14
742 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 29, NO. 2, MARCH 2014 Optimal PMU Placement Considering Controlled Islanding of Power System Lei Huang, Student Member, IEEE, Yuanzhang Sun, Senior Member, IEEE, Jian Xu, Member, IEEE, Wenzhong Gao, Senior Member, IEEE, Jun Zhang, Member, IEEE, and Ziping Wu, Student Member, IEEE Abstract—This paper proposes an optimal phasor measurement unit (PMU) placement model considering power system con- trolled islanding so that the power network remains observable under controlled islanding condition as well as normal operation condition. The optimization objectives of proposed model are to minimize the number of installed PMUs and to maximize the measurement redundancy. These two objectives are combined together with a weighting variable so that the optimal solution with minimum PMU number and maximum measurement redun- dancy would be obtained from the model. To reduce the number of required PMUs, the effect of zero-injection bus is considered and incorporated into the model. Furthermore, additional constraints for maintaining observability following single PMU failure or line loss are also derived. At last, several IEEE standard systems and the Polish 2383-bus system are employed to test the presented model. Results are presented to demonstrate the effectiveness of the proposed method. Index Terms—Controlled islanding, integer linear program- ming, measurement redundancy, optimal phasor measurement unit (PMU) placement, state estimation. I. INTRODUCTION S TATE estimator plays an important role in the security of power system operation. Its main purpose is to precisely estimate the voltage phasors of all system buses based on a set of acquired measurements [1]. When a measurement set al- lows a unique solution of the state estimation (SE) problem, the power system is said to be observable [2]. Recently phasor mea- surement units (PMUs) have been used as measurement device for SE, which will advance the traditional supervisory control and data acquisition (SCADA) system. PMU provides voltage phasor of the bus where it is installed and current phasors of all branches incident to that bus [3]. The PMU measurements from different buses, which are synchronized by the common clock signal from global positioning system (GPS), can help simplify Manuscript received February 16, 2013; revised June 04, 2013 and September 07, 2013; accepted October 06, 2013. Date of publication November 04, 2013; date of current version February 14, 2014. This work was supported in part by the National Natural Science Foundation of China under Grant 51007067 and the Ministry of Science and Technology of China under Grant 2012AA050218. Paper no. TPWRS-00198-2013. L. Huang, Y. Sun, and J. Xu (corresponding author) are with the School of Electrical Engineering, Wuhan University, Wuhan, Hubei 430072, China (e-mail: [email protected]; [email protected]; [email protected]). W. Gao, J. Zhang, and Z. Wu are with the Department of Electrical and Computer Engineering, University of Denver, Denver, CO 80210 USA (e-mail: [email protected]; [email protected]; [email protected]). Color versions of one or more of the gures in this paper are available online at http://ieeexplore.ieee.org. Digital Object Identier 10.1109/TPWRS.2013.2285578 the process of state estimation and improve the accuracy of es- timation results. If we place PMUs in all busses of a network, all the voltage phasors can be directly measured without run- ning any state estimator [4]. However, PMU and its associated communication facilities are costly. Furthermore, the voltage phasor of the bus incident to the bus with PMU installed can be computed with branch parameter and branch current phasor measurement [5]. So it is neither economical nor necessary to install PMUs at all system buses. Thus, one of the important is- sues is to nd the optimal number and placement of PMUs for power system state estimation. Optimal PMU placement (OPP) is rstly attempted in [6], formulating as a combinatorial optimization problem of min- imizing the PMU number for system observability. In recent literatures, the OPP model has been generalized to include additional constraints or contingencies. In [7], an integer pro- gramming formulation of OPP problem is proposed with the presence of conventional measurements. A generalized integer linear programming (ILP) formulation for OPP is presented in [8], considering effects of zero-injection buses (ZIBs) and conventional measurements. The model proposed in [9] takes into account PMU channel limitations. Contingency conditions of line outage or PMU loss are considered separately or si- multaneously in the OPP model proposed in [10]. Generally, the existing OPP models concerns about the determination of minimum number and optimal location set of PMUs, ensuring that the entire power system remains a single observable island [1]. In another word, these models can only handle the cases in which the power system is operated as a single and inte- grated network. However, some severe faults may lead parts of the network to angle, frequency or voltage instability. In that case, trying to maintain system integrity and operate the system entirely interconnected is very difcult and may cause propagation of local weaknesses to other parts of the system [11]. As a solution, controlled islanding (CI) is employed by system operators, in which the interconnected power system is separated into several planned islands prior to catastrophic events [12], [13]. After system splitting, wide area blackout can be avoided because the local instability is isolated and prevented from further spreading [14]. In order to operate each island with power balancing and stability after controlled islanding, it is essential to provide an OPP scheme which can keep the network observable for the post-islanding condition as well as normal condition. After having determined the model of OPP, many investiga- tors have presented different methods to solve this optimization problem. These methods can be generally divided into math- ematical and heuristic algorithms [1]. The representative mathematical algorithm is ILP [7]–[10], which is capable of solving large-scale problems in a short time and achieving the globally optimal solution. Exhaustive search [15] is another 0885-8950 © 2013 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.

5-Optimal PMU Placement Considering Controlled Islanding of Power System

Embed Size (px)

Citation preview

  • 742 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 29, NO. 2, MARCH 2014

    Optimal PMU Placement ConsideringControlled Islanding of Power System

    Lei Huang, Student Member, IEEE, Yuanzhang Sun, Senior Member, IEEE, Jian Xu, Member, IEEE,Wenzhong Gao, Senior Member, IEEE, Jun Zhang, Member, IEEE, and Ziping Wu, Student Member, IEEE

    AbstractThis paper proposes an optimal phasor measurementunit (PMU) placement model considering power system con-trolled islanding so that the power network remains observableunder controlled islanding condition as well as normal operationcondition. The optimization objectives of proposed model areto minimize the number of installed PMUs and to maximize themeasurement redundancy. These two objectives are combinedtogether with a weighting variable so that the optimal solutionwith minimum PMU number and maximum measurement redun-dancy would be obtained from the model. To reduce the number ofrequired PMUs, the effect of zero-injection bus is considered andincorporated into the model. Furthermore, additional constraintsfor maintaining observability following single PMU failure or lineloss are also derived. At last, several IEEE standard systems andthe Polish 2383-bus system are employed to test the presentedmodel. Results are presented to demonstrate the effectiveness ofthe proposed method.

    Index TermsControlled islanding, integer linear program-ming, measurement redundancy, optimal phasor measurementunit (PMU) placement, state estimation.

