Upload
amit-mishra
View
47
Download
0
Embed Size (px)
Citation preview
Contents A. 220/132 KV & 400 KV SUB-STATION
1. Definition 2. Introduction
B. About the substation
B.1 Construction –Site Selection & Layout
C. Equipment in a 220KV & 4 0 0 K V Substation
1) Bus- bar 2) Insulators
a) Pin type insulators
b) Suspension type insulators
c) Strain type insulators
3) Isolating Switches 4) Circuit breaker
a) SF6 Circuit break er
b) Air Circuit breaker
c) Oil Circuit breaker
5) Protective relay 6) Instrument Transformer
i . Current Transf ormer
ii . Voltage Transformer
7) Metering and Indicating Instrument
8) Miscellaneous equipment
9) Power Transformer
a) autotransformer
10) Lightening arrestors
11) Line isolator
12) Conductors
I. Bundled conductors
II. Ground wires
13) Wave trap
14)Communication in power system
A) Telecommunication
I. Microwave Communication System
II. Fibre Optic Communication System
III. Power Line Carrier Communication System
B) SCADA system
A .1) Definit ion of sub - s t a t i o n : -
“The assembly of apparatus used to change some
characteristics (e.g. Voltage ac t o d c freq. p.f. etc) of
electric supply is called sub-station”.
A . 2 ) Introduction : - The present day electrical power system is a.c. i.e. electric
power is generated, transmitted and distributed in the
form of Alternating current. The electric power is produce
at the power station, which are located at favorable places,
generally quite away from the consumers. It is delivered to
the consumer through a large network of transmission and
distribution. At many place in the line of power system, it
may be desirable and necessary to change some
characteristic (e.g. Voltage, ac to dc, frequency p.f. etc.) of
electric supply. This is accomplished by suitable apparatus
called sub-station for example, generation voltage (11KVor
6.6 KV) at the power station is stepped up to high voltage
(Say220KVt o 1 3 2 KV) for transmission of electric power.
Similarly near the consumer‟s localities, the voltage may
have to be stepped down to utilization level. This job is again
accomplished by suitable apparatus called sub-station.
B ) A b o u t t h e s u b s t a t i o n : - Panki Thermal Power Station is located at Panki in Kanpur district in the
Indian state of Uttar pradesh , about 16 km from Kanpur . It has an installed
capicity of 220 Mega Watts.
The Central government has commissioned a 210 MW unit at Panki Power
Station.
At PTPS, 2x110 MW BHEL made coal fired turbo generating units are
presently in operation. These 110 MW machines were manufactured,
supplied and commissioned by M/s BHEL, during 1976-77 with features of
reheating and regenerative feed heating. The Steam Generator is balanced
draft, radiant, dry bottom, single drum, natural circulation, vertical water
tube type construction with skin casing and semi direct type of firing
system. Apart from the above 110 MW units, 2x32 MW Russia made turbo
generating units were also installed at PTPS in 1967-68, however these units
have become obsolete and permanently closed now after running for about
30 years.
The most important of any substation is the grounding
(Earthing System) of the instruments, transfor mers etc. used in
the substation for the safety of the operation personnel as well as
for proper system operation and performance of the protective
devices.
An earthes system comprising of an earthing mat buried at a
suitable depth below ground and supplemented with ground rods
at suitable points is provided in the substations. These ground the
extra high voltage to the ground. As it is dangerous to us to go
near the instrument without proper earth. If the instruments
are not ground properly they may give a huge shock to anyone
who would stay near it and also it is dangerous for the costly
instrument as they may get damaged by this high voltage.
B . 1 ) S i t e S e l e c t i o n & L a y o u t 2 2 0 K V & 4 0 0 K V S u b s t a t i o n : -
2 2 0 K V S u b -Station forms an important link between
Transmission network and Distribution network. It has a
vital influence of reliability of service. Apart from
ensuring efficient transmission and Distribution of
power, the sub-station configuration should be such that
it enables easy maintenance of equipment and minimum
interruptions in power supply. Sub-Station is
constructed as near as possible to the load center. The
voltage level of power transmission is decided on the
quantum of power to be transmitted to the load center.
