7 1 MRP Process

  • Upload
    ashok

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

  • 7/27/2019 7 1 MRP Process

    1/27

    Materials Planning

    Material requirement planning (MRP-I) is a

    logical approach for determining raw materials,assemblies, sub-assemblies and parts needed toproduce each end product on a short-term basis.

    It also provides the schedule, specifying wheneach of these should be ordered or produced.

    It deals with dependent demand situations.

    Starting from computing materials required andcreating a schedule, it has evolved intomanufacturing resource planning (MRP-II), andnow into enterprise resource planning (ERP).

  • 7/27/2019 7 1 MRP Process

    2/27

    MRP-I

    MRP-I determines how much of each item is

    needed and when to produce a specified numberof end products in a specified time period byevaluating the master production schedule (MPS),and bill of materials (BOM) and inventory record

    file.

    It is based on dependent demand. Dependentdemand is caused by the demand for higher level

    of items (end products). For example, tyres, wheelsand engines are dependent items of automobile.

  • 7/27/2019 7 1 MRP Process

    3/27

    Basic purposes of MRP System

    To determine requirements of parts materials

    needed for end products

    To create implementable schedules for receivingparts/materials

    To do capacity planning To control inventory

    To satisfy customer at optimum cost

    RIGHT MATERIAL TO RIGHT POINT AT RIGHT TIME

  • 7/27/2019 7 1 MRP Process

    4/27

    Role of Materials Management in

    a Business As a basic function of the firm

    As a manager of outside manufacturing:Materials manager is answerable for purchase of

    items manufactured outside as productionmanager is answerable for parts produced in-house. Hence, materials manager is rightly calledmanager of outside manufacturing.

    As a controller of cost: Major costs withmaterials include ordering or set-up costs,carrying costs, logistics costs (transportation andwarehousing) and shortages or surpluses costs,besides the cost of purchased items.

  • 7/27/2019 7 1 MRP Process

    5/27

    Philosophy in MRP

    MRP adopts the philosophy of expediting andde-expediting.

    A lot of effort is put to expedite the supply whenit is behind the schedule (schedule receipt is past

    due) or when the requirement shifts to an earlierdate.

    It tries to de-expedite the supply if material is

    needed later than the schedule date (against thetraditional approach where it was not a concernand it results in piling up of inventory).

  • 7/27/2019 7 1 MRP Process

    6/27

    Application areas

    Most valuable for companies involved inassembly operations

    Assemble to stock/order: High benefits, for

    example, automobiles, watches, tools,appliances.

    Manufacture to order: High benefits; e.g.,turbine, heavy machine tools.

    Process industries: Medium benefit; e.g., paper,chemicals, paint.

    Fabricate to stock/order: Low benefit; e.g.,piston rings, electrical switches, bearings, gears.

  • 7/27/2019 7 1 MRP Process

    7/27

    Complexities associated with MRP

    Number of parts/sub-assemblies that go into an end product may run

    into several thousands.

    Inventory of a part can exist in the form of raw material, work in

    process (WIP) and finished goods. Keeping track of these make the

    problem complex.

    Even with uniform demand of end products, requirement of parts at

    different points of time becomes non-uniform. This could be due toseveral reasons like, batching of production/ procurement, same part

    going into different sub-assemblies etc. (see the example in next slide)

    The firm as well as suppliers have capacity constraints.

    Changes in customer orders, lead times, machine breakdowns,quality rejections and so forth bring uncertainty in the problem.

    ------- in the presence of the above factors, an optimal solution to the complexproblem is extremely difficult. One can hope for a feasible solution at

    reasonable cost.

  • 7/27/2019 7 1 MRP Process

    8/27

    An example of non-uniform requirements

    subassemblies, X (Each of assemblies A, B, C

    requires one unit of subassembly x.)

    Week->

    1 2 3 4 5 6 7 8 9 10

    D(A) 20 20 20 20 20 20 20 20 20 20

    P(A) 60 - - 60 - - 60 - - 60

    D (B) 10 10 10 10 10 10 10 10 10 10

    P(B) 40 - - - 40 - - - 40 -

    D(C) 5 5 5 5 5 5 5 5 5 5

    P(C) 15 - - 15 - - 15 - - 15

    R(X) 115 - - 75 40 - 75 - 40 75

  • 7/27/2019 7 1 MRP Process

    9/27

    MRP System

    Master Production Schedule(MPS)

    Bill of Materials(BOM)

    Material Planning(MRP Computer

    Programme)

    Secondary Report:Exception reportPlanning reportsReports for performance control

    Primary Report:Schedule of planned ordersSchedule of order releaseChanges in schedule

    Inventory Record File

  • 7/27/2019 7 1 MRP Process

    10/27

    MRP System (cont.)

    Three major inputs:

    (i) Master Production Schedule (MPS)

    (ii) Bill of Materials (BOM)(iii) Inventory Record File

  • 7/27/2019 7 1 MRP Process

    11/27

    Master Production Schedule MPS shows the number of items to be

    produced/received in specific period.

    Aggregate production planning (APP)specifies the optimal combination of product

    rates (for product groups, parts and sub-assemblies), work force level and inventorylevel for intermediate range (a year). It uses avariety of tools and techniques and forms the

    basis of MPS. MPS decides what we are going to make in

    terms of specific product configuration onspecific quantities and on specific dates.

