4 Project Mgt

Embed Size (px)

Citation preview

  • 8/13/2019 4 Project Mgt

    1/69

    2013 Lew Hofmann

    Project Management

  • 8/13/2019 4 Project Mgt

    2/69

    2013 Lew Hofmann

    Managing Projects

    Projects are usually large & infrequent or one-time.

    No two projects are the same.

    Projects are usually fairly long. Several months to many years

    They Involve different people in different phases

    Most people are only involved with a part of a project

    Even though a project may be under the overallpurview of a single department or group, other

    departments are often involved.

  • 8/13/2019 4 Project Mgt

    3/69

    2013 Lew Hofmann

    Projects

    The three main goals of projectmanagementare

    1. Complete the project on time or earlier.

    2. Complete the project on or under budget.

    3. Meet the specifications to the satisfaction ofthe customer.

  • 8/13/2019 4 Project Mgt

    4/69

  • 8/13/2019 4 Project Mgt

    5/69

    2013 Lew Hofmann

    Pro ject Structu res

    Functional Structure: The team is housed in a

    specific functional area.Assistance from other

    areas must be negotiated.

    Pure Project: Team members work exclusively for

    the project manager. (Best for large projects.)

    Matrix Structure:A compromise between the

    functional and project structures. Members remain

    in various functional areas and the project manager

    coordinates across functional areas. Having two

    bosses (dual authority) can cause problems.

  • 8/13/2019 4 Project Mgt

    6/69

    2013 Lew Hofmann

    Project Management Techn iques

    PERT CPM GERT

    Program Evaluation and Review Technique PERT(Program Evaluation and Review Technique) is

    utilized when activity times are uncertain (involved risk).

    Critical Path Method CPM(Critical Path Method) is used when activity times

    are known and certain.

    Graphic Evaluation and Review Technique Rarely used, and then only in very complex projects.

    It overcomes many of the limitations of PERT and CPM

    Provides much more project flexibility.

  • 8/13/2019 4 Project Mgt

    7/69

    2013 Lew Hofmann

    Project Management Steps

    1. Describe the Project (Defining all the tasksthat must be completed, and in what sequence.)

    2. Develop a Graph Model(diagram thenetwork showing task relationships)

    3. Develop an activity Schedule (Determinethe time estimates for each task)

    4. Analyzing cost-time trade-offs(Determine the cost of each task.)

    5. Assess Risks (Probability analysis)

  • 8/13/2019 4 Project Mgt

    8/69

    2013 Lew Hofmann

    Step 1

    Desc r ibe the p ro ject

    What is the project?

    When does the project start and end?

    What activities make up the project?

    Activitiesare defined as the smallest units ofwork that a project manager is expected toschedule and control.

    ...a managers project description should reflect onlythe level of detail that he or she needs in order to

    make scheduling and resource allocation decisions.

    Task Ownership: Each activity must havean owner who is responsible for seeing thatthe work is accomplished.

  • 8/13/2019 4 Project Mgt

    9/69

    2013 Lew Hofmann

    Relat ionships

    between Act iv i t ies

    A project is a sequence of activities. Large projects have interrelated sequences.

    Except for the beginning activity/activities, every

    activity in a project has one or more activities

    that must be done immediately prior.

    These are called Precedent (Pre-cee-ent)

    activities

    Theymust be defined before the project begins.

    EG: In order to bury a body you must first dig a hole.

  • 8/13/2019 4 Project Mgt

    10/69

    2013 Lew Hofmann

    Step 2

    Develop a Network Model

    A Network Diagramvisually displays theinterrelated activities using nodes (circles) andarcs (arrows) that depict the relationships between

    activities. It is a graphical diagram.

    For very large projects it may only be a numericalarrangement of activities rather than graphical.

    Two types of Graphical Network Models Activity On Arc(AOA)

    Activity On Node(AON) (We will use AON)

  • 8/13/2019 4 Project Mgt

    11/69

    2013 Lew Hofmann

    Two Types

    of Network Models

    Activity-on-Arc (AOA)

    Activity-on-Node (AON)Activity Activity

    Link

    We wil l

    use th is!D E

    Time Time

    Activity E

    Time

    Activity D

  • 8/13/2019 4 Project Mgt

    12/69

    2013 Lew Hofmann

    What AON Nodes look l ike.

    The earliest you can completean activity--determined byadding the activity time(duration) to the early start time.