Selection of s ite :-
Main points to be considered while selecting the site for Grid
Su b-Station are as follows:
i) The site chosen should be as near to the load center as possible.
ii) It should be easily approachable by road or rail for
transportation of equipments.
iii) Land should be fairly leveled to minimize development cost.
iv) Source of water should be as near to the site as possible. This is
because water is required for various construction activities
(especially civil works), earthing and for drinking purposes etc.
v) T h e s u b -station site should be as near to the town / city but
should be clear of public places, aerodromes, and Military / police
installations.
vi) The land should be have sufficient ground area to accommodate
substation equipments, buildings, staff quarters, space for storage
of material, such as store yards and store sheds etc. with roads
and space for future expansion.
vii) Set back distances from various roads such as National
Highways, State Highways should be observed as per the regulations
in force.
Viii While selecting the land for the Substation preference to be
given to the Govt. land over private land.
ix) The land should not have water logging problem.
x) Far away from obstructions, to permit easy and safe approach
/ termination of high voltage overhead transmission lines.
B . 2 ) E q u i p m e n t i n 2 2 0 K V & 4 0 0 K V S u b - St at ion : -
The equipment required for a transformer Sub-Station
depends upon the type of Sub-Station, Service
requirement and the degree of protection desired.
220K V EHV Sub-Station has the following major
equipments.
1 ) B u s - b a r :-
When a no. of lines operating at the same voltage have to
be directly connected electrically, bus-bar are used, it is made up of
copper or aluminum bars (generally of rectangular X-Section) and
operate at constant voltage.
The bus is a line in which the incoming feeders come into a nd
get into the instruments for further step up or step down. The first
bus is used for putting the incoming feeders inLAsingleline.There
may be double line in the bus so that if any fault occurs in the
one the other can still havethe current and the supply will not
stop. The two lines in the bus are separated by a little
distanceby a Conductor having a connector between them. This is
so that one can work at a time and theother works only if the first
is having any fault.
Bus bars:-
b
2 ) I n s u l a t o r s : -
The insulator serves two purpose. They support the conductor (or
bus bar) and confine the current to the conductor.
The most commonly used material for the manufactures of
insulators is porcelain. There are several type of insulator (i.e.
pine type, suspension type etc.) and there used in Su b-Station will
depend upon the service requirement.
Ceramic insulators
Glass insulators
a) PIN INSULATOR:- Offering an extensive range of 11KV, 22KV and 33 KV pin insulators that
are fabricated from high grade raw material as per the demand of various
electrical industries. Pin insulators it is supported on a pin and provide a
means to hold the insulator to the pin and provide a means to secure the
conductor to the insulator. We offer these pin insulators at varied standard
and customized specifications at cost efficient rates.
11 KV PIN INSULATORS
Our range of 11KV pin insulators encompasses RR / PN / 1105, RR / PN /
1103, RR / PN / 1104 and RR / PN / 1102 which are available in different
technical specifications. These highly efficient pin insulators are less
vulnerable to damage and can normally withstand the line voltage for a
considerable time with ease.
RR / PN / 1105 RR / PN / 1103
RR / PN / 1104
RR / PN / 1102
VOLTAGE CLASS 22 KV AND 33 KV
Pin insulators in voltage class 22KV and 33KV have found application in
varied industries and are widely used in low cost distribution lines. Our
pin insulator is designed to secure the conductor to itself. Top quality pin
insulator includes RR / PN / 2201, RR / PN / 3301, RR / 004 / 22 PIN and
RR / 003 / 33 PIN.
RR / PN / 2201 RR / PN / 3301
RR / 004 / 22 PIN RR / 003 / 33 PIN
b) SUSPENSION INSULATORS:-
Suspension insulators are made of multiple units, with the number of unit
insulator disks increasing at higher voltages. The number of disks is
chosen based on line voltage, lightning withstand requirement, altitude,
and environmental factors such as fog, pollution, or salt spray. Longer
insulators, with longer creepage distance for leakage current, are required
in these cases.
