59
1. 2. 3. 4. 5. 6. 7. ADMINISTRATIVE DOCUMENTS (Yellow Paper) E P . C ES-201-1/' xam reparation hecklist . / Exam Outline Quality Checklist. J:>:u=: ES-201-2 Exam Security Agreement(s) ES-201-3./ Administrative Topics Outline (Final) ES-301-1 / Room Systems & Facility Walk-through Test Outline ./ (Final) ES-301-2 / Operating Test Quality Check Sheet ES-301-3 J Simulator Scenario Quality Check Sheet ES-301-4 8. Transient and Event Checklist . 9. Competencies Checklist . 10. Written Exam Quality Check Sheet . I ES-301-5 / ES-301-6 . / ES-401-6 11. Written Exam Review Worksheet ES-401-9 12. Written Exam Grading Quality Checklist ES-403-1 ./ 13. Post-Exam Check Sheet ES-501-1/' 14. Facility Submittal Letter.s ( 0 SE{}uoyAH []

8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

1.

2.

3.

4.

5.

6.

7.

ADMINISTRATIVE DOCUMENTS(Yellow Paper)

E P . C ES-201-1/'xam reparation hecklist .

/Exam Outline Quality Checklist. J:>:u=: ES-201-2

Exam Security Agreement(s) ES-201-3./

Administrative Topics Outline (Final) ES-301-1 /

C~ntrol Room Systems & Facility Walk-through Test Outline . /(Final) ES-301-2

/Operating Test Quality Check Sheet ES-301-3

JSimulator Scenario Quality Check Sheet ES-301-4

8. Transient and Event Checklist .

9. Competencies Checklist .

10. Written Exam Quality Check Sheet .

IES-301-5

/ES-301-6

. /ES-401-6

11. Written Exam Review Worksheet ES-401-9

12. Written Exam Grading Quality Checklist ES-403-1 ./

13. Post-Exam Check Sheet ES-501-1/'

14. Facility Submittal Letter.s ( 0

SE{}uoyAHoZO~8-JL)/

[] ~.

Page 2: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES·201 Examination Preparation Checklist Form ES·201·1

Facility: <: lVlAO;! rW Date of Examination: -:r4-N. &'OClC~

Developed by: Written - Facility~NRC 0 II Operating - Facility MNRC 0

Target ChiefDate" Task Description (Reference) Examiner's

Initials

-180 1. Examination administration date confirmed (C.1.a; C.2.a and b) IJifS-120 2. NRC examiners and facility contact assigned (C.1.d; C.2.e) r~-120 3. Facility contact briefed on security and other requirements (C.2.c) r0kP-120 4. Corporate notification letter sent (C.2.d) y11f>[-90] [5. Reference material due (C.1.e; C.3.c; Attachment 3)] !Y~{-75} 6. Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3,

ES-301-1, ES-301-2, ES-301-5, ES-O-1's, ES-401-1/2, ES-401-3, and~ES-401-4, as applicable (C.1.e and f; C.3.d)

{-70} {7. Examination outline(s) reviewed by NRC and feedback provided to facility tmslicensee (C.2.h; C.3.e)}

{-45} 8. Proposed examinations (including written, walk-through JPMs, andscenarios, as applicable), supporting documentation (including Forms

m$>ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, and any FormES-201-3 updates), and reference materials due (C.1.e, f, g and h; C.3.d)

-30 9. Preliminary license applications (NRC Form 398's) due (C.1.1; C.2.g;

I~ES-202)

-14 10. Final license applications due and Form ES-201-4 prepared (C.1.1; C.2.i;

/I~ES-202)

-14 11. Examination approved by NRC supervisor for facility licensee review;}~(C.2.h; C.3.f)

-14 12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) 'rn!b-7 13. Writt~n exam~ons and oper~tests approved by NRC supervisor *(C.2.1; C.3.h)

-7 14. Final applications reviewed; 1 or 2 (if >10) applications audited to confirm

flI4IPqualifications / eligibility; and examination approval and waiver letters sent(C.2.i; Attachment 5; ES-202, C.2.e; ES-204) ],w-s;..v--et'::,-,,) :2 G..K!~"""'-l.£v;....J

-7 15. Proctoring/written exam administration guidelines reviewed mrswith facility licensee (C.3.k)

-7 16. Approved scenarios, job performance measures, and questions ~distributed to NRC examiners (C.3.i)

• Target dates are generally based on facility-prepared examinations and are keyed to the examination dateidentified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.[Applies only] {Does not apply} to examinations prepared by the NRC.

ES-201, Page 25 of 28

Page 3: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES·201 Examination Outline Quality Checklist Form ES·201·2

c#b'a

~1ZJrwP

~7ZJIMP-~ 'llJ r#b

Initials

Date of Examination: 1/;)..00?:j'

Task Description

d. Assess whether the justifications for deselected or rejected KIA statements are appropriate.

a. Verify that the outline(s) fit(s) the appropriate model, in accordance with ESA01.

f--.--·-·--------------------------------+--t-'-~+_~__11

b. Assess whether the outline was systematically and randomly prepared in accordance with--2..,,:cOon 0.1 of ES-401 ar:.d whether all KIA cateqories are appropriately sampled.

c. Assess whether the outline over-emphasizes any systems, evolutions, or generic topics.

Item

I----+-·--------------------------------t-::..-j-..:;:--t-~I

1.WRITTEN

c. To the extent possible, assess whether the outline(s) conform(s) with the qualitativeand quantitative criteria specified on Form ES-301-4 and described in Appendix D.

a. Using Form E$-301-5, verify that the proposed scenario sets cover the required numberof normal evolutions, instrument and component failures, technical specifications,and major transients.

f--·-------------'-----------------------;---;f-<--t---ilb. Assess whether there are enough scenario sets (and spares) to test the projected number

and mix of applicants in accordance with the expected crew composition and rotation schedulewithout compromising exam integrity, and ensure that each applicant can be tested usingat least one new or significantly modified scenario, that no scenarios are duplicatedfrom the applicants' audit test(s), and that scenarios will not be repeated on subsequent davs.

2.

IMULAToR

s

Ir----I-·--·-~----------------------------_t_-+_-+--_il

3

WIT

a. Verify that the systems walk-through outline meets the criteria specified on Form ES-301-2:(1) the outlir&(s) contain(s) the required number of control room and in-plant tasks

distributed among the safety functions as specified on the form ./'(2) task repetition from the last two NRC examinations is within the limits specified on the fonrn ......(3) no tasks are duplicated from the applicants' audit test(s)./ 1~."11 J fY\tS(4) the number of flew or modified tasks meets or exceeds the minimums specified on the form ,/ . /!II./ I(5) the number of alternate path, low-power, emergency, and RCA tasks meet the criteria.>

on the form.

-;~tZ.. Iv~

15 '1?J ifVIfJ

i1'~ 1lJ 1~

f0~'iv~

-j-:) 7lJ \\rR>

Assess whether the 10 CFR55,41 143 and 55,45 sampling is appropriate.

Assess whether the exam fits the appropriate job level (RO or SRO).

e. Check the entire exam for balance of coverage.

d. Check for duplication and overlap among exam sections.

b.1-·-·-----------------....:..--:..-..:....:....:....:..-----------j-!:~+"u::.'9-'~-i1

c. Ensure that KIA importance ratings (except for plant-specific priorities) are at least 2.5.

GENERp.,L

b. Verify that the administrative outline meets the criteria specified on Form ES-301-1:(1) the tasks are distributed among the topics as specified on the form ,./(2) at least one task is new or significantly modified ,./(3) no more than one task is repeated from the last two NRC licensing examinations ./'

c. Determine if there are enough different outlines to test the projected number and mix 0/'

,..--.- of applicants and ensure that no items are duplicated on subsequent days.

4. R. Assess whether plant-specific priorities (including PRA and IPE insights) are coveredin the appropriate exam sections.

Note:

Datej 1/7(t/'8I JI7/~

Q2 /0.4bM'-,t'-7{l5'I",

a. Author

b. Facility Reviewer (')

c. NRC Chief Examiner (if)

d. NRC Supervisor IJA.II'Fn..l./~\'''nll.Uf..:,/ ~ •

II-' --Ifll.<::~~.,/Y 'L

# Independent NRC reviewer initial items in Colbmrr"C"; ctlref examiner concurrence required.:j,; >:».:,c,;c 'z... .,f<:'., ... ,' ",.; 11;;',;!:>;[' :);V,':".

E8-201, Page 26 of 28

Page 4: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-201 Examination Outline Quality Checklist

DIll 7Form ES-201-2

(

(

Facility: Date of Examination:

InitialsItem Task Description

b* c#a

1. a. Verify that the outline(s) fills) the appropriate model, in accordance with ES-401. ~ V ~W./

R b. Assess whether the outline was systematically and randomly prepared in accordance with -IS .#J.... '01{SI Section 0.1 of ES-401 and whether all KiA cateqories are appropriately sampled.T Assess whether the outline over-emphasizes any systems, evolutions, or generic topics. --1) .,~

*Tc.

Ed. Assess whether the justifications for deselected or rejected KiA statements are appropriate. ~ I-ra)N NJ6

2. a. Using Form ES-301-5, verify that the proposed scenario sets cover the required number

~ 1Yof normal evolutions, instrument and component failures, technical specifications, M$S and major transients.I

M b. Assess whether there are enough scenario sets (and spares) to test the projected number

U and mix of applicants in accordance with the expected crew composition and rotation schedule

~ ~ r1£L without compromising exam integrity, and ensure that each applicant can be tested using

A at least one new or significantly modified scenario, that no scenarios are duplicated

T from the applicants' audit testis). and that scenarios will notbe repeated on subsequent days.

0 c. To the extent possible, assess whether the outline(s) conform(s) with the qualitative pR and quantitative criteria specified on Form ES-301-4 and described in AppendiX2Ctt -tlcn Irv~- 30 ' u.h .~ w.A ,'U wl-\' .L ioCe\15E'e YIlt!>~ ~ •tdt:S- i-l.IWa.S""Y\Df- s ~\' Lv. u.. {)IIVII~ W(V.[\SI".fL "i-iAS ~,'''IA ~'1'v)k-\t: .3. a. Verify that the systems walk-through outline meets the criteria specified on Form ES-301-2:

(1 ) the outline(s) contain(s) the required number of control room and in-plant tasksW distributed among the safety functions as specified on the form

r«V/ (2) task repetition from the last two NRC examinations is within the limits specified on the form 76 rrT (3) no tasks are duplicated from the applicants' audit testis)

(4) the number of new or modified tasks meets or exceeds the minimums specified on the form

'*(5) the number of altemate path, low-power, emergency, and RCA tasks meet the criteriaon the form.

b. Verify that the administrative outline meets the criteria specified on Form ES-301-1:(1 ) the tasks are distributed among the topics as specified on the form

7!J ~ (ff6(2) at least one task is new or significantly modified(3) no more than one task is repeated from the last two NRC licensinq examinations

c. Determine if there are enough different outlines to test the projected number and mix 15,iJ ~of applicants and ensure that no items are duplicated on subsequent days.

4. a. Assess whether plant-specific priorities (including PRA and IPE insights) are covered 76 ~ tI1tin the appropriate exam sections.G b. Assess whether the 10 CFR 55.41/43 and 55.45 sampling is appropriate. .~ ~ tWPEN c. Ensure that KiA importance ratings (except for plant-specific priorities) are at least 2.5. 76 .<lJ~E

d. Check for duplication and overlap among exam sections. 76 .<tJ~RA e. Check the entire exam for balance of coverage. 76 4r/ \'\XbL

Assess whether the exam fits the appropriate job level (RO or SRO). o» ~v..I 'f\\t5f.

7"1omitS -:s::: Printed Na ...' JO ioltcPJiha. Author O"V'" .:> ~ ~~

b. Facility Reviewer (*) TJJ& I""" "'~ 0 cJA If.." e, /-- Y "' r. trJ/ jV//? (07c. NRC Chief Examiner (#) M.AI\~ A- 'B4-r£5 I ~~ L/ J O<.:t.':is "'/fltlo7d. NRC Supervisor J IIUI'N 1.(1:\\IfT)dlHIi-! / tfb' 1 {I/N!lJ1

( -, r ....Note: # Independent NRC reviewer initial items in Coiwr;n "c"; chief examiner concurrence required.

* ()(C~'h\trl.s CU'€- i1cted d'Y1 L1'Mf\'\eJ."\1- 'S"'~-\-.

ES-201, Page 25 of 27

Page 5: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-201 Examination Security Agreement Form ES-201-3

1. Pre-Examination J /:< elog ike!

I acknowledge that I have acquired specialized knowledge about the NRC licensing examinations scheduled for the week(s) of ,7/?I/o (f as of thedate of my signature. I agree that I will not knowingly divulge any information about these examinations to any persons who have not been authorizedby the NRC chief examiner. I understand that I am not to instruct, evaluate, or provide performance feedback to those applicants scheduled to beadministered these licensing examinations from this date until completion of examination administration, except as specifically noted below andauthorized by the NRC (e.g., acting as a simulator booth operator or communicator is acceptable if the individual does not select the training content orprovide direct or indirect feedback). Furthermore, I am aware of the physical security measures and requirements (as documented in the facilitylicensee's procedures) and understand that violation of the conditions of this agreement may result in cancellation of the examinations and/or anenforcement action against me or the facility licensee. I will immediately report to facility management or the NRC chief examiner any indications orsuggestions that examination security may have been compromised.

2. Post-Examination

To the best of my kno~ledg2~1 id not divulge to any unauthorized persons any information concerning the NRC licensing examinations administeredduring the week(s) of !h9 - i'~ O:9From the date that I entered into this security agreement until the completion of examination administration, I did notinstruct, evaluate, or provide performance feedback to those applicants who were administered these licensing examinations, except as specificallynoted below and authorized by the NRC. .