    I. INTRODUCTION

    S TATE estimator plays an important role in the security ofpower system operation. Its main purpose is to preciselyestimate the voltage phasors of all system buses based on aset of acquired measurements [1]. When a measurement set al-lows a unique solution of the state estimation (SE) problem, thepower system is said to be observable [2]. Recently phasor mea-surement units (PMUs) have been used as measurement devicefor SE, which will advance the traditional supervisory controland data acquisition (SCADA) system. PMU provides voltagephasor of the bus where it is installed and current phasors of allbranches incident to that bus [3]. The PMU measurements fromdifferent buses, which are synchronized by the common clocksignal from global positioning system (GPS), can help simplify

    Manuscript received February 16, 2013; revised June 04, 2013 and September07, 2013; accepted October 06, 2013. Date of publication November 04, 2013;date of current version February 14, 2014. This work was supported in part bythe National Natural Science Foundation of China under Grant 51007067 andthe Ministry of Science and Technology of China under Grant 2012AA050218.Paper no. TPWRS-00198-2013.L. Huang, Y. Sun, and J. Xu (corresponding author) are with the

    School of Electrical Engineering, Wuhan University, Wuhan, Hubei430072, China (e-mail: [email protected]; [email protected];[email protected]).W. Gao, J. Zhang, and Z. Wu are with the Department of Electrical and

    Computer Engineering, University of Denver, Denver, CO 80210 USA (e-mail:[email protected]; [email protected]; [email protected]).Color versions of one or more of the figures in this paper are available online

    at http://ieeexplore.ieee.org.Digital Object Identifier 10.1109/TPWRS.2013.2285578

    the process of state estimation and improve the accuracy of es-timation results. If we place PMUs in all busses of a network,all the voltage phasors can be directly measured without run-ning any state estimator [4]. However, PMU and its associatedcommunication facilities are costly. Furthermore, the voltagephasor of the bus incident to the bus with PMU installed canbe computed with branch parameter and branch current phasormeasurement [5]. So it is neither economical nor necessary toinstall PMUs at all system buses. Thus, one of the important is-sues is to find the optimal number and placement of PMUs forpower system state estimation.Optimal PMU placement (OPP) is firstly attempted in [6],

    formulating as a combinatorial optimization problem of min-imizing the PMU number for system observability. In recentliteratures, the OPP model has been generalized to includeadditional constraints or contingencies. In [7], an integer pro-gramming formulation of OPP problem is proposed with thepresence of conventional measurements. A generalized integerlinear programming (ILP) formulation for OPP is presentedin [8], considering effects of zero-injection buses (ZIBs) andconventional measurements. The model proposed in [9] takesinto account PMU channel limitations. Contingency conditionsof line outage or PMU loss are considered separately or si-multaneously in the OPP model proposed in [10]. Generally,the existing OPP models concerns about the determination ofminimum number and optimal location set of PMUs, ensuringthat the entire power system remains a single observable island[1]. In another word, these models can only handle the casesin which the power system is operated as a single and inte-grated network. However, some severe faults may lead partsof the network to angle, frequency or voltage instability. Inthat case, trying to maintain system integrity and operate thesystem entirely interconnected is very difficult and may causepropagation of local weaknesses to other parts of the system[11]. As a solution, controlled islanding (CI) is employed bysystem operators, in which the interconnected power systemis separated into several planned islands prior to catastrophicevents [12], [13]. After system splitting, wide area blackoutcan be avoided because the local instability is isolated andprevented from further spreading [14]. In order to operateeach island with power balancing and stability after controlledislanding, it is essential to provide an OPP scheme which cankeep the network observable for the post-islanding condition aswell as normal condition.After having determined the model of OPP, many investiga-

    tors have presented different methods to solve this optimizationproblem. These methods can be generally divided into math-ematical and heuristic algorithms [1]. The representativemathematical algorithm is ILP [7][10], which is capable ofsolving large-scale problems in a short time and achieving theglobally optimal solution. Exhaustive search [15] is another

    0885-8950 2013 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.

    ROCARSALResaltado

    UsuarioNota adhesivaun modelo de colocacin optima de PMU, que considera la observabilidad del sistema en isla y normal

    UsuarioNota adhesivaLas unidades de medicin de fasores Recientemente se han utilizado como dispositivo de medicin para la estimacin de estado, que har avanzar el control de supervisin y adquisicin tradicional de datos (SCADA)

  • HUANG et al.: OPTIMAL PMU PLACEMENT CONSIDERING CONTROLLED ISLANDING OF POWER SYSTEM 743

    mathematical method used for OPP. However, it is not suitablefor large-scale systems with huge search space. Among theheuristic optimization algorithms, genetic algorithm [16], Tabusearch [17], simulated annealing [6], differential evolution[18], particle swarm optimization [19], immunity algorithm[20], iterated local search [21], spanning tree search [22], andgreedy algorithm [23] have been developed. In spite of someadvantages, the major disadvantage associated with intelligentsearch-based methods is that they do not guarantee that aglobally optimal solution is found [15].In this paper, an ILP model of OPP considering controlled is-

    landing (OPP-CI) is proposed. This model is able to determinethe minimal number and optimal location set of PMUs in orderto provide the full network observability in normal operation aswell as in controlled islanding scenario. To distinguish multipleoptimal solutions, measurement redundancy is incorporated intothe optimization objective. Meanwhile the effect of ZIBs is con-sidered for further reducing the number of required PMUs. Inaddition, to enhance the robustness of OPP scheme, the contin-gencies of single PMU or line outage are also incorporated intothe proposed OPP model.The rest of this paper is structured as follows. In Section II,

    the concepts and rules of network observability are introducedand the basic OPP formulation is described. The derivation ofOPP model considering controlled islanding is introduced withdetails in Section III. In Section IV, contingencies of singlePMU or line outage are incorporated into OPP-CI model indi-vidually or simultaneously. In Section V the performance of theproposed new model is assessed using several IEEE standardsystems and a practical 2383-bus system. Finally, conclusionsare given in Section VI.

    II. BASIC FORMULATION OF OPTIMAL PMU PLACEMENT

    A. Observability Analysis Based on PMUs

    The observability of a system is the precondition for its stateestimation. Power system observability analysis is usually car-ried out in two different ways, namely, numerical observabilityanalysis and topological observability analysis [24]. Numericalobservability algorithm makes use of the gain matrix of stateestimation in a system. When the gain matrix is of full rank,the system is said to be numerically observable. However, dueto high computation burden of verifying the rank of the gainmatrix, this approach would not be preferred for practical ap-plications [19]. On the other hand, graph concept is utilized intopological observability methods. The network is consideredto be topologically observable if a spanning tree of full rankcan be found in the graph [25]. This tree connects all nodes andbranches observed by direct measurements or calculations.Observability analysis with phasor measurements has been

    studied in a number of literatures. A method to combine phasormeasurements and conventional measurements in observabilityanalysis is firstly proposed in [26] and then improved in [27]. Itis able to handle not only systems including only phasor mea-surements, but also the ones with both phasor measurementsand conventional measurements. Additionally, current phasormeasurements which lead to multiple-solutions can be detectedusing the proposedmethod. In [28], a direct numerical algorithmis presented to determine observable islands and restore observ-ability for power systems. The adoption of reduced networkmodel makes the proposed method computationally attractive.Based on PMUmeasurements as well as conventional measure-

    ments, a hybrid topological/numerical method for power systemobservability analysis is provided in [29], which shows goodperformance in simulations.In this paper the concept of topological observability is

    adopted and the following simple rules have been applied [19]. If voltage phasor and current phasor at one end of a branchare known, voltage phasor at the other end of that branchcan be obtained using Ohms law.

