QUALITY ASSURANCE DATA BOOK
TRANSIERRA S.A.
SIERRA 1 & 2, PD# 728712 EACH - TAURUS 70 GAS TURBINE DRIVEN COMPRESSOR SET
Solar TurbinesA Caterpillar Company
Volume 1, Unit Number 1
Solar TurbinesA Caterpillar Company
FOREWORD
This technical manual contains manufacturing records and quality/test documentation for Gas Turbine Driven equipment designed and manufactured by Solar Turbines Incorporated in San Diego, California.
TECHNICAL MANUAL OVERVIEW
The technical manual is provided in volume sets. The manual contains the approved Inspection and Test Plan, Package C of C, required records, reports, data sheets and inspection and test reports. Each volume is complete and described below.
TRANSIERRA S.A.
Volume 1, Unit Number 1
SIERRA 1 & 2, PD# 728712 EACH - TAURUS 70 GAS TURBINE DRIVEN COMPRESSOR SET
SIERRA 1 & 2, PD # 72871Table of Contents
ITEMNUMBER
Solar TurbinesA Caterpillar Company
The Table of Contents items for this project correspond to the ITP item numbers identified within each section of the ITP (Inspection and Test Plan). These items are identified with an "X" in column A of the project ITP. A copy of the Project ITP is supplied in section 10.00 for reference.
1. Asme Data Report
LUBE OIL COOLER01.06
2. Pressure Test And Flush Certificate
LUBE OIL COOLER01.06
Asme Data Report
LUBE OIL FILTERS01.07
Asme Data Report
GAS FUEL FILTERS01.08
Certificate
ENGINE HANDLING KIT01.09
Certificate
PACKAGE LIFTING KIT01.10
Pqr, Wps
REVIEW WELDING PROCEDURES02.01
Wqr
REVIEW WELDER QUALIFICATIONS02.02
Traveler
WELD SKID/LIFTING BOLLARDS02.03
SIERRA 1 & 2, PD # 72871 Table of Contents, Continued
ITEMNUMBER
C Of C
LUBE OIL TANK - PNEUMATIC LEAK TEST02.04
C Of C
SURFACE PREPARATION AND PAINT02.05
C Of C
LUBE OIL TANK - INTERNALLY COATED WITH BRAYCO 78502.06
Wps, Pqr
REVIEW WELDING PROCEDURES03.01
Wqr
REVIEW WELDER QUALIFICATION03.02
C Of C
WELD MANIFOLDS DIMENSIONAL CHECK 03.03
C Of C
NDE MANIFOLDS (RADIOGRAPHY - RT)03.04
Hydro Test Log
HYDROSTATIC TEST MANIFOLDS 03.05
Included In The Certified Test Data In Section 08.01
VISUAL INSPECTION OF CONTROL WIRING04.01
Included In The Certified Test Data In Section 08.01
HARDWARE VERIFICATION 04.02
Included In The Certified Test Data In Section 08.01
PROJECT SOFTWARE VERIFICATION 04.03
SIERRA 1 & 2, PD # 72871 Table of Contents, Continued
ITEMNUMBER
Leak Test Chart
COMPRESSOR CASE LEAK TEST05.03.A
Leak Test Chart
COMBUSTOR CASE LEAK TEST05.03.B
Leak Test Chart
ENGINE FUEL MANIFOLD LEAK TEST05.03.C
Shop Floor Information System (inspection Data)
GAS PRODUCER COMPRESSOR ROTOR05.04.A
Shop Floor Information System (inspection Data)
GAS PRODUCER TURBINE ROTOR05.04.B
Shop Floor Information System (inspection Data)
POWER TURBINE ROTOR05.04.C
Shop Floor Information System (inspection Data)
BALANCE GAS PRODUCER COMPRESSOR ROTOR05.04.D
Shop Floor Information System (inspection Data)
BALANCE GAS PRODUCER TURBINE ROTOR05.04.E
Shop Floor Information System (inspection Data)
BALANCE POWER TURBINE ROTOR05.04.F
Included In The Certified Test Data In Section 08.01
ENGINE PERFORMANCE TEST05.07
Shop Floor Information System
IMPELLER OVERSPEED SPIN TEST 06.05
SIERRA 1 & 2, PD # 72871 Table of Contents, Continued
ITEMNUMBER
Shop Floor Information System (inspection Data)
CENTER BODY HYDRO TEST06.06
Shop Floor Information System (inspection Data)
END CAPS HYDRO TEST 06.07
Inspection Data
MECHANICAL AND ELECTRICAL RUNOUT06.08
Balance Computer Printout
ROTOR BALANCE06.08.A
Air Test*
GAS COMPRESSOR AIR TEST 06.10
No Documents Required
PACKAGE ASSEMBLY07.00
Certified Test Data
PACKAGE/CONSOLE ACCEPTANCE TEST08.01
Included In The Certified Test Data In Section 08.01
ENCLOSURE ASSEMBLY STATIC TEST 08.02
Included In The Certified Test Data In Section 08.01
NO LOAD MECHANICAL STRING TEST (ONE UNIT ONLY)08.03
No Documents Required
PACKAGE FINAL INSPECTION09.00
1. Package Certificate Of Compliance
QC DATA BOOK REVIEW 10.01
SIERRA 1 & 2, PD # 72871 Table of Contents, Continued
ITEMNUMBER
2. Itp (reference Copy)
QC DATA BOOK REVIEW 10.01
SECTION: 01.06
LUBE OIL COOLER
1. ASME DATA REPORT
To: Date:
AXC Job Number
Solar Project Name
Solar PD Number
Attn: Solar Part Number
complete this job manual:
6) Murphy-VS-2EX Vibration Switch
Very truly yours,
AIR-X-CHANGERS
Pamela A. Thomas
9330 SKY PARK COURT
SAN DIEGO, CA 92123
LYNNE MELENDREZ & SOLAR QUALITY DOCS
023115AB
TRANSIERRA
PD 72871
154765-72871
3) Metrix-Vibration Switch
April 11, 2003SOLAR TURBINES
The following AXC Library Manual and Vendor files from the Air-X-Changers Library CD are required to
cc: WESTLAND ENGINEERING
Dear Customer:
1) Installation, Maintenance, and Operating Instructions for Electric Drive Units.
