2
Presorted Standard Mail US Postage Paid Phoenix, AZ Permit No. 90 Mail Station 3293 P.O. Box 53933, Phoenix, AZ 85072 NORTH PEORIA 69kV Power Line Siting Project APRIL 2018 Please visit our project website at aps.com/siting For more information, please visit the project website at aps.com/siting Arizona Public Service Company (APS) is developing a plan to build new energy facilities to better serve the growing population in the northern region of Peoria. APS continually monitors its electrical system and, when necessary, adds or upgrades facilities. These improvements enhance reliability and help ensure that an adequate supply of electric power is available to customers. ADDITION OF NEW FACILITIES To maintain reliable electric service and accommodate future load growth, APS has determined the need to build new substations and associated 69 kilovolt (kV) power lines in the North Peoria region, as shown within the study area on the attached map. These facilities would be generally located within or adjacent to the new Vistancia North, Lake Pleasant Heights, and Saddleback Heights developments. A network of 69kV power lines would be constructed to bring power from existing substations and power lines near the east side of the study area and provide possible connections for new sources of power near the northwest side of the study area. A total of four new substations and the associated interconnecting 69kV power lines are included in this siting process. APS anticipates the first substation (Substation W03) and related 69kV lines to be in service in 2021, located near the Vistancia North and Lake Pleasant Heights developments (see Phase 1 – W03 Substation Siting Area on the included map). Although the remaining three substations (W04, W05 and TS14) and interconnecting lines are part of this siting effort, it is anticipated that these facilities would not need to be constructed for 5 to 10 (or more) years, based on current housing development projections. The new segments of the 69kV power lines would be built on steel poles, with either a single 69kV circuit configuration or a double 69kV circuit configuration (three wires per circuit). The new 69kV power lines may be constructed in a new alignment or added in areas where some lines already exist. In most cases, if there are existing facilities they would be rebuilt on the new poles to consolidate structures. It is anticipated that any new poles would be approximately 65 feet in height. The line segments would require a right- of-way or easement approximately 40 to 60 feet in width to construct, operate, and maintain the facilities. SITING PROCESS APS has hired Environmental Planning Group (EPG) to assist in evaluating substation sites and route alternatives, to assess potential environmental impacts, and to support the public outreach process. Baseline information about land use, visual, biological, cultural, and recreational resources for the area will be collected. This information will be used to develop preliminary power line route and substation location alternatives within the study area. When developing alternatives, APS evaluates many criteria, including: environmental impacts, engineering and construction feasibility, land acquisition timing and costs, regulatory approvals, potential impacts to existing and planned neighborhoods, and input from agencies and the public. The work completed thus far has included initial data collection of existing and planned land uses. APS and EPG have identified a project study area (see map) and have held initial briefings with developers as well as federal, state, and City of Peoria jurisdictional representatives. APS and EPG will continue to hold NORTH PEORIA 69kV Power Line Siting Project IMPORTANT TRANSMISSION LINE INFORMATION Public Information Open House Meetings 5:30–7:30 p.m. Thursday, May 3rd Oasis Elementary School 17161 W Bajada Rd Surprise, AZ 85387 5:30–7:30 p.m. Tuesday, May 8th Lake Pleasant Elementary School 31501 N Westland Rd Peoria, AZ 85383 Typical 69kV double-circuit pole

69kV Power Line Siting Project - aps

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 69kV Power Line Siting Project - aps

PresortedStandard Mail

US Postage PaidPhoenix, AZ

Permit No. 90

Mail Station 3293P.O. Box 53933, Phoenix, AZ 85072

NORTH PEORIA

69kV Power Line Siting ProjectAPRIL 2018

Please visit our project website at aps.com/siting For more information, please visit the project website at aps.com/siting

Arizona Public Service Company (APS) is developing

a plan to build new energy facilities to better serve the

growing population in the northern region of Peoria.

APS continually monitors its electrical system and, when

necessary, adds or upgrades facilities. These improvements

enhance reliability and help ensure that an adequate

supply of electric power is available to customers.

