48-Building a University on Liquiable Soils

Embed Size (px)

Citation preview

  • 8/17/2019 48-Building a University on Liquiable Soils

    1/36

    BUILDING A UNIVERSITY ONLIQUEFIABLE SOILS USING DYNAMIC

    COMPACTION

    Ravi Sundaram, Sanjay Gupta, Sorabh GuptaCENGRS GEOTECHNICA PVT. LTD.

  • 8/17/2019 48-Building a University on Liquiable Soils

    2/36

    Project Details

    Gautam Budh University at Greater Noida,

    Uttar Pradesh Covers an area of about 511 acres

    , ,cover 

    Site in the flood plains of the River Yamuna,

    about 2 km from river 

    2

  • 8/17/2019 48-Building a University on Liquiable Soils

    3/36

     Vicinity Map

    3

  • 8/17/2019 48-Building a University on Liquiable Soils

    4/36

     The Project 2007..

    4

  • 8/17/2019 48-Building a University on Liquiable Soils

    5/36

     The Project Today..

    5

  • 8/17/2019 48-Building a University on Liquiable Soils

    6/36

    .. And what it will be.

    6

  • 8/17/2019 48-Building a University on Liquiable Soils

    7/36

    Site Conditions

    Site is in Earthquake Zone IV - IS 1893: 2002

    Loose alluvium - fine sand (Yamuna Sand)

    Groundwater met at shallow depth

    an o - m ep s prone o que ac on Ground Improvement by Dynamic Compaction

    carried out for all buildings planned at site

    Each structure was individually assessed

    7

  • 8/17/2019 48-Building a University on Liquiable Soils

    8/36

    Benefits achieved

    Dynamic compaction successfully mitigated

    liquefaction potential Greater stability during earthquake

    Need for piling was eliminated and the buildings

    were supported on open foundations Substantial savings achieved – foundation cost was

    less than 50% of what would be required if piling

    was done Savings also achieved in time required to complete

    foundation construction

    8

  • 8/17/2019 48-Building a University on Liquiable Soils

    9/36

    Investigations Before CompactionInvestigations Before Compaction

    9

  • 8/17/2019 48-Building a University on Liquiable Soils

    10/36

    Investigations After CompactionInvestigations After Compaction

    10

  • 8/17/2019 48-Building a University on Liquiable Soils

    11/36

    Plethora of Data..

    Over 700 boreholes and200 static cone penetration

    es s comp e e n eUniversity area over a

    period of 3 years

    11

  • 8/17/2019 48-Building a University on Liquiable Soils

    12/36

     This Paper Presents..

    Ground Improvement by

    DYNAMIC COMPACTIONDYNAMIC COMPACTION done for 

    FACULTY BLOCKFACULTY BLOCK

    as an ustrat ve examp e o t e woras an ustrat ve examp e o t e wordone and extent of improvementdone and extent of improvementachievedachieved

    The need for piling was eliminatedThe need for piling was eliminatedresulting in substantial savingsresulting in substantial savings

    12

  • 8/17/2019 48-Building a University on Liquiable Soils

    13/36

    Faculty Block Location

    13

  • 8/17/2019 48-Building a University on Liquiable Soils

    14/36

    Scope of Work- Faculty Block 

     At Faculty Block:

    Before Compaction:

    4 boreholes – 15 m

    1 SCPT

     After Compaction: 4 boreholes – 15 m

    1 SCPT

    14

  • 8/17/2019 48-Building a University on Liquiable Soils

    15/36

    Before Compaction

    15

  • 8/17/2019 48-Building a University on Liquiable Soils

    16/36

     After Compaction

    16

  • 8/17/2019 48-Building a University on Liquiable Soils

    17/36

    Borehole Data – Before Compaction

    SPT values

    typically 10-15 to

    8 m depth

     

    5-10 %

    Groundwater at 4-

    5 m depth, mayrise to GL

    17

  • 8/17/2019 48-Building a University on Liquiable Soils

    18/36

    Liquefaction Assessment

    Seed & Idriss (1971) method – NCEER

    Summary Report

    Cyclic Stress Ratio (CSR)

    Maximum Credible Earthquake (MCE)