JOB TITLE / RESPONSIBILITY

:szl14EDP~Tlo~

ES-201, Page 26 of 27

Page 6: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-201 Examination Security Agreement Form ES-201-3

1. Pre-Examination / / II '2.~{ o?f t"~v

I acknowledge that I have acquired specialized knowledge about the NRC licensing examinations scheduled for the week(s) of ;2./ 'lJ (0 'if as of thedate of my signature. I agree that I will not knowingly divulge any information about these examinations to any persons who have not been authorizedby the NRC chief examiner. I understand that I am not to instruct, evaluate, or provide performance feedback to those applicants scheduled to beadministered these licensing examinations from this date until completion of examination administration, except as specifically noted below andauthorized by the NRC (e.g., acting as a simulator booth operator or communicator is acceptable if the individual does not select the training content orprovide direct or indirect feedback). Furthermore, I am aware of the physical security measures and requirements (as documented in the facilitylicensee's procedures) and understand that violation of the conditions of this agreement may result in cancellation of the examinations and/or anenforcement action against me or the facility licensee. I will immediately report to facility management or the NRC chief examiner any indications orsuggestions that examination security may have been compromised.

2. Post-Examination

To the best of my knowled~e I did not divulge to any unauthorized persons any information concerning the NRC licensing examinations administeredduring the week(s) of ~~ - Y'f'OG' From the date that I entered into this security agreement until the completion of examination administration, I did notinstruct, evaluate, or provide performance feedback to those applicants who were administered these licensing examinations, except as specificallynoted below and authorized by the NRC.

JOB TITLE / RESPONSIBILITY

kDIfo

~ogo/20

ES-201, Page 26 of 27

DATE

Page 7: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

SC-&»fY#/ l:-£JOf"ES~201

Examination See!~tl-A-8-ree-m-l!-n-t-F-crm-------------f-o-nn""(~s-2ft1·3Pre-Exarnin:atfon

)!;z.r; /t;? ~wVI ackrlo.edge that Ehave acquirHdspecialized knowledge about the-tIRe Ijc;ensing examillations t.cheduled for the week(s) of ?j~ 10 "l as of thedate o.fmy signaturtr. I agree that I will no'! knowin{ly divulge any infurmation about these examinaoons to aly per-mns who haw not been authnrizedby the NRC chief examinet'". I urtde:rsland t'lat I ern £101to instruc;l. evaluate, or provide performeoce feedback 10thoseapj;li[;Clnls scheduled to beadmi l'iisteled these licensing examinatlO1l$. from this dat.eunlil c:omplel:ion of examination admi nistniliorl, except as specifica lit noted oolow andaultlorized byttle NRC (e.g., acting as a simt.Jator boot! h'Opef~or or eemmurlicatOl' is aooeptableif 111 iii indi\lidLSlI does not select the fJainingCOnient orllfovide direct a'" indirec1 feedback). Furthemllre. I aIrI aware of !tie physical security measures aJ1d rE!q\lirernel11s (as documented fl the facjlil~

lit:erJsee's procecb'es) and understand thai vio!a1ion of the conditions of thks agreem enJ. mayrestflt in carnl!Dalion (If the elo:aminatioos and/or anenfDlcement action agains1 me or lhefaGilitv licensee. Iw. immEdialelyreport to facility managemeritOf tire NRC chief examio@r 8rIY indications Dr

suggesfons that eKaminal~on o.ewrity may ha\19 been compromised.

1.

2_ Post-E nmination

To tf1ebest of my lfficMtIedge. td id not divLIIgeto any un<llJthorlzed persons any irforrnatiQn ooncemiog the NRC Ii-cerlsing exarnillaticns admTiistereddlJri1g the week(s) of . From the dale that I entered into this sewlil1' agreemeflt unlil ttle compleliort of e:xami1ation admi1istratioo. rtid ootinstrudl. evaluale, or provide pelfurmance feedback m thase applicants who were administered these licensi"lg elC3minations, ext:ept as spef;ificallynoted beJow:and authorized by the NRC .

ES-201, Page 26 of 27

----------------------------

JOB rrns I RESPONSIBILITYfS. €\J !ef'JPR

PRlmED!'WAE~ SIGNAT~ DJ}T~. ~."T { VA E TE1:~s8'H M.$G..*Jb( .f-~-Fli../L-:o,..t=,-,_"L-J-=;;:..__~__Yf_·_~iLE:.!LQ.7~~Z· Jl oK2. ---l.[~>--·----- ~_" _3. . --'- _4. . _5. . _6. _

7. _

a.9. --:.~ _

10., _11., . _

12., ~__13,, _

14.

15_,-=' -----------------NOTES:

C0-

Page 8: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-301 Administrative Topics Outline Form ES-301-1

(

(

Facility: Sequoyah 1 & 2

Ro9

Date of Examination: 1/2008

Examination Level (circle one): Operating Test Number: NRC

Administrative Topic Type Code* Describe activity to be performed(see Note)

Conduct of Operations 2.1.1 Knowledge of conduct of operations requirements. (CFR:

N,R 41.10/45.13) 3.7/3.8

Determine license status Active / Inactive

Conduct of Operations 2.1.33 Ability to recognize indications for system operatingparameters which are entry-level conditions for technical

D,S specifications. (CFR: 43.2 /43.3/45.3) 3.4 / 4.0

Perform Shift Log SI-2 SG Level Instrumentation (JPM176)

2.2.18 Knowledge of the process for managing maintenance

Equipment Control activities during shutdown operations.

N,R (CFR: 43.5/45.13) 3.6

Containment Closure Time

Radiation Control 2.3.10 Ability to perform procedures to reduce excessive levels ofradiation and guard against personnel exposure. (CFR:

D,R 43.4 / 45.10) 2.9/3.3

Survey Map (JPM 166)

Emergency Plan 2.4.41 Knowledge of the emergency action level thresholds andclassifications.(CFR: 43.5/45.11) 4.1

D,S

Classify the REP Degraded Core with Possible Loss ofCoolable Geometry and Likely Cntmt Failure (JPM 109)

NOTE: All items (5 total are required for SROs. RO applicants require only 4 items unless they are retakingonly the administrative topics, when 5 are required.

*Type Codes & Criteria: (C)ontrol room

Class(R)oom

(D)irect from bank (:S: 3 for ROs; :s: for SROs & RO retakes)

(N)ew or (M)odified from bank (> 1)

(P)revious 2 exams (:S: 1; randomly selected)

(S)imulator

NUREG-1021 Revision 9

Page 9: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-301 Administrative Topics Outline

SRO Admin JPM Summary

Form ES-301-1

(

A1a The applicant will evaluate the status of licensed operators work history to determine if license is active orinactive.

A1b The applicant will be required to recognize a required Technical Specification entry while completing and aportion of the daily shift surveillance instruction.

A2 The applicant will evaluate a request to open a containment penetration during a refuel outage and determinethe requirements.

A3 The applicant will use a survey map to determine anti-contamination clothing requirements, stay time, andradiation levels in area.

A4 The applicant will evaluate conditions for entry into the E-Plan, determine the proper classification, protectionaction recommendation, and make required notifications.

NUREG-1021 Revision 9

Page 10: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2

(

Facility: Sequoyah 1 & 2 Date of Examination: 1/2008-Exam Level (circle one): R~SRO~I SRO (U) Operating Test No.: NRC

Control Room Systems@ (8 for RO; 7 for SRO-I; 2 or 3 for SRO-U, including 1 ESF)

System I JPM Title Type Code* SafetyFunction

a. W/E14 High Containment Pressure (EA-1.1 ) 3.7 I 3.7D,A,S 5

Respond to High Containment Pressure (JPM 057AP1)

b. 003 Reactor Coolant Pump System (A2.01 ) 3.5 I 3.9N,L,S 4P

Respond to a #1 RCP Seal Failure

c. 001 Control Rod Drive System (A3.05) 3.5 I 3.5M,A,L,S 1

Shutdown Bank Withdrawal

d. 004 Chemical and Volume Control System (A4.06) 3.6 13.1N,L,S 2

Fill and Vent Excess Letdown

e. 038 Steam Generator Tube Rupture (EA1.32 ) 4.6 14.7D,A,S 3

SG tube rupture with MSIV fails to Close (JPM 075AP)

f. 015 Nuclear Instrumentation System (A1.01) 3.5 I 3.8D,A,S 7

Calibrate Power Range Nuclear Instrumentation (JPM 22-AP2)

g. 064 Emergency Diesel Generator (ED/G) System (A4.06) 3.9 I 3.9M,D,S 6

Shutdown the Diesel Generator (1A-A and 1B-B) (JPM 046-1)

h.

In-Plant Systems@ (3 for RO; 3 for SRO-I; 3 or 2 for SRO-U)

i. 061 Auxiliary I Emergency Feedwater System (A2.04) 3.4 I 3.8D,A,E,R 4S

Operate the TO AFW Pump Locally (JPM 74-2AP)

j. 004 Chemical and Volume Control System (A2.25) 3.8 14.3D,R 1

Uncontrolled Dilution Flow Path Isolation (O-SI-OPS 063-214.0)) (JPM 40-2)

k. 062 AC Electrical Distribution (A2.10) 3.0 13.3D,A 6

Transfer 480v SO Board 2A1-A from Normal to Alternate (JPM 061AP2)

@ All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions;all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlapthose tested in the control room.

NUREG-1021 Revision 9

Page 11: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2

\,

~

* Type Codes Criteria for RO / SRQl-1 j SRO-U" --

(A)lternate path 4-6/4-0'/2-3 iJJ

(C)ontrol roomff!:<;47(D)irect from bank '5,9 /

(E)mergency or abnormal in-plant 1 / 1"1:?: 1 \(L)ow-Power / Shutdown <:: 1 / 11:'?:1 .:>(N)ew or (M)odified from bank including 1(A) 2/'?2"1'2:1-1(P)revious 2 exams 3/ 3/ 2 (randomly selected) 0(R)CA 1 / 1/<:: 1 .......-(S)imulator

JPM Summary

JPMA

JPM B

JPM C

JPM D

JPM E

('- JPM F

JPM G

JPM I

RHR spray will be established in accordance with FR-Z.1, High Containment Pressure. This is a BankAlternate Path JPM.

An RCP seal failure will be diagnosed and the Abnormal Operating Instruction used to remove the pumpfrom service. This is a new low power/shutdown JPM

A failure of the step counter will occur during the withdrawal of Shutdown Rods requiring a reactor trip.This is a new alternate path low power/shutdown JPM.

Excess letdown system will be filled and vented from the control room using the system operatinginstruction. This is a new low power/shutdown JPM.

A Main Steam Isolation valve will fail to close during the isolation of steam side of a ruptured steamgenerator will be isolated.. This is a Bank Alternate Path JPM.

Power Range nuclear instruments will be adjusted in accordance with the surveillance instruction O-SI-OPS­092-078.0. This is a Bank Alternate Path JPM.

Unit 1 Diesel Generators will be shutdown per EA-82-1. This is a Bank modified JPM.

Plant JPM -The trip and throttle valve will not open electrically while TDAFW pump is being placed inservice locally. This is an Alternate path Bank JPM using emergency abnormal procedure performed insidethe RCA.

JPM J Dilution flow path will be isolated using O-SI-OPS 062-214.0. This is a Bank JPM performed inside theRCA using an Appendix contains in a surveillance instruction.

JPM K Plant JPM - A breaker will fail to operate while a transfer of a 480v Shutdown Board is being attempted.This is a Bank Alternate Path JPM.

NUREG-1021 Revision 9

Page 12: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2

(

Facility: Sequoyah 1 & 2 Date of Examination: 1/2008-Exam Level (circle one): RO I SRO(I)(:;RO (uij Operating Test No.: NRC

Control Room Systems@ (8 for RO; 7 for SRO-I; 2 or 3 for SRO-U, including 1 ESF)

System I JPM TitleType Code* Safety

Function

a. W/E14 High Containment Pressure (EA-1.1 ) 3.7 I 3.7D,A,S 5

Respond to High Containment Pressure (JPM 057AP1)

b. 003 Reactor Coolant Pump System (A2.01) 3.5 I 3.9N,L,S 4P

Respond to a #1 RCP Seal Failure

c. 001 Control Rod Drive System (A3.05) 3.5 I 3.5M,A,L,S 1

Shutdown Bank Withdrawal

d.

e.

f.

g.

h.

In-Plant Systems@ (3 for RO; 3 for SRO-I; 3 or 2 for SRO-U)

i. 061 Auxiliary I Emergency Feedwater System (A2.04) 3.4 I 3.8D,A,E,R 4S

Operate the TD AFW Pump Locally (JPM 74-2AP)

j. 004 CI ,eli lieal alld 'v'olUilie Conti 01 Systel Ii (AZ.25) 3.8/4-:&-D,R '---1--

Ulieo'iti~IIedDilution Flow Patll IS9Iatiol~I-OPS0,6~+4:&)7~('"d'~!\11~40'"2»-~~'f. tl143 "I ~3/z~~n,C- Y-tc.<,;"",<'d '?e-t- p/~.;,,,r "-G'v-.t-_<:.~ <-..~ ~(A. '. k ..A,,-(.j..·W,J. 1:::>, s<:..."""",t ... / L,="'-

k.D(PJ. /tc EIe..G\-t-\c::..",J, 1:);sk\"Du-Hc"" (A J, 10) :,.0/3,.3 D 1 ri 0-Y;:-e",v5k ~v 'SD ~e.....J. ''2.;11-1-14 ~.iVv\. (Vct1'f"'oC...(, ~ i41~ok(W(t O~ I /l.p2.)

@ All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions;all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlapthose tested in the control room.

NUREG-1021 Revision 9

Page 13: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2

(

(

(

* Type Codes Criteria for RO / SRO-I / SRO-U

(A)lternate path 4-6 / 4-6 / 2-3 :>(C)ontrol room(D)irect from bank ~9/:':;8/ 4],(E)mergency or abnormal in-plant 1 / 1/:2::1\(L)ow-Power / Shutdown 1 / 1 / 21 7-

(N)ew or (M)odified from bank including 1(A) 2/ 2/ 1'</(P)revious 2 exams 3/ 3/ 2 (randomly selected)(R)CA ?; 1 / 1/21!fJ(S)imulator

JPM Summary

JPM A RHR spray will be established in accordance with FR-Z.1, High Containment Pressure. This is a BankAlternate Path JPM.

JPM B An RCP seal failure will be diagnosed and the Abnormal Operating Instruction used to remove the pumpfrom service. This is a new low power/shutdown JPM

JPM C A failure of the step counter will occur during the withdrawal of Shutdown Rods requiring a reactor trip.This is a new alternate path low power/shutdown JPM.

