62
December 2015 Himdhara Environment Research and Action Collective Palampur, Himachal Pradesh [email protected] www.himdhara.org

A CASE FOR URGENTLY ASSESSING IMPACT OF DRILLING AND BLASTING FOR CONSTRUCTION … · 2017. 3. 4. · The Drill and blast method (DBM) is the conventional tunneling method in hard

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

  • December 2015

    Himdhara Environment Research and Action Collective Palampur, Himachal Pradesh

    [email protected] www.himdhara.org

    mailto:[email protected]

  • A CASE FOR URGENTLY ASSESSING IMPACT OF DRILLING AND

    BLASTING FOR CONSTRUCTION OF TUNNELS AND ROADS IN

    HIMACHAL

    Himdhara, Environment Research and Action Collective

    I. Hydropower Development in Himachal using Run-of-the-River Technology

    Himachal Pradesh is the largest producer of Hydropower in India. The state has already

    installed 9433 MW worth of projects (a total of 53 large, medium and small projects and

    several micro-hydels). It is is planning to harness a total 27436 MW1 of power from the

    five major river basins of the state namely Satluj, Chenab, Ravi, Beas and Yamuna. The

    Satluj river basin alone has a planned potential of 13,332 MW. Projects with a capacity of

    3490 MW are under construction, 2623 MW are under various stages of clearance and

    another 121 MW are under investigation (planning).

    It is thus clear that the magnitude of Hydropower Projects construction in the state is

    large.

    The Hydropower development that is being undertaken in Himachal and the entire

    Himalayan region of India is based on the Run-of-the-river technology which produces

    electricity by checking and diverting river flow. The diverted water is made to flow

    through underground tunnels in the mountains and released downstream on the turbines

    that spin generators before returning the water back to the river. It is important to note

    that the projects using this technology are being built in a cascade form on a river basin.

    This means that at the tail of one project, the head of the next is located.

    It is critical to note that a series of these projects are being built bumper to bumper on the

    streams and rivers to harness the capacity of the rivers to produce power to its maximum.

    Use of the Drill and Blast Method of Underground Tunneling

    The construction of Hydropower projects using the ROR technology involves surface as

    well as underground construction. The surface construction consists of high concrete

    gravity dam, roads, power house, colony and labour camps etc. The underground civil

    works for the ROR projects are an extremely critical and substantial component. The

    typical underground construction has the following components:

    A headrace tunnel (These tunnels are large enough to allow the passage of heavy vehicles. A Head race tunnel can be upto 9 to 10 m diametres.)

    A surge shaft

    Underground powerhouse

    Underground transformer hall

    1 �Economic Survey of the State of Himachal Pradesh 2014

  • Tailrace tunnel

    Desilting chambers

    Adit Tunnels (access tunnels)

    In the Satluj River Basin alone the total length of tunnels once all the planned

    hydroprojects are built will be 185 kms. If all the planned projects in Himachal and

    across the Himalayas are constructed there will be hundreds of kilometres of tunnels

    underneath the mountains in this region.

    The Drill and blast method (DBM) is the conventional tunneling method in hard rock and

    is being used in the hydropower construction across Himachal. In this method excavation

    is achieved by drilling a predetermined pattern of holes in the rock face, filling these

    holes with explosives, which are then discharged to crack and fracture the rock. Loosened

    debris is removed and the tunnel is secured.

    II. Blast induced vibrations and slope destabilisation

    It is important to note that local people, environmentalists and experts have been raising

    concerns with regard to the the blast induced vibrations caused by the use of the DBM for

    tunneling and their geological and ecological impacts.

    (A) In Himachal Pradesh a series of occurances of slope destabilisation have been seen

    over the past few years in areas where construction work involving DBM for

    underground tunneling or for roads. The most evident impacts of these have been:

    - Seepages and leakages in tunnels

    - Land Slides

    - Damages to Houses

    Given below is an audio-visual documentation of a series of events of slope

    destabilisation, caving in, collapse in the Ravi and Satluj valleys in the year 2014-15.

  • IMAGE 1

    Project Chamera III HEP

    Capacity (MW) 231

    Basin Ravi

    District Chamba

    Village Mokhr

    GPS Co-ordinates N 31° 01’ 18.2” E 76° 37’58.1”

    Picture was taken on 29/04/2014

    Elevation 1263 m

    Remarks In April 2012, there was a massive leakage in the 16km HRT of the

    Chamera III project just above the Mokhar village leading to severe

    threat to the village downhill so much so that the 40 families residing

    there had to be evacuated. This picture is of Adit 6 of the tunnel. The

    leakage occurred during testing of the generating units.

    News reports http://www.jagran.com/news/state-10802084.html

    http://www.jagran.com/news/state-10802084.html

    http://www.tribuneindia.com/2012/20120418/himplus.htm#2

    http://www.jagran.com/news/state-10802084.htmlhttp://www.jagran.com/news/state-10802084.htmlhttp://www.tribuneindia.com/2012/20120418/himplus.htm#2

  • IMAGE 2

    Project Chamera III HEP

    Capacity (MW) 231

    Basin Ravi

    District Chamba

    Village Mokhr

    GPS Co-ordinates N 31° 01’18.2” E 76° 37’54.1”

    Elevation 1361 m

    Picture were taken on 29/04/2014

    Remarks Leakages in the surge shaft of the Chamera III tunnel just above

    Mokhar village.