    This is the latest you can finishan activity without delayingproject completion. It is thesame as the Late Start time of

    the next activity. If there are twoor more subsequent activities,this time is the same as the

    earliest of those Late Starttimes.

    The is the earliest you can start anactivity. It is determined by the earlyfinish time of the precedent activity. Ifthere are two or more precedentactivities, this time is the same asprecedent activity with the latestEarly Finish time.

    This is the Late-Finish time minusthe activity duration.

    Slack

    Slack (S) is the difference, if any,

    between the early start (ES) and latestart times (LS) or the early finish(EF) and late finish (EF) times.

    S = LS - ES or S = LF - EF

    2013 Lew Hofmann

    EarlyStart

    EarlyFinish

    Late

    Finish

    Late

    Start

    Activity

    Name

    ActivityDuration

  • 8/13/2019 4 Project Mgt

    13/69

    2013 Lew Hofmann

    Example: This homework Ass ignment

    EarlyStart

    EarlyFinish

    Late

    Finish

    Late

    Start

    Home-

    work #2

    1 hour

    Slack

    If it takes one hour, theearliest you can complete thisassignment is one hour afterclass ends.

    One hour after your late starttime.

    The earliest you can start thisassignment it is immediately afterthis class ends.

    You can wait untilone hour before theclass in which it isdue to start it; inthis case one weekfrom now.

    The slack in this case would be one

    week, expressed in hours, since thatis the unit of time used for theactivities. It would be how long youcould delay doing the assignment.

    2013 Lew Hofmann

  • 8/13/2019 4 Project Mgt

    14/69

    2013 Lew Hofmann

    Precedent

    Relat ionshipsPrecedent relationshipsdetermine the sequencefor accomplishing activities. They specify that anygiven activity cannot start until its preceding activityor activities have been completed.

    In our AON approach, thenodes (circles) representactivities, and the arcs

    (arrows) represent thesequential relationshipsbetween them.

    AON

    S T U

    Activity On Node approach

    S precedes T which

    precedes U

    Nodes are simplified in the following examples.

  • 8/13/2019 4 Project Mgt

    15/69

  • 8/13/2019 4 Project Mgt

    16/69

    2013 Lew Hofmann

    Act iv i ty Relat ionsh ips

    S

    T

    U

    V

    U& Vcant begin until S& T

    have been completed.

    S

    T

    U

    V

    Ucannot begin until S& Thave

    been completed. Vcannot begin

    until Thas been completed.

  • 8/13/2019 4 Project Mgt

    17/69

    2013 Lew Hofmann

    Act iv i ty Relat ionsh ips

    S T V

    U

    T& Ucannot begin until Shas been

    completed; Vcannot begin until both T&Uhave been completed.

  • 8/13/2019 4 Project Mgt

    18/69

    2013 Lew Hofmann

    Logic Errors

    C H

    G

    This is a logic error. C cannot be an

    immediate predecessor of both G &H if

    G is also an immediate predecessorofH.

    Logic errors are hard to identify except on the

    network diagrams. If you see a tr iangle, then it is a

    logic error. Eliminate the short cut.

  • 8/13/2019 4 Project Mgt

    19/69

    2013 Lew Hofmann

    St. Adolfs Hospital(A sample project)

    Immediate

    Activity Description Predecessor(s) Responsibility

    A Select administrative and medical staff.

    B Select site and do site survey.C Select equipment.

    D Prepare final construction plans and layout.

    E Bring utilities to the site.

    F Interview applicants and fill positions in

    nursing, support staff, maintenance,

    and security.

    G Purchase and take delivery of equipment.H Construct the hospital.

    I Develop an information system.

    J Install the equipment.

    K Train nurses and support staff.

  • 8/13/2019 4 Project Mgt

    20/69

    2013 Lew Hofmann

    A Select administrative and medical staff. 12

    B Select site and do site survey. 9C Select equipment. A 10

    D Prepare final construction plans & layout. B 10

    E Bring utilities to the site. B 24

    F Interview applicants and fill positions in A 10

    nursing, support staff, maintenance,

    and security.

    G Purchase and take delivery of equipment. C 35H Construct the hospital. D 40

    I Develop an information system. A 15

    J Install the equipment. E,G,H 4

    K Train nurses and support staff. F,I,J 6

    St. Adolfs Hospital(A sample pro ject)

    Immediate

    Activity Description Predecessor(s) Activity Times

    *We wont assigning Responsibility data, but it is important in project management.

