the OAM IUB Hub is connected so the licences can be downloaded. If itshows disconnected then this cannot be done.
8/7/2019 3G Site Integration
http://slidepdf.com/reader/full/3g-site-integration 7/9
7/9 Document Type
Author
Unit/Dept.
Document Title
Date, VersionFor internal use
If all ok then Open up Network Editor to create or update the GUI view with the correctMaintenance Region & BTS IP Address. The Licence Manager will only allow licences to bedownloaded if this information is correct & if the Target Id appears in the view. Refer to the PoolLicence procedure for more details.
8/7/2019 3G Site Integration
http://slidepdf.com/reader/full/3g-site-integration 8/9
8/9 Document Type
Author
Unit/Dept.
Document Title
Date, VersionFor internal use
Once this has been checked open up Pool Licence Manager and download the Licencesrequired per the Project. This information is found in the Licence Keys & Capacity Document.Once downloaded. Click on Configuration on the WBTS Manager menu and select LicenceManagement. It will then display all the licences currently loaded to the site. Review andensure none are missing or incorrect amounts are loaded.
8/7/2019 3G Site Integration
http://slidepdf.com/reader/full/3g-site-integration 9/9
9/9 Document Type
Author
Unit/Dept.
Document Title
Date, VersionFor internal use
Once completed advise the tech to proceed with call testing which will be monitored per thecall testing procedure document. Before allowing the tech to leave one last alarm check is tobe completed to ensure the site is alarm free or if there are alarms the tech is aware of theissues so they can either be resolved then or be highlighted back to the project to be ceared upat a later date.