Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
December 2015
Himdhara Environment Research and Action Collective Palampur, Himachal Pradesh
[email protected] www.himdhara.org
mailto:[email protected]
A CASE FOR URGENTLY ASSESSING IMPACT OF DRILLING AND
BLASTING FOR CONSTRUCTION OF TUNNELS AND ROADS IN
HIMACHAL
Himdhara, Environment Research and Action Collective
I. Hydropower Development in Himachal using Run-of-the-River Technology
Himachal Pradesh is the largest producer of Hydropower in India. The state has already
installed 9433 MW worth of projects (a total of 53 large, medium and small projects and
several micro-hydels). It is is planning to harness a total 27436 MW1 of power from the
five major river basins of the state namely Satluj, Chenab, Ravi, Beas and Yamuna. The
Satluj river basin alone has a planned potential of 13,332 MW. Projects with a capacity of
3490 MW are under construction, 2623 MW are under various stages of clearance and
another 121 MW are under investigation (planning).
It is thus clear that the magnitude of Hydropower Projects construction in the state is
large.
The Hydropower development that is being undertaken in Himachal and the entire
Himalayan region of India is based on the Run-of-the-river technology which produces
electricity by checking and diverting river flow. The diverted water is made to flow
through underground tunnels in the mountains and released downstream on the turbines
that spin generators before returning the water back to the river. It is important to note
that the projects using this technology are being built in a cascade form on a river basin.
This means that at the tail of one project, the head of the next is located.
It is critical to note that a series of these projects are being built bumper to bumper on the
streams and rivers to harness the capacity of the rivers to produce power to its maximum.
Use of the Drill and Blast Method of Underground Tunneling
The construction of Hydropower projects using the ROR technology involves surface as
well as underground construction. The surface construction consists of high concrete
gravity dam, roads, power house, colony and labour camps etc. The underground civil
works for the ROR projects are an extremely critical and substantial component. The
typical underground construction has the following components:
A headrace tunnel (These tunnels are large enough to allow the passage of heavy vehicles. A Head race tunnel can be upto 9 to 10 m diametres.)
A surge shaft
Underground powerhouse
Underground transformer hall
1 �Economic Survey of the State of Himachal Pradesh 2014
Tailrace tunnel
Desilting chambers
Adit Tunnels (access tunnels)
In the Satluj River Basin alone the total length of tunnels once all the planned
hydroprojects are built will be 185 kms. If all the planned projects in Himachal and
across the Himalayas are constructed there will be hundreds of kilometres of tunnels
underneath the mountains in this region.
The Drill and blast method (DBM) is the conventional tunneling method in hard rock and
is being used in the hydropower construction across Himachal. In this method excavation
is achieved by drilling a predetermined pattern of holes in the rock face, filling these
holes with explosives, which are then discharged to crack and fracture the rock. Loosened
debris is removed and the tunnel is secured.
II. Blast induced vibrations and slope destabilisation
It is important to note that local people, environmentalists and experts have been raising
concerns with regard to the the blast induced vibrations caused by the use of the DBM for
tunneling and their geological and ecological impacts.
(A) In Himachal Pradesh a series of occurances of slope destabilisation have been seen
over the past few years in areas where construction work involving DBM for
underground tunneling or for roads. The most evident impacts of these have been:
- Seepages and leakages in tunnels
- Land Slides
- Damages to Houses
Given below is an audio-visual documentation of a series of events of slope
destabilisation, caving in, collapse in the Ravi and Satluj valleys in the year 2014-15.
IMAGE 1
Project Chamera III HEP
Capacity (MW) 231
Basin Ravi
District Chamba
Village Mokhr
GPS Co-ordinates N 31° 01’ 18.2” E 76° 37’58.1”
Picture was taken on 29/04/2014
Elevation 1263 m
Remarks In April 2012, there was a massive leakage in the 16km HRT of the
Chamera III project just above the Mokhar village leading to severe
threat to the village downhill so much so that the 40 families residing
there had to be evacuated. This picture is of Adit 6 of the tunnel. The
leakage occurred during testing of the generating units.
News reports http://www.jagran.com/news/state-10802084.html
http://www.jagran.com/news/state-10802084.html
http://www.tribuneindia.com/2012/20120418/himplus.htm#2
http://www.jagran.com/news/state-10802084.htmlhttp://www.jagran.com/news/state-10802084.htmlhttp://www.tribuneindia.com/2012/20120418/himplus.htm#2
IMAGE 2
Project Chamera III HEP
Capacity (MW) 231
Basin Ravi
District Chamba
Village Mokhr
GPS Co-ordinates N 31° 01’18.2” E 76° 37’54.1”
Elevation 1361 m
Picture were taken on 29/04/2014
Remarks Leakages in the surge shaft of the Chamera III tunnel just above
Mokhar village.
