Upload
tanay-ambavane
View
218
Download
0
Embed Size (px)
Citation preview
8/4/2019 A Functional Design Brief (July 2009)
1/6
Queens Wharf Passenger Cruise Terminal
Final Design BriefJuly 2009
8/4/2019 A Functional Design Brief (July 2009)
2/6
Aerial of Queens Wharf with existing sheds and cart dock
Que
en
s W
ha
r
f C
r
uis
e Te
r
min
al: D
esi
gn P
ar
ame
t
e
r
s
This design brief has been informed by the information gathered through the Auckland Cruise
Terminal Project, including:
Understanding and reviewing the cruise operational activities on Princes Wharf and Queens
Wharf
Desk top research on international cruise terminals
Engaging with the cruise sector - Ports of Auckland (Marine Services Staff), Ministry of
Agriculture (Biosecurity), New Zealand Customs Service, ID Tours, ISS Mackay Shipping and
Carnival Australia.
Obje
ctiv
e
s
The development of any new terminal and supporting wharf space needs to be fit for cruise
purposes. The development of the four options in this document has been informed by the
objectives listed below:
That the building and supporting wharf space be fit for cruise purposes and be able to provide
for the future growth of the cruise industry
That the building and supporting wharf space be designed in a manner that allows the agencies
involved to efficiently process passengers, crew and the cruise vessel
That the building be designed to allow for two-way activity, i.e. be able to processes both
embarking and disembarking passengers and crew
The building be of sufficient size to providing suitable and comfortable holding facilities for
passengers
That the building be designed to separate out passengers and cruise related activities for
safety, security and servicing purposes (separate entry/exits for embarking and disembarking
can assist this)
That the building be designed to allow for differing levels of finish, depending on the final use
That where possible the building edges must be active, attractive and welcoming during and
outside of cruise visits
That the building and operational area can be secured during cruise visits to meet national and
international security standards
That the building be multifunctional, i.e. be able to support other/compatible uses outside of
the cruise season. For multipurpose uses, service elevators are needed that can operate fromeach end of the building (at both the disembarking and the embarking end, or to cater for
different functions or seminars scheduled at the same time)
The major spaces of the building need to be large, simple, flexible floor spaces with movable
partitioning to enable re-configuration of equipment and furniture to facilitate various layouts of
passenger processing, baggage handling and different sized functions and seminars
Cool Store Cart Dock Shed 10
9m 24m 17m 24m 9m
8/4/2019 A Functional Design Brief (July 2009)
3/6
D
e
si
gn Param
eter
s
The existing structure of the wharf has determined the design of the proposed building envelope in
the four options. The level differences on the wharf with the original cart dock down the middle
(see aerial) are about 1.5 meters lower than the shed-platforms on either side and have prescribed
the footprint of the new terminal building.
The building cannot be wider than Shed 10 because of this (unless considerable cost is allowed for
to adjust the wharf itself) but the new terminal building can be longer and it could have more levels.
The cart dock is ideal to accommodate coaches and taxis parking and moving in two directions for
use of the terminal.
Although there is no single model for developing a cruise terminal, there are common elements
that need to be incorporated into the design of the building that make it fit for cruise purposes.
This work has concluded that the following design parameters must be built in to a cruise terminal
design brief:
F
lo
or
D
e
s
c
r
ip
ti
o
n
No
te
Ground Floor Terminal Building:
Entrance lobby for embarking
passengers and an exit lobby for
disembarking passengers
Baggage drop and handling area
Lifts, elevators and stairs to the first
floor
Storage space for equipment, (e.g. x-
ray screening)
Supporting wharf area:
Supporting turning circles and
queuing for buses, coaches, taxis,
shuttles
Space for re-provisioning the vessel
on a secured 10 20 metre strip
from the wharf edge
The quality of finish in the baggage handling
area should be of a moderate quality. This
area is not public facing so will not require
the same standard of finish as that provided
on the first and second floors
Shelter is needed for those passengers
waiting for coaches and taxis. Building
overhangs need to be integrated to the
design
First Floor Passenger check in zone
(MAF/Customs/Cruise check in)
Passenger waiting area of a sufficient
size to hold passengers and crew
waiting to embark with seats, WCs,
and refreshment areas
Lifts and stairs to the ground and
second floor at each end, central
escalator for major flows
Storage space for equipment
A connecting concourse and
gangways
Passengers must be separated from
operational areas on the ground floor
On this level is it expected that the finish of
the interior is of a high quality
Cruise companies prefer two gangways for
passenger safety
There should be flexibility to process forembarkation and disembarkation at variable
rates
At other times the major space should be
sub-dividable for functions
Second Floor A space (e.g. caf and/or restaurant)
that can be accessible to the public
during cruise visits with outside deck
Lifts, elevators and stairs to the
ground and first floor
Public access during cruise visits needs to
be carefully managed for security purposes
Cruise passengers and general public can
mix on the second floor but not on the first
floor or ground floors
8/4/2019 A Functional Design Brief (July 2009)
4/6
C
on
clusions Ab
out Optim
al S
iz
e and Sp
a
c
e
This work has concluded that for a single berth on Queens Wharf:
A terminal building of 6000 square meters (option one) would be suitable for a dedicated cruise
terminal building that can process one vessel (up to 3000 passengers and crew)
A terminal building of 8000 square meters (option two) would b e suitable for a multi purpose
facility that can process one vessel and have sufficient space to host other events.
