6673670 Transmission Line Design Construction[1]

Embed Size (px)

Citation preview

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    1/37

    1

    TRANSMISSION LINES DESIGN

    AND CONSTRUCTION

    BY

    K.VEERABHADRA RAO

    RETD.CHIEF ENGINEER,AP TRANSCO

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    2/37

    2

    DEVELOPMENT OF AC TRANSMISSION LINES

    16-5-1888 TRANSMISSION LINE PATENT GIVEN

    FIRST LINE 25 kV LINE LAUFFEN TO FRANKFURT

    IN GERMANY

    1912 110 kV LINE LAUCHLAMMER TO RIESA17-4-1929 220 kV LINE BRAUWEILER TO FRANKFURT

    TOWERS DESIGNED FOR 380 kV

    5-10-1957 380 kV LINE ROMERSKIRCHEN TO LUDWIGSBURG-

    HOHENECH

    1967 735 kV LINE IN HYDRO QUEBEC1982 1200 kV LINE IN SOVIET UNION

    EXTREMEMELY HIGH VOLTAGE TRANSMISSION BEYOND 2000

    kV NOT PREFERED DUE TO HIGH CORONA

    DISCHARGELOSSES MORE THAN LOSSES DUE TO LINE

    RESISTANCE

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    3/37

    3

    DESIGN BASIS

    1.ECONOMIC FACTORS

    2.NETWORK SAFETY

    3.REDUNDANCY

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    4/37

    4

    MAIN COMPONENTSMAIN COMPONENTS

    1. CONDUCTOR

    2. CONDUCTOR ACCESSORIES

    a) REPAIR SLEEVES b) COMPRESSION JOINTS

    c) VIBRATION DAMPERS d) SPACERS / SPACER

    DAMPERS

    3. EARTH WIRE

    a) COMPRESSION JOINTS

    b) VIBRATION DAMPERS

    c) COPPER EARTH BONDS

    4. INSULATORS

    5. EARTHING/ COUNTER POISE EARTHING SETS

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    5/37

    5

    6. INSULATOR STRING HARDWARE

    a) SUSPENSION STRING HARD WARE

    b) TENSION STRING HARD WARE

    7. OPGW

    8. EARTH WIRE /OPGW HARDWARE

    9. TOWERS

    10.TOWER ACCESSORIES

    a) PHASE PLATES b) DANGER BOARDS

    c) BIRD GAURDS d) ANTI CLIMBING DEVICES

    e) STEP BOLTS

    MAIN COMPONENTSMAIN COMPONENTS contd..contd..

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    6/37

    6

    CONDUCTORS

    1. COPPER

    2 .COPPER CONDUCTOR STEEL REINFORCED

    3. ALUMINIUM

    4. ALL ALUMINIUM ALLOY CONDUCTORS(AAAC)

    5. ALUMINIUM ALLOY CONDUCTOR STEEL

    REINFORCED(AACSR)

    5. ALUMINIUM CONDUCTOR STEEL

    REINFORCED(ACSR)

    6. ALUMINIUM CONDUCTOR ALUMINIUM CLAD

    STEEL REINFORCED - ACSR(AS)

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    7/37

    7

    ADVANTAGES OF ACSR

    1. MORE SPAN-LESS SAG

    2. LARGER DIA -LESS CORONA LOSS FOR UHV

    LINES

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    8/37

    8

    STANDARDS

    1. IS:398 IEC-1098-1991:

    SPECIFICATION FOR ALUMINIUM

    CONDUCTORS FOR OVERHEAD

    TRANSMISSION LINES

    2 IS-398 PART-II : ACSR

    3. IS-398 PART-V : ACSR FOR 400 kV AND ABOVE

    4. IEC-1232 : ALUMINIUM CLAD STEEL WIRES FOR

    ELECTRICAL PURPOSES

    5.IS-1778 :REELS AND DRUMS FOR BARECONDUCTORS

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    9/37

    9

    PRINCIPAL PARAMETERS OF ACSR

    1. APPLICABLE STANDARDS

    2. NO./WIRE DIA.AL./STEEL

    3. SECTIONAL AREA OF ALUMINIUM (SQ,mm)

    4. TOTAL SECTIONAL AREA (SQ,mm)

    5. OVERAL DIA.(mm)

    6. APPROXIMATE WT(.KG / KM)

    7. DC RESISTANCEAT 20 DEG.C( OHM/KM)

    8. ULTIMATE TENSILE STRENGTH ( KN)

    9. FINAL MODULUS OF ELASTICITY (KG/cm)

    10. COEFFICIENT OF LINEAR EXPANSION (PER DEG.C)

    11.LAY RATIO( MAX./MIN.)