2) Moore Fan-EM
4) Siemens -Motor Data
5) Dodge-S-2000 Fan Shaft Bearing
P.O. Box 1804 Tulsa, Oklahoma 74101 918-266-1850 FAX 918-266-1322
Table of Contents
Job Specific DocumentationTransmittal1Table of Contents2Certified Drawing3Parts List4Spec. Sheet 5U1A Data Reports6-7Nameplate8Hydrostatic Test Certifications 9-10Heat Treat Charts11X-Ray Test Reports12-15Ultrasonic Test Reports 16Hardness Survey17Material Traceability Records11-13X-Ray Test Reports14-21Dye Penetrant Test Report22-25Flushing Record 26-31Final Acceptance Certificate 32Form 101633Electrical Device List34Final-In Process35-36Additional-In Process 37-38Paint-In Process 39-40Fan Data41-42Motor Data43-45
P.O. Box 1804 Tulsa, Oklahoma 74101 918-266-1850 FAX 918-266-1322
PARTS LIST
Post Office Box 1804Tulsa, OK 74015Phone: (918) 266-1850Fax (918) 266-1322
JOB NUMBER: 023115 CUSTOMER: SOLAR TURBINES ORDER COVERS: (2) Model 60A-2H
FINISH: GALVANIZED FAN GUARDS (AND HAIL GUARDS IF REQUIRED) SURFACE PREPARATION: Commercial Blast Cleaning - (SSP-SP6) PRIMER COAT: Amercoat 68HS; Minimun of 3 MILS. DFT. FINISH COAT: Amershield Color Solar Grey (RAL 7032); Minimum of 3 MILS. DFT. (Note: Motors and Slidebases are to be painted with the above system, except no sandblast)
P.O. QTY. DESCRIPTION OF COMPONENTS
NOTE: AN ASTERIK (*) IN QUANTITY COLUMN INDICATES A RECOMMENDED SPARE PART 2 SECTION(S) IN ACCORDANCE WITH SPECIFICATION SHEET DATED: 1/30/03
2 60A-2H STRUCTURE(S), COMPLETE WITH: Seal Weld Entire Cooler
* 4 FAN(S): 60 Inch DIAMETER, 3 BLADES, RH ROTATION, MOORE-CL5K MAKE, 6.1 ANGLE @ Clevis, 2-3/16 Inch BORE WITH 1/2 Inch X 1/4 Inch KEYWAY. MODEL/PITCH: 27-VT/Manual, HUB:TAPER
* 4 FAN SHAFT(S): 2-3/16 Inch DIA. X 32 Inch LONG WITH 1/2 Inch SQ. KEYS each END, KEYWAY LENGTH(DRIVE END): 6 Inch, KEYWAY LENGTH(FAN END): 6 Inch, KEY LENGTH: 5.5 Inch
* 8 2-3/16 Inch FAN SHAFT BEARINGS, MAKE/MODEL: Dodge-S2000/P2B-S2-203R, AXC P/N BR1106
* 4 MOTOR(S) Reliance, Siemens, Baldor MAKE, 5 H.P., 1800 RPM, 3 PHASE, 60 Hz, 460 VOLTS, (CSA), (115 volt Space Heater), Per Specification ES1923, w/ a 3/8-16, 1-1/8 deep threaded hole for grounding stud. Explosion Proof (Type 5), Solar P/N: None ENCL.VARIABLE TORQUE, SINGLE WINDING, Vertical SHAFT, W-6 MOUNTING, 184T FRAME, With SLIDEBASE, CUST. SPECIFICATIONS Yes, MOTOR DATA REQUIRED Yes, WIRING DIAGRAMS Yes
* 8 V-BELTS: 3VX-750 TYPE, 17.5 Inch CENTER DISTANCE, 5.3 HP EACH, MATCHED SETS OF 2
4 SHEAVE SET(S): 2 GROOVES, 3V PITCH, FAN SHEAVE: 19 Inch OD, 2-3/16 Inch BORE WITH 1/2 Inch X 1/4 Inch KEYWAY MOTOR SHEAVE: 4.75 Inch OD, 1-1/8 Inch BORE WITH 1/4 Inch X 1/8 Inch KEYWAY
4 VIBRATION SWITCH(ES): Murphy MAKE, VS-2EX, XP MODEL, CSA: YES
4 VELOCITY TRANSMITTER(S): Metrix MAKE, 164V-121 MODEL, CSA: YES 2 SET(S) WIRE BUGSCREENS PER DRAWING 023115-BPL 2 PIPE NIPPLE: O.D., 80 SCHEDULE, 2 LENGTH, 316L MATERIAL 2 UNION ORFICE: N.P.S., 3000# RATING, 1/8 ORFICE, 316L MATERIAL 6 GROUND CONNECTOR: Burndy MAKE, KC23B1 MODEL, MS7001 SYMIX PART NUMBER 2 OUNCE(S) OF CONDUCTIVE ELECTRICAL LUBRICANT: Penetrox MAKE, P8A TYPE, MS7000 SYMIX 4 feet GROUND WIRE: 8 AWG, Tinned, Stranded, copper wire, green insulation with yellow longitudinal stripe,
MS7002 SYMIX PART NUMBER (Contact Boyce Owens of Nelson Electric Supply)
SECTION: 01.07
LUBE OIL FILTERS
ASME DATA REPORT
SECTION: 01.08
GAS FUEL FILTERS
ASME DATA REPORT
SECTION: 01.09
ENGINE HANDLING KIT
CERTIFICATE
LOAD TEST NOT REQUIRED
SECTION: 01.10
PACKAGE LIFTING KIT
CERTIFICATE
SECTION: 02.01
REVIEW WELDING PROCEDURES
PQR, WPS
SECTION: 02.02
REVIEW WELDER QUALIFICATIONS
WQR
SECTION: 02.03
WELD SKID/LIFTING BOLLARDS
TRAVELER
SECTION: 02.04
LUBE OIL TANK - PNEUMATIC LEAK TEST
C OF C
SECTION: 02.05
SURFACE PREPARATION AND PAINT
C OF C
SECTION: 02.06
LUBE OIL TANK - INTERNALLY COATED WITH BRAYCO 785
C OF C
SECTION: 03.01
REVIEW WELDING PROCEDURES
WPS, PQR
SECTION: 03.02
REVIEW WELDER QUALIFICATION
WQR
SECTION: 03.03
WELD MANIFOLDS DIMENSIONAL CHECK
C OF C
SECTION: 03.04
NDE MANIFOLDS (RADIOGRAPHY - RT)
C OF C
SECTION: 03.05
HYDROSTATIC TEST MANIFOLDS
HYDRO TEST LOG
Part Number: M.O. #: QTY. Customer:
Test Pressure: HOLD 10 MIN. Type in other
times.
