2
87716 Nangarhar Project Construction Best Practices – Presentation #1 Site grading is the process of adjusting the slope and elevation of the soil around buildings or civil structures. Prior to construction or renovation, site grading may be performed to even out the surface and provide a solid foundation, and at other times, grading may be required to improve drainage and create the desired appearance for landscaping features. Clearing vegetative cover and then grading a site are arguably the most destructive stages in the development process and can dramatically impact pre-existing hydrology. Soils are exposed to erosion, the site is compacted by heavy equipment, and the natural terrain and drainage are completely altered. Civil Works Contractors should maintain as much natural vegetation as possible and limit clearing, grading, and land disturbance activities to the minimum needed for construction, maintenance, and emergency services. UNOPS has a social and professional responsibility to manage all construction works that involve the grading of an area where the slope of the area is to be excavated or filled; the excavation, fill, or rearrangement of earth material on any site; all grading or clearing operations; the excavation or fill of any portion of a site that increases or decreases its elevation following the completion of grading at any point; the diversion of rainwater runoff from an area that is greater than the impervious area threshold for new development; the blockage or alteration of a waterway or drainage way; or the excavation for the installation, removal, or repair of any underground structure. UNOPS JICA IV Project is undertaking building construction works for school and clinic facilities, and the works involve site grading. The project engineering team has to evaluate contractors’ grading plan, including contours and grade elevations for existing and proposed ground surface elevations at each given site. This is a UNOPS JICA IV PowerPoint presentation explaining of the following: Site Grading – Definition, Methods and Challenges and Recommendation for Best Practices UNOCA Compound Jalalabad Road P.O. Box 1772, Central Post Office Kabul, Afghanistan Email [email protected] | T +93 799295393 | www.unops.org | UNOPS is ISO 9001 Certified

87716 Nangarhar Project Construction Best Practices Presentation #1 - 8 Jun 15

Embed Size (px)

DESCRIPTION

construction best practices

Citation preview

87716 Nangarhar Project Construction Best Practices Presentation #1

Site grading is the process of adjusting the slope and elevation of the soil around buildings or civil structures. Prior to construction or renovation, site grading may be performed to even out the surface and provide a solid foundation, and at other times, grading may be required to improve drainage and create the desired appearance for landscaping features.

Clearing vegetative cover and then grading a site are arguably the most destructive stages in the development process and can dramatically impact pre-existing hydrology. Soils are exposed to erosion, the site is compacted by heavy equipment, and the natural terrain and drainage are completely altered. Civil Works Contractors should maintain as much natural vegetation as possible and limit clearing, grading, and land disturbance activities to the minimum needed for construction, maintenance, and emergency services.

UNOPS has a social and professional responsibility to manage all construction works that involve the grading of an area where the slope of the area is to be excavated or filled; the excavation, fill, or rearrangement of earth material on any site; all grading or clearing operations; the excavation or fill of any portion of a site that increases or decreases its elevation following the completion of grading at any point; the diversion of rainwater runoff from an area that is greater than the impervious area threshold for new development; the blockage or alteration of a waterway or drainage way; or the excavation for the installation, removal, or repair of any underground structure.

UNOPS JICA IV Project is undertaking building construction works for school and clinic facilities, and the works involve site grading. The project engineering team has to evaluate contractors grading plan, including contours and grade elevations for existing and proposed ground surface elevations at each given site.

This is a UNOPS JICA IV PowerPoint presentation explaining of the following:

Site Grading Definition, Methods and Challenges and Recommendation for Best Practices

Presentation topics:

1) Key Words used in the presentation

2) Key terminology or definition to understand the presentation

3) Site Grading definition, purpose and process or techniques

4) Requirement information before site grading design

5) Requirement information after site grading construction works

6) Equipment used in site grading

7) Site grading techniques or methods used in JICA IV works

8) Implementing site grading works in JICA IV process and roles/responsibilities

9) Challenges applying site grading techniques in JICA IV subproject sites

10) Recommendations for best practices in site grading for building construction works

UNOCA Compound Jalalabad Road P.O. Box 1772, Central Post Office Kabul, Afghanistan

Email [email protected] | T +93 799295393 | www.unops.org | UNOPS is ISO 9001 Certified

AFGHAN I STAN