7'-6 1 2 " 2" 3" 11'-10" 3' 2'-6" CLEAR 10' 2'-11" 3' 3' 3' 2'-6" 3' 2'-6" TECTONICS BLDG 7194 JACK BASKIN ENGINEERING - DEMOLITION & NEW WORK PLANS 7194 - A1.1 DEMOLITION GENERAL NOTES 1. CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING CLEAN, DUST-FREE WORK AREAS AND AREAS ADJACENT TO THE WORK AREAS. MITIGATION MEASURES SHALL INCLUDE BUT SHALL NOT BE LIMITED TO: WALK-OFF MATS AT WORK AREA POINTS OF ENTRY; VISQUEEN CURTAINS AND PARTITIONS; DAILY SWEEPING, VACUUMING AND DAMP-MOPPING; AND DAILY REMOVAL OF TRASH AND DEBRIS. 2. REMOVE (E) MISC WALL-MOUNTED AND FLOOR-MOUNTED ITEMS IN THE AREA OF PROPOSED (N) TR'S. REPAIR, PATCH SMOOTH, CLEAN AND PREP (E) FINISHES TO REMAIN FOR (N) FINISHES. DEMOLITION KEYNOTES PREPARE (E) DOOR FOR (N) HARDWARE REMOVE PORTION OF (E) GYPBD PARTITION FOR (N) DOOR REMOVE (E) WIRE MESH PARTITIONS, CEILING AND DOOR. PATCH AND REPAIR (E) SUBSTRATES AND FINISHES. (E) OSP ENTRY THRU BASEMENT WALL TO REMAIN. NEW WORK NOTES (N) DOOR HARDWARE FOR (E) DOOR. SEE DOOR SCHEDULE. (N) DOOR, FRAME AND HARDWARE. SEE DOOR SCHEDULE. (N) TELECOM EQUIPMENT, SEE TELECOM DWGS (N) MTL STUD AND GYPBD WALL INFILL (E) GYPBD PARTITION TO BE REMOVED OR MODIFIED AREA OF WORK (E) DOOR & FRAME TO REMAIN (E) INTERIOR PARTITION TO REMAIN LEGEND 7194 A11.dwg PROJECT LOCATION KEYPLANS 7194 BASEMENT 7194 FIRST FLOOR 7194 SECOND FLOOR 7194 THIRD FLOOR 7194 A11.dwg 7194 A11.dwg 7194 A11.dwg 7194 A11.dwg 7194 A11.dwg 7194 A11.dwg 7194 A11.dwg 7194 A11.dwg

7194 - A1 · a1.1 demolition general notes 1.contractor shall be responsible for maintaining clean, dust-free work areas and areas adjacent to the work areas. mitigation measures

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 7194 - A1 · a1.1 demolition general notes 1.contractor shall be responsible for maintaining clean, dust-free work areas and areas adjacent to the work areas. mitigation measures

7'-6

1

2

"

2"

3"

11'-10"

3'

2'-6"

CLEAR

10'

2'-11"

3'

3'

3'

2'-6"

3'

2'-6"

TEC

TON

ICS

B

LD

G 7

19

4

JA

CK

B

AS

KIN

E

NG

IN

EE

RIN

G -

DE

MO

LIT

IO

N &

N

EW

W

OR

K P

LA

NS

7194 -

A1.1

DEMOLITION GENERAL NOTES

1.CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING CLEAN,

DUST-FREE WORK AREAS AND AREAS ADJACENT TO THE WORK AREAS.

MITIGATION MEASURES SHALL INCLUDE BUT SHALL NOT BE LIMITED TO:

WALK-OFF MATS AT WORK AREA POINTS OF ENTRY; VISQUEEN CURTAINS

AND PARTITIONS; DAILY SWEEPING, VACUUMING AND DAMP-MOPPING; AND

DAILY REMOVAL OF TRASH AND DEBRIS.

2. REMOVE (E) MISC WALL-MOUNTED AND FLOOR-MOUNTED ITEMS IN THE

AREA OF PROPOSED (N) TR'S. REPAIR, PATCH SMOOTH, CLEAN AND PREP

(E) FINISHES TO REMAIN FOR (N) FINISHES.

DEMOLITION KEYNOTES

PREPARE (E) DOOR FOR (N) HARDWARE

REMOVE PORTION OF (E) GYPBD PARTITION FOR (N) DOOR

REMOVE (E) WIRE MESH PARTITIONS, CEILING AND DOOR. PATCH AND

REPAIR (E) SUBSTRATES AND FINISHES.

(E) OSP ENTRY THRU BASEMENT WALL TO REMAIN.

NEW WORK NOTES

(N) DOOR HARDWARE FOR (E) DOOR. SEE DOOR SCHEDULE.

(N) DOOR, FRAME AND HARDWARE. SEE DOOR SCHEDULE.

(N) TELECOM EQUIPMENT, SEE TELECOM DWGS

(N) MTL STUD AND GYPBD WALL INFILL

(E) GYPBD PARTITION TO BE

REMOVED OR MODIFIED

BUILDING NAME: SOCIAL SCIENCE 2

YEAR CONSTRUCTED: ???

TOTAL BUILDING AREA: APPROX. 75,619 SF (FIVE STORIES)

ACTUAL PROJECT AREA: APPROX. 450 SF (ALL FLOORS)

OCCUPANCY TYPE: B (OFFICES AND LABORATORIES)

CONSTRUCTION TYPE: I

FIRE SPRINKLERS: YES

DESCRIPTION OF WORK: TELECOMMUNICATION ROOM

MODIFICATION/UPGRADE

CODE ANALYSIS:

PROJECT INFORMATION

AREA OF WORK

(E) DOOR & FRAME TO REMAIN

(E) INTERIOR PARTITION TO REMAIN

LEGEND

7194 A11.dwg

PROJECT LOCATION KEYPLANS

7194 BASEMENT

7194 FIRST FLOOR

7194 SECOND FLOOR

7194 THIRD FLOOR

7194 A11.dwg

7194 A11.dwg

7194 A11.dwg

7194 A11.dwg

7194 A11.dwg

7194 A11.dwg

7194 A11.dwg

7194 A11.dwg

Page 2: 7194 - A1 · a1.1 demolition general notes 1.contractor shall be responsible for maintaining clean, dust-free work areas and areas adjacent to the work areas. mitigation measures
Page 3: 7194 - A1 · a1.1 demolition general notes 1.contractor shall be responsible for maintaining clean, dust-free work areas and areas adjacent to the work areas. mitigation measures
Page 4: 7194 - A1 · a1.1 demolition general notes 1.contractor shall be responsible for maintaining clean, dust-free work areas and areas adjacent to the work areas. mitigation measures
Page 5: 7194 - A1 · a1.1 demolition general notes 1.contractor shall be responsible for maintaining clean, dust-free work areas and areas adjacent to the work areas. mitigation measures
Page 6: 7194 - A1 · a1.1 demolition general notes 1.contractor shall be responsible for maintaining clean, dust-free work areas and areas adjacent to the work areas. mitigation measures
Page 7: 7194 - A1 · a1.1 demolition general notes 1.contractor shall be responsible for maintaining clean, dust-free work areas and areas adjacent to the work areas. mitigation measures
Page 8: 7194 - A1 · a1.1 demolition general notes 1.contractor shall be responsible for maintaining clean, dust-free work areas and areas adjacent to the work areas. mitigation measures
Page 9: 7194 - A1 · a1.1 demolition general notes 1.contractor shall be responsible for maintaining clean, dust-free work areas and areas adjacent to the work areas. mitigation measures