  • 8/13/2019 4 Project Mgt

    21/69

    2013 Lew Hofmann

    St. Adolfs HospitalDiagramm ing the Network

    FinishStart

    A

    B

    C

    D

    E

    F

    G

    H

    I

    J

    K

    Immediate

    Predecessors

    A 12

    B 9

    C A 10

    D B 10

    E B 24

    F A 10

    G C 35

    H D 40

    I A 15

    J E,G,H 4

    K F,I,J 6

    Act iv i ty

    Times (wks)

  • 8/13/2019 4 Project Mgt

    22/69

    2013 Lew Hofmann

    St. Adolfs Hospi ta lAct iv i ty Paths

    FinishStart

    A

    B

    C

    D

    E

    F

    G

    H

    I

    J

    K

    Path Time (wks)

    A-I-K 33

    A-F-K 28A-C-G-J-K 67

    B-D-H-J-K 69

    B-E-J-K 43

    Paths are sequences ofactivities between a

    projects start and finish.

  • 8/13/2019 4 Project Mgt

    23/69

    2013 Lew Hofmann

    St. Adolfs Crit ical Path

    FinishStart

    A

    B

    C

    D

    E

    F

    G

    H

    I

    J

    KPath Time (wks)

    A-I-K 33

    A-F-K 28

    A-C-G-J-K 67

    B-D-H-J-K 69

    B-E-J-K 43

    Project Expected

    Time is 69 wks.

    The longest path is the

    critical path!

  • 8/13/2019 4 Project Mgt

    24/69

  • 8/13/2019 4 Project Mgt

    25/69

    2013 Lew Hofmann

    PERTs

    Three time-es t imates

    OPTIMISTIC TIME: Best time if everything goes

    perfectly when doing the activity.

    REALISTIC TIME: Most likely time for the activity

    PESSIMISTIC TIME:A worst-case situation

    B + 4M + PExpected Time = -------------------

    6In this example, the most likely time is given a weight of four, and the

    other two times (pessimistic and optimistic) are each given weights of one.

    Risky act iv i ty t imes make the pro ject length r isky, so there is a need

    for r isk assessment based on the prob abi l ity distr ibu t ion of t imes.

    (Standard deviation and variance are computed by the software.)

  • 8/13/2019 4 Project Mgt

    26/69

    2013 Lew Hofmann

    Activity slackis the maximum length of time that anactivity can be delayed without delaying the entireproject.

    It is the difference between the earliest time wecan start an activity and the latest time we can

    start the activity without delaying the project.

    The critical path activities have zero slack.

    For the St. Adolfs Hospital project, 69 weeks is theproject length because 69 weeks is the longest path.

    Project delays beyond the projected completion date

    often involve penalties.

    Act iv i ty Slack

  • 8/13/2019 4 Project Mgt

    27/69

    2013 Lew Hofmann

    Earliest Start Time(ES) for an activity is the earliest finishtime of the immediately preceding activity.

    Earliest Finish Time(EF) for an activity is its earliest starttime plus how long it takes to do it (activity time).

    Latest Start Time(LS) is the latest you can finish the activityminus the activitys estimated duration.

    Latest Finish Time(LF) is the latest start time plus the activitytime.

    The latest finish time is the same as the latest start time of the activity activity

    which follows it. (Latest start and finish times for each activity are computed

    starting at the projects last activity completion time and working forward.)

    Slackis the difference between the Earliest Start and Latest start

    times for an activity (or earliest finish and latest finish times.)

    Act iv i ty Start and Finish Times

  • 8/13/2019 4 Project Mgt

    28/69

    2013 Lew Hofmann

    Earl iest Start and Earl iest Finish Times

    K

    6

    C

    10

    G

    35

    J

    4

    H

    40

    B

    9

    D

    10

    E

    24

    I

    15

    FinishStart

    A

    12

    F

    10

    0

    Earliest start time

    12

    Earliest finish time

    0 9

    9 33

    9 19 19 59

    22 5712 22

    59 63

    12 27

    12 22 63 69

    2013 Lew Hofmann

    E li t St t d E l i t Fi i h Ti

  • 8/13/2019 4 Project Mgt

    29/69

    2013 Lew Hofmann

    Earl iest Start and Earl iest Finish Times

    Crit ical Path

    The Crit ical Path

    takes 69 weeks

    K

    6

    C

    10

    G

    35

    J

    4

    H

    40

    B

    9

    D

    10

    E

    24

    I

    15

    FinishStart

    A

    12

    F

    10

    0 9

    9 33

    9 19 19 59

    22 5712 22

    59 63

    12 27

    12 22 63 690 12

    Path Time (wks)