    If voltage phasors at both ends of a branch are known, thecurrent phasor through this branch can be calculated.

    The measurements such as bus voltage phasors and branchcurrent phasors, directly obtained from PMUs, are referred toas direct measurements; measurements derived by employingthe above two rules are referred to as indirect measurements,or pseudo measurements as in [30]. When the voltage phasorat a bus can be obtained either from direct measurements orindirect measurements, this bus is identified as observable. Inan observable network, each and every bus must be observed atleast once by using direct or indirect measurement.

    B. Basic Optimal PMU PlacementIn a power system network, the PMU placement at a bus can

    be seen as a binary decision variable defined as

    ifotherwise.

    (1)

    For a system with buses, therefore, the optimal PMU place-ment problem can be formulated as an integer linear program-ming problem as follows:

    (2)

    subject to constraints

    (3)

    where is the cost of installing a PMU at bus . Without loss ofgenerality, cost of PMU installation at each bus is assumedto be equal to 1 per unit in the present study.

    refers to the number of times that the th bus is observedthrough PMU measurements.

    is the th entry of network connectivity matrixdefined as

    ifotherwise.

    (4)

    For example, with (2), minimizing the number of PMUsfor the IEEE 14-bus system (Fig. 1) can be formulated asfollows:

    (5)

    where are PMU placement variables that are generatedby binary integer programming. Therefore, (5) represents theminimum number of PMUs.

    UsuarioResaltado

    UsuarioNota adhesivaLa observabilidad de un sistema es la condicin previa para la estimacin de estado. Anlisis de observacin del sistema de alimentacin se lleva a cabo por lo general en dos formas diferentes, a saber, el anlisis de observabilidad numrica y el anlisis de observabilidad topolgica

    UsuarioNota adhesivaSe adopta el concepto de observabilidad topolgica y aplica las siguientes reglas simples. Si se conocen fasor de voltaje y fasor de corriente en un extremo de una rama, el fasor de voltaje en el otro extremo de la rama se puede obtener usando la ley de Ohm. Si se conocen fasores de tensin en ambos extremos de una rama, el fasor de corriente a travs de esta rama se puede calcular.

    UsuarioNota adhesivaColocacin optima bsica de PMU en un sistema de potencia. que permite observar el sistema en condiciones normales de operacin.

  • 744 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 29, NO. 2, MARCH 2014

    Fig. 1. IEEE 14-bus system.

    The observability constraints (3) are listed explicitly asfollows:

    (6)

    The inequality constraints in (6) represent the requirementsof observed times for each of the 14 buses. For example, if atleast one PMU is installed on bus 1, 2 or 5, constraint issatisfied, and bus 1 will be observable. In Fig. 1, the 14-bussystem is made completely observable by placing 4 PMUs onbuses 2, 6, 7, and 9 [31], although this is not the only optimalsolution.

    III. OPTIMAL PMU PLACEMENT CONSIDERINGCONTROLLED ISLANDING

    A. Controlled Islanding

    Cascading failures are the most significant threats for powersystem security. Cascading failures together with additional linetripping can lead the system to uncontrolled splitting [11]. For-mation of uncontrolled islands with significant power imbalanceis the main reason for system blackouts. In order to avoid cat-astrophic wide area blackouts due to cascading failures, con-trolled islanding has been considered as an effective defensestrategy. The main advantages of controlled islanding of powersystems can be listed as follows [11]: It can separate weak and vulnerable areas from other stableparts of the system.

    Compared to the whole system, small subsystems areeasier to be handled and controlled under dynamic andemergency conditions.

    To date, a lot of investigations have been conducted on thistopic and various methods for controlled islanding [11][14],[32][35] have been proposed; for example, a method of con-trolled islanding with constraint of observability is presented in[36]. Since our research is focused on the OPP problem, thispaper does not study methods of controlled islanding in detailbut only uses the controlled islanding results of several IEEEstandard systems presented in [13], [34], and [35], and assumesa suitable controlled islanding scheme for the Polish 2383-bussystem. However, the proposed OPP method can be applied toany other controlled islanding schemes.After establishment of planned islands, there exist some

    factors which may threat the stability and integrity of eachisland, such as power imbalance, line overloading, voltage,angle and frequency instabilities, etc. [11]. Therefore, to main-tain static and dynamic stability, necessary load shedding andother control actions may be needed in each island, whichalways require real-time information throughout the island. Inaddition, real-time measurements in different islands shouldbe collected and analyzed together to determine whether andhow the power system can be restored to normal operation. Toensure the effectiveness of all the above actions, it is essentialto keep each island totally observable through properly placedPMUs. In other words, the optimal placement of PMUs shouldbe carried out in such a manner that the network remains ob-servable under controlled islanding condition as well as normaloperation condition.Compared to (3), the observability constraints of OPP-CI

    model are modified as follows:

    (7)

    where is the binary entry in the connectivity matrix forpost-islanding network, which is defined as

    ifotherwise. (8)

    For instance, assuming that the controlled islanding is in ef-fect for the IEEE 14-bus system following a cascading fault,as shown in [34] and Fig. 1, the whole system is separatedinto two subsystems and several lines are opened during the is-landing process. According to (7), the observability constraintsfor OPP-CI can be written explicitly as follows:

    (9)

    UsuarioNota adhesivaColocacin optima de PMU considerando el control del sistema con separacin en islas del anterior sistema en el cual se permita la observabilidad y el control del sistema en estas condiciones.

    UsuarioNota adhesivaventajas del islado de sistemas de potencia

    UsuarioResaltadoSe puede separar reas dbiles y vulnerables de otras partes estables del sistema.

    UsuarioNota adhesivaUnmarked definida por Usuario

    UsuarioResaltadoEn comparacin con el conjunto del sistema, subsistemas pequeos son ms fciles de ser manipulados y controlados bajo condiciones dinmicas y de emergencia.

    UsuarioNota adhesivaUnmarked definida por Usuario

  • HUANG et al.: OPTIMAL PMU PLACEMENT CONSIDERING CONTROLLED ISLANDING OF POWER SYSTEM 745

    Comparing (6) and (9), it is concluded that the observabilityconstraint shown in (7) is stricter than that in (3). Therefore, anOPP scheme subject to (7) can keep the power network com-pletely observable both for normal operation scenario and con-trolled islanding condition.