  • 7/27/2019 7 1 MRP Process

    12/27

    MPS (cont.)

    Generally, MPS deals with the end product.

    However, it may include major sub-assemblies orcomponents, in case the product is large or quiteexpensive.

    All manufacturing systems have resourceconstraints such as inventory, material, capacity(equipment/labor), suppliers, money and storage.

    Also, there exist conflicting priorities among

    functional groups. Some of these are illustrated inthe next page.

  • 7/27/2019 7 1 MRP Process

    13/27

    MPS (cont.)

    Some of the conflicting goals are:

    Sales: Meet the customers promised date.

    Finance: Minimize inventory.

    Management: Maximize productivity andcustomer service, minimize resource needs.

    Manufacturing: Have level schedule andminimize set-ups.

    The last two factors pose a big challenge to preparethe master schedule. It takes many iterations tocome to an acceptable plan.

  • 7/27/2019 7 1 MRP Process

    14/27

    MPS (cont.): Aggregate plan

    and MPS: exampleAggregat

    ePlanningfor cars

    Month 1 2

    Car 10000 9000

    MPS fordiff.

    Carmodels

    Week 1 2 3 4 5 6 7 8

    Model-

    1

    2000 4000 2000 1000

    Model-2

    1000 1000 1000 1000

    Model-3

    2000 2000 2000

  • 7/27/2019 7 1 MRP Process

    15/27

    MPS (cont.) conflicting

    facors Time fences: Change in customer demand

    disrupts the planning process. This calls forexpediting and de-expediting.

  • 7/27/2019 7 1 MRP Process

    16/27

    Bill of Materials (BOM)

    BOM shows the list of materials, parts, andsubassembly needed to make the endproduct and the sequence in which the

    product is created. It is also called the product structure file or

    product structure tree because it shows howa product is put together.

    It identifies each item and the quantity usedto make higher order item of which it is apart.

  • 7/27/2019 7 1 MRP Process

    17/27

    Product structure tree

    (PST)A

    B (2) C (3)

    D(2) E (4) F(2) G(4)

    E (1) F (3)

  • 7/27/2019 7 1 MRP Process

    18/27

    BOM (cont.)

    BOM files often list parts using indentation.There are two systems of indentation multi-level and single level indentation

    Multi-level indentation identifies each item andthe manner in which it is assembled. Eachindentation signifies the lower order items orcomponents of the higher order item.

    In single level indentation, listing is doneassembly-wise (item and components).Components are separated from the item usingindentation.

  • 7/27/2019 7 1 MRP Process

    19/27

    Multi-level indentation

    A

    B(2)

    D(2)

    E(1)

    F(3)

    E(4)

    C(3)

    F(2)

    G(4)

  • 7/27/2019 7 1 MRP Process

    20/27

    Single level indentation

    A

    B(2)C(3)

    B

    D(2)

    E(4)C

    F(2)

    G(4)

    D

    E (1)

    F(3)

  • 7/27/2019 7 1 MRP Process

    21/27

    Modular Bill of Material

    It is the term used for item that is producedand stocked as a subassembly (or, module).

    Many end items that are large expensive arebetter scheduled and controlled as modules.

  • 7/27/2019 7 1 MRP Process

    22/27

    A Planning Bill of Material

    A planning bill of materials includes itemswith fractional options. A planning bill canspecify, for example, 0.4 of a part. It meansthat 40% of the units produced contain thatpart and 60% do not.

    l di

  • 7/27/2019 7 1 MRP Process

    23/27

    Low Level Coding

    Identical parts may occur at different levels in different sub-

    assemblies for each end items. Here, identical parts are placed at same level.

    It facilitates the computation of the parts.

    A

    B(2) C(3)

    E(4)

    G(4)

    F(2)

    D(2)

    F(3)E(1)

  • 7/27/2019 7 1 MRP Process

    24/27

    Inventory Record File (IRF)

    A variety of information is contained in IRF.

    These include:1. DATA RELATED ITEM:

    Part number

    Description Lead time

    Standard cost

    Safety stock

    Order quantity

    Last years usage

  • 7/27/2019 7 1 MRP Process

    25/27

    IRF ( cont.)

    2. INVENTORY DATA:

    Gross requirement

    Scheduled receipt on hand Planned order releases

    The inventory status file is kept up to date byposting inventory transaction as they occur.

  • 7/27/2019 7 1 MRP Process

    26/27

    Output Reports:

    1. PRIMARY REPORTS:

    Schedule of planned orders, showing

    quantity and time of orders Schedule of order release for executing the

    planned orders

    Changes in schedule, which include revisionin due dates, order quantity, cancellation oforders etc.

  • 7/27/2019 7 1 MRP Process

    27/27

    Output Reports:

    2. SECONDARY REPORTS:

    Performance control reports indicate

    deviations from plans in respect to quantity,due dates, stock outs, quality, costs, etc.

    Planning reports are connected withforecasting requirements and inventory.

    Exception reports present seriousdiscrepancies, like late or over due orders,excessive scrap and non-existent parts.