Suspension type insulators:-
C) STRAIN INSULATORS :-
A strain insulator is an insulator that provides both large electrical
insulation and a large load-bearing capacity. A typical strain insulator is a
piece of glass or porcelain that is shaped to accommodate two cables or a
cable shoe and the supporting hardware on the support structure (hook
eye, or eyelet on a steel pole/tower). The shape of the insulator maximizes
the distance between the cables while also maximizing the load-bearing
transfer capacity of the insulator. When the line voltage requires more
insulation than a single insulator can supply, strain insulators are used in
series: A set of insulators are connected to each other using special
hardware. The series can support the same strain as a single insulator, but
the series provides a much higher effective insulation.
Strain type insulators:-
3) I s o l a t i n g S w i t c h e s : -
I n S u b - Station, it is often desired to disconnect a part of the
system for general maintenance and repairs. This is accomplished by
an isolating switchor isolator. An isolator is essentially a kniff
Switch and is design to often open a circuit under no load, in other
words, isolator Switches are operate only when the line is which they
are connected carry no load. For example, consider that the isolator
are connected on both side of a cut breaker, if the isolators are to be
opened, the C.B. must be opened first .
3 pole switch:-
4 ) C i r c u i t b r e a k e r : -
A circuit breaker is an equipment, which can open or close a
circuit under normal as well as fault condition. These circuit
breaker breaks for a fault which can damage other instrument in the
station.It is so designed that it can be operated manually (or by
remote control) under normal conditions and automatically under
fault condition.There are mainly two types of circuit breakers
used for any substations. They are
(a) SF6 circuit breakers;
(b) air circuit breakers;
(c) oil circuit breakers.
For the latter operation a relay wt. is used with a C.B. generally bulk
oil C.B. are used for voltage upto 66 KV while for high voltage low oil
& SF6 C.B. are used. For still higher voltage, air blast vacuum or
SF6 cut breaker are used.
(a) SF6 CIRCUIT BREAKER :-
The use of SF6 circuit breaker is mainly in the substations
which are having high input kv input, say above 220kv and more.
The gas is put inside the circuit breaker by force i .e. under high
pressure.
When if the gas gets decreases there is a motor connected to the
circuit breaker. The motor starts operating if the gas went lower
than 20.8 bar. There is a meter connected to the breaker so that it
can be manually seen if the gas goes low. The circuit breaker uses
the SF6 gas to reduce the torque produce in it due to any faul t in
the line. The circuit breaker has a direct link with the
instruments in the station, when any fault occur alarm bell rings.
SF6 ckt breaker diagram:-
(b) AIR CIRCUIT BREAKER :-
These type of breakers employ „air blast‟ as the quenching medium.The
contacts are opened by air blast produced by the opening of blast valve.The
air blast cools the arc and sweeps away the arcing products to the
atmosphere.This rapidly increases the dielectric strength of the medium
between contacts and prevents from re-establishing the arc.Consequently
the arc is extinguished and the flow of current is interrupted.
(c ) OIL CIRCUIT BREAKER :-
A high-voltage AC electrical switch whose main contacts are located in a
space filled with mineral (transformer) oil. Upon interruption of the
electric circuit, an electric arc forms between the contacts of the circuit
breaker. Because of the high temperature of the arc the oil is evaporated
rapidly and oil vapors are partially decomposed, liberating ethylene,
methane, and other gases. A gas bubble is formed in the arcing zone; the
pressure in the bubble may be as high as several dozen mega newtons per
sq m. The arc is then extinguished, both because of its elongation upon
parting of contacts and because of intensive cooling by the gases and oil
vapor.
Low oil ckt breaker diagram :-
5) P r o t e c t i v e r e l a y :-
A p r o t e c t i v e relay is a device that detects the fault and initiates
the operation of the C.B. to isolate the defective element from the
rest of the system”. The relay detects the abnormal condition in the
electrical circuit by constantly measuring the electrical quantities,
which are different under normal and fault condition. The electrical
quantities which may change under fault condition are voltage,
current, frequency and p hase angle. Having detect the fault, the
relay operate to close the trip circuit of C.B.
