Upload
al-ain-homes
View
221
Download
0
Embed Size (px)
Citation preview
8/17/2019 48-Building a University on Liquiable Soils
1/36
BUILDING A UNIVERSITY ONLIQUEFIABLE SOILS USING DYNAMIC
COMPACTION
Ravi Sundaram, Sanjay Gupta, Sorabh GuptaCENGRS GEOTECHNICA PVT. LTD.
8/17/2019 48-Building a University on Liquiable Soils
2/36
Project Details
Gautam Budh University at Greater Noida,
Uttar Pradesh Covers an area of about 511 acres
, ,cover
Site in the flood plains of the River Yamuna,
about 2 km from river
2
8/17/2019 48-Building a University on Liquiable Soils
3/36
Vicinity Map
3
8/17/2019 48-Building a University on Liquiable Soils
4/36
The Project 2007..
4
8/17/2019 48-Building a University on Liquiable Soils
5/36
The Project Today..
5
8/17/2019 48-Building a University on Liquiable Soils
6/36
.. And what it will be.
6
8/17/2019 48-Building a University on Liquiable Soils
7/36
Site Conditions
Site is in Earthquake Zone IV - IS 1893: 2002
Loose alluvium - fine sand (Yamuna Sand)
Groundwater met at shallow depth
an o - m ep s prone o que ac on Ground Improvement by Dynamic Compaction
carried out for all buildings planned at site
Each structure was individually assessed
7
8/17/2019 48-Building a University on Liquiable Soils
8/36
Benefits achieved
Dynamic compaction successfully mitigated
liquefaction potential Greater stability during earthquake
Need for piling was eliminated and the buildings
were supported on open foundations Substantial savings achieved – foundation cost was
less than 50% of what would be required if piling
was done Savings also achieved in time required to complete
foundation construction
8
8/17/2019 48-Building a University on Liquiable Soils
9/36
Investigations Before CompactionInvestigations Before Compaction
9
8/17/2019 48-Building a University on Liquiable Soils
10/36
Investigations After CompactionInvestigations After Compaction
10
8/17/2019 48-Building a University on Liquiable Soils
11/36
Plethora of Data..
Over 700 boreholes and200 static cone penetration
es s comp e e n eUniversity area over a
period of 3 years
11
8/17/2019 48-Building a University on Liquiable Soils
12/36
This Paper Presents..
Ground Improvement by
DYNAMIC COMPACTIONDYNAMIC COMPACTION done for
FACULTY BLOCKFACULTY BLOCK
as an ustrat ve examp e o t e woras an ustrat ve examp e o t e wordone and extent of improvementdone and extent of improvementachievedachieved
The need for piling was eliminatedThe need for piling was eliminatedresulting in substantial savingsresulting in substantial savings
12
8/17/2019 48-Building a University on Liquiable Soils
13/36
Faculty Block Location
13
8/17/2019 48-Building a University on Liquiable Soils
14/36
Scope of Work- Faculty Block
At Faculty Block:
Before Compaction:
4 boreholes – 15 m
1 SCPT
After Compaction: 4 boreholes – 15 m
1 SCPT
14
8/17/2019 48-Building a University on Liquiable Soils
15/36
Before Compaction
15
8/17/2019 48-Building a University on Liquiable Soils
16/36
After Compaction
16
8/17/2019 48-Building a University on Liquiable Soils
17/36
Borehole Data – Before Compaction
SPT values
typically 10-15 to
8 m depth
5-10 %
Groundwater at 4-
5 m depth, mayrise to GL
17
8/17/2019 48-Building a University on Liquiable Soils
18/36
Liquefaction Assessment
Seed & Idriss (1971) method – NCEER
Summary Report
Cyclic Stress Ratio (CSR)
Maximum Credible Earthquake (MCE)
Design Earthquake Magnitude: 6.7
Peak Ground Acceleration: 0.24g
18
8/17/2019 48-Building a University on Liquiable Soils
19/36
Liquefaction Assessment
Cyclic Resistance Ratio (CRR) determined
from SPT & SCPT As per the analysis, the fine sands to 8 m
liquefaction in the event of the designearthquake