JPM I Plant JPM -The trip and throttle valve will not open electrically while TDAFW pump is being placed inservice locally. This is an Alternate path Bank JPM using emergency abnormal procedure performed insidethe RCA.

JPM J Dilution flow path will be isolated using O-SI-OPS 062-214.0. This is a Bank JPM performed inside theRCA using an Appendix contains in a surveillance instruction.

NUREG-1021 Revision 9

Page 14: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-301 Operating Test Quality Checklist Form ES-301-3

(

(

(

Facility: Sequoyah 1 & 2 Date of Examination: 1/28/2008 Operating Test Number: NRC

1. GENERAL CRITERIAInitials

a b* c#

a. The operating test conforms with the previously approved outline; changes are consistentwith sampling requirements (e.g. 10 CFR 55.45, operational importance, safety function '/6 -;LJ t~~distribution).

b. There is no day-to-day repetition between this and other operating tests to be administered -rs lyK!?during this examination. -rZJc. The operating test shall not duplicate items from the applicants' audit test(s) (see Section

/'~ \ri:7D.1.a). ,7ZJd. Overlap with the written examination and between different parts of the operating test is /0 t~within acceptable limits. rzJe. It appears that the operating test will differentiate between competent and less-than-

~ ~ifvcompetent applicants at the designated license level. JZ---'2. WALK-THROUGH CRITERIA - - -

a. Each JPM includes the following, as applicable:

* initial conditions .,..

* initiating cues ./

* references and tools, including associated procedures v

* reasonable and validated time limits (average time allowed for completion) and specificdesignation if deemed to be time-critical by the facility licensee /"

17--~* operationally important specific performance criteria that include: 76- detailed expected actions with exact criteria and nomenclature v

- system response and other examiner cues .,'

- statements describing important observations to be made by the applicant ,"

- criteria for successful completion of the task ",,"

- identification of critical steps and their associated performance standards ./

- restrictions on the sequence of steps, if applicable ."

b. Ensure that any changes from the previously approved systems and administrative walk-through outlines (Forms ES-301-1 and 2) have not caused the test to deviate from any of

~ f7J {~the acceptance criteria (e.g., item distribution, bank use, repetition from the last 2 NRCexaminations) specified on those forms and Form ES-201-2.

3. SIMULATOR CRITERIA - - -The associated simulator operating tests (scenario sets) have been reviewed in accordance with

~ -n:.~Form ES-301-4 and a copy is attached.

Printed Name /Signa~Q. Date.---r/'

~rvz'-5 /-:~~, /1-- //;7108a. Author 7 hOl11ffS

b. Facility Reviewer (*) ~, i.)tlJLc.~ -:»: Iff 7/0 4. I ...."'"'- '-' .1-_ ./~~~..I~

c. NRC Chief Examiner (#) 't-f\ MUl A"'v':)AIK7 '/n~..~/l fti. 1l1'::1f:--.-.. o i /1"3!~trJBd. NRC Supervisor J).AtG(jJJ...l. \V If)MJJ.JAJ I 7!:.mlor

....-.--t'i!lJ/!",

\ " \ .~

NOTE: * The facility signature is not applicable for NRC-developed tests.

# Independent NRC reviewer initial items in Column "c"; chief examiner concurrence required.

NUREG-1021 Revision 9

Page 15: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-301 Simulator Scenario Quality Checklist Form ES-301-4

(

(

Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC

QUALITATIVE ATTRIBUTES Initials

a b* c#

1. The initial conditions are realistic, in that some equipment and/or instrumentation may be out of73service, but it does not cue the operators into expected events. 10 W$

2. The scenarios consist mostly of related events. -J~ "J'1-' ~3. Each event description consists of

• the point in the scenario when it is to be initiated

• the malfunction(s) that are entered to initiate the event1~/~ JV

• the symptoms/cues that will be visible to the crew

• the expected operator actions (by shift position)

• the event termination point (if applicable)

4. No more than one non-mechanistic failure (e.g., pipe break) is incorporated into the scenario without '70 1'~a credible preceding incident such as a seismic event. 7Z/5. The events are valid with regard to physics and thermodynamics. 7~ -IZ..- \~6. Sequencing and timing of events is reasonable, and allows the examination team to obtain complete

'76 'j~evaluation results commensurate with the scenario objectives. -rt»7. If time compression techniques are used, the scenario summary clearly so indicates. Operators /'-5 Jl; \,,~have sufficient time to carry out expected activities without undue time constraints.

8. The simulator modeling is not altered. ?~ ri- ~9. The scenarios have been validated. Pursuant to 10 CFR 55.46(d), any open simulator performance

deficiencies or deviations from the referenced plant have been evaluated to ensure that functional /~ 71J ~fidelity is maintained while running the planned scenarios.

10. Every operator will be evaluated using at least one new or significantly modified scenario. All other:7~ ~scenarios have been altered in accordance with Section 0.5 of ES-301. 1V

11. All individual operator competencies can be evaluated, as verified using Form ES-301-6 (submit the -/:5 .~form along with the simulator scenarios). jJ../12. Each applicant will be significantly involved in the minimum number of transients and events

-;!~ ~~specified on Form ES-301-5 (submit the form with the simulator scenarios). TL/

13. The level of difficulty is appropriate to support licensing decisions for each crew position. 76 ~ '{'(lDTarget Quantitative Attributes (Per Scenario; See Section D.5.d) Actual Attributes - - -

1 2 3 4

1. Total malfunctions (5-8) 8/

16""' 7/ '16/ -;f~ -;L; Mf:,2. Malfunctions after EOP entry (1-2) 2""' 1...-- 72/ ;2/ /~ -rc; ~3. Abnormal events (2-4) 3""-

3" 4/ 3/ .~ "T/.J l~~

4. Major transients (1-2) 1/ 1v 1 / 1/ /,:) /L i:~ID5. EOPs entered/requiring substantive actions (1-2) 1 ,/ 1/ 1/ 1/ ?5 '17- "rib6. EOP contingencies requiring substantive actions (0-2) 1v 0,/ 1/ 1/ 7'7 7tr- ~7. Critical tasks (2-3) 2/ 3v 2/ 2/ 7~ -rt- vWJ3

NUREG-1021 Revision 9

Page 16: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-301 Transient and Event Checklist Form ES-301-5

(

(

(

Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Operating Test No.: NRC

A E ScenariosP V

P E 1 2 3 4 T ML N Spare 0 II T T NCREW CREW CREW CREW

C POSITION POSITION POSITION POSITION A IA T L MN Y UT P M(*

E S A B S A B S A B S A B R I UR T 0 R T 0 R T 0 R T 00 C P 0 C P 0 C P 0 C P

RX 0",,- 1 1 1 1 0

NOR 1/ I 0 1 1 1 1

SROU I/C ,\5/ Z 3 8 4 4 2

MAJ 1/ i 0 1 2 2 1

TS 3/ c 0 3 0 2 2

RX 1/ 0/ 1 1 1 0

NOR Ov 1/ 1 1 1 1

SROI-1 I/C 3/ 5/ 8 4 4 20

MAJ 1v 1 v 2 2 2 1

TS 0 3/ 3 0 2 2

RX 0 1/ 0 1 1 1 0

NOR I 0" 1 1 1 1 1

SROI-2 I/C Y 4/ 7 11 4 4 2

MAJ f 1 v 2 3 2 2 1

TS ~ Ov 2 2 0 2 2

0 1 0 1 1 1 0

1 0 1 2 1 1 1

NA 7 5 3 15 4 4 2

1 1 1 3 2 2 1

2 0 0 2 0 2 2

1 1 0

1 1 1

4 4 2

2 2 1

0 2 2

NUREG 1021 Revision 9

Page 17: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-301 Transient and Event Checklist Form ES-301-5

(

Facility: Sequoyah 1 &2 Date of Exam: 4/9/2007 Operating Test No.: NRC

A E Scenarios

P V

P E 1 2 3 4 T ML N Spare 0 II T TCREW CREW CREW CREW NC POSITION POSITION POSITION POSITION A IA T L MN Y UT P M(*

E S A B S A B S A B S A B R I UR T 0 R T 0 R T 0 R T 00 C P 0 C P 0 C P 0 C P

1 1 0

1 1 1

4 4 2

2 2 1

0 2 2

1 1 0

1 1 1

4 4 2

2 2 1

0 2 2

1 1 0

1 1 1

4 4 2

2 2 1

0 2 2

Instructions:

1. Circle the applicant level and enter the operating test number and Form ES-D-1 event numbers for each eventtype; TS are not applicable for RO applicants. ROs must service in both the "at-the-controls (ATC)" and"balance-of-plant (BOP)" positions; Instant SROs must do one scenario, including at least two instrument orcomponent (I/C) malfunctions and one major transient, in the ATC position.

2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to SectionD.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may bereplaced with additional instrument or component malfunctions on a 1-for-1 basis.

3. Whenever practical, both instrument and component malfunctions should be included; only those that requireverifiable actions that provide insight to the applicant's competence count toward the minimum requirementsspecified for the applicant's license level in the right-hand columns.

This matrix assumes that Scenario 3 is used as the spare. If scenario 3 is used in combination with anyother scenario, the minimum requirements are still met for each applicant.

NUREG 1021 Revision 9

Page 18: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-301 Competencies Checklist Form ES-301-6

(

(

Facility: Sequoyah 1 & 2 Date of Exam:1/28/2008 Operating Test No.: NRC

SRO RO (ATC) BOP/CRO

Competencies SCENARIO SCENARIO SCENARIO

1 2 3 4 1 2 3 4 1 2 3 4

Interpret/Diag-2,3,6, 3,4,5, 3,4,5, 2,5,6, 1,2,3, 2,5,6, 3,4,5,nose Events 2-9 1-7,9 2-9 2-9

9 6,7,9 6,8,9 7,84-8

4,7,8 7 9and Conditions

Comply With 1,2,3,3,5,6,

1,3,4,1,2,5, 1,4,5, 1,2,3, 1,2,6,

1,3,4,and Use ALL ALL ALL ALL 6,8,9

95,6,8,

6,7,8 6,8 5,7 75,6,7,

Procedures (1) 9 9

Operate 1,2,3,3,5,6,

1,3,4,1,2,5, 1,4,5, 2,3,5, 1,2,6,

1,3,4,Control Boards N/A N/A N/A N/A 6,8,9

95,6,8, 6,7,8 6,8,7 7 7

5,6,7,

(2) 9 9

Communicate 1,2,3, 1,3,4, 1,3,4,and ALL ALL ALL ALL 6,8,9

3,4,5,5,6,8,

1,2,5, 1,4,5, 1,2,3, 1,2,5,5,6,7,

6,7,9 6,7,8 6,8,7 4,7,8 6,7Interact 9 9

DemonstrateSupervisory ALL ALL ALL ALL N/A N/A N/A N/A N/A N/A N/A N/A

Ability (3)

Comply Withand Use Tech. 2-4 1,2,4 3,4 2,3 N/A N/A N/A N/A N/A N/A N/A N/A

Specs. (3)

Notes:

(1) Includes Technical Specification compliance for an RO.

(2) Optional for an SRO-U.

(3) Only applicable to SROs.

Instructions:

Circle the applicants' license type and enter one or more event numbers that will allow theexaminers to evaluate every applicable competency for every applicant.

NUREG-1021 Revision 9

Page 19: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401 Written Examination Quality Checklist Form ES-401·6

~-CilitY:5(~~uoyah u s: Date of Exam: 1/;1.008 Exam Level' RO .:·iSRO~1..

Initial

Item Description a b* c'

--;15-

1 Questions and answers are technically accurate and applicable to the facilitv. 71r-J ~2. o . NRC KJAs are referenced for all questions. -;s J}--/ rrIf?b. Facility learning objectives are referenced as available.

3. SRO guestions are appropriate in accordance with Section D.2.d of ES-401 --J6 -rz,J v'v'R>- ....4 The sampling process was random and systematic (If more than 4 RO or 2 SRO questions % 1P ~were repeated from the last 2 NRC licensmp exams, consult the NRR OL program office).

5. Question duplication from the license screening/audit exam was controlledas indicated below (check the item that applies) and appears appropriate:_ the audit exam was systematically and randomly deveioped; or_ the audit exam was completed before the license exam was started; or 76 JZJ~__ the examinations were developed independently; or

"Jf.- the licensee certifies that there is no duplication; or__ other (explain)

----------_._- Ban:-r Mcditied6. Bank use meets limits (no more than 75 percent Newfrom the bank, at least 10 percent new, and the rest

;5/~-r;3 ~ 25/'6 "f1J fYIf;>new or modified); enter the actual RO / SRO-only ,J,7 I IS

r---- question distribution(s) at right.

7. Between 50 and 60 percent of the questions on the RO1MClnory CIAexam are wntten at the comprehension/ analysis level,

-15the SR.O exam may exceed 60 percent If the randomly -n>~selected K/As support the hiqhe: cognitive levels, enter 3 c; / 7 i70 / lathe actual RO I SRO question distributiorus) at light J

8. References/handouts provided do not give away answers -;:5 7lr/ IVSor aid in the elimination of distractors.

9. Question content conforms with specific K/A statements in the previously approvedexamination outline and is appropriate for the tier to which they are assigned; /6 .-fl-/ /'if:>

~.deviations are justified.

10. Question psychometric quality and format meet the guidelines in ES Appendix B. -/~ --y1-- 1W1S11 The exam contains the required number of one-point, multiple choice items; -D 11P ~~the total is correct and agrees with the value on the cover sheet.

____ Printed Name /~nat~~ Date

a. Author 210mm O:'IV~'> / '/L/ - v----:=:- //1/ot'b. Facility Reviewer (*J -Z;Z~~... /././/6'- /~~ /'.;, /Z fft;c. NRC Chief Examiner (#) ~ It BtrT$/ ff;["J (j, I '" .J;:-:...

d NRC Regional Supervisor J..!J4<AUJ---r:. WttiJ)NV.t>J / ~ .~ ( ."----'" "

Note: * The facility reviewer's initials/signature are not applicable for NRC-developed examinations.# Independent NRC reviewer initial items in Column "c"; chief examiner concurrence required.

ES-401, Page 30 of 34

Page 20: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KiA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q~ SRO E ExplanationN K D Focus Cred Cred KiA Only S

Dist Dist BIW

GENERAL COMMENTS

B= Bank 1M=Modified 1N-New 1F-Fundamental Level (I.E. Memory) 1H-Higher Cognitive Level (I.E. CIA)I

For All BANK questions: swap the order of the answer choices so that applicants cannot rely on recall of the correct answer location.