    B. Dealing With Multiple Optimal Solutions

    PMUs placement through the objective function (2) and in-equality constraints (7) may lead to multiple optimal solutionswith the same minimum number of PMUs. For the 14-bussystem in Fig. 1, installations of 5 PMUs in {1, 2, 6, 8, 9}, {1,4, 6, 7, 9}, {2, 5, 6, 8, 9}, {4, 5, 6, 7, 9}, and {4, 5, 6, 8, 9} canall satisfy the constraints (7) and lead the system to completeobservability in both normal operation condition and controlledislanding scenario.In this study, thus, maximizing the measurement redundancy

    is considered as an additional objective to pick out the most suit-able OPP scheme for power systems. Conventionally, measure-ment redundancy is defined as the ratio of the number of mea-surements (including direct measurements and indirect mea-surements) to the number of states [37]. Considering that themost important state variables in state estimation are bus voltagephasors, the measurement redundancy can be redefined as theratio of the number of voltage measurements to the number ofsystem buses. Moreover, the measurement redundancy under is-landing operation scenario as well as normal operation shouldbe considered.To keep consistency with (2) which is a minimization

    problem, the objective function of maximizing measurementredundancy is formulated as a minimization problem as well:

    (10)

    where is the total number of system buses; constant isthe maximum number of times that the th bus can be observedin normal operation, which equals to the number of its incidentlines plus one; variable represents the number of times thatthe th bus is observed by the solved OPP scheme in normaloperation; and refer to the corresponding constant andvariable in islanding operation condition, respectively; and

    are weighting factors assigned to the two componentsof the objective function. Since there is greater probability fora power system to be operated in normal condition than in is-landing condition, in this study and are set at 0.7and 0.3, respectively.Therefore, for the 14-bus system, set {4, 5, 6, 7, 9} is the most

    suitable solution because it has smaller value of than otherones, as shown in Table I.

    C. OPP Model Considering Controlled Islanding

    In this part, the problem of optimal PMU placement con-sidering controlled islanding is modeled. The objective ofOPP-CI is to minimize the number of installed PMUs and tomaximize the measurement redundancy with the full networkobservability for normal operation and controlled islandingscenarios as the constraints.1) OPP-CI Ignoring the Effect of Zero-Injection Bus: : The

    ZIBs refer to the network nodes without generation or load con-nected. A ZIB together with all its incident buses can be defined

    TABLE ICOMPARISON ON MEASUREMENT REDUNDANCY OF DIFFERENT

    OPP SOLUTIONS FOR IEEE 14-BUS SYSTEM

    as a zero injection cluster (ZIC). For a power network, if the in-fluence of ZIBs is ignored or the network does not contain anyZIBs at all, its OPP-CI model can be formed as

    (11)

    subject to observability constraints (7), where is theweighting factor.Here the two components of the objective function, and, stand for the considerations of PMU number (2) and mea-

    surement redundancy (10), respectively. The weighting factoris used to determine which factor is more dominant than the

    other one in the OPP procedure. In this study, reducing PMUnumber is selected as the more important objective. Note that

    is the number of incident lines to the th bus; letand . This way

    of specifying can ensure the value of to be less than1, which guarantees the priority of minimizing PMU numberin OPP-CI problem. As a result, the globally optimal solutionwith minimum PMU devices installed and maximum measure-ment redundancy can be found out.2) OPP-CI Considering the Effect of Zero-Injection Bus: If

    the effect of ZIBs is considered, the total number of PMUs inOPP problem will be reduced due to the following rules [20]: In a ZIC, if the zero-injection bus is observable and its ad-jacent buses are all observable except one, then the unob-servable bus will be identified as observable by applyingKirchhoffs current law (KCL) at ZIB.

    In a ZIC, if all the buses are observable except the zero-in-jection one, then the zero-injection bus can be also identi-fied as observable by using nodal equations.

    Combining these two cases can lead to the conclusion that aZIC is observable when it has at most one unobservable bus.Since this unobservable bus could become observable finallyby means of the properties of ZIC, in this paper, it is defined aspseudo unobservable bus.Assuming that is the index of the th zero-injection bus

    and is the th zero injection cluster, the auxiliary binaryvariable is defined so that implies that bus isthe pseudo unobservable bus in . Then the observabilityconstraint of can be mathematically formulated as

    (12)

    Notice that the power system could be operated in bothnormal operation condition and controlled islanding condition,and the elements of a ZIC may change due to the line tripping in

  • 746 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 29, NO. 2, MARCH 2014

    the process of islanding. Thus the incorporation of ZIB effectsinto OPP-CI problem should be simultaneously considered forthese two operation scenarios of power system.For an -bus power network with zero-injection buses,

    the observability constraints of OPP-CI considering the effectof ZIBs are listed as follows:

    (13)

    Here, and indicate the numbers of times that busis observed by means of the installed PMUs and the proper-ties of ZIC, in normal operation condition and controlled is-landing condition, respectively. On the other hand, the secondand fourth equations in (13) indicate that the number of pseudounobservable buses in a ZIC must be less than or equal to 1,for both normal scenario and islanding scenario. Therefore, theconstraints in (13) simultaneously ensure that one of the busesin a ZIC will be observable when it can be reached by PMUs,or it is the only pseudo unobservable bus in this ZIC.

    IV. OPP-CI FORMULATION AGAINST SINGLEPMU LOSS OR SINGLE LINE OUTAGE

    The previous OPP-CI formulation ensures complete observ-ability of the network assuming a fixed network topology aftercontrolled islanding as well as absolutely reliable measurementdevices. However, PMUs may fail to work due to loss of GPSsignal, failure of measurement instruments or loss of communi-cation channels. Furthermore, transmission line outages may re-sult in loss of complete observability. Thus, operators may planto have a reliable monitoring system by installing extra PMUsin the network.In this section, constraints associated with OPP-CI against

    single PMU or single line loss are formulated. Meanwhile, theobjective function still remains the same as (11). Therefore, forOPP-CI considering each contingency, it is sufficient to replacethe previous constraints with the following related constraints.

    A. OPP-CI Formulation Considering Single PMU Outage

    Outage of a PMU at bus , denoted as , can be con-sidered into the previous OPP-CI model by setting the corre-sponding decision variable to zero. To facilitate the formu-lation of the optimization problem, a parameter, , is definedas follows:

    ifotherwise

    (14)

    then, the associated constraints to OPP-CI situation consideringsingle PMU outage are as follows.For network without ZIBs:

    (15)

    For network with ZIBs:

    (16)In these expressions, and are binary auxil-

    iary variables whose values are equal to 1, if bus is the pseudounobservable bus for and (the th zero injectioncluster in controlled islanding condition), respectively.

    B. OPP-CI Formulation Considering Single Line OutageOutage of a line may cause the loss of observability for one of

    its terminal buses which would otherwise be observable usingcurrent phasor of that line [15].For a power network with lines, single line contingen-

    cies can be defined. The connectivity matrices for the networkin normal operation condition and controlled islanding condi-tion change in each of such defined contingencies. Let param-eters and be defined as th entries of theconnectivity matrices for networks in normal and islanding sce-narios, respectively, where superscript represents loss ofline . Thus, related constraints of OPP-CI considering singleline outage are as follows:For network without ZIBs:

    (17)

    For network with ZIBs:

    (18)

    Similarly, and are binary auxiliary variableswhose values are equal to 1, if bus is pseudo unobservable bus,when line is out, for and , respectively.

    C. OPP-CI Formulation Considering Single ContingenciesIn this case, the assumed contingency for power system could

    be either one of the two types, i.e., the single PMU loss or thesingle line outage. Hence, the set of constraints defined in thetwo previous subsections should be considered simultaneously.It can be expected that more PMUs are required in order tomain-tain network observability in this case than in cases with onlysingle contingency.