Date: Badge #:
1038463-301 3857632 2 SIERRA N/A 2/12/03 39211
1011087-300 3857304 2 SIERRA N/A 2/12/03 23120
1014525-302 3857312 1 SIERRA 150 2/13/03 22463
1044497-301 3857313 2 SIERRA 900 2/13/03 39211
201632-300 3857281 2 SIERRA 225 2/13/03 22463
1015583-301 3857273 2 SIERRA 225 2/13/03 23120
1015648-300 3857274 2 SIERRA 225 2/13/03 23120
1036476-300 3857300 2 SIERRA 600 2/13/03 23120
1042817-301 3857297 2 SIERRA 225 2/13/03 23120
1009336-301 3857268 1 SIERRA N/A 2/14/03 23120
1011087-300 3857342 10 SIERRA N\A 2/17/03 22463
1044675-300 3857282 2 SIERRA 225 2/17/03 22463
1051762-300 3857314 2 SIERRA 900 2/17/03 22463
1008396-301 3857305 2 SIERRA 225 2/17/03 23120
1008396-301 3857285 2 SIERRA 225 2/17/03 23120
1008394-301 3857286 2 SIERRA 225 2/17/03 23120
1055704-300 38573156 2 SIERRA 900 2/18/03 39211
1020153-301 3857633 1 SIERRA N/A 2/18/03 39211
1046284-300 3857271 2 SIERRA N/A 2/18/03 39211
1037008-301 3857301 2 SIERRA 600 2/18/03 39211
1007065-300 3857278 2 SIERRA 225 2/18/03 23120
1046283-300 3857270 2 SIERRA N\A 2/19/03 22463
1028668-301 3857306 2 SIERRA 225/450 2/19/03 39211
66-16013-300 3857272 1 SIERRA N\A 2/19/03 22463
1008394-301 3857307 2 SIERRA 225 2/19/03 39211
1044765-300 3857436 1 SIERRA 1075 2/19/03 39211
1008448-301 3857289 2 SIERRA N/A 2/19/03 39211
1008447-300 3857288 4 SIERRA N/A 2/19/03 39211
1018011-301 3857634 1 SIERRA 225 2/19/03 39211
1008871-301 3857341 4 SIERRA N/A 2/19/03 39211
1007064-300 3857277 2 SIERRA 225 2/19/03 23120
1028081-300 3857291 2 SIERRA 300 2/20/03 22463
1044678-300 3857284 2 SIERRA 225 2/20/03 22463
1045040-300 3857276 2 SIERRA 225 2/20/03 23120
1044677-300 3857283 1 SIERRA 225 2/21/03 22463
1042956-300 3857299 1 SIERRA 225 2/21/03 22463
1031750-301 3857295 2 SIERRA 300 2/21/03 23120
1042020-301 3857309 2 SIERRA 300 2/21/03 23120
1031286-302 3857292 2 SIERRA 300 2/25/03 39211
1031751-302 3857296 2 SIERRA 300 2/25/03 22463
1020287-300 3857279 2 SIERRA N\A 2/25/03 22463
1014911-301 3857635 1 SIERRA N/A 2/25/03 39211
1008872-301 3857290 2 SIERRA N\A 2/26/03 22463
1008394-301 3857718 2 SIERRA 225 2/26/03 22463
1039160-301 3857308 2 SIERRA 100 2/26/03 39211
1042024-300 3857310 2 SIERRA 225 2/26/03 39211
1046140-300 3857819 1 SIERRA 500 2/27/03 39211
1037121-300 3857302 2 SIERRA 600 2/27/03 39211
1031289-302 3857293 2 SIERRA 300 2/27/03 39211
1055248-300 3857298 2 SIERRA 300 2/27/03 23120
1025957-300 3857280 2 SIERRA 100 3/4/03 36068
1008403-301 3857287 2 SIERRA 225 3/4/03 36068
1031548-300 3857294 1 SIERRA 300 3/7/03 22463
1042437-300 3858140 1 SIERRA 225 3/13/03 23120
1042166-300 3858138 1 SIERRA N\A 3/14/03 22463
1031548-300 3857294 1 SIERRA 300 3/19/03 22463
1038463-301 3858136 2 SIERRA N\A 3/21/03 22463
1042220-301 3858139 1 SIERRA N/A 3/26/03 39211
1058189-300 3100612 2 SIERRA N\A 3/27/03 22463
1042094-300 3858137 1 SIERRA 225 3/27/03 22463
1040959-301 8085975 1 SIERRA 225 4/21/03 22463
1040959-301 8085876 1 SIERRA 225 4/21/03 22463
1042817-301 3100613 1 SIERRA 225 4/23/03 22463
1040959-300 3857802 2 SIERRA 1/2 225 2/26/03 39211
1018011-301 3857782 1 SIERRA -2 225 2/26/03 39211
1018007-301 3857781 1 SIERRA-2 2250/225 2/25/03 39211
1008396-301 3857719 2 SIERRA-2 225 2/25/03 39211
1020153-301 3857783 1 SIERRA-2 N/A 2/26/03 39211
1044765-300 3857311 2 SIERRA 1075 1/30/03 22463
SECTION: 04.01
VISUAL INSPECTION OF CONTROL WIRING
INCLUDED IN THE CERTIFIED TEST DATA IN SECTION 08.01
SECTION: 04.02
HARDWARE VERIFICATION
INCLUDED IN THE CERTIFIED TEST DATA IN SECTION 08.01
SECTION: 04.03
PROJECT SOFTWARE VERIFICATION
INCLUDED IN THE CERTIFIED TEST DATA IN SECTION 08.01
SECTION: 05.03.A
COMPRESSOR CASE LEAK TEST
LEAK TEST CHART
SECTION: 05.03.B
COMBUSTOR CASE LEAK TEST
LEAK TEST CHART
SECTION: 05.03.C
ENGINE FUEL MANIFOLD LEAK TEST
LEAK TEST CHART
Plotter4.viC:\Prueba de Presion\Plotter4.viLast modified on 1/24/03 at 10:57 AMPrinted on 1/24/03 at 3:53 PM
P a g e 1
3 0 1 5 0 4 - 1 0 1P a r t N u m b e r
T T A 0 3 - 8 4 1 5 2 A N D 8 4 1 5 3Serial Number
3 1N u m b e r o f M e a s u r e m e n t s
0 - 500 psia
S e n s o r
C o m m e n t s
J O S E MO p e r a t o r
1 5 1 4 2 5Start Time
Fri 01- 24- 2003 Start Date
1T i m e B e t w e e n M e a s u r e m e n t s
5 0 0
0
1 0 0
2 0 0
3 0 0
4 0 0
1 2 5
0
2 5
5 0
7 5
1 0 0
3 10 1 2 3 4 5 6 7 8 9 1 0 1 1 1 2 1 3 1 4 1 5 1 6 1 7 1 8 1 9 2 0 2 1 2 2 2 3 2 4 2 5 2 6 2 7 2 8 2 9 3 0
1 3
7
Printer StatusY e s
Print Report?
Fri 01- 24- 2003 Finish Date
1 5 4 8 0 1Finish Time
P r e s s u r e
T e m p e r a t u r e
p
s
i
a
oF
Time (mins.)