ROEXAMI 007EAl.08 N H 2 B Can the first two bullets be replaced with the following single bullet:

"Unit I was at 10% power when both MFPTs tripped."S First bullet revised. Second bullet not changed. The teaching in the

second bullet does not affect the a11SWerS to this question or any otherquestions. OK MAB 02/04/2008

Can the third bullet read as follows:"Stearn generator levels dropped to a minimum of##% and then began torise." - (use a level that is a couple of percent above the AFW start signal)Incorporated. OK MAB 02/0412008

l

.' Is there an extra space in the correct answet between "controlled" and"manually"? Fixed OK MAB 02/0412008

Is there an extra space in "A" and "B" between "required" and "to"?Fixed OK MAB 02/04/2008

2 008AA2.29 N H 2 B Be consistent with periods in answer choices. Fixed. OK MAB02/0412008

SDoes the cause of the lowering RCS pressure affect which answer iscorrect? Is it important to state that pzr pressure is inadvertently loweredwith pzr sprays or that the safety leakage rises, etc? If the pressure dropresults from a problem elsewhere, then the level behavior may change.Discuss with licensee. Licensee agreed. Comment incorporated. OKMAB 02/04/2008

3 009EA2.24 N H 2 B There is no point in stating the reason why the RCPs are required to betripped. Consider the following suggestion for the answer choices:

S A. ALL RCPs are required to be tripped.

Page I of29

Page 21: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KJA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KJA Only S

Dis! Dis! BIW

B. ONLY RCP #1 and #3 are required to be tripped.C. ONLY RCP #1 is required to be tripped.D. ONLY RCP #3 is required to be tripped.

Incorporated. OK MAB 02/04/2008

4 01lEK3.13 B F 2 B Change answer choices to:A. Realigns the ECCS suction path from the RWST to the

S contairunent sump.B. No change neededC. No change neededD. Realigns the ECCS flow to prevent boron precipitation.

Incorporated for "D". Licensee and CE agreed on change for "A". OKMAB 02/0412008

5 015/017 B H 2 S Suggest making slight modification to "C" and "D":AK2.08 C. The RCP stator windings will overheat.

D. The RCP motor bearings will overheat.Incorporated. OK MAB 02/04/2008

6 022AA2.03 B H 2 X? B Have licensee explain the mechanism for "A" to occur. I need to betterunderstand the failure mechanism that can cause the charging to go to 120

S gpm and then retum to normal with pressurizer level also returning tononna!.Licensee modified "A" based on comment. OK MAB 02/04/2008

7 025AK2.05 M H 2 X? Y "B" and "D" plausibility: Why would it be plausible for an applicant toii + believe that spray pumps would be drawing suction from the sump when, there is 68% remaining in the RWST? Also, why would an applicant

S believe that suction for the spray pumps would be from the sump whenthey are in ECA-I.I. If adequate level existed in the sump and spraypumps are operating why would they be in ECA-I.I ?Parameters in the stem changed to address these concerns. The changes tothe parameters also caused the correct answer to change. OK MAB02/04/2008

This question contains overlap flaws with questions on the SRO exam.This question provides information that indicates that E-Ois entered upon areactor trip. I think this comment could alleviate itself ifthe issues on theSRO exam are resolved. Concern addressed on SRO exam. OK MAB02/0412008

Add a period after the sentence at 08:0 l. Fixed. MAB 02/04/2008

Does the information in the stem preclude an applicant from assuming thatcontainment pressure could have been greater than 12 psid and has nowdecreased to 9.7 psid? Ifthis is an assumption that the applicants are

Page 2 of29

Page 22: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KiA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KiA Only S

Dist Dist B/W

forced to make, would it change the correct answer. Is there a possibleargument that there are two correct answers to this question based onforcing the applicant to make assumptions? Qnestion statement has beenenhanced to preclnde an assnmption that conld make two answers correct.There is enough info in the stem to preclnde applicants having a need tomake any assumptions on containment pressure. OK MAB 02/04/2008

8 026AK3.03 B F 2 x E "B" and "C" are really the same distractor. They both state to reduce heatload, or minimize heat load. "C" implies that RCPs must not be needed if

S they are not cooled to maintain CCS within design capability.One of these two distractors should be modified/replaced. "B" has beenchanged to address concem. OK MAB 02/04/2008

9 027AAI.02 B H 2 E "start" should be plural in the answer choices. Fixed. OK MAB02/04/2008

SDelete the piece of each answer choice that states that heaters ENERGIZEor DEENERGIZE. This is not needed to make answer choices unique. I.E.A. Pressurizer Pressure HI alarm annunciates. Actual pressurizer pressurestarts to rise.Etc. for the rest of the answer choices.Incorporated. OK MAB 02/04/2008

10 038G2.1.3 N F 2 E Technical accuracy of "A" and "B": Is there a requirement to cool theplant prior to tumover? The supporting documentation does not support

S this. The supporting documentation supports that the cooldown is notJ.! permitted to be performed by an operator who is simultaneously

" conducting tumover. This is different than requiring that the cooldowntake place prior to tumover. TIle more precise way to phrase this would beto state the converse of what is stated in "C" and "D". I.E. An operator isnot permitted to simultaneously tumover and perform the cooldown.Incorporated. OK MAB 02/04/2008

First part of "C" and "D" also needs wording enhancements becauseOPDP-I would not provide direction to cooldown while ccncurrentlyperforming tumover. OPDP-I provides Administrative guidance, notguidance that is specific to the SGTR accident. Consider: An operator ispermitted to simultaneously turnover and perform the cooldown.Incorporated. OK MAB 02/04/2008

II 040AKI.03 B F 2 x :y KIA Match: The IvA requires testing knowledge of operationalimplications of RCS shrink and depressurization as they apply to steam

S line break. This question tests knowledge of brittle failure which stemsfrom an RCS cooldown and subsequent pressurization.New Q written. OK MAB 02/04/2008

Page 3 of29

Page 23: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q- SRO E ExplanationN K D Focns Cred Cred KIA Only S

Dist Dist B/W

This question has other issues with distractors, but because of the abovecomment, there is no need to address these comments at this time.New Q written. OK MAB 02/04/2008

12 055G2.4.29 N F I- x .y Is the 19:30 bullet worded correctly?2 Q replaced. OK MAB 02/04/2008

SPunctuation in answer does not appear to be correct,Q replaced. OK MAB 02/04/2008

KIA not Matched: The KIA requires a SBO. Does this question testknowledge of a SBO, or just knowledge of a security threat? The way Iread this question is that you could delete all the information in the stemand simply state that there is a credible insider security t1ueat and it isnecessary to dispatch an operator to the EDG room. In other words, theLOOP appears to be irrelevant.Q replaced. OK MAB 02/04/2008

13 056AKI.03 B H I- x .g Be consistent with periods after bullets. Fixed. OK MAB 02/04/20082

S Replace "D" with the logical error that would result from subtracting 15 psifrom 2085.Incorporated. OK MAB 02/04/2008

Consider combining the subtraction of 15 psi and tile use ofThot to replace"e".Incorporated. OK MAB 02/04/2008

Technically this question could be rated as U, but the fix is simple enoughthat it is being rated as E. The above comment incorporation will help tomake the LOD more acceptable. As written, two distracters are notplausible. It is not reasonable for a licensed operator to use Tcold or Tavein a subcooling calculation.Noted. Issues addressed. OK MAB 02/04/2008

14 058AK1.01 B H 2 .g After 4 hours would the batteries be discharged? Or is there a requirementthat only states that the batteries will not be discharged prior to 4 hours?

S We need to ensure that the aIISWer choices accurately represent the statusof the batteries. Concems addressed by changing the wording. OK MAB02/04/2008

15 062AA1.01 M F 2 S Q is SAT.

16 W/E04 B F I- x X? .g Be consistent with periods in the aIISWer choices. Fixed OK MABG2.4.28 2 'I 02/04/2008

Page 4 of29

Page 24: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Nou Partial Miu Q- SRO E ExplanationN K D Focus Crcd Crcd KIA Only S

Dist Dist B/W

S Distractor "A" is not plausible. ECCS flow is an indirect parameter, whichwill follow RCS pressure, which is answer choice "DO'. It does not havethe procedure guidance to monitor the indirect parameter (ECCS flow)when the direct parameter is available (RCS P).Concern addressed. OK MAE 02/04/2008

I also have some issues with "B" because subcooling is calculated fromRCS pressure. It makes no sense to monitor the calculated parameter whenthe direct parameter is available. Concern addressed. OK MAB02/04/2008

The only thing that makes "A" and "B" incorrect is that the procedure doesnot state these parameters, but they would work as a method fordetermining if the leak was isolated. Noted. MAB 02/04/2008

The KIA does not restrict this question to be written to test leak isolation.Noted. MAB 02/0412008

17 W/E05 B F 2 X? E How is "A" different from "D"? Are these unique answer choices? ItEK3.1 should be possible to modify the wording of these two distractors to ensure

S that they are unique, I.E., "A" could be pertaining to high temperaturesand "DO' could speak to cold water on dry tubes as is suggested in thedistractor analysis. Wording in "DO' enhanced to ensure uniqueness ofanswer choice. OK MAB 02/04/2008

18 W/Ell M H 1 x Y Question does not discriminate at the licensed operator level. This is aEK2.2 h question that, when provided the reference, almost anyone could arrive atREF S the correct answer. i

Following suggestion incorporated. OK MAB 02/04/2008

Suggestion to improve question:Use most of the same items in the stem. Some can be deleted if theybecome unnecessary,Q: Which one ofthe following correctly describes the flow rate that meetsthe intent of ECA-l.1, Step 20 RNO?

A. Establish 325 gpm ECCS flow. ECCS pumps may be startedand stopped as necessary to accomplish the desired flow rate.

B. Establish 325 gpm ECCS flow. ECCS pumps are not permittedto be started and stopped as necessary to accomplish the desiredflow rate.

C. Establish 400 gpm ECCS flow. ECCS pumps may be startedand stopped as necessary to accomplish the desired flow rate.

D. Establish 400 gpm ECCS flow. ECCS pumps are not permittedto be started and stopped as necessary to accomplish the desiredflow rate.

This suggestion raises the plausibility ofthe distractors and still tests

Page 5 of29

Page 25: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L PsychometricFlaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dist B/W

whether the applicants understand the intent of the procedure step.Suggestion incorporated. OK MAB 02/04/2008

19 001AK2.05 M H 1- B Be consistent with periods behind bulleted phrases. Fixed. OK MAB2 02/04/2008

SWould the question be enhanced if one of the Thot or Tcold instrumentswere to fail instead of the Tavg auctioneering unit? Discuss with licensee.Decided not to make a change on temp inst. OK MAB 02/04/2008

20 033G2.4.2l M F 2 S Q is SAT

21 036AKl.Ol N F 2 S Maintain past tense in third bullet. Somewhat incorporated, but it does notaffect technical accuracy of question. OK MAB 02/04/2008

Question is written in the "NOT' format, which is discouraged byNUREG-l02l. This question can remain in its current form as long as thelicensee agrees that the question being in this format will not affectapplicant performance. In other words, their applicants have seenquestions in this format and would not get the incorrect answer for anyother reason than a knowledge weakness.Noted. OK MAB 02/04/2008

22 060AAl.02 M F 2 X? x lei KIA Match: Have the licensee provide an explanation of how the KIA ismatched. The KIA requires testing knowledge ofhow to operate or

S monitor ventilation systems during an accidental gaseous radwaste release.:1' How is a ventilation system being monitored? Rad Mntr is part of the

ventilation system. KIA match is OK. MAB 02/04/2008

When would the Waste Gas Rad Monitor not detect a leak from a WasteGas Decay Tank? Changed stem to a flange leak which would not causethe Waste Gas Rad Mntr to alarm. OK MAB 02/0412008

23 069G2.4.45 N H 2 B Technical accuracy of the question is a concern because they do not haveto restore integrity within 1 hour. Ifthey do not restore integrity within 1

S hour, then they are required to shutdown. TIle answer choices need to bemore precise in order to be technically correct.Wording enhancements made to specifically ask for what the ActionStatement states. OK MAB 02/04/2008

24 074EK3.07 B F 1 x lei LOD= 1: Distractors are not plausible. Due to the non-credible distractors,this question does not discriminate at the appropriate level to make a

S licensing decision. Changed distractors. OK MAB 02/04/2008

Reflux boiling is a cooling method used when RCPs are off.How would it be reasonable for an operator to think that starting an RCP

Page 6 of29

Page 26: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KJA# B L L PsychometricFlaws Content Flaws U CommentM 0 0 Stem Cnes T/F 1 Non >1 Non Partial Min Q- SRO E ExplanationN K D Focus Cred Cred KJA Only S

Dist Dist B/W

would keep pressure from rising?Changed distractor. OK MAB 02/04/2008

2S 076AK2.01 B H I x tf A pinhole leak of a fuel assembly would be evident in RCS samples thatare analyzed for various isotopes; however, small leaks will not necessarily

S result in rising radiation monitor trends. There are concerns with "B"being an altemate correct answer because the size of the leak is notdefined. Also, the RCS leakage locations are not defmed, so there are alsoconcems about whether a small RCS leak would result in a rising radmonitor reading."Significant increase in RCS activity" added to stem. OK MAB02/04/2008

LOD= I: Distractors are not plausible. Due to the non-credible distractors,this question does not discriminate at the appropriate level to make alicensing decision.Question is on the cusp ofbeing unacceptable due to low LOD. Noted.MAB 02/04/2008

Consider writing a question that has a plant nip and a SGTL. This willallow testing MSL monitors as well as Condenser Off Gas Monitors. Thisidea may help to raise the question to a level where it could be used todiscriminate between a competent and less than competent licensedoperator.Not incorporated. Allowed by CEo The rest ofthe exam is at anacceptable level to not warrant a change to this question. OK MAB02/04/2008

26 W/E09 B H 2 B The "repressurization" piece of "A" and "B" should be deleted. It does not

EA2.1 add information that is needed to make these answer choices unique.S Discuss with licensee. Deleted. OK MAE 02/04/2008

Consider rewording the question as follows:Which one of the following correctly states the procedure that maximizesthe allowable cooldown rate for the provided circumstances and themaximum cooldown rate allowed by that procedure?

