TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I Tender Notice No: A-17012/003/2020-CR Page 1 of 125 Signature of Contractor with seal TIDEL PARK COIMBATORE LTD. (A JV of TIDCO, ELCOT, TIDEL & STPI) INFORMATION TECHNOLOGY PARK BUILDING COMPLEX AT ELCOSEZ, COIMBATORE – 641 014 VOLUME – I Technical Bid (Technical Bid - Conditions of Contract, Special Conditions, Scope of Work & Pre-Qualification) TENDER FOR INTEGRATED OPERATIONS & NON-COMPREHENSIVE MAINTENANCE OF AIR CONDITIONING & MECHANICAL VENTILATION SYSTEM (ACMV), BUILDING AUTOMATION SYSTEM (BAS), DIESEL GENSET (DG) & CONNECTED WORKS Tender No: A-17012/003/2020-CR Date of Issue: 14-12-2020 Date for Online Submission through website https://tntenders.gov.in/) On or before 12-01-2021 before 3.00 p.m. DECEMBER 2020

(A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 1 of 125 Signature of Contractor with seal

TIDEL PARK COIMBATORE LTD. (A JV of TIDCO, ELCOT, TIDEL & STPI)

INFORMATION TECHNOLOGY PARK BUILDING COMPLEX AT

ELCOSEZ, COIMBATORE – 641 014

VOLUME – I Technical Bid

(Technical Bid - Conditions of Contract, Special Conditions, Scope of Work & Pre-Qualification)

TENDER FOR INTEGRATED OPERATIONS & NON-COMPREHENSIVE

MAINTENANCE OF AIR CONDITIONING & MECHANICAL VENTILATION SYSTEM (ACMV), BUILDING AUTOMATION SYSTEM (BAS), DIESEL

GENSET (DG) & CONNECTED WORKS

Tender No: A-17012/003/2020-CR

Date of Issue: 14-12-2020

Date for Online Submission through

website https://tntenders.gov.in/)

On or before 12-01-2021 before

3.00 p.m.

DECEMBER 2020

Page 2: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 2 of 125 Signature of Contractor with seal

Volume – I

(CONDITIONS OF CONTRACT, SPECIAL CONDITIONS, SCOPE OF WORK AND PRE-

QUALIFICATION CRITERIA)

INDEX

Sl.No. Particulars Page

Nos.

1. Tender Notice 3

2. Contract Data 4

3. About TIDEL Park Coimbatore 5

4. General Instructions 6

5. Conditions of Contract 17

6. Pre-Qualification Criteria 34

7. Scope of Work 36

8. Quarterly Performance Evaluation 71

9. Tender Acceptance Letter 72

10. Article of Agreement 74

11. Form of Performance Guarantee 78

12. Special Conditions 80

13. Formats 87

14. Hand Book on Health & Safety at work 112

15. Conditions of BOQ 121

16. Insurance 122

Page 3: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 3 of 125 Signature of Contractor with seal

1.TENDER NOTICE

Tender Notice has been released in dailies in on 14.12.2020

and copy of the same is reproduced below:

Page 4: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 4 of 125 Signature of Contractor with seal

2. Contract Data

Tender Document Begins on 14-12-2020 & will close on 12-01-2020

1. Method of Tender Open Tender System (e-tender process) (Online submission of Vol-I (Technical Bid) and Vol-II (Financial Bid-BOQ) through Website https://tntenders.gov.in/

2. Document Cost Nil

3. Earnest Money Deposit Rs. Two Lakhs only

4. URL for online bid submission for e-tender

https://tntenders.gov.in

5. Date, Time & Venue of Pre-bid Meeting

21-12-2020 at 3.00 PM at TIDEL Park Coimbatore Ltd., I Floor, ELCOSEZ, Aerodrome Post, Coimbatore – 641 014. Clarifications can also be sought through e-mail before 3.00 PM on 21.12.2020. email id: [email protected] / [email protected].

6. Date of closing of online e-tender for submission of Technical and Financial Bids-BOQ

12-01-2021 upto 3.00 P.M

7. Date & time of opening of

technical tender electronically

13-01-2021 / 4.00 P.M

8. Documents to be uploaded Technical Bid with necessary annexures and other documents

(Vol-I)

Price Bid should be quoted in BOQ (Vol.II).

9. Tender Validity 90 days from the date of opening of price bid

10. Date of commencement of

work

Ten days from issue of LoA

11. Period of Contract One year, renewable every year for upto 3 years with

escalation of 5% on the total contract value, subject to

satisfactory performance of the contractor as decided by TPCL.

12. Performance Bond

An amount equivalent to 10% of annual contract value in the

form of Bank guarantee from any nationalized/ scheduled bank

valid for the contract period. The Bank Guarantee shall be valid

upto One year with additional irrevocable period of six months

from the date of completion of the job and due fulfillment of

the contract. If the contract is renewed, the contractor should

renew the Bank Guarantee for every renewed contract period

with additional irrevocable period of six months.

13. Solvency Certificate Rs.80 Lakhs issued by any scheduled commercial bank

and should not have been obtained earlier than 3

months from the date of issue of tender.

14. Signing of Agreement The Contract is concluded by issuing LoA and the Contractor

has to comply the requirements as per the Tender including

signing of agreement within 15 days from the date of LoA.

Page 5: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 5 of 125 Signature of Contractor with seal

3. ABOUT TIDEL PARK COIMBATORE

IT – PARK (SEZ)

TIDEL Park Coimbatore Ltd., a Joint Venture of Tamil Nadu Industrial Development

Corporation (TIDCO) and Electronics Corporation of Tamil Nadu (ELCOT), TIDEL Park

Ltd. and Software Technology Parks of India (STPI) has constructed a State-of-the-Art

Multistoried Intelligent Building, with built up area of 1.7 million Sq.ft., located at

ELCOSEZ, Aerodrome Post, Coimbatore and provides quality business space for 12,000

IT Professionals.

Page 6: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 6 of 125 Signature of Contractor with seal

4. GENERAL INSTRUCTIONS

1. Preamble:

The bidding under this contract is electronic bid submission through website

https://tntenders.gov.in/ only. Detailed guidelines for viewing bids, enrollment and

submission of online bids are given on the website. The tender notice and documents

are also available in https://tidelcbe.com. Prospective bidders can logon to this website

and can find TPCL tender by searching the menu “Tender by Organisation”. The website

https://tntenders.gov.in also has “bidder manual kit” with detailed guidelines on

enrollment and participation in the online bidding process. The user manuals can be

downloaded for ready reference. Queries pertaining to the e-tendering system may be

addressed to the E-Tender Cell by sending an E-Mail to [email protected].

2. Registration:

i) The bidders can enroll themselves on the website https://tntenders.gov.in using

the “Online Bidder Enrollment”. This enrollment is free at this point of time.

ii) The bidders are required to have enrollment/registration in the website by clicking

on the link “Online bidder enrollment” which is free of charge.

iii) As part of the enrollment process, the bidders are required to choose a unique

username and assign a password for their accounts.

iv) Bidders are advised to register their valid email address and mobile numbers as

part of the registration process. These details would be used for any

communication from the e-Portal.

v) Possession of valid Digital Signature Certificate (DSC) (Class III Certificates

as per NIC guidelines with signing key usage) in the Company’s name issued by

any Certifying Authority recognized by CCA India (e.g. Sify / nCode / eMudhra

etc.), is a prerequisite for registration and participation in the bid submission

activities.

vi) Only one valid DSC should be registered by a bidder. Please note that the bidders

are responsible to ensure that they do not lend their DSC to others which may

lead to misuse.

vii) Bidder can login to the site through the secured login by entering their user ID /

password and the password of the DSC / e-Token.

viii) The website also has user manuals with detailed guidelines on enrollment and

participation in the online bidding process which can be downloaded for ready

reference.

ix) Correspondence details:

For queries related to registration and online bidding (NIC): e-mail : [email protected] Contact No.: 044 – 24466495 24902580

Extn : 332 24917850

For queries related to tender enquiry / specification: 1) 0422-2513605 2) Email: [email protected]

[email protected]

Page 7: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 7 of 125 Signature of Contractor with seal

3. Searching for Tender Documents

i) After successfully logging in, bidder will be able to view the Dashboard of their

profile. Click Search Active Tenders on the left side of the page to search the

tenders.

ii) Once the bidder has selected and preferred the tender they are interested in, they

can select “My Tenders‟ menu, wherein the bidders can view and download the

Technical Bid (Vol.I) and BOQ (Vol.II). This would enable the Tamil Nadu Govt. e-

Procurement Portal, to intimate the bidders through SMS / e-mail in case there is

any corrigendum issued to the tender document.

iii) The bidder should make a note of the unique Tender ID assigned to each tender,

in case they want to obtain any clarification / help from the Helpdesk (NIC).

4. Preparation of Bids

i) Bidder should take into account any corrigendum published on the tender

document before submitting their bids.

ii) Bidders are requested to go through the NIT and the tender document carefully to

understand the documents required to be submitted as part of the bid. Please note

the number of covers in which the bid documents have to be submitted, the

number of documents including the names and content of each of the document

that need to be submitted. Any deviations from these may lead to rejection of the

bid.

iii) Bidder, in advance, should keep ready the bid documents to be submitted as

indicated in the tender document and generally, they can be in PDF / XLS formats.

Bid documents may be scanned with 100 dpi with black and white option

which helps in reducing size of the scanned document.

iv) To avoid the time and effort required in uploading the same set of standard

documents which are required to be submitted as a part of every bid, a provision

of uploading such standard documents (e.g. PAN card copy, annual reports,

auditor certificates etc.) has been provided to the bidders. Bidders can use “My

space or “Other Important Documents” area available to them to upload such

documents. These documents may be directly submitted from the “My Space” area

while submitting a bid, and need not be uploaded again and again. This will lead

to a reduction in the time required for bid submission process. Anyhow, over and

above the documents available in “my space” option, it is the sole responsibility

of the bidder to ensure uploading/submitting the required documents as called for

in the tender.

v) The completed bid comprising scanned copy of necessary technical and

commercial documents should be uploaded on the website along with signed and

scanned copies of requisite certificates, mentioned in the different sections in the

tender document, with necessary attestation wherever called for, in the tender.

vi) The bidder should submit the bid in two volumes:

Page 8: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 8 of 125 Signature of Contractor with seal

The first volume relates to Technical Bid submitting all the required details and

documents complying with all the eligibility conditions and the other tender

conditions/instructions in PDF Format.

The second volume relates to Financial Bid (BOQ) furnishing the rate for each

item in XLS Format.

5. Electronic submission of Bids:

The bidder shall submit online the requirements under qualification criteria, the

Technical Documents required and Price Schedule/BOQ. All the documents are

required to be signed digitally by the bidder. After electronic online bid submission,

the system generates a unique bid reference number which is time stamped. This shall

be treated as acknowledgement of bid submission.

6. Procedure for submission of bids:

i) Bidder should log into the site well in advance for bid submission so that they can

upload the bid in time i.e. on or before the bid submission time. Bidder will be

responsible for any delay due to other issues.

ii) After successfully logging in, bidder will be able to view the Dashboard of their

profile. Click Search Active Tenders on the left side of the page to search the

tenders.

iii) A tender searched using "Organization" search criteria can be made as “Favorite”.

Check the field under favorite and click Save. The tender is made as your favorite.

The tenders gets moved to “My Tenders”. Click My Tenders from the menu in the

left side of the page. The tenders made as favorite gets displayed. Click View to

view the details of a particular tender

iv) The bidder has to digitally sign and upload the required bid documents one by one

as indicated in the tender document.

v) Bidder has to select the payment option as “pay online” to pay the EMD amount.

Only after payment of EMD, bidder will be able to encrypt/upload their bids. In

order to avoid last minute lapses, it is recommended to make payment and submit

the bid as early as possible. The contracting authority is not responsible for any

sort of difficulty faced/failure in submission of bids online by the bidder.

vi) A BOQ format for the price bid has been provided with the tender document to be

filled by all the bidders. Bidders are requested to note that they should necessarily

submit their financial bids in the BOQ format provided and no other format is

acceptable. Bidders are required to download the BOQ file, open it and complete

the coloured (Unprotected) cells with their respective financial quotes and other

details (such as name of the bidder). No other cells should be changed. Once the

details have been completed, the bidder should save it and submit it online,

without changing the file name. If the BOQ file is found to be modified by the

bidder, the bid will be rejected.

Page 9: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 9 of 125 Signature of Contractor with seal

vii) The server time (which is displayed on the bidders‟ dashboard) will be

considered as the standard time for referencing the deadlines for

submission of the bids by the bidders, opening of bids etc. The bidders

should follow this time during bid submission.

viii) All the documents being submitted by the bidders would be encrypted using PKI

encryption techniques to ensure the secrecy of data. The data entered cannot be

viewed by unauthorized persons until the time of bid opening. Any bid document

that is uploaded to the server is subjected to symmetric encryption using a system

generated symmetric key. Further this key is subjected to asymmetric encryption

using buyers/bid openers‟ public keys.

ix) The uploaded tender documents become readable only after the tender opening

by the authorized bid openers.

x) Upon the successful and timely submission of bids, (i.e. after clicking “Freeze Bid

submission” in the portal) the portal will give a successful bid submission message

& a bid summary will be displayed with the bid no. and the date & time of

submission of the bid with all other relevant details.

xi) The bidder is responsible to ensure they have sufficient time to submit an

electronic bid prior to closing date and time including the payment of any fees

including the Bid security and getting e-receipt. Contracting authority is not

responsible for any failure, outside their control.

xii) TIDEL Park Coimbatore may, at its discretion, extend the deadline for the

submission of bids by amending the bidding document, in which case all rights

and obligations of TIDEL Park Coimbatore and bidders subject to the previous

deadline shall thereafter be subject to the extended deadline.

7. Late Bids

The Electronic bidding system would not allow any late submission of bids after

due date and time as per server time.

8. Modification and withdrawal of bids:

i) Bidders may modify their bids online before the deadline for submission of bids.

ii) In case a bidder intends to modify his bid online before the deadline, the bidder

need not make any additional payment towards the cost of bid processing. For bid

modification and consequential re-submission, the bidder is not required to

withdraw his bid submitted earlier. Modification and consequential re-submission

of bids is allowed any number of times. The last modified bid submitted by the

bidder within the bid submission time shall be considered as the bid. For this

purpose, modification/withdrawal by other means will not be accepted. The bidder

may withdraw his bid by uploading his request before the deadline for submission

of bids, however, if the bid is withdrawn, the re-submission of the bid is not

allowed.

iii) No bid may be modified after the deadline for submission of Bids.

Page 10: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 10 of 125 Signature of Contractor with seal

9. Assistance to Bidders:

Any queries relating to the tender document and the terms and conditions

contained therein should be addressed to the Tender Inviting Authority for a tender

or the relevant contact person indicated in the tender.

Any queries relating to the process of online bid submission or queries in general

may be directed to the 24x7 Central Public Procurement Portal Helpdesk.

10. TPCL does not bind itself to accept the lowest or any tender and reserve to itself

the right to accept or reject any or all the tenders, either in whole or in part, without

assigning any reasons for doing so.

Offers of Bidders who are under suspension / termination / banned / blacklisted by

any PSU / Govt. Dept. or otherwise shall not be considered / accepted.

11. a) The tender form must be filled in English. If any of the documents is missing, or

unsigned, TPCL, in its discretion may accept / reject the tender. All the pages of

tender including prebid clarification are to be signed and uploaded. Missing of any

pages will lead to rejection of tender at initial stage itself.

b) Any items left unpriced shall be deemed to be included for elsewhere in the BOQ

or the schedule and hence the rate for that item will be taken as Nil. No unsolicited

advice of any change in rate or conditions after the opening of the tender will be

entertained.

c) The rate quoted includes all expenses, cost of Manpower, tools & equipment

etc., including overheads and profits for the lumpsum prices quoted in the Bill of

Quantities. The rates quoted should be exclusive of All Duties & Taxes since the

facility is in Special Economic Zone (SEZ). TPCL will provide necessary document

to avail Tax exemption. However, statutory payment for taxes and levies such as

Income Tax (TDS), surcharges, other taxes, if any, etc., will be deducted from bills

at applicable rates prevailing from time to time. Taxes and Duties if any, introduced

by the Govt. during the course of the contract will become payable.

d) Each page of the tender documents should be signed by the person or persons

with seal of authority submitting the tender in token of his/their having acquainted

himself/themselves with the General Conditions of Contract, Specifications, Special

Conditions, etc., as laid down. Tender documents not so signed will be rejected.

Any additions/ deletions/corrections/ omissions/modifications/clarifications in the

tender document will be intimated to the tenderer at the time of pre-bid meeting

and the same will also form part of the tender document.

12. Earnest Money Deposit

i) Intending Tenderer should pay an EMD amount as specified in the Tender

Contract Data.

ii) Online payment gateway has been enabled for TIDEL Park Coimbatore Ltd. in

TN Tenders Portal. All the payments for the tenders will be carried out by

bidders only through online payment mode. Bidders shall select the option for

payment of EMD as Online [download the PDF document SI.10: Online

payment Procedure-Online_Payment_Procedure_TN.pdf available from the

website https://tntenders.gov.in/ under Bidders Manual Kit. The Bidders

Manual Kit is available in Right Side Bottom of the Home Page. The bidders

should follow the Instructions step by step for online payment submission].

Page 11: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 11 of 125 Signature of Contractor with seal

iii) The EMD amount should be the exact amount and no excess or less amount

should be transferred through online payment gateway. If excess or short, the

tender status will be shown as invalid.

iv) The EMD will not carry any interest.

v) In order to avoid any issues and last minute delay in processing of payment

online, bidders should ensure payment of EMD, 72 hours in advance. TPCL will

not be responsible for any sort of difficulties or delay faced by the bidder during

submission of bids online, due to local issues.

vi) In respect of the successful tenderer, the EMD shall be returned (without any

interest) by TIDEL Park Coimbatore Ltd. on submission of Performance

Guarantee.

vii) Any other mode of payment of EMD shall not be accepted.

13. Online payment mode

i) During online bid submission process, bidder shall select SBI MOPS option and

submit the page, to view the terms and conditions page. On further submission,

bidder will be re-directed to MOPS gateway, where two options namely SBI

and Other Banks will be shown, Here, bidder may proceed as follows:

a) SBI Account Holder: Shall click ‘SBI’ option to view the Net Banking

Facility, where they can enter their internet banking credentials and transfer

the EMD amount.

b) Other Bank Account Holders: Shall click ‘Other Bank’ option to view the

bank selection page and select their respective bank to proceed with Net

Banking Facility for payment of EMD.

Note - Bidders using “Other Bank” option under SBI MOPS payment

Gateway are advised by SBI to make online payment 72 hours in advance

before tender closing time.

ii) Any transaction charges levied while using any of the above modes of online

payment has to be borne by the bidder.

iii) The bidders will be evaluated only if payment status shows “Success” during

bid opening. It is necessary to click on “Freeze bid” link/icon to complete the

process of bid submission, otherwise the bid will not get submitted online and

same shall not be available for viewing/opening during technical bid opening.

14. Refund of EMD of unsuccessful bidders

The EMD paid by the bidder will automatically be deposited in the “Pooling

Account” of the State Govt. only and not in TPCL’s account. Hence refund process

will be initiated automatically, once the bid is rejected by TPCL during technical /

financial evaluation and TPCL is no way responsible for refund of EMD of the

unsuccessful bidders.

15. The Earnest Money Deposit made by Tenderer will be forfeited after e-tender

opening:

i) If he withdraws his tender or backs out after acceptance of the tender or fails

to remit the Security deposit.

ii) If he revises any of the terms quoted during the validity period.

iii) If he violates any of the conditions of the Tender specification.