IMAGE 3
Project Chamera III HEP
Capacity (MW) 231
Basin Ravi
District Chamba
Village Mokhar
GPS Co-ordinates N 32° 28’54.7” E 76° 17’18.1”
Elevation 1213 m
Picture were taken on 29/04/2014
Remarks Vidya Devi’s house in Mokhar was completely damaged by the
landslide caused due to the seepage from the surge shaft in April 2012.
IMAGE 4
Project Chamera III HEP
Capacity (MW) 231
Basin Ravi
District Chamba
Village Mokhr
GPS Co-ordinates N 32° 28’53.7” E 76° 17’15.7”
Elevation 1202 m
Picture were taken on 29/04/2014
Remarks Shri Jagdish Sharma standing in front of the debris of his leftover house
after the leakage tragedy .
IMAGE 5
Project Chamera III HEP
Capacity (MW) 231
Basin Ravi
District Chamba
Village Mokhr
GPS Co-ordinates N 31° 01’18.2” E 76° 37’54.1”
Elevation 1361 m
Picture were taken on 29/04/2014
Remarks The pastures of the village buried under the landslide caused by
seepages.
Damages caused to houses in Mokhar village due to leakages in the HRT
IMAGE 6
Project Chanju HEP
Capacity (MW) 36
Basin Ravi (Chanju Nallah)
District Chamba
Village Dhalanjan
GPS Co-ordinates N 32° 28’54.7” E 76° 17’18.2”
Elevation 1308 m
Picture were taken on 30/04/2014
Remarks Cracks on the walls of Aaganbhadi Kendra of Dhalanjan village due to
the tunnel construction of Chanju HEP.
IMAGE 7
Project Chanju HEP
Capacity (MW) 36
Basin Ravi (Chanju Nallah)
District Chamba
Village Dhalanjan
GPS Co-ordinates N 32° 28’54.7” E 76° 17’18.2”
Elevation 1309 m
Picture were taken on 30/04/2014
Remarks Lilo Devi’s house was located just above the HRT of Chanju project. 12
houses were completely damaged by the tunnel construction in this
village in December 2013.
IMAGE 8
Project Chanju HEP
Capacity (MW) 36
Basin Ravi (Chanju Nallah)
District Chamba
Village Dhalanjan
GPS Co-ordinates N 32° 45’45.0” E 76° 12’08.4”
Elevation 1280 m
Picture were taken on 30/04/2014
Remarks Power house site of Chanju HEP, where 1000s of trees were damaged
by the blasting for the tunnel construction due to activation of a
landslide.
IMAGE 9
People of Dhalanjan village show their destroyed and dilapidated houses. They are now
residing in temporary shelters (tents)
IMAGE
10
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Yulla
GPS Co-ordinates N 31°33’00.6” E 078°08’14.1”
Elevation 2536 m
Picture were taken on 26/05/2014
Remarks Jyoti Prakash’s house suffered from cracks because of the tunnel.
IMAGE 11
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200 MW
Basin Satluj
District Kinnaur
Village Urni
GPS Co-ordinates N 31°20’50.0” E 078°27’35.8”
Picture was taken on 06/04/2015
Elevation 2341m
Remarks The apple orchards of almost 13 families in Urni village are sliding
down. Urni is sitting rather precariously above the junction of the
flushing tunnel, Head Race Tunnel and Adit tunnel of Karcham
Wangtoo HEP.
IMAGE 12
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Urni
GPS Co-ordinates N 31°31’29.5” E 078°07’49.1”
Elevation 2356 m
Picture were taken on 28/05/2014
Remarks Ramanand’s house where several cracks and crevices developed due to
the blasting and construction.
IMAGE 13
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Urni
GPS Co-ordinates N 31°32’08.8” E 078°07’49.7”
Picture was taken on 06/04/2015
Elevation 2451m
Remarks The heavy rainfall in 2013 triggered many landslides in the area
causing extensive damage to personal property (orchards).
IMAGE 14
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1000
Basin Satluj
District Kinnaur
Village Runnag
GPS Co-ordinates N 31°31’04.8” E 078°10’51.9”
Elevation 2268 m
Picture were taken on 31/05/2014
Remarks Runnag Chashma is used by the villagers for washing and drinking.
The water discharge has reduced substantially.
IMAGE
15
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Runnag
GPS Co-ordinates N 31°30’56.3” E 078°10’45.8”
Elevation 2307 m
Picture were taken on 31/05/2014
Remarks Munni Lal’s apple orchard which was impacted by a landslide last year
during 2013 monsoon.
IMAGE 16
Project Karcham-Wangtoo (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Runang
GPS Co-ordinates N 31°31’50.4” E 078°08’44.5”
Picture was taken on 07/04/2015
Elevation 2388m
Remarks The landslide almost touched people's houses. Residents are now
building check walls by themselves as a safety measure. Cracks have
developed in houses.
IMAGE
17
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Meeru
GPS Co-ordinates N 31°31’45.2” E 078°08’31.2”
Elevation 2149 m
Picture were taken on 01/06/2014
Remarks Landslide just above the tunnel of KW project at Rangle. It was 2014
monsoons that activated the sliding.