ADDITION OF NEW FACILITIESTo maintain reliable electric service and accommodate

future load growth, APS has determined the need to build

new substations and associated 69 kilovolt (kV) power

lines in the North Peoria region, as shown within the

study area on the attached map. These facilities would

be generally located within or adjacent to the new

Vistancia North, Lake Pleasant Heights, and Saddleback

Heights developments. A network of 69kV power lines

would be constructed to bring power from existing

substations and power lines near the east side of the study

area and provide possible connections for new sources

of power near the northwest side of the study area.

A total of four new substations and the associated

interconnecting 69kV power lines are included in this

siting process. APS anticipates the first substation

(Substation W03) and related 69kV lines to be in service

in 2021, located near the Vistancia North and Lake

Pleasant Heights developments (see Phase 1 – W03

Substation Siting Area on the included map). Although

the remaining three substations (W04, W05 and TS14)

and interconnecting lines are part of this siting effort, it

is anticipated that these facilities would not need to be

constructed for 5 to 10 (or more) years, based on current

housing development projections.

The new segments of the 69kV power lines would

be built on steel poles, with either a single 69kV circuit

configuration or a double 69kV circuit configuration

(three wires per circuit). The new 69kV power lines may

be constructed in a new alignment or added in areas where

some lines already exist.

In most cases, if there

are existing facilities

they would be rebuilt

on the new poles

to consolidate

structures. It is

anticipated that any

new poles would be

approximately

65 feet in height.

The line segments

would require a right-

of-way or easement

approximately 40 to

60 feet in width to

construct, operate, and

maintain the facilities.

SITING PROCESSAPS has hired Environmental Planning Group (EPG) to

assist in evaluating substation sites and route alternatives,

to assess potential environmental impacts, and to support

the public outreach process. Baseline information about

land use, visual, biological, cultural, and recreational

resources for the area will be collected. This information

will be used to develop preliminary power line route and

substation location alternatives within the study area.

When developing alternatives, APS evaluates many

criteria, including: environmental impacts, engineering and

construction feasibility, land acquisition timing and costs,

regulatory approvals, potential impacts to existing and

planned neighborhoods, and input from agencies and the

public. The work completed thus far has included initial

data collection of existing and planned land uses.

APS and EPG have identified a project study area (see

map) and have held initial briefings with developers

as well as federal, state, and City of Peoria jurisdictional

representatives. APS and EPG will continue to hold

NORTH PEORIA

69kV Power Line Siting Project

IMPORTANT TRANSMISSION LINE INFORMATION

Public Information Open House Meetings

5:30–7:30 p.m.Thursday, May 3rdOasis Elementary School 17161 W Bajada Rd Surprise, AZ 85387

5:30–7:30 p.m. Tuesday, May 8thLake Pleasant Elementary School 31501 N Westland RdPeoria, AZ 85383

Typical 69kV double-circuit pole

Page 2: 69kV Power Line Siting Project - aps

T:\GIS\Projects\APS\APS0099_North Peoria\MXD\Production\North_Peoria_Own_Jurisd_Newsletter.mxd

April 2018

WestwingSubstation

MorganSubstation

RacewaySubstation

CalderwoodSubstation

New WaddellSubstation

HumbugSubstation

(Western Area Power Administration)

LakesideSubstation

(City of Phoenix)

HatfieldSubstation

Jomax Rd.

Dixileta Dr.

Dove Valley Rd.

Carefree Hwy.

Happy Valley Rd.

Lake

Ple

asan

t Pkw

y.

Vistancia Blvd.

El M

irage

Rd.

Dys

art R

d.

Litc

hfie

ld R

d.

Bul

lard

Ave

.

Lone Mtn. Pkwy.

Jomax Rd.

Ag

ua

Fr i

a R

iver

Wadde l l

Cana l

Hay de n-Rhodes Aqueduct

Cana l

Bea

rdsl

ey

City of Peoria

City of Surprise

City of Peoria

City of Phoenix

Twin Buttes

Saddleback Mountain

X

X

New

R

ive r

Prince Mountain

H I E R O G L Y P H I CM O U N T A I N S

Happy Valley Pkwy.

Beardsley Cana l

x

x

x

x

x

Cent ra l A r izona Pro jec t

Dynamite Rd.

Dixileta Dr.

West Wing MountainX

Calderwood ButteX

x

Saddle Mountain Rd.

L a k eP l e a s a n t

Cast

le H

ot S

prin

gs R

d.