A. Use ES-0.2, Natural Circulation Cooldown. The cooldownlimit is SOF/hr.

B. Use ES-0.2, Natural Circulation Cooldown. The cooldownlimit is 100F/hr.

C. / Use ES-O.3, Natural Circulation Cooldown with Steam Voids inVessel (with RVLSI). The cooldown limit is SOF/hr.

D. Use ES-O.3, Natural Circulation Cooldown with Steam Voids inVessel (with RVLSI). The cooldown limit is SOF/hr

Incorporated. OK MAE 02/04/2008

Page 7 of29

Page 27: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psvchometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q~ SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dist B/W

27 W/EI4 B F 2 S Q is SAT.EA2.2

28 003K3.04 B H 2 S Q is SAT.

29 003G2.3.10 N F 2 S Q is SAT.

30 004K5.26 N H 2 S Q is SAT.

31 004A3.08 B H I- X B "D": it is not credible for an applicant to make this error. There is no2 division needed in this calculation.

S Consider making "D" 60%. Discuss with licenseeIncorporated. OK MAB 02/04/2008

32 005A4.03 B H I- x :y "RCS cooldown rate is too high" - what does this mean? It may not2 matter, but it would be better to provide the applicant with information that

S they would normally have available to them, such as an actual temperatureat two different times. It may also be necessary to state that SRO gavethem direction to cooldown at a certain value. The question piece wouldneed to change slightly to ask for the actions needed to comply with theSRO's directions. (These changes will make "C" plausible)Q replaced. OK MAB 02/04/2008

Question should be tied to the procedure. I.E. Which one of the following..... CONSTANT RHR flow, in accordance with 0-SO-74-1, "proceduretitle"?Q replaced. OK MAB 02/04/2008

"A" and "B" do not contain credible misconceptions to discriminatebetween competent and less than competent licensed operators.Q replaced. OK MAB 02/04/2008

33 006KI.02 M F 2 B Is there an extra space between "SSPS" and "if' in the stem?Fixed. OK MAB 02/04/2008

SHave licensee walk me through the technical aspects of the question. Imay be OK with the question with a couple of minutes of discussion.Q is SAT. MAB 02/04/2008

34 007K3.01 B H 2 x B Is there an extra space in "D" between "..4," mId "failed"?Fixed. MAB 02/0412008

S"C" not plausible because there is no relationship with the PRT.The following change would correct the distractor plausibility issue:

A. #2 seal on RCP #4 failed; Pressurizer Safety Valve, 1-68-568,failed open; Reactor Head Vent Valve, I-FCV-68-394, Failed

Page 8 of29

Page 28: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q- SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dist BIW

OpenB. #2 seal on RCP #4 failed; Pressurizer Safety Valve, 1-68-568,

failed open; Reactor Head Vent Valve (I-FCV-68-394, FailingOpen, could not cause the stated conditions)

C. Pressurizer Safety Valve, 1-68-568, failed open; Reactor HeadVent Valve, I-FCV-68-394, Failed Open (#2 seal on RCP #4failing could not cause these conditions)

D. Pressurizer Safety Valve, 1-68-568, failed open (PressurizerSafety Valve, 1-68-568, failing open could not cause the statedplant conditions AND Reactor Head Vent Valve, I-FCV-68-394, Failing Open could not cause the stated plant conditions.)

Discuss the above change with thelicensee, If we can get this change towork, then the question may be SAT.Worked with licensee to develop plausible distractors. OK MAB02/04/2008

35 007G2.1.1 N F 2 x B Is fourth bullet worded correctly? Fixed. MAB 02/04/2008

S "A" and "B" are not mutually exclusive, which harms their plausibility. Inother words, If"B" were true, it will still makes sense to do "A". Theproblem is that if the applicant determines that the alarm is valid, adjustinglevel will always be correct."A" and "B" corrected. MAB 02/04/2008

Is there an extra space in "C" and "D" between "level" and "alarm"?They neglected to correct this; however, the extra space appears in the

~! ' correct answer as well as a distractor, so it will not adversely affectr' plausibility. OK MAB 02/04/2008

The question should be specific to the answer choices provided:Which one of the following correctly states the validity ofthe PRT levelalarm and the required actions as a result of the alarm?Incorporated. OK MAB 02/04/2008

I would prefer to have "A" and "B" read as follows:A. The PRT level alarm is valid. (need a better second half of distractor)B. The PRT level alarm is valid. 0-SI-OPS-068-137.0, RCS WaterInventory, is required to be performed.A version ofthis comment was incorporated. AOP-R.05 was used. OKMAB 02/04/2008

I would prefer the second half of "C" and "D" to read such that itspecifically states the information being tested. I.E.:C. The PRT level alarm is false. According to OPDP-4, the maximum timethat Maintenance has to correct the condition causing the invalid alarm is 7days, at which time the alarm is required to be cleared/disabled.

Page 9 of29

Page 29: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q- SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dist B/W

D. The PRT level alarm is false. According to OPDP-4, the maximumtime that Maintenance has to correct the condition causing the invalidalarm is 72 hours, at which time the alarm is required to becleared/disabled.Incorporated. OK MAB 02/04/2008

36 008K4.07 N F 2 x E Is there an extra space between "CCS" and "Pump" in the stem?(I am beginning to think that it just may be the way it prints out and thatthere may not be an extra space - but it is free to ask.)

S Fixed. MAB 0210412008

Would it be possible to test the RED light on the throwover switch for thefirst part of every answer choice. I think this would be a better test of theactual plant indications. I.E. Either the red light is ON or OFF. Discusswith licensee. I think this could help the plausibility of "B".Did not incorporate after discussions with licensee. MAB 02/04/2008

37 010K6.03 M H 2 S Be consistent with periods after bullets. Fixed. MAB 02/04/2008

Simplify the answer choices as follows:A. Master controller output would increase. PZR pressure would

be maintained above the reactor trip setpoint.B. Master controller output would increase. PZR pressure would

decrease to the reactor trip setpoint.C. Master controller output would decrease. PZR pressure would

be maintained above the reactor trip setpoint.·c D. Master controller output would decrease. PZR pressure would

" be maintained above the reactor trip setpointIncorporated. MAB 02/0412008

38 012K4.04 N H 2 X? f "A" and "D" are not plausible because the last bullet in the stem leads theapplicant to only consider answer choices where RTA "A" is different than

S RTA "B" UV and Shunt coils. Simply using psychometrics, and applicantcan eliminate these two answer choices. Discuss with licensee.Answer choices simplified. Issue resolved. OK MAB 02/04/2008

39 013K2.01 B H 2 S Potential overlap issues with 006Kl.02 should be discussed. If it isdetermined that there is no overlap, then question may be SAT.Overlap issue resolved. OK MAB 02/04/2008

40 022A2,04 N H 2 X? f Is the wording correct in the second paragraph, "Compare the effects on ofthe .."? Fixed. OK MAB 02/04/2008

SHave the licensee explain the plausibility of additional cooling units beingplaced in service. Are there additional cooling units that would beavailable at any time in order to reduce temp? If there are additional

Page 10 of29

Page 30: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KiA# B L L PsychometricFlaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q~ SRO E ExplanationN K D Focus Cred Cred KiA Only S

Dist Dist BIW

cooling units that could be used, under what conditions would theytypically be used?Additional cooling units are available one of the units. Unit differencesmake the distractors plausible. OK MAB 02/04/2008

41 025K5.02 M F 2 B Is the incorrectness of this answer choice based entirely on the word"each"? This needs to be discussed to ensure only one correct answer.

S Distractors reworked to ensure only one correct answer. OK MAB02/04/2008

42 026K4.07 M F 2 B The licensee needs to explain why the II % level requirement is because ofthe I-FCV-74-3 interlock. I am not sure that the attached reference

S material supports this. Maybe the supporting documentation is in anotherprint or lesson plan. Also as part ofthis discussion, the wording of thequestion should be reviewed to ensure that it is accurate and will elicit theanswer.Licensee explained the level requirement. OK MAB 02/04/2008

43 026G2.4.48 M H 2 x lei Are there extra spaces in "A" and "B"? Fixed. MAB 02/04/2008

S Will the terminology "loading room" confuse any of the applicants?Should this be defmed with more precise terminology?"loading room" deleted. OK MAB 02/04/2008

Is the wording of "A" and "B" precise enough? The pump did not (failedto) auto start - this is a fact. I would prefer more precise terminology such

'1'[ as: "Pump did not auto start even with an auto start signal present."Altemative similar wording would work as well.Incorporated. OK MAB 02/04/2008

Should the answer choices contain commas or periods between the twoanswer parts. It looks like two complete sentences are separated bycommas.Two sentences used. OK MAB 02/04/2008

Second set ofbullets should be introduced with a colon, vice semi-colon.Fixed. MAB 02/04/2008

Time in the stem is only provided to the minute, yet 14:05:00 is almost afull 4 minutes from 14:07:59. The clock in the control room may read thesame, but this is greater than 180 seconds. Discuss whether this questionneeds to be more precise to elicit the correct answer.More precise times are not needed - I made an error with my math whenthis comment was made. OK MAB 02/04/2008

"A" and "B" are not mutually exclusive because it may never be wrong to

Page II of29

Page 31: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L PsychometricFlaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dist B/W

verify that there is room on the EDG prior to manually placing a load onthe EDG. If "A" is correct, the "B" will also be correct,Wording revised to ensure unique answer choices. OK MAB 02/0412008

When did the containment pressure reach 2.81 psig? Discuss whether thisis important information to contain in the stem.Q stem is precise enough. OK MAB 02/0412008

"A" and "B" plausibility: If the pump was supposed to auto start, then Iknow, just using common sense, that the EDG is desigoed to have room tostart the pump (assuming that the sequencer has timed out). If thesequencer has not timed out, then it would not be smart to start the pumpanyway. "A" wording revised. "B" determined to be OK with the changeto "A". OK MAB 02/04/2008

44 039Al.09 N H 2 x .g KIA Match: The KIA requires testing knowledge of monitoring mainsteam line radiation monitor parameters associated with operating the

S MRSS controls to prevent exceeding design limits. How does this questiontest the knowledge required by the KIA? How is knowledge of theradiation monitor indications being tested in relation to how thoseindications are used to avoid exceeding design limits?Q replaced. OK MAB 02/04/2008

The question asks for the condition that is causing the alarm. Is there apossibility that another condition, such as an actual high rad conditioncould cause the alarm? High rad may not cause the other conditions, but

,1 could it cause the alarm? The wording of the question may need someminor revision to ensure that the correct answer is elicited.Q replaced. OK MAE 02/0412008

Are the second parts of the answer choices worded correctly? The subjectof the sentence appears to be implied. It would be better to state the noun.Q replaced. OK MAE 02/04/2008

No reference is being suggested. Are the time requirements a closed bookknowledge item at SQ?Q replaced. OK MAB 02/0412008

45 059A2.07 N H 2 x ? B What conditions would automatically close the 2B MFPT Cond FCVs?Valve operation depends on power being above or below 60%. OK MAB

S 02/0412008

"A" Plausibility: What is the logic behind the FCVs being re-opened in theAOP? This distractor may not be plausible. It may not be credible for anoperator to think that they would re-open valves that automatically closed.Discussed with licensee. OK MAB 02/0412008

Page 12 of29

Page 32: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KiA# B L L PsychometricFlaws Content Flaws U CommentM 0 0 Stem Cnes T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KiA Only S

Dist Dist B/W

The stem and answer choice talks about some AOP that has been entered.Is there a reason that the AOP that the operators are performing is notmentioned in the stem or the answer choices? Discuss the possibility ofadding the AOP to tighten the question and tie the answers to a specificAOP. AOP-S.OI added to the stem. OK MAB 02/04/2008

46 059A4.01 M H 2 S Second to last bullet: I assume the SG level is below setpoint, but thisneeds to be specific. Fixed. MAB 02/04/2008

Last Bullet: is it necessary to state that the dumps are armed?No - "armed" deleted. OK MAB 02/04/2008

47 061K5.01 B H 2 S Typos in 5th bullet. Fixed. MAB 02/04/2008

Trends are provided for all parameters except for SG levels.Added. MAE 02/04/2008

48 062KI.02 B F 2 B Too many items are being iterated on in the answer choices. This providesthe applicants with multiple ways to eliminate distractors. Discuss with

S licensee. Discussed. OK MAB 02/04/2008

Consider the following:A. After 1.25 seconds, all EDGs will auto start .B. After 1.25 seconds, only the IB-B EDG will start.C. After 300 seconds all EDGs will autostart.

c D. After 300 seconds only the IB-B EDG will statioIncorporated. OK MAB 02/04/2008

49 063K2.01 N H 2 ? + Distractor analysis states that an applicant may think that control power forthe breaker is supplied from the EDG battery. Why would an applicant

S think this. Do the EDG batteries supply control power to other buses or tothis bus under different plant conditions? I need to understand the crediblemisconception a little better.Answer choices revised to correct issue. OK MAE 02/04/2008

50 064K6.08 B F 2 x x .y "B" is not plausible: TIle entire reason for having a standby pump is tohave it backup the lead pump. The second pump is not referred to in the

S distractor as the standby pump, but it is strongly implied by the stemstating that there is a lead pump. A manual alignment does not appear tomake sense.Distractors revised. OK MAB 02/04/2008

"C" is not plausible because the stem provides a cue that these pumps starton tank level. "C" allowed this distractor to stay on exam after discussionswith licensee. OK MAB 02/04/2008

Page 13 of29

Page 33: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cnes T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K 0 Focus Cred Cred KIA Only S

Dist Dist BIW

"A" is the obvious answer because the stem states that these pumps start onlow tank level. It would also be common sense to assume that the standbypump would not stilt at the same time or level as the lead pump, which iswhy it is a standby pump. After discussion with licensee, decided to allowthis distractor. OK MAB 02/04/2008

If possible, place the conditions of the plant in the stem, rather than makingthe answer choices conditional. A specific tank level and switch positionfor the backup pump should be placed in the stem.It is not prohibited to place conditions in answer choices, therefore Q wasnot changed. OK MAB 02/04/2008

Consider the following:Initial plant conditions:

- 2A-A EDG running- Fuel oil day tank level = ##%- Lead fuel oil transfer pump is running- The backup fuel oil transfer pump control switch is in AUTO

Current plant conditions:- Lead fuel oil transfer pump shaft completely shears

Which one of the following correctly describes the operation of the backupfuel oil transfer pump?