  • IMAGE 3

    Project Chamera III HEP

    Capacity (MW) 231

    Basin Ravi

    District Chamba

    Village Mokhar

    GPS Co-ordinates N 32° 28’54.7” E 76° 17’18.1”

    Elevation 1213 m

    Picture were taken on 29/04/2014

    Remarks Vidya Devi’s house in Mokhar was completely damaged by the

    landslide caused due to the seepage from the surge shaft in April 2012.

  • IMAGE 4

    Project Chamera III HEP

    Capacity (MW) 231

    Basin Ravi

    District Chamba

    Village Mokhr

    GPS Co-ordinates N 32° 28’53.7” E 76° 17’15.7”

    Elevation 1202 m

    Picture were taken on 29/04/2014

    Remarks Shri Jagdish Sharma standing in front of the debris of his leftover house

    after the leakage tragedy .

  • IMAGE 5

    Project Chamera III HEP

    Capacity (MW) 231

    Basin Ravi

    District Chamba

    Village Mokhr

    GPS Co-ordinates N 31° 01’18.2” E 76° 37’54.1”

    Elevation 1361 m

    Picture were taken on 29/04/2014

    Remarks The pastures of the village buried under the landslide caused by

    seepages.

  • Damages caused to houses in Mokhar village due to leakages in the HRT

  • IMAGE 6

    Project Chanju HEP

    Capacity (MW) 36

    Basin Ravi (Chanju Nallah)

    District Chamba

    Village Dhalanjan

    GPS Co-ordinates N 32° 28’54.7” E 76° 17’18.2”

    Elevation 1308 m

    Picture were taken on 30/04/2014

    Remarks Cracks on the walls of Aaganbhadi Kendra of Dhalanjan village due to

    the tunnel construction of Chanju HEP.

  • IMAGE 7

    Project Chanju HEP

    Capacity (MW) 36

    Basin Ravi (Chanju Nallah)

    District Chamba

    Village Dhalanjan

    GPS Co-ordinates N 32° 28’54.7” E 76° 17’18.2”

    Elevation 1309 m

    Picture were taken on 30/04/2014

    Remarks Lilo Devi’s house was located just above the HRT of Chanju project. 12

    houses were completely damaged by the tunnel construction in this

    village in December 2013.

  • IMAGE 8

    Project Chanju HEP

    Capacity (MW) 36

    Basin Ravi (Chanju Nallah)

    District Chamba

    Village Dhalanjan

    GPS Co-ordinates N 32° 45’45.0” E 76° 12’08.4”

    Elevation 1280 m

  • Picture were taken on 30/04/2014

    Remarks Power house site of Chanju HEP, where 1000s of trees were damaged

    by the blasting for the tunnel construction due to activation of a

    landslide.

    IMAGE 9

  • People of Dhalanjan village show their destroyed and dilapidated houses. They are now

    residing in temporary shelters (tents)

    IMAGE

    10

  • Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Yulla

    GPS Co-ordinates N 31°33’00.6” E 078°08’14.1”

    Elevation 2536 m

    Picture were taken on 26/05/2014

    Remarks Jyoti Prakash’s house suffered from cracks because of the tunnel.

  • IMAGE 11

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200 MW

    Basin Satluj

    District Kinnaur

    Village Urni

    GPS Co-ordinates N 31°20’50.0” E 078°27’35.8”

    Picture was taken on 06/04/2015

    Elevation 2341m

    Remarks The apple orchards of almost 13 families in Urni village are sliding

    down. Urni is sitting rather precariously above the junction of the

    flushing tunnel, Head Race Tunnel and Adit tunnel of Karcham

    Wangtoo HEP.

  • IMAGE 12

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Urni

    GPS Co-ordinates N 31°31’29.5” E 078°07’49.1”

    Elevation 2356 m

    Picture were taken on 28/05/2014

    Remarks Ramanand’s house where several cracks and crevices developed due to

    the blasting and construction.

  • IMAGE 13

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Urni

    GPS Co-ordinates N 31°32’08.8” E 078°07’49.7”

    Picture was taken on 06/04/2015

    Elevation 2451m

    Remarks The heavy rainfall in 2013 triggered many landslides in the area

    causing extensive damage to personal property (orchards).

  • IMAGE 14

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1000

    Basin Satluj

    District Kinnaur

    Village Runnag

    GPS Co-ordinates N 31°31’04.8” E 078°10’51.9”

    Elevation 2268 m

    Picture were taken on 31/05/2014

    Remarks Runnag Chashma is used by the villagers for washing and drinking.

    The water discharge has reduced substantially.

  • IMAGE

    15

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Runnag

    GPS Co-ordinates N 31°30’56.3” E 078°10’45.8”

    Elevation 2307 m

    Picture were taken on 31/05/2014

    Remarks Munni Lal’s apple orchard which was impacted by a landslide last year

    during 2013 monsoon.

  • IMAGE 16

    Project Karcham-Wangtoo (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Runang

    GPS Co-ordinates N 31°31’50.4” E 078°08’44.5”

    Picture was taken on 07/04/2015

    Elevation 2388m

    Remarks The landslide almost touched people's houses. Residents are now

    building check walls by themselves as a safety measure. Cracks have

    developed in houses.