Not
e:
More work is needed on optimal internal building flows in association with the cruise sector,
but a key aspect is that the internal spaces should be flexible to allow for change over the
course of a ship visit, for different types of ship visits (transit/exchange, etc) or as processing
security systems change over time
This project provides opportunity to demonstrate practical responses to sustainable design,
construction and operation. The final product should be able to incorporate low impact design
features and green building practices to achieve a minimum five Green Star performance rating
(or equivalent).
Internati
onal Example
s
Desk top research on other cities indicates that new cruise facilities are averaging over 8500 m2
In
t
e
rna
t
ion
al E
x
a
m
p
le
s
D
e
sc
r
ipt
io
n
To
t
a
l f
lo
o
r ar
e
a
o
f t
h
e bui
ld
ing
B
e
r
th
Le
n
g
t
h
Southampton Ocean
Terminal Brand new terminal, completed in 2009. One
of four in Southampton. New terminal capable
of handling 4000 passengers
Terminal not designed for multipurpose use,
but can accommodate such as required
9100 m2 480 meters
Amsterdam
Passenger Terminal
Amsterdam
Established terminal, one of four in
Amsterdam
Used as a multi purpose facility (conferences,
exhibitions, events)
15,000 m2 600 meters
Barcelona -
Palacurceros terminal
Purpose built terminal, exclusive for Carnival
Not a multi purpose facility, but generous
space provided for passenger services
10,000 m2 580 meters
Savona Palacrociere
terminal Purpose built terminal
Multi purpose facility, space provided for a
conference room (host up to 200 people)
8,500 m2 430 meters
New York - Brooklyn
Cruise terminal Brand new terminal, dedicated cruise use
Designed to handle 4000 passengers
18,500 m2 345 meters
Queens Wharf Ferry building and red fence Eastside of Shed 10 looking to the South
Shed 10 with Cart Dock Queens Wharf and shed 10 from the harbour
8/4/2019 A Functional Design Brief (July 2009)
5/6
QUEENS WHARF PASSENGER CRUISE TERMINAL -Dat e: 0 3- 07 -2 00 9 S ca le N /A S he et 1 o f 4
Option 1 - 6,000m2 Dedicated Terminal - Single Berth
Wharf - Taxi/Car Passenger Pick Up
Wharf - Taxi strip
Wharf - Coach Bus strip
Wharf - Container Area (Cruise Call)
Wharf - Quay Secure Area Cruise Call
First floor - Service Core
Ground floor - Embarkation entrance
Ground floor - Service Core
Ground floor - Debarkation hall
First floor - Concourse ca. 110m
First floor - 2 Gangways Western Berth
First floor - Check-in and Waiting area
Second floor - Cafe Balcony / PromenadeSecond floor - Service Core
Second floor - Cafe/Restaurant Area
Second floor-Public Fare well Promenade
Ground floor - Baggage Handling Area
8/4/2019 A Functional Design Brief (July 2009)
6/6
QUEENS WHARF PASSENGER CRUISE TERMINAL -Dat e: 0 3- 07 -2 00 9 S ca le N /A S he et 2 o f 4
Option 2 - 8,000m2 Terminal + Multi Purpose floor area - Single Berth
Wharf - Taxi/Car Passenger Pick Up
Wharf - Parking Taxi strip
Wharf - Parking Coache Bus strip
Wharf - Container Area (Cruise Call)
Wharf - Quay Secure Area Cruise Call
Second floor - Multi Purpose Centre
First floor - Service Core
Ground floor - Embarkation hall
Ground floor - Service Core
Ground floor - Debarkation hall
First floor - Concourse 110 m
First floor - 2 Gangways Western Berth
First floor - Check-in and Waiting Area
Second floor - Service Core
Second floor - Cafe/Restaurant Area
Second floor-Public Fare well Promenade
Ground floor - Baggage Handling Area