  • HUANG et al.: OPTIMAL PMU PLACEMENT CONSIDERING CONTROLLED ISLANDING OF POWER SYSTEM 747

    TABLE IISPECIFICATIONS OF TEST SYSTEMS

    TABLE IIICONTROLLED ISLANDING SCHEMES FOR DIFFERENT SYSTEMS

    TABLE IVCOMPARISON OF OPP RESULTS WITH OR WITHOUT CONSIDERATION OF CONTROLLED ISLANDING (IGNORING THE EFFECT OF ZIB)

    V. CASE STUDIES AND RESULTS

    The proposed OPP-CI model was tested on the IEEE 14-, 30-,39-, 118-bus systems, and the Polish 2383-bus system, whosedetailed information can be found in Table II. The case studieswere performed in two parts. First, for all the test systems, OPPsconsidering controlled islanding, with and without inclusion ofthe effect of zero-injection bus, are carried out and the resultsare compared with those neglecting controlled islanding. Next,single line and single PMU contingencies are taken into accountand their influence on the OPP-CI solution is studied. The simu-lation results with respect to IEEE standard systems and Polish2383-bus system are given in the following. All simulations areexecuted in a laptop having a 2.60-GHz dual-core CPU and 4GB of RAM. The OPP problem is modeled in MATLAB andsolved by CPLEX Toolbox for MATLAB.

    A. Case Results for IEEE Standard Test Systems1) OPP Considering Controlled Islanding: At the first part,

    optimal PMU placement is carried out so as to achieve totally

    observability of network under both normal operation conditionand controlled islanding condition. To perform the OPP-CI pro-cedure, the controlled islanding plans for different IEEE sys-tems should be known a priori. In this paper, these controlledislanding schemes are extracted from [34], [35], and [13]. Forclarity, they are listed again in Table III. As for IEEE 14-bussystem, two islands with 6 buses and 8 buses in each island,respectively, are included in the islanding scheme. However, asmentioned in Section III, the proposed OPP-CI model is not justsuitable to the above controlled islanding cases but also can beapplied to any other controlled islanding schemes.Table IV provides the comparison of the number and loca-

    tions of required PMUs resulting fromOPPwith or without con-sideration of controlled islanding. The effect of zero-injectionbus is incorporated into the comparison in Table V. the PMUsinstallation percentage in the two tables refers to the ratio be-tween the number of PMUs and the number of system buses.Results of Tables IV and V reveal that generally more PMUs

    are required by power network to maintain observability forboth controlled islanding scenario as well as normal condition.

  • 748 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 29, NO. 2, MARCH 2014

    TABLE VCOMPARISON OF OPP RESULTS WITH OR WITHOUT CONSIDERATION OF CONTROLLED ISLANDING (INCLUDING THE EFFECT OF ZIB)

    TABLE VIOPP-CI RESULTS WITH CONSIDERATION OF SINGLE CONTINGENCIES (IGNORING THE EFFECT OF ZIB)

    TABLE VIIOPP-CI RESULTS WITH CONSIDERATION OF SINGLE CONTINGENCIES (INCLUDING THE EFFECT OF ZIB)

    Comparing Tables IV and V , it is also noticed that consideringthe influence of zero-injection bus reduces the number of re-quired PMUs in all cases.2) OPP-CI Considering Contingencies of Single Line and

    PMU Outages: In this part, OPP-CI is implemented for IEEE14-, 30-, 39- and 118-bus systems considering contingenciesof line or PMU outages. Corresponding to the constraints(15)(16), (17)(18) and the combination of (15)(18), threedifferent cases are considered, i.e., outage of a single line, lossof a single PMU, and a single contingency of line outage orPMU loss. The influence of zero-injection bus is neglected inTable VI, while it is considered in Table VII.As expected, a robust measurement system against single

    PMU or line outages needs more PMUs than the case neglectingcontingencies. Additionally, in comparison with single line

    outage, single PMU loss has more adverse impact on the net-work observability, which can be concluded from the requirednumber of PMUs in the relevant cases.Table VIII shows the CPU computation times for solving

    OPP-CI problems. For each IEEE test system, only the timeneeded for the most complex calculation, i.e., OPP-CI consid-ering the single contingency and the effect of ZIB, is listed.In all the previous calculations in the paper, the uncertain-

    ties of PMUmeasurements and network parameters are ignored,and the values of weighting factors and are fixed. How-ever, two appendixes are added at the end of this paper: in Ap-pendix A, the uncertainties associated with the voltage phasorsmeasured or computed by the proposed OPP-CI schemes areassessed, while the variances of OPP-CI results with differentvalues of and are shown in Appendix B.

  • HUANG et al.: OPTIMAL PMU PLACEMENT CONSIDERING CONTROLLED ISLANDING OF POWER SYSTEM 749

    TABLE VIIICPU COMPUTATION TIMES FOR CALCULATIONS OF OPP-CI CONSIDERING SINGLE CONTINGENCY AND EFFECT OF ZIB

    TABLE IXOPP RESULTS AND THEIR ASSOCIATED CPU COMPUTATION TIMES FOR POLISH 2383-BUS SYSTEM

    TABLE XSTANDARD UNCERTAINTIES IN THE INDIRECT-MEASUREMENTS

    OF MAGNITUDES AND PHASOR ANGLES OF VOLTAGEPHASORS FOR IEEE 14-BUS SYSTEM

    B. Case Results for Polish 2383-Bus SystemThe details about the Polish 2383-bus system can be obtained

    from [38] which indicates that all the buses in this system aredivided into different areas. Based on this, a CI scheme for thePolish 2383-bus system is assumed, in which the partition ofcontrolled islands is roughly consistent with that of sub-areasdetermined in [38]. However, a few buses are repartitioned inthe CI scheme to avoid isolated bus or areas in each island.Finally, in the CI scenario the whole Polish 2383-bus systemwill be divided into 5 islands with 369 buses, 281 buses, 880buses, 560 buses, 293 buses, respectively. The OPP-CI resultswith different considerations and their associated CPU compu-tation times are shown in Table IX.

    VI. CONCLUSIONAn effective OPP scheme should ensure complete observ-

    ability of a power network under various operation conditions.To avoid wide-area blackout following cascading failures,power system might be operated in controlled islanding mode.

    TABLE XISTANDARD UNCERTAINTIES IN THE MEASUREMENTS OF VOLTAGEPHASORS AT PSEUDO UNOBSERVABLE BUS FOR IEEE 14-BUS SYSTEM

    In this paper, an OPP model considering controlled islandingof power system is proposed. The proposed model guaranteescomplete observability of power network for normal conditionas well as controlled islanding condition, with or withoutconsidering the effect of zero-injection bus. By introducingthe measurement redundancy into the optimization objective,our OPP-CI model can find the globally optimal solution withthe minimum number of PMUs and maximum measurementredundancy. Furthermore, single PMU or line loss is also in-corporated into the model. At last, case studies on several IEEEstandard test systems and a large-scale practical system provideverification of the effectiveness of the presented OPP models.