Dove Valley Rd.

x

163r

d A

ve.

93rd

Ave

.

City of Peoria

Hayden-Rhodes AqueductCentra

l Arizona Project

Maricopa County

Maricopa County

City of Peoria

Maricopa County

Maricopa County

Maricopa County

City of Surprise

W03 SubstationSiting Area

W04 SubstationSiting Area

W05 SubstationSiting Area

TS14SubstationSiting Area

Phase 1

Phase 1

Phase 1 T

6 N

T 6

N

T 5

N

T 5

N

T 4

N

T 4

N

R 2 W R 1 W R 1 E

R 2 W R 1 W R 1 E

0 0.5 1 1.5 2

Miles

Conceptual Siting

PIMA

60

10

8

17

10

Phoenix

MARICOPA

YUM

ALA

PA

Z

YAVAPAI

GILA

PINAL

CasaGrande

Regional Area Map

Potential 69kV ElectricalTransmission Connection

Local Road

Highway

Arterial Road

Study Area Contour (20ft Interval)

Township and Range

Reference Features

Canal

North PeoriaFacilities Siting StudyLand Ownership / Jurisdiction

69/12kV Substation Siting Area

230/69/12kV Substation Siting Area

Siting Areas and Potential Electrical Transmission Connnectionneeds are conceptual and not all connections are required.Conceptual 69/12kV Substation Siting Areas, as displayed, areapproximately 875 acres. Actual 69/12kV Substation sites requireapproximately 5 acres.

Note:

Bureau of Land Management

Bureau of Reclamation

Arizona State Trust

Maricopa County

Private

Land Ownership

Land JurisdictionCity of Peoria

City of SurpriseCity of Phoenix

Maricopa County

Transmission Facilities500kV Transmission Line500kV Substation

230kV Transmission Line

69kV PowerlineNote: APS is sole or joint owner of substation unless shown otherwise

345kV Transmission Line230kV Substation

69kV Substation

*Phase 1*Phase 1 - Conceptual connections to, and location of, Substation W03

briefings with said developers and jurisdictions to solicit

input from them as the project moves forward.

YOUR INPUT IS IMPORTANT TO APSAn important component of this siting process is to receive

input from residents, tenants, property owners, businesses

and other stakeholders within the study area. Members of

the public and all interested parties are invited to join APS

for an open house to learn more about the purpose and

need for the project and the project siting process, and

to provide input. As a convenience to the public APS will

be holding two open houses. The first open house will be

held Thursday, May 3rd, from 5:30–7:30 p.m. at the Desert

Oasis Elementary School (17161 W Bajada Rd, Surprise, AZ

85387). The second open house will be held Tuesday, May

8th, from 5:30–7:30 p.m. at the Lake Pleasant Elementary

School (31501 N Westland Rd, Peoria, AZ 85383).

Following the public meeting, APS, with EPG’s assistance,

will evaluate the input gathered and will analyze and

further develop potential power line route and substation

location alternatives.

After the data has been analyzed, APS will hold a second

round of briefings to share and discuss possible power

line route and substation location alternatives with local

jurisdictional leaders and affected stakeholders seeking

their input. A second newsletter will be distributed

showing power line route and substation location

alternatives and inviting the public to participate

in a second round of public meetings.

Following the second round of meetings, APS and EPG

will evaluate all the information received throughout

the process. Based on these evaluations, APS will select

the final preferred route. A third and final newsletter

will be prepared and distributed to the public and key

stakeholders. This final newsletter will illustrate the

selected power line routes and substation locations and

the anticipated schedule for construction.

PROJECT UPDATESThroughout the planning process, a webpage will

be maintained with the latest information. This can

be found by navigating to aps.com/siting, then clicking

on “find out more” under current projects. Comment forms

can be completed and submitted through the website,

or if preferred, comments can be sent to Stephen Eich,

APS Siting Consultant, at [email protected].

Comments also can be provided by phone

at 1 (888) 352-4365. CS#1803050

Public Information Open House Meetings5:30–7:30 p.m. Thursday, May 3rdOasis Elementary School 17161 W Bajada RdSurprise, AZ 85387

5:30–7:30 p.m. Tuesday, May 8thLake Pleasant Elementary School 31501 N Westland Rd Peoria, AZ 85383