IMAGE
18
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Meeru
GPS Co-ordinates N 31°32’07.2” E 078°09’00.3”
Elevation 2708 m
Picture were taken on 01/06/2014
Remarks Landslide at Meeru village activated last year which destroyed the only
passage to the village.
IMAGE 19
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Meeru
GPS Co-ordinates N 31°31’44.2” E 078°08’29.7”
Picture was taken on 07/04/2015
Elevation 2171m
Remarks The area lies below the Hindustan Tibet road. Apple orchards have
been destroyed due to frequent land sliding in the area. Cracks have
developed throughout on empty patches.
IMAGE20
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Meeru
GPS Co-ordinates N 31°31’40.6” E 078°08’26.2”
Picture was taken on 07/04/2015
Elevation 2111m
Remarks Satish Kumar's area lies in red zone as slides have reached the
settlement area. Parts of apple orchards are completely destroyed,
cracks have developed all over the land, some parts of land have
caved in.
IMAGE 21
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Meeru
GPS Co-ordinates N 31°31’50.4” E 078°08’44.5”
Picture was taken on 07/04/2015
Elevation 2388m
Remarks The area stands completely destroyed by the landslide and other
remaining area has developed cracks. Concerned authorities have
visited the area but no action has been taken yet.
IMAGE22
Project Karcham-Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Meeru
GPS Co-o
rdinates
N 31°31’51.6” E 078°08’48.5”
Picture was taken on 07/04/2015
Elevation 2447m
Remarks A newly constructed house in middle of apple orchards now partially
destroyed by the landslide. The affected family has been paid no
compensation as yet. Authorities have visited the area but no action
taken as yet.
IMAGE 23
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Chugaon
GPS Co-ordinates N 31°31’40.1” E 078°05’17.8”
Elevation 2072 m
Picture were taken on 02/06/2014
Remarks Jagdish Chand Negi’s house was impacted because of the tunnel
construction.
IMAGE 24
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Chugaon
GPS Co-ordinates N 31°31’39.7” E 078°05’20.9”
Elevation 2065 m
Picture were taken on 02/06/2014
Remarks A cow shed in Chugaon which developed cracks.
News Links: http://www.tribuneindia.com/2013/20130128/himachal.htm#7
http://www.tribuneindia.com/2013/20130128/himachal.htm#7
http://www.bbnnews24.com/news.php?id=678
http://indianexpress.com/article/india/regional/9-621-trees-to-be-axed-for-jaypee-
transmission-line/
http://www.dayandnightnews.com/2012/07/seepage-in-karcham-wangtoo-project-tunnel/
IMAGE 25
Project Nathpa Jhakari HEP
Capacity (MW) 1500
Basin Satluj
District Kinnaur
Village Nigulseri
GPS Co-ordinates N 31°33’23.0” E 077°53’14.9”
Elevation 1864 m
Picture were taken on 29/05/2014
Remarks On 25th May 2014 this landslide occurred in Nigulseri village. Locals
claim that the tunnel of Nathpa Jhakri Project had already disturbed the
area which was further disturbed because of the transmission tower
construction for Baspa and Karchham.
http://www.bbnnews24.com/news.php?id=678http://indianexpress.com/article/india/regional/9-621-trees-to-be-axed-for-jaypee-transmission-line/http://indianexpress.com/article/india/regional/9-621-trees-to-be-axed-for-jaypee-transmission-line/http://www.dayandnightnews.com/2012/07/seepage-in-karcham-wangtoo-project-tunnel/
IMAGE26
Project Nathpa Jhakari HEP
Capacity (MW) 1500
Basin Satluj
District Kinnaur
Village Nigulseri
GPS Co-ordinates N 31°33’25.3” E 077°53’02.3”
Elevation 1662 m
Picture were taken on 29/05/2014
Remarks Geeta Ram’s house affected by the landslide at Nigulseri.
IMAGE 27
Project Nathpa Jhakari HEP
Capacity (MW) 1500
Basin Satluj
District Kinnaur
Village Nigulseri
GPS Co-ordinates N 31°33’25.0” E 077°53’03.5”
Elevation 1689 m
Picture were taken on 29/05/2014
Remarks Shamsher Singh’s cracked house at Nigulseri as of May 2014. A total of
13 houses have suffered such damages.
IMAGE 28
Project Nathpa Jhakari HEP
Capacity (MW) 1500
Basin Satluj
District Shimla
Village Jhakari
GPS Co-ordinates N 31°31’40.1” E 078°05’17.8”
Elevation 1167 m
Picture were taken on 03/06/2014
Remarks This landslide has occurred near powerhouse of the Nathpa Jhakri
project
IMAGE 29
Project Shongtong- Karcham HEP
Capacity (MW) 402
Basin Satluj
District Kinnaur
Village Meber
GPS Co-ordinates N 31°29’24.1” E 078°13’38.6”
Picture was taken on 09/04/2015
Elevation 2740m
Remarks This area is called Limkatay. This area stands completely damaged by
landslides and avalanche. The land has caved in.