Relay diagram:-
6 ) Instrument Trasformer: -
The line in Sub-Station operate at high voltage and carry
current of thousands of amperes. The measuring
instrument and protective devices are designed for low
voltage (generally 110V) and current (about 5A). Therefore,
they will not work satisfactory if mounted directly on the
power lines. This difficulty is overcome by installing
Instrument transformer, on the power lines. There are two
types o f instrument transformer.
i ) C u r r e n t Transformer : -
A current transformer is essentially a step-down
transformer which steps-down the current in a known
ratio, the primary of this transformer consist of one or
more turn of thick wire connected in series with the line,
the secondary consist of thick wire connected in series
with line having large number of turn of fine wire and
provides for measuring instrument, and relay a current
which is a constant faction of the current in t h e l i n e .
Current transformers are basically used to take the
readings of the currents entering the substation. This
transformer steps down the current from 800 amps
to1amp. This is done because we have no instrument for
measuring of such a large current. The main use of his
transformer is
(a) distance protection;
(b) backup protection;
(c) measurement.
Current transformer(CT) diagram:-
i i ) V o l t a g e T r a n s f o r m e r : -
It is essentially a step– down transformer and step down the
voltage in known ratio. The primary of these transformer consist
of a large number of turn of finewire connected across the line.
The secondary way consist of a few turns and provides for
measuring instruments and relay a voltage which is known
fraction of the line voltage.
Potential transformer(PT) diagram:-
7 ) Metering and Indicating Instrument :-
There are several metering and indicating Instrument (e.g.
Ammeters, Volt- meters, energy meter etc.) installed in a
Substation to maintain which over the circuit quantities. The
instrument transformer are invariably used with them for
satisfactory operation .
8 ) Miscellaneous equipme nt:-
In addition to above, there may be following equipment in a
Substation :
i ) Fuses
i i ) Carrier - current equipment
i i i ) S u b -Station auxiliary supplies
9) Power Transformer : -
There are three transformers in the incoming feeders so that the
three lines are step down at the same time. In case of a 220KV or
more KV line station auto transformers are used. While in case of
lower KV line such as less than 132KV line double winding
transformers are used.
a) Autotransformer :
Transformer is static equipment which converts electrical energy
from one voltage to another. As the system voltage goes up, the
techniques to be used for the Design, Construction, Installation,
Operation and Maintenance also become more and more critical.
If properc a r e i s exercised in the installation, maintenance and
condition monitoring of the transformer, it can give the user
trouble free service throughout the expected life of equipment
which of the order of 25-35 years. Hence, it is very essential that the
personnel associated with the installation, operation or
maintenance of the transformer is through with the instructions
provided by the manufacture.
Autotransformer taping:-
10) Lightening arrestors:-
Lightening arrestors with earth switch lightening arrestors after
the current transformer are used so as to protect it from
lightening i.e. from high voltage entering into it. This lightening
arrestor has an earth switch, which can directly earth the
lightening. The arrestor works at 30° to 45° angel of
the lightening making a cone. The ear th switch can be operated
manually, by pulling the switch towards ground. This also helps in
breaking the line entering the station. By doing so maintenance
and repair of any instrument can b performed.
Different types of lighning arrestors:-
It is a device used on electrical power systems to protect the
insulation on the system from the damaging effet of
lightning. Metal oxide varistors (MOVs) have been used for power
system protection since the mid 1970s. The typical lightning arrester
also known as surge arrester has a high voltage terminal and a
ground terminal. When a lightning surge or switching surge travels
down the power system to the arrester to the ground.
11) Line isolator :-
The line isolators are used to isolate the high voltage
Flow throughthe line into the bus. This isolator prevents the
instruments to get damaged. It also allows the only needed voltage
andrest is earthed by itself. In electrical engineering, a disconnector or
isolator switch is used to make sure that an electrical circuit can be
completely de-energised for service or maintenance. Such switches are
often found in electrical distribution and industrial applications where
machinery must have its source of driving power removed for adjustment
or repair. High-voltage isolation switches are used in electrical substations
to allow isolation of apparatus such as circuit breakers and transformers,
and transmission lines, for maintenance.