    Design Earthquake Magnitude: 6.7

    Peak Ground Acceleration: 0.24g

    18

  • 8/17/2019 48-Building a University on Liquiable Soils

    19/36

    Liquefaction Assessment

    Cyclic Resistance Ratio (CRR) determined

    from SPT & SCPT  As per the analysis, the fine sands to 8 m

    liquefaction in the event of the designearthquake

    19

  • 8/17/2019 48-Building a University on Liquiable Soils

    20/36

    Dynamic Compaction

    Dropping a heavy

    weight can compact

    loose sands to

    substantial depth Effective for sands

    only

    Done on a grid pattern

    20

  • 8/17/2019 48-Building a University on Liquiable Soils

    21/36

    Conceptual Illustration

    The maximum depth of improvement

    (Df ) at the project site was estimated

    using Mitchell & Katt i, 1981:

    where

    n = modification factor (taken as 0.7)

    W = weight of pounder, and

    H = height of drop

    n= n=

    21

  • 8/17/2019 48-Building a University on Liquiable Soils

    22/36

    Compaction Details

    Conventional Crane – 

    TLC 955A Compaction in 3 Phases:

    Ironing Phase

    1 week time lag in

    between – to allow porepressures to dissipate

    22

  • 8/17/2019 48-Building a University on Liquiable Soils

    23/36

    Compaction Phase

     Area divided into 4 x 4 m grids

    11.65 T pounder falling from

    height of 14 m

     

    Energy Imparted: 1600 kN-m

    Corresponding depth of

    improvement: 9 m

    2nd Phase staggered 2 m

    23

  • 8/17/2019 48-Building a University on Liquiable Soils

    24/36

    Ironing Phase

    Craters filled with GSB Grade II

    material

    Hammer weight: 11.65 T

     

    No. of drops: 5

    Energy: 2114 kN-m

     Area graded with 10 passes

    of 10 T vibratory roller 

    24

  • 8/17/2019 48-Building a University on Liquiable Soils

    25/36

    SPT before compaction

    25

  • 8/17/2019 48-Building a University on Liquiable Soils

    26/36

    SPT before & after compaction

    75 % Improvement to

    about 4 m depth

    25~30 % Improvement to

    about 10 m depth

    26

  • 8/17/2019 48-Building a University on Liquiable Soils

    27/36

    SPT & SCPT before & after

    compaction

    75 % Improvement to

    4 m depth

    25~30 % Improvement to

    10 m depth

    27

  • 8/17/2019 48-Building a University on Liquiable Soils

    28/36

    SPT & SCPT before & after

    compaction

    50-170 % Improvement

    to 4 m depth

    25~50 % Improvement

    to 10 m depth

    28

  • 8/17/2019 48-Building a University on Liquiable Soils

    29/36

    Extent of Improvement Achieved

     After Compaction, N>20, qc > 50 MPa

    Peak Improvement: Between 1 and 5 m

    Improvement below 10 m depth is

    marginal

    29

  • 8/17/2019 48-Building a University on Liquiable Soils

    30/36

    CRR Evaluation (Before Compaction)

    30

  • 8/17/2019 48-Building a University on Liquiable Soils

    31/36

    CRR Evaluation (After Compaction)

     After Compaction, CRR > CSR After Compaction, CRR > CSR

    31

  • 8/17/2019 48-Building a University on Liquiable Soils

    32/36

    FOS against Liquefaction

    (based on SPT & SCPT)

       f   i  a   b   l  e

       Z  o  n  e

       L   i  q  u  e

    No LiquefactionLiquefaction to

    8m depth

    Before Compaction After Compaction

    32

  • 8/17/2019 48-Building a University on Liquiable Soils

    33/36

    Liquefaction Mitigation

    Untreated ground (before compaction) is

    susceptible to liquefaction to 8 m depth  After compaction, Factor of Safety against

    >

    Susceptibility to liquefactionSusceptibil ity to liquefaction

    successfully mitigatedsuccessfully mitigated

    33

  • 8/17/2019 48-Building a University on Liquiable Soils

    34/36

    Foundation Selection

    For unimproved ground, pile foundations transferringthe loads below the liquefiable zone would benecessary. Pile lengths would be on the order of 15to 20 m

    O en foundations on im roved round: Isolated 

    footings with connecting beam Design Net Bearing Pressure: 175 kPa175 kPa

    RESULTED IN SUBSTANTIAL SAVINGSRESULTED IN SUBSTANTIAL SAVINGSIN COST AND CONSTRUCTION TIMEIN COST AND CONSTRUCTION TIME

    34

  • 8/17/2019 48-Building a University on Liquiable Soils

    35/36

    Concluding Remarks

    Case Study demonstrates successful

    mitigation of liquefaction potential by use ofdynamic compaction

     

    Field trials are necessary to confirm feasibility

    Sufficient in-situ testing before and after

    improvement should be done to confirmefficacy of the improvement

    35

  • 8/17/2019 48-Building a University on Liquiable Soils

    36/36

    Thank You!Thank You!

    36