4 0 8 . 7M aximum Pressure
7 1 . 0M a x i m u m T e m p e r a t u r e
Turbotec Pressure Test
)2* 4GX
4 0 6 . 7 3First Pressure Reading
4 0 8 . 6 9Last Pressure Reading
4 0 8 . 6 9M a x i m u m T e s t P r e s s u r e
4 0 6 . 2 4M i n i m u m T e s t P r e s s u r e
2 . 4 5Test Pressure Diference
Sensor 0-500 PSIGComments: Date: Fri 01- 24- 2003Time: 15 14 25Operator: JOSE MSerial Number: TTA03-84152 AND 84153Part Number: 301504-101Nominal Test Pressure: *********Sampling Time (mins): 31
Time (mins) Pressure (psia) Temperature (F)0.000 15.216 70.7441.000 406.726 70.7322.000 406.408 70.8233.000 406.253 70.8494.000 406.245 70.7175.000 406.269 70.9026.000 406.416 70.8617.000 406.563 70.7388.000 406.620 71.0059.000 406.734 70.82310.000 406.864 70.84311.000 406.897 70.74712.000 407.052 70.71413.000 407.215 70.62014.000 407.288 70.79415.000 407.402 70.81116.000 407.549 70.82617.000 407.696 70.81118.000 407.737 70.70319.000 407.867 70.82920.000 407.924 70.94621.000 408.038 70.63522.000 408.177 70.72623.000 408.209 70.74424.000 408.356 70.61725.000 408.405 70.89626.000 408.519 70.91427.000 408.527 70.78228.000 408.601 70.83529.000 408.690 70.77630.000 408.690 70.65931.000 13.961 70.703First Pressure Reading: 406.73
Last Pressure Reading: 408.69
Maximum Test Pressure: 408.69
Minimum Test Pressure: 406.24
Maximum Temperature: 71.004925
Finish Date: Fri 01- 24- 2003Finish Time: 15 48 01These results are a verified copy of the data maintained in the testconputer, according toEs 9-78. No leaks.
SECTION: 05.04.A
GAS PRODUCER COMPRESSOR ROTOR
SHOP FLOOR INFORMATION SYSTEM (INSPECTION DATA)
CERTIFICATE OF COMPLIANCESOLAR TURBINES INCORPORATED, HEADQUARTERED IN SAN DIEGO, CALIFORNIA,
HEREWITH CERTIFIES ON INFORMATION AND BELIEF:
ROTORS ASSEMBLY COMPRESSOR AND TURBINEMECHANICAL/ELECTRICAL RUNOUTS AND BALANCE DATA
The following rotors and their supporting documents for Engine Serial # 0203B,PD72871 have been reviewed to ensure that they are in accordance with Solarstandards, drawings, specifications and practices and Quality requirements.
Compressor Rotor Mechanical /Electrical 05.04.A P/N 330206-103 S/N ROB03-25533Balance 05.04.D P/N S/N
GP RotorMechanical/Electrical 05.04.B P/N 199270-200 S/N ROB03-26931Balance 05.04.E P/N S/N
PT RotorMechanical/Electrical 05.04.C P/N 199351-101 S/N ROB03-26932Balance 05.04.F P/N S/N
March 28, 2003Dimensional summary sheet for serial number:
(Dim_Rpt_Opn.Rdf)
ROB03-25533
COMPANY CONFIDENTIAL For Reference Only
Page 1 of 1
ER0 #1ERO #2MRO #1MRO #2SPLINE
Dimension
ELECT R/O NO.1 BRGELECT R/O NO.2 BRGMECH R/O NO.1 BRGMECH R/O NO.2 BRGFWD CONE SPLINE R/O
Description
00500050005000500050
Op#
.04
.02
.00005
.00005
.0001
Result
00000
Minimum
.05
.05.0002.0002.0002
Maximum Red
3921939219392193921939219
Badge
24-FEB-0324-FEB-0324-FEB-0324-FEB-0324-FEB-03
Date Initials Red Sign Off
SECTION: 05.04.B
GAS PRODUCER TURBINE ROTOR
SHOP FLOOR INFORMATION SYSTEM (INSPECTION DATA)
March 28, 2003Dimensional summary sheet for serial number:
(Dim_Rpt_Opn.Rdf)
ROB03-26931
COMPANY CONFIDENTIAL For Reference Only
Page 1 of 1
ELECTMECH
Dimension
RUNOUT #3 BEARING JOURNALRUNOUT #3 BEARING JOURNAL
Description
00200020
Op#
.02
.00005
Result
00
Minimum
.05.0002
Maximum Red
2972829728
Badge
21-FEB-0321-FEB-03
Date Initials Red Sign Off
SECTION: 05.04.C
POWER TURBINE ROTOR
SHOP FLOOR INFORMATION SYSTEM (INSPECTION DATA)
March 28, 2003Dimensional summary sheet for serial number:
(Dim_Rpt_Opn.Rdf)
ROB03-26932
COMPANY CONFIDENTIAL For Reference Only
Page 1 of 1
#4ELEC#4MECH#5ELEC#5MECH
Dimension
BEARING JOURNAL RUNOUTBEARING JOURNAL RUNOUTBEARING JOURNAL RUNOUTBEARING JOURNAL RUNOUT
Description
0020002000200020
Op#
.02
.00005
.02
.00005
Result
0000
Minimum
.05.0002.05
.0002
Maximum Red
28052280522805228052
Badge
22-FEB-0322-FEB-0322-FEB-0322-FEB-03
Date Initials Red Sign Off
SECTION: 05.04.D
BALANCE GAS PRODUCER COMPRESSOR ROTOR
SHOP FLOOR INFORMATION SYSTEM (INSPECTION DATA)
March 28, 2003Dimensional summary sheet for serial number:
(Dim_Rpt_Opn.Rdf)
ROB03-25533
COMPANY CONFIDENTIAL For Reference Only
Page 1 of 1
AFTAMTFWDAMT
Dimension
FINAL RESIDUAL BALFINAL RESIDUAL BAL
Description
00900090
Op#
.0253
.0435
Result
00
Minimum
.18
.18
Maximum Red
2862228622
Badge
25-FEB-0325-FEB-03
Date Initials Red Sign Off
SECTION: 05.04.E
BALANCE GAS PRODUCER TURBINE ROTOR
SHOP FLOOR INFORMATION SYSTEM (INSPECTION DATA)
March 28, 2003Dimensional summary sheet for serial number:
(Dim_Rpt_Opn.Rdf)
ROB03-26931
COMPANY CONFIDENTIAL For Reference Only
Page 1 of 1
ANG.-EANG.-FOZ.IN-EOZ.IN-FR/O1R/O2
Dimension
ANGLE OF IMBALANCEANGLE OF IMBALANCEALLOWABLE IMBALANCE PLANE -E-ALLOWABLE IMBALANCE PLANE -F-FACE RUNOUT DISC #1FACE RUNOUT DISC #2
Description
006000600060006000600060
Op#
246108.023.031.0005.001
Result
000000
Minimum
360360.1.1
.003
.003
Maximum Red
336443364433644336443364433644
Badge
21-FEB-0321-FEB-0321-FEB-0321-FEB-0321-FEB-0321-FEB-03
Date Initials Red Sign Off
SECTION: 05.04.F
BALANCE POWER TURBINE ROTOR
SHOP FLOOR INFORMATION SYSTEM (INSPECTION DATA)
March 28, 2003Dimensional summary sheet for serial number:
(Dim_Rpt_Opn.Rdf)
ROB03-26932
COMPANY CONFIDENTIAL For Reference Only
Page 1 of 1
#3R/O#4R/OANGLE-FANGLE-GOZ.IN.-FOZ.IN.-G
Dimension
DISC #3 FACE RUNOUTDISC #4 FACE RUNOUTANGLE OF IMBALANCEANGLE OF IMBALANCEALLOWABLE IMBALANCE @ PLANE -F-ALLOWABLE IMBALANCE AT PLANE -G-
Description
006500650065006500650065
Op#
.001
.001291180.08.07
Result
000000
Minimum
.004
.003360360.2.2
Maximum Red
336443364433644336443364433644
Badge
22-FEB-0322-FEB-0322-FEB-0322-FEB-0322-FEB-0322-FEB-03
Date Initials Red Sign Off
SECTION: 05.07
ENGINE PERFORMANCE TEST
INCLUDED IN THE CERTIFIED TEST DATA IN SECTION 08.01
SECTION: 06.05
IMPELLER OVERSPEED SPIN TEST
SHOP FLOOR INFORMATION SYSTEM
SECTION: 06.06
CENTER BODY HYDRO TEST
SHOP FLOOR INFORMATION SYSTEM (INSPECTION DATA)
SECTION: 06.07
END CAPS HYDRO TEST
SHOP FLOOR INFORMATION SYSTEM (INSPECTION DATA)
SECTION: 06.08
MECHANICAL AND ELECTRICAL RUNOUT
INSPECTION DATA
SECTION: 06.08.A
ROTOR BALANCE
BALANCE COMPUTER PRINTOUT
SECTION: 06.10
GAS COMPRESSOR AIR TEST
AIR TEST*
SECTION: 07.00
PACKAGE ASSEMBLY
NO DOCUMENTS REQUIRED
SECTION: 08.01
PACKAGE/CONSOLE ACCEPTANCE TEST
CERTIFIED TEST DATA
SECTION: 08.02
ENCLOSURE ASSEMBLY STATIC TEST
INCLUDED IN THE CERTIFIED TEST DATA IN SECTION 08.01
SECTION: 08.03
NO LOAD MECHANICAL STRING TEST (ONE UNIT ONLY)
INCLUDED IN THE CERTIFIED TEST DATA IN SECTION 08.01
SECTION: 09.00
PACKAGE FINAL INSPECTION
NO DOCUMENTS REQUIRED
SECTION: 10.01
QC DATA BOOK REVIEW
1. PACKAGE CERTIFICATE OF COMPLIANCE
SECTION: 10.01
QC DATA BOOK REVIEW
2. ITP (REFERENCE COPY)
Inspection and Test Plan
PAGE 1
Solar TurbinesA Caterpillar Company
The legend at the bottom of each page indicates what inspection / test points or documents are required.
'01'
'02'
'A1'
'R1'
'X'
'M2'
Indicates Customer, Third Party or Certifying Agency inspection on 100% of units, operations or tests on that project. Every effort is made to have the inspector present when these operations are conducted. The inspection or test has not necessarily been performed in advance, prior to the observation point. Should the inspector be unavailable at the time of the actual inspection or test, production is not stopped. Review of verifying documents is included. Equipment in ITP Section 1.0 shall be released if Customer's Inspector fails to respond or fails to appear.
Identical to 'O1', but performed on a sampling of units, operations or tests on that project (not necessarily 100%). Every effort is made to have the inspector present when these operations are conducted. The inspection or test has not necessarily been performed in advance, prior to the observation point. Should the inspector be unavailable at the time of the actual inspection or test, production is not stopped. Notification requirements are the same as for '01'. Equipment in ITP Section 1.0 shall be released if Customer's Inspector fails to respond or fails to appear.
Indicates Solar inspection or test on 100% of units, operations or tests on that project.
Indicates an in-process document review is required on 100% of units on that project. The in-process review is to take place at the operation or test location unless the document is included in the databook. A copy of the verifying document is not supplied unless also identified with an 'X' in Solar's column 'A'.
In Solar's column 'A' indicates a copy of the document will be supplied in the Project Quality Assurance Data Book. The Databook contains a reference copy of the ITP. Individual documents are identified with the ITP Item number and are found in the corresponding sections. The documents consist of supplier information and Solar information.
Indicates a sample monitoring of Solar's system is required. This monitoring will be on random equipment, and may not be project specific.
The ITP is developed from the Solar Application Check Sheet (ACS) and information provided by the Business Manager and the Project Applications Engineer. Revisions are based on Customer input provided during project execution.
Inspection Points: Column A is
Special inspections, documents or tests above and beyond our standard are shown.
Column B is Column C isASTRA TRANS
Transierra
Equipment includes 2 Each, Taurus CS Package(s). Powered by Taurus 70-10302 turbine(s).
SIERRA 1 & 2 PD # 72871
Solar Inspector / Engineer
Driving a C402 Compressor.
'A2' Indicates Solar inspection or test on only a sampling of units, operations or tests on that project.
'R2' Indicates an in-process document review is required on only a sample of units on that project. The in-process review is to take place at the operation or test location unless the document is included in the databook. A copy of the verifying document is not supplied unless also identified with an 'X' in Solar's column 'A'.
All documents are to be submitted to: or Emailed to: [email protected] Document CoordinatorSolar Turbines Incorporated (KM20)4200 Ruffin Rd.San Diego CA 92123-1836, USA
FIVE (5) Working Days Notification Required For All Customer INSPECTION/OBSERVATION Items.
Prepared for
This ITP was Prepared By: Larry Proctor, Quality Engineer
Column D isOther
Certification:
NECRevision Number: 4 Dated: May 01, 2003
Caterpillar Confidential: Yellow
Inspection and Test Plan PAGESolar TurbinesA Caterpillar Company
2
Source Inspection Instructions for ITP Section 1.0 ONLY Solar Turbines Supplier Quality Engineer- (Ray Greeves) 1. Create Project File. 2. Send (email/fax/mail) copies of latest revisions of ITP, Unpriced Purchase Order,
Drawings, etc. to assigned contracted Inspector. 3. Send (email/fax/mail) copies of latest revisions of ITP, Unpriced Purchase Order to
Drawings to Inspection Agency. 4. Follow up on Supplier to Inspector Second Notifications. 5. Reassign inspection to different Solar Inspector and/or Inspection Agency 24 hours after
Supplier notification to Solar that Inspector did not respond to Second Notice (see Supplier item number 6).
6. Request Customer Inspection Waiver from Project Manager, if Customer Inspector did not respond to Supplier within 48 hours after Supplier issued Second Notice (see Supplier Item 6).