Page 12: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 12 of 125 Signature of Contractor with seal

iv) If, the documents furnished with the offer are found to be bogus or the

documents contain false particulars.

v) If, the successful tenderer fails to execute the agreed contract / agreement.

vi) If the Bid Qualification Requirements are found to be fraudulent/ non-genuine,

the EMD paid will be forfeited in addition to black listing in future contracts with

TIDEL Park Coimbatore Ltd.

vii) Undue delay in submission of performance guarantee

Under no circumstances, earnest money deposit shall be accepted in the form of

fixed deposit receipts of Bank or Insurance guarantee or cheque.

16. Rejection of Tender

A) Tender will be summarily rejected if,

i) Received by Post / Courier / telex / telegram / Fax / E-mail/ any other mode

other than e-submission.

ii) Received with EMD in any other mode of payment other than online

iii) Not accompanied with attested copies of evidences for meeting the bid

qualification requirement

iv) Does not meet Bid Qualification Requirement.

v) Received from a tenderer whose past performance is not satisfactory.

vi) The documents furnished with the offer being found to be bogus or the

documents contain false particulars.

vii) Price is indicated in Technical bid

viii) Incomplete and evasive offer.

ix) Not in the prescribed Form & Procedure.

x) At any time before the acceptance of tender, it comes to the notice of TPCL

that the Bidder has been blacklisted or left any contract work incomplete in

PSUs, institutions of Government of Tamil Nadu or Government of India or

joint ventures and associates of TPCL and its promoters.

B) Tender is LIABLE for rejection if,

i) Received without GSTIN NUMBER

ii) Not in conformity with TIDEL Park Coimbatore commercial terms

iii) With validity period less than that specified in the specification.

iv) Not containing all required particulars

17. Performance Guarantee

Successful Tenderer on receipt of LOA should pay to TPCL 10% of the annual contract

value as performance security in the form of Bank Guarantee issued by a Nationalized

Bank/Scheduled Bank within 15 days from the receipt of LOA in approved format. The

Bank Guarantee shall be valid upto the full contract period with additional

irrevocable period of six months from the date of completion of the job and due

fulfillment of the contract, i.e for a total period of One and Half years. EMD of the

successful bidder will be refunded only after submission of the performance guarantee.

On renewal of contract, the contractor should renew the Bank Guarantee for every

renewed contract period with additional irrevocable period of six months.

The said Performance Bond in the form of Bank Guarantee shall indemnify TPCL against

loss from defects arising from any cause under this Contract or due to the failure of the

Contractor to promptly carry out any matters arising under this Contract.In the event

of refusal to carry out work by the successful Contractor on any grounds, security

deposit/the bank guarantee shall be invoked without any information.

Page 13: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 13 of 125 Signature of Contractor with seal

18. Modifications/Clarifications to Tender Documents:

a) At any time after the commencement of e-Tender and before the closing of the

event, TIDEL Park Coimbatore may make any changes, modifications or

amendments to the tender documents and same will be intimated to the concerned

through corrigendum which can be downloaded from the login.

b) In case any tenderer asks for a clarification on the tender documents before the

date specified, TIDEL Park Coimbatore will clarify the same.

c) If any tenderer raises clarifications after the opening of the tender, the clarification

issued by TIDEL Park Coimbatore will be final and binding on the Tender.

d) All information in the tender offer shall be in ENGLISH only. It shall not contain

interlineations, erasures or overwriting except as necessary to correct errors made

by the tenderer. Such erasures or other changes in the tender documents shall be

attested by the persons signing the tender offer.

19. Quotation of Rates

a) Rates should be quoted in figures i.e., integers only.

b) Lump sum price quoted without giving breakup as per details indicated in the BOQ,

shall be liable for rejection.

20. Incomplete Tenders

Tender, which is incomplete, obscure or irregular will be rejected.

The tender offer shall contain full information asked for, in the accompanying

schedules and elsewhere in the specification.

Tenderers shall bear all costs associated with the participation in the e-Tender and

TIDEL Park Coimbatore will in no case be responsible or liable for these costs.

No offer shall be withdrawn by the Tenderer in the interval between the deadline for

submission and the expiry of the period of validity specified / extended validity of the

tender.

21. Tender Opening

Opening of Technical Bids (Vol-I):

The Tender offer except price Bid will be opened electronically at 16.00 Hrs. on the

date notified by TIDEL Park Coimbatore through https://tntenders.gov.in/.

Tenderers need not visit this office during tender opening, whereas tenderers can

witness the tender opening event through their login.

Opening of Price Bids (Vol- II):

The date and time of opening of Price Bids shall be later notified through registered e-

mail to the Bidders who fulfill the pre-qualification criteria and whose bids are found

to be technically acceptable.

In the event of the opening day of the tender being declared as a holiday / closed day

/ or if tenders could not be opened due to unforeseen circumstances on that day, such

as force majeure, the tenders will be opened on the next appointed time and date to

be notified later.

Page 14: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 14 of 125 Signature of Contractor with seal

22. Information required and clarifications

In the process of examination, evaluation and comparison of tender offers, TIDEL Park

Coimbatore may at its discretion, ask the Tenderer for a clarification of the offers. All

responses to requests for clarifications shall be in writing to the point only. No change

in the price or substance of the offer shall be permitted.

TIDEL Park Coimbatore will examine the tender offers to determine whether they

are complete, whether any computational errors have been made, whether

required documents have been furnished, whether the documents have been

properly signed and whether the offers are generally in order.

The Tender offers shall be deemed to be under consideration immediately after

they are opened and until such time official intimation of award / rejection is made

by the Tender Accepting Authority to the tenderers.

The Tenderers shall not make attempts to establish unsolicited and unauthorized

contact with the Tender Inviting Authority, Tender Accepting Authority or Tender

Scrutiny Committee after the opening of the tender and prior to the notification of

the award and any attempt by any tenderers to bring to bear extraneous pressures

on the Tender Accepting Authority shall be sufficient reason to disqualify the

tenderer.

Mere submission of any Tender offer connected with these documents and

Specification shall not constitute any agreement. The tenderer shall have no cause

of action or claim, against TIDEL Park Coimbatore for rejection of their offer. TIDEL

Park Coimbatore shall always be at liberty to reject or accept any offer or offers at

its sole discretion and any such action will not be called into question and the

Tenderer shall have no claim in that regard against TIDEL Park Coimbatore.

23. Negotiation

Negotiation will be carried out with the L1 tenderer after opening of tenders.

TIDEL Park Coimbatore reserves the right to carry out negotiation with the L1

tenderer after opening of price bid.

24. General

a) On receipt of Letter of Award (LOA) from TIDEL Park Coimbatore Ltd., within

15 days, the successful tenderer shall be bound to implement the contract

with TPCL and sign an agreement in accordance with the draft agreement and

the Schedule of Conditions but the written acceptance in the form of Letter of

Award (LoA) by TIDEL Park Coimbatore Ltd. will constitute a binding contract

between TIDEL Park Coimbatore Ltd., and the person/contractor submitting

the tender, whether such formal agreement is or not subsequently executed.

b) All compensation or other sums of money payable by the Contractor to TPCL

under the terms of this Contract may be adjusted/deducted either from

payment of amount due or by call of performance guarantee if the amount

due is not sufficient or such adjustment and the contractor fails to make good

in cash, the amount within 10 days of intimation to do so by TPCL.

c) The Contractor shall not assign the Contract to any Sub-Contractor. No portion

of the Contract shall be given on subcontract except with the written consent

of TPCL. In case of breach of these conditions, TPCL may serve a Notice in

Page 15: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 15 of 125 Signature of Contractor with seal

writing to the Contractor / rescinding the Contract whereupon the

Performance Bond shall stand forfeited to TPCL, without prejudice to its other

remedies/rights against the Contractor.

d) The Contractor shall carry out all the work strictly in accordance with

Documents, details and instructions of TPCL’s Representative. If any changes

are desired by TPCL, the Contractor shall carry out the same without any extra

charge. TPCL’s decision in such cases shall be final and binding on the

Contractor. The Contractor shall report to TPCL or its representative regarding

day-to-day Operation, reporting, preventive and regular maintenance.

e) The Schedule of Quantities is liable to alterations, omissions, deductions or

additions in the scope of work and items of work at the discretion of TPCL.

Each tender should contain not only the rates but also the value of each item

of work entered in the amount column and all the items should be totaled in

order to show the aggregate value of the entire tender. Value of each item

worked out shall be rounded off to nearest rupee ignoring paise below fifty.

f) The tenderer must obtain for himself on his own responsibility and at his own

expense all the information which may be necessary for the purpose of making

a tender and for entering into a contract and must examine the Documents

and must inspect the site of the work and acquaint himself with all local and

site conditions, means of access to the job, nature of the job and the

availability of any infrastructure and all matters appertaining thereto.

Ignorance of the site conditions or the nature and details of existing contract

or the specifications of any work falling within the ambit of the Contractor

shall not be accepted by TPCL as a basis for any claim for compensation.

g) While making the tender, the tenderer should keep his rates firm till the

completion of the job/end of the contract period and no price variation shall

be considered for any reason whatsoever, except variation caused due to

statutory changes such as minimum wages act etc. and dearness allowance,

resulting in more than 15% variation on minimum wages against proof of such

payment, provided the quoted price is specifically provided with the details of

amounts considered at the prevailing rates and conditions, while tendering

the quote.

h) The successful tenderer is bound to carry out any related and connected work

necessary for proper performance of the job even though such work(s) is or

are not specifically mentioned or included in the item of work. No claim in this

respect shall be entertained unless considered beyond the scope of the

agreement by TPCL whose decision is binding on the Contractor.

i) The successful tenderer must note that all performance of the job shall be

strictly in accordance with the requirements and fulfillments of the local/public

authorities, statutory approvals and to the requirements of TPCL and no

deviation on any account will be permitted.

j) The total rate quoted will be considered for the purpose of deciding the

competitive tender.

Page 16: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 16 of 125 Signature of Contractor with seal

k) Supply of water and electricity required for performance of Operation and

Maintenance services shall be made available free of charge by TPCL. However

the successful tenderer shall bear all costs of extending supplies from the

source of maintenance purposes to place of work, maintaining the supplies,

etc. as required within the quoted rates.

l) The Contractor shall strictly comply with the provision of safety code and

safety manual annexed hereto. The Contractor shall keep TPCL fully

indemnified against any claims or liabilities arising out of Contractor’s lapse in

safety practices.

m) The successful tenderer/Contractor shall mobilize all men required for timely

performance of the Integrated Operation & Non Comprehensive Maintenance

of ACMV, BAS, DG Sets & Connected Works involving various activities within

15 days from the date of LOA and also sign the agreement in the prescribed

format after producing performance bank guarantee.

25. Annual Renewal

The contractor should submit renewable request letter by end of 10th month. Based

on evaluation of TPCL, if renewable order has not been issued on or before

completion of 11th month of contract, it is construed that there will be no renewal

of contract and contract will come to an end in that year without any further notice.

26. Final Decision Making Authority

TIDEL PARK COIMBATORE LTD. reserves the right to accept or reject any of the

applications/tender(s) without assigning any reasons thereof. TPCL reserves the

right to increase or decrease the scope of work and may split the scope of work

(including Manpower, Materials, equipment etc.,) and award the works to one or

more agencies and as deemed necessary by TPCL, decision of TPCL is final and

binding.

All tenders, documents and other information submitted by the bidders to TPCL

shall become the property of TPCL. Bidders shall treat all information furnished as

strictly confidential. TPCL will not return any submission.

Page 17: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 17 of 125 Signature of Contractor with seal

5. CONDITIONS OF CONTRACT

(DEFINITIONS AND INTERPRETATION)

1. Interpretation clause:

In construing these Conditions, the Technical Specifications, Skilled manpower to be

deployed and Contract Agreement, the following words shall have the meanings herein

assigned to them except where the subject or context otherwise requires.

a) "TPCL"/"Employer": shall mean TIDEL Park Coimbatore Ltd., Coimbatore and

shall include its assigns and successors.

b) “TENDERER”/ “CONTRACTOR”, in case of a Company, shall mean

…………………………….………………………………….. a company incorporated under

……………………… act dated …………….…... with CIN

…………………………………………………………………………. and having its registered office at

……………………………………………………………………………………………………………………………………

…………………………………………. and shall include its successors and permitted assigns.

c) “TENDERER”/ “CONTRACTOR”, in case of a partnership firm, shall mean a firm

trading as partners in the name and style of

…………………………………………………………………….……………………………… with registration

number ……………………………………………………… and having business at

……………………………………………………………………………………………………………………………………

………………………………….…………………. and shall include the partners for time being of

the said firm and the legal representatives of a deceased partner.

2. Definitions:

The contract document consists of the Articles of Agreement, General Instructions and

Notice Inviting Tender, Conditions of the Contract, Special Conditions, Scope of work

and Skilled manpower to be deployed, Tender Form & Tender documents including all

modifications thereof incorporated in the document before the execution. These form

the contract.

The TPCL : TIDEL Park Coimbatore Ltd., Coimbatore

The Contractor : ________________________________

All those mentioned as such in the Articles of Agreement shall include their legal

representatives, assigns or successors. They are treated throughout the Contract

Document as if each were of the singular number and masculine gender.

"The Site" shall mean the site of the contract work / job; any other land allotted by

TPCL for the contractor use and any other nearby land that TPCL may include for

beneficial use by Occupants of TPCL.

“Occupant” shall mean authorized persons, agencies, companies who have been

authorized by TPCL to occupy any part of the building either under outright sale or

through a Lease Deed or authorized sub-lease for a specific period.

Page 18: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 18 of 125 Signature of Contractor with seal

Written notice shall be deemed to have been duly served if delivered in person to the

individual or to a member of the firm or to an office of the corporation for whom it is

intended, or if delivered at or sent by registered mail to the last business address

known to him who gives the notice.

The term "Work" of the Contractor includes labour.

All time limits stated in the contract document are the essence of the contract.

The law of the place of work shall govern the job under this contract.

The performance during the Contract period shall be in accordance with the Contract

Documents as modified by any change or variation orders agreed to by the parties and

to the satisfaction of TPCL, so that TPCL can issue completion certificate within 90 days

after the end of the term of Agreement.

The words ‘Bidder’/‘Tenderer’ shall mean the specialized Contractor who tender for the

work.

3. Contract Document:

The following documents shall constitute the contract document.

i. Tender Form

ii. Articles of Agreement.

iii. General Instructions

iv. Conditions of Contract

v. Scope of work

vi. Schedule of Contract Bill.

vii. Special Conditions

viii. Various Annexures as referred under this Contract.

ix. Letters and documents including the covering letter of the tenderer,

minutes of meeting, if any, post tender and the letter of Award by TPCL.

The Contract Document is complementary. What is called for in any one shall be as

binding as if called for by all.

4. Type of Contract:

This Contract is neither a fixed Lump sum Contract nor a Piece Work Contract but is a

Contract to carry out the work in respect of provision of Integrated Operation & Non

Comprehensive Maintenance of ACMV, BAS, DG Sets & Connected Works to TPCL’s IT

Park Building and its services & facilities, to be paid for according to the actual services

performed and works done at the lump sum rates contained in the Skilled manpower

to be deployed or as provided in the said Conditions.

The contract will be for a period of one year renewable every year for upto 3 years

renewable on annual basis, subject to satisfactory performance and assessment of

evaluation parameters. TPCL will alone have absolute discretion in this regard and the

Contractor shall have no vested right to seek extension of the contract. TPCL, however

reserves the right to terminate the said contract at any time on the ground of ineffective

services (shortage of manpower supply, garbage removal, equipment supply, material

supply, scope of work etc.) rendered by the contractor. TPCL will be the sole judge to

determine these facts.

Page 19: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 19 of 125 Signature of Contractor with seal

5. Skilled manpower to be deployed:

Skilled manpower to be deployed are meant to indicate the intent of the work and to

provide a uniform basis for tendering. TPCL reserves the right to add or delete from

the scope of work, manpower as it may deem fit and the Contractor shall not claim

any extras or damages on these grounds.

6. Contract Sum / Contract Price:

The Contract sum or Contract price shall be the total amount quoted by the successful

tenderer and accepted value of the work as mentioned in the letter of acceptance of

TPCL. The Contract sum shall not be adjusted or altered in any way whatsoever

otherwise than in accordance with the express provisions of these conditions.

7. Contract Bills:

Any error in description or in quantity or omission of items from the Contract Bills shall

not vitiate this Contract but shall be corrected and deemed to be a variation required

by TPCL.

8. Scope and intent:

a) Integrated Operation & Non- Comprehensive Maintenance of ACMV, BAS, DG Sets

& Connected Works are to be provided round the clock for the specified period to

a high international standard. The details about the scope of work are more fully

described elsewhere in this document, but, in brief, TPCL expects the Contractor

to take a single point and full responsibility of Integrated Operation & Non-

Comprehensive Maintenance of ACMV, BAS, DG Sets & Connected Works covered

by this contract. TPCL’s objective is that Contractor does not perceive this as a

short term or a one-time contract but as an exercise in Asset value maximization

and Asset Life Prolongation.

b) TPCL requires a single point responsibility for the Contractor in controlling and

managing in respect of the works / system covered by this contract during the

entire contract period.

c) The bidders are expected to price the attached bills of quantities with workable and

sustainable rates, which shall remain firm for the full duration of the contract. No

price change will be admitted due to a lack of understanding of the contractual

conditions or inadequate study of the present conditions of contract or improper

understanding or improper assessment of manpower, supervision, scope or any

other reasons whatsoever.

d) The rates quoted for each section shall be self sustainable and correct reflective of

the Scope envisaged. TPCL reserves the right to add or delete from the Scope of

work, items as he may deem fit. The successful bidder cannot make any claim on

account of such changes.

e) The work is for provision of Integrated Operation & Non Comprehensive

Maintenance of ACMV, BAS, DG Sets & Connected Works and responsibility shall

be with modern systems and services of International Quality, integrating all

functions necessary to support the daily operations to high-tech operation and

maintenance smoothly, deploying competent, trained and experienced work force

under a well structured system and using modern management techniques

including hardware and software support. Integrated Operation & Non

Comprehensive Maintenance of ACMV, BAS, DG Sets & Connected Works shall be

ensured as ‘Life Time Care’ with planned preventive maintenance schedule,

procedures, self-audit and continuous improvement, precisely determining most

appropriate type and level of services to fulfillment of objectives of TPCL.

Page 20: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 20 of 125 Signature of Contractor with seal

9. Place of work:

a) Visit: Before tendering, the Contractor shall have visited and examined the place

of work and satisfied and understood himself as to the correct requirement of the

work / job and the facilities for obtaining any special articles called for in the tender

/ contract document and shall have obtained generally his own information on all

matters affecting performance of the job.

b) No extra charge / claims made in consequence of any misunderstanding or

incorrect information on any of these points will be allowed nor entertained. Should

the contractor after visiting the place of work, find any discrepancies, omissions,

antiquities or conflicts in or among the tender / contract document or be in doubt

as to their meaning, he shall bring the questions to TPCL’s attention, before the

date of pre-bid meeting.

10. Possession:

The successful bidder shall be allowed admittance to the work place on the ”Date of

Commencement” stated in the appendix and he shall thereupon and forthwith begin

the work and shall regularly proceed with the performance of the job till the end of the

contract period stated in the appendix subject nevertheless to the provision for renewal

of time hereinafter contained.

11. Defect / Complaint cum Rectification checklist:

The successful bidder shall follow the existing formats approved by TPCL on day to day

basis. The charts indicate the method of services to be executed for each group of

service, the date of commencement and completion of each of the defect/complaint.

The chart shall also indicate the availability of materials and labour therefor. If the

Contractor feels any improvements are required in the existing formats, the same

should be brought to the notice of TPCL Management and got approved before

execution.

12. Access for owner to the Works:

The owner (TPCL) and his authorized representatives shall at all reasonable times have

access to the Works or other places of the Contractor where work is being prepared

for the Contract.