    A-I-K 33

    A-F-K 28

    A-C-G-J-K 67

    B-D-H-J-K 69

    B-E-J-K 43

    2013 Lew Hofmann

    Latest Start and Latest Finish Times

  • 8/13/2019 4 Project Mgt

    30/69

    2013 Lew Hofmann

    K

    6

    C

    10

    G

    35

    J

    4

    H

    40

    B

    9

    D

    10

    E

    24

    I

    15

    FinishStart

    A

    12

    F

    10

    0 9

    9 33

    9 19 19 59

    22 5712 22

    59 63

    12 27

    12 22 63 690 12

    LatestStart and LatestFinish Times(You s tar t with the last act iv i ty and w ork toward th e f i rs t act iv i ty)

    48 63

    53 63

    59 63

    24 59

    19 59

    35 59

    14 24

    9 19

    2 14

    0 9

    Latest

    finish

    time

    63 69

    Latest

    start

    time

    2013 Lew Hofmann

    Node Duration ES LS Slack

  • 8/13/2019 4 Project Mgt

    31/69

    2013 Lew Hofmann

    Act iv i ty Slack

    Analys is

    K

    6

    C

    10

    G

    35

    J

    4

    H

    40

    B

    9

    D

    10

    E

    24

    I

    15

    FinishStart

    A

    12

    F

    10

    0 9

    9 33

    9 19 19 59

    22 5712 22

    59 63

    12 27

    12 22 63 690 12

    48 63

    53 63

    59 63

    24 59

    19 59

    35 59

    14 24

    9 19

    2 14

    0 9

    63 69

    Slack is the difference betweenLS and ES or EF and LFA 12 0 2 2

    B 9 0 0 0

    C 10 12 14 2

    D 10 9 9 0

    E 24 9 35 26

    F 10 12 53 41

    G 35 22 24 2

    H 40 19 19 0

    I 15 12 48 36

    J 4 59 59 0

    K 6 63 63 0

    2013 Lew Hofmann

  • 8/13/2019 4 Project Mgt

    32/69

    2013 Lew Hofmann

    Analyz ing

    Cost-Time Trade-Offs .

    There are always cost-time trade-offs in projectmanagement.

    You can completing a project early by hiring more

    workers or running extra shifts.There are often penalties if projects extends beyond

    some specific date, and a bonus may be provided forearly completion.

    Crashinga project means finishing the projectearly by expediting one or more activities.

    Not all activities can be shortened.

  • 8/13/2019 4 Project Mgt

    33/69

    2013 Lew Hofmann

    Pro ject Cos ts

    Total Project Costs=

    direct costs + indirect costs + penalty costs

    Direct costsinclude labor, materials, and any other

    costs directly related to project activities.

    Indirect costsinclude administration, depreciation,financial, and other variable overhead costs.

    These can be reduced by reducing total project time.

    The shorter the duration of the project, the lower the indirectcosts will be.

    Penalty costs are essentially late fees incurred forgoing over the projected due date.

  • 8/13/2019 4 Project Mgt

    34/69

    2013 Lew Hofmann

    We do cost analysis to determine the projectschedule that minimizes total project costs.

    When crashing an activity or project, extra money is

    spent on direct costs, but money is saved on indirectcosts and possible penalties.

    A minimum-cost scheduleis determined by startingwith the normal project time schedule and shorteningactivities along th e cr i t ical pathuntil the costs ofcrashing (direct costs) start to exceed the savings inindirect costs and penalty costs. New critical paths usually appears while doing this.

    Minim izing Costs

  • 8/13/2019 4 Project Mgt

    35/69

    2013 Lew Hofmann

    a. Determine the projects critical path(s).

    b. Find the activity or activities on the critical path(s)with the lowest cost of crashing (shortening) per week.

    c. Reduce the time for this activity until

    a. it cannot be further reduced,

    b. or another path becomes critical,

    c. or the increase in direct costs exceed the savings that result

    from lower indirect costs.

    d. Repeat this process until the total project costs are nolonger decreasing.