Suppliers Noted in Section 1.0 of this ITP- 1. Per ITP requirement, send (email/fax) Inspection Notification to Solar Inspector and/or
Solar Customer Inspector. 2. Send (email/fax) copy(s)of Inspection Notification(s) to Solar Supplier Quality Engineer
(Ray Greeves). 3. Send (e-mail/fax) copy of Notification to Solar Purchasing Representative. 4. Send (e-mail/fax) Second Notification to Solar Inspector and/or Solar Customer
Inspector, if required; copy Solar Supplier Quality Engineer. 5. At Inspectors arrival, confirm Inspector has latest Purchase Order and Drawing revision,
and provide Inspector with current copy(s), if required. 6. If Inspector and/or Solars Customers Inspector has not responded to a Second Notice
Notification within 48 hours, notify the Solar Turbines Supplier Quality Engineer. Solars Contracted Source Inspector (Column A of Section 1.0)- 1. Upon receipt of Solar ITP, Purchase Order and Drawing, notify Supplier of your
inspection assignment. 2. Upon receiving Inspection Notification from Supplier, send (e-mail/fax) inspection
confirmation to the Supplier. 3. Send (e-mail/fax) copy of inspection confirmation to Solar Supplier Quality Engineer and
Inspection Agency. 4. Respond to Supplier Second Notification within 48 hours (see Supplier Item 6 and Solar
Turbines Supplier Quality Engineer Item 5). 5. Send Inspection Reports to Solar Quality Engineer. Note: For Solar Source Inspections, only a Quality Engineer, Quality Manager, or Project Manager can waive Source Inspection requirements. For Customer inspections, only the Customer can waive Source Inspection Requirements. All waivers must be in writing (email or faxed). Please address ITP Section 1.0 Source Inspection issues to Ray Greeves 858/292-3146. Email address: [email protected]
Caterpillar Confidential: Yellow
SOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
2
0.0
0.3
ITP approval by Solar Project Management.
DATE:
COLUMN B CONTACT INFORMATION:
ITEM DESCRIPTION
PROJECT QE CONTACT:
Contact:
Phone #:
Fax #:
Email:
0.2
0.4 COLUMN C CONTACT INFORMATION:
Company:
Contact:
Phone #:
Fax #:
Cell/Pgr #:
Company:
Contact:
Phone #:
Fax #:
Cell/Pgr #:
Company:
Contact:
Phone #:
Fax #:
Cell/Pgr #:
ITEM DESCRIPTIONITEM
Company:
Contact:
Phone #:
Fax #:
Email:
Company:
Contact:
Phone #:
Fax #:
Cell/Pgr #:
Company:
Contact:
Phone #:
Fax #:
Cell/Pgr #:
ITEM
PAGE 3
SOLAR SOURCE INSPECTION CONTACT:
Contact: Ray Greeves
Phone: 858-292-3146 Fax: 858-694-6733
Cristian Alonso - Dto. de COMPRAS - Purchasing Department A-Evangelista S.A. - Phone: 011-54-11-4239-3852 Fax: 011-54-11-4239-3702 [email protected]
Fabian Rivas - Cristian's backup - Phone: 011-54-11-4239 3706 [email protected]
Cell/Pgr #:
Email:
Email:
Email:
Email:
Email:
Jaime Mellina, Project Manager
Larry Proctor
Bob Sutherland, Project Engineer
0.1
4 May 01, 2003
Julio Craysman
5411-4239-3700
5411-4239-3701
Astra Evangelista
Cesar Coronel
5411-4239-3760
5411-4239-3701
Astra Evangelista
5411-15-5400-3760
See Additional Contact names below
Jorge Luiz Kauer
591-335-86-350
591-335-86-183
Transierra
(858) 694-6851
(858) 715-7770
Larry Proctor
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
42
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
01.00 PACKAGING OPERATIONS PURCHASED PARTS Purchase Order
PSO PQ.S06.06
Engineering Drawings
R1POMQ Computer Screen
01.01 RECEIVING INSPECTION - Inspect material per Solar practices
SUPPLIERS BELOW TO NOTE THE FOLLOWING:
ALL DOCUMENTATION MARKED WITH "X" IN COLUMN A SHALL BE PROVIDED TO SOLAR WITHIN 14 CALENDAR DAYS OF COMPLETION OF MANUFACTURING, AND/OR FINAL SOLAR OR CUSTOMER INSPECTION. DOCUMENTATION SHALL INCLUDE SOLAR PO#, SOLAR PART NUMBER AND SOLAR PROJECT NAME/NUMBER.
ELECTRONIC TRANSMITTAL OF DOCUMENTS IS PREFERRED. SEND TO:[email protected]
DOCUMENTS SHALL BE MAILED TO:QUALITY DOCUMENTS COORDINATORSOLAR TURBINES, INC. (KM20)4200 RUFFIN RD.SAN DIEGO, CA 92123
NOTE: RECEIVING INSPECTION VERIFYING DOCUMENTS ARE NOT APPLICABLE TO DROP SHIPPED ITEMS.
Purchase Order
PSO PQ.S10.01PSO PQ.S10.02PSO PQ.S10.03PSO PQ.S10.05PSO PQ.S13.08
Engineering Drawings
R2On-Line Material Review and Corrective Action System
01.03 AIR INLET SILENCER(Drop Ship Item)
Purchase Order
ES 1692
Engineering Drawings
01.04 AIR INLET FILTER(Drop Ship Item)
Purchase Order
ES 1725
Engineering Drawings
01.05 EXHAUST SILENCER(Drop Ship Item)
Purchase Order
ES 1632
Engineering Drawings
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
52
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
01.06 LUBE OIL COOLER(Drop Ship Item)
Must Be ASME Code Stamped
SOURCE INSPECT PER SOLAR SUPPLIER QUALITY ASSURANCE.
Purchase Order
Engineering Drawings
ASME VIII
R1 X1. ASME Data Report
A1 X2. Pressure Test and Flush Certificate
01.07 LUBE OIL FILTERS Purchase Order
Engineering Drawings
ASME VIII
R1 XASME Data Report( if applicable )
01.08 GAS FUEL FILTERS Purchase Order
Engineering Drawings
ASME VIII
R1 XASME Data Report
01.09 ENGINE HANDLING KIT Purchase Order
Engineering Drawings
R1 XCertificate
01.10 PACKAGE LIFTING KIT Purchase Order
Engineering Drawings
R1 XCertificate
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
62
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
02.00 SKID BASE PLATE (TURBINE PACKAGE) (TurboFab, Houston)
TurboFab Contact: Chuck BelsonTel: 281-860-6702
02.01 Review welding procedures TF 1009
AWS D1.1
M2 XPQR, WPS
02.02 Review welder qualifications TF 1009
AWS D1.1
M2 XWQR
02.03 Weld skid/lifting bollardsDimensional check and visual inspection to AWS D1.1 Section 6.
(Built to engineering specifications using ASTM A36 material)
TF 1009
Fabrication Drawings
AWS D1.1
A1 XTraveler
02.04 Lube Oil Tank - Pneumatic leak test TF 2005 XC of C
A1Traveler
02.05 Surface preparation and paint PSO QAS 701PSO QAS 710
ES 9-58
XC of C
A1TurboFab Form 3016
02.06 Lube Oil Tank - Internally coated with Brayco 785
PSO QAS 702 XC of C
A1Traveler
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
72
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
03.00 MANIFOLDS
Solar Contact: Ron LangTel: 858-694-6121
03.01 Review welding procedures ASME IX M2 XWPS, PQR
03.02 Review welder qualification ASME IX M2 XWQR
03.03 Weld manifolds Dimensional check and visual inspection
WPS
PSO QAS 709
Engineering Drawings
XC of C
A1Traveler
03.04 NDE Manifolds (Radiography - RT)(Standard is 5% per welder on circumferential butt welds only. NOTE: Not per project)
ASME B31.3 XC of C
03.05 Hydrostatic Test Manifolds -(1.5 times design pressure for 10 minutes minimum)
* Hydro Test Log maintained by part number, not project specific.