A. The backup pump will be running due to a start signal on lowdischarge pressure.

B. The backup pump will be running due to a start signal on lowtanklevel.

C. The backup pump will not be running and will not start atanytime as tank level lowers.

D. The backup pump will not be running, but will start as tanklevel lowers with no discharge pressure on the lead pump.

Allowed Q to remain with only minor revision. OK MAB 02/0412008

51 073AI.01 N II 2 x :g Is second bullet worded correctly? Fixed. MAB 02/04/2008

F S Be consistent with periods behind bullets. Licensee did not incorporatethis comment, but does not affect the technical accuracy of the question,OK MAE 02/0412008

This question is really written at the (Fnmdamental knowledge level. Itappears like there may be infonnation in the stem that does not add valueto the question. The question really does not ask anything more than:What automatic actions occur as a result of2-RM-90-123A alarming onhigh radiation? Licensee did not incorporate comment, TIley are in themiddle of the band for CIA and F questions, therefore designating thisquestion in either category will not cause all exam metric to be encroached

Page 14 of29

Page 34: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# n L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q- SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dist BIW

upon. I would have required this to be fixed if it affected the adherence tothe higher cog criteria. OK MAE 02/04/2008

"B" is not plausible: What information in the stem would lend credibilityto this distractor. It is very basic that there is an auto isolation ofthe surgetank. It is not enough to simply test whether an auto isolation exists. Iagree with the plausibility that you have built into the other two distrators.Is there any way to improve this distractor by requiring the applicants toknow a little more than whether or not an auto isolation exists?"B" replaced. MAB 02/04/2008

Does "C" contain grammatical errors in both sentences?Fixed. MAB 02/04/2008

"D": when possible, always word questions and answers for what isrequired to be done, not what an operator will or may do. This is becauseoperators may do anything, but we want to test what they are required todo.Revised. OK MAE 02/04/2008

52 076A2.02 N H 2 :y Typo in second bullet. Fixed. MAE 02/0412008

S Is there enough information in the stem to elicit the correct answer?During the review in Atlanta we will need to pull prints and do a detailedreview of the information in the stem, detennine if the stem permitsapplicants, or forces applicants to make assumptions on the location of the

.j( leak, on how and where the leak is isolated, and whether there are credible

" arguments for no correct answers or mnltiple correct answers. Plausibilityof the distractors will also need to be discussed.OK. We pulled prints during IP and question is sat. MAB 02/04/2008

This question will be rated as unsat, pending the detailed review that willtake place with the licensee.Q OK MAB 02/04/2008

53 076A4.02 M F 2 E Is there an extra space between "following" and "the"?Q simplified. Corrected. MAE 02/04/2008

S"A": Would it be more plausible for I-FCY-67-146 to be "Auto" and 2-FCY-67-146 to be "Manual"? This qnestion is being asked because on thesurface it may make sense for the valve on the unit with the SI to autoreposition, rather than the other unit's valve? This may be due to myunfamiliarity with SQ. Discuss with licensee.Corrected. MAB 02/04/2008

Is there any possibility that EA-67-1 allows operators to reposition O-FCY-

Page 15 of29

Page 35: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KiA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KiA Only S

Dist Dist B/W

67-152, thus bringing into question the possibility that Manual would bethe correct response for all three valves? Q revised. Corrected. MAB02/04/2008

The stem contains a lot of words. Are we simply asking the following:Which one of the following correctly describes the following valveresponses to a Unit I safety injection?

0-FCV-67-152 I-FCV-67-146 2-FCV-67-146A. Auto repositions Auto repositions Does NOT auto repositionB. etc.Incorporated, OK MAB 02/04/2008

54 078K3.01 M F I- S Question is right at the cusp of being acceptable. When all other changes2 to the exam have been made, an overall evaluation of the exam will be

performed. Q is OK. MAB 02/04/2008

55 103A3.01 M H I- X :g "C" and "D" plausibility: There are no indications in the stem that would2 lead an applicant to believe that CVI should only have occurred on one

S train. Are rad monitors train specific for CVI? If so, add values for boththe "A" and "B" monitors, with the "B" at a lower value.Specific rad monitor information added. OK MAB 02/04/2008

56 011K6.05 N H 2 ? :g Be consistent with periods after bullets. Fixed. 02/04/2008S'f What credible misconception would lead an applicant to believe that I-LT-

68-321 would have an impact on pzr level control when I-LT-68-320 isI S selected?"

Licensee revised answer choices to correct. OK MAB 02/04/2008

AJ:e the cold cal instruments ever used for pzr level control?Cold Cal instruments deleted from answer choices. OK MAB 02/04/2008

57 015K2.01 M F I- x Y "B" and "C" are not plausible: These two choices can be eliminated just2 by knowing that even channels are powered by the same bus and the odd

S channels are powered from the same bus (or at least the same division ofpower). The mixing of even and odd NI numbers make these twodistractors not plausible.Distractors revised to correct concem. OK MAB 02/04/2008

58 016K1.10 M F 2 S Q is SAT.

59 o17K4.03 B F I x Y Remaining "in" limits, or "within" limits? Either way - it just depends onhow you want your applicants to read the question. Fixed. MAB

S 02/04/2008

What does "limits" mean in the stem? Is this specific enough to elicit the

Page 16 of29

Page 36: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KJA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KJA Only S

Dist Dist BIW

correct answer? I understand what it means only by reading the questionanalysis, which the applicants will not have. Wording enhancementsmade. OK MAE 02/04/2008

The question should also be tied to the procedure. Incorporated. MAB02/04/2008

"C" and "D" are not plausible. The magnitude of these two answer choicesmake them completely non-credible.Distractors revised. OK MAB 02/04/2008

Are there any other choices that have meaning at your plant? 600F?700F? nOF? 750F? Different values were agreed upon with licensee.OK MAE 02/04/2008

60 045K5.17 N H I- x Y "A" is not plausible. This is not a method which is directed by plant2 procedures, which does not create a plausible distractor.

S Qand distractor revised to address concem. OK MAE 02/04/2008

"D" is not plausible. Two variables, the two parameters being analyzed,moving is not plausible. Q and distractor revised to address concem. OKMAB 02/04/2008

This question is pure GFE. Applicants have already passed a GFE. This isthe Site Specific written exam. Steam header pressure incorporated, whichmakes the question more plant specific. OK MAB 02/04/2008

;. Will the correct answer be correct under all plant conditions that can beassumed with the information provided in the stem? To be safe, does abumup need to be provided in the stem as well? Answer will always becorrect at 50% power. OK MAB 02/04/2008

This question can be brought to an acceptable level by making it plantspecific. Maybe iterating on "B" and "C" and then adding a second half tothe distractors would accomplish plausibility and allow for a plant specificquestion. Q revised. OK MAB 02/04/2008

61 055A3.03 N H 2 x g "C": lacks a period. Fixed. MAB 02/04/2008

S "B" is not plausible. The reason in "B" is not tied to conditions that areprovided in the stem. Compare to "A" - where "A" contains a reason thatcorresponds to an alarm that is provided in the stem. To raise theplausibility of"B", the reason needs to be tied to a condition in the stem.Simplified to only tie to high pressure, vice rad inst malfunction. OKMAE 02/04/2008

Page 17 of29

Page 37: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psvchometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q~ SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dist B/W

62 068A4.02 M F 2 S Q is SAT. TIle chosen wording does not appear to be the easiest tointerpret, but the Q is OK if you want to go with the current wording. Ifyou would like your applicants to see this question worded slightlydifferent, I am OK with that too.OK MAB 02/0412008

63 071K3.04 M H 2 S Q is SAT.

64 075G2.2.1 I N H 2 :g Grammar issue in first bullet.Q replaced. OK MAB 02/04/2008

SThe stem of the question is vague with respect to how the design will bechanged. It is implied, that the change will cause the valve toautomatically close. Is it important to state this. Will it be possible for anapplicant to assume a change that would affect the answer choices?Q replaced. OK MAB 02/04/2008

Do you want to ask this question to all RO? Do you have ally RO learningobjectives associated with temp changes? Is this knowledge part of the ROILT program? Discuss with licensee.Q replaced. OK MAB 02/04/2008

If licensee can produce documentation that this is OK to ask an RO, thenthe question is SAT.Q replaced. OK MAB 02/04/2008

65 086AI.OI N F '5. x Y Answer choices need some "the'ts added between "trip" and "pump".Q revised. OK MAB 02/04/2008

SKIA not matched: The KIA requires testing the ability to monitorlpredictchanges in parameters as they relate to operating controls to preventexceeding design limits (fire header pressure). This question only testsknowledge of existence of design features. The question does not test theability to monitor changes in parameters to prevent from exceeding designlimits.Q revised. OK MAE 02/04/2008

66 G2.I.3 N F 2 S Question is written as a ''NOT'' question, which is discouraged by theNUREG. I will allow this format if the licensee does not have an issuewith presenting the question to the applicants in this format.Noted. MAB 02/04/2008

Repeated the word "during" in the stem. Fixed. MAE 02/0412008

67 G2.I.27 B H 2 S Third bullet: "start" should be plural. Fixed. MAB 02/04/2008

Page 18 of29

Page 38: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KiA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q- SRO E ExplanationN K D Focns Cred Cred KiA Only S

Dist Dist B/W

Fourth bullet: "level" should be plural. Fixed. MAB 02/04/2008

Be consistent with tense in all answer choices. Consider:A. Arming conditions for AMSAC were not present.B. AMSAC actuated.C. Arming conditions were present, but actuation conditions were

not present.D. AMSAC has not actuated, but will actuate after the appropriate

time delay if SG levels stabilize at their current values.Fixed. MAB 02/04/2008

68 G2.1.28 M F 2 x .g "C" and "D" plausibility: ERCW pumps are the same type of pumpperforming the same function. If an applicant had a misconception that

S they were both sequenced on the bus, why would it make any differencewhich pump starts first? Are there other pumps in the plant that both getsequenced on a bus and the order of that sequence is determined by aswitch position that is manipulated by the operators? Discuss withlicensee. If there is more plausibility here than I realize, then this questionmay be SAT.Q replaced. OK MAB 02/04/2008

"C' and "D" should have an "in which" added.Q replaced. OK MAB 02/04/2008

The second part of "A" and "C" appears to be a little cryptic. Is this easilyunderstandable?

T Q replaced. OK MAB 02/04/2008

69 G2.2.26 N H 2 S Q is SAT.REF

70 G2.2.33 B H 2 B Is there an extra space between "and" and "the"? Corrected. MAB02/0412008

S"B" is not plausible. With dumps open and rods inserting it is not crediblefor an applicant to have a misconception that temperature will go up.Consider changing the temperature to something lower than 559 F, butplausible. Answer choices changed to iterate on temps and speed. OKMAB 02/04/2008

71 G2.3.2 N H 2 S Q is SAT.

72 G2.3.9 B F 2 S Be consistent with periods behind bullets. Fixed. MAB 02/04/2008

Q is SAT.

73 G2.3.l0 B F I x x x .g "A" is not plausible. If "A" is correct, then any of the others would be

Page 19 of29

Page 39: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q~ SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dist B/W

also. TIle question asks for which would be correct to exit the RCA. If itS is correct to simply exit, then doing anything above and beyond that would

not be wrong. Q replaced. OK MAB 02/04/2008

"B" is not plausible. PCM-IB monitors alarm quite often. Can youimagine how many whole body counts would be needed if this were true?How many times have these applicants had a PCM-IB alarm?Q replaced. OK MAB 02/04/2008

This question does not discriminate at the appropriate level. An ROapplicant getting tins question correct does not provide useful informationin making a license decision. Q replaced. OK MAB 02/04/2008

74 G2.4.16 B H 2 S Typo in "D": E-O? vice E-O. Fixed. MAB 02/04/2008

Typo "D": should "exist" be plural? Licensee failed to correct. It does notaffect tec1micalaccuracy of question. I would make them change it if itappeared only in a distractor. OK MAB 02/04/2008

This question looks very familiar. No response needed from licensee - Iam just noting this. Noted. MAB 02/04/2008

75 02.4.22 N F 2 S Why is "Larger" capitalized in "A' and "D"? Corrected. MAB02/04/2008

SROEXAM76 008G2.4.49 NJH 2 II "C": Is there an extra space between "and" and "immediately"?