  • IMAGE

    17

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Meeru

    GPS Co-ordinates N 31°31’45.2” E 078°08’31.2”

    Elevation 2149 m

    Picture were taken on 01/06/2014

    Remarks Landslide just above the tunnel of KW project at Rangle. It was 2014

    monsoons that activated the sliding.

  • IMAGE

    18

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Meeru

    GPS Co-ordinates N 31°32’07.2” E 078°09’00.3”

    Elevation 2708 m

    Picture were taken on 01/06/2014

    Remarks Landslide at Meeru village activated last year which destroyed the only

    passage to the village.

  • IMAGE 19

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Meeru

    GPS Co-ordinates N 31°31’44.2” E 078°08’29.7”

    Picture was taken on 07/04/2015

    Elevation 2171m

    Remarks The area lies below the Hindustan Tibet road. Apple orchards have

    been destroyed due to frequent land sliding in the area. Cracks have

    developed throughout on empty patches.

  • IMAGE20

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Meeru

    GPS Co-ordinates N 31°31’40.6” E 078°08’26.2”

    Picture was taken on 07/04/2015

    Elevation 2111m

    Remarks Satish Kumar's area lies in red zone as slides have reached the

    settlement area. Parts of apple orchards are completely destroyed,

    cracks have developed all over the land, some parts of land have

    caved in.

  • IMAGE 21

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Meeru

    GPS Co-ordinates N 31°31’50.4” E 078°08’44.5”

    Picture was taken on 07/04/2015

    Elevation 2388m

    Remarks The area stands completely destroyed by the landslide and other

    remaining area has developed cracks. Concerned authorities have

    visited the area but no action has been taken yet.

  • IMAGE22

    Project Karcham-Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Meeru

    GPS Co-o

    rdinates

    N 31°31’51.6” E 078°08’48.5”

    Picture was taken on 07/04/2015

    Elevation 2447m

    Remarks A newly constructed house in middle of apple orchards now partially

    destroyed by the landslide. The affected family has been paid no

    compensation as yet. Authorities have visited the area but no action

    taken as yet.

  • IMAGE 23

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Chugaon

    GPS Co-ordinates N 31°31’40.1” E 078°05’17.8”

    Elevation 2072 m

    Picture were taken on 02/06/2014

    Remarks Jagdish Chand Negi’s house was impacted because of the tunnel

    construction.

  • IMAGE 24

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Chugaon

    GPS Co-ordinates N 31°31’39.7” E 078°05’20.9”

    Elevation 2065 m

    Picture were taken on 02/06/2014

    Remarks A cow shed in Chugaon which developed cracks.

    News Links: http://www.tribuneindia.com/2013/20130128/himachal.htm#7

    http://www.tribuneindia.com/2013/20130128/himachal.htm#7

  • http://www.bbnnews24.com/news.php?id=678

    http://indianexpress.com/article/india/regional/9-621-trees-to-be-axed-for-jaypee-

    transmission-line/

    http://www.dayandnightnews.com/2012/07/seepage-in-karcham-wangtoo-project-tunnel/

    IMAGE 25

    Project Nathpa Jhakari HEP

    Capacity (MW) 1500

    Basin Satluj

    District Kinnaur

    Village Nigulseri

    GPS Co-ordinates N 31°33’23.0” E 077°53’14.9”

    Elevation 1864 m

    Picture were taken on 29/05/2014

    Remarks On 25th May 2014 this landslide occurred in Nigulseri village. Locals

    claim that the tunnel of Nathpa Jhakri Project had already disturbed the

    area which was further disturbed because of the transmission tower

    construction for Baspa and Karchham.

    http://www.bbnnews24.com/news.php?id=678http://indianexpress.com/article/india/regional/9-621-trees-to-be-axed-for-jaypee-transmission-line/http://indianexpress.com/article/india/regional/9-621-trees-to-be-axed-for-jaypee-transmission-line/http://www.dayandnightnews.com/2012/07/seepage-in-karcham-wangtoo-project-tunnel/

  • IMAGE26

    Project Nathpa Jhakari HEP

    Capacity (MW) 1500

    Basin Satluj

    District Kinnaur

    Village Nigulseri

    GPS Co-ordinates N 31°33’25.3” E 077°53’02.3”

    Elevation 1662 m

    Picture were taken on 29/05/2014

    Remarks Geeta Ram’s house affected by the landslide at Nigulseri.

  • IMAGE 27

    Project Nathpa Jhakari HEP

    Capacity (MW) 1500

    Basin Satluj

    District Kinnaur

    Village Nigulseri

    GPS Co-ordinates N 31°33’25.0” E 077°53’03.5”

    Elevation 1689 m

    Picture were taken on 29/05/2014

    Remarks Shamsher Singh’s cracked house at Nigulseri as of May 2014. A total of

    13 houses have suffered such damages.

  • IMAGE 28

    Project Nathpa Jhakari HEP

    Capacity (MW) 1500

    Basin Satluj

    District Shimla

    Village Jhakari

    GPS Co-ordinates N 31°31’40.1” E 078°05’17.8”

    Elevation 1167 m

    Picture were taken on 03/06/2014

    Remarks This landslide has occurred near powerhouse of the Nathpa Jhakri

    project

  • IMAGE 29

    Project Shongtong- Karcham HEP

    Capacity (MW) 402

    Basin Satluj

    District Kinnaur

    Village Meber

    GPS Co-ordinates N 31°29’24.1” E 078°13’38.6”

    Picture was taken on 09/04/2015

    Elevation 2740m

    Remarks This area is called Limkatay. This area stands completely damaged by

    landslides and avalanche. The land has caved in.