    APPENDIX AEVALUATION OF MEASUREMENT UNCERTAINTYFOR IEEE 14-BUS AND 118-BUS SYSTEMS

    The uncertainties associated with the voltage phasors mea-sured or computed by the proposed OPP-CI configurations areevaluated in this appendix. For each IEEE test system, the uncer-tainty evaluation is performed only for the OPP-CI scheme con-sidering the effect of ZIB, which implies the minimum numberof installed PMUs and consequently the worst performance onuncertainty.Detailed formulas of uncertainty calculation for different

    types of measurements are derived in the following.DirectMeasurements: The uncertainties of direct measure-

    ments are calculated from the manufacturers specifications.Assuming that the probability of measurement uncertainty isof uniform distribution and the is the bounding limitsof the measurement of , the standard uncertainty in the

  • 750 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 29, NO. 2, MARCH 2014

    TABLE XIIOPP-CI RESULTS WITH REGARDS TO DIFFERENT VALUES OF FOR IEEE 30-BUS SYSTEM

    measurement can be expressed as [39]

    (19)

    where is usually specified by PMU manufacturers [40].Indirect-Measurements: The uncertainties for indi-

    rect-measurements are evaluated by using the classical uncer-tainty propagation theory [39].Let there be a PMU installed at bus , with bus connected to

    bus through line . With the help of PMU measurements,i.e., the voltage phasor at bus and the currentphasor through the line , the voltage at buscan be expressed as

    (20)

    where and are line resistance and reactance.By decoupling (20) into two equations in the real-imaginary

    coordinate system and solving the new equations, the magni-tude and the phasor angle of the voltage phasor can be

    obtained, which are functions of the magnitude and phase angleof and , and the parameters of line :

    (21)

    Assuming that the input quantities in (21) are uncorrelated(similar assumptions are made for the following derivations),the combined standard uncertainty of the voltage magnitudeand the phase angle , according to [39], can be given by

    (22)

    where is the partial derivative, , , , , ,, and is the standard uncertainty in the measurement.

  • HUANG et al.: OPTIMAL PMU PLACEMENT CONSIDERING CONTROLLED ISLANDING OF POWER SYSTEM 751

    TABLE XIIIOPP-CI RESULTS WITH REGARDS TO DIFFERENT VALUES OF FOR IEEE 39-BUS SYSTEM

    Measurements Calculated With the Properties of ZIC: Forthis type of measurements, i.e., the voltage phasors at the pseudounobservable buses, their uncertainties can also be obtained bythe classical uncertainty propagation theory.If the pseudo unobservable bus is exactly the ZIB of one

    ZIC, it implies that there is no bus in the ZIC with PMUinstalled. The voltage phasor of bus is obtained from thefollowing KCL equation:

    (23)

    where is the number of buses in this ZIC, is the number oflines connecting bus and the zero-injection bus . andare resistance and reactance, respectively, of th line betweenbus and bus .The voltage magnitude and phasor angle of bus can then be

    expressed as

    (24)

    where and are sets of voltage magnitudes and phasorangles, respectively, of buses in the ZIC except the bus .and are parameter sets of lines incident to the bus .

    Thus, the standard uncertainty of and can be given by

    (25)

    with , , , and is the total number of variablesin .For the situation that the pseudo unobservable bus is not

    the zero-injection bus (assuming that bus is the zero-injec-tion bus), there may exist some PMUs having been placed atthe buses incident to bus . Another equation, thus, should beformulated to obtain the bus s voltage phasor:

    (26)

    here, is the set of PMU buses in the ZIC and refers to theset of buses without PMU installed. is the current phasorthrough the th line from bus to bus .

  • 752 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 29, NO. 2, MARCH 2014

    TABLE XIVOPP-CI RESULTS WITH REGARDS TO DIFFERENT VALUES OF FOR IEEE 30-BUS SYSTEM

    Similarly to (24), there exists a new pair of equations for themagnitude and phasor angle of voltage phasor :

    (27)

    where and are sets of magnitudes and phasor angles, re-spectively, of the currents from buses in to bus . andare sets of voltage magnitudes and phasor angles of buses inexcept the bus , respectively. and are parameter sets oflines from buses in to bus .Then the standard uncertainties can be obtained with the fol-

    lowing formula:

    (28)

    Table X shows the standard uncertainties in the voltagephasors corresponding to the indirect-measurements, whileTable XI gives the standard uncertainties in the voltage phasorsof pseudo unobservable buses. The uncertainties of the PMUbuses are excluded, since they can be directly computed from(19). The typical values of maximum uncertainties in PMUmeasurements are specified by the manufacturer in [40], wherethe maximum uncertainties for voltage and current magnitude

    Fig. 2. Standard uncertainties in calculated voltage phasors for the IEEE14-bus system.

    are 0.02% and 0.03% of the actual values, respectively; andthe maximum error in the measurement of phase angle is0.01 degrees. The actual values of phasor measurements aredetermined by performing power flow for the power system.Additionally, a 5% uncertainty is assumed to all transmissionline parameters.

  • HUANG et al.: OPTIMAL PMU PLACEMENT CONSIDERING CONTROLLED ISLANDING OF POWER SYSTEM 753

    TABLE XVOPP-CI RESULTS WITH REGARDS TO DIFFERENT VALUES OF FOR IEEE 39-BUS SYSTEM

    It is noted that under the proposed OPP-CI configuration abus may be observed by more than one PMU, such as bus 7in Table X. In that case, a pair of measurement uncertainties,i.e., uncertainty in voltage magnitude and uncertainty in voltagephasor angle, can be obtained with regard to each connectedPMU. The minimum value of magnitude uncertainty and min-imum value of angle uncertainty should be chosen and treatedas the final uncertainties for that bus. Additionally, there aresome buses located on the boundary of islands. In other words,these buses have lines incident to other islands, such as bus 2 inIEEE 14-bus system. As shown in Table X, the CI process maycause the loss of the observations on these buses from the PMUslocated in other islands. Therefore, their measurement uncer-tainties in CI condition may be different from that in normalcondition.The standard uncertainties in calculated voltage phasors for

    IEEE 14-bus system are shown in Fig. 2. The order in whichthe buses are selected to depict the measurement uncertaintiescorresponds to the bus indices. In other words, the order forIEEE 14-bus system is 1-3, 7-8, and 10-14. In Fig. 2, the solidcircle and x-mark refer to the measurement uncertainties fornormal operation condition, while the dashed circle and x-mark

    are used to display the measurement uncertainties in CI opera-tion condition.Fig. 3 shows the standard uncertainties associated with cal-

    culated voltage phasors for IEEE 118-bus system. There are 4buses having different uncertainties for normal condition andCI condition. Among them buses 26 and 65 are the boundarybuses with tie lines incident to other islands, and buses 26 and65 are pseudo unobservable buses. It is noted that buses 26 and65 have small measurement uncertainties in CI condition thanthat in normal condition. The reason is that the bus numbersof the ZICs which they belonged to are reduced due to the CIprocess. This leads to the reduction of uncertainty sources in thecalculation equations of their voltage phasors, and consequentlyresults in smaller measurement uncertainties.

