Upload
bharathanin
View
218
Download
1
Embed Size (px)
DESCRIPTION
OPWP Plan 2020 Page 39
Citation preview
7-Year Statement (2014-2020) Page 35
Figure 11 Future Power Generation Capacity Requirements Salalah System
2014 2015 2016 2017 2018 2019 2020
Capacity Potentially Available
Contracted Capacity 718 718 718 718 718 718 718
Prospective Salalah 2 IPP (minimum of range) - - - - 300 300 300
Contingency Resources (non-firm) 100 100 100 100 150 150 150
Expected Demand
Peak Demand 468 510 562 628 685 748 800
Total Contracted Capacity Required 524 571 629 703 767 838 896
Deficit (Additional Capacity Required):
Above Current Contracts - - - - 49 120 178
Above Current + Prospective - - - - - - -
"High Case" Demand
Peak Demand 502 560 638 708 781 867 940
Total Contracted Capacity Required 562 627 714 793 875 971 1053
Deficit (Additional Capacity Required):
Above Current Contracts - - - 75 157 253 335
Above Current + Prospective - - - 75 - - 35
Above Current + Prospective + Reserves - - - - - - -
"Low Case" Demand
Peak Demand 441 471 503 563 605 649 676
Total Contracted Capacity Required 493 527 564 631 678 727 758
Deficit (Additional Contracted Capacity Required):
Above Current Contracts - - - - - 9 40
Above Current + Prospective - - - - - - -