Aids to Navigation Report

MALAYSIA

41TH

MEETING OF THE TRIPARTITE TECHNICAL

EXPERT GROUP

28-29 SEPTEMBER 2016

YOGYAKARTA

Page 2: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIAAids to Navigation Work Scope

Lighthouse

i. One Fathom Bank

ii. Bukit Jugra

iii. Bukit Segenting

iv. Pulau Undan

v. Tanjung Tuan

C&S

Maintenance

Maintenance

Restoration

Maintenance

Light Beacon

i. Mudah Selatan

ii. Mudah Utara

iii. One Fathom Bank North

iv. Panjang Selatan

v. Panjang Utara

vi. Pulau Mungging

vii. Tanjung Gabang

viii. Tanjung Piai

ix. Tanjung Tohor

x. Tanjung Rhu

xi. Tompok Utara

C&S

C&S

Maintenance

Maintenance

Maintenance

Maintenance

C&S

Maintenance

Maintenance

Replacement

Maintenance

Resilient Light Beacon

i. Sepat

Maintenance

Light Buoy

i. Piai Maintenance

Page 3: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

C&S works:

OFB LH 2nd phase already tendered out and will

start work in 4th Quarter 2016 with estimated cost

USD 125,000.00

Tanjung Tuan Lighthouse C&S works was

completed on 9th September 2016 with actual cost

USD 120,885.00

Pulau Mungging Light Beacon C&S works was

complete on July 2016 with actual cost USD

97,000.00

Page 4: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

C&S works:• Mudah Selatan and Mudah Utara C&S

specification already completed and will be tender

out in October 2016. The works schedule will start

in 1st Quarter 2017 with estimated cost of USD

60,000.00 each

• Panjang Utara Light Beacon and Sepat Resilient

Light Beacon C&S works postponed for the next

few years as the light beacons still in good

condition.

• All the C&S work cost borne by Malaysia.

Page 5: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Pulau Undan Restoration Work

The restoration work for Pulau Undan Lighthouse

already completed on 5th August 2016

Total amount for balance project cost will be claim to

ANF on 4th quarter 2016

Total claim for reimbursement that already submitted

to ANF is USD 1,158,543.56

Balance to claim under ANF is USD 105,600.00

Page 6: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Pulau Undan Restoration Work

1. Lighthouse Front View

Page 7: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Pulau Undan Restoration Work

2. Lighthouse Rear View

Page 8: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Pulau Undan Restoration Work

3. Lighthouse Side View

Page 9: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Pulau Undan Restoration Work

4. Mess Block

Page 10: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Pulau Undan Restoration Work

Page 11: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Pulau Undan Restoration Work

5. Toilet

Page 12: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Pulau Undan Restoration Work

6. Storeroom

Page 13: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Pulau Undan Restoration Work

Page 14: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Spare and Electrical Parts

• Amount of spare and electrical

parts purchase USD 242,168.50.

Page 15: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Replacement Tanjung Rhu LB

Tanjung Rhu LB replacement work already

started 25 April 2016 and expect to

complete 25th November 2016 with actual

cost USD 1,099,575.00

Page 16: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Replacement Tanjung Rhu LB

Page 17: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

SummaryNo. Item Cost (USD) Remark

1. C&S work OFB LH 2nd Phase 125,000.00 Borne by

Malaysia

2. C&S work Tanjung Tuan 120,885.00 Borne by

Malaysia

3. C&S work Pulau Mungging

LB

97,000.00 Borne by

Malaysia

4. C&S work Mudah Selatan LB - Borne by

Malaysia

5. C&S work Mudah Utara LB - Borne by

Malaysia

Page 18: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

SummaryNo. Item Cost (USD) Remark

6. Restoration of Pulau Undan LH - Borne by ANF

7. Spare and Electrical Parts 242,168.50 Borne by

Malaysia

8. Replacement of Tanjung Rhu

LB

1,099,575.00 Borne by

Malaysia

9. ANF Inspection 15,000.00 Borne by

Malaysia

Total 1,699,628.50

Page 19: 41TH MEETING OF THE TRIPARTITE TECHNICAL EXPERT GROUP … D 5.1 Aids to Navigation in the... · Tanjung Piai ix. Tanjung Tohor x. Tanjung Rhu xi. Tompok Utara C&S C&S Maintenance

Aids to Navigation Report

MALAYSIA

Thank You