    12.TECHNICAL PARTICULARS OF STEEL AND AL.STRANDS

    a) strand dia. b) cross sectional area c) wt./km d) min.breaking load befor

    stranding and after stranding KN e)zinc coating of steel wire f) joints in

    strands g) chemical composition of steel wire

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    10/37

    10

    IMP. TYPE TESTS

    1.ULTIMATE TENSILE STRENGTH

    2.CORONA EXTINSION VOLTAGE

    3.RADIO INTERFERENCE VOLTAGE

    4.DC RESISTANCE

    5.STESS STAIN TEST

    This test is to collect the creep data of theconductor.Creep is due to settlement of strands and due tonon -elastic elongation of metal when subjected toload.The manufacturer shall furnish the amount of creep in

    10,20,30,40,50 years along with supportingcalculations.The calculation to be based on every daytemp. and tension 22 % of UTS. for 400 kV

    and 25 %UTS for 220 kV

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    11/37

    11

    INSULATOR STRINGS

    TYPES OF INSULATORS1. PORCELAIN DISC INSULATORS,LONG ROD

    INSULATORS2.TOUGHENED GLASS3.POLYMER SILICON RUBBER/ALLOY OF SILICON

    RUBBER AND EPDM

    NORMAL SIZES1.254 X 145 mm 70KN/90KN EMS. 280mm CREEPAGE2.280 X 170 mm 120 KN/160KN,

    280mm/330mm/430mm CREEPAGE3.305 X 145 mm 120 KN,

    280mm /330mm/430mm CREEPAGE4.305 X 170 mm 160 KN

    280mm /330mm/430mm CREEPAGEBALL DIA--16mm, 20mm

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    12/37

    12

    INSULATOR STRINGS---- CONTINUED

    TYPES OF STRINGS

    1.SINGLE SUSPENSION

    2.DOUBLE SUSPENSION

    3.SINGLE TENSION

    4. DOUBLE TENSION

    5.V-SRTING

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    13/37

    13

    CONSTRUCTION WORKSCONSTRUCTION WORKS

    1. SURVEYS

    a) ROUTE ALIGNMENT

    b) DETAILED SURVEY c) CHECK SURVEY

    i) PROFILES

    ii) SOIL PARTICULARS

    iii) SAG TEMPLATE

    iv)TOWER SPOTTING

    v) RIGHT OF WAY

    2. APPROVALS FROM CONCERNED

    a) ROAD CROSSINGS

    i) RAIL CROSSINGS ii) TELECOM LINES

    iii) RIVER CROSSINGS iv) AIR PORT AUTHORITIES

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    14/37

    14

    CONSTRUCTION WORKSCONSTRUCTION WORKS contd..contd..

    3. FOUNDATIONS

    i) DESIGN FOR DIFFERENT SOILS ii) EXCAVATION PLAN

    iii) FORM BOXES iv) STUB SETTING

    v) CONCRETING vi) REVETMENTSvii) EARTHING

    4. TOWER ERRECTION

    i) TOWER SCHEDULES ii) INSEPCTION AND SORTING

    OUT MEMBERS

    iii) TREATMENT OF JOINS iv) ASSEMBLY

    v) TIGHTENING AND PUNCHING OF BOLTS AND NUTS

    vi) FIXING ACCESSORIES

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    15/37

    15

    CONSTRUCTION WORKSCONSTRUCTION WORKS contd..contd..

    5. INSULATOR HOISTING

    6. POWER AND EARTH CONDUCTOR ERRECTION

    i) DELIVERY OF CONDUCTOR AT SITE ii) PAYING OUT AND STRINGING

    iii) TENSIONING AND SAGGING iv) CLIPPING -IN

    7. FIXING OF CONDUCTOR AND EARTH WIRE ACCESSORIES

    8. FINAL CHECKING

    9. TESTING AND COMMISIONING

    i) CONDUCTOR CONTINUITY TEST ii) INSULATION RESISTENCE TEST

    iii) TO BE CHARGED AT LOW VOLTAGE

    iv) STATUTORY REQUIREMENTS TO BE MET

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    16/37

    16

    COST COMPONENTSCOST COMPONENTS

    1. TOWERS AND ACCESSORIES 28%

    2. ACSR CONDUCTOR AND ACCESSORIES 36%

    3. EARTH WIRE AND ACCESSORIES 01%4. INSULATOR AND STRINGS 06%

    5. FOUNDATIONS 04%

    6. ERRECTION 14%

    7. CENTAGES 11%

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    17/37

    17

    DESIGN BY PROBABILISTIC METHODDESIGN BY PROBABILISTIC METHOD

    IECIEC--826826CLIMATIC LOADS

    a) RETURN PERIODS OF CLIMATIC EVENTS

    1) 50 YEARS

    2) 150 YEARS3) 500 YEARS

    b) DRAG COEFFICIENT OF CONDUCTOR

    c) TERRAIN CATEGORIES

    DESIGN CONSIDERATIONS

    a) RELIABILITY (STRUCTURAL)