  • IMAGE 30

    Project Shongtong- Karcham HEP

    Capacity (MW) 402

    Basin Satluj

    District Kinnaur

    Village Barang

    GPS Co-ordinates N 31°30’ 18.0” E 078°15’59.7”

    Picture was taken on 10/04/2015

    Elevation 2474m

    Remarks The mid-section of the land in consideration has been swept clean by

    2013 flood. The use of high intensity explosives for blasting further

    aggravated the sliding. The land belonged to four families who were

    completely dependent on this land for their livelihood.

  • IMAGE 31

    Project Shongtong- Karcham HEP

    Capacity (MW) 402

    Basin Satluj

    District Kinnaur

    Village Barang

    GPS Co-ordinates N 31°30’ 32.2” E 078°16’14.2”

    Picture was taken on 10/04/2015

    Elevation 2196m

    Remarks Landslide near a stream at Barang link road.

  • IMAGE 32

    Project Shongtong- Karcham HEP

    Capacity (MW) 402

    Basin Satluj

    District Kinnaur

    Village Tangling

    GPS Co-ordinates N 31°31’ 20.9” E 078°16’51.8”

    Picture was taken on 10/04/2015

    Elevation 2021

    Remarks The entire road was under debris, the village below the road is under

    threat.

  • IMAGE 33

    Project Shongtong- Karcham HEP

    Capacity (MW) 402

    Basin Satluj

    District Kinnaur

    Village Powari

    GPS Co-ordinates N 31°33’ 20.7” E 078°17’11.3”

    Picture was taken on 10/04/2015

    Elevation 2289m

    Remarks Narendra Singh’s house developed massive cracks after the tunnel

  • construction began.

    IMAGE 34

    Project Shongtong- Karcham HEP

    Capacity (MW) 402

    Basin Satluj

    District Kinnaur

    Village Sudarang

    GPS Co-ordinates N 31°31’ 11.5” E 078°15’57.2”

    Picture was taken on 13/04/2015

    Elevation 2172m

    Remarks Twenty families have moved to another place, with only one remaining.

    The family has to be moved immediately as the land is fragile and

    prone to further landslides. This area had (before the slide took place)

    buildings and shops which were swept off during 2013 flood.

  • IMAGE

    35

    Project Integrated Kashang II HEP

    Capacity (MW) 243

    Basin Satluj

    District Kinnaur

    Village Pangi

    Way Point 879

    GPS Co-ordinates N 31°35’45.2” E 078°17’06.5”

    Picture was taken on 11/04/2015

    Elevation 2651m

    Remarks Upper side of Pangi village. Apple orchards damaged by a landslide in

    2013.

  • IMAGE 36

    Project Integrated Kashang II HEP

    Capacity (MW) 243

    Basin Satluj

    District Kinnaur

    Village Pangi

    Way Point 880

    GPS Co-ordinates N 31°35’46.1” E 078°17’10.5”

    Picture was taken on 11/04/2015

    Elevation 2634m

    Remarks This photograph shows Mr. Harbhagwan Singh's completely ruined

    house.

  • IMAGE 37

    Project Integrated Kashang II HEP

    Capacity (MW) 243 MW

    Basin Satluj

    District Kinnaur

    Village Pangi

    Way Point 881

    GPS Co-ordinates N 31°35’45.6” E 078°17’11.6”

    Picture was taken on 11/04/2015

    Elevation 2614m

    Remarks Half damaged house of Kalawati Devi. Her farm lies below her house.

    Huge cracks have developed in her farm and also lower portion of her

    farm was swept away by landslides along with the road seen in

    photograph.

  • IMAGE 38

    Project Integrated Kashang II HEP

    Capacity (MW) 243

    Basin Satluj

    District Kinnaur

    Village Pangi

    Way Point 877

    GPS Co-ordinates N 31°35’42.9” E 078°17’04.3”

    Picture was taken on 11/04/2015

    Elevation 2609m

    Remarks This is Jakmun Negi”s farm. Cracks have developed due to vibration in

    land.

  • IMAGE 39

    Project Integrated Kashang II HEP

    Capacity (MW) 243

    Basin Satluj

    District Kinnaur

    Village Pangi

    Way Point 883

    GPS Co-ordinates N 31°35’44.2” E 078°17’11.9”

    Picture was taken on 11/04/2015

    Elevation 2587m

    Remarks This is below Kalawati Devi's house. Damaged apple orchards belong

    to her neighbors.

  • IMAGE

    40

    Project Integrated Kashang II HEP

    Capacity (MW) 243

    Basin Satluj

    District Kinnaur

    Village Pangi

    Way Point 885

    GPS Co-ordinates N 31°35’43.9” E 078°17’13.7”

    Picture was taken on 11/04/2015

    Elevation 2567m

    Remarks Damaged farms of Mr. Parvinder Singh. He has a total of 6 bighas out

    of which 4 bighas were lost in a landslide.