13. Owner’s Representative:

Owner’s Representative shall mean the person authorized by Owner (TPCL) and acting

under the order of the Owner to inspect the works. The successful bidder shall afford

the Owner’s Representative every facility and assistance for inspecting and checking

the works and materials.

The Contractor shall constantly keep a watch on his work during the progress of work

and shall deploy required qualified and competent Manager as an Operation and

Maintenance Incharge who shall have experience in the field of Integrated Operation

& Non Comprehensive Maintenance of ACMV, BAS, DG Sets & Connected Works.

The Manager will be responsible for carrying out the job to the true meaning of e

Contract document, Schedule of Quantities, Technical specifications, equipment

operations, TPCL instructions and directions to the satisfaction of TPCL. Any directions

or instructions given to him by TPCL or its authorized representative shall be deemed

to have been issued to the Contractor. The man power of experienced and trained

technical and non-technical support staff shall assist the works as required, fulfill the

scope of work envisaged as listed in the Volume I. If TPCL establishes at any time the

need to augment the field organization, either on a short term or long term measure,

the Contractor is bound to implement TPCL’s instructions forthwith within the agreed

rates.

Page 21: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 21 of 125 Signature of Contractor with seal

14. Arrangement of execution of work:

The Contractor shall arrange for all materials, tools tackles, equipment and labour

necessary including its transportation for proper execution and completion of the job

and contract to the satisfaction of TPCL.

15. Fluctuations:

The Contractor shall not claim any extras for fluctuation of price and the Contract Price

and item rates shall not be subject to any rise or fall of prices and shall be firm

throughout the tenure of the contract.

16. Safety rules to be followed by the contractor during execution of work

a) All electrical equipment used by the Contractor should have double earthing and to

be connected through an ELCB. No temporary electrical connections with loose wire

will be permitted. For all electrical connections, proper sockets and plugs will be used

and wiring / cabling clamped.

b) Un-necessary waste of energy shall be avoided. Electrical hand tools like drilling

machine will be of 230 volts AC type. All electricians should have wiremen’s license.

welding operators and electricians should wear rubber gloves and protective goggles.

c) All staff working at heights shall use safety belts, helmets and standard platforms

with 42” height railing. All the staff working shall as far as possible wear shoes. Only

Standard ladders should be used.

d) Inflammable/explosive materials like Petrol, diesel, Kerosene, Wax, etc. will not be

allowed to be stored at site stores. Crackers/Explosives will not be allowed inside the

premises at any cost.

e) Personal protecting equipment like Gloves, Safety Belt, Safety Helmet, etc. should

be used and available in Contractor’s stores.

f) If correct manual handling is not used, it can result in injuries. Therefore all workers

should be trained in safe manual handling. Special objects require special handling.

All scaffolding will be of steel and double stage.

g) Contractor to ensure that all equipment/tools brought on to the premises have

recently been checked and are in good condition and that all personnel using the

equipment and tools have been trained in their safe use. Contractor to ensure that

whilst on site premises, he will comply with all health and safety rules as required

by TPCL.

17. Maintenance:

a) The material required for replacement of damages etc. shall be supplied by

TPCL. The Contractor shall however, be required to deposit the damaged parts

with the Stores.

b) If it is observed that due to poor Maintenance / unsatisfactory work, any part is

found damaged / required to be replaced, the same will have to be attended and

replaced by the Contractor at its own cost. In this regard, TPCL’s decision will be

final.

Page 22: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 22 of 125 Signature of Contractor with seal

18. General:

a) The Contractor and TPCL shall make every effort to resolve any dispute or dis-

agreement amicable by direct informal negotiations. However, incase of any

unresolved issues/ disagreements / disputes in connection with the contract, the

same shall be settled through Arbitration or through Court of Law within the

jurisdiction of Coimbatore. The resultant contract will be interpreted under Indian

Laws.

b) It shall be the responsibility of the Contractor to meet transportation, food,

medical and any other requirements in respect of the workers engaged by the

Contractor at TPCL and TPCL shall have no liabilities in this regard.

c) The workers deployed by the Contractor in TPCL shall not have claim of any

Master and Servant relationship nor have any principal and agent relationship with

or against TPCL

d) The Contractor shall be solely responsible for redressal of grievances / resolution of

disputes relating to workers engaged by them. TPCL shall, in no way, be responsbile

for settlement of such issues whatsoever.

e) TPCL shall not be responsible for any damages, losses, theft, claims, financial or

other injury to any workers deployed by service providing Contractor in the course

of their performing the functions.duties or for payment towards any compension.

f) The workers deployed by the contractor shall not claim nor shall be entitled to pay

Perks and other facilities admissible to casual, adhoc, regular / confirmed employees

during or after expiry of the contract period.

g) In case of termination of this contract on its expiry or otherwise, the workers

engaged by the contractor shall not be entitled to and shall have no claim for

any absorption nor for any relaxation for absorption in the regular /

otherwise capacity in TPCL.

h) The contractor shall also be liable for depositing all taxes, levies, cess etc. on account

of services rendered by it to TPCL to concerned tax collection authorities from time

to time as per extant rules and regulations on the matter.

i) Statutory Payment such as GST or any other tax will be the responsibility of the

Contractor. Contractor has to enclose certified copy of Tax Challan, PAN Card No.,

Income tax / Any other tax as applicable from time to time will be deducted while

making every payment.

j) In case, the contractor fails to comply with any statutory/taxation liability under

appropriate law, and as a result thereof TPCL is put to any loss/obligation, monetary

or otherwise, TPCL shall be entitled to get itself reimbursed out of the outstanding

bills or the Performance Security Deposit of the contractor, to the extent of the loss

or obligation in monetary terms.

k) If any worker wants to go on leave, they shall inform well in advance to TPCL and

alternative proper arrangements shall be made by the Contractor.

l) The successful contractor shall provide uniforms with his organization’s

name/logo and safety shoes to the staff deployed at TPCL. It will be the

responsibility of the contractor to insist the staff to carry their Identity Cards while

on the duty at TPCL.

Page 23: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 23 of 125 Signature of Contractor with seal

19. Statutory Compliance by the Contractor:

a) The Contractor should have all necessary license and statutory compliance from all

Government authorities such as Municipality, Local Authority, Pollution control

board etc. at its own cost. TPCL shall not be responsible in any way for any breach

of the rules and regulations by the contractor.

b) The contractor shall comply with all statutory requirements in respect of engaging

the personnel, their service condition, rules and regulations and all liabilities under

the various labour law and other statutory obligations like PF, ESCI, Bonus,

Workmen’s Compensation, Gratuity and also comply with the provisions of

Minimum Wages Act, Payment of Wages Act etc. TPCL shall in no way be

responsible or liable in case of any dispute, prosecution or awards made by court

of law or other authorities.

c) The Contractor shall obtain separate code for deposit of PF dues, if applicable, with

the concerned PF Authority directly.

d) The Contractor shall obtain and keep in force throughout the term of agreement,

necessary / valid labour license from the Licensing authority. The contract

Labour (R&A) Act 1970, and the rules framed there under and produce the same

to TPCL before commencement of the services under the contract and also take

steps for getting the agreement registered under the act. The Contractor shall also

indemnify TPCL from and against any claims under the aforesaid act and the rules

and shall continue to have a valid licence until completion of the contract period or

any extended period. Any failure to fulfill this requirement shall attract penal

provisions of the contract arising out of resultant non-performance of the work.

e) The Contractor shall keep TPCL indemnified against all the losses, damages or

liability arising out of or imposed in pursuance of any violation by the Contractor

of/under labour laws & the rules there under or of any prosecution of award made by

cout of law or other authorities specifically under the Industrial Disputes Act 1947.

f) The Contractor shall at all times indemnify TPCL against all claims which

may be made under the Workmen’s Compensation Act 1923 or any statutory

modification thereof or otherwise for or in respect of any damages or compensation

payable in consequences of any accident, injury sustained by

any labour/servant or person in his employment and engaged in the

performance of contract. If any such accident occur which may involve any

such liability under the Act, TPCL shall be at liberty to withhold such amount from

the bills of the Contractor and also deposit the same with Commissioner

under the W.C. Act.

g) The Contractor has to strictly follow the provisions of Payment of Wages Act

1936 and the rules made there under and further the Contractor shall strictly

adhere to provisions of The Minimum Wages Act 1948 and the rules made

there under from time to time revising the wages payable to the workmen.

h) All labour and / or personnel employed by the Contractor shall be engaged by him /

them as his / their own employees in all respect implied or expressed. The

responsibilities whatsoever, incidental or direct, arising out of or for compliance with

or enforcement of the provisions of various labour laws of the country shall be that

of the Contractor and TPCL shall, in no way, be responsible or liable for their wages,

salaries, bonus, gratuity or any other allowances, leave salary, wages for holidays or

any compensation, notice pay etc. The Contractor shall specifically ensure compliance

with the provisions of following labour laws/acts and their enactment / amendments.

Page 24: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 24 of 125 Signature of Contractor with seal

The Payment of Wages Act, 1936

The Payment of Minimum Wages Act, 1948

The Factories Act, 1948

The Workmen’s Compensation Act, 1923

The Employee’s State Provident Fund Act, 1952

The Contract Labour (Regulation & Abolition) Act, 1970

The Payment of Bonus Act, 1965

The Payment of Gratuity Act, 1976

The Equal Remuneration Act, 1976

The Employee State Insurance Act, 1948

The Industrial Disputes Act, 1947

i) The contractor shall pay to the labour employed by him/them wages as per

provision of the aforesaid act and the rules, wherever applicable.

j) In every case, in which, by virtue of the provision of the aforesaid acts or

the rules, TPCL is obliged to pay any amount of wages to the personnel

employed by the contractor in execution of the work or to incur any expenditure in

providing welfare, Health & safety amenities required to be provided under

the aforesaid act and rules or to incurr any expenditure on account of contingent

liability of TPCL due to contractor to fulfill his statutory obligation under the

afore said act or the rules, TPCL shall be at liberty to withhold from the bills of the

Contractor the amount of the wages as paid or the amount of expenditure so incurred

and without prejudice to the rights of TPCL under Section 20(2) and Section 21(4) of

the aforesaid act, TPCL shall be at liberty to recover such amount or part thereof by

deducting it from any sum payable by TPCL to the contractor. The decision of TPCL

regarding the amount actually recoverable from the contractor as stated

above shall be final and binding on the Contractor.

k) The Contractor shall not employ any person below the age of 18 years. The

contractor shall indemnify TPCL from and against all claims and penalties which

may be suffered by TPCL by reason of any default on the part of Contractor to

observe and/ or in the performance of the provisions of Employment of Children Act

1938 or any re-enactment or modification of the same.

l) The Contractor shall be responsible for the compliance with the provisions of the

hours of the employment regulation in respect of the staff employed by him in the

manner decided upon by the appropriate authority.

20. Hand book on health and safety at work

The Contractor to do work in the campus shall follow the guidelines given in the

handbook on health and safety at work appended herewith during execution.

21. Statutory obligations, notices, fees and charges

a) The Contractor shall comply with and give all notices required by any Government

authority, and instrument, rule or order made under any Act or Parliament or State

Legislature or any regulation or Bye-law of any local authority relating to the work

or with whose system the same is or will be connected.

b) The Contractor shall pay and indemnify TPCL against liability in respect of any fees

or charges (including any rates) legally demandable under any Act of Parliament,

or State Legislature instrument, rule or order or any regulation or Bye-law or any

local authority in respect of the work.

Page 25: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 25 of 125 Signature of Contractor with seal

22. Assignment or giving Sub-Contract

No subcontracting is ordinarily permitted for items mentioned in the scope of work. In

case of any specific requirements, Contractor shall not without the written consent of

the Owner assign any responsibility needed to discharge the functions of the O&M

Contract as a subcontract.

a) Provided that even in case of such subcontracting, the Contractor shall be solely

responsible for the overall supervision, necessary domain knowledge support,

service quality, system support on technology, training, validating day to day

monitoring and overall management.

b) Provided that on receipt of any request from the Contractor with proper reasons

for approval of the Owner to give a portion of non-core activity or a specialised

activity on sub-contract, the Owner shall not unreasonably delay their decision on

giving consent for subcontracting such portion of work, to the prejudice of the

Contractor.

23. Separate Contract

TPCL reserves the right to let other contracts in connection with the work under similar

general condition, in case the contractor fails and neglects the work assigned within

the period specified in the order. The work shall be carried out at their risk and cost

without any notice to the contractor, and any excess cost incurred due to engaging

alternate Contractor shall be recovered from the bills, security deposit or any other

amount due to the contractor. The contractor shall be liable for all charges and

expenses that may be sustained or incurred by TPCL for not carrying out the work on

the part of the contract. The contract is non-exclusive and TPCL reserves right to

appoint additional contractor to meet the requirement.

24. Termination of the Agreement

During the currency of this agreement, TPCL shall have the right to terminate this

agreement for the following reasons:

i. For administrative reasons - Two-months notice period

ii. Non satisfactory performance - One month notice period

iii. Non provisioning of required manpower

for 3 occasions during the entire period

of contract including renewals

- One month notice period

For this purpose, TPCL shall be the sole Judge to decide whether the performance

of the Contractor is satisfactory or not and such decision of TPCL shall be final,

conclusive and binding on the Contractor and the Contractor shall not be entitled

to any compensation in that regard. Further more if on account of non-renewal of the

contract and/or termination of this contract, the Contractor has to terminate its

employees, then it shall be the responsibility of the Contractor

to pay the legal dues to its employees. In the event of non-compliance of

legal requirements, Contractor shall be liable for all the costs and consequences.

Page 26: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 26 of 125 Signature of Contractor with seal

25. Variations

a) The term “Variation” as used in these conditions shall mean any additional services

not within the scope of service required to be performed during the currency of the

contract.

b) TPCL may issue instructions requiring a variation and sanction in writing any

variation made by the CONTRACTOR. No such variation required by TPCL or

subsequently sanctioned by it shall in any way vitiate this contract.

c) If TPCL decides the variation shall be carried out, it shall intimate the Contractor

in writing to quote its price. Thereupon Contractor shall submit its price for

additional services with full details in writing. After finalising the price with

Contractor, TPCL shall give its written acceptance to carry out the variation. No

variation shall be paid where it shall be within the scope of service or shall be due

to Contractor’s act or omission in complying with this contract.

26. Deduction for uncorrected work

If TPCL deems it inexpedient to correct the work damaged or not done in accordance

with the Contract, an equitable deduction from the contract price and the amount of

such loss which arise due to non-completion of the work in time shall be deducted from

the payment of contractor.

27. Fluctuations

The Contractor shall not claim any extras for fluctuation of price and the Contract Price

shall not be subject to any rise or fall of prices and shall be firm throughout the tenure

of the contract.

The Contractor shall furnish promptly without additional charge all reasonable

facilities, labour necessary for the safe and convenient that may be required by TPCL.

28. Materials and workmanship:

All materials and workmanship shall be as per the relevant code of BIS or relevant

specification and of approved type and the Contractor shall immediately remove from

the works any material and/or workmanship which in the opinion of TPCL are defective

or unsuitable and shall substitute proper materials and/or workmanship at his own

cost. The term approval used in connection with the contract shall mean the approval

of TPCL.

29. Inspection:

a) All materials, equipment’s and workmanship shall be subject to inspection,

examination and test by TPCL or its representative at any and all times during the

period of contract. TPCL shall have the right to reject defective material and

workmanship or require its correction. Rejected material and workmanship shall

be satisfactorily replaced with proper material without additional charge therefor

and the Contractor shall promptly segregate and remove the rejected material from

the site. If the contractor fails to proceed at once with the replacement of rejected

materials and/or the correction of defective workmanship, TPCL may by contract

or otherwise replace such materials and/or correct such workmanship and charge

the cost thereof to the Contractor, or may terminate after giving reasonable notice

the right of the Contractor to proceed further with the work.

b) The Contractor shall furnish promptly without additional charge all reasonable

facilities, labour and materials necessary for the safe and convenient inspection

that may be required by TPCL.

Page 27: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 27 of 125 Signature of Contractor with seal

30. Defects:

a) The Contractor shall make good at its own cost and to the satisfaction of TPCL, all

defects/non completions or small faults, arising in the opinion of TPCL from work

not being in accordance with the Skilled manpower to be deployed or the

instructions of TPCL.

b) Such defects, faults shall upon direction in writing of TPCL or its representative and

within such reasonable time as shall be specified therein be amended and made

good by the contractor, at its own cost unless TPCL shall decide that ought to be

paid for such amending and making good and in case of default. TPCL may employ

and pay other agency to amend and make good such defects, fault, non

completions/building and all damages loss and expenses consequent thereon or

incidental thereto shall be made good and bore by the Contractor and such

damage, loss or expenses shall be recoverable from it by TPCL, upon the Owner’s

certificate together with any expenses TPCL may have incurred in connection

herewith.

31. Deficient services and rejection:

a) If at any time before issue of the completion certificate there becomes apparent

any failure of the services or part thereof to conform to the warranties or any other

defect or deficiency in the services for which notice from Owner and at his own

expense promptly remedy the same by, at Owner’s option, repair or replacement.

Deficient services shall also include Contractor’s failure to respond with diligence

and despatch.

b) Even if Contractor shall fail to promptly effect the required remedy then Owner

shall be entitled to reject the part of the services affected and to replace the same

at Contractor’s expense.

c) If Owner does not exercise its rights under the immediately preceding paragraph

within a reasonable time, Contractor shall not be relieved from liability in respect

of the relevant non-conformity or other defect or deficiency but his full and

complete responsibility shall be limited to the repayment of all monies paid by

Owner to him in respect of the part of the services affected thereby.

d) Contractor shall, if required by Owner, search for the cause of any malfunction,

defect or deficiency in the services and, if the same shall be found to be within the

scope of Contractor’s remedial responsibility as aforesaid, the cost of the services

carried out by Contractor in searching shall be borne by Contractor.

e) Contractor’s failure to perform any of its obligations under this Sub-article shall

(without prejudice to any other rights which Owner shall have in the matter) result

in Owner making demand under the performance Bank Guarantee and / or any

monies in its possession.

32. Liquidated Damages:

I. ACMV Works, BAS Works and DG & Connected Works

Manpower requirement is calculated at per day for 24X7 operations within the quoted

unit rate. The deployment of adequate manpower on continued basis with the required

material, tools and equipment’s and supply of man power are the essence for carrying

out Integrated Operations & Non-Comprehensive Maintenance of ACMV,BAS,DG to the

satisfactorily level. Penalty shall be imposed on monthly basis as given below, if the

required manpower is not provided at the discretion of TPCL:

Page 28: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 28 of 125 Signature of Contractor with seal

Value of labour contract as required by TPCL for one month (in Rupees

ACMV BAS DG

21 9 9

Nil Above 85% of

man days

Above 80% of

man days

Above 80% of

man days

5% 65% to 85% 65% to 80% 65% to 80%

7.5% 51% to 65% 51% to 65% 51% to 65%

10% 50% and below 50% and below 50% and below

33. Contract sum:

In consideration of performing the services in full conformity with the contract, Owner

shall pay to the contractor the contract sum as specified in the bill of quantities.

34. Payment:

Payment for Integrated Operations & Non-Comprehensive Maintenance of

ACMV,BAS,DG Services will be made to the contractor after checking and certification

by TPCL on monthly basis within 14 days from the date of submission of Invoice

completed in all respects subject to fulfilling other terms and conditions of TPCL.

Contractor should submit the Bank statement of employees for every quarter along

with the invoice.

No advance shall be paid to the Contractor. As far as possible, Contractor should make

the payments to the contracted staff through ECS/Bank Transfer. In case of exigencies,

the employees may be paid by Cheque/in cash (for the first month only). However,

cash payments shall be witnessed and certified by the concerned TPCL representative.