    Sophisticated project management software will do this.

    St. Adolfs Hospital

    Min imum Cost Schedu le

    Of the five critical-path activities, the

  • 8/13/2019 4 Project Mgt

    36/69

    2013 Lew Hofmann

    K

    6

    C

    10

    G

    35

    J

    4

    H

    40

    B

    9

    D

    10

    E

    24

    I

    15

    FinishStart

    A

    12

    F

    10

    0 9

    9 33

    9 19 19 59

    22 5712 22

    59 63

    12 27

    12 22 63 690 12

    48 63

    53 63

    59 63

    24 59

    19 59

    35 59

    14 24

    9 19

    2 14

    0 9

    63 69

    p ,contractor says Dand Hcannot beshortened. Jis the least costly toshortenat $1000 a week. Contractorsays it can be shortened to 1 week.

    2012 Lew Hofmann

    The project manager must nowcompare the cost of shortening J by 3weeks ($3,000 in additional directcosts) with savings in indirect costs,to see if the total cost is lower.

    Shorten from 4

    weeks to 1 week

  • 8/13/2019 4 Project Mgt

    37/69

    2013 Lew Hofmann

    Assess ing Risks

    Riskis a measure of the probability (andconsequences) of not completing a projecton time.

    A major responsibility of the project managerat the start of a project is to develop a risk-management plan.

    A Risk-Management Planidentifies the keyrisks to a projects success and prescribesways to circumvent them.

  • 8/13/2019 4 Project Mgt

    38/69

    2013 Lew Hofmann

    Causes o f Pro ject Risk

    1. Service/Product Risks: If the project involves a

    new service or product, several risks can arise.

    Market riskcomes from competition.

    Technological riskcan arise from technology advancesmade once the project has started, rendering obsolete the

    technology chosen for service or product.

    Legal riskfrom liability suits or other legal action.

    2. Project Team Problems: Poor member selections

    and inexperience, lack of cooperation, etc.

    3. Operations Risk: Information inaccuracy, miss-

    communications, bad project timing, weather

  • 8/13/2019 4 Project Mgt

    39/69

    2013 Lew Hofmann

    ANALYZING PROBABIL ITIES

    What is the probability that our sample project

    will finish in 69 weeks as scheduled?

    100% (Why?)

    Because we used CPM!

    (This means we were certainof all of our activity times.)

    If we werent certain, we should have used PERT

    You only do risk analysis if you use PERT

  • 8/13/2019 4 Project Mgt

    40/69

    2013 Lew Hofmann

    PERT and PROBABIL ITIES

    With PERTs three time-estimates, we get a mean

    (average) time and a var ianceforeach activityand

    each path.

    We also get a projectmean time and variance.

    In order to compute probabilities (assuming a

    normal distribution) we need the activity means andvariances.

    Most computer packages calculate this for you.

  • 8/13/2019 4 Project Mgt

    41/69

    2013 Lew Hofmann

    Probabi l i ty

    of Project Complet ion

    The probability of a project being completed by a givendate is a function of the mean activity times andvariances along the critical path(s).

    The probability of a specific act iv i ty being completed bya given date is a function of the mean activity times andvariances along the longest path leading up to thatactivity.

    If you have more than one critical path, focus on the pathwith the greatest variance.

    A near-critical path may also be a problem,

    depending on the mean and variance of its activities.

  • 8/13/2019 4 Project Mgt

    42/69

    2013 Lew Hofmann

    Dist r ibut ions & Probabi l ity

    A Beta distribution is often used for the three

    estimates of each act iv i ty

    This allows skewed distributions.

    Optimistic------Most likely-----------------------Pessimistic

    (3------------- 5---------------------------------- 11)

    Normal distributions are needed for probabilities.

    A distribution of act iv i ty-meansis a normal

    distribution, even though each activity time may be

    a beta distribution.

  • 8/13/2019 4 Project Mgt

    43/69

    2013 Lew Hofmann

    Beta Distr ibut ion

    Mean

    ma b Time

    Probabilit

    y

    PessimisticOptimistic

    Each activity may have its three time

    estimates skewed (Beta Distribution), but the

    path along which this activities lie has a

    normal distribution and thus a mean and

    variance.

  • 8/13/2019 4 Project Mgt

    44/69

    2013 Lew Hofmann

    Figu r ing Probab i li t ies

    Assume a PERT project critical path takes 40 days, and that the

    variance of the critical path is 2.147

    You wish to know the probability of the project going over 42 days.