  • (B) Literature Review We could consider some of the internationally published scientific research papers for the

    same:

    Petley, D. A. V. I. D. (2013). Global losses from landslides associated with dams and

    reservoirs. Ital J Eng Geol Environ, 6, 63-72.

    “In the construction phase of many projects, landslide accidents continue to occur

    regularly. In many cases these events are situated in or around construction sites;

    landslides onto temporary camps are also common. These events have been responsible

    for an unacceptable level of loss of life in the last decade.”

    Johansson, J., Lovolt, F., Andersen, K. H., Madshus, C., & Aabøe, R. (2013). Impact of

    blast vibrations on the release of quick clay slides. In Proceedings of 18th international

    conference on soil mechanics and geotechnical engineering, ICSMGE, Paris.

    “In 2009, a large quick clay slide involving up to 500,000 m3 soil, and affecting some 10

    houses, was triggered by rock blasting for a road cutting in Kattmarka near the city of

    Namsos in Norway. For this event it was concluded the trigger was not the vibrations

    themselves, but a large block of rock that was punched in to the soil by the blast effect,

    due to unfavourable fault planes in the rock...”

    The literature review further indicates that if blast vibrations are assumed to have

    triggered a slide it is often in combination with other adverse factor such as low stability

    prior to blasting, higher than normal ground water level due to high precipitation, erosion

    at the slope base, temporary placement of fill masses, etc.

    Djordjevic, N., Brunton, I., Cepuritis, P., Chitombo, G., & Heslop, G. (1999). Effect of

    blast vibration on slope stability. Proceedings ofEXPLO 1999, 105-115.

    “There is a significant amount of past evidence that links blasting and occurrences of

    slope failure.”

    Dvořák, A. (1977). Landslides caused by blasting. Bulletin of the International

    Association of Engineering Geology-Bulletin de l'Association Internationale de Géologie

    de l'Ingénieur, 16(1), 166-168. (Abstract Only) http://link.springer.com/

    “The man-made landslides can also be caused by blasting operations. Under

    unfavourable conditions e.g. if the strata of a rock massif dip into the slope, the

    damage can be considerable. It is shown that in addition to the acceleration of the

    vibrations caused by blasting the displacement amplitude has a substancial influence

    on the origin of a slope movement and its limit values are given in relation to the

    jointing of the rock massif.”

    While there have been investigations by the State Geological Wing in some of these

    areas, the reports made by them are inadequate and superficial. So far no detailed and

    independent assessment has been undertaken on the geological implications of the blast

    http://link.springer.com/article/10.1007/BF02591472

  • induced vibrations as a recult of underground tunneling work in the fragile regions of the

    Himalayas. There needs to a clear study of the risk factors vis a vis geology, siesmicity,

    landslide proneness, flood proneness at a cumulative river basin level before planning the

    magnitude of surface and under-ground construction in the Himalayan regions.

    III. Impact on hydrological regimes

    The other major reported impact in the villages located along the tunnel alignment is the

    drying up or reduction in the discharge of the natural water springs. This has been evident

    in case of many projects like Sawra Kuudu, Parbati II, Chamera II and III, Nathpa Jhakri,

    Karchham Wangtoo. Data obtained from the Irrigation and Public Health Department for

    the 1200 MW Karchham Wangtoo Project indicates

    According to information provided by Irrigation and Public Health Department (IPH)

    Himachal, in reply to RTI application filed (Annexure), there are total 167 number of

    water sources in the project affected area of Karcham Wangtoo HEP which falls under the

    jurisdiction of Gram Sabha. Out of these 167 water sources 146 water sources are

    traditional water sources and 21 water sources pertains to IPH department. IPH

    department has collected and discharge data and readings of a twice a year for individual

    sources i.e. in the first half of year (From January to June) and in the second half of a

    year (from July to December) from 2006 to 2010. To know the impact of construction of

    Karcham Wangtoo HEP on water sources, IPH department compared the discharge data

    collected in the first half and the second half of each year. For maintenance of these

    water sources and for development of alternative facilities the funds are coming from

    LADA (Local Area Development Authority)

    Table-1- Yearwise information provided by IPH department on status of water

    sources

    Year No. of Water Sources dried Discharge level reduced

    2006 10 55

    2007 7 68

    2008 37 32

    2009 43 67

    2010 23 6

    Analysis of Table-1

  • In 2009 almost 43 i.e. almost 26% water sources dried up and in 67 i.e almost 40% water sources discharge reduced.

    The variation in number of water sources dried up drastically reduced from 43 number in 2009 to 23 number in 2010 seems to be due to heavy rainfall in 2010

    Discharged level reduced from 67 water sources to 6 because IPH department compared the data collected in two different season of the year 2010 not with the

    data collected before construction of project i.e 2006.

    Analysis of Table-2

    1. Discharge level reduced in 93% of water sources in this period 2. 83% water sources discharged level reduced by more than half 3. More than 50% water sources are either dried up or in verge of drying up.