Contractor shall be required to pay to its employees, roped in for services under the

contract, based on category of minimum wages as per the provision of relevant

statutes given by TPCL and deposit/disburse other statutory dues to respective

agencies/employees as claimed by the contractor and paid by TPCL on behalf of the

contractor. No payment/less payment of wages and other dues and failure to

deposit/less deposit of statutory dues will tantamount to violation of Terms and

conditions of the contract and necessary penalty may be imposed on the contractor as

per the terms and conditions of the tender, including but not limited to withholding of

payment access under the contract and remittance of the statutory dues directly to

the authorities wherever called upon so, which will be treated as settlement of dues to

the contractors.

Notwithstanding the release/payment of the bill by TPCL to the Contractor, the

contractor shall all times ensure the due and timely payment of wages to all its

manpower pursuant to this contract. Nothing contained herein shall establish any link

between release/payment of the bill by TPCL to the contractor and the payment of any

salary/wages or any other dues whatsoever by the Contractor to its manpower.

Salary /payment to the contracted employees shall be made on or before 5th of every

month by the contractor

35. Invoicing:

The contractor shall submit to TPCL detailed invoices in respect of the services

performed under each category of Facility Management at the end of each month in

arrears. The invoice shall be submitted in one (1) original, clearly stamped “Original”.

The Invoices shall be bear reference to this agreement and be supported with

a) Certificate of compliance as per condition of contract (Payment to Local Bodies /

Authorities) Bills with all necessary supporting documents should be submitted

within 10 days after completion of the month.

Page 29: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 29 of 125 Signature of Contractor with seal

b) All documentation with proof of statutory payment details

c) Details of deployment duly verified along with summary of bills (Copy of Bio

metric attendance to be enclosed).

d) Salary statement for the previous month with Bank statement/Bank Transfer

details to corroborate the payment. (Copy of wage-slips with staff signature &

muster roll to be enclosed).

e) Details of Bonus paid to all terminated/resigned contracted employees, employee

wise of the previous month.

f) Proof of having deposited the contribution to EPF, ESI, etc. with the concerned

authorities for the previous month as per the relevant statutes i.e. EPF Payment

contribution Challan, EPF’s Form 36B (Original), Copy of EPF’s ECR, Consolidated

Statement to refer EPF’s Form 36B & ECR, ESI Payment Contribution Challan,

ESI contribution history from the EPF/ESI authority along with muster roll to be

enclosed.

g) Clearly state the reason for which the payments are required. Payment shall be

made to the Contractor at monthly intervals. Upon receipt of each Invoice, with

all relevant enclosures complete in all respect in accordance with Tender Terms,

TPCL shall approve the said Invoice and the payment shall be made to the

Contractor within fourteen (14) days from the receipt of correct invoice by TPCL

subject to the bills being in the complete shape and in the accepted format.

Without waiver or limitation of any of its rights under this contract or law, the

Owner shall be entitled to deduct from any monies payable to the Contractor

under the contract and all amounts due from the Contractor to TPCL. However,

all payments under the contract shall be made only after the receipt of the

performance bank guarantee required under this contract.

36. Accident and Incident Reporting

All notifiable accidents, dangerous occurrences and potential hazard situations shall be

reported to the safety officer of TPCL. Injuries are to be treated by experienced medical

staff available at site at the contractor’s cost.

37. Hazardous Materials:

The Contractor must inform the safety officer, prior to commencement of work,

procurement of or materials connected with the contract work of a hazardous nature.

The Contract will have to secure storage for any such materials.

38. Bankruptcy of Contractor

a) In the event of the CONTRACTOR becoming bankrupt or making a composition or

arrangement with his creditors or being a company having a winding up order made

or (except for purposes or reconstruction) a resolution for voluntary winding up

passed or a receiver or manager of his business or undertaking duly appointed or

possession taken by or on behalf of the holders of any debentures secured by a

floating charge, of any property comprised in or subject to the floating charge, the

employment of the CONTRACTOR under this Contact shall be forthwith

automatically determined but the said employment may be reinstated and

continued if TPCL and the CONTRACTOR, his trustee in bankruptcy, liquidator,

receiver or manager as the case may be shall so agree.

Page 30: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 30 of 125 Signature of Contractor with seal

b) TPCL shall be entitled to determine the employment of the CONTRACTOR under

this Contract, if the Contractor shall have offered or given or agreed to give to any

person any gift or consideration of any kind as an inducement or reward for doing

or forbearing to do or for having done or forborne to do any action in relation to

the obtaining or execution of this Contract with TPCL, or for showing or forbearing

to show favour or dis-favour to any person in relation to this Contract or any other

Contract with TPCL, or if the like acts shall have been done by any person employed

by the CONTRACTOR or acting on his behalf (whether with or without the

knowledge of the CONTRACTOR), or if in relation to this Contract or any other

Contract with TPCL, the CONTRACTOR or any person employed by him or acting

on his behalf shall have committed any offence under the prevention of corruption

act, or shall have given any fee or reward the receipt of which is an offence under

the Local Government Act.

c) In the event of the employment of the CONTRACTOR being determined as aforesaid

and so long as it has not been reinstated and continued, the following shall be the

respective rights and duties of TPCL and CONTRACTOR.

d) TPCL may employ and pay other persons/agencies to carry out and complete the

works and he or they may enter upon the Works and use all temporary buildings,

plant, machinery, appliances, goods and materials intended for, delivered to and

placed on or adjacent to the works and may purchase all materials and goods

necessary for carrying out the completion of works.

e) The CONTRACTOR shall if so required by TPCL within 14 days of the date of

determination assign to TPCL without payment, the benefit of any Agreement for

the execution of any works for the purpose of this contract but on the terms that

a supplier or sub-contractor shall be entitled to make any reasonable objection to

any further assignment thereof by TPCL. In any case TPCL may pay any supplier

or Sub-contractor for any work executed for the purposed of the Contract (whether

before or after the date of determination), in so far as the price thereof has not

already been paid by the CONTRACTOR. TPCL’s rights under the paragraph are in

addition to his rights to pay Sub-contractors under this paragraph and all such

payments may be deducted from any sum due or to become due to the

CONTRACTOR.

f) The CONTRACTOR shall as and when required in writing by TPCL so to do (but not

before) remove from the works any temporary buildings, plant, tool, equipment,

goods and materials belonging to or hired by him. If within a reasonable time after

any such requirements has been made the CONTRACTOR, has not complied

therewith then TPCL may (but without being responsible for any loss or damage)

remove and sell any such property of the CONTRACTOR, holding the proceeds less

all costs incurred to the credit of the CONTRACTOR.

g) The CONTRACTOR shall allow or pay to TPCL in the manner hereinafter appearing

the amount of any direct loss and/or damage caused to TPCL by the determination.

Until after completion of the works under this Clause TPCL shall not be bound by

any provisions of this Contract to make any further payment to the CONTRACTOR,

but upon such completion and the verification within a reasonable time of the

accounts therefore TPCL shall certify the amount of expense properly incurred by

TPCL and the amount of any direct loss and/or damage caused to TPCL by the

determination and if such amounts when added to the monies paid before the date

of determination exceed the total amount which would have been payable on due

Page 31: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 31 of 125 Signature of Contractor with seal

completion in accordance with this Contract, the difference shall be a debt payable

to TPCL by the CONTRACTOR and if the said amounts, when added to the said

monies be less than the said total amount, the difference shall be a debt payable

by TPCL to the CONTRACTOR.

39. Determination by TPCL

Default:

If the CONTRACTOR shall make default in any one or more of the following respects,

that is to say: -

If he without reasonable cause wholly suspends the carrying out of the works before

completion thereof, or if he fails to proceed regularly and diligently with the works, or

if he refuses or persistently neglects to comply with a written notice from TPCL

requiring him to remove defective work or improper materials or goods and by such

refusal or neglect the work is materially affected, or If he fails to comply with the

provisions, then TPCL may give him the notice by registered post or recorded delivery

specifying the default, and if the CONTRACTOR either shall continue such a default for

14 days after receipt of such a notice and shall at any time thereafter repeat such a

default (whether previously repeated or not), then TPCL without prejudice to any other

rights or remedies may within 10 days after such continuance or repetition of default

by notice by registered post or recorded delivery forthwith determine the employment

of the CONTRACTOR under this Contract, provided that such notice shall not be given

unreasonably or vexatiously.

40. Labour

a) The CONTRACTOR shall employ no child labour under 18 years of age on the work.

If female labour is engaged the CONTRACTOR shall make necessary provision for

safeguarding small children and keeping them clear of the site of operations. No

labour shall reside within the compound except authorized guards. Labour Acts

issued by the State/Central Government from time to time has to be followed

scrupulously.

b) The employees (Supervisor, technicians and Workers – full time and part time)

indicated in the bill of quantities is an essential term of contract. TPCL shall be

entitled at all times to inspect or calculate the actual manpower deployed at TPCL.

If during such inspection or calculation, TPCL discovers that the agreed minimum

manpower has not been deployed, then TPCL shall be entitled to deduct

proportionate amount from the lump sum quoted for the deployment of the

manpower. This right of TPCL shall be without prejudice to any other right of TPCL

available under this Contract on such matters

41. Guarantee

Besides guarantees required elsewhere, the CONTRACTOR shall guarantee the work in

general and shall submit all required guarantees to TPCL when requesting certification

of accounts for payment by TPCL.

42. Disputes: “Arbitration”

a) All disputes, differences or claims of any kind whatsoever arising out of or relating

to, this agreement, or its validity, construction, breach or performance between

the parties to the Agreement shall be finally settled through Arbitration. However

the parties shall first endeavour to settle the same amicably in a spirit of co-

operation.

Page 32: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 32 of 125 Signature of Contractor with seal

(i) The arbitration shall be governed by the Arbitration & Conciliation Act

1996 of India as amended up to date.

(ii) The arbitrator shall be appointed by Managing Director and Company

shall ensure that Arbitrator shall satisfy the norms of independence as

provided in Arbitration & Conciliation Act 1996 and any amendment

thereon.

(iii) The arbitration hearing and all proceedings in connection therewith shall

take place in Coimbatore and the language of the arbitration shall be

English.

(iv) The arbitration award shall be final and binding on the parties, and shall

be enforceable in any competent court of law and the parties agree to

be bound thereby and to act accordingly. The rights of the parties shall

remain suspended in relation to matters which are being arbitrated. Each

party shall bear its own costs for the arbitration and any attorney’s fees,

unless declared otherwise by the arbitral award.

(v) The Courts in Coimbatore shall have exclusive jurisdiction to try any and

all disputes arising out of this agreement, including the Arbitration

Agreement.

b) Except as above, all matters arising under this agreement shall be subject to the

exclusive jurisdiction of the Courts at Chennai only.

43. Protection and cleaning

The CONTRACTOR shall protect and preserve the work from all damage or accident by

providing any temporary coverings, boxing or other construction as required by TPCL.

This protection shall be provided for all property adjacent to the site as well as on the

site.

44. The bidder should physically inspect the entire systems which are to be covered

under contract and also to make an assessment of the average consumption of

consumables/spares etc., before quoting their rates.

45. In case of any damage/theft/injury to TPCLs people/tenants/premises/ property

/assets/installations due to negligence of his workers for which Contractor is

accountable, the Contractor will be liable to pay the compensation to TPCL as

decided and advised by TPCL.

46. The Contractor shall keep proper upkeep of all the areas under the contract.

47. The Contractor shall maintain liaising with concerned Statutory Body (ies), if any

on behalf of TPCL to get permissions/licenses/permits etc. as and when required.

48. Registers and Forms

The Contractor shall maintain the following records and log books during the contract

period:

The Contractor shall be responsible to maintain the registers/forms as required under

the prevalent labour laws in force from time to time. The Contractor shall maintain the

above neatly, completely and legibly for inspection by various statutory authorities

and the company officials even at short notice.

Page 33: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 33 of 125 Signature of Contractor with seal

49. Withdrawal of Contract Services in between the Contract Period

If contractor desires to withdraw the contract:

a) The contractor has to issue 3 months notice to terminate the contract.

b) The Contractor has to pay two months labour bill as penalty

c) Performance Bank Guarantee given by the Contractor will be revoked by TPCL.

Page 34: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 34 of 125 Signature of Contractor with seal

6. PRE - QUALIFICATION CRITERIA

1. The bidder must be a Firm or a Company registered under Companies Act, with a

minimum experience of 5 years in the field of Integrated Operation & Non-

Comprehensive Maintenance of ACMV, BAS, DG Sets & Connected Works.

2. The bidder should have a minimum average annual turnover of Rs.1 crore for any

three financial years during the last five financial years. Audited / certified balance

sheet (by Chartered Accountant) for all 5 years shall be submitted.

3. The Bidder should submit Solvency Certificate for Rs.80 Lakhs issued by any

scheduled commercial bank. The Solvency Certificate should not have been

obtained earlier than 3 months from the date of issue of tender.

4. Capacity magnitude

Bidder’s should have experience in handling any of the following two works during

the last three years

i) 2000TR ACMV system in single location.

ii) The intending bidder should be OEM (Honeywell) / OEM Authorized Channel

Partner / Solution provider of Honeywell Building Management System or

must have back to back agreement with Honeywell for supply of spares and

comprehensive onsite maintenance support. The Bidder must submit

authorization letter from Honeywell, clearly stating that bidder has the

competence to provide maintenance service for Honeywell, Niagara AX /

WEBs-N4 Supervisor / WEB 600/ 200/ 8000 Series Controller system,

Spyder DDC Controller. The bidder should submit necessary proof for

getting the back to back AMC from Honeywell along with the tender

document.

iii) 3 Nos x 2000 KVA DG sets in single location. The bidder should submit an

undertaking from the Original Equipment Manufacturer (MTU and Leroy

Somer) stating that they would facilitate the bidder on a regular basis for

the maintenance and service support of MTU engine and Leroy Somer

during contract term.

5. Experience in Multistoried Building (MSB)

Bidder should have successfully completed similar works in any three years during

the past five years in which atleast two years of work was carried out at the same

facility.

“Similar work” mentioned above shall mean successful completion of operation and

maintenance services of ACMV, BAS and DG works in atleast one MSB of 10 lakh square

feet or in two MSBs of 5 lakh square feet each, in IT parks / commercial complexes /

hospitals / offices of the financial institutions, Central & State Government

Departments or Organisations, Public Sectors Undertakings or reputed multinational

companies in India.

Page 35: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 35 of 125 Signature of Contractor with seal

(The following combinations are permitted

• Three continuous years in single MSB of 10 lakh square feet

• Three continuous years in two MSBs of 5 lakh square feet each

• Two continuous years in one MSB and one year in another, of 10 lakh square

feet each

• Two continuous years in two MSBs and one year each in two MSBs, of 5 lakh

square feet each

• Two continuous years in each of the three MSBs of 5 lakh square feet each

• Two continuous years in one MSB of 10 lakh square feet and one year in two

MSBs of 5 lakh square feet each

• One year in one MSB of 10 lakh square feet and two continuous years in 2 MSBs

of 5 lakh square feet each)

6. Consortium of bidders is not allowed.

Page 36: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 36 of 125 Signature of Contractor with seal

7. SCOPE OF WORK UNDER

VARIOUS OPERATIONS

Page 37: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 37 of 125 Signature of Contractor with seal

7A – AIR CONDITINING AND MECHANICAL

VENTILATION WORKS

I. ACMV Works

The ACMV system at TPCL comprises of the following:

1. Air Cooled Chillers.

2. Water Cooled Chillers.

3. Constant Speed & Variable Speed Pumping system.

4. Induced Draft Cooling towers

5. Double Skin Air handling units (AHUs).

6. Fan coil units (FCUs) and Cassette units.

7. Gas based spilt units.

8. Latent Heat Storage System.

9. Centrifugal & Propeller fans for mechanical ventilation systems.

10. Integrators for Integrating Chiller Packages for BMS System.

11. Induction Jet Vent Fans for Basement Exhaust System.

12. Motorized valves & thermostats for AHUs & FCUs.

13. Pressurized expansion tanks along with accessories.

14. Chilled water, condensing water and condensate drain piping inclusive of all

valves and fittings.

15. Sheet metal ducts inclusive of external insulation, acoustic lining, canvas

connections, silencers, and volume control dampers and smoke dampers and

similar ducting for toilet exhaust systems..

16. Supply and return air diffusers.

17. Insulation of pipes pumps and tanks.

18. Vibration isolators for all ACMV equipment.

19. Enthalpy Recovery Wheels

20. Variable Frequency Drives

21. Associated Electrical Works

22. Automation of the system.

II. Ventilation Systems:

i) Basement ventilation (for car parking areas).

ii) Kitchen / Pantry Exhaust.

iii) Electrical Room Exhaust.

iv) Rest Room Exhaust and Fresh Air.

III. SCOPE OF WORK

The Scope of work includes (but not restricted to) the following.

1) TPCL has critical requirement of Air-Conditioning for clients. In no case, outage of

Air conditioning for critical, Water cooled and comfort circuit is not acceptable.

2) Hence, the essence of this contract is to achieve ‘Zero Breakdown”. All efforts are

to be made with up to date maintenance in achieving this, by using predictive and

proactive maintenance techniques at times, and, by strictly adhering to preventive

maintenance practices and schedules. Only qualified with experienced Engineers

and Technicians who have carried out similar works with good track records shall

be considered for engagement.

Page 38: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 38 of 125 Signature of Contractor with seal

3) Operation and routine, preventive and breakdown maintenance of 17 Nos. Chillers,

compressors, Breakers, Contactors and controlling/protective accessories.

4) Contractors shall engage and deploy experienced technical staff, who have

experience in troubleshooting to meet these kinds of requirements and handling

Break down situations. The detailed scope of work is as follows:

a) Operation and routine, preventive and breakdown maintenance of, LT PCC and

Distribution panel, AHUs, Chillers and VFD Panel, Main Distribution Boards,

Panels DB’s, PDB’S in, Utility Building, DIDW Fans, JET FANs and their Control

Panels, Primary and secondary pumps & motors and their control panels, all

Motors & pumps, Exhaust fans, Fresh air fans, OHT Cranes motors and control

panels, LT cables & Wirings, Pumps Electrical System, electric switchgear and

drives for primary and secondary pumps, control panels and motors.

b) Liasioning with Electrical Inspectorate, for Annual Safety Inspection, and any

other works related with Electrical Inspectorate and Documentation.

c) Any addition or alterations made in the ACMV system during the tenure of this

contract, have to be maintained by the contractor.

d) All small fabrication works, repairs, servicing of machines / equipment / parts

therein shall have to be carried out by the contractor within specified time.

Contractor shall never say ‘no’ to any of the requirement of TPCL, which is in

the area of technical services, as found reasonable to be entrusted onto the

contractor by Engineer In charge.

e) All works to be carried out in accordance with relevant Indian Standards and

as per Indian Electricity rule as amended. The contractor has to obtain

necessary clearance from Electrical Inspectorate. Panels, Fittings, Equipment,

Systems etc., all the components, accessories, Sub-Assembly, assemblies etc.

which are attachments or parts needed for the purpose. Any other work which

are incidental or part of the above, but not specifically spelt out will also be

included in the scope.

f) For carrying out the job, the contractor has to make his own arrangements for

tools, tackles and measuring equipment, measuring meters, safety and

protective devices for carrying out the work.

g) TPCL is an Information Technology Park and has critical requirement. Please

note maintenance should be in such a way that the break down should not be

more than 8 hrs in any case.

h) For some of the emergency load points power availability has to be monitored

round the clock.

i) Contractor will ensure consistency of work and workforce, correct trouble

shooting, good workmanship, follow all safety procedures and will make all

necessary efforts to maintain healthy environment and reliable services.

j) All equipment that require repairing shall be immediately serviced and repaired.

k) The contractor shall operate & maintain, test and adjust all air conditioning,

ventilation and exhaust system units, fan motors, all air handling appliances

provided in this connection and shall make all necessary adjustments and

corrections thereof including the adjustments of all regulating dampers.