12) Conductors:-
Aluminium conductors reinforced with steel (known as ACSR) are
primarily used for medium and high voltage lines and may also be used for
overhead services to individual customers. Aluminium conductors are
used as it has the advantage of lower resistivity/weight than copper, as well
as being cheaper.
While larger conductors may lose less energy due to lower electrical
resistance, they are more costly than smaller conductors. An optimization
rule called Kelvin's Law states that the optimum size of conductor for a
line is found when the cost of the energy wasted in the conductor is equal
to the annual interest paid on that portion of the line construction cost due
to the size of the conductors. The optimization problem is made more
complex due to additional factors such as varying annual load, varying cost
of installation, and by the fact that only definite discrete sizes of cable are
commonly made.
I. Bundle conductors :-
Bundle conductors are used to reduce corona losses and audible noise.
Bundle conductors consist of several conductor cables connected by non-
conducting spacers. For 220 kV lines, two-conductor bundles are usually
used, for 380 kV lines usually three or even four.
Bundle conductors are used to increase the amount of current that may be
carried in a line. Due to the skin effect, ampacity of conductors is not
proportional to cross section, for the larger sizes. Therefore, bundle
conductors may carry more current for a given weight.
A bundle conductor results in lower reactance, compared to a single
conductor. It reduces corona discharge loss at extra high voltage (EHV)
and interference with communication systems. It also reduces voltage
gradient in that range of voltage.
Double conductors four conductors
II. Ground wires :-
Overhead power lines are often equipped with a ground conductor (shield
wire or overhead earth wire). A ground conductor is a conductor that is
usually grounded (earthed) at the top of the supporting structure to
minimise the likelihood of direct lightning strikes to the phase conductors.
Shield wires on transmission lines may include optical fibers (OPGW),
used for communication and control of the power system.
13) wave trap:-
It is also called "Wave trap". It is connected in series with the power
(transmission) line.It blocks the high frequency carrier waves (24 KHz to
500 KHz) and let power waves (50 Hz - 60 Hz) to pass through. It is
basically an inductor of rating in Milli henry (approx 1 milli Henry for 220
KV 1250 Amp.).
Wave trap diagram:-
14) Communication in Power System
Following are mainly three inter-related areas of functions in UPPTCL for
management of power system:
A) Telecommunication
B) SCADA- Supervisory Control and Data Acquisition System.
A) TELECOMMUNICATION
There are three different types of telecommunication systems in UPPTCL
i.e.
i. Microwave Communication System,
ii. Fibre-optic Communication System,
iii. PLCC-Power Line Carrier Communication.
Voice Frequency (VF) channels of all these systems have been
integrated/interconnected to make a hybrid communication system.
Microwave & Fibre Optic are multi-channels communication systems and
are also called 'Wideband communication system'. PLCC is single channel
communication system. A brief overview of these three types of
telecommunication system of UPPTCL is as below:
I. Microwave Communication System
Microwaves travel in 'Space' and any object in the path can obstruct
communication system. Microwave is called 'line-of-sight' communication
system. As such, its antennas are mounted on high towers so that even
trees should not obstruct path of microwaves. UPPTCL is using frequency
band between 2.3 GHz to 2.5 GHz. The height for antenna are calculated by
taking into account many factors, such as, distance between two locations,
path clearance, height from sea level of these locations, tropical area,
reflection points, and so on. As such, height of towers varies from location
to location. Tower heights at our microwave stations range from 30 to 110
meters. Starting from Muzaffarnagar (220KV substation Nara), in the
north-west, to Rihand (Pipri), in south-east of UP, 33 microwave stations
have been established. A list of microwave stations with height of towers
has been given at the end of this write-up. This covers a route length of
over 1000 Km.