    Table-2: Status of water sources when discharge level collected in the 1st half of 2006

    compared with discharge level collected in first half of 2010

    Status of Water sources

    Discharge increased 4 5.71%

    No change in discharge 1 1.43%

    Reduction in discharge from 1 -

  • IMAGE 1

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Choling (Urni Panchayat)

    GPS Co-ordinates N 31°31’16.2” E 078°08’18.6”

    Elevation 1825 m

    Picture were taken on 25/05/2014

    Remarks Choling water source/chashma near the highway. The water was used

    for drinking not just by the people in Choling but also by those passing

    by the route. Owing to the tunnel construction, this source has totally

    dried up. Source Discharge

    LPS 2006

    Discharge

    LPS 2007

    Discharge

    LPS 2008

    Discharge

    LPS 2009

    Discharge

    LPS 2010

    Discharge

    LPS 2011

    Discharge

    LPS 2012

    Discharge

    LPS 2013

    Discharge

    LPS 2014 Choling 0.11 0.05 Dry Dry Dry Dry Dry Dry Dry

  • IMAGE 2

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Yulla (Yulla Panchayat)

    GPS Co-ordinates N 31°32’58.8” E 078°08’15.0”

    Elevation 2481 m

    Picture were taken on 26/05/2014

    Remarks Another source of water -Ptokhey-II, whose discharge reduced by 30 to

    40 percent. Source Discharge

    LPS 2006

    Discharge

    LPS 2007

    Discharge

    LPS 2008

    Discharge

    LPS 2009

    Discharge

    LPS 2010

    Discharge

    LPS 2011

    Discharge

    LPS 2012

    Discharge

    LPS 2013

    Discharge

    LPS 2014

    Ptokhey-

    II

    0.8 0.7 2.2 2 2.5 2.5 1.8 2.8 2.1

    5.1.2 Impact on Water Availability and Quality

  • IMAGE 3

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Choling (Meeru panchyat)

    GPS Co-ordinates N 31°30’50.0” E 078°09’36.8”

    Elevation 1822 m

    Picture were taken on 25/05/2014

    Remarks Murim water source dried up due to Karchham Wangtoo's 17 Km long

    tunnel. The stream is not only surrounded by grazing lands but also

    provides drinking water for livestock.

    Source Discharge

    LPS 2006

    Discharge

    LPS 2007

    Discharge

    LPS 2008

    Discharge

    LPS 2009

    Discharge

    LPS 2010

    Discharge

    LPS 2011

    Discharge

    LPS 2012

    Discharge

    LPS 2013

    Discharge

    LPS 2014

    Murim Not

    Measure

    0.7 Dry Dry Dry Dry Dry Dry Dry

  • IMAGE 4

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Meeru (Meeru Panchayat)

    GPS Co-ordinates N 31°32’07.2” E 078°09’00.3”

    Elevation 2708 m

    Picture were taken on 01/06/2014

    Remarks Bhudh Kaso-I IPH source has fully dried due to tunnel construction.

    The entire village was dependent on this water for drinking. Source Discharg

    e LPS

    2006

    Discharg

    e LPS

    2007

    Discharg

    e LPS

    2008

    Discharg

    e LPS

    2009

    Discharg

    e LPS

    2010

    Discharg

    e LPS

    2011

    Discharg

    e LPS

    2012

    Discharg

    e LPS

    2013

    Discharge

    LPS 2014

    Bhudh

    Kaso-I 1.5 0.8 0.08 0.05 0.2 0.3 0.12 0.15 0.2

  • IMAGE 5

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Urni (Urni Panchayat)

    GPS Co-ordinates N 31°20’50.0” E 078°27’35.8”

    Elevation 2148 m

    Picture were taken

    on

    28/05/2014

    Remarks Ramanand Negi showed Kage water source which emerged all of a

    sudden in 2006. He indicated the location as a point where a potential

    landslide is getting active.

    Source Discharge

    LPS 2006

    Discharge

    LPS 2007

    Discharge

    LPS 2008

    Discharge

    LPS 2009

    Discharge

    LPS 2010

    Discharge

    LPS 2011

    Discharge

    LPS 2012

    Discharge

    LPS 2013

    Discharge

    LPS 2014

    Kage Not

    measure

    0.15 0.07 0.05 0.1 0.1 0.1 0.15 0.1

  • IMAGE 5

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Urni (Urni Panchayat)

    GPS Co-ordinates N 31°32’04.5” E 078°07’44.0”

    Picture was taken on 06/04/2015

    Elevation 2471m

    Remarks There existed a traditional flour mill owned by Banwarilal, which

    ran on Kuhl (from Darfo Nallah) but now this kuhl is completely

    destroy. Banwarilal does not use his watermill anymore.

  • IMAGE 6

    Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)

    Capacity (MW) 1200

    Basin Satluj

    District Kinnaur

    Village Chagaon (Chagaon Panchayat)

    GPS Co-ordinates N 31°31’47.7” E 078°05’14.0”

    Picture was taken on 05/04/2015

    Elevation 2177m

    Remarks Fully dried Yach Bio water source in village Chagaon.