IMAGE 30
Project Shongtong- Karcham HEP
Capacity (MW) 402
Basin Satluj
District Kinnaur
Village Barang
GPS Co-ordinates N 31°30’ 18.0” E 078°15’59.7”
Picture was taken on 10/04/2015
Elevation 2474m
Remarks The mid-section of the land in consideration has been swept clean by
2013 flood. The use of high intensity explosives for blasting further
aggravated the sliding. The land belonged to four families who were
completely dependent on this land for their livelihood.
IMAGE 31
Project Shongtong- Karcham HEP
Capacity (MW) 402
Basin Satluj
District Kinnaur
Village Barang
GPS Co-ordinates N 31°30’ 32.2” E 078°16’14.2”
Picture was taken on 10/04/2015
Elevation 2196m
Remarks Landslide near a stream at Barang link road.
IMAGE 32
Project Shongtong- Karcham HEP
Capacity (MW) 402
Basin Satluj
District Kinnaur
Village Tangling
GPS Co-ordinates N 31°31’ 20.9” E 078°16’51.8”
Picture was taken on 10/04/2015
Elevation 2021
Remarks The entire road was under debris, the village below the road is under
threat.
IMAGE 33
Project Shongtong- Karcham HEP
Capacity (MW) 402
Basin Satluj
District Kinnaur
Village Powari
GPS Co-ordinates N 31°33’ 20.7” E 078°17’11.3”
Picture was taken on 10/04/2015
Elevation 2289m
Remarks Narendra Singh’s house developed massive cracks after the tunnel
construction began.
IMAGE 34
Project Shongtong- Karcham HEP
Capacity (MW) 402
Basin Satluj
District Kinnaur
Village Sudarang
GPS Co-ordinates N 31°31’ 11.5” E 078°15’57.2”
Picture was taken on 13/04/2015
Elevation 2172m
Remarks Twenty families have moved to another place, with only one remaining.
The family has to be moved immediately as the land is fragile and
prone to further landslides. This area had (before the slide took place)
buildings and shops which were swept off during 2013 flood.
IMAGE
35
Project Integrated Kashang II HEP
Capacity (MW) 243
Basin Satluj
District Kinnaur
Village Pangi
Way Point 879
GPS Co-ordinates N 31°35’45.2” E 078°17’06.5”
Picture was taken on 11/04/2015
Elevation 2651m
Remarks Upper side of Pangi village. Apple orchards damaged by a landslide in
2013.
IMAGE 36
Project Integrated Kashang II HEP
Capacity (MW) 243
Basin Satluj
District Kinnaur
Village Pangi
Way Point 880
GPS Co-ordinates N 31°35’46.1” E 078°17’10.5”
Picture was taken on 11/04/2015
Elevation 2634m
Remarks This photograph shows Mr. Harbhagwan Singh's completely ruined
house.
IMAGE 37
Project Integrated Kashang II HEP
Capacity (MW) 243 MW
Basin Satluj
District Kinnaur
Village Pangi
Way Point 881
GPS Co-ordinates N 31°35’45.6” E 078°17’11.6”
Picture was taken on 11/04/2015
Elevation 2614m
Remarks Half damaged house of Kalawati Devi. Her farm lies below her house.
Huge cracks have developed in her farm and also lower portion of her
farm was swept away by landslides along with the road seen in
photograph.
IMAGE 38
Project Integrated Kashang II HEP
Capacity (MW) 243
Basin Satluj
District Kinnaur
Village Pangi
Way Point 877
GPS Co-ordinates N 31°35’42.9” E 078°17’04.3”
Picture was taken on 11/04/2015
Elevation 2609m
Remarks This is Jakmun Negi”s farm. Cracks have developed due to vibration in
land.
IMAGE 39
Project Integrated Kashang II HEP
Capacity (MW) 243
Basin Satluj
District Kinnaur
Village Pangi
Way Point 883
GPS Co-ordinates N 31°35’44.2” E 078°17’11.9”
Picture was taken on 11/04/2015
Elevation 2587m
Remarks This is below Kalawati Devi's house. Damaged apple orchards belong
to her neighbors.
IMAGE
40
Project Integrated Kashang II HEP
Capacity (MW) 243
Basin Satluj
District Kinnaur
Village Pangi
Way Point 885
GPS Co-ordinates N 31°35’43.9” E 078°17’13.7”
Picture was taken on 11/04/2015
Elevation 2567m
Remarks Damaged farms of Mr. Parvinder Singh. He has a total of 6 bighas out
of which 4 bighas were lost in a landslide.
(B) Literature Review We could consider some of the internationally published scientific research papers for the
same:
Petley, D. A. V. I. D. (2013). Global losses from landslides associated with dams and
reservoirs. Ital J Eng Geol Environ, 6, 63-72.
“In the construction phase of many projects, landslide accidents continue to occur
regularly. In many cases these events are situated in or around construction sites;
landslides onto temporary camps are also common. These events have been responsible
for an unacceptable level of loss of life in the last decade.”
Johansson, J., Lovolt, F., Andersen, K. H., Madshus, C., & Aabøe, R. (2013). Impact of
blast vibrations on the release of quick clay slides. In Proceedings of 18th international
conference on soil mechanics and geotechnical engineering, ICSMGE, Paris.
“In 2009, a large quick clay slide involving up to 500,000 m3 soil, and affecting some 10
houses, was triggered by rock blasting for a road cutting in Kattmarka near the city of
Namsos in Norway. For this event it was concluded the trigger was not the vibrations
themselves, but a large block of rock that was punched in to the soil by the blast effect,
due to unfavourable fault planes in the rock...”
The literature review further indicates that if blast vibrations are assumed to have
triggered a slide it is often in combination with other adverse factor such as low stability
prior to blasting, higher than normal ground water level due to high precipitation, erosion
at the slope base, temporary placement of fill masses, etc.
Djordjevic, N., Brunton, I., Cepuritis, P., Chitombo, G., & Heslop, G. (1999). Effect of
blast vibration on slope stability. Proceedings ofEXPLO 1999, 105-115.
“There is a significant amount of past evidence that links blasting and occurrences of
slope failure.”
Dvořák, A. (1977). Landslides caused by blasting. Bulletin of the International
Association of Engineering Geology-Bulletin de l'Association Internationale de Géologie
de l'Ingénieur, 16(1), 166-168. (Abstract Only) http://link.springer.com/
“The man-made landslides can also be caused by blasting operations. Under
unfavourable conditions e.g. if the strata of a rock massif dip into the slope, the
damage can be considerable. It is shown that in addition to the acceleration of the
vibrations caused by blasting the displacement amplitude has a substancial influence
on the origin of a slope movement and its limit values are given in relation to the
jointing of the rock massif.”
While there have been investigations by the State Geological Wing in some of these
areas, the reports made by them are inadequate and superficial. So far no detailed and
independent assessment has been undertaken on the geological implications of the blast
http://link.springer.com/article/10.1007/BF02591472
induced vibrations as a recult of underground tunneling work in the fragile regions of the
Himalayas. There needs to a clear study of the risk factors vis a vis geology, siesmicity,
landslide proneness, flood proneness at a cumulative river basin level before planning the
magnitude of surface and under-ground construction in the Himalayan regions.
III. Impact on hydrological regimes
The other major reported impact in the villages located along the tunnel alignment is the
drying up or reduction in the discharge of the natural water springs. This has been evident
in case of many projects like Sawra Kuudu, Parbati II, Chamera II and III, Nathpa Jhakri,
Karchham Wangtoo. Data obtained from the Irrigation and Public Health Department for
the 1200 MW Karchham Wangtoo Project indicates
According to information provided by Irrigation and Public Health Department (IPH)
Himachal, in reply to RTI application filed (Annexure), there are total 167 number of
water sources in the project affected area of Karcham Wangtoo HEP which falls under the
jurisdiction of Gram Sabha. Out of these 167 water sources 146 water sources are
traditional water sources and 21 water sources pertains to IPH department. IPH
department has collected and discharge data and readings of a twice a year for individual
sources i.e. in the first half of year (From January to June) and in the second half of a
year (from July to December) from 2006 to 2010. To know the impact of construction of
Karcham Wangtoo HEP on water sources, IPH department compared the discharge data
collected in the first half and the second half of each year. For maintenance of these
water sources and for development of alternative facilities the funds are coming from
LADA (Local Area Development Authority)
Table-1- Yearwise information provided by IPH department on status of water
sources
Year No. of Water Sources dried Discharge level reduced
2006 10 55
2007 7 68
2008 37 32
2009 43 67
2010 23 6
Analysis of Table-1
In 2009 almost 43 i.e. almost 26% water sources dried up and in 67 i.e almost 40% water sources discharge reduced.
The variation in number of water sources dried up drastically reduced from 43 number in 2009 to 23 number in 2010 seems to be due to heavy rainfall in 2010
Discharged level reduced from 67 water sources to 6 because IPH department compared the data collected in two different season of the year 2010 not with the
data collected before construction of project i.e 2006.
Analysis of Table-2
1. Discharge level reduced in 93% of water sources in this period 2. 83% water sources discharged level reduced by more than half 3. More than 50% water sources are either dried up or in verge of drying up.