Page 39: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 39 of 125 Signature of Contractor with seal

l) The Operation & Maintenance [to identify when maintenance is required and to

monitor performance and to diagnose problems more quickly and adequately

than through traditional means] preventive maintenance visits by qualified

personnel of the ACMV Contractors who are thoroughly familiar with the type

of equipment and system. Maintenance will consist of monthly maintenance

and necessary adjustment and lubrication of the equipment by the contractor’s

under competent direction and supervision.

m) These consumable materials shall be provided to ACMV contractor by TPCL.

n) All the maintenance work will be performed during regular hours of regular

working days. However the works in condenser, coil and cleaning of cooling

coils etc. should be carried out with prior permission from the TPCL.

o) Response Time-Any breakdown which is deemed which is deemed to be Minor

shall be rectified within 4 Hours from the time of breakdown. Major breakdown

shall be rectified within 12 Hours from the time of breakdown. This excludes

material replacement and dependency cases.

p) It is expected that persons operating/maintaining or servicing these equipment

should possess the knowledge for performing the tasks properly and safely.

q) During operation/maintenance or service, individuals may be exposed to

certain components or conditions including, but not limited to, refrigerants, oils

and materials under pressure, rotating components and both high and low

electrical voltages. Each of these items has the potential, if misused or handled

improperly to cause bodily injury or death. It is essential that operating /service

/maintenance personal identify and recognize these inherent hazards, protect

themselves and proceed safely in completing their tasks.

r) Works on electronic equipment should not be undertaken unless the

individual(s) have been trained in the proper maintenance of equipment and is

(are) familiar with the potential hazards. System components should be

maintained according to the individual manufacturer recommendations, as their

operation will affect the operation of the ACMV system.

s) As a minimum requirement, the ACMV Contractor shall carry out the inspection,

maintenance and service of all machinery and equipment comprising the ACMV

systems in accordance with the periodic service schedule and at the time of

such inspections shall perform when and where necessary the normal services.

t) ACMV Contractor shall submit TPCL the details of the proposed preventive

maintenance schedule. Any other services that will normally form part of

maintenance requirement as per International Best Practice shall be deemed to

be included in the scope of work for Operation and maintenance.

u) The maintenance intervals of the filter directly depends on the air cleanliness

of each locality. A dirty filter alters the pressure balance in the machine. It is

strongly recommended that the ACMV Contractor set up programme which

ensures that filters are replaced or cleaned prior to getting clogged “enough”

to become system problem.

v) In addition to the regular monthly inspection and service, the ACMV Contractor

shall also perform the following items of work:-

Page 40: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 40 of 125 Signature of Contractor with seal

w) Every 3 months, check and analyse the oil and refrigerant of all water chilling

units and replace oil and refrigerant, if necessary. Every 3 months, check and

balance outside air quantities for all air handling units.

x) Every 6 months, check and clean all strainers on pipe work.

y) Every 12 months, check and balance water flow rates for all equipment. Every

12 months overhaul all water chilling units including inspection and cleaning of

heat exchanger tubes of condenser and chiller.

z) The ACMV Contractor shall supply the necessary labour, equipment and

instruments for testing of the systems in the ACMV system by the Authorities

during inspection. After every inspection and service, the ACMV Contractor shall

submit a written report to TPCL.

IV. Manpower Requirement

1. Man Power requirement for Maintenance of ACMV and Connected

Works

S.

No. Designation

No. of

persons Qualification Minimum Exp. in O&M

ACMV Works

1. O&M

Incharge

1 Engineer

Graduate in

Mechanical

Engineering

Should have minimum 10 years

experience in operation and

maintenance of Air Conditioning system

of capacity not less than 2000 TR

Diploma in

Mechanical

Engineering

Should have minimum 12 years

experience in operation and

maintenance of Air Conditioning system

of capacity not less than 2000 TR

2. Shift

Mechanical

Engineer

4 Diploma in

Mechanical

Engineering

Should have minimum 5 years

experience in operation and

maintenance of Air conditioning system

3. Shift

Electrical

Engineer

4 Diploma in

Electrical and

Electronics

Engineering

Should have minimum 5 years

experience in operation and

maintenance of Electrical switch gears

with “C” license.

4. Shift

Technician

8 Diploma -

Mechanical /

Electrical /

Cert. course

in AC

Should have minimum 2 years

experience in operation and

maintenance of ACMV

ITI –

Mechanical /

Electrical /

Cert. course

in AC

Should have minimum 3 years

experience in operation and

maintenance of ACMV

5. Helper 4 8th or SSLC Should have minimum 4 years

experience in operation and

maintenance of ACMV

ITI –

Mechanical /

Electrical

Fresher

Total 21

Page 41: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 41 of 125 Signature of Contractor with seal

Note:

a) Working hours for Operation & Maintenance of ACMV and Connected Works will be

round the clock, seven days a week, 365 days an year including Sundays, Festivals,

National Holidays / Holidays. Adequate number of personnel as per tender

document shall be deployed by the Contractor in suitable shift duties. Exact working

hours will be fixed in consultation with Officer-in-Charge of TPCL. The Contractor

shall abide by all the Statutory Laws while deputing personnel in TPCL premises.

The personnel deployed by the Contractor should be duly qualified and trained

having requisite experience.

b) The above manpower is minimum requirement for routine O&M of ACMV and

Connected works. In case of Annual Maintenance, major breakdowns, emergency

situation etc., Bidder has to provide required manpower, tools, tackles, testing

instruments etc. to fulfill the contractual requirement. If the bidder feels that the

above minimum manpower is not adequate for routine operation and Maintenance

of ACMV works, the bidder shall engage more manpower within quoted price.

c) The Contractor shall deploy the required number of employees / workmen as stated

above to ensure rendering satisfactory services round the clock in three shift basis

including shift relievers, as may be required by TPCL.

d) The Contractor shall deploy such of their personnel who are courteous, trained well

mannered and disciplined. The personnel deployed by the Contractor should observe

at all times during the contract period, strict discipline and should see that the

decency and decorum are maintained during the course of their working. They shall

abide by the disciplinary procedures; rules, regulation, guidelines, Standing Orders

laid down by TPCL and shall strcitly follow the instructions given by the

representative or office incharge of TPCL from time to time.

e) Contractor shall take suitable measure in the event of any of his personnel failing to

observe discipline and decency in the campus as may be brought to the knowledge

of the Contractor and shall make immediate replacement of such of the personnel

who are habitually indulging in commissions & ommissions of acts which

would render the services of the Contractor in effective. In case of failure to do on

the part of the Contractor, TPCL would be at liberty to restrict the entry of such

personnel inside the campus and in such an event, necessary deduction shall be

effected from the monthly bills of the Contractor.

2. The Contractor shall employ the required number of personnel for carrying out

the jobs specified in the tender round the clock and as per following shifts for

rendering satisfactory services:

Shift 1st Shift 2nd Shift 3rd Shift

Reliever General

Timings 6 am – 2 pm 2 pm – 10 pm 10 pm – 6 am 9 am – 6 pm

O&M Incharge 1 General Shift - 9 am to 6 pm

Engineers 8 1 1 1 1 4

Technicians 12 2 2 2 2 6

Page 42: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 42 of 125 Signature of Contractor with seal

(8 hours working per day in a calender month of 30/31 days including wages of weekly

off. No Shift person shall be allowed to work beyond normal shift time, (specific

approval to be obtained from TPCL incase of exigency).

V. PERIODIC MAINTENANCE & SERVICE SCHEDULE

As a minimum requirement, the ACMV Contractor shall carry out the inspection,

maintenance and service of all machinery and equipment comprising the ACMV

systems in accordance with the periodic service schedule listed below and at the time

of such inspections shall perform when and where necessary the normal services listed

below:

Though the list is exhaustive, it cannot be taken to be all inclusive. Hence, any other

services that will normally form part of maintenance requirement as per International

Best Practice shall be deemed to be included in the scope of work for maintenance

contract. The maintenance intervals of the filter depends on the air cleanliness of each

locality. A dirty filter alters the pressure balance in the machine and thus performance. A. CHILLER

MONTHLY INSPECTION AND SERVICE

a) Check refrigerant level, Leak test with electronic leak detector. If abnormal, trace

fault and rectify as necessary. Inform CLIENT’S in writing on the rectification.

b) Inspect level and condition of oil. If abnormal, trace fault and rectify as necessary.

Inform CLIENT’S in writing on the rectification.

c) Check the liquid line sight glasses for proper flow.

d) Check all operating pressure and temperature.

e) Inspect and adjust, if required, all operating safety controls, motors, control panels

and accessories.

f) Check capacity control. Adjust if necessary.

g) Check motorised valves and its BAS functions and Inlet and outlet valves of chill

water lines.

h) Visual inspect machine and associated components and listen for unusual sound or

noise for evidence of unusual conditions.

i) Check lock bolts and chiller spring mount.

j) Review daily operating log maintained by CLIENT’S’s operating personnel.

k) Providing written report to CLIENT’S, outlining services carried out, adjustment

made, rectification carried out and if the deficiency is of a major nature, arrange

with CLIENT’S for shut-down to rectify equipment

l) Check motor terminals.

Page 43: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 43 of 125 Signature of Contractor with seal

m) Check connections in starter.

n) Check motor ground, meg. motor and connection wiring on each leg.

o) Check motor temperature cut-out, tighten motor terminals.

p) Check starter contacts, arc shield, transformer etc.

ANNUAL INSPECTION

a) Perform all functions for monthly check.

b) Check all flanges for tightness.

c) Change oil and oil filter, if required.

d) Check oil temperature control and oil acidity test.

e) Check dashpot oil, clean dashpot and replace oil when necessary.

f) Test and calibrate overload setting.

g) Inspect, calibrate and adjust to original specifications all gauges, safety and

operating controls including low temperature and high pressure cut-out, oil

pressure switch, load limit relay and electrical interlocks.

h) For Water cooled condenser systems, inspect condenser tubes for fouling.

i) If fouling exceeds original specifications, ACMV Contractor shall carry out cleaning

of the tubes.

j) For Air-cooled condenser coils, dust should not be allowed to accommodate on the

condenser coil surfaces. Cleaning should be as often as necessary (approximately

every six months) to keep coil clean.

k) Exercise care when cleaning the coil, use a soft brush and a sprayer, so that the

coil fins are not damaged. Under no circumstances should this unit be clean with

Acid based cleaner.

B. WATER PUMPS

MONTHLY INSPECTION

a) Inspect all water pumps, motors, control panels etc.

b) Check all seals, glands and pipelines for leaks and rectify as necessary.

c) Re-pack and adjust pump glands as necessary.

d) Check all pump bearings and lubricate with oil or grease as necessary.

e) Check the tension of all belt drivers and adjust as necessary.

f) Check the alignment and condition of all rubber couplings between pumps and

drive motors and rectify as necessary.

Page 44: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 44 of 125 Signature of Contractor with seal

g) Check all bolts and nuts for tightness and tighten as necessary.

ANNUAL INSPECTION

a) Perform all function for monthly checks.

b) Check motor ground, meg. motor and connection wiring on each leg.

c) Tighten motor terminals.

d) Check starter contacts.

e) Test and calibrate overload setting.

C. EXPANSION TANK

MONTHLY CHECK

a) Inspect expansion tanks. Drain, clean and flush out tanks as necessary.

b) Analyse chilled water and check on chemical treatment.

D. FANCOIL UNITS AND AIR HANDLING UNITS, CASSETTE UNITS AND SPLIT

AC UNITS

MONTHLY INSPECTION

a) Check all air filters and clean or change filters as necessary.

b) Check all water coils, seals and pipelines for leaks and rectify as necessary.

c) Check and re-calibrate modulating valves and controls. Adjust and rectify as

necessary to ensure compliance to the original specifications.

d) Purge air from all water coils.

e) Checks all fan and motor bearings and lubricate with grease as necessary and

motor cable terminal tightness, control panel tightness etc.

f) Check the tension of all belt drives and adjust as necessary.

g) Check and clean all the condensate pans, trays and drains.

h) Check, measure and re-calibrate all sensors as necessary.

i) Check, clean and service smoke detectors. Carry out a system test to ensure that

the smoke detector will trip the AHU’s.

j) Check spring vibration isolators for abnormal vibration. Rectify as necessary.

k) Coil to be cleaned by (a) spray of high-pressure clean water (not exceeding 30 Psi)

(b) with chemical spray, if necessary.

Page 45: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 45 of 125 Signature of Contractor with seal

ANNUAL INSPECTION

a) Perform all functions for monthly checks.

b) Check motor ground, meg. motor and connection wiring on each leg.

c) Tighten motor terminals.

d) Check starter contacts.

e) Test and calibrate overload settings.

E. VENTILATION

MONTHLY CHECK AND ANNUAL INSPECTION

a) Check, adjust as necessary the air flow of all fans are in compliance with the original

specification.

b) Check the tension of all belt drives and adjust as necessary.

c) Check and lubricate all fan and motor bearings, check the control panels etc.

d) Tighten motor terminals.

e) Check starter contacts.

f) Test and calibrate overload settings.

g) A system check shall be carried out for all Mechanical ventilation (MV),

Pressurization and Exhaust System to verify the performance of the systems.

D. ELECTRICAL PANELS

MONTHLY AND ANNUAL INSPECTION

a) Clean and adjust all switchgear, contactors, relays and associated electrical

equipment at intervals not exceeding six months.

b) Check and prove operation of thermal overload and protection devices.

c) Check and ensure tightness of all equipment fastenings and cable terminations

within switchboards.

d) Vacuum clean all switchboard cubicles.

E. PIPING SYSTEM

MONTHLY AND ANNUAL INSPECTION

a) Check all piping systems for leaks and repair these where they have occurred.

b) Check for damage or deterioration of insulation or sheathings. Rectify as necessary.

c) Check all valves, meters and their insulations.

F. MEG SYSTEM

Page 46: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 46 of 125 Signature of Contractor with seal

MONTHLY CHECKING EM

Monthly checking of MEG - PH and density and top up the MEG as required.

VI. CONSUMABLE MATERIALS

1. All consumable materials will be supplied by TPCL.

2. All oils and greases required for lubrication of compressors, fan bearings, motors

bearings, pivots and other moving parts. All refrigerants required to replace

refrigerant losses in the refrigerant systems.

3. All consumable, filter elements / rolls.

4. All Chemicals for the correct chemical treatment of the chilled water system.

5. All carbon brushes required to replace worn brushes in electric motors.

6. All electric contact points required to replace worn electric contact points in

switchgears, motor starter gears, electronic control gears and electric relays.

7. All electric fuses required to replace blown fuses.

8. All cotton waste, soap detergent and other cleaning materials required for

cleaning purpose.

9. Mono-ethylene Glycol.

10. Necessary quantity cooling water chemicals, micro biocides for control destruction

of corrosion and scaling due to dissolved solids, the growths of fungi and algae etc.

Corrosion control shall be done every day / month and microbiological control shall

be carried out quarterly per annum.

VII. SPARES OWNED BY TPCL

The Spares owned by TPCL shall be used by Contractor and TPCL shall replenish /

replace the items used at site. Necessary requirements of usage on weekly/monthly

basis shall be furnished by the Contractor.

VIII. List of Equipment

S.NO EQUIPMENT UOM QTY

1 Critical Chiller Nos 7

2 Brine Chiller Nos 3

3 Comfort Chiller Nos 3

4 Water Cooled Chiller Nos 4

5 Cooling Towers Nos 4

6 Make Up water Pump Nos 2

7 Comfort Water Cooled Primary pump Nos 6

8 Comfort Air Cooled Primary pump Nos 4

9 Comfort Water Cooled Secondary pump Nos 5

10 Plate Heat Exchanger – Chill Water pump Nos 6

Page 47: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 47 of 125 Signature of Contractor with seal

11 Plate Heat Exchanger – Thermal Storage Primary pump Nos 6

12 Brain Air Cooled pump Nos 3

13 Critical Air Cooled Primary pump Nos 8

14 Comfort Chill Water Secondary pump Nos 5

15 Comfort Chill Water Secondary pump Nos 4

16 Plate Heat Exchanger Nos 4

17 Thermal Energy Storage Tank Nos 47

18 Air Handling Units Nos 87

19 Heat Recovery Wheel Nos 59

20 Ceiling Suspended Units Nos 3

21 Plenum Nos 87

22 Pantry Exhaust Fan Nos 4

23 Electrical Room Exhaust Fan Nos 4

24 Fresh Air Unit AHU Nos 4

25 Fresh Air-Gents Toilet Nos 8

26 Fresh Air-Ladies Toilet Nos 8

27 Exhaust Air-Gents Toilet Nos 8

28 Exhaust Air-Ladies Toilet Nos 8

29 Lift Well Pressurization Unit Nos 8

30 Stair Case Pressurization Unit Nos 18

31 Lift Lobby Nos 4

32 Fresh Air unit AHU-B1 Nos 2

33 Fresh Air-Kitchen Nos 4

34 Exhaust Air-Kitchen Nos 4

35 Fresh Air-STP Nos 1

36 Exhaust Air-STP Nos 1

40 Jet Fan Nos 300

41 DIDW Fan-Fire Mode Nos 30

42 DIDW Fan-Normal Mode Nos 30

IX. LIST OF MINIMUM TOOLS AND TACKELS TO BE PROVIDED BY THE

CONTRACTOR

All the tools required for carrying out the work stipulated in this document shall be

provided by the Contractor at site. But, the following minimum is a must at all times:

Sl.

No. Description Unit

Qty.

1. Air Blowers Nos 2

2. Heavy Duty Wet And Dry Industrial Vacuum Cleaner Nos 2

3. Hand drilling machine - small / Heavy Duty Nos Each 1

4. SKF full Bearing assembly kit set 1

Page 48: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 48 of 125 Signature of Contractor with seal

5. Laser Alignment Tool kit set 1

6. Oxy - Accetylene Gas cutting & welding set with cylinders set 1

7. Dial Gauge set set 1

8. Hydraulic puller set set 1

9. Complete spanner sets set 3

10. Flaring Tool set Set 1

11. Oil charging pump for chiller compressor Set 1

12. High Pressure washing pump with 10 meter length hose Set 1

13. Refrigerant Vaccum pump Set 1

14. Refrigerant Recovery pump Set 1

15. Manifold set with gauges Set 1

16. Vibration meter No. 1

17. Taco meter - IR No. 1

18. Megger No. 1

19. Multi meter No. 3

20. Water Balancing meter Set 1

21. Loop calibration meter No. 1

22. Clamp meter No. 2

23. Temperature Thermometer – IR No. 1

24. Electrical Refrigerant leak detector No. 1

All the Engineers/Technicians should be given with the following:

a) One set of screwdrivers (one light duty & one heavy duty) with insulated handles.

b) One cutting plier, 500V grade with insulated handles.

c) One live line tester, 500 Volts

Following tools should always be available at site:

a) One set of Box type Spanner with Ratchet

b) One Heavy duty hydraulic Cable Crimping tool (to crimp size up to 300 Sq.mm)

c) Two sets of 6-7 to 30 – 32 size 9 metric 0 double end open spanner

Page 49: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 49 of 125 Signature of Contractor with seal

d) One set of 6-7 to 30 – 32 size (metric) double end ring spanner

e) Two Nos. adjustable wrenches (12 inch)

f) One No. 0.5 to 16 sq.mm hand crimping tools

g) Two sets of allen keys

h) One star screwdriver set

i) One screwdriver set

j) Two Nos. of hammers (1lb & 2lb)

k) One soldering gun with lead & flux.

l) One drilling / hammering machine with drill bits (concrete / metal) (2.5mm to 16

mm each).

m) Two Nos of Tommy Bar

n) Two pairs of 11000 Volts grade Rubber Gloves (with valid test certificate)

o) Rubber mats.

p) One LT FRP Telescopic Earth / Discharge Rod (400v to 11 Kv)

Following calibrated and well maintained instruments should be available at

site:

1. One Clamp on Ammeter (Tong testers, preferably Kyoritsu make)

AC/DC -400 & 1000 AMPS

AC – 400V & 750V

DC – 400 V & 1000V

Resistance – 400 ohm to 4000 ohm

2. One Multi meters (True RMS preferably Fluke make)

CAT IV 600V – 50 to 500 MV

CAT III 1000V – 5V to 1000 V

DC – 400 mA to 5000 µA

Resistance – 50 ohm to 500 mega ohm

3. One 500V Megger / IR tester (analog) (with valid calibration and test certificate)

Page 50: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 50 of 125 Signature of Contractor with seal

7B - BUILDING AUTOMATION SYSTEM

Operation & Maintenance for Building Automation System

Preamble

1. TPCL has in place Honeywell Building Automation System comprising of Niagara

AX Supervisor, WEB 600/200 series of Network Controllers (JACE) and Spider

PUB6438S DDC Controllers. TPCL is in the process of upgrading the BAS by

using Niagara WEBs-N4 Supervisor and WEB 8000 series controllers.