    Source Discharge LPS 2006

    Discharge LPS 2007

    Discharge LPS 2008

    Discharge LPS 2009

    Discharge LPS 2010

    Discharge LPS 2011

    Discharge LPS 2012

    Discharge LPS 2013

    Discharge LPS 2014

    Yach

    Bio

    0.5 0.15 0.05 Dry Dry Dry Dry Dry Dry

  • Water Availability: As mentioned earlier, the river Satluj is not the main source of water

    in the area. The natural springs and ‘chashme’ are the key sources of water for people

    living in the area for their own domestic consumption, livestock use and irrigation

    purposes. In most of the villages except those situated on high hills, IPH Department has

    laid down the pipelines to connect the natural springs (at upper reaches) to the households

    through storage tanks for water supply after providing primary treatment. The villages

    those are located on higher reaches depend directly on natural springs or khads flowing in

    vicinity. Hence, massive hydropower development in the area, which is causing diversion

    of flow from river for power generation, will not directly put an impact on availability of

    water for consumption purpose for village population. However, complete drying of

    natural springs (at its original location) has been reported by the villagers due to

    construction and blasting activities. It has been reported that more than 30 chashme have

    dried up in Yangpa village due to the construction works for Sanjay Vidyut Pariyojna.

    Also, it was found out during primary surveys conducted for the study that more than 8-

    12 chashme have dried up in Nathpa-Jhakri areas due to NJHEP project. Considering a

    post project measure, SJVNL has conducted a monitoring campaign for examining the

    flow of springs. It was established that blasting/digging activities can cause

    building up of excessive water pressure at particular location, which may lead to shift in

    the position of a spring or reduction in the flow rate of spring, but complete drying of

    springs is not likely. Due to construction of NJHEP, the IPH water supply scheme was

    badly affected in following villages:

  • ( Source: IPH Department, Rampur )

    Safety Issues

    The case of Karchham Wangtoo Tunnel Seepages

    In December 2012 during an inspection by the officials of the CWC, DOE and CEA in

    the case of the 1200 MW Karchham Wangtoo project profuse leakages were found from

    the surge shaft possibly due to cracks and fissures that may have developed. Through an

    RTI application we had sought some information wrt the incident and we found the

    following (Annuexure) – Response of DOE to RTI Application dated ):

    The letter issued to the project proponent by the authorities provided no details of the exact nature and extent of the leakage. A news report with

    appeared in The Tribune on January 27th 2013 (Annexure) mentioned the

    quantum to be 5 to 9 cumecs which is a substantial amount.

    The response also clearly states that till 2013 there was no authority in the state for control and monitoring of safety and water flows as required by the

    Hydropower Policy 2006 of the state of Himachal Pradesh.

    In the meanwhile while several hydropower projects have been/are being constructed and some are even ready for commissioning in the absence of any

    safety control monitoring authority. This is a matter of serious concern

    considering.

    Further, this not the first time that there has been a safety issue reported for a

    Name of Scheme Habitation

    Majhewali 490

    Koshgar 130

    Kartot 437

    Chandapur 138

    WSS Khasha Shah Jaleend Gasho 622

    Shah 326

    WSS Sharn Rattanpur

    Rattanpur 151

    Rattanpur 50

    Basara 329

    Sansra 282

    Halti 229

    WSS Jhakri Jhakri 4980

    Total 12 habitations 8164

    Table No 5.1 Affected Water Supply of IPH due to NJHEP project

    Present

    population

    WSS Maghara Majholi Koshgar

    WSS Kartot Chandpur

  • hydro project. Please refer to news item of the Tribune dated 17th April 2012

    regarding leakage from the head race tunnel of Chamera III HEP (Annexure)

    Even today, local communities from villages around the Karchham Wangtoo

    tunnel are reporting that leakages in some portions of the tunnel. Until and

    unless a strict monitoring mechanism is created this problem is unlikely to be

    resolved. In such a scenario the state government should take measures to not

    commission projects unless the safety issues have been addressed and an authority is in

    place to examine the same.

    The reservoir burst Aleo-II

    On January 12 2014 the reservoir of the newly built Aleo II hydro project on the Aleo

    nallah, a tributary of the Beas river, collapsed during its very first trial run o. Quite

    shockingly, neither the local authorities nor the villagers were intimated by the project

    authorities about its testing. Though, there was no casualty reported, but the incident

    could have conveniently claimed lives of several workers had it been a working day.

    Makeshift tin shelters for workers built on the boundary of the reservoir wall towards

    Aleo, and also a double storey building adjacent to the power house of Aleo II would

    have been washed away had the water not flown straight into the Beas.

    For the locals, bursting of the dam at this stage, was a result of its location and the poor

    quality material used for construction. Govind, a resident of Aleo Village was not very

    shocked at what happened. According to him, “what occurred was inevitable as the

    foundation of Aleo II stood on the indiscriminate muck and silt dumped by Allian

    Duhangan, a 192 MW project on the same nallah”. On being asked whether the project

    authorities had sought a No Objection Certificate (NOC) from the Gram Sabha, Govind

    says, it was all done under the blanket – without consent of the majority.

    Penstock Burst at Sorang Nallah

    http://www.hindustantimes.com/punjab/penstock-pipe-burst-at-himachal-hydro-project-

    three-feared-dead/story-4JMjxYUOW9ciwSGDmB9ByL.html

    At least three people were feared dead after a penstock pipe burst at the 100MW Sorang

    Hydroelectric project at Burang village in Bhabanagar sub-division of Kinnaur district on

    Wednesday night.

    Two securities guards were reportedly buried in the muck while a local resident was

    washed away. The gushing water also damaged the village path and the land adjoining the

    project, besides destroying some makeshift houses.

    The local administration also rushed to the spot at midnight to take stock of the situation.

    SDM Nichar Neelam Dulta said efforts were on to rescue missing people.