    Compute the standard deviation of the critical path. The square root of the variance of 2.147 = Std. Dev. = 1.465

    POM/QM software gives you the variance of the critical path.

    Compute the Z value: Z = (absolute time difference) / Std. Dev.

    In this example, Z= (42 days - 40 days) / 1.465= 1.365

    Look up the Zvalue of 1.365in a Normal Distribution table to get

    the probability of the project taking 42 days.

    Subtract it from 100% to get the probability of going over 42.

  • 8/13/2019 4 Project Mgt

    45/69

    2013 Lew Hofmann

    Look up the Z value (1.365)in the table of normal distribution.

    (In this case you need to interpolate between the Z values of .9313 and .9147)

    .9139 or 91.39%is the probability of the project taking 42 days.

    Thus the probability of going over 42 days is 100 - 91.39 = 8.61%

    .9139

  • 8/13/2019 4 Project Mgt

    46/69

    St Ad lf H it l

  • 8/13/2019 4 Project Mgt

    47/69

    2013 Lew Hofmann

    2= (variances of activities along critical path) z=TC

    2

    2= 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89

    z= 726911.89

    What is the Probability of it taking 72 weeks?

    Critical Path = B - D - H - JK = 69 weeks

    T=72 weeks C= 69weeks

    St. Adolfs HospitalA 69-week Project

    Look up Z value in normal distribution tableZ = 0.870

    CriticalPathVariance

    z=3

    3.44818

  • 8/13/2019 4 Project Mgt

    48/69

    2013 Lew Hofmann

    Look up the Z value (0.870) in the table of normal distribution.

    .8078 or 80.78%is the probability of the project taking 72 wks.Going over 72 weeks would be 10080.78 = 19.22%

  • 8/13/2019 4 Project Mgt

    49/69

    2013 Lew Hofmann

    Project duration (weeks)

    69 72

    Probability of

    taking 72 weeks

    is 0.8078 or

    80.78%

    Length of

    critical path is

    69 weeks

    Normal distribution:

    Mean = 69 weeks;

    = 3.45 weeks

    Probability of

    exceeding 72

    weeks is 0.1922

    or 19.22%

    St. Adolfs HospitalProbability of Completing Project On Time

  • 8/13/2019 4 Project Mgt

    50/69

  • 8/13/2019 4 Project Mgt

    51/69

    2013 Lew Hofmann

    Path Mergersoccur when two or more activitypaths combine at a particular node. Both paths mustbe completed up to this point, which will eliminate any

    built-up slack. Multitaskingis the performance of multiple project

    activities at the same time. Work on some activities isoften delayed for other work.

    Loss of Focusby a manager can happen if thecritical path changes frequently.

    Failure to have all the needed resources on time.

    Resource-Related Prob lems

  • 8/13/2019 4 Project Mgt

    52/69

    2013 Lew Hofmann

    PERT / CPM

    ADVANTAGES

    Enables Resource Management & Allocation

    You can move slack resources to critical points

    Focuses on your critical activities

    Visualize relationships (The big picture)

    Enables Cost analysis

  • 8/13/2019 4 Project Mgt

    53/69

    2013 Lew Hofmann

    PERT / CPM PITFALLS

    Can be complex to setup relationships in

    large project

    Time estimatesare often biased.

    Near critical paths are easily overlooked.

  • 8/13/2019 4 Project Mgt

    54/69

    2013 Lew Hofmann

    GERT(Graphical Evaluation and Review Technique)

    Gives more flexibilityto project planning than PERT/CPM

    Allows any individual activity to either be

    completed or not completed (Succeed or fail)

    PERT & CPM both require all activities be successfully

    completed. GERT does not require this.

    GERT Allows looping back (redoing an activity) orskipping an activity entirely.

    There are computerized GERT packages.

  • 8/13/2019 4 Project Mgt

    55/69

    2013 Lew Hofmann

    Solved Problem

    What is the probabi l i ty of

    complet ing the pro ject in

    23 weeks?