~ Q and KIA changed. OK MAB 02/04/2008

S "D": Is there an extra space between "in" and "E-O"?Q and KIA changed. OK MAB 02/04/2008

What pressure causes phase B to actuate?Would it be incorrect for the SRO to direct starting of the EDG? Is this anautomatic action that should have occurred? Does SQ have all Adminprocedure that states that it is permissible to manually perform an autoaction that should have occurred?Q and KIA changed. OK MAB 02/04/2008

If this question is determined to require knowledge of procedure selection,i.e. beyond general rules of procedure usage, then it will be acceptable asan SRO question. Discuss SRO-only learning objectives that may beavailable to support this question as SRO only.Q and KIA changed. OK MAB 02/04/2008

It is my knowledge that a general Westinghouse rule of usage is that

Page 20 of29

Page 40: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dist BIW

operators do not exit E-O until E-O instructs them to exit. I would view thisas RO knowledge unless there is some plant documentation that wouldstate otherwise.Q and KiA changed. OK MAB 02/04/2008

77 029EA2.09 M H 2 x Y Discuss deleting parameters at the time of transition. They do not addplausibility to "turbine not tripped"; therefore, they may not be necessary

S information.PRT values deleted. OK MAB 02/04/2008

Change feed water flow to something that is just over the limit. Like 120gpm to each SG. Heat sink requirements are 440 gpm total. Discuss withlicensee.FW flow values revised. OK MAB 02/0412008

Not SRO-only: ROs are required to know status trees. Therefore, thequestion can be answered by knowing that H.l is not required to be enteredand that the turbine is tripped. Both of these knowledge items are requiredRO-knowledge.(G2.4.21 has an RO importance rating of 3.7)Q revised. OK MAB 02/04/2008

78 054AA2.05 N H 2 x Y Not SRO-only: Question requires systems knowledge for response of theMFW B/P Reg Valve, which is RO knowledge. Question also requires

S knowledge of AOP and EOP entry conditions, which is also ROknowledge. Furthermore, the applicant can use systems knowledge to

I determine that the reactor will not trip and that not SI is present, thereby,allowing the applicant to eliminate going to E-O, "Reactor Trip or SafetyInjection."(2.4.1 and 2.4.4 have RO importance ratings of 4.3 and 4.0 respectively)Q revised to make SRO only. OK MAB 02/04/2008

Are the applicants required to go to the AOP? Would an operator bewrong if the AOP was not entered?Q revised. OK MAB 02/04/2008

79 057AA2.17 N H 2 x y Is punctuation in second bullet correct?Q revised. OK MAB 02/04/2008

SNot SRO-only: Both parts of the answer choices can be analyzed usingRO required knowledge. Systems knowledge is required by ROs;therefore, this question does no require any knowledge that is specific onlyto the SRO position.Q revised. OK MAB 02/04/2008

80 065AA2.01 N H 2 E Wording on LCO 3.0.3 is too loose. LeO 3.0.3 is always applicable and

Page 21 of29

Page 41: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KiA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KiA Only S

Dist Dist BIW

licensees are always required to comply with 3.0.3. Change the wordingS to: Required Actions ofLCO 3.0.3 are required to be performed, OR not

required to be performed. This will not change the meaning of what isbeing asked, but it will be more direct and more technically correct tophrase the second part of each answer choice in this manner.Incorporated. MAB 02/04/2008

Delete the air pressure in the stem. The ala1111 annunciates, which isenough to inform the operator that pressure is below 68 psig. Discuss withlicensee. Allowed air pressure to remain. OK MAB 02/0412008

The piece of each answer choice that discusses that fuel movement isrequired to be suspended does not add value since it is the same in eachanswer choice. The answer choices should only contain the informationneeded to make them unique answer choices:

A. ABGTS Train A remains OPERABLE until Train AContainment Air Isolation Valve automatically closes, at whichtime LCO 3.0.3 required actions would NOT be required to betaken.

B. ABGTS Train A remains OPERABLE until Train AContainment Air Isolation Valve automatically closes, at whichtime LCO 3.0.3 required actions would be required to be taken.

C. Both trains of ABGTS would immediately be INOPERABLEwith the current conditions. LCO 3.0.3 required actions wouldNOT be required to be taken.

D. Both trains of ABGTS would immediately be INOPERABLEwith the current conditions. LCO 3.0.3 required actions wouldbe required to be taken

Incorporated. OK MAB 02/04/2008

81 W/Ell B H I- x X? B Be consistent with punctuation after bulleted items. Fixed. MABG2.4.48 2 02/04/2008

STransfer to RHR containment sump is not plausible. The stem clearlystates that a LOCA Outside Containment is occurring. This distractor mustbe replaced. Corrected. OK MAB 02/04/2008

Is there a way to provide some indications in the stem that are indicative ofa LOCA outside containment without telling them that the operators are inECA-1.2 due to a WCA in the Aux Bid. Is there a less obvious way toprovide indications of abnormal radiation in the aux building - i.e. andala1111? Containment sump level added. OK MAB 02/04/2008

The easiest fix for this question may be to use the two best answer choicesand then iterate on operator actions, etc. I.E. Iterate on ECA 1.I and E- IAND then operator actions. Incorporated. MAB 02/04/2008

Page 22 of29

Page 42: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues TIF 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dis! B/W

-Another possible fix may be to test procedure path for two transitions.Operators would go to ECA-I.I, then to ...Distractors revised. OK MAB 02/0412008

82 W/EI2 B H 2 x E Questions testing knowledge of what operators "should" do are tooG2.I.32 ambiguous to ask. Questions must ask what operators are required to do.

S This may just be a phrasing issue with the question statement, butquestions need to test requirements.Corrected. OK MAB 02/0412008

Distractor "B": Not plausible because there is not a crediblemisconception that could lead an applicant to stop terminating SI butremain in the same procedure. At least with the procedure transition theyneed to evaluate if they are to stop the SI termination in order to make thetransition. Corrected. MAB 02/04/2008

Modify the stem slightly to place the operators at Step 14 where they aremonitoring for SI termination criteria and provide them the criteria that areindicative of them proceeding to step 15. Answer choices could besomething like:

A. Terminate SI in ECA-2. I, then transition to E-2B. Transition to E-2, then terminate SIC. Remain in ECA-2. I. SI termination criteria are not currently

met.D. Transition to E-2, SI termination criteria are not currently met.

Discuss this option with licensee.Incorporated. OK MAB 02/04/2008

83 003G2.2.22 N F I x x .y Can the stem state that the control rod drops to the middle of the core?Otherwise, a rod dropping to the bottom makes "B" non-plausible because

S there would not be any axial concerns for a rod that falls to the bottom.Added. OK MAB 02/04/2008

"D" is a correct statement and could successfully be argued as correct byan applicant. The accident analysis will remain valid at 75% power.Corrected. MAB 02/0412008

Is there a more specific option to use for "A"? Any reactivity 1 powerredistribution issue is going to be a fuel integrity concern."A" allowed to remain. OK MAB 02/04/2008

A more specific choice for "A" and replacement of"D" could result in asatisfactory question. "D" revised and "A" allowed to remain with theother changes made to the question. OK MAB 0210412008

Page 23 of29

Page 43: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KiA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KiA Ouly S

Dist Dist B/W

84 005AA2.03 N H 2 X X .y Delete "causing a runback from the stem". Applicants should haveenough information with the plant at 86% and a MFP trip to understand

S that a runback will occur. Discuss with licensee to ensure that this is thecase.Deleted. OK MAB 02/04/2008

Is second bullet worded corrected?Corrected. MAB 02/04/2008

Not SRO-only knowledge: ROs are required to know reactor trip criteria.Q revised and allowed for SRO due to location of trip criteria. MAB02/04/2008

Is "D" a subset of "C"? Is (ripping the reactor a means of removing theUnit from service within 6 hours? This may be able to be alleviated bychanging the wording of the question to ask for the specific requirementsas stated in AOP-C.OI. Corrected. MAB 02/0412008

85 051AA2.02 M H 2 X .y Is second bullet worded correctly? Corrected. MAB 02/04/2008

S Delete all unnecessary information in answer choices. In other words,delete the information that is not needed to make the answer choicesunique. All of the extraneous procedure entry information is not needed tomake the answer choice unique. I.E.:

A. Manual turbine trip criteria is currently met.B. Manual reactor trip criteria is currently met.C. Manual turbine trip criteria will be met if condenser pressure

I exceeds 2.7 psia and cannot be restored within 5 minutes.D. Manual turbine trip criteria will be met ifcondenser pressure

exceeds 2.7 psia and cannot be restored within 5 minutes.Extra info deleted from answer choices. MAB 02/0412008

Question should be worded in the plural fonn. Currently it is worded forsingular (or plural), but each answer choice has more than one item.Corrected. MAB 02/0412008

Not SRO-only: Reactor Trip criteria is RO knowledge. The abovecomments will be irrelevant unless the SRO-only issue is corrected.(G2.1.7 and G2.4.l have RO IRs of3.7 and 4.3 respectively)Allowed for SRO exam due to knowledge of being able to stay in AOP toaddress vacuum problem for 5 minutes. MAB 02/04/2008

86 W/E02 N H I x .y Should "Safety" be capitalized in second bullet? "Injection" is also nowEA2.2 capitalized. OK MAB 02/04/2008

S"B" and "D": This reviewer does not understand how the conditions in the

Page 24 of29

Page 44: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psychometric Flaws Content Flaws V CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q~ SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dist B/W

stem result in LCO 3.0.3 being plausible. There is not a reasonablemisconception that would lead an applicant to thinking that LCO 3.0.3.Corrected. MAB 02/04/2008

"C" and "0": Nothing has really occurred in the stem except for aninadvertent SI. There is no reasonable misconception that would lead anapplicant to E-I for a LOCA.Condition in the stem revised and distractors changed. OK.MAB02/04/2008

TIle lack of plausibility in the distractors results in an LOD= I, which doesnot allow this question to discriminate between a competent and less thancompetent SRO. Q revised to bring to acceptable level. OK MAB02/0412008

87 W/EI6 M H 2 x B Can "The reactor is in Mode 6 with" be deleted from first bullet?G2.2.31 2 Deleted. MAB 02/0412008

S Not SRO-only: ROs are licensed to move fuel and therefore are requiredto know how to handle a loss ofrefueling water event. TIns is snpportedby KIA 036AAI.04, which has an RO IR of 3.7. Lowering water level is afuel handling incident, which is supported by AOP-M.04, RefuelingMalfunctions. See comment below. OK MAB 02/0412008

This was a modified question. TIle reviewer would like to see a copy ofthe source question, from which this one was modified. Provided. MAB02/0412008

Do ROs currently move fuel at SQ? Ifnot, when was the last time an ROmoved irradiated fuel at SQ? Is there an SRO-only leaming objective tosupport tins being SRO-only knowledge? Based on the above reasoningtins falls into the category of an RO question; however, if sufficientjustification can be provided it may be permissible to allow this on theSRO exam.Licensee provided sufficient justification for SRO only level. MAB02/04/2008

88 008A2.09 M H 2 x :y Reactor Physics and systems knowledge are the only requirements foranswering this question. Plant response to a controller failure is systems

S knowledge that is required of an RO. Determining whether a temp changeadds positive or negative reactivity is basic GFE reactor physicsknowledge. This question can be answered only by knowing GFEknowledge. No SRO-only knowledge is required to answer this question.Q replaced. OK MAB 02/04/2008

89 0IOG2.4.38 N F I x :y "A" and "0": 5 minutes is not plausible. Leading to a LOD I.

Page 25 of29

Page 45: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psvchometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dist B/W

Q revised to address concern. OK MAE 02/0412008S

Question LOD would be acceptable if the acceptable ODS notificationrequirement is tested, instead of the 15 minute to declare. Test whether therequirement to notify ODS is 5 minutes from the event or 5 minutes frommaking the declaration. This will test knowledge of whether the ODSnotification is required to be made prior to or after event declaration.Incorporated. OK MAB 02/0412008

90 013A2.05 N H 2 x Y Question is not SRO-only: Can this question be answered using onlysystems knowledge? The first piece of each answer choice can be

S answered by knowing what the cause of the condition could be, which issystems knowledge. This limits the potential answer choices to "C" and"D" using RO knowledge. Applicants can also determine that the pumpswill not start manually based on the physical configuration of the plant, I.E.systems knowledge. Therefore, this question can be answered by anapplicant without needing to use any SRO-only level knowledge.Concerns addressed. Distractors and stem revised. OK MAB 02/04/2008

91 103G2.2.l4 N F 2 S Tie the second half of the question to the procedure just as you did withwhen Containment Closure Control is required to be implemented. I.E.. . .who will maintain the listing of the Containment Closure Exceptions ineffect in accordance with 0-GO-15.Incorporated, MAB 02/04/2008

92 029G2.4.46 N H 3 x x? E Question is backward logic. This is discouraged by NUREG-I 021;, :1 however, it is not prohibited. Licensee does not need to address this

comment if they are satisfied with their applicants receiving this question.S Noted. MAB 02/04/2008

Can "B" be eliminated using systems knowledge? Will ABI result in anauto shutdown of Unit I containment purge when ORA-90-10IA alarmswith Unit I Lower Containment Purge in progress? Discuss with licensee.This will determine the status of the question.ABI will not auto SID UI purge. After discussion with licensee, Q is OK.MAB 02/0412008

93 034A2.02 N F 2 x E "B": Rad Control Manager is not plausible because this is not an irradiatedfuel bundle. Contamination and exposure should not be a concern.

S Fixed. MAB 02/0412008

Consider the following changes:. Per AOP-M.04, which one of the following correctly describes the

lowest level of approval required for approval of recovery instructions?A. Refueling SROB. Shift Manager

Page 26 of29

Page 46: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KlA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cnes T/F 1 Non >1 Non Partial Min Q~ SRO E ExplanationN K D Focus Cred Cred KIA Only S

Dist Dist B/W

C. Operations ManagerD. Plant Manager

Incorporated. OK MAB 02/04/2008

94 G2.1.12 N H 2 S Is second bullet worded correctly? Fixed. MAB 02/04/2008

REF Be consistent with periods after bullets. Fixed. MAB 02/04/2008

95 G2.1.33 N H 2 x :y KIA Match: The KIA requires that tech spec entry conditions are tested.This question skips that part and then tests the actions that are required

S once the tech spec is entered.Q revised. OK MAB 02/0412008

TIle stem does not even state that fuel is being moved; therefore, stoppingfuel movement does not appear like a reasonable answer.Answer choices revised. OK MAB 02/05/2008

Question is disjointed. "A" and "B" are testing knowledge of mode changerequirements and "C" and "D' are testing knowledge of fuel movementrequirements. This is not the reason the question is unsat, but simply anobservation.Answer choices revised. OK MAB 02/0512008

96 G2.2.8 B F 2 .g Consider wording the Q as follows:Which one of the following correctly describes the MINIMUM required

S qualifications for the person(s) PREPARING the safety evaluation

Ipaperwork in accordance with SPP-9.4, IOCFR50.59 Evaluations ofChanges, Tests, and Experiments?Incorporated. OK MAB 02/0512008

97 G2.3.l B H 2 .g The topic and construction of the question is satisfactory, There areconcems with the wording of the "Why" column choice for "A" and "B".

S Where is "maintain critical safety function" defined? Would it be wrongfor an applicant to believe that the emergency exposure would be needed toprevent the conditions from elevating beyond Yellow? Discuss withlicensee.Q replaced. OK MAB 02/05/2008

98 G2.3.6 M F 2 x .g Tie the question to the procedure, I.E.: Which one ofthe following . ....in accordance with "procedure name and number"?