II. Fibre Optic Communication System
It is new communication system and has been introduced in UPPTCL since
2001. Optical fibre cable, in the form of 'Optical Fibre Composite Ground
Wire' (OPGW), has been installed on transmission towers by replacement
of earth wire. Earth wires of following five transmission lines, total route
length of 408 Km., have been replaced:
'Optical Line Terminal Equipment' (OLTE) have been manufactured by
Fujitsu, Japan and have been installed at eight sub-stations (Muradnagar,
Moradabad, C.B.Ganj, Unnao, Panki, Sahupuri, Sarnath & Azamgarh). The
electrical signal of 2Mb/s or 34Mb/s, as the case may be, from OLTE is
connected with Primary Multiplexing equipment supplied by 'Nokia'
Finland. Its NMS provides operational support for the 'Fibre Optic
Transmission System' (FOTS). For testing, commissioning & maintenance
'FLEXR' and 'FLEXR Plus' computer software programmes have been
provided. 'FLEXR' is used for initial settings of OLTEs of fibre optic
network. Similar to microwave NMS, 'FLEXR Plus' helps in remote
diagnosis, operation and maintenance of fibre optic network. For complete
communication control system, a NMS100 system has installed at NRLDC,
New Delhi, which is in position to diagnose faults of whole northern
region.
OPGW has been manufactured by Farukawa, Japan. They have done
replacement work, on live (hot) lines, by using a unique installation
technology. The OPGW in our system has got twelve (12) 'Dual Window
Single Mode' (DWSM) type fibres in it. Optical signals of 1310 or 1550
nanometer (nm) wavelength are being used. Only two fibres are required
for a multi-channel link between two stations. One fibre is used for
transmitting optical signal and second for receiving from other end. In our
system two fibres have been used for 'Normal' communication path and
two fibres for 'protection' path. Fibre optic communication system has got
a wide bandwidth transmission capability. Two fibres are sufficient for
providing more than one lakh telephone channels on both sides. As such, a
high-speed data, containing large volumes of information can be
transmitted at low cost.
III. Power Line Carrier Communication
System
Power Line Carrier Communication (PLCC) is a single channel
communication system in which its channel (300 to 3400 Hz) is divided
into two parts i.e. speech band is generally kept 300 to 2400Hz or 300 to
2000Hz and rest is used as data band. Due to narrow speech band in PLCC,
voice of poor quality is available in comparison to wideband
communication system. In this system, signal travels on the transmission
line from one end to other end. Transmitter output (Radio Frequency
signal) is fed to the transmission line through a Coupling Capacitor or CVT.
RF power output is in frequency band from 70 KHz to 500 KHz. Inductors,
called 'Wave Traps' are used at the ends of the signals. PLCC is also used
for line protection signal. Protection signals are transmitted through PLCC
system for tripping circuit breaker of other end of transmission line.
UPPTCL has a wide network of PLCC links. Presently, its number of PLCC
links are about 550.
Plc block diagram:-
B) SCADA SYSTEM
In SCADA system measured values, i.e. analogue (measured value) data
(MW, MVAR, V, Hz Transformer tap position), and Open/Closed status
information, i.e. digital data (Circuit Breakers/Isolators position i.e. on/off
status), are transmitted through telecommunication channels to respective
sub-LDCs. For this purpose Remote Terminal Units (RTUs) at 400KV,
220KV and few important 132KV sub-stations have been installed. System
values & status information below 132 KV have not been picked up for data
transmission, except for 33KV Bus isolator position and LV side of
generators. Secondary side of Current Transformers (CT) and Potential
Transformer (PT) are connected with 'Transducers'. The output of
transducers is available in dc current form (in the range of 4mA to 20mA).
Analogue to digital converter converts this current into binary pulses.
Different inputs are interleaved in a sequential form and are fed into the
CPU of the RTU. The output of RTU, containing information in the form of
digital pulses, is sent to subLDC through communication links. Depending
upon the type of communication link, the output of RTU is connected,
directly or through Modem, with the communication equipment. At
subLDC end, data received from RTU is fed into the data servers. In
general, a SCADA system consists of a database, displays and supporting
programmes. In UPPTCL, subLDCs use all major functional areas of
SCADA except the 'Supervisory Control/Command' function. The brief
overview of major 'functional areas' of SCADA system is as below:
1. Communications - Sub-LDC's computer communicates with all RTU
stations under its control, through a communication system. RTU polling,
message formatting, polynomial checking and message retransmission on
failure are the activities of 'Communications' functional area.