2. BAS also comprise of Actuators, CO2 Sensors, Damper Actuators, Damper

Controllers, DP Switches, Flow meters, Valve Actuators, Temperature Sensors,

DDC Controllers, Network Controllers, associated software etc. The Building

Management System/Building Automation System works are to be Operated and

Maintained on a round the clock, full time basis for the specified period to a high

international standard. The details about the scope of work are more fully

described elsewhere in this document, but, in brief, the Owner expects the

Contractor to take a single point and full responsibility of Operation and

Maintenance of the Building Automation System covered by this contract.

3. TPCL requires a single point responsibility for the Contractor in controlling and

managing in respect of the works / system covered by this contract during the

entire contract period.

4. OEM Support

The Bidder / their sub-contractor must submit authorization letter from Honeywell,

clearly stating that bidder / their subcontractor has the competence to provide

maintenance service for Honeywell, Niagara AX / WEBs-N4 Supervisor / WEB 600/

200/ 8000 Series Controller system, Spyder DDC Controller. The bidder should

submit necessary proof for getting the back to back AMC from Honeywell along

with the tender document. If the bidder fails to do so, bidders shall be disqualified

from the tender process.

5. All maintenance for equipment, sub-system and installation shall include

planned preventive, routine, annual and breakdown maintenance. For each, the

Contractor should follow the existing procedures and if any improvement is

necessary, the same shall be incorporated after TPCL’s approval. During contract

period, Contractor may liaise with Original Equipment Manufacturer (OEM).

6. The work is for Operation and Maintenance under single point responsibility and

shall be with modern systems and services of International Quality, integrating all

functions necessary to support the daily operations to high-tech operations and

maintenance smoothly, deploying competent, trained and experienced work force

under a well structured system and using modern management techniques

including hardware and software support. Maintenance of BAS shall be ensured as

‘Life Time Care’ with planned preventive maintenance schedule, procedures, self-

audit and continuous improvement, precisely determining most appropriate type

and level of services to fulfillment of standards and objectives of TPCL Park.

Page 51: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 51 of 125 Signature of Contractor with seal

Contractors field organization and Equipment

Operation & Maintenance In-charge

1. The Contractor shall constantly keep a watch on his work during the progress of

work and shall deploy required qualified and competent engineer as an O&M

Incharge who shall have experience in the field of Operation and Maintenance of

Building Automation System Works.

2. The O&M Manager will be responsible for carrying out the job to the true meaning

of the Contract document, Schedule of Quantities, Technical specifications,

equipment operations, Owner instructions and directions to the satisfaction of the

Owner. Any directions or instructions given to him by the Owner or his authorised

representative shall be deemed to have been issued to the Contractor. The man

power of experienced and trained technical and non-technical support staff shall

assist the works as required to fulfill the scope of work envisaged as listed in this

document. The exact organisation chart to be implemented shall be got approved

from the Owner prior to commencement. If the Owner establishes at any time

the need to augment the field organisation, either on a short term or long term

measure, the Contractor is bound to implement Owner’s instructions forthwith

within the agreed rates.

3. In the case of replacement of any engineer so deployed with the others of

required qualification, TPCL shall be informed atleast 3 months in advance.

Frequent replacements of engineers has to be avoided. No staff shall be replaced

within one year from his date of joining unless otherwise, TPCL desires to relieve

him. No staff shall be relieved/replaced from this site, without the concurrence of

TPCL

Arrangement of Execution of Work

The Contractor shall arrange for all materials, tools tackles, equipment and labour

necessary including its transportation for proper execution and completion of the

job and contract to the satisfaction of the Owner.

II. SCOPE OF WORK

The scope of work under the contract includes the following:

a) The Contractor will provide maintenance services and will carry out day to day

operations, repairs and maintenance of the entire systems / equipment, including

fixing, installing of spare parts/ materials / consumables cabling, pipes, testing /

replacement of duct/space/ immersion temperature sensor/ RH sensor/Differential

Pressure sensor/CO2 sensor/Duct smoke Detectors/Fire Dampers/BTU

meters/Control Valve/Honeywell Spyder DDC / JACE Controllers.

b) To ensure smooth, trouble free and disruption free functioning of all the Niagra

supervisor systems and the systems/equipment that may be installed during

tenure of the contract.

Page 52: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 52 of 125 Signature of Contractor with seal

c) All the routine, preventive maintenance, overhaul, breakdown maintenance,

repair, maintenance, replacements of parts/equipment etc. are part of the Scope

of Work. Services are to be provided round the clock i.e. 24 hours, 365 days a year

in the building. Most of the activities of Electro Mech. Services (ACMV, Electrical,

Instruments) are integrated with BAS and to be maintained all the times.

d) Monitoring and maintaining Time Schedule of AHU required parameter of the

various equipment within the permissible limit as per the clients requirements.

e) Coordination with the fire team during fire simulation audit, emergency evacuation

and evacuation audits.

f) Trouble shooting of equipment related problems. Carryout necessary rectification

/ replacement and putting back the equipment into the operation within the

stimulated time.

g) Reporting of breakdown / abnormalities to TPCL

h) Reporting to TPCL about any faults arising in the devices of fire alarm system

including offline problems and alarms rises out of BMS.

i) Operating and maintenance of the equipment shall include routine check-up,

equipment preventive maintenance work and management of any breakdowns.

j) Maintain log books and records of operational / maintenance activities.

k) The contractor shall submit weekly, monthly and annual reports as required by

TPCL.

l) Any breakdown loss of material or damage to the BMS equipment as a result of

negligent activity on the parts of the Contractor shall deemed to be unsatisfactory

by TPCL and costs, damages would be recovered from the Contractor.

m) Response Time-Any breakdown which is deemed which is deemed to be Minor shall

be rectified within 4 Hours from the time of breakdown. Major breakdown shall be

rectified within 12 Hours from the time of breakdown. This excludes material

replacement and dependency cases.

n) The operation and maintenance of BMS equipment as listed below;

Page 53: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 53 of 125 Signature of Contractor with seal

LIST OF BAS EQUIPMENTS

SYSTEMS OS/APPLICATION FUNCTIONAL

AREA

SYSTEM

ARCHITECTURE

SOFTWARE

VERSION

MAKE/MODEL TOTAL

(Nos.)

BAS SERVER

HONEYWELL

NIAGARA AX

FRAMEWORK

BUILDING

MANAGEMENT

SYSTEM

TO CONTROL

ACMV SYSTEMS

INTEGRATED

WITH BAS

WORKBENCH

VERSION -

3.3.22

HP PROLIANT

ML330G6,

Windows 2008

R2

3

BAS

WORKSTATION

WINDOWS 10

PROFESSIONAL

BUILDING

MANAGEMENT

SYSTEM

TO CONTROL

ACMV SYSTEMS

INTEGRATED

WITH BAS

HP Elite Desk

800G4 1

BAS

WORKSTATION

WINDOWS 7

PROFESSIONAL

BUILDING

MANAGEMENT

SYSTEM

TO CONTROL

ACMV SYSTEMS

INTEGRATED

WITH BAS

HP PRO3090MT 2

BAS

WORKSTATION

WINDOWS 7

PROFESSIONAL

BUILDING

MANAGEMENT

SYSTEM

TO CONTROL

ACMV SYSTEMS

INTEGRATED

WITH BAS

DELL OPTIPLEX

380 1

S. NO. FIELD DEVICES MAKE MODEL Total Qty

1 NETWORK CONTROLLER HONEYWELL WEB600 5

2 NETWORK CONTROLLER HONEYWELL WEB201 2

3 DDC CONTROLLER HONEYWELL PUB6438S 560

4 VFD DANFOSS P101/102 71

5 CHW Valve Actuator -2WAY VALVE FLOWCON S.M3.1/4.1 90

6 Differential Pressure Switch GREYSTONE GFS80N-1K 440

7 Duct Temperature Sensor GREYSTONE TE200B20D2 660

8 CHW Temperature Sensor (20K) GREYSTONE TE200C20D2E 180

9 CHW Temperature Sensor (10K) CLIVET 34

10 Fire damper controller NIL NIL 570

11 Static Pressure Sensor GREYSTONE LP3A04 90

12 CO2 Sensor GREYSTONE CDD1A6000 90

13 RH Sensor GREYSTONE RH200A03K 90

14 Duct Smoke detector GREYSTONE SL-2000-P 140

15 Outside-Temperature/RH Sensor GREYSTONE RH300A05K 2

16 BTU Meter HONEYWELL UH50 193

17 BTU Meter LANDYS GYR T350 42

* The JACE controllers and Niagara AX supervisor mentioned in the above tables will

be migrated to Honeywell WEB 8000 Series Controller and WEBs-N4 Supervisor in

future

The following minimum maintenance schedule/procedures are to be adhered to for

carrying out the routine/maintenance works:

Page 54: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 54 of 125 Signature of Contractor with seal

a) Routine Preventive Maintenance Schedule: The Contractor shall also prepare a

Preventive Maintenance Schedule of all the systems in compliance with the

manufacturers recommendations and consultation with officer-in-charge of TPCL.

b) The Contractor shall also maintain Plant & Machinery/equipment history card to

ensure the full details of equipment, frequency of check and overhaul. The

Contractor shall provide list of inventories of critical spare parts/consumables etc.

to be maintained for the purpose of corrective and preventive maintenance to

ensure that the faults are rectified immediately without any downtime. It shall be

the responsibility of the Contractor to provide special tools, testing of equipment

always in readiness.

c) The Contractor shall strictly monitor the Scheduling of all AHU’s/Chillers/ Exhaust

fans and Building Automation System server /Workstations/ all process parameters

of temperature, RH, Flow of Chillers/AHU’s/Fire Dampers and other related

systems/services etc. and to ensure that the systems are operational at all times

round the clock. The Contractor shall maintain the monthly backup of Entire Niagra

Supervisor system and same to be maintained in storage medium given by TPCL.

During monitoring of the same, if any things unusual are noticed, like abnormal

noise in the AHU’s and Chillers etc. coming from any equipment, quick action

should be taken for rectification of the faults immediately.

d) As per request of tenants, the Contractor has to maintain & record of all the entries

of extra working hours, entries of AC energy consumption, electrical energy

consumption and submit the report as and when required.

e) The Contractor shall ensure that in emergency cases the reported fault/support

request is to be attended promptly and in any case within eight hours from the

reporting time and rectification thereof and defects/faults of general or not of

serious nature have to be ensured within 48 hours of the reporting.

f) All complaints have to be attended to, in minimum agreed time, as per industry

norms/practice, failing which, TPCL will be at liberty to get the work done on its

own/another agency and recover the costs incurred from your running bills/security

deposit.

g) In case of renovation/modification of any floor, the Contractor has to ensure safe

removal of existing sensors, controllers, JACE, Workstation, Servers, other systems

involved in BAS and again re-installation and configuration of the same with the

BAS system without any additional charges.

h) All systems/equipment shall be operated as per mutually agreed programs. The

Contractor shall maintain proper entry and upkeep of relevant log books/registers

as per statutory obligations in physical and shall also maintain complaints register,

and work done/carried out reports to the satisfaction of TPCL. The same can also

be maintained in soft copy.

i) Duty allocation and roaster control shall be the Contractor’s responsibility. Exact

working hours will be fixed in consultation with officer-in-charge of TPCL. TPCL

reserves the right to advise replacement/change in the manpower deployed by the

Contractor, if his service is found not satisfactory.

j) The Building Automation System works are to be Operated and Maintained on a

round the clock, full time basis for the specified period to a high international

Page 55: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 55 of 125 Signature of Contractor with seal

standard. The details about the scope of work are more fully described elsewhere

in this document, but, in brief, the TPCL expects the Contractor to take a single

point and full responsibility of Operation and Maintenance of the BAS covered by

this contract. The TPCL’s objective is that Contractor does not perceive this as a

short term or a one-time contract but as an exercise in Asset value maximization

and Asset Life Prolongation.

k) The bills of quantities are divided into several sections. The rates quoted for each

section shall be self sustainable and correct reflective of the Scope envisaged. TPCL

reserves the right to add or delete from the Scope of work, items as he may deem

fit. The successful bidder cannot make any claim on account of such changes.

l) For operations and Maintenance, provided will ensure availability of the Tools as

required at each location at their cost for effective operation and maintenance

The work is for Operation and Maintenance under single point responsibility and shall

be with modern systems and services of International Quality, integrating all functions

necessary to support the daily operations to high-tech operation and Maintenance

smoothly, deploying competent, trained and experienced work force under a well

structured system and using modern management techniques including hardware and

software support. Maintenance of Building Automation System Systems shall be

ensured as ‘Life Time Care’ with planned preventive maintenance schedule,

procedures, self-audit and continuous improvement, precisely determining most

appropriate type and level of services to fulfillment of standards as per objectives of

TPCL.

Operation and Building automation controls check the following on a quarterly basis:

1. Check operation of control valves, signal should be compared with feedback

2. Check operation of temperature sensors, apply offset and calibrate if required

3. Check operation of dampers in auto mode (check the feedback)

4. Check wiring termination in control panels and ensure tightness

5. Check chilled water control loop and operation of all associated devices

i) Quarterly ppm shall cover the following systems as well

ii) DDC panels

iii) Actuators

iv) Software/Application

v) Sensors

6. Vendor to discuss the plan for quarterly/ half yearly / annually Maintenance

before the PPM activity and MIS report after PPM with Concerned officer of TPCL.

7. Vendor to take up one training session at site every six months and to ensure

that all the concerned stakeholders are present for this as well.

8. Vendor to advice on the in-house maintenance.

9. Vendor to monitor the inventory of minimum critical spares at TPCL stores.

10. All the breakdown and service calls shall be attended as per the defined SLA.

11. All the critical components shall be tested for normal functionality.

12. Energy conservation measure shall be taken and discussed with Admin for any

recommendation and suggestion. If logic to be modified, get the approval and

commission the controller.

13. All spare parts required for repair/replacement of the equipment’s will be TPCL’s

scope.

Page 56: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 56 of 125 Signature of Contractor with seal

15. Corrective maintenance visits to be carried out within 24 hours of logging the

complaint.

16. Any repair / replacement of field equipment will be done within 24 hours of

identifying the fault.

17. Third party integration, hardware / software interface), need to be verified;

problem should be escalated to the Admin team.

18. Check the healthiness of the network communication system, if problem exist,

escalate to the admin team.

19. Possibilities to be explored for central monitoring system for the entire campus.

20. The reports and backup shall be shared when the TPCL officer requesting the

information.

The Building Management System will have following aspects:

1. Equipment Operation and Planned Preventive Maintenance.

2. Overall Management, Co-ordination and Reporting.

3. Managing statutory requirement for operation if any (License, NOC, etc.).

Equipment Operation

As part of operation of Building Management Systems following needs to be completed:

a) Check and verify all systems points on a daily basis

b) Check any points which are overridden with a temporary set point and clear

them

c) Verify operating schedules of equipment ensuring equipment operation is

meeting building occupancy. Bring any required changes to the attention of the

TPCL officer.

d) Verify that the set points are correct and are within the recommended limits

e) Check any outstanding alarms and clear

f) Complete daily operations report, energy usage report, occupancy report etc.

g) Ensure all data points from third party equipment like Energy meters, Chillers,

VFD’s are all displaying properly.

h) Capture any faulty devices, communication issues etc, in daily report and raise

required service requests to ensure timely closure of outstanding issued.

Maintain overall tracker of such issued. Maintain overall tracker of such issues.

i) Submit all trend charts of all equipment on a daily basis to TPCL officer.

j) Ensure system time is in synch with network time

As part of maintenance of the Building management System following needs to be

completed at least on a weekly basis:

a) Check all sensors are displaying the proper status

b) Check operation of all field controllers and associated devices

c) Check operation of dampers, field linkages

d) Check VFD drives for proper operation

e) Ensure chillers, chilled water pumps and VFD and associated equipment are

working according to sequence of operation for maximum energy efficiency and

occupant comfort.

f) Ensure all critical parameters of chiller are getting logged and trended

g) Check calibration of all sensors on an annual basis including temperature,

humidity, CO2 sensors

Page 57: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 57 of 125 Signature of Contractor with seal

Managing the Services

i. Provided will take ownership of all the services as described in this statement

of Work and will work as an independent unit. TPCLS intervention should be

only on major issues and not on routine/operational issues.

ii. Provided will ensure that the Checklists are adhered to with utmost care and

regularity

iii. Provided will ensure that the Preventive Maintenance is performed for all

equipment as per the Preventive Maintenance Plan.

iv. Provided will prepare and follow Standard Operating Procedures for smooth

functioning of the maintenance services, within 30 days of commencement of

agreement.

v. Provider site in charge will brief TPCL representative on maintenance and

operational proceedings on day to day basis

Reporting

Provider will submit the Daily, Weekly, Monthly, Quarterly, Half-yearly and Annual

Report as per the formats discussed and decided between TPCL and provider. These

Formats will be submitted by Provided within 2 weeks of commencement of Services

at TPCL and will be finalized within one week from submission.

The Reports will include the following:

i. The checklists which will be prepared by the Provided Supervisors for every

equipment at TPCL

ii. Report on Electrical Power consumption and BTU Energy consumption.

iii. Report on UPS Parameters

iv. Report in individual AHU operating parameters including zone temp, setpoint,

on/off status, VFD speed

v. Report on detailed Zone temperatures

vi. Report on chiller water equipment status

vii. Report on the Major Replacements & repairs undertaken

viii. Report on Inventory Status of Spares and Consumables

ix. report on forthcoming Preventive Maintenance

x. Report on breakdowns

xi. Report on Spares Consumption (Highlighting abnormal consumptions)

xii. Report on Employee Health & Safety (EFS)

xiii. Report on Customer satisfaction

The above Reports are indicative. final Reports and the Formats will be developed

and finalized as mentioned above.

Value -Adds & Key Deliverables of Provided

i. Minimum Emergency repairs-this will be monitored on a monthly basis and over

6 months of services there should be a decline in the number of incidents and

expense thereof towards the Emergency Maintenance

ii. Preventive Maintenance schedule to be followed with 100% compliance and

predictive maintenance techniques to be followed.

iii. Response and resolution Time to be followed to be complied within 100% of

the cases. Resolution time is to be complied with in 98% of the cases. In a most

Page 58: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 58 of 125 Signature of Contractor with seal

2% cases, wherein the problem is beyond the control pf provider, the

Resolution Time can go beyond the committed Time but has to be apprised to

TPCL and approved by TPCL. all such deviations are to be reported separately

to TPCL.

iv. All the Daily, Weekly, Monthly, Quarterly. Half-Yearly and Annual Reports and

Checklists to be adhered to.

v. Energy audits – Participate in Energy Audits

vi. Energy savings – Targets to be set with TPCL representative

vii. Maintaining adequate inventory of critical parts and reporting it a monthly

basis.

III. Manpower Requirement for Maintenance of BAS and Connected Works

S.