PSO QAS 708
Engineering Drawings
ASME B31.3
A1 XHydro Test Log
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
82
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
04.00 CONTROLS
Solar Contact: Ron LangTel: 858-694-6121
04.01 Visual inspection of control wiring Project Electrical Drawings
A1 XIncluded in the Certified Test Data in Section 08.01
04.02 Hardware verification of the project control system. This verification is performed on each unit of a multi-unit Sales Order.
Project Electrical Drawings
A1 X O1 O1Included in the Certified Test Data in Section 08.01
04.03 Project software verification using software simulators to represent the operation of the equipment controlled by the software. This verification is performed only once on a multi-unit Sales Order.
Project Electrical Drawings
A1 X O1 O1Included in the Certified Test Data in Section 08.01
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
92
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
05.00 GAS TURBINE ENGINE
Solar Contact: Ron LangTel: 858-694-6121
05.01 SUPPLIER QUALITY ENGINEERING - Review and approval of purchase requisitions for first-time buy or revised parts.
Purchase Order
PSO PQ.S6.06
Engineering Drawings
POMQ Computer Screen
05.02 RECEIVING INSPECTION - Inspect material per Solar practices.
Purchase Order
PSO PQ.S10.01PSO PQ.S10.02PSO PQ.S10.03PSO PQ.S10.05PSO PQ.S13.08
Engineering Drawings
A2Check List, Check Chart, or ENPS Computer Screen
R2Inspection Accumulation Record Form
05.03.A Compressor Case Leak Test
Cases are leak tested at the place of manufacture. Cases are not assigned to a specific project or a specific engine at the time of leak testing.
Engineering Drawing
A1 XLeak Test Chart
05.03.B Combustor Case Leak Test
Cases are leak tested at the place of manufacture. Cases are not assigned to a specific project or a specific engine at the time of leak testing.
Engineering Drawing
A1 XLeak Test Chart
05.03.C Engine Fuel Manifold Leak Test
Manifolds are leak tested at the place of manufacture. Manifolds are not assigned to a specific project or a specific engine at the time of leak testing.
NOTE: Fuel manifolds are manufactured and tested at TurboTec, Tijuana, Mexico.
ES 9-78
Engineering Drawing
A1 XLeak Test Chart
05.04 ROTOR ASSEMBLY - COMPRESSOR AND TURBINENOTE: Customer identification is assigned at this point.
TMP QP 602.0
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
102
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
05.04.A Gas Producer Compressor Rotor(Mechanical and Electrical runout)
Engineering Drawing
A1 XShop Floor Information System (Inspection Data)
05.04.B Gas Producer Turbine Rotor(Mechanical and Electrical runout)
Engineering Drawing
A1 XShop Floor Information System (Inspection Data)
05.04.C Power Turbine Rotor(Mechanical and Electrical runout)
Engineering Drawing
A1 XShop Floor Information System (Inspection Data)
05.04.D Balance Gas Producer Compressor Rotor Engineering Drawing
TMP QAS 712
A1 XShop Floor Information System (Inspection Data)
05.04.E Balance Gas Producer Turbine Rotor Engineering Drawing
TMP QAS 712
A1 XShop Floor Information System (Inspection Data)
05.04.F Balance Power Turbine Rotor Engineering Drawing
TMP QAS 712
A1 XShop Floor Information System (Inspection Data)
05.05 ENGINE ASSEMBLY TMP QP 602.0 A1Shop Floor Information System (Inspection Data)
05.07 ENGINE PERFORMANCE TEST(Utilizing the Facility Test Stand and Dynamometer to load engine)
*Included In Certified Test Data In Section 8.01
PSOP P10.11PSOP P10.22PSOP P11.01
ES 2235
A1 X O1 O1Acceptance Test Stamp Sheet*
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
112
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
06.00 GAS COMPRESSOR ASSEMBLY
Solar Contact: Ron LangTel: 858-694-6121
06.01 SUPPLIER QUALITY ENGINEERING - Review and approval of purchase requisitions for first-time buy or revised parts.
Purchase Order
PSO PQ.S6.06
POMQ Computer Screen
Engineering Drawings
POMQ Computer Screen
06.02 RECEIVING INSPECTION - Inspect material per Solar practices.
Purchase Order
POMQ Computer Screen
Engineering Drawings or ENPS Computer Screen
A2Check List, Check Chart, or POMQ Computer Screen
06.03 Gas Compressor Dry Gas Seals Purchase Order
POMQ Computer Screen
Engineering Drawings
A2POMQ Computer Screen
06.05 Impeller Overspeed Spin Test and Dimensional Check One Minute at 115% speed.
Engineering Drawings
A1 XShop Floor Information Systemor Process Log (Inspection Data)
06.06 Center Body Hydro Test(center body hydro test at 1.5 times design pressure for 30 minutes minimum)
NOTES:Hydrotests performed for extended time periods will apply to the centerbody and endcaps only. Additional tests on services ports will be the standard 30 minute duration.
ES 9-78
Engineering Drawings
A1 XShop Floor Information System (Inspection Data)
06.07 End Caps Hydro Test (end caps hydro test at 1.5 times design pressure for 30 minutes minimum)
ES 9-78
Engineering Drawing
A1 XShop Floor Information System (Inspection Data)
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
122
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
06.08 Mechanical and electrical runout Engineering Drawings
A1 XInspection Data
06.08.A Rotor balance Engineering Drawings
A1 XBalance Computer Printout
06.09 Compressor Assembly TMP QP 602.0 A1Shop Floor Information System or Traveler (Assy / Inspection Data)
06.10 GAS COMPRESSOR AIR TEST (On facility test stand including 100% mechanical run, air test and nitrogen static leak test)
* Included in the Certified Test Data in Section 08.01
PSOP P10.22PSOP P11.01
ES 1597
A1 X O1 O1Air Test*
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
132
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
07.00 PACKAGE ASSEMBLY
Solar Contact: Ron LangTel: 858-694-6121
PSOP P10.11 .
