4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

Embed Size (px)

Citation preview

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    1/27

    Four-Dimensional Visualization of

    Construction Scheduling and Site

    Utilization

    K. W. Chau; M. Anson; and J. P. Zhang

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    2/27

    Outline

    Abstract

    Introduction to 4D

    Example case The developed system

    Conclusion and discussion

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    3/27

    Abstract

    Site management are at times lacking inthe following areas:

    generation of site usage layouts

    estimation ofquantities of constructionmaterials

    cost evaluation

    The objective of this work is to enablevisual study of the effects ofjob progresson the logistics and resource schedules.

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    4/27

    (1) Introduction to 4D

    What is different in the before?

    Why we need 4D?

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    5/27

    State of construction before

    A major characteristic of a contemporary

    construction project is its complex and

    multidisciplinary nature.

    That for most construction projects, the

    clients requirements are still represented

    in terms ofpaper-based working drawings.

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    6/27

    Site planning

    In this process, planners have to take intoconsideration practical constructionsequence, proper workspace logistics, and

    feasible resource allocation, and the useof site space.

    In practice, the initial site layout drawingsthat show the site organization andutilization are normally not updated asconstruction progresses.

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    7/27

    State of computer tools before

    contemporary computer-aided toolsincluding bar charts orcritical path methodnetwork charts can only represent the

    schedule, but not the spatial features orthe associated resource requirements.

    Visual representations of the project atdifferent instants cannot be provided

    project progress

    status of site space usage

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    8/27

    Site management

    Si t e

    Pl at e

    St eelWorkspace

    et c. . . .

    where t o put ?when t o put ?

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    9/27

    Tradition

    si t e

    can you f i ne any er ror?

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    10/27

    4D

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    11/27

    (2) Example case

    The system developed in this research

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    12/27

    Building background

    Tradeport Logistic Center

    a three-story warehouse building site

    during the actual construction of the project, in order

    to verify and validate its performance in real practice. The construction period for the structural works

    was from January to October 2002.

    The client, The Hong Kong Land Company

    Limited

    The contractor, Gammon Skanska Limited

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    13/27

    Input of building story

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    14/27

    Input data of various elements and their relationships

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    15/27

    Input of segment and associated scheduling

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    16/27

    Some predefined templates of construction activities

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    17/27

    4D visualization linking 3D geometrical model with schedule

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    18/27

    4D state being updated

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    19/27

    4D visualization on projected data

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    20/27

    (3) The system developed in

    this research

    How to develop this system?

    What is the system architecture?

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    21/27

    Characteristics of 4D Visualization

    Model in this research

    Generation 4D visualization model

    3D geometrical model

    associated schedule of activities.

    to enhance its capability to carry out usefulsite management functions overdifferentspatial and temporal domains.

    visualized planning Analysis for each activity, material

    allocation, and cost breakdown.

    Bidi i l D E h b

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    22/27

    Bidirectional Data Exchange between

    3D Model and

    Schedule This model allows bidirectional data exchange

    between the 3D geometrical model and theproject schedule.

    to update the construction plan eitherthrough 3D graphical environment bar chart scheduling environment.

    If the timing of a certain activity is modified

    graphically on the screen, synchronizedadjustment of that activity will be madeautomatically to the bar schedule

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    23/27

    Architecture of 4D Visualization Model

    MS Project

    Construction

    SchedulingData

    Visual C++

    Construction

    Processor

    AutoCAD

    3D Geometrical

    Module

    AutoCAD ObjectARX

    4D Visualization Module

    Micrsoft OLAPData Warehouse

    User Interface

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    24/27

    Architecture of 4D Visualization

    Model

    4D Visualization Module withAutoCAD

    ObjectARX

    Construction Processorwith Visual C++

    Key instrument for changing data

    3D Geometrical Model underAutoCAD

    Environment

    Bar Chart Scheduling with Microsoft Project Data Warehouse with Microsoft OLAP

    User Interface with Visual C++

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    25/27

    (4) Conclusion and discussion

    It is almost to end.

    Wake up and wait to finish class.

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    26/27

    Conclusions

    a prototype 4D visualization model has

    been developed

    This 4D visualization model

    activity schedule

    associated allocation ofresources

    layout of site facilities at any projected instant.

    resulting in a user-friendly and integrated

    site management tool.

  • 7/27/2019 4D Four Dimensional Visualization of Construction Scheduling & Site Utilization

    27/27

    Discussion

    This system are bonded with AutoCad and

    Microsoft project. If we want to sell this

    system, how can we deal with the license

    problem?

    Did you have any suggestion for this

    system? How do you think of an online

    version of 4D software?