No. Designation No. of

persons Qualification Minimum Exp. in O&M

(No. of years)

1. O&M

Incharge 1

Engineering

Graduate in Instrumentation / Electronics /

Electrical Engineering

Should have minimum 10 years experience in operation and maintenance of Building Management system and should have experience in Honeywell BAS (Niagara AX/N4

Supervisor/ WEB600 / 8000 Series Controllers)

2. Shift

Engineer 4

Engineering/ Diploma

Graduates in Instrumentation

/ Electronics / Electrical

Engineering

Should have minimum 3 (For Engineering Graduates) / 5 (For Diploma holders) years of experience in

operation and maintenance of Building Management system

3. Shift

Technician 4

Diploma

Graduates in

Instrumentation / Electronics /

Electrical Engineering

Should have minimum 3 years of

experience in operation and maintenance of Building Management system

Note:

a) Categories are defined for the purpose of taking Minimum Wages into consideration,

as notified by the Govt. of Tamil Nadu from time to time that are to be paid to the

workers deployed by the Contractor at TPCL Site(s). However, for the Staff falling

under above Skilled Category and having Managerial/Specialized role at TPCL Site,

the bidders may consider wages as per industry standards.

b) Working hours for Operation & Maintenance of BAS and Connected Works will be

round the clock, seven days a week, 365 days an year including Sundays, Festivals,

National Holidays / Holidays. Adequate number of personnel as per tender

document shall be deployed by the Contractor in suitable shift duties. Exact working

hours will be fixed in consultation with Officer-in-Charge of TPCL. The Contractor

shall abide by all the Statutory Laws while deputing personnel in TPCL premises.

The personnel deployed by the Contractor should be duly qualified and trained

having requisite experience.

c) The above manpower is minimum requirement for routine O&M of BAS and

Connected works. In case of Annual Maintenance, major breakdowns, emergency

situation etc., Bidder has to provide required manpower, tools, tackles, testing

Page 59: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 59 of 125 Signature of Contractor with seal

instruments etc. to fulfill the contractual requirement. If the bidder feels that the

above minimum manpower is not adequate for routine operation and Maintenance

of BAS works, the bidder shall engage more manpower within quoted price.

d) The Contractor shall deploy the required number of employees / workmen as stated

above to ensure rendering satisfactory services round the clock in three shift basis

including shift relievers, as may be required by TPCL.

e) The Contractor shall deploy such of their personnel who are courteous, trained well

mannered and disciplined. The personnel deployed by the Contractor should

observe at all times during the contract period, strict discipline and should see that

the decency and decorum are maintained during the course of their working. They

shall abide by the disciplinary procedures; rules, regulation, guidelines,

Standing Orders laid down by TPCL and shall strcitly follow the instructions given by

the representative or office incharge of TPCL from time to time.

f) Contractor shall take suitable measure in the event of any of his personnel failing to

observe discipline and decency in the campus as may be brought to the knowledge

of the Contractor and shall make immediate replacement of such of the personnel

who are habitually indulging in commissions & ommissions of acts which

would render the services of the Contractor in effective. In case of failure to do on

the part of the Contractor, TPCL would be at liberty to restrict the entry of such

personnel inside the campus and in such an event, necessary deduction shall be

effected from the monthly bills of the Contractor.

3. The Contractor shall employ the required number of personnel for carrying out the

jobs specified in the tender round the clock and as per following shifts for rendering

satisfactory services:

Shift 1st Shift 2nd Shift 3rd Shift General

Timings 6 am – 2 pm 2 pm – 10 pm 10 pm – 6 am 9 am – 6 pm

O&M Incharge 1 General Shift - 9 am to 6 pm

Engineers 4 1 1 1 1

Technicians 4 1 1 1 1

(8 hours working per day in a calender month of 30/31 days including wages of

weekly off. No Shift person shall be allowed to work beyond normal shift time,

(specific approval to be obtained from TPCL incase of exigency).

Page 60: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 60 of 125 Signature of Contractor with seal

7C – DIESEL GENSET AND CONNECTED

WORKS

I. DG-MECHANICAL SCOPE OF WORK

Preamble

1. TPCL has in place DG plant with total capacity of 10 MVA (5 x 2000 KVA). The plant

is to provide 100% backup to entire operation of the Building. The DG Sets and

Connected works are to be Operated and Maintained on a round the clock (24 hours

x 7 days), full time basis for the specified period to a high international standard.

The details about the scope of work are more fully described elsewhere in this

document, but, in brief, the Owner expects the Contractor to take a single point

and full responsibility of Operation and Maintenance of the Diesel Generator Sets

and Connected works covered by this contract. The Owner’s objective is that

Contractor does not perceive this as a short term or a one-time contract but as an

exercise in Asset value maximisation and Asset Life Prolongation.

2. TPCL requires a single point responsibility for the Contractor in controlling and

managing in respect of the works / system covered by this contract during the entire

contract period. TPCL will impose / charge Liquidated Damages (not as penalty) on

the Contract in terms of one day’s O&M charges in case of failure of any utility /

service for each occurrence, for each day of delay has agreed by the contractor

herein.

The scope of work under the contract includes the following:

3. The work is for O&M under single point responsibility and shall be with modern

systems and services of International Quality, integrating all functions

necessary to support the daily operations to high-tech operations and

maintenance smoothly, deploying competent, trained and experienced work

force under a well structured system and using modern management

techniques including hardware and software support. Maintenance of DG Sets

and Connected works shall be ensured as ‘Life Time Care’ with planned

preventive maintenance schedule, procedures, self-audit and continuous

improvement, precisely determining most appropriate type and level of services

to fulfillment of objectives of TPCL Park.

The single point responsibility shall cover:

a) Taking possession with all service systems in satisfactory working conditions

duly tested and commissioned, from the existing Contract agency and in Co-

ordination with the Owner/Representative.

b) All maintenance for equipment, sub-system and installation shall include

planned preventive, routine, annual and breakdown maintenance. For each,

the Contractor should follow the existing procedures and if any improvement

is necessary, the same shall be incorporated after TPCL’s approval. During

Page 61: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 61 of 125 Signature of Contractor with seal

contract period, Contractor may liaise with Original equipment manufactures

(OEM). The selected Contractor shall co-ordinate with existing Contractor for

knowing existing operation and maintenance practices during handing over of

system

c) Adequately man the O&M implementation inclusive of support from their Head

Office, on Administration and Technical matters. Also provide adequately for

transport, insurance, uniforms etc. for all O&M staff.

4. OEM Service Support

The bidder should submit an undertaking from the Original Equipment

Manufacturer (MTU and Leroy Somer) stating that they would facilitate the

bidder on a regular basis for the maintenance and service support of MTU

engine and Leroy Somer during contract term.

5. The operator shall be required to record the duration of interruption in syst

em operation during power failure.

6. Operation and Maintenance of 5 Nos. of 2000 KVA MTU Make DG Sets,

Synchronizing panel, Ancillary panel, Sandwich bus ducts, Fuel pumps,

Ventilation system and Flue Gas Desulphurization (FGD) system during power

failures / load tests (schedule will be given by TPCL) as per OEM

recommendations

i. Logging, Monitoring and maintaining of required parameter values of

the DG sets within permissible limits.

ii. Devising Energy Efficient Pattern of Operation for DG Sets in line with

the energy conservation schemes of TPCL.

iii. Monitoring and maintaining the parameters of radiator coolant within

limits by topping up the DM water/Coolant chemicals.

7. All major breakdowns in Engine/Alternator/Connected Accessories shall be taken

up with OEM and repair has to be carried out under the Supervision of OEM. The

spares from OEM shall be arranged based on the report by OEM for all

breakdowns by TPCL. The contractor shall have arrangement with OEM for on

the spot study/analysis/repairs to be undertaken by OEM supervision. The details

of such arrangement shall be submitted to TPCL to be acceptable by TPCL.

8. The Contractor will maintain log books and registers in which full and detailed

records of all daily operational maintenance and repair activities will be kept to

provide a basis for preparation of periodic reports by the Contractor as required

to TPCL. All Log books and registers shall be accessible to TPCL at all times

during the period of contract.

9. Carry out change-over operations to DG power supply within 1 Minute during

power failures.

Page 62: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 62 of 125 Signature of Contractor with seal

10. Submitting of Completed PPM checklists/ Work orders and daily, weekly and

monthly reports to TPCL.

11. Trouble-shooting of equipment related problems by carrying out necessary

rectification /replacement and putting back the equipment into operation within

the stipulated time mentioned in the contract documents.

12. Generating spare consumption reports on a monthly basis and submitting to

TPCL.

13. The contractor will operate manage and maintain the system to suit the

Owner’s requirements for the whole of the Contract Period.

14. The Contractor shall undertake to carry out the Works in such a manner as to

ensure that the DG sets and connected works and equipment are fully

functional and performing.

15. The Contractor shall refer all operational and maintenance management issues

for consideration and decision to TPCL.

16. The primary purpose of carrying out the Works is to ensure that the best O&M

practices and engineering standards are maintained at all times round the year.

17. The Contractor will operate and maintain the equipment and system daily in

accordance with Original Equipment Suppliers operation and maintenance

specifications as a minimum requirement, and Standard O&M Procedures.

18. Daily Operation and Maintenance of the equipment will include routine checkup

of and adjustment to the equipment preventive maintenance works and

management of any breakdowns.

19. Any breakdown, loss of material or damage to the Plant as a result of negligent

activity on the part of the Contractor shall be deemed to be unsatisfactory

performance and must be immediately repaired to the proper condition and to

the satisfaction of TPCL at contractor cost.

20. The Contractor shall bring necessary tools, tackles, vibration monitoring

equipment and measuring equipment, for efficient operation and maintenance

of entire DG sets and connected works.

21. During annual maintenance period/ major breakdowns the Contractor shall

provide additional man power, tools, tackles etc. to manage the above in time.

22. The contractor should check and report to TPCL on daily stock of HSD. If HSD

stock level comes to minimum level, the same shall be informed immediately

and followed with TPCL for further procurement of HSD.

23. Planned Preventive Maintenance (PPM) to be done as per schedules / checklists

for DG sets and equipment and carrying out the PPM activities as per the

Page 63: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 63 of 125 Signature of Contractor with seal

Schedule /Checklist. The check list are to be updated based on OEM/TPCL

recommendations.

24. The scope of work other then the above also mentioned in anywhere in the tender

document is applicable during contract period.

25. The contractor shall co-ordinate with REPRESENTATIVE during TNPCB

inspection, CEIG inspections and other statutory inspections.

26. All measuring instruments (Energy meters, Voltmeters, Ammeters, relays,

circuit breakers, etc.) shall be tested and calibrated once in a year for ensuring

correctness of measurements and report to be submitted within the quoted

rate.

27. A further purpose of carrying out the Works is to ensure that all plant and

equipment to be maintained to a standard that will ensure that at the end of

the Contract Period all the plant and equipment should be handed over in a

satisfactory working condition.

28. Periodically carrying out painting of equipment/ pipelines/stack/ platforms, as

and when they get damaged / peeled off.

29. Maintaining the lubricating oil levels by topping up the same as and when

required.

30. Replacement of damaged oil/ air/ fuel oil filters (Lubrication Oil and filters will

be supplied by TPCL).

31. O&M of FGD system. (Consumables Supplied by TPCL)

32. The contractor shall arrange OEM inspection/health checkup for all DG

Engines/Alternators/ Equipment on yearly basis and OEM should submit report

to owner.

33. Checking and maintaining of battery voltage and acid specific gravity within

permissible levels.

34. Replacement of damaged batteries. (New batteries supplied by TPCL)

35. O&M contractor is responsible for round the clock operation of the entire system

and all the operation and maintenance shall be performed by suitably trained

and qualified personnel.

36. Hence, the essence of this contract is to achieve ‘Zero Breakdown”. All efforts

are to be made with up to date maintenance in achieving this, by using

predictive and proactive maintenance techniques at times, and, by strictly

adhering to preventive maintenance practices and schedules. Only qualified

with experienced Electrical Engineers and Technicians who have carried out

similar works with good track records shall be considered for engagement.

Page 64: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 64 of 125 Signature of Contractor with seal

37. Contractors shall engage and deploy experienced technical staff, who have

experience in troubleshooting to meet these kinds of requirements and handling

Break down situations. So engaged supervisors / technicians shall have ability

to read continuous power and control circuit drawing of 30 pages or more, able

to do troubleshooting and rectification.

Special Conditions:

i. All works to be carried out in accordance with relevant Indian Standards and

as per Indian Electricity rule as amended. The contractor has to obtain

necessary clearance from Electrical Inspectorate. Panels, Fittings, Equipment,

Systems etc., all the components, accessories, Sub-Assembly, assemblies etc.

which are attachments or parts needed for the purpose. Any other work which

are incidental or part of the above, but not specifically spelt out will also be

included in the scope.

ii. For carrying out above job the contractor has to make his own arrangements

for tools, tackles and measuring equipment, measuring meters, safety and

protective devices for carrying out the work.

iii. TPCL is an Information Technology Park and has critical power requirement.

Please note maintenance should be in such a way that the break down should

not be more than 8 hrs in any case.

iv. For some of the emergency load points power availability has to be monitored

round the clock.

v. Contractor will ensure that the deployed staff should have basic qualification,

License (issued by Chief Electrical Inspectorate to Govt) and are capable of

handling work as stipulated in scope of work. Contractors should deploy

electrical staff having experience in handling such Break-down situations and

have ability to read continuous drawing of 30 pages or more and capable of

troubleshooting and rectification.

vi. As the work involved is quite specialized and continuous monitoring is required,

absenteeism of the contractor’s employees will not be tolerated.

vii. It is presumed that contractor will deploy skilled manpower as required. All the

labour and expertise are included in the scope of work. No extra payment will

be made for carrying out wiring work, routine breakdown and preventive

maintenances.

viii. All the breakdown calls should be attended immediately. In case frequency /

work demands more manpower, Contractor will arrange additional manpower,

at no extra cost, so as not to disturb the research activities.

ix. It is fully contractor’s responsibility to deploy qualified Engineer, Supervisor and

Technicians with relevant Qualifications, License, hands on experience to

handle electrical System and Equipment specified in the scope of work. They

should be well conversant with Indian Standard, Indian Electricity Rule and Acts

as applicable and should have knowledge of electrical and Industrial safety

practices.

Page 65: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 65 of 125 Signature of Contractor with seal

x. Contractor will ensure consistency of work and workforce, correct trouble

shooting, good workmanship, follow all safety procedures and will make all

necessary efforts to maintain healthy environment and reliable services.

xi. It is purely contractor’s responsibility to get his staff acquainted with the site

condition, operation and maintenance procedures, equipment details, safety

devices, Scope of work etc.

III. Deployment of Staff by the Contractor:

Minimum Man Power requirement for Operation and Maintenance of Diesel

Generator Sets and Connected Works

Sl. No.

Designation No. of Persons

Qualification Minimum Experience (No. of years)

1. O&M Incharge

1 Engineering Graduate in Mechanical Engineering

Or

Diploma in Mechanical Engineering

Should have minimum 10 years experience in Operation and Maintenance of Diesel

Generator Sets of capacity not less than 1250 KVA. Should have minimum 12 years experience in Operation and Maintenance of Diesel Generator Sets of capacity not less than 1250 KVA

2. Shift Mechanical Engineer

4 Diploma in Mechanical Engineering

Should have minimum 5 years experience in Operation and Maintenance of Diesel Generator Sets of capacity not less than 1250 KVA

3. Shift Electrical Engineer

4 Diploma in Electrical and Electronics Engineering

Should have minimum 5 years experience in Operation and Maintenance of Diesel Generator Sets of not less than 1250

KVA/1010 KVA with “C” license.

Note:

a) TPCL reserves the right to increase or decrease the manpower requirement as

per LOA. Intent will be issued before 10 days of commencement of next contract

month. If no intent is issued, it is presumed that previous month manpower will

be continued.

b) Categories are defined for the purpose of taking Minimum Wages into

consideration, as notified by the Govt. of Tamil Nadu from time to time that are

to be paid to the workers deployed by the Contractor at TPCL Site(s). However,

for the Staff falling under above Skilled Category and having Managerial/

Specialized role at TPCL Site, the bidders may consider wages as per industry

standards.

c) Working hours for Operation & Maintenance of DG Sets and Connected Works

will be round the clock, seven days a week, 365 days a year including Sundays,

Festivals, National Holidays/Holidays. Adequate number of personnel as per

tender document shall be deployed by the Contractor in suitable shift duties.

Exact working hours will be fixed in consultation with Officer-in-Charge of TPCL.

The Contractor shall abide by all the Statutory Laws while deputing personnel

in TPCL premises. The personnel deployed by the Contractor should be duly

qualified and trained having requisite experience of DG Systems.

d) The above manpower is minimum requirement for routine O&M of DG Sets and

Connected works. In case of Annual Maintenance, major breakdowns,

Page 66: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 66 of 125 Signature of Contractor with seal

emergency situation etc., Bidder has to provide required manpower, tools,

tackles, testing instruments etc. to fulfill the contractual requirement. If the

bidder feels that the above minimum manpower is not adequate for routine

Operation and Maintenance of DG Sets and Connected works, the bidder shall

engage more manpower within quoted price. The manpower deployed in shifts

should always be available as agreed in the contract.

1. Duties and Responsibilities of O&M Incharge:

i) Take care of the Operation and Maintenance of entire DG Sets &

troubleshooting

ii) Daily / Monthly / Weekly PPM Works.

iii) Preparing, maintaining and submission of Log Sheets/Books

iv) Supervising of DG team and maintenance of all DG Sets.

v) Maintain daily checklists

2. The Contractor shall employ following required number of Engineers for carrying

out the jobs specified in the tender and as per following shifts for rendering

satisfactory services:

O&M Incharge 1 General Shift - 9 am to 6 pm

Shift Engineers 8 2 2 2 2

Shift 1st Shift 2nd Shift 3rd Shift Reliever

Timings 6 am – 2 pm 2 pm – 10 pm 10 pm – 6 am

(8 hours working per day in a calender month of 30/31 days including wages of

weekly off. No Shift person shall be allowed to work beyond normal shift time,

(specific approval to be obtained from TPCL incase of exigency).

IV. TESTING, MEASURING EQUIPMENTS, TOOLS & TACKLES

All the tools required for carrying out the work stipulated in this document shall be

provided by the Contractor at site. But, the following minimum is a must at all times:

All the Engineers/Technicians should be given with the following:

i. One set of screwdrivers (one light duty & one heavy duty) with insulated

handles.

ii. One cutting plier, 500V grade with insulated handles.

iii. One live line tester, 500 Volts

Following tools should always be available at site:

i. One set of Box type Spanner with Ratchet

ii. One Heavy duty hydraulic Cable Crimping tool (to crimp size up to 300

Sq.mm)

iii. Two sets of 6-7 to 30 – 32 size 9 metric 0 double end open spanner

Page 67: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 67 of 125 Signature of Contractor with seal

iv. One set of 6-7 to 30 – 32 size (metric) double end ring spanner

v. Two Nos. adjustable wrenches (12 inch)

vi. One No. 0.5 to 16 sq.mm hand crimping tools

vii. Two sets of allen keys

viii. One star screwdriver set

ix. One screwdriver set

x. Two Nos. of hammers (1lb & 2lb)

xi. One soldering gun with lead & flux.

xii. One drilling / hammering machine with drill bits (concrete / metal) (2.5mm to

16 mm each).

xiii. Two Nos of Tommy Bar

xiv. Two pairs of 11000 Volts grade Rubber Gloves (with valid test certificate)

xv. Rubber mats.

xvi. One LT FRP Telescopic Earth / Discharge Rod (400v to 11 Kv)

Following calibrated and well maintained instruments should be available at

site:

1. One Clamp on Ammeter (Tong testers, preferably Kyoritsu make)

AC/DC -400 & 1000 AMPS

AC – 400V & 750V

DC – 400 V & 1000V

Resistance – 400 ohm to 4000 ohm

2. One Multi meters (True RMS preferably Fluke make)

CAT IV 600V – 50 to 500 MV

CAT III 1000V – 5V to 1000 V

DC – 400 mA to 5000 µA

Resistance – 50 ohm to 500 mega ohm

3. One 500V Megger / IR tester (analog) (with valid calibration and test certificate)

4. One earth resistance measurement instrument (0.1 Ohm LC) with kit (with valid

calibration and test certificate) (analog)

5. One phase sequence meter (analog) (with valid calibration and test certificate)

6. One Tachometer – Photo / Contact (Lutron) (with valid calibration and test

certificate)

7. One IR Thermal monitoring equipment (Fluke) (with valid calibration and test

certificate)

8. One vibration measuring instrument (with valid calibration and test certificate).

9. One noise level measuring instrument (with necessary calibration and test

certificate).