    2013 Lew Hofmann

    S l d P bl

  • 8/13/2019 4 Project Mgt

    56/69

    2013 Lew Hofmann

    Solved Problem

    2013 Lew Hofmann

  • 8/13/2019 4 Project Mgt

    57/69

    2013 Lew Hofmann

    Solved Problem

    Finish

    Start

    A

    4.0

    0.0

    4.0

    4.0

    8.0

    D

    12.0

    4.0

    8.0

    16.0

    20.0

    E

    6.5

    9.0

    9.0

    15.5

    15.5

    G

    4.5

    15.5

    15.5

    20.0

    20.0

    C

    3.5

    5.5

    5.5

    9.0

    9.0

    F

    9.0

    5.5

    6.5

    14.5

    15.5

    B

    5.5

    0.0

    0.0

    5.5

    5.5

    2013 Lew Hofmann

  • 8/13/2019 4 Project Mgt

    58/69

    Homework #2

  • 8/13/2019 4 Project Mgt

    59/69

    2013 Lew Hofmann

    Homework #2

    Due next week

    Problem 1 is on the next slide. Draw thenetwork and solve it manuallyusing the

    AON method. No credit if you use thecomputer.

    Problems 2and 3are on the following

    slides. Use the POM/QM software for these last two

    problems.

    Problem 1

  • 8/13/2019 4 Project Mgt

    60/69

    2013 Lew Hofmann

    Problem 1Do manually (no computer)

    A project has the following precedence relationships and activitytimes. Draw the netwo rk diagram and calculate the total slackfor each act iv i ty . Which act iv i t ies are on the cr i t ical path?

    Activity Activity Time (wks)

    Immediate

    Predecessor(s)

    A 4

    B 9

    C 5 A

    D 15 B,CE 12 B

    F 4 D

    G 8 E

    H 7 F,G

    PROBLEM 2 (Use POM/QM)1 There are logic errors in the data You will have to run the program in order

  • 8/13/2019 4 Project Mgt

    61/69

    2013 Lew Hofmann

    Activities for Problem #2 Time Precedents

    A Demolition of present structures 3 None

    B Excavation and filling of site 2 A

    C Forming & pouring of concrete 2 BD Construction of steel skeleton 3 C

    E Construction of concrete structure 2 C

    F Construction of exterior skin 1 D,E

    G Installation of plumbing 3 E

    H Installation of electrical 3 D,E

    I Installation of heating & cooling 3 D,E,F

    J Construction of interior flooring 3 I

    K Lighting fixtures and finish work 2 J

    1. There are logic errorsin the data. You will have to run the program in orderto find them. Then make the appropriate corrections and re-run the problemto get the correct solution. Identify the critical path and its length.

    2. Include 4 printouts:Input screen, PERT/CPM results table, Precedencegraph and the Gantt chart of early & late times.

    2013 Lew Hofmann

  • 8/13/2019 4 Project Mgt

    62/69

    Problem #3

  • 8/13/2019 4 Project Mgt

    63/69

    2013 Lew Hofmann

    Activity Precedent Optimistic Most Likely Pessimistic

    A - 6 7 8

    B A 4 4 4

    C A 5 6 8

    D B 8 10 10

    E B 7 10 15F C 9 9 13

    G C 7 7 7

    H D 4 6 8I E, F 6 9 11

    J G 8 9 10

    K H, I, J 3 5 6

    Problem #3

    2013 Lew Hofmann

  • 8/13/2019 4 Project Mgt

    64/69

    2013 Lew Hofmann

    Sample POM/QM

  • 8/13/2019 4 Project Mgt

    65/69

    2013 Lew Hofmann

    Sample POM/QM

    Input Tab le Prin tou t

    Note that this is CPM since there is only one time estimate foreach activity. You will need to change the method for PERT.

    S l POM/QM

  • 8/13/2019 4 Project Mgt

    66/69

    2013 Lew Hofmann

    Sample POM/QM

    Solut ion Tab le pr intou t

  • 8/13/2019 4 Project Mgt

    67/69

  • 8/13/2019 4 Project Mgt

    68/69

  • 8/13/2019 4 Project Mgt

    69/69

    POM/QM Print ing Hin t

    Avoid using the print screen button on the bottom left

    of the screen or in the file menu.

    Screen prints are small and very hard to read.

    Select the File pull-down menu and use the Printoption.

    You can then indicate which items you wish to print

    and get a much better output.

    OPTION: Download the free program Jing. It is

    available for Mac and PC, and what I use for the

    printouts on my PPT slides.

    htt // t h ith /ji ht l

    http://www.techsmith.com/jing.htmlhttp://www.techsmith.com/jing.html