    “Relief material will be distributed to needy people today. Nothing can be said about the

    incident right now,” she said.

    The villagers have demanded action against the project. In the wake of tense situation,

    police arrangements have also been made in the village.

    http://www.hindustantimes.com/punjab/penstock-pipe-burst-at-himachal-hydro-project-three-feared-dead/story-4JMjxYUOW9ciwSGDmB9ByL.htmlhttp://www.hindustantimes.com/punjab/penstock-pipe-burst-at-himachal-hydro-project-three-feared-dead/story-4JMjxYUOW9ciwSGDmB9ByL.html

  • An Abu Dhabi National Energy Company, TAQA, was working on this project, which

    was yet to be commissioned.

    VI. Failures and Inadequacies in Planning, Impact Assessment, Monitoring and

    Regulatory mechanisms

    EIA and Cumulative Impact Assessment Studies not taking into account the impact of tunnels: No studies are conducted as a part of the Environment Impact

    Assessment process to assess the geo-hydrological impacts of the tunneling and

    blasting on the water sources.

    Impact of quarrying – disturbing the stability of the land: This is a common feature

    evident in areas where tunnelling work is being carried out. Yet there are absolutely no

    independent studies being undertaken to look into the geological fragility and the

    probable impacts on villages in the alignment of the tunnel and in constructions zones.

    Local people have been raising these issues in Environment Clearance Public

    hearings and the standard response from project proponents, that comes from

    the denial of adverse impacts of tunneling, is that the incidences of drying of

    water sources and cracks in houses will be monitored and videographed.

    Unfortunately niether the EIA studies nor the Cumulative Impact Assessment studie not

    look at tunnel impacts in the kind of detail required. The tunnel issue should also be

    studied as part of carrying capacity and river basin level impact assessment studies that

    should be an important part of planning hydropower development in an ecologically and

    geologically fragile region but are not being carried out.

    People affected by tunnels should be treated as project affected people/families in the Rehabilitation Plans:

    Since the impact of tunneling as a project activity is not studied the villages in the

    alignment of the tinnel are excluded from the definition ‘project-affected’ in project

    reports, environment impact assessment studies and rehabilitation plans.To ensure a fair

    compensation to families affected as a result of the loss of access to water sources or the

    river itself as well as for any other kind of damages caused by the construction of the

    tunnel it is critical that they be recognised as project affected people in all the reports.

    Further, Like in case of Karcham Wangtoo HEP the money given to IPH for alternative arrangements for making water available, is from Local Area

    Development Fund (LADF) which is actually for overall development of the

    project affected area and not for the mitigation measures due to impact of the

    project. The amount of compensation offered for cracks in houses is measly and

    there are no provisions for rebuilding or relocation for the villagers who encounter

    frequent landslides, erosion and cracks that have begun to appear in their houses

    as a result of the underground blasting activities.

  • Recently, the Himachal State Disaster Management Authority in an advisory issued to the

    Public Works Department, State Electricity Board and other hydro and road project

    authorities, Deputy Commissioners in the wake of tunnel collapse while carrying out the

    four-laning of Kiratpur-Nerchowk on September 12, stated that National Safety Council’s

    safety norms should be followed while constructing tunnels for hydro-electric projects or

    carving out roads.. The advisory states that topographical, geological and hydrological

    parameters will be kept in mind before selecting tunnel sites. “The construction of all

    tunnels shall be done as per the standard, norms and practices of Himalayan geology

    which is young and fragile and if any geological changes are observed or encountered

    during construction, necessary innovative and remedial measures will be incorporated in

    the design,” the advisory reads. Government agencies will be mandated to check the

    ongoing tunnel construction works periodically and the designs will be vetted by them.

    (http://www.tribuneindia.com/news/himachal/community/now-geological-study-a-must-

    for-tunnels/151686.html)

    This establishes that there is a recognition of the impacts of tunneling, however, there is

    need to study whether following of “safety norms” is an adeqauate response at this stage

    where the scale of the activity is so large.

    Key Demands

    1. Carrying Capacity Studies on the river basin should be mandatory before allocation of Hydropower Projects. Until and unless such studies are conducted

    along with Cumulative Impact Studies which assess the impacts of tunneling in

    cascade of projects there should be a moratorium on further construction

    2. The TORs for River Valley Projects involving tunnel construction should include 'Assessing the impacts of tunnels – both ecological and socio-economic' as part of

    the EIA studies

    3. Tunnel Affected communities should be included in the list of Project Affected Families and should be eligible for adequate compensation

    4. Until an active Authority for Safety Control is established there should be a halt on further commissioning of projects

    5. Projects that are violating safety guidelines and clearance conditions should be eligible for punitive action in a timely manner after issuance of show cause

    notices. Penal action, rather than imposition of fines should be initiated in case of

    forest offences. Compliance monitoring mechanisms need to be strengthened to

    ensure regular inspections by PCB and regional authorities

    6. There should be a scientific multi discplinary study of the probable geological and hydrological ramifications of the DBM in construction of tunnels and roads in

    the Himalayan region needs to be conducted.

    http://www.tribuneindia.com/news/himachal/community/now-geological-study-a-must-for-tunnels/151686.htmlhttp://www.tribuneindia.com/news/himachal/community/now-geological-study-a-must-for-tunnels/151686.html