    OR

    PROBABILITY OF SURVIVAL

    b) SECURITY (STRUCTURAL)

    c) SAFETY

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    18/37

    18

    DESIGN BY PROBABILISTIC METHODDESIGN BY PROBABILISTIC METHODIECIEC--826826

    COORDINATION OF STRENGTH OF COMPONENTS

    --------------------------------------------------------------------------------------------------------

    MAJOR COORDINATION WITH

    COMPONENT MA JOR COMPONENTS

    --------------------------------------------------------------------------------------------------------TO FAIL FIRST TANGENT TOWER TOWER,FOUNDATIONS,

    HARDWARE

    NOT TO FAIL FIRST ANGLE TOWER TOWER,FOUNDATIONS,

    WITH 90% CONFIDENCE HARDWARE

    DEAD END TOWER TOWER,FOUNDATIONS,

    HARDWARECONDUCTOR CONDUCTORS, INSUL-

    LATORS, HARDWARE

    NOTE: WITH IN EACH MAJOR COMPONENTS THE UNDERLINED

    COMPONENT IS THE WEAKEST WITH 90% CONFIDENCE

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    19/37

    19

    LOADINGS ON TRANSMISSION LINESLOADINGS ON TRANSMISSION LINES

    LIVE LOADS

    1. WIND LOADS

    a. NON-SNOWY REGIONS

    b. WITH ICE SNOWY REGIONS

    c. WITHOUT ICE SNOWY REGIONS

    2. DEAD LOADS

    a. WEIGHT OF TOWER

    b. WEIGHT OF CONDUCTORS,

    c. HARDWARE AND INSULATORS

    3. SPECIAL LOADS

    a. EXTERNAL LOADS DURING

    b. CONSTRUCTION AND MAINTENANACE

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    20/37

    20

    REQUIREMENT OF LOADSREQUIREMENT OF LOADS

    1.RELIABILITY REQUIREMENTS

    CLIMATIC LOADS UNDER NORMAL CONDITIONS

    2.SECURITY REQUIREMENTS

    FAILURE CONTAINMENT LOADS UNDER BROKEN WIRE CONDITION

    3.SAFETY REQUIREMENTSLOADS DURING CONSTRUCTION AND MAINTENANCE LOADS

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    21/37

    21

    METHODOLOGY FOR THE DESIGNMETHODOLOGY FOR THE DESIGNOF TRANSMISSION LINESOF TRANSMISSION LINES

    ESTABLISH SAFETY

    REQUIREMENTSSELECT SECURITY

    REQUREMENTS

    SELECT

    RELIABILITY

    CALCULATE

    CONSTRUCTION

    AND MAINTENANCE LOADS

    CALCULATE LOADS

    RELATED TO

    SECURITY

    CALCULATE

    CLIMATIC LOADS

    COMBINE ALL LIMIT

    LOADS

    CHECK SAFETY

    REQUIREMENTSFROM

    NATIONAL

    REGULATIONSCALCULATE STRENGTH

    NEEDED TO COMPLY

    WITH ALL LOADS AND

    REQUIREMENTS

    DESIGN COMPONENTS

    FOR LOADS AND

    STRENGTH

    REQUIREMENTS

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    22/37

    22

    TOWER OUTLINETOWER OUTLINE

    1. TOWER HEIGHT

    2. TOWER WIDTH

    3. CROSS ARM WIDTH

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    23/37

    23

    ELECTRICAL CLEARANCESELECTRICAL CLEARANCES

    1. MIN.GROUND CLEARANCE

    2. MIN.CLEARANCE ABOVE HIGHEST FLOOD LEVEL

    3. CLEARACE AND SWING ANGLES

    4. AIR CLEARANCE

    5. POWER LINE CROSSINGS

    6. TELECOM.LINE CROSSINGS

    7. RAIL TRACK CROSSINGS

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    24/37

    24

    DESIGN PARAMETERSDESIGN PARAMETERS

    1. NO.OF CIRCUITS

    2. CLIMATIC CONDITIONS

    a. WIND

    b. TEMPERATUREc. ISOKERANIC LEVEL

    d. SEISMIC INTENSITY

    e. ICE FORMATION

    3. ENVIRONMENT AND ECOLOGICAL CONSIDERATIONS

    4. CONDUCTOR

    5. EARTH WIRE

    6. INSULATOR STRINGS

    7. SPAN

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    25/37

    25

    LOADINGSLOADINGS

    1. CLIMATIC LOADS RELATED TO RELIABILITY REQUIREMENTS:

    WIND LOADS

    i) SNOWY WITH ICE ii) SNOWY WITH OUT ICE

    iii) NON SNOWY

    2. FAILURE CONTAINMENT LOADS RELATED TO SECURITY

    REQUIREMENTS.