    APPENDIX BOPP-CI RESULTS WITH DIFFERENT AND

    FOR IEEE 30-BUS AND 39-BUS SYSTEMS

    Results With Different Weighting Factor : Tables XIIand XIII show the OPP-CI results with regards to differentvalues of for IEEE 30-bus system and 39-bus system,

  • 754 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 29, NO. 2, MARCH 2014

    Fig. 3. Standard uncertainties in calculated voltage phasors for the IEEE118-bus system.

    respectively. For all of the calculations, the values of are setthe same as before, i.e., .In these two tables, corresponds to the results cal-

    culated in Section V. refers to the case in which onlythe measurement redundancy of normal operation condition isconsidered, while indicates that only the measurementredundancy of islanding condition is activated. The cells withthe same OPP result are joined together.Since the priority of minimizing PMU number is ensured in

    (11) by the selected value of , all the OPP results for a givenOPP-CI strategy are with the same minimum number of PMU,as shown in the tables. However, the PMU locations may varywith the value of , especially for the cases associated withthe IEEE 30-bus system. It is because that the weighted propor-tions of the two components in (10), i.e., the measurement re-dundancy differences in normal condition and islanding condi-tion, are changed due to the varying . Consequently, for thosebuses with tie lines connected to other islands, their weightedmeasurement redundancy differences will be changed.

    Results With Different Weighting Factor : The variancesof OPP-CI solutions with the weighting factor in (11) arelisted in Tables XIV and XV. All the calculations are accom-plished under the value of . Similarly, for each tablethe cells with the same result are combined together.The values of calculated from are

    0.1111 for IEEE 30-bus system and 0.1429 for 39-bus system.For the cases of , the component in (11) isan integer and the component has the value between 0 and1. This guarantees that minimizing PMU number is more domi-nant than maximizing measurement redundancy in the OPP pro-cedure. Thus with a given , a robust OPP solution can be ob-tained for each OPP-CI strategy. On the other hand, the value

    of will increase with and may exceed 1. In that case,additional PMUmay be needed due to the trade-off between theobjective of minimizing PMU number and the objective of max-imizing measurement redundancy.

    REFERENCES

    [1] N. M. Manousakis, G. N. Korres, and P. S. Georgilakis, Taxonomyof PMU placement methodologies, IEEE Trans. Power Syst., vol. 27,no. 2, pp. 10701077, May 2012.

    [2] A. Abur and A. G. Exposito, Power System State Estimation: Theoryand Implementation. New York, NY, USA: Mercel Dekker, 2004.

    [3] B. Milosevic and M. Begovic, Nondominated sorting genetic algo-rithm for optimal phasor measurement placement, IEEE Trans. PowerSyst., vol. 18, no. 1, pp. 6975, Feb. 2003.

    [4] A. Enshaee, R. A. Hooshmand, and F. H. Fesharaki, A newmethod foroptimal placement of phasor measurement units to maintain full net-work ob-servability under various contingencies, Elect. Power Syst.Res., vol. 89, no. 1, pp. 110, Aug. 2012.

    [5] B. K. S. Roy, A. K. Sinha, and A. K. Pradhan, An optimal PMU place-ment technique for power system observability, Int. J. Elect. PowerEnergy Syst., vol. 42, no. 1, pp. 7177, Nov. 2012.

    [6] T. L. Baldwin, L.Mili, M. B. Boisen, and R. Adapa, Power system ob-servability withminimal phasormeasurement placement, IEEE Trans.Power Syst., vol. 8, no. 2, pp. 707715, May 1993.

    [7] B. Xu and A. Abur, Observability analysis and measurement place-ment for systems with PMUS, in Proc. IEEE Power Eng. Soc. PowerSystems Conf. Expo., Oct. 2004, pp. 943946.

    [8] B. Gou, Generalized integer linear programming formulation for op-timal PMU placement, IEEE Trans. Power Syst., vol. 23, no. 3, pp.10991104, Aug. 2008.

    [9] M. Korkali and A. Abur, Placement of PMUs with channel limits, inProc. IEEE Power Eng. Soc. General Meeting, 2009.

    [10] F. Aminifar, A. Khodaei, M. Fotuhi-Firuzabad, and M. Shahidehpour,Contingency-constrained PMU placement in power networks, IEEETrans. Power Syst., vol. 25, no. 1, pp. 516523, Feb. 2010.

    [11] M. R. Aghamohammadi and A. Shahmohammadi, Intentionalislanding using a new algorithm based on ant search mechanism,Int. J. Elect. Power Energy Syst., vol. 35, no. 1, pp. 138147, Feb.2012.

    [12] G. Xu, V. Vittal, A. Meklin, and J. E. Thalman, Controlled islandingdemonstrations on the WECC system, IEEE Trans. Power Syst., vol.26, no. 1, pp. 334343, Feb. 2011.

    [13] L. Ding, F. M. Gonzalez-Longatt, P. Wall, and V. Terzija, Two-stepspectral clustering controlled islanding algorithm, IEEE Trans. PowerSyst., vol. 28, no. 1, pp. 7584, Feb. 2013.

    [14] S. S. Ahmed, N. C. Sarker, A. B. Khairuddin, M. R. B. A. Ghani, andH. Ahmad, A scheme for controlled islanding to prevent subsequentblackout, IEEE Trans. Power Syst., vol. 18, no. 1, pp. 136143, Feb.2003.

    [15] S. Azizi, A. S. Dobakhshari, S. A. N. Sarmadi, and A. M. Ranjbar,Optimal PMU placement by an equivalent linear formulation for ex-haustive search, IEEE Trans. Smart Grid, vol. 3, no. 1, pp. 174182,Mar. 2012.

    [16] B. Milosevic and M. Begovic, Nondominated sorting genetic algo-rithm for optimal phasor measurement placement, IEEE Trans. PowerSyst., vol. 18, no. 1, pp. 6975, Feb. 2003.

    [17] J. Peng, Y. Sun, and H. F. Wang, Optimal PMU placement for fullnetwork observability using tabu search algorithm, Int. J. Elect. PowerEnergy Syst., vol. 28, no. 4, pp. 223231, May 2006.

    [18] C. Peng, H. Sun, and J. Guo, Multi-objective optimal PMU placementusing a non-dominated sorting differential evolution algorithm, Int. J.Elect. Power Energy Syst., vol. 32, no. 8, pp. 886892, Oct. 2010.

    [19] M. Hajian, A. M. Ranjbar, T. Amraee, and B. Mozafari, Optimalplacement of PMUs to maintain network observability using a modi-fied BPSO algorithm, Int. J. Elect. Power Energy Syst., vol. 33, no.1, pp. 2834, Jan. 2011.

    [20] F. Aminifar, C. Lucas, A. Khodaei, andM. Fotuhi-Firuzabad, Optimalplacement of phasor measurement units using immunity genetic algo-rithm, IEEE Trans. Power Del., vol. 24, no. 3, pp. 10141020, Jul.2009.

    [21] M. Hurtgen and J.-C. Maun, Optimal PMU placement using iteratedlocal search, Int. J. Elect. Power Energy Syst., vol. 32, no. 8, pp.857860, Oct. 2010.

