ISO 9001 System Implementation Plan
Activity Responsibility Days Jan Feb Mar1 Develop a quality manual Cons/Comp 22 Review existing systems and procedures Cons/Comp 0.5
3 Cons/Comp 1
4 Cons/Comp 0.5
5 Cons/Comp 2
6 Cons 1.5
7 Cons/Comp 18 3rd party document review Cert 1
9 Cons 0.510 Implementation of systems/procedures Comp -
11 Cons/Comp 212 Perform a pre-assessment audit Cons 113 3rd party assessment Cert 1
Important note: all days shown are approximate and may vary dependent upon client involvementSome of the days shown are not part of the projected consultancy days e.g. 3rd party assessmentThe above plan is a broad estimate and will have to be fine tuned once implementation is under way.
Cons = consultantComp = companyCert = certification body
Produce a process map of the main business processes and a quality policy
Review applicable statutory and regulatory requirements
Develop/modify process based procedures /flowcharts for main activities
Develop procedures/flowcharts for mandatory activities e.g. internal auditing
Train man rep in ISO 9001 and internal auditing
Train remaining staff in awareness and use of the system
Conduct internal audits and a management review
Responsibilities Key: