91
A comparison of time-based maintenance and condition-based maintenance Bram de Jonge Ruud Teunter Warse Klingenberg Tiedo Tinga University of Groningen The Netherlands COPE congres 2013 November 1, 2013

A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

A comparison of time-based maintenance andcondition-based maintenance

Bram de Jonge Ruud TeunterWarse Klingenberg Tiedo Tinga

University of GroningenThe Netherlands

COPE congres 2013November 1, 2013

Page 2: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Introduction

We consider the following setting:

I A single unit.

I Gradual deterioration, condition monitoring is possible.

I The cost of a breakdown is 1, after which a new unit isputting into use.

I Preventive maintenance can be performed at cost c < 1 andmakes the unit as good as new.

Page 3: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Introduction

We consider the following setting:

I A single unit.

I Gradual deterioration, condition monitoring is possible.

I The cost of a breakdown is 1, after which a new unit isputting into use.

I Preventive maintenance can be performed at cost c < 1 andmakes the unit as good as new.

Page 4: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Introduction

We consider the following setting:

I A single unit.

I Gradual deterioration, condition monitoring is possible.

I The cost of a breakdown is 1, after which a new unit isputting into use.

I Preventive maintenance can be performed at cost c < 1 andmakes the unit as good as new.

Page 5: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Introduction

We consider the following setting:

I A single unit.

I Gradual deterioration, condition monitoring is possible.

I The cost of a breakdown is 1, after which a new unit isputting into use.

I Preventive maintenance can be performed at cost c < 1 andmakes the unit as good as new.

Page 6: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Introduction

We consider the following setting:

I A single unit.

I Gradual deterioration, condition monitoring is possible.

I The cost of a breakdown is 1, after which a new unit isputting into use.

I Preventive maintenance can be performed at cost c < 1 andmakes the unit as good as new.

Page 7: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Introduction

We consider the following setting:

I A single unit.

I Gradual deterioration, condition monitoring is possible.

I The cost of a breakdown is 1, after which a new unit isputting into use.

I Preventive maintenance can be performed at cost c < 1 andmakes the unit as good as new.

Page 8: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Maintenance policies

I Time-based maintenance (TBM)

I Easy to implement, no condition monitoring needed.

I Decision variable: T (maintenance age).

I Maintenance is performed when the unit reaches age T .

I Condition-based maintenance (CBM)

I Condition monitoring required, more appropriate scheduling.

I Decision variable: M (threshold deterioration level).

I Maintenance is performed when the deterioration level M isreached.

Page 9: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Maintenance policies

I Time-based maintenance (TBM)

I Easy to implement, no condition monitoring needed.

I Decision variable: T (maintenance age).

I Maintenance is performed when the unit reaches age T .

I Condition-based maintenance (CBM)

I Condition monitoring required, more appropriate scheduling.

I Decision variable: M (threshold deterioration level).

I Maintenance is performed when the deterioration level M isreached.

Page 10: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Maintenance policies

I Time-based maintenance (TBM)

I Easy to implement, no condition monitoring needed.

I Decision variable: T (maintenance age).

I Maintenance is performed when the unit reaches age T .

I Condition-based maintenance (CBM)

I Condition monitoring required, more appropriate scheduling.

I Decision variable: M (threshold deterioration level).

I Maintenance is performed when the deterioration level M isreached.

Page 11: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Maintenance policies

I Time-based maintenance (TBM)

I Easy to implement, no condition monitoring needed.

I Decision variable: T (maintenance age).

I Maintenance is performed when the unit reaches age T .

I Condition-based maintenance (CBM)

I Condition monitoring required, more appropriate scheduling.

I Decision variable: M (threshold deterioration level).

I Maintenance is performed when the deterioration level M isreached.

Page 12: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Maintenance policies

I Time-based maintenance (TBM)

I Easy to implement, no condition monitoring needed.

I Decision variable: T (maintenance age).

I Maintenance is performed when the unit reaches age T .

I Condition-based maintenance (CBM)

I Condition monitoring required, more appropriate scheduling.

I Decision variable: M (threshold deterioration level).

I Maintenance is performed when the deterioration level M isreached.

Page 13: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Maintenance policies

I Time-based maintenance (TBM)

I Easy to implement, no condition monitoring needed.

I Decision variable: T (maintenance age).

I Maintenance is performed when the unit reaches age T .

I Condition-based maintenance (CBM)

I Condition monitoring required, more appropriate scheduling.

I Decision variable: M (threshold deterioration level).

I Maintenance is performed when the deterioration level M isreached.

Page 14: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Maintenance policies

I Time-based maintenance (TBM)

I Easy to implement, no condition monitoring needed.

I Decision variable: T (maintenance age).

I Maintenance is performed when the unit reaches age T .

I Condition-based maintenance (CBM)

I Condition monitoring required, more appropriate scheduling.

I Decision variable: M (threshold deterioration level).

I Maintenance is performed when the deterioration level M isreached.

Page 15: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Maintenance policies

I Time-based maintenance (TBM)

I Easy to implement, no condition monitoring needed.

I Decision variable: T (maintenance age).

I Maintenance is performed when the unit reaches age T .

I Condition-based maintenance (CBM)

I Condition monitoring required, more appropriate scheduling.

I Decision variable: M (threshold deterioration level).

I Maintenance is performed when the deterioration level M isreached.

Page 16: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Maintenance policies

I Time-based maintenance (TBM)

I Easy to implement, no condition monitoring needed.

I Decision variable: T (maintenance age).

I Maintenance is performed when the unit reaches age T .

I Condition-based maintenance (CBM)

I Condition monitoring required, more appropriate scheduling.

I Decision variable: M (threshold deterioration level).

I Maintenance is performed when the deterioration level M isreached.

Page 17: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The state of the unit is assumed to deteriorate gradually accordingto a stationary/homogeneous gamma process X (t).

Properties:

I Continuous-time process.

I X (0) = 0 with probability 1.

I X (τ) − X (t) ∼ fa(τ−t),b for τ > t ≥ 0 (f is the gammadensity function).

I X (t) has independent increments.

I Jump process with infinitely many jumps in any time interval.

Page 18: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The state of the unit is assumed to deteriorate gradually accordingto a stationary/homogeneous gamma process X (t).

Properties:

I Continuous-time process.

I X (0) = 0 with probability 1.

I X (τ) − X (t) ∼ fa(τ−t),b for τ > t ≥ 0 (f is the gammadensity function).

I X (t) has independent increments.

I Jump process with infinitely many jumps in any time interval.

Page 19: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The state of the unit is assumed to deteriorate gradually accordingto a stationary/homogeneous gamma process X (t).

Properties:

I Continuous-time process.

I X (0) = 0 with probability 1.

I X (τ) − X (t) ∼ fa(τ−t),b for τ > t ≥ 0 (f is the gammadensity function).

I X (t) has independent increments.

I Jump process with infinitely many jumps in any time interval.

Page 20: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The state of the unit is assumed to deteriorate gradually accordingto a stationary/homogeneous gamma process X (t).

Properties:

I Continuous-time process.

I X (0) = 0 with probability 1.

I X (τ) − X (t) ∼ fa(τ−t),b for τ > t ≥ 0 (f is the gammadensity function).

I X (t) has independent increments.

I Jump process with infinitely many jumps in any time interval.

Page 21: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The state of the unit is assumed to deteriorate gradually accordingto a stationary/homogeneous gamma process X (t).

Properties:

I Continuous-time process.

I X (0) = 0 with probability 1.

I X (τ) − X (t) ∼ fa(τ−t),b for τ > t ≥ 0 (f is the gammadensity function).

I X (t) has independent increments.

I Jump process with infinitely many jumps in any time interval.

Page 22: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The state of the unit is assumed to deteriorate gradually accordingto a stationary/homogeneous gamma process X (t).

Properties:

I Continuous-time process.

I X (0) = 0 with probability 1.

I X (τ) − X (t) ∼ fa(τ−t),b for τ > t ≥ 0 (f is the gammadensity function).

I X (t) has independent increments.

I Jump process with infinitely many jumps in any time interval.

Page 23: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The state of the unit is assumed to deteriorate gradually accordingto a stationary/homogeneous gamma process X (t).

Properties:

I Continuous-time process.

I X (0) = 0 with probability 1.

I X (τ) − X (t) ∼ fa(τ−t),b for τ > t ≥ 0 (f is the gammadensity function).

I X (t) has independent increments.

I Jump process with infinitely many jumps in any time interval.

Page 24: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The state of the unit is assumed to deteriorate gradually accordingto a stationary/homogeneous gamma process X (t).

Properties:

I Continuous-time process.

I X (0) = 0 with probability 1.

I X (τ) − X (t) ∼ fa(τ−t),b for τ > t ≥ 0 (f is the gammadensity function).

I X (t) has independent increments.

I Jump process with infinitely many jumps in any time interval.

Page 25: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The stationary gamma process has two parameters:

I Shape parameter a.

I Scale parameter b.

Properties:

I E (X (t)) = abt.

I Var(X (t)) = ab2t.

A breakdown is assumed to occur if the level of deteriorationexceeds 1.

We choose a and b such that the mean time to failure equals 1(this does not imply ab = 1).

Page 26: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The stationary gamma process has two parameters:

I Shape parameter a.

I Scale parameter b.

Properties:

I E (X (t)) = abt.

I Var(X (t)) = ab2t.

A breakdown is assumed to occur if the level of deteriorationexceeds 1.

We choose a and b such that the mean time to failure equals 1(this does not imply ab = 1).

Page 27: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The stationary gamma process has two parameters:

I Shape parameter a.

I Scale parameter b.

Properties:

I E (X (t)) = abt.

I Var(X (t)) = ab2t.

A breakdown is assumed to occur if the level of deteriorationexceeds 1.

We choose a and b such that the mean time to failure equals 1(this does not imply ab = 1).

Page 28: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The stationary gamma process has two parameters:

I Shape parameter a.

I Scale parameter b.

Properties:

I E (X (t)) = abt.

I Var(X (t)) = ab2t.

A breakdown is assumed to occur if the level of deteriorationexceeds 1.

We choose a and b such that the mean time to failure equals 1(this does not imply ab = 1).

Page 29: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The stationary gamma process has two parameters:

I Shape parameter a.

I Scale parameter b.

Properties:

I E (X (t)) = abt.

I Var(X (t)) = ab2t.

A breakdown is assumed to occur if the level of deteriorationexceeds 1.

We choose a and b such that the mean time to failure equals 1(this does not imply ab = 1).

Page 30: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The stationary gamma process has two parameters:

I Shape parameter a.

I Scale parameter b.

Properties:

I E (X (t)) = abt.

I Var(X (t)) = ab2t.

A breakdown is assumed to occur if the level of deteriorationexceeds 1.

We choose a and b such that the mean time to failure equals 1(this does not imply ab = 1).

Page 31: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The stationary gamma process has two parameters:

I Shape parameter a.

I Scale parameter b.

Properties:

I E (X (t)) = abt.

I Var(X (t)) = ab2t.

A breakdown is assumed to occur if the level of deteriorationexceeds 1.

We choose a and b such that the mean time to failure equals 1(this does not imply ab = 1).

Page 32: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

The stationary gamma process has two parameters:

I Shape parameter a.

I Scale parameter b.

Properties:

I E (X (t)) = abt.

I Var(X (t)) = ab2t.

A breakdown is assumed to occur if the level of deteriorationexceeds 1.

We choose a and b such that the mean time to failure equals 1(this does not imply ab = 1).

Page 33: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

0

1

X(t)

0 1t

Page 34: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

0

1

X(t)

0 1t

Low a, high b

Page 35: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

0

1

X(t)

0 1t

Low a, high b

High a, low b

Page 36: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Gamma deterioration process

0

1

X(t)

0 1t

Low a, high b

High a, low b

In between

Page 37: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Research methodology

Simulation:

I Exact calculations are practically impossible.

I If the number of iterations is sufficiently high, the outcomesare very accurate.

I Simulation details:I Time step: ∆ = 0.01.I Number of iterations: n = 100,000.

Page 38: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Research methodology

Simulation:

I Exact calculations are practically impossible.

I If the number of iterations is sufficiently high, the outcomesare very accurate.

I Simulation details:I Time step: ∆ = 0.01.I Number of iterations: n = 100,000.

Page 39: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Research methodology

Simulation:

I Exact calculations are practically impossible.

I If the number of iterations is sufficiently high, the outcomesare very accurate.

I Simulation details:I Time step: ∆ = 0.01.I Number of iterations: n = 100,000.

Page 40: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Research methodology

Simulation:

I Exact calculations are practically impossible.

I If the number of iterations is sufficiently high, the outcomesare very accurate.

I Simulation details:I Time step: ∆ = 0.01.I Number of iterations: n = 100,000.

Page 41: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Research methodology

Simulation:

I Exact calculations are practically impossible.

I If the number of iterations is sufficiently high, the outcomesare very accurate.

I Simulation details:I Time step: ∆ = 0.01.I Number of iterations: n = 100,000.

Page 42: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Base case

Gamma deterioration process:

I a = 5, b ≈ 0.2246.

Relative cost preventive maintenance:

I c = 0.2.

Page 43: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Base case

Gamma deterioration process:

I a = 5, b ≈ 0.2246.

Relative cost preventive maintenance:

I c = 0.2.

Page 44: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Base case

Gamma deterioration process:

I a = 5, b ≈ 0.2246.

Relative cost preventive maintenance:

I c = 0.2.

Page 45: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost saving CBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Page 46: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost saving CBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Page 47: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

0

1

Cost

0 1T or M

Page 48: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost saving CBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Page 49: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

0

1

Cost

0 1T or M

Page 50: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

0

1

Cost

0 1T or M

TBM

Page 51: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost saving CBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Page 52: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

0

1

Cost

0 1T or M

TBM

Page 53: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

0

1

Cost

0 1T or M

TBM

CBM

Page 54: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Cost saving CBM

Page 55: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Cost saving CBM

Page 56: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Effect of deterioration process

0

1

Cost

0 5σ

Page 57: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Effect of deterioration process

0

1

Cost

0 5σ

TBM

Page 58: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Effect of deterioration process

0

1

Cost

0 5σ

TBM

CBM

Page 59: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost benefit CBM compared with TBM

0

0.25

Cost

0 5σ

Page 60: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Cost saving CBM

Page 61: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Planning time

I Preventive maintenance needs to be planned s time units inadvance.

I The cost c of preventive maintenance does not have to bepaid if failure occurs between the moment that maintenance isplanned and the moment that maintenance would have beenperformed.

I Under the CBM policy, maintenance is performed at timet(M) + s, with t(M) the time at which deterioration level Mis reached.

I The planning time s has no influence on the TBM policy.

Page 62: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Planning time

I Preventive maintenance needs to be planned s time units inadvance.

I The cost c of preventive maintenance does not have to bepaid if failure occurs between the moment that maintenance isplanned and the moment that maintenance would have beenperformed.

I Under the CBM policy, maintenance is performed at timet(M) + s, with t(M) the time at which deterioration level Mis reached.

I The planning time s has no influence on the TBM policy.

Page 63: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Planning time

I Preventive maintenance needs to be planned s time units inadvance.

I The cost c of preventive maintenance does not have to bepaid if failure occurs between the moment that maintenance isplanned and the moment that maintenance would have beenperformed.

I Under the CBM policy, maintenance is performed at timet(M) + s, with t(M) the time at which deterioration level Mis reached.

I The planning time s has no influence on the TBM policy.

Page 64: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Planning time

I Preventive maintenance needs to be planned s time units inadvance.

I The cost c of preventive maintenance does not have to bepaid if failure occurs between the moment that maintenance isplanned and the moment that maintenance would have beenperformed.

I Under the CBM policy, maintenance is performed at timet(M) + s, with t(M) the time at which deterioration level Mis reached.

I The planning time s has no influence on the TBM policy.

Page 65: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Planning time

I Preventive maintenance needs to be planned s time units inadvance.

I The cost c of preventive maintenance does not have to bepaid if failure occurs between the moment that maintenance isplanned and the moment that maintenance would have beenperformed.

I Under the CBM policy, maintenance is performed at timet(M) + s, with t(M) the time at which deterioration level Mis reached.

I The planning time s has no influence on the TBM policy.

Page 66: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Planning time

0

1

Cost

0 1T or M

TBM

CBM (s=0)

Page 67: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Planning time

0

1

Cost

0 1T or M

TBM

CBM (s=0)

CBM (s=0.1)

Page 68: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Planning time

0

0.6Cost

0 0.5s

Page 69: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Planning time

0

0.6Cost

0 0.5s

TBM

Page 70: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Planning time

0

0.6Cost

0 0.5s

TBM

CBM

Page 71: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Cost saving CBM

Page 72: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Cost saving CBM

Page 73: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Imperfect condition monitoring

I The difference between the true level of deterioration and theobserved level of deterioration is modelled by σpW (t).

I W (t) is a standard Brownian motion.

Page 74: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Imperfect condition monitoring

I The difference between the true level of deterioration and theobserved level of deterioration is modelled by σpW (t).

I W (t) is a standard Brownian motion.

Page 75: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Imperfect condition monitoring

I The difference between the true level of deterioration and theobserved level of deterioration is modelled by σpW (t).

I W (t) is a standard Brownian motion.

Page 76: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Imperfect condition monitoring

−0.4

0.0

0.4

Progn

osticerror

0 1t

Low σp

Page 77: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Imperfect condition monitoring

−0.4

0.0

0.4

Progn

osticerror

0 1t

High σp

Page 78: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Imperfect condition monitoring

0

0.6Cost

0 0.5σp

Page 79: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Imperfect condition monitoring

0

0.6Cost

0 0.5σp

TBM

Page 80: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Imperfect condition monitoring

0

0.6Cost

0 0.5σp

TBM

CBM

Page 81: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Cost saving CBM

Page 82: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Cost saving CBM

Page 83: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Uncertainty deterioration level failure

I The deterioration level at which failure occurs is normallydistributed with mean 1 and standard deviation σf .

I The normal distribution is left truncated at 0 and righttruncated at 2.

Page 84: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Uncertainty deterioration level failure

I The deterioration level at which failure occurs is normallydistributed with mean 1 and standard deviation σf .

I The normal distribution is left truncated at 0 and righttruncated at 2.

Page 85: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Uncertainty deterioration level failure

I The deterioration level at which failure occurs is normallydistributed with mean 1 and standard deviation σf .

I The normal distribution is left truncated at 0 and righttruncated at 2.

Page 86: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Uncertainty deterioration level failure

0

0.8

Cost

0 0.5σf

Page 87: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Uncertainty deterioration level failure

0

0.8

Cost

0 0.5σf

TBM

Page 88: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Uncertainty deterioration level failure

0

0.8

Cost

0 0.5σf

TBM

CBM

Page 89: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Cost saving CBM

Page 90: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Cost analysis

Failure cost = 1

Cost saving TBM

Cost due to uncertain failure levelCost due to imperfect condition monitoring

Cost due to maintenance planning

Cost due to noncontinuous deterioration informationCost due to deterioration process with jumps

Minimal cost (PM just before failure) = c

Cost saving CBM

Page 91: A comparison of time-based maintenance and condition-based … · 2016. 10. 19. · putting into use. I Preventive maintenance can be performed at cost c

Questions?

[email protected]