All the above tools and instruments shall be suitably kept at site, with

contractors own security arrangement.

V. TECHNICAL SPECIFICATION OF 2000 KVA DG SETS

Page 68: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 68 of 125 Signature of Contractor with seal

Equipment Details Unit DG

Engine

Make MTU

Model 16 V 4000 G23

Mfg. Yr 2008

Weight Kg 7710

Power KW 1798

Speed rpm 1500

Sl. No 527 106 495, 291, 292, 293, 294.

Alternator

Make Leroy Somer

Type 86 L

Sl. No 186-060, 62, 65, 61, 64.

Continuous KVA 2850

Duty Rating KW 2280

D.E. Bearing NU 1036

N.D.E. Bearing NU 1036 ÷ 16036

AVR R 449

Voltage V 415

Current A 3965

Cos Ø 0.8

Phase 3

Thermal Class H

Excitation V/A V/A 45/4.25

Speed rpm 1500

Frequency Hz 50

Enclosure IP 23

Weight Kg 6250

VI. SYSTEM DESCRIPTION

The total capacity of the DG plant is 10 MVA. The plant is to provide 100% backup to

entire operation of the Building. The plant is consists of the following:

a) 2000 KVA DG Sets

Diesel Generator (D.G.) sets of 2000 KVA / 1798 kW of 0.8 PF, speed of 1500

RPM, four stroke engine, operating on High Speed Diesel (HSD), coupled to a

415V air-cooled alternator and radiator with motor, fan and fan guard.

Engine : MTU, Model - 16V 4000 G23

Alternator : Leroy Somer

Quantity : 5 Nos.

b) HSD storage with Fuel pumping system

Bulk HSD storage underground tanks of capacity 2 Nos of 30 KL and connected

piping works and flame proof pumps with manual system

Page 69: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 69 of 125 Signature of Contractor with seal

b) Acoustic Treatment for entire DG room

c) Ventilation System

11 Nos. of Fresh Air Fans and 6 Nos of Exhaust Fans are provided for ventilation

of the DG room

d) Flue Gas De-sulphurisation System.

Flue Gas De-sulpharisation (FGD) consisting of scrubber and ETP. The treated

and scrubbed gas is let out through the stack. The by-product of the system

is a semi dry solid waste. There are two separate systems one catering to 3

Nos. 2000 KVA sets, and the other one catering to 2 Nos. 2000 KVA sets.

e) MCC’s, Sandwich Bus ducts, Cabling and Earthing

f) Stainless steel stack of 20 meters height, Lighting Arrestor, Aviation

Light – Two (2) Nos.

g) AMF panels

All the 5 Nos of DG sets are connected to AMF panels. The 2000 KVA DG sets

are connected to of One No. Microprocessor based Auto Mains Failure control

panel, which has facility to start 5 Nos. of 2000 KVA DG sets automatically in

the event of EB supply failure. The above system also includes control of the

DG incomer breaker in DG Control panel.

VII. QUALITY CONTROL AND ASSURANCE

1.0 CONTRACTOR'S’S RESPONSIBILITIES

1.1 Quality Control

Contractor shall be responsible for producing a Quality Control Procedure for

implementation. The procedure shall contain inspection report forms and test

report forms to record the quality of the materials and workmanship, in

accordance with the requirements of the Contract. The Procedures shall only

be implemented with the approval of Owner.

1.2 Quality Assurance

Contractor shall be responsible for producing and implementing a Quality

Assurance Plan to ensure that inspection and testing of the WORKS are carried

out in accordance with the relevant provisions of the Contract.

1.3 Testing

Testing shall be in accordance with the requirements of the Contract. A full

formal record shall be kept by Contractor. Contractor shall inform Owner/

Representative at least twenty four (24) hours in advance of all tests requiring

witnessing so that Owner can be present for the test.

Page 70: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 70 of 125 Signature of Contractor with seal

2.0 INSPECTION AND TESTING BY OWNER

2.1 General

Owner shall have the right to inspect at all times any tools, instruments

materials, staging, or equipment used or to be used in the performance of the

WORKS. Contractor shall make all parts of the WORK accessible for these

inspections.

2.2 Rejected Work and Equipment

Owner shall have the right to condemn any and all tools, instruments,

materials, staging, equipment, or work which does not conform to

Specifications.

Any defective work not conforming to Specification shall be rectified by

Contractor at no additional cost to Owner.

Page 71: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 71 of 125 Signature of Contractor with seal

8. QUARTERLY PERFORMANCE EVALUATION

SL.

NO Evaluation Criteria Marks Score Remarks

1 Whether the contractor has provided the man

power and materials as per contract terms and

conditions, fulfilling EPF, ESI remittance on

timely, medical insurance covers for eligible staff

and other statutory provisions. (Payslip details

and bank account statement of individual

employees of the contractor will have to be

submitted for verification of TPCL)

5

2 Whether the contractor has maintained the

operating procedures, PPM schedules, failure /

missing / damage report, material consumption

report etc.

5

3 Whether the contractor has maintained log books

for daily technical activities, equipment running

status, deployment sheet, check list and

submitted all reports to TPCL periodically.

5

4 Whether the contractor has provided the

adequate trainings, meetings and Technical

updates to his employees.

5

5 Whether the contractor has provided the required

basic Tools and Accessories to his technical

employees, Personal Protective equipment like

shoes, uniforms, other required PPE’s, computers

and other required office equipment.

5

Total 25

Note: -

Performance Evaluation will be done by TPCL for every quarter.

Based on the performance evaluation, annual renewal and yearly escalations

will be decided.

If the annual performance evaluation is 50 and below, the contract may be

terminated.

Page 72: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 72 of 125 Signature of Contractor with seal

9. TENDER ACCEPTANCE LETTER To

The Managing Director

M/s. TIDEL Park Coimbatore Ltd.

ELCOSEZ

Aerodrome Post

Coimbatore - 641 014

Dear Sir,

Sub: Tender for Integrated Operation & Non Comprehensive

Maintenance of ACMV, BAS, DG Sets & Connected Works – Reg.

Ref: e-Tender issued in Website: www.tntenders.gov.in on

14.12.2020 ~~~~~~

Tender No. A-17012/003/2020-CR

A copy of the tender notice is enclosed. I / We M/s

____________________________

have submitted a tender for Integrated Operation & Non Comprehensive Maintenance

of ACMV, BAS, DG Sets & Connected Works.

1. Having examined the scope of work, schedule of quantities etc., relating to the

works specified in the memorandum hereinafter set out and having visited and

examined the site of the job specified in the said memorandum and having acquired

the requisite information relating thereto as affecting the tender, I/we hereby offer

to undertake the job specified in the said memorandum for the duration specified

in the said memorandum at the rates mentioned in the attached schedule of

quantities and in accordance, in all respects with the specifications, scope of work

and instructions in writing referred to in conditions of tender, the Articles of

Agreement, Special Conditions, O&M activities of Various works, Schedule of

Quantities and Conditions of Contract and with such materials as are provided for,

by, and in all other respects in accordance with such conditions so far as they may

be applicable

2. Scope of work and instructions in writing referred to in conditions of tender, the

Articles of Agreement, Special Conditions, Scope of Work, O&M activities of various

works, Schedule of Quantities and Conditions of Contract and with such materials

as are provided for, by, and in all other respects in accordance with such conditions

so far as they may be applicable.

3. We agree to abide by this bid for a period of 90 days from the date fixed for bid

opening and it shall remain, binding upon us and may be accepted at any time

before expiration of that period.

MEMORANDUM

1) a) Outline description of

works:

Integrated Operation & Non

Comprehensive Maintenance of ACMV,

BAS, DG Sets & Connected Works for One

year, renewable every year upto 3 years subject to satisfactory performance of the contractor as decided by TPCL.

b) Bidder / Contractor will be solely responsible for effective operation

and maintenance.

c) Earnest money Rs.2,00,000/- (Rupees Two Lakhs only)

Page 73: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 73 of 125 Signature of Contractor with seal

2) We hereby unconditionally accept the tender conditions of above mentioned

tender document(s)/corrigendum(s) in its totality/entirely.

3) Should this tender be accepted, I/we hereby agree to abide by and fulfill the

terms and provisions of the said Conditions of Contract annexed hereto so far

as they may be applicable or in default thereof to forfeit and pay to TIDEL Park

Coimbatore Ltd., Coimbatore the amount mentioned in the said contract.

4) I/We have deposited a sum of Rs.2,00,000/- (Rupees Two Lakhs only) as

earnest money with TIDEL Park Coimbatore Ltd., which amount shall not bear

any interest. Should I/we fail to execute the contract when called upon to do

so, immediately after the issue of Letter of award by TIDEL Park Coimbatore

Ltd., I/we do hereby agree that this sum shall be forfeited by me/us to TIDEL

Park Coimbatore Ltd., Coimbatore.

5) All schedules necessary in connection with the job are enclosed as required.

6) Our bankers are:

i)

ii)

The names of partners / Director of our firm / Company are:

i)

ii)

Name of the partner / Director of the

firm authorised to sign:

or

Name of person having Power of:

Attorney to sign the contract.

(Certified true copy of the Power of

Attorney should be attached) Yours faithfully,

Signature of Tenderer

along with Seal of the Tenderer

WITNESSES

i) Signature:

Occupation:

Address:

ii) Signature:

Occupation:

Address:

Page 74: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 74 of 125 Signature of Contractor with seal

10. ARTICLES OF AGREEMENT (FORMAT)

(The successful bidder has to execute a non judicial stamp paper for a value of

not less than Rs.100/-)

ARTICLES OF AGREEMENT made on this .……. day of .........…… 2020 between TIDEL

PARK COIMBATORE LTD. having its registered office at First floor, No-4, Rajiv Gandhi

Salai, Taramani, Chennai – 600 113 (Hereinafter called "TPCL”) of the one part and

…………………………………………………………………………………………………………………………………………

…………………................................of the other part whose registered office is situated

at ……………………………….……….(Hereinafter called "The Contractor")

WHEREAS TPCL is desirous of availing the services of M/s._________ for Integrated

Operation & Non Comprehensive Maintenance of ACMV, BAS, DG Sets & Connected

Works (hereinafter called "the Work") at its IT Park in ELCOSEZ, Coimbatore and has

caused documents and details of Skilled manpower to be deployed along with

description of work to be done.

The Contractor has informed that the Contractor is sufficiently equipped to carry out

and possess extensive experience in the field of Integrated Operation & Non

Comprehensive Maintenance of ACMV, BAS, DG Sets & Connected Works in accordance

with the terms and conditions prescribed in this regard.

AND WHEREAS the following documents shall be deemed to form and the document

to form and be read and construed as part of the agreement viz:

(i) Letter of Acceptance of contract

(ii) General and standard terms and conditions

(iii) Notice Inviting Tender

(iv) Bill of Quantities

(v) Detailed work specification and supplementary work

(vi) Addendum, if any

(vii) Any other document forming part of the contract

AND WHEREAS the Contractor has furnished Bank Guarantee No.____ dated_____

issued by _____ Bank _______ Branch for a sum of Rs…………….. (Rupees

…………………………………………) as Performance Bond, valid for entire contract period with

additional irrevocable period of six months from the date of commencement for due

performance of this agreement, that is for 18 months ending on______.

AND WHEREAS the Contractor has supplied TPCL with a fully priced offer for aforesaid

services and has been selected and is willing to render the services as per requirement

of tender and as desired by TPCL.

Page 75: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 75 of 125 Signature of Contractor with seal

NOW IT IS HEREBY AGREED AS FOLLOWS:

1. For the consideration hereinafter mentioned the Contractor will upon and

subject to the Conditions annexed carry out and complete the job shown upon

the Contract Document and described by or referred to in the Contract Bills and

in the said Conditions.

2. TPCL will pay the Contractor, the said contract amount of Rs. ….................

(Rupees.....................................…………………….. only) (hereinafter referred to

as "the Contract Sum") or such other sum as shall become payable hereunder

at the times and in the manner specified in the said Conditions.

3. The agreement and documents mentioned herein shall form the basis of this

Contract.

4. This Contract is to carry out the work in respect of provision of Integrated

Operation & Non Comprehensive Maintenance of ACMV, BAS, DG Sets &

Connected Works to TIDEL PARK COIMBATORE LTD. and its services & Facilities

to be paid for according to actual services performed and works done at the

lump sum rates contained in the Vol.II or as provided in the said Conditions.

5. TPCL shall afford every reasonable facility for carrying out of all works relating

to the provision of Integrated Operation & Non Comprehensive Maintenance of

ACMV, BAS, DG Sets & Connected Works in the manner laid down in the said

Conditions till the completion of the contract.

6. TPCL reserves to itself the right of altering the Documents and nature of the

work by adding to or omitting any items of work or having portions of the same

carried out without prejudice to this Contract. There shall be changes ordered

by TPCL on the scope and the Contractor shall not be entitled to any

compensation or claim due to such change (s) / Order (s) by TPCL. The

Contractor will only be paid for the actual services performed and works done

payable at the accepted unit rates.

7. Timely performance of the contract obligation shall be considered as the

essence of the Contract and the Contractor hereby agrees to commence the

work within 7 days from LoA as provided for in the said Conditions and to

perform the job during and within the stipulated contract period.

8. All payments by TPCL under this contract will be made only at Coimbatore in

Indian Rupees and shall be within 14 days from submission of interim bills

(monthly) including period of certification subject to bills being in complete

shape and format to be mutually agreed.

The final payment will be made within a period 3 months after completion of

contract and due verification of final bill with all necessary supporting

documentation such as handing over of documents, Maintenance during the

contract period, material handed over by TPCL etc.

Page 76: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 76 of 125 Signature of Contractor with seal

9. All disputes, differences or claims of any kind whatsoever arising out of or

relating to, this agreement, or its validity, construction, breach or performance

between the parties to the Agreement shall be finally settled through

Arbitration. However the parties shall first endeavour to settle the same

amicably in a spirit of co-operation. The arbitration shall be governed by the

Arbitration & Conciliation Act 1996 of India as amended up to date. The

arbitrator shall be appointed by the TPCL and Company shall ensure that the

Arbitrator shall satisfy the norms of independence as provided in Arbitration &

Conciliation Act 1996 and any amendment thereon. The arbitration hearing and

all proceedings in connection therewith shall take place in Coimbatore and the

language of the arbitration shall be English.

10. Except as above, all matters arising under this agreement shall be subject to

the exclusive jurisdiction of the Courts at Chennai only.

11. That the several parts of this Contract have been read by the Contractor and

fully understood by the Contractor.

12. All correspondences and notices shall be sent by both the parties to the

following addresses only, unless any change has been specifically intimated by

any of the party through ‘Registered Post with Acknowledgement Due’ (RPAD).

To TPCL To the Contractor

The Managing Director,

TIDEL Park Coimbatore Limited,

ELCOSEZ, Civil Aerodrome Post,

If the Contractor is a partnership or an individual:

IN WITNESS WHEREOF TPCL and the Contractor have set their respective hands to

these presents and hereof the day and year first herein above written.

If the Contractor is a Company:

IN WITNESS WHEREOF TPCL has set its hand to these presents through its duly

authorized official and the Contractor has caused its common seal to be affixed

hereunto and has caused these presents and hereof to be executed on its behalf, the

day and year first herein above written.

Signature Clause:

For and on behalf of the For and on behalf of the

TIDEL PARK COIMBATORE LTD. CONTRACTOR

Name : Name :

Designation : Designation :

Address : TIDEL PARK COIMBATORE LTD. Address :

Page 77: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 77 of 125 Signature of Contractor with seal

ELCOSEZ, Aerodrome Post

Coimbatore – 641 014

WITNESSES:

1. Signature : 1. Signature :

Name : Name :

Occupation : Occupation :

Address : Address :

2. Signature : 2. Signature :

Name : Name :

Occupation : Occupation :

Address : Address :

Page 78: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 78 of 125 Signature of Contractor with seal

11. FORM OF PERFORMANCE GUARANTEE

1. In consideration of TIDEL PARK Coimbatore Ltd. (hereinafter called “TPCL,”) having

agreed to allow M/s. ……………………….. [hereinafter called “Integrated Operation &

Non Comprehensive Maintenance of ACMV, BAS, DG Sets & Connected Works”

from the demand under the terms and conditions of an Agreement No. .. . . . . . . . . .

for Integrated Operation & Non Comprehensive Maintenance of ACMV, BAS, DG Sets

& Connected Works at Information Technology Park at Vilankurichi Special Economic

zone, Coimbatore, (hereinafter called “the said Agreement” for furnishing Performance

Bond for the due fulfillment by the said Contractor(s) of the terms and conditions in

the said Agreement, by production of a BANK GUARANTEE for Rs.. . . . . . . . (Rupees..

. . . . . . . . . . only). We the . . . . . . . . . . . . . (Name of the Bank) having our Head

Office at . . . . . . . . . . . and having branch at . . . . . . . . . . referred to as “the Bank”

at the request of M/s. ….. . . . . . . . do hereby undertake to pay to TPCL, an amount

not exceeding Rs.. . . . . . . on demand by TPCL.

2. We . . . . . . . . . . . . . . . . . . . . (Name of the Bank) . . . . . . . . branch do hereby

undertake to pay the amounts due and payable under this guarantee without any

demur, merely on a demand from TPCL, stating that the amount claimed is required

to meet the recoveries due or likely to be due from the said Contractor(s). Any such

demand made on the Bank shall be conclusive as regards the amount due and payable

by the Bank under this guarantee. However, our liability under this guarantee shall be

restricted to an amount not exceeding Rs.... . . . . . . (Rupees.. . . . . . . . only).

3. We undertake to pay to TPCL, the amount due under this Guarantee so demanded

not withstanding any dispute to disputes raised by the said Contractor(s) in any suit

or proceeding pending before any Court or Tribunal relating thereto, our liability under

this present being absolute and unequivocal. The payment so made by us under this

bond shall be a valid discharge of our liability for payment thereunder.

4. We . . . . . . . . . . . . (Name of the Bank) . . . . . . . . .. branch further agree that the

guarantee herein contained shall remain in full force and effect during the period that

would be taken for the performance of the said agreement and that it shall continue

to be enforceable till the dues of TPCL, under or by virtue of the said agreement have

been fully paid and its claims satisfied or discharged or till the Engineer in charge on

behalf of TPCL, certifies that the terms and conditions of the said Agreement have

been fully and properly carried out by the said Contractor(s) accordingly discharges

this guarantee.

5. We . . . . . . . . . . (Name of the Bank) . . . . . . . . branch further agree with TPCL,

that TPCL, shall have the fullest liberty without our consent and without affecting in

any manner our obligations hereunder to vary any of the terms and conditions of the

said Agreement or to extend time of performance by the said Contractor(s) from time

to time or to postpone for any time or from time to time any of the powers exercisable

by TPCL, against the said Contractor(s) and to forbear or enforce any of terms and

conditions relating to the said agreement and we shall not be relieved from our liability

by reason of any such variation or extension being granted to the said Contractor(s)

or for any forbearance act or omission on the part of TPCL, or any indulgence by TPCL,

to the said Contractor(s) or by any such matter or thing whatsoever which under the

law relating to sureties would but for this provision