S Incorporated. OK MAB 02/05/2008

Be a little more precise with the first piece of each answer choice. I.E.Approval not permitted. I Approval is permitted.The above suggestion is a little more accurate because the SRO could justchoose to not sign it, which is neither disapproving or approving. The

Page 27 of29

Page 47: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KiA# B L L Psychometric Flaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q= SRO E ExplanationN K D Focus Cred Cred KiA Only S

Dist Dist BIW

above wording covers all cases and speaks directly to the procedurerequirement.Incorporated. OK MAB 02/05/2008

Delete the last piece of"D": ", but dilution flow requirements are raiseddue to the higher activity." This really does not add to plausibility becauseit is not needed to make the answer choice unique. If an applicant knowswhether the SM is required to approve, then this extraneous information isnot meaningful.Incorporated. OK MAB 02/05/2008

"B" is not plausible only because of the verbiage. There may be someimproper grammar, which is easily fixed. I.E.:

B. Approval not permitted. Cannot release monitor tank until 0-RM-90-122 has been retnmed to OPERABLE status.

Incorporated. OK MAB 02/05/2008

What does "two independent discharge valve lineups" mean? Wordingmust be precise and reflect exactly what the procedures require. Do twolineups need to be performed? Is one lineup performed and then it isindependently verified?Answer choices modified. OK MAB 02/05/2008

ODCM states that two qualified staff members independently verifyrelease rate calculations. The answer choices in the questions states that 2release rate calculations are verified. I am not sure that these requirements,as stated, are exactly the same. Discuss with licensee.

, Answer choices modified. OK MAB 02/05/2008

99 G2.4.9 B H 2 x x lei Not SRO-only: Knowing how to recognize pump cavitation and theactions to take to mitigate the cavitation is RO required knowledge.

S Knowing that dilution is not permitted is also RO required knowledge.All I hour and less tech specs are RO knowledge.Equipment protection actions are also RO knowledge.Through discussion with licensee, CE allowed Q to remain. OK MAB0210512008

There are also plausibility concerns with taking suction from VCT withboron too low. This point is inconsequential due to the question not beingwritten at the SRO level.Through discussion with licensee, CE allowed distractors to remain. OKMAB 02/05/2008

100 G2.4.49 N H 2 x lei "Shutdown Boards Energized" is not an action, it is a statement of fact. -Similar comment for "Safety Injection Actuated".

S Qreplaced. OK MAB 02/05/2008

Page 28 of29

Page 48: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-401, Rev. 9 Written Exam Review WorksheetSequoyah 2008-301

Form ES-401-9

Q# KiA# B L L PsychometricFlaws Content Flaws U CommentM 0 0 Stem Cues T/F 1 Non >1 Non Partial Min Q~ SRO E ExplanationN K D Focus Cred Cred KiA Only S

Dist Dist B/W

Not SRO-only: Knowing whether the status of the reactor and turbine issystems knowledge, which is a required RO knowledge item. Knowingthat upon a reactor trip that E-Ois entered is an RO knowledge item. Thisis all that is needed to arrive at the correct answer.Q revised/replaced to test SRO-only knowledge. OK MAB 02/05/2008

Page 29 of29

Page 49: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES-403 Written Examination GradingQuality Checklist

Form ES-403-1

Facility: ~E('OUD\(MA Date of Exam: OJJoO~B Exam Level: ROIl SRolro

Initials

Item Description a b c

1. Clean answer sheets copied before grading 1JK. NfIJ Ifff32. Answer key changes and question deletions justified ?Jk. flJIA f}$and documented

3. Applicants' scores checked for addition errors sc ~ ~(reviewers spot check> 25% of examinations) A4. Grading for all borderline cases (80 ±2% overall and 70 or 80, ?1H. I'k m>as applicable, ±4% on the SRO-only) reviewed in detail /~

5. All other failing examinations checked to ensure that grades ~ I~ rrfJare iustified

6. Performance on missed questions checked for training~ ~ n'1Odeficiencies and wording problems; evaluate validity .~

of Questions missed by half or more of the applicants

Printed Name/Signature Date

a. Grader ~R.\AN{) ~~1§.UdtL z/I er!fJtb. Facility Reviewer(*) N)A . N;/4

c. NRC Chief Examiner (*) M"", A,B~I;3,1//2i/}£tp r:~I.l..ItJ.//J06'el

d. NRC Supervisor (*) /l.)jJ..UJJLJJ T lVfDj,).AA/A/ / !1iJjJAfJft~ ozl'l/ItJ?

r } {

(*) The facility reviewer's signature is not applicable for ex~ations graded by the NRC;two independent NRC reviews are required.

ES-403, Page 6 of 6

Page 50: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ES·S01 Post-Examination Check Sheet Form ES-S01-1

Post-Examination Check Sheet

Facility: Sf::: (QU 0 \{ Vt If Date of Examination: -:Yt~u.e.,•.'( 0<005

Task Description Date Complete

1. Facility written exam comments or graded exams received ();;' /Itt!JDG ~and verified complete

2. Facility written exam comments reviewed and incorporated()J. /1'-/ J;)C'Cf C;;and NRC grading completed, if necessary

3. Operating tests graded by NRC examiners O?- ) ILl) Jtr/?

4. NRC chief examiner review of operating test and written examOJ!!41;}or/~grading completed

5. Responsible supervisor review completed O;Z I;{d;)C)O C?

6. Management (licensing official) review completed o,,:2/;;q IJc;l1}~

7. License and denial letters mailed o2);) JdtJ{)~

8. Facility notified of results o ;;;./~ J/?CJJ'?,

jJ:i9. Examination report issued (refer to NRC MC 0612) os .' :<oeJg'10. Reference material returned after final resolution of any appeals Aliff

ES-501, Page 23 of 25

Page 51: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

Tennessee Valley Authority, Post Office Box 2000, Soddy-Daisy, Tennessee 37384-2000

Confidential information submittedunder 10 CFR 2.390

February 13, 2008

10 CFR 55.40Dr. William D. TraversRegional Administrator, Region IIU.S. Nuclear Regulatory CommissionSam Nunn Atlanta Federal Center61 Forsyth Street, SW, Suite 23T85Atlanta, Georgia 30323-8931

Attention: Mr. M. T. Widmann

In the Matter ofTennessee Valley Authority (TVA)

Docket Nos. 50-32750-328

SEQUOYAH NUCLEAR PLANT (SQN) - REACTOR AND SENIOR REACTOROPERATOR INITIAL EXAMINATIONS - 05000327/2008301 AND 05000328/2008301

In accordance with Examination Standard (ES) 501, "Initial Post-ExaminationActivities," of NUREG-1021, "Operator Licensing Examination Standards for PowerReactors," SON is providing the following information: written examination, examinationanswer key, ES 401-8, examination cover sheets, seating chart, student answersheets, and student clarifying questions.

In accordance with 10 CFR 55.49, "Integrity of Examinations and Tests," andNUREG-1 021, appropriate measures have been taken to ensure examination integrityand security. The Examination Security Agreement Form ES-201-3 will be providedfollowing the post-examination signatures.

Because of the administratively confidential nature, it is requested that the informationcontained in the enclosure be withheld from public disclosure in accordance with10 CFR 2.390(a)(6). This letter contains no new commitments. If you should have anyquestions, please contact me at (423) 843-7170.

S. inc.e.relY,. JI.. ~_~~Cff-------.~;:::;?'- J

,~ .. '~ames D. SmithManager, Site Licensing and

Industry Affairs

Enclosures

Printed on recycled paper

Page 52: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

Tennessee Valley Authority, Post Office Box 2000, Soddy-Daisy, Tennessee 37384-2000

December 5, 2007

Dr. William D. TraversRegional Administrator, Region IIU.S. Nuclear Regulatory CommissionSam Nunn Atlanta Federal Center61 Forsyth Street, SW, Suite 23T85Atlanta, Georgia 30323-8931

Attention: Mr. M. T. Widmann

In the Matter ofTennessee Valley Authority (TVA)

Docket Nos. 50-32750-328

(

(

SEQUOYAH NUCLEAR PLANT (SQN) - REACTOR AND SENIOR REACTOROPERATOR INITIAL EXAMINATIONS - 05000327/2008301 AND 05000328/2008301

This letter transmits the requested information identified in NRC's letter toWilliam R. Campbell dated August 3,2007, for the examinations to be administrated theweeks of January 28, 2008, and February 4, 2008.

There are no commitments contained in this submittal. In accordance with 10 CFR 55.49and NUREG 1021, "Operator Licensing Examination Standards for Power Reactors,"appropriate measures have been taken to ensure examination integrity and security.Accordingly, it is requested that this letter and the enclosed documents be withheld frompublic disclosure until the examinations are completed.

TVA's principal contact regarding the license examinations is Tom Jones, SON OperationsTraining. Should you require additional information regarding this matter, please contactMr. Jones at (423) 843-4206 or contact me at (423) 843-7170.

Sincerely,

w.?~

James D. SmithManager, Site Licensing and

Industry Affairs

Enclosure

Printed on recycled paper

Page 53: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

(

(

U.S. Nuclear Regulatory CommissionPage 2December 5, 2007

JWP:KTScc: L. E. Nicholson, BR 4X-C

T. D. Wallace, STC 2H-SQNB. A. Wetzel, BR 4X-CEDMS, WT CA-K

The information contained within this document is the Property of the TennesseeValley Authority and has been determined to be sensitive. Any further distribution ofits contents will be on a need to know basis only as determined by the originator ofthe document or the recipient.

SENSITIVE INFORMATION

I:License\Operator license\2007\Requested information IR2008301

Page 54: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

(

(

ENCLOSURE

TENNESSEE VALLEY AUTHORITYSEQUOYAH NUCLEAR PLANT (SQN)

UNITS 1 AND 2

OPERATING EXAMINATIONS FOR REACTOR OPERATOR (RO)AND SENIOR REACTOR OPERATOR (SRO) CANDIDATES

Written Examination - RO and SRO Portions Including Student Reference MaterialQuestion Development Reference Material for RO and SRO Written ExaminationsJob Performance Measures for RO and SRO examinationsFour Simulator examinationsES-201-3 - Examination Security AgreementES-301-2 - Control Room/In-Plant Systems OutlineES-301-3 - Operating Test Quality ChecklistES-301-4 - Simulator Scenario Quality ChecklistES-301-5 - Transient and Event ChecklistES-301-6 - Competencies ChecklistES-401-6 - Written Examination Quality Checklist

Page 55: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

(

Tennessee Valley Authority, Post Office Box 2000, Soddy-Daisy, Tennessee 37384-2000

October 23, 2007

Dr. William D. TraversRegional Administrator, Region IIU.S. Nuclear Regulatory CommissionSam Nunn Atlanta Federal Center61 Forsyth Street, SW, Suite 23T85Atlanta, Georgia 30323-8931

Attention: Mr. M. T. Widmann

In the Matter ofTennessee Valley Authority

Docket Nos. 50-32750-328

(

(

SEQUOYAH NUCLEAR PLANT - REACTOR AND SENIOR REACTOR OPERATORINITIAL EXAMINATIONS - 05000327/2008301 AND 05000328/2008301

As requested by NRC letter to TVA dated August 3,2007, this letter transmits theexamination outlines identified in NRC's letter to William R. Campbell dated August 3,2007, for the examinations to be administrated the weeks of January 28, 2008 andFebruary 4, 2008.

There are no commitments contained in this submittal. In accordance with 10 CFR 55.49and NUREG 1021, "Operator Licensing Examination Standards for Power Reactors,"appropriate measures have been taken to ensure examination integrity and security.Accordingly, it is requested that this letter and the enclosed documents be withheld frompublic disclosure until the examinations are completed.

Please direct questions concerning this issue to me at (423) 843-7170.

~rzJ.~Glenn W. MorrisManager, Site Licensing and

Industry Affairs

Enclosure

Printed on recycled paper

Page 56: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

(

ENCLOSURE

TENNESSEE VALLEY AUTHORITYSEQUOYAH NUCLEAR PLANT (SQN)

UNITS 1 AND 2

The following are included in this enclosure:

License Examination Outlines:

ES-201-2 Examination Outline Quality ChecklistES-201-3 Examination Security AgreementES-301-1 Administrative Topics JPM Outlines for RO and SRO examsES-301-2 Control Room/In-Plant Systems JPM Outlines for RO and SRO examsES-301-5 Transient and Event ChecklistES-D-1 Simulator Scenario Outlines for 4 scenariosES-401-2 and 3 Written Exam Outlines for RO and SRO examsES-401-4 Record of Rejected KlAs for RO and SRO examsWritten Exam development methodology statement

Page 57: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

Tennessee Valley Authority, Post Office Box 2000, Soddy-Daisy, Tennessee 37384-2000

August 15,2007

Dr. William D. TraversRegional Administrator, Region IIU.S. Nuclear Regulatory CommissionSam Nunn Atlanta Federal Center61 Forsyth Street, SW, Suite 23T85Atlanta, Georgia 30323-8931

Attention: Mr. R. C. Haag

In the Matter ofTennessee Valley Authority

Docket Nos. 50-32750-328

( SEQUOYAH NUCLEAR PLANT - REACTOR AND SENIOR REACTOR OPERATORINITIAL EXAMINATIONS - 05000327/2008301 AND 05000328/2008301

As requested by Mark Bates of your staff, this letter transmits the written examinationoutlines identified in NRC's letter to William R. Campbell dated August 3, 2007, for theexaminations to be administrated the week of January 28, 2008.

Due to the administratively confidential nature of the enclosure, it is requested that theinformation contained in the enclosure be withheld from public disclosure until after theexaminations are complete.

Please direct questions concerning this issue to me at (423) 843-7170.

~ZuN.~Glenn W. MorrisManager, Site Licensing and

Industry Affairs

Enclosure

Printed on recycled paper

Page 58: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

(

u.s. Nuclear Regulatory CommissionPage 2August 15, 2007

JWP:KTScc: R. H. Bryan, BR 4X-C

T. D. Wallace, STC 2H-SQNEDMS, WTC A-K

The information contained within this document is the Property of the TennesseeValley Authority and has been determined to be sensitive. Any further distribution ofits contents will be on a need to know basis only as determined by the originator ofthe document or the recipient.

SENSITIVE INFORMATION

I:License\Operator license\2007\Exam outline IR2008301

Page 59: 8. Transient and Event Checklist . 9. Competencies ... · Facility: Sequoyah 1 & 2 Date of Exam: 1/28/2008 Scenario Numbers: 1,2,3,4 Operating Test No.: NRC QUALITATIVE ATTRIBUTES

ENCLOSURE

TENNESSEE VALLEY AUTHORITYSEQUOYAH NUCLEAR PLANT (SQN)

UNITS 1 AND 2

LICENSE WRITTEN EXAMINATION OUTLINES