Table-2: Status of water sources when discharge level collected in the 1st half of 2006
compared with discharge level collected in first half of 2010
Status of Water sources
Discharge increased 4 5.71%
No change in discharge 1 1.43%
Reduction in discharge from 1 -
IMAGE 1
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Choling (Urni Panchayat)
GPS Co-ordinates N 31°31’16.2” E 078°08’18.6”
Elevation 1825 m
Picture were taken on 25/05/2014
Remarks Choling water source/chashma near the highway. The water was used
for drinking not just by the people in Choling but also by those passing
by the route. Owing to the tunnel construction, this source has totally
dried up. Source Discharge
LPS 2006
Discharge
LPS 2007
Discharge
LPS 2008
Discharge
LPS 2009
Discharge
LPS 2010
Discharge
LPS 2011
Discharge
LPS 2012
Discharge
LPS 2013
Discharge
LPS 2014 Choling 0.11 0.05 Dry Dry Dry Dry Dry Dry Dry
IMAGE 2
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Yulla (Yulla Panchayat)
GPS Co-ordinates N 31°32’58.8” E 078°08’15.0”
Elevation 2481 m
Picture were taken on 26/05/2014
Remarks Another source of water -Ptokhey-II, whose discharge reduced by 30 to
40 percent. Source Discharge
LPS 2006
Discharge
LPS 2007
Discharge
LPS 2008
Discharge
LPS 2009
Discharge
LPS 2010
Discharge
LPS 2011
Discharge
LPS 2012
Discharge
LPS 2013
Discharge
LPS 2014
Ptokhey-
II
0.8 0.7 2.2 2 2.5 2.5 1.8 2.8 2.1
5.1.2 Impact on Water Availability and Quality
IMAGE 3
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Choling (Meeru panchyat)
GPS Co-ordinates N 31°30’50.0” E 078°09’36.8”
Elevation 1822 m
Picture were taken on 25/05/2014
Remarks Murim water source dried up due to Karchham Wangtoo's 17 Km long
tunnel. The stream is not only surrounded by grazing lands but also
provides drinking water for livestock.
Source Discharge
LPS 2006
Discharge
LPS 2007
Discharge
LPS 2008
Discharge
LPS 2009
Discharge
LPS 2010
Discharge
LPS 2011
Discharge
LPS 2012
Discharge
LPS 2013
Discharge
LPS 2014
Murim Not
Measure
0.7 Dry Dry Dry Dry Dry Dry Dry
IMAGE 4
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Meeru (Meeru Panchayat)
GPS Co-ordinates N 31°32’07.2” E 078°09’00.3”
Elevation 2708 m
Picture were taken on 01/06/2014
Remarks Bhudh Kaso-I IPH source has fully dried due to tunnel construction.
The entire village was dependent on this water for drinking. Source Discharg
e LPS
2006
Discharg
e LPS
2007
Discharg
e LPS
2008
Discharg
e LPS
2009
Discharg
e LPS
2010
Discharg
e LPS
2011
Discharg
e LPS
2012
Discharg
e LPS
2013
Discharge
LPS 2014
Bhudh
Kaso-I 1.5 0.8 0.08 0.05 0.2 0.3 0.12 0.15 0.2
IMAGE 5
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Urni (Urni Panchayat)
GPS Co-ordinates N 31°20’50.0” E 078°27’35.8”
Elevation 2148 m
Picture were taken
on
28/05/2014
Remarks Ramanand Negi showed Kage water source which emerged all of a
sudden in 2006. He indicated the location as a point where a potential
landslide is getting active.
Source Discharge
LPS 2006
Discharge
LPS 2007
Discharge
LPS 2008
Discharge
LPS 2009
Discharge
LPS 2010
Discharge
LPS 2011
Discharge
LPS 2012
Discharge
LPS 2013
Discharge
LPS 2014
Kage Not
measure
0.15 0.07 0.05 0.1 0.1 0.1 0.15 0.1
IMAGE 5
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Urni (Urni Panchayat)
GPS Co-ordinates N 31°32’04.5” E 078°07’44.0”
Picture was taken on 06/04/2015
Elevation 2471m
Remarks There existed a traditional flour mill owned by Banwarilal, which
ran on Kuhl (from Darfo Nallah) but now this kuhl is completely
destroy. Banwarilal does not use his watermill anymore.
IMAGE 6
Project Karcham Wangtoo HEP (Jaiprakash Power Venture Limited)
Capacity (MW) 1200
Basin Satluj
District Kinnaur
Village Chagaon (Chagaon Panchayat)
GPS Co-ordinates N 31°31’47.7” E 078°05’14.0”
Picture was taken on 05/04/2015
Elevation 2177m
Remarks Fully dried Yach Bio water source in village Chagaon.
Source Discharge LPS 2006
Discharge LPS 2007
Discharge LPS 2008
Discharge LPS 2009
Discharge LPS 2010
Discharge LPS 2011
Discharge LPS 2012
Discharge LPS 2013
Discharge LPS 2014
Yach
Bio
0.5 0.15 0.05 Dry Dry Dry Dry Dry Dry
Water Availability: As mentioned earlier, the river Satluj is not the main source of water
in the area. The natural springs and ‘chashme’ are the key sources of water for people
living in the area for their own domestic consumption, livestock use and irrigation
purposes. In most of the villages except those situated on high hills, IPH Department has
laid down the pipelines to connect the natural springs (at upper reaches) to the households
through storage tanks for water supply after providing primary treatment. The villages
those are located on higher reaches depend directly on natural springs or khads flowing in
vicinity. Hence, massive hydropower development in the area, which is causing diversion
of flow from river for power generation, will not directly put an impact on availability of
water for consumption purpose for village population. However, complete drying of
natural springs (at its original location) has been reported by the villagers due to
construction and blasting activities. It has been reported that more than 30 chashme have
dried up in Yangpa village due to the construction works for Sanjay Vidyut Pariyojna.