2. Data Processing - After receipt of data through communication system it is
processed. Data process function has three sub-functions i.e. (i)
Measurements, (ii) Counters and (iii) Indications.
'Measurements' retrieved from a RTU are converted to engineering units
and linearised, if necessary. The measurement are then placed in database
and are checked against various limits which if exceeded generate high or
low limit alarms.
The system has been set-up to collect 'Counters' at regular intervals:
typically 5 or 10 minutes. At the end of the hour the units is transferred
into appropriate hour slot in a 24-hour archive/history.
'Indications' are associated with status changes and protection. For those
statuses that are not classified as 'alarms', logs the change on the
appropriate printer and also enter it into a cyclic event list. For those
statuses, which are defined as an 'alarms' and the indication goes into
alarm, an entry is made into the appropriate alarm list, as well as in the
event list and an audible alarm is generated in the sub-LDC.
3. Alarm/Event Logging - The alarm and event logging facilities are used by
SCADA data processing system. Alarms are grouped into different
categories and are given different priorities. Quality codes are assigned to
the recently received data for any 'limit violation' and 'status changes'.
Alarms are acknowledged from single line diagram (or alarm lists) on
display terminal in LDCs.
4. Manual Entry - There is a provision of manual entry of measured values,
counters and indications for the important sub-station/powerhouse, which
are uncovered by an RTU or some problem is going on in its RTU,
equipment, communication path, etc.
5. Averaging of Measured Values - As an option, the SCADA system supports
averaging of all analogue measurements. Typically, the averaging of
measured values over a period of 15 minutes is stored to provide 24 hours
trend.
6. Historical Data Recording (HDR) - The HDR, i.e. 'archive', subsystem
maintains a history of selected system parameters over a period of time.
These are sampled at a pre-selected interval and are placed in historical
database. At the end of the day, the data is saved for later analysis and for
report generation.
7. Interactive Database Generation - Facilities have been provided in such a
way that an off-line copy of the SCADA database can be modified allowing
the addition of new RTUs, pickup points and communication channels.
8. Supervisory Control/Remote Command - This function enables the issue of
'remote control' commands to the sub-station/powerhouse equipment e.g.
circuit breaker trip command. Though, there is provision of this function
in this system, yet it is not used in U.P. As such, related/associated
equipment have not been ordered.
9. Fail-over - A 'Fail-over' subsystem is also provided to secure and maintain
a database of devices and their backups. The state of the device is
maintained indicating whether it is 'on-line' or 'failed'. There is a 'backup'
system, which maintains database on a backup computer and the system is
duplicated.
SLDC Lucknow has a large and active 'Mimic Board' in its Control room.
This mimic board displays single line diagram of intra State transmission
system i.e. grid network of 400KV, 220KV and important 132KV sub-
stations, transmission lines, thermal & hydro powerhouses. Outgoing
feeders, shown in the mimic board, have 'achieve' (LED display) colored
indications, of three different colors, to show the range of power flow at
any moment i.e. 'Normal', 'Nominal' or 'Maximum' of its line capacity.
UPPTCL's transmission network is expanding rapidly and thereby number
of RTUs is also increasing. For new substations and lines, displays in active
and passive forms are required to be made in the Mimic diagram. But,
Mimic Board has a limitation that it cannot incorporate/add large volume
of displays for substations/power houses/transmission lines in 'active'
form due to space constraint and congestion. Due to this Mimic Board is
going to be supplemented with a Video Projection System (VPS) at SLDC,
Lucknow in near future. Also in SLDC & subLDCs, displays of single line
diagrams of RTU sub-stations/power house are viewed on VDUs of large
size (21").
Transmission & reciver block diagram :-
Scada system diagam:-