    UsuarioResaltadoMtodos para la formacin de islas controladas

    UsuarioResaltadoMtodos para la formacin de islas controladas

    UsuarioResaltadoMtodos para la formacin de islas controladas

    UsuarioResaltadoMtodos para la formacin de islas controladas

  • HUANG et al.: OPTIMAL PMU PLACEMENT CONSIDERING CONTROLLED ISLANDING OF POWER SYSTEM 755

    [22] R. F. Nuqui and A. G. Phadke, Phasor measurement unit placementtechniques for complete and incomplete observability, IEEE Trans.Power Del., vol. 20, no. 4, pp. 23812388, Oct. 2005.

    [23] I. Kamwa and R. Grondin, PMU configuration for system dynamicperformance measurement in large multiarea power systems, IEEETrans. Power Syst., vol. 17, no. 2, pp. 385394, May 2002.

    [24] B. Gou and A. Abur, A direct numerical method for observabilityanalysis, IEEE Trans. Power Syst., vol. 15, no. 2, pp. 625630, May2000.

    [25] G. N. Korres, P. J. Katsikas, K. A. Clements, and P. W. Davis, Nu-merical observability analysis based on network graph theory, IEEETrans. Power Syst., vol. 18, no. 3, pp. 10351045, Aug. 2003.

    [26] M. Gl and A. Abur, Observability analysis of systems containingphasor measurements, in Proc. 2012 IEEE Power Eng. Soc. GeneralMeeting, pp. 16.

    [27] M. Gl and A. Abur, Observability and Criticality Analyses forPower Systems Measured by Phasor Measurements, IEEE Trans.Power Syst., to be published.

    [28] G. N. Korres and N. M. Manousakis, Observability analysis andrestoration for systems with conventional and phasor measurements,Int. Trans. Elect. Energy Syst., DOI: 10.1002/etep.1684., 2012.

    [29] G. N. Korres and N. M. Manousakis, Observability analysis andrestoration for state estimation using SCADA and PMU data, in Proc.2012 IEEE Power Eng. Soc. General Meeting, pp. 18.

    [30] R. Sodhi, S. C. Srivastava, and S. N. Singh, Optimal PMU placementmethod for complete topological and numerical observability of powersystem, Elect. Power Syst. Res., vol. 80, no. 9, pp. 11541159, Sep.2010.

    [31] B. Gou, Optimal placement of PMUs by integer linear programming,IEEE Trans. Power Syst., vol. 23, no. 3, pp. 15251526, Aug. 2008.

    [32] K. Sun, D.-Z. Zheng, and Q. Lu, Splitting strategies for islanding op-eration of large-scale power systems using OBDD-based methods,IEEE Trans. Power Syst., vol. 18, no. 2, pp. 912923, May 2003.

    [33] P. A. Trodden, W. A. Bukhsh, A. Grothey, and K. I. M. McKinnon,MILP formulation for controlled islanding of power networks, Int.J. Elect. Power Energy Syst., vol. 45, no. 1, pp. 501508, Feb. 2013.

    [34] S. A. Nezam-Sarmadi, S. Nouri-Zadeh, A. M. Ranjbar, and M. R.Pishvaie, An islanding algorithm to restore a PMU installed powersystem, in Proc. 2010 IEEE Asia-Pacific Power and Energy Eng.Conf., pp. 14.

    [35] B. Pradhan, K. H. Reddy, D. S. Roy, and D. K. Mohanta, Intentionalislanding of electric power systems in a grid computing framework: agraph-theoretic approach, in Proc. 2011 Int. Conf. Recent Trends inInf. Syst., pp. 156160.

    [36] M. Rihan, M. Ahmad, M. S. Beg, and A. Anees, Optimal PMU place-ment on network branches for intentional islanding to prevent black-outs, Int. J. Emerg. Technol. Adv. Eng., vol. 3, no. 3, Mar. 2013.

    [37] A. Monticelli, Electric power system state estimation, Proc. IEEE,vol. 88, no. 2, pp. 262282, Feb. 2000.

    [38] R. D. Zimmerman, C. E. Murillo-Snchez, and D. Gan, MAT-POWER: a MATLAB Power System Simulation Package, CornellUniv.. Ithaca, NY, USA. [Online]. Available: http://www.pserc.cor-nell.edu/matpower.

    [39] JCGM 100:2008: Evaluation of Measurement DataGuide to the Ex-pression of Uncertainty in Measurement, 2008.

    [40] Model 1133A GPS-Synchronized Power Quality/Revenue Standard,Operation Manual, Arbiter Systems. Paso Robles, CA, USA.

    Lei Huang (S13) was born in Hunan, China, in1987. He received the B.E. degree in electricalengineering from Wuhan University, Wuhan, China,in 2009. Currently he is pursuing the Ph.D. degreein the School of Electrical Engineering, Wuhan Uni-versity. He is also a visiting scholar in the Universityof Denver, Denver, CO, USA.His research interests include optimal PMU place-

    ment, voltage stability analysis and wind power.

    Yuanzhang Sun (SM01) received the Ph.D. degreein electrical engineering from Tsinghua University,Beijing, China, in 1988.He is currently a Professor of the School of Electric

    Engineering,WuhanUniversity,Wuhan, China. He isalso an adjunct Professor at Tsinghua University. Hismain research interests are power system dynamicsand control, voltage stability, and renewable energy.

    Jian Xu (M08) received the B.E. and Ph.D. degreesin electrical engineering from Wuhan University,Wuhan, China, in 2002 and 2007, respectively.Currently he is an Associate Professor in the

    School of Electric Engineering, Wuhan University.Also, he is a visiting scholar in Washington StateUniversity, Pullman, WA, USA. His research inter-ests are PMU application, power system operation,and voltage stability.

    Wenzhong (David) Gao (SM03) received the M.S.and Ph.D. degrees in electric power engineering fromGeorgia Institute of Technology, Atlanta, GA, USA,in 1999 and 2002, respectively.He is currently an Associate Professor in the De-

    partment of Electrical and Computer Engineering,University of Denver, Denver, CO, USA. His re-search interests are renewable energy, smart grid,and power system analysis.

    Jun Zhang (M09) received the Ph.D. degree inelectric engineering from Arizona State University,Tempe, AZ, USA, in 2008.He is currently an Assistant Professor in the De-

    partment of Electrical and Computer Engineering,University of Denver, Denver, CO, USA. His re-search interests are smart grid and statistical signalprocessing.

    Ziping Wu (S12) received the B.E. degree inthermal power engineering and the M.S. degreein electrical power engineering from North ChinaElectric Power University, Beijing, China, in 2006and 2009, respectively. Now he is pursuing the Ph.D.degree in the Department of Electrical and ComputerEngineering, University of Denver, Denver, CO,USA.His research interests include wind power genera-

    tion, renewable energy, and smart grid.

    UsuarioResaltadoMtodos para la formacin de islas controladas

    UsuarioResaltadoMtodos para la formacin de islas controladas

    UsuarioResaltadoMtodos para la formacin de islas controladas

    UsuarioResaltadoMtodos para la formacin de islas controladas