Also, it was found out during primary surveys conducted for the study that more than 8-
12 chashme have dried up in Nathpa-Jhakri areas due to NJHEP project. Considering a
post project measure, SJVNL has conducted a monitoring campaign for examining the
flow of springs. It was established that blasting/digging activities can cause
building up of excessive water pressure at particular location, which may lead to shift in
the position of a spring or reduction in the flow rate of spring, but complete drying of
springs is not likely. Due to construction of NJHEP, the IPH water supply scheme was
badly affected in following villages:
( Source: IPH Department, Rampur )
Safety Issues
The case of Karchham Wangtoo Tunnel Seepages
In December 2012 during an inspection by the officials of the CWC, DOE and CEA in
the case of the 1200 MW Karchham Wangtoo project profuse leakages were found from
the surge shaft possibly due to cracks and fissures that may have developed. Through an
RTI application we had sought some information wrt the incident and we found the
following (Annuexure) – Response of DOE to RTI Application dated ):
The letter issued to the project proponent by the authorities provided no details of the exact nature and extent of the leakage. A news report with
appeared in The Tribune on January 27th 2013 (Annexure) mentioned the
quantum to be 5 to 9 cumecs which is a substantial amount.
The response also clearly states that till 2013 there was no authority in the state for control and monitoring of safety and water flows as required by the
Hydropower Policy 2006 of the state of Himachal Pradesh.
In the meanwhile while several hydropower projects have been/are being constructed and some are even ready for commissioning in the absence of any
safety control monitoring authority. This is a matter of serious concern
considering.
Further, this not the first time that there has been a safety issue reported for a
Name of Scheme Habitation
Majhewali 490
Koshgar 130
Kartot 437
Chandapur 138
WSS Khasha Shah Jaleend Gasho 622
Shah 326
WSS Sharn Rattanpur
Rattanpur 151
Rattanpur 50
Basara 329
Sansra 282
Halti 229
WSS Jhakri Jhakri 4980
Total 12 habitations 8164
Table No 5.1 Affected Water Supply of IPH due to NJHEP project
Present
population
WSS Maghara Majholi Koshgar
WSS Kartot Chandpur
hydro project. Please refer to news item of the Tribune dated 17th April 2012
regarding leakage from the head race tunnel of Chamera III HEP (Annexure)
Even today, local communities from villages around the Karchham Wangtoo
tunnel are reporting that leakages in some portions of the tunnel. Until and
unless a strict monitoring mechanism is created this problem is unlikely to be
resolved. In such a scenario the state government should take measures to not
commission projects unless the safety issues have been addressed and an authority is in
place to examine the same.
The reservoir burst Aleo-II
On January 12 2014 the reservoir of the newly built Aleo II hydro project on the Aleo
nallah, a tributary of the Beas river, collapsed during its very first trial run o. Quite
shockingly, neither the local authorities nor the villagers were intimated by the project
authorities about its testing. Though, there was no casualty reported, but the incident
could have conveniently claimed lives of several workers had it been a working day.
Makeshift tin shelters for workers built on the boundary of the reservoir wall towards
Aleo, and also a double storey building adjacent to the power house of Aleo II would
have been washed away had the water not flown straight into the Beas.
For the locals, bursting of the dam at this stage, was a result of its location and the poor
quality material used for construction. Govind, a resident of Aleo Village was not very
shocked at what happened. According to him, “what occurred was inevitable as the
foundation of Aleo II stood on the indiscriminate muck and silt dumped by Allian
Duhangan, a 192 MW project on the same nallah”. On being asked whether the project
authorities had sought a No Objection Certificate (NOC) from the Gram Sabha, Govind
says, it was all done under the blanket – without consent of the majority.
Penstock Burst at Sorang Nallah
http://www.hindustantimes.com/punjab/penstock-pipe-burst-at-himachal-hydro-project-
three-feared-dead/story-4JMjxYUOW9ciwSGDmB9ByL.html
At least three people were feared dead after a penstock pipe burst at the 100MW Sorang
Hydroelectric project at Burang village in Bhabanagar sub-division of Kinnaur district on
Wednesday night.
Two securities guards were reportedly buried in the muck while a local resident was
washed away. The gushing water also damaged the village path and the land adjoining the
project, besides destroying some makeshift houses.
The local administration also rushed to the spot at midnight to take stock of the situation.
SDM Nichar Neelam Dulta said efforts were on to rescue missing people.
“Relief material will be distributed to needy people today. Nothing can be said about the
incident right now,” she said.
