4.3 Nulec pole-mounted automatic control recloserDCWI
DCWI 4.3 Nulec pole-mounted automatic control recloser
2 of 3DM# 1648164Network Standard 11/2013
Network Standard 11/2013DM# 16481641 of 3
OBSERVE SAFETY LIFESAVERS
DISTRIBUTION COMMISSIONING WORK INSTRUCTION
4.3 NULEC POLE-MOUNTED AUTOMATIC CONTROL RECLOSER
Purpose: This instruction covers the testing and commissioning of all replacements or new installationsofNulecpolemounted automatic reclosers before energisation.
Note: The following tests must be carried out after installation and before the recloser isputintoservice.
Note: Bolts and screws in all electrical connections across the Western Power network must be properly tightened.
Address/Pole No.:
Work Package No.:_________________ SPIDAWeb Pick ID:
1. PRE-INSTALLATION CHECK
Earth resistance test and recloser nameplate
Ensure that the earth resistance test result is acceptable.
Ensure that switch rating matches the system voltage.
Note: Three-phase reclosers with internal voltage transformers (identified by three nameplates) can only be removed under an electrical access permit; an insulation resistance test between V1 and W1 is not applicable.
2. INSULATION RESISTANCE TEST (FOR A SINGLE-PHASE RECLOSER)
Use a 5kV insulation resistance tester. Measure the resistance after 1 minute of testing. Put the test recloser in the OFF (open contact) position. Operate the manual trip level if required.
Bushings
Test Results
Acceptable Results
Between contacts X & I
M
Not