    i) LONGITUDINAL LOADS ii) TORSIONAL LOADS

    iii) ANTI CASCADING LOADS

    3. LOADS DURING CONSTRUCTION AND MAINTENANCE LOADS

    RELATED TO SAFETY REQUIREMENTS.

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    26/37

    26

    LOADINGSLOADINGS contd..contd..

    NATURE OF LOADS

    1. TRANSVERSE LOADS(T)

    WIND LOAD ON TOWER STRUCTURE, CONDUCTOR, GW &

    INSULATOR STRING

    COMPONENT OF MECHANICAL TENSION2. VERTICAL LOADS(V)

    SELF WEIGHT

    LOADS DURING CONSTRUCTION AND MAINTENANCE

    3. LONGITUDINAL LOADS(L)

    RELIABILITY CONDITION(NORMAL CONDITION),

    SECURITY CONDITION (BROKEN WIRE CONDITION) AND

    SAFETY CONDITION (CONSTRUCTION AND MAINTENANCE)

    HAVE ALL THE ABOVE LOADS UNDER THEIR LOADING

    COMBINATIONS.

    SAFTETY CONDITION HAS BOTH NORMAL AND BROKEN WIRE

    CONDITION.

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    27/37

    27

    ANTI CASCADING CHECKSANTI CASCADING CHECKS

    ALL ANGLE TOWERS SHALL BE CHECKED FOR ANTI CASCADING

    CONDITIONS WITH ALL THE CONDUCTORS AND G.W. INTACT

    ONLY ON ONE SIDE.

    1. TRANSVERSE LOADS(T) : UNDER NO-WIND CONDITION

    2. VERTICAL LOADS(V) : CONDUCTOR, GW WEIGHTS ON

    ONE SIDE ONLY, WEIGHT OF INSULATOR STRINGS AND

    ACCESSORIES

    3. LONGITUDINAL LOADS(L): PULL OF CONDUCTOR/GW AT

    EVERY DAY TEMPERATURE AND NO-WIND APPLIED

    SIMULTANEOUSLY AT ALL POINTS ON ONE SIDE WITH ZERO

    DEGREE DEVIATION.

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    28/37

    28

    BROKEN WIRE CONDITIONBROKEN WIRE CONDITION

    (BWC)(BWC)SINGLE CIRCUIT: ONE PHASE OR GW BROKEN WHICH EVER IS

    MORE STRINGENT FOR A PARTICULAR MEMBER

    MULTI CIRCUIT:

    SUSPENSION TOWER: ANY ONE PHASE OR GW BROKEN WHICH

    EVER IS MORE STRINGENT FOR A PARTICULAR MEMBER

    SMALL ANGLE TOWERS: ONE PHASE AND GW OR TWO PHASES

    BROKEN ON ONE SIDE.

    LARGE ANGLE TOWERS/DEAD END TOWERS: ANY THREE

    PHASES BROKEN ON THE SAME SIDE OR ANY TWO PHASES

    AND GW BROKEN ON THE SAME SIDE.

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    29/37

    29

    DESIGN OF TOWER MEMBERSDESIGN OF TOWER MEMBERS

    STRESS ANALYSIS:

    1. GRAPHICAL DIAGRAM METHOD: NOW OBSOLETE

    2. ANALYTICAL METHOD

    3. COMPUTER AIDED ANALYSIS: 3D ANALYSIS

    SELECTION OF MATERIAL

    i) BOLT DIAMETER FLARGE WIDTH16MM 45 MM

    ii) MINIMUM THICKNESS: 5 MM LEG

    4MM BRACINGS/REDUNDENT MEMBERS

    iii) GRADE OF STEEL : MILD STEEL AND HIGH TENSILE STEEL

    iv) STENDERNESS RATIO:

    LEGS < 120

    BRACINGS < 200

    REDUNDENT < 250

    TENSION < 400

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    30/37

    30

    DESIGN OF TOWER MEMBERSDESIGN OF TOWER MEMBERS contd..contd..