19
8/17/2019 48-Building a University on Liquiable Soils
20/36
Dynamic Compaction
Dropping a heavy
weight can compact
loose sands to
substantial depth Effective for sands
only
Done on a grid pattern
20
8/17/2019 48-Building a University on Liquiable Soils
21/36
Conceptual Illustration
The maximum depth of improvement
(Df ) at the project site was estimated
using Mitchell & Katt i, 1981:
where
n = modification factor (taken as 0.7)
W = weight of pounder, and
H = height of drop
n= n=
21
8/17/2019 48-Building a University on Liquiable Soils
22/36
Compaction Details
Conventional Crane –
TLC 955A Compaction in 3 Phases:
Ironing Phase
1 week time lag in
between – to allow porepressures to dissipate
22
8/17/2019 48-Building a University on Liquiable Soils
23/36
Compaction Phase
Area divided into 4 x 4 m grids
11.65 T pounder falling from
height of 14 m
Energy Imparted: 1600 kN-m
Corresponding depth of
improvement: 9 m
2nd Phase staggered 2 m
23
8/17/2019 48-Building a University on Liquiable Soils
24/36
Ironing Phase
Craters filled with GSB Grade II
material
Hammer weight: 11.65 T
No. of drops: 5
Energy: 2114 kN-m
Area graded with 10 passes
of 10 T vibratory roller
24
8/17/2019 48-Building a University on Liquiable Soils
25/36
SPT before compaction
25
8/17/2019 48-Building a University on Liquiable Soils
26/36
SPT before & after compaction
75 % Improvement to
about 4 m depth
25~30 % Improvement to
about 10 m depth
26
8/17/2019 48-Building a University on Liquiable Soils
27/36
SPT & SCPT before & after
compaction
75 % Improvement to
4 m depth
25~30 % Improvement to
10 m depth
27
8/17/2019 48-Building a University on Liquiable Soils
28/36
SPT & SCPT before & after
compaction
50-170 % Improvement
to 4 m depth
25~50 % Improvement
to 10 m depth
28
8/17/2019 48-Building a University on Liquiable Soils
29/36
Extent of Improvement Achieved
After Compaction, N>20, qc > 50 MPa
Peak Improvement: Between 1 and 5 m
Improvement below 10 m depth is
marginal
29
8/17/2019 48-Building a University on Liquiable Soils
30/36
CRR Evaluation (Before Compaction)
30
8/17/2019 48-Building a University on Liquiable Soils
31/36
CRR Evaluation (After Compaction)
After Compaction, CRR > CSR After Compaction, CRR > CSR
31
8/17/2019 48-Building a University on Liquiable Soils
32/36
FOS against Liquefaction
(based on SPT & SCPT)
f i a b l e
Z o n e
L i q u e
No LiquefactionLiquefaction to
8m depth
Before Compaction After Compaction
32
8/17/2019 48-Building a University on Liquiable Soils
33/36
Liquefaction Mitigation
Untreated ground (before compaction) is
susceptible to liquefaction to 8 m depth After compaction, Factor of Safety against
>
Susceptibility to liquefactionSusceptibil ity to liquefaction
successfully mitigatedsuccessfully mitigated
33
8/17/2019 48-Building a University on Liquiable Soils
34/36
Foundation Selection
For unimproved ground, pile foundations transferringthe loads below the liquefiable zone would benecessary. Pile lengths would be on the order of 15to 20 m
O en foundations on im roved round: Isolated
footings with connecting beam Design Net Bearing Pressure: 175 kPa175 kPa
RESULTED IN SUBSTANTIAL SAVINGSRESULTED IN SUBSTANTIAL SAVINGSIN COST AND CONSTRUCTION TIMEIN COST AND CONSTRUCTION TIME
34
8/17/2019 48-Building a University on Liquiable Soils
35/36
Concluding Remarks
Case Study demonstrates successful
mitigation of liquefaction potential by use ofdynamic compaction
Field trials are necessary to confirm feasibility
Sufficient in-situ testing before and after
improvement should be done to confirmefficacy of the improvement
35
8/17/2019 48-Building a University on Liquiable Soils
36/36
Thank You!Thank You!
36