07.01 Base qualification of customer fixed interfacepoints prior to build-up of package.
Project Mechanical Installation Drawings
A1QC Folder Check List
07.02 Mechanical Assembly PSO QAS 800PSO QAS 803PSO QAS 804PSO QAS 805PSO QAS 806PSO QAS 812PSO QAS 814PSO QAS 815PSO QAS 816PSO QAS 817PSO QAS 821PSO QAS 826PSO QAS 829PSO QAS 834PSO QAS 835
A2QC Folder Check List
07.03 Electrical Assembly PSO QAS 503 PSO QAS 504PSO QAS 506DE.380.F01
A2QC Folder Check List
07.04 Review alignments PSO QAS 806
Project Mechanical Installation Drawings
A1QC Folder Alignment Sheet
07.05 Dimensional check of customer connections and interface points during build-up of package. (Including customer connection plates and flanges)
Project Mechanical Installation Drawings
A1Dimensional Verification Sheet
A1QC Folder Check List
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
142
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
08.00 PACKAGE TEST
Solar Contact: Ron LangTel: 858-694-6121
08.01 Package/Console Acceptance Test PSOP P10.11PSOP P10.22PSOP P11.01
ES 2153 (T70)
A1 O1 O1Acceptance Test Stamp Sheet
A1 XCertified Test Data
08.02 Enclosure assembly static test including simulated test of fire and combustible gas system (if present).
*Included in the Certified Test Data in Section 08.01
See PSO QAS list in section 07.02 and 07.03.
A1 X O1 O1Acceptance Test Stamp Sheet*
08.03 No Load Mechanical String Test (one unit only)
4 Hour Gas Fuel Run1 Package Only
*Included in the Certified Test Data in Section 08.01
ES 1782 A1 X O1 O1Acceptance Test Stamp Sheet*
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
152
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
09.00 PACKAGE FINAL INSPECTION
Solar Contact: Ron LangTel: 858-694-6121
PSOP P10.11 .
09.01 Mechanical Final Inspection See PSO QAS list in section 07.02.
Project Mechanical Drawings
A1 O1 O1QC Folder Check List
09.02 Electrical Final Inspection See PSO QAS list in section 07.03.
Project Electrical Drawings
A1 O1 O1QC Folder Check List
09.03 Paint Final Inspection PSO QAS 701 A1 O1 O1QC Folder Checklist
09.04 Loose Ship PSOP P10.11
PSO QAS 818
A1 O1 O1Pack Slip
09.05 Pre-shipment Inspection O1 O1
09.06 Package preservation and preparation for shipment
Shipping/Traffic Functional Practices
PSOP P15.10
ES 9-249
ES 9-248
A1 O1 O1OK to Ship QC Tag
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
PAGESOLAR TURBINES INCORPORATED INSPECTION AND TEST PLAN
CLIENT: PROJECT NAME:
NO. UNITS:PD NO:
ISSUED BY:
PURCHASE ORDER:
REV:
EQUIPMENT
72871
Transierra SIERRA 1 & 2
Taurus CS
Taurus 70-10302
172
TRANSITEM ITEM DESCRIPTION CONTROLLING DOCUMENT
VERIFYING RECORD A B C
Solar ASTRA
Larry Proctor 4 May 01, 2003
REVISION RECORD SHEET
REV DATE BY REMARKS
0 08/05/02 Larry Proctor Revision 0 is the initial release of the ITP.
1 10/31/02 Larry Proctor Revision 1: Changed PM. Moved 4 hr run from 05.07 to 08.03. Deleted item 06.11. Changed item 09.05 to 09.06 and then added pre-shipment inspection in 09.05. No other changes.
2 02/19/03 Larry Proctor Revision 2: Added customer contact information. Added O1's to columns B and C in sections 5, 6, 8. No other changes.
3 03/11/03 Larry Proctor Revision 3: Changed controlling document from ES2041 to ES2235 in item 05.07. No other changes.
4 05/01/03 Larry Proctor Revision 4: Added customer contact information. No other changes.
A2 SOLAR SAMPLE INSP/TEST M2 MONITOR SYSTEM
R1 100% DOCUMENT REVIEW O1 100% OBSERVE INSP/TEST
R2 SAMPLE DOCUMENT REVIEW
SOLAR SUBMIT VERIFYING DOCUMENT
A1 SOLAR 100% INSP/TEST
O2 SAMPLE OBSERVE INSP/TEST
X
Caterpillar Confidential: Yellow
Quality Assurance Data Book, SIERRA, PD # 72871, Volume 1ForwardTable of ContentsSection 1: Purchased Parts01.06 Lube Oil CoolerLO Cooler.pdf023115ABTransmittalTable of ContentsCertified DrawingParts ListSpec. SheetU-1A Data Reports023115.1A023115.1B
NameplateHydrostatic Test Certifications1 of 22 of 2
Material Traceability RecordsPipePlateTubes
X-Ray Test Reports1 of 82 of 83 of 84 of 85 of 86 of 87 of 88 of 8
Dye Penetrant Test Report1 of 42 of 43 of 44 of 4
Flushing Record1 of 62 of 63 of 64 of 65 of 66 of 6
Final Acceptance CertificateForm 1016Electrical Device ListFinal-In Process1 of 22 of 2
Additional Final-In Process1 of 22 of 2
Paint-In Process1 of 22 of 2
Fan Data1 of 22 of 2
Motor Data1 of 32 of 33 of 3
1. ASME Data Report2. Pressure Test and Flush Certificate
01.07.A Lube Oil FiltersASME Data Report
01.08 Gas Fuel Filter01.09 Engine Handling Kit01.10 Package Lift Kit
Section 2: Skid Base Plate 02.01 Review Welding Procedures02.02 Review Welder Qualifications02.03 Weld Skid/ Lifting Bollards02.04 Lube Oil Tank Pneumatic Leak Test02.05 Skid surface preparation and paint02.06 Lube Oil Tank - Internal Coating
Section 3: Manifolds 03.01 Review Welding Procedures 03.02 Review Welder Qualifications03.03 Weld Manifolds Dimensional Check03.04 NDE Manifolds03.05 Hydostatic Test Log
Section 4: Control System04.01 Visual Inspection of Control Console 04.02 Hardware Verification of Control System04.03 Software Verification of Control System
Section 5: Turbine Engine05 03.A Compressor Case Leak Test05.03.B Combustor Case Leak Test05.03.C Hydrostatic Test Chart05.04.A Gas Producer Compressor Rotor Runout05.04.B Gas Producer Turbine Rotor Runout05.04.C Power Turbine Rotor Runout05.04.D Balance Gas Producer Compressor Rotor05.04.E Balance Gas Producer Turbine Rotor05.04.F Balance Power Turbine Rotor05.07 Engine Performance Test
Section 6: Gas Compressors06.05 Impeller Overspeed Spin Test 06.06 Center Body Hydro Test06.07 End Caps Hydro Test06.08 Mechanical and Electrical Runout06.08.A Rotor Balance 06.10 Gas Compressor Air Test
Section 7: Package Assembly07.00 No Documents Required
Section 8: Package Test08.01 Certified Test ReportCertified Test DataItem 1: Turbine Acceptance TestItem 2: Turbine PerformanceItem 3: Turbine Operating ParametersItem 4: Turbine Vibration DataItem 5: Dry EmissionsItem 6: Package Acceptance TestItem 7: Gas Compressor Acceptance TestItem 8: Gas Compressor DataItem 9: String Test Data
08.02 Enclosure Assembly Static Test08.03 No Load Mechanical String Test
Section 9: Package Final Inspection09.00 No Documents Required
Section 10: Documentation / Certification10.01 Package Certificate of Compliance10.01 ITP (Reference Copy)