    PERMISSIBLE STRESSES

    SELECTION OF MEMBERS

    BOLTS & NUTS

    i) CLASS 4.6

    ULTIMATE BEARING STRESS - 4440 Kgf/cm2

    ULTIMATE SHEARING STRESS - 2220 Kgf/cm2

    ii) CLASS 5.6

    ULTIMATE BEARING STRESS - 6322 Kgf/cm2

    ULTIMATE SHEARING STRESS -3161 Kgf/cm2

    FOR 16 mm DIA BOLTS

    i) CLASS 4.6

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    31/37

    31

    TESTING OF TOWERSTESTING OF TOWERS

    TOWER TESTING STATION

    1. TEST BED

    2. PERMANENT ANCHORS: LONGITUDINAL MOST

    3. ARRANGEMENT FOR APPLYING THE COMBINATION OF LOADS

    4. ELECTRICAL WRINCHES (REMOTE CONTROLLED)

    5. INSTRUMENTS TO RECORD THE LOAD APPLIED:

    MECHANICAL SPRING GAUGES OR ELECTRICAL /

    ELECTRONIC TRANSDUCEROS/DYNAMO METERS

    6. CONTROL ROOM

    7. THEODOLOTES TO OBSERVE DEFLECTION OF TOWER

    TESTING

    1. BOLT SLIP TEST 2. BWC/ANTI CASCADE CONDITION

    3. NC 4. DESTRUCTION TEST

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    32/37

    32

    APPLICATION OF LOADSAPPLICATION OF LOADS

    TRANSVERSE, LONGITUDINAL LOADS AND VERTICAL LOADS

    AT PEAK AND RESPECTIVE CROSS ARM POINTS.

    WIND LOAD ON TOWER BODY SIMULATED ATA. G.W.

    B. CROSS ARM LEVELS

    C. WIND BELOW CROSS ARM LEVEL TO BE

    SIMULATED TO ACT AT BOTTOM CROSS ARM LEVEL

    D. TOWER WITH EXTENSION AT TOP OF EXTENSION

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    33/37

    33

    QUALITY ASSURANCE PLANQUALITY ASSURANCE PLAN

    1. QUALITY POLICY

    2. QUALITY CONTOL(QC) DEPARTMENT

    3. QUALITY PLANNING

    4. DESIGN AND DRAWING5. COMPANY STANDARDS

    6. INSPECTION EQUIPMENT, TOOLS AND GUAGES

    7. MATERIAL MANAGEMENT

    8. INSPECTION OF INCOMING MATERIAL

    9. BOUGHTOUT ITEMS

    10. IN-PROCESS INSPECTION

    11. DOCUMENTATION

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    34/37

    34

    DESIGN OF FOUNDATIONSDESIGN OF FOUNDATIONS

    1. TYPE OF LOADS

    a. COMPRESSION OR DOWN WARD THRUST

    b. TENSION OR UPLIFT

    c. LATERAL FORCES OR SIDE THRUST BOTH, TRANSVERSE AND

    LOGITUDINAL DIRECTIONS

    2. SOIL PARAMETERS

    a. LIMIT BEARING CAPACITY

    b. DENSITY OF SOIL

    c. ANGEL OF EARTH FRUSTRUM

    3. SOIL INVESTIGATION

    a. TYPY OF SOIL

    b. GROUND WATER TABLE

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    35/37

    35

    DESIGN OF FOUNDATIONSDESIGN OF FOUNDATIONS contd..contd..

    4. TYPES OF FOUNDATIONS

    a. NORMAL DRY SOIL FOUNDATION

    b. WET SOIL FOUNDATION

    c. PARTIAL SUBMERGED FOUNDATION

    d. FULLY SUBMERGED FOUNDATION

    e. BLACK COTTON SOIL FOUNDATION

    f. PARITAL BLACK COTTON SOIL FOUNDATIONg. SOFT ROCK/FISSURED ROCK FOUNDATION

    h. HARD ROCK FOUNDATION

    i. SANDY SOIL FOUNDATION

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    36/37

    36

    DESIGN OF FOUNDATIONSDESIGN OF FOUNDATIONS contd..contd..

    5. STRUCTURAL ARRANGEMENT OF FOUNDATION

    a. PCC TYPE

    b. RCC SPREAD TYPE

    c. BLOCK TYPEd. UNDER CUT TYPE

    e. GROUTED ROCK AND ROCK ANCHOR TYPE

    f. PILE TYPE

    g. WELL TYPE

    6. REVETMENT ON FOUNDATION

  • 8/6/2019 6673670 Transmission Line Design Construction[1]

    37/37

    37

    THE END