The villagers have demanded action against the project. In the wake of tense situation,
police arrangements have also been made in the village.
http://www.hindustantimes.com/punjab/penstock-pipe-burst-at-himachal-hydro-project-three-feared-dead/story-4JMjxYUOW9ciwSGDmB9ByL.htmlhttp://www.hindustantimes.com/punjab/penstock-pipe-burst-at-himachal-hydro-project-three-feared-dead/story-4JMjxYUOW9ciwSGDmB9ByL.html
An Abu Dhabi National Energy Company, TAQA, was working on this project, which
was yet to be commissioned.
VI. Failures and Inadequacies in Planning, Impact Assessment, Monitoring and
Regulatory mechanisms
EIA and Cumulative Impact Assessment Studies not taking into account the impact of tunnels: No studies are conducted as a part of the Environment Impact
Assessment process to assess the geo-hydrological impacts of the tunneling and
blasting on the water sources.
Impact of quarrying – disturbing the stability of the land: This is a common feature
evident in areas where tunnelling work is being carried out. Yet there are absolutely no
independent studies being undertaken to look into the geological fragility and the
probable impacts on villages in the alignment of the tunnel and in constructions zones.
Local people have been raising these issues in Environment Clearance Public
hearings and the standard response from project proponents, that comes from
the denial of adverse impacts of tunneling, is that the incidences of drying of
water sources and cracks in houses will be monitored and videographed.
Unfortunately niether the EIA studies nor the Cumulative Impact Assessment studie not
look at tunnel impacts in the kind of detail required. The tunnel issue should also be
studied as part of carrying capacity and river basin level impact assessment studies that
should be an important part of planning hydropower development in an ecologically and
geologically fragile region but are not being carried out.
People affected by tunnels should be treated as project affected people/families in the Rehabilitation Plans:
Since the impact of tunneling as a project activity is not studied the villages in the
alignment of the tinnel are excluded from the definition ‘project-affected’ in project
reports, environment impact assessment studies and rehabilitation plans.To ensure a fair
compensation to families affected as a result of the loss of access to water sources or the
river itself as well as for any other kind of damages caused by the construction of the
tunnel it is critical that they be recognised as project affected people in all the reports.
Further, Like in case of Karcham Wangtoo HEP the money given to IPH for alternative arrangements for making water available, is from Local Area
Development Fund (LADF) which is actually for overall development of the
project affected area and not for the mitigation measures due to impact of the
project. The amount of compensation offered for cracks in houses is measly and
there are no provisions for rebuilding or relocation for the villagers who encounter
frequent landslides, erosion and cracks that have begun to appear in their houses
as a result of the underground blasting activities.
Recently, the Himachal State Disaster Management Authority in an advisory issued to the
Public Works Department, State Electricity Board and other hydro and road project
authorities, Deputy Commissioners in the wake of tunnel collapse while carrying out the
four-laning of Kiratpur-Nerchowk on September 12, stated that National Safety Council’s
safety norms should be followed while constructing tunnels for hydro-electric projects or
carving out roads.. The advisory states that topographical, geological and hydrological
parameters will be kept in mind before selecting tunnel sites. “The construction of all
tunnels shall be done as per the standard, norms and practices of Himalayan geology
which is young and fragile and if any geological changes are observed or encountered
during construction, necessary innovative and remedial measures will be incorporated in
the design,” the advisory reads. Government agencies will be mandated to check the
ongoing tunnel construction works periodically and the designs will be vetted by them.
(http://www.tribuneindia.com/news/himachal/community/now-geological-study-a-must-
for-tunnels/151686.html)
This establishes that there is a recognition of the impacts of tunneling, however, there is
need to study whether following of “safety norms” is an adeqauate response at this stage
where the scale of the activity is so large.
Key Demands
1. Carrying Capacity Studies on the river basin should be mandatory before allocation of Hydropower Projects. Until and unless such studies are conducted
along with Cumulative Impact Studies which assess the impacts of tunneling in
cascade of projects there should be a moratorium on further construction
2. The TORs for River Valley Projects involving tunnel construction should include 'Assessing the impacts of tunnels – both ecological and socio-economic' as part of
the EIA studies
3. Tunnel Affected communities should be included in the list of Project Affected Families and should be eligible for adequate compensation
4. Until an active Authority for Safety Control is established there should be a halt on further commissioning of projects
5. Projects that are violating safety guidelines and clearance conditions should be eligible for punitive action in a timely manner after issuance of show cause
notices. Penal action, rather than imposition of fines should be initiated in case of
forest offences. Compliance monitoring mechanisms need to be strengthened to
ensure regular inspections by PCB and regional authorities
6. There should be a scientific multi discplinary study of the probable geological and hydrological ramifications of the DBM in construction of tunnels and roads in
the Himalayan region needs to be conducted.
http://www.tribuneindia.com/news/himachal/community/now-geological-study-a-must-for-tunnels/151686.htmlhttp://www.tribuneindia.com/news/himachal/community/now-geological-study-a-must-for-tunnels/151686.html