Section 9 SANITARY WARES
9.1 STANDARDS OF CONSTRUCTION
Refer to Clause 1.1.1 of section 1- preliminaries, which applies to this section. All materials and
workmanship shall comply with design requirements
9.2 NON-CONFORMANCE WITH STANDARDS
Refer to clause 1.1.2 of section 1- preliminaries, which applies to this section.
9.3 REQUIREMENTS FOR ACCEPTANCE
9.3.1 Inspection of the work
The Contractor shall demonstrate that he has checked the installed work before notifying
Engineer to inspect. The method of checking shall be to Engineers satisfaction.
Comply with Engineers inspections to meet requirements for acceptance at the following stages;
a. Approval of items at delivery inspections
b. Approval workmanship at in-process inspections
9.3.2 Sample room
The Engineer will nominate one room at the project that shall be used to establish the samples for
the sanitary wares. Engineers acceptance of the samples will be the standard on which
subsequent materials and installation is based.
9.3.3 Hand-over documents
Refer to clause 1.1.3 of section 1- preliminaries, which applies to this section. Submit documents
required by The Relevant Authorities in Vietnamese language, and documents required by
Engineer in English language.
9.4 MATERIALS
9.4.1 The Engineer has based certain of his sanitary wares at the supply unit rates stated
hereinbelow. The contractor shall submit sufficient samples of the various sanitary
wares for the Engineers approval. In the event that the contractors samples are
rejected, at the sole discretion of the Engineer, the Engineer reserves the right to select
the sanitary wares from his sources at the supply unit rates as stated hereinbelow.
Contractor shall then purchase the said sanitary wares for their construction works.
Contractor shall be deemed to have applied the same supply unit rates as hereinbelow
stated (and the quantities involved in this project) in his tender sum and there shall be
no variation to the Contract and no additional cost shall be payable to the Contractor.
Contractor shall note that the supply unit prices stated are nett and that he shall allow
for all damages, breakage, pilferage, wastages, suppliers payment terms and delivery
terms and all other costs involved which the contractor deems appropriate, in his
tender sum and there shall be no variation to the contract and no additional cost shallbe payable to the contractor. Contractor shall price accordingly. Only if there is a
difference between the actual nett supply price (i.e. after all discounts etc) and the
supply unit price stated hereinbelow, the nett difference shall be a variation addition or
omission to the contract sum as the case may be and the contract sum shall be adjusted
accordingly.
Contractor shall be fully aware that he shall include the installation of the sanitary
wares in his tender sum.
S/No Item Supply Unit Price***
1 WC (Water Closet) US $120.00 per set
2 Basin US $40.00 per set
*** The supply unit rates are stated in United States of America Dollars. The contractor shall convert as
necessary to Vietnam Dong.
8/10/2019 9 1SA9A-Sanitary Wares
2/2
SA9-SANITARYWARE
S/No Item Supply Unit Price***
3 Urinals US $40.00 per set
4 Basin taps US $15.00per set
5
6 Toilet roll holder US $5.00. per set7 Shower US $20.00 per set
*** The supply unit rates are stated in United States of America Dollars. The contractor shall convert as
necessary to Vietnam Dong.
9.4.2 For sanitary wares not stated above but shown in the drawings or indicated elsewhere
in the tender/contract documents, Contractor shall be deemed to have priced for those
sanitary wares in his tender /contract sum. Contractor shall carefully study the contract
documents and drawings and price accordingly.
9.5 FINAL INSPECTION AND HAND-OVER
When the sanitary wares installation is completed and has been agreed to be handed over, the
Contractor shall, at the time of the joint inspection, submit to Engineer the following documents,
certificates, and records of the Works completed;
a. Copy of approved shop drawings and samples of full-scale assemblies
b. Copy of in-progress inspection records
c. Copy of suppliers warranty for the sanitary wares
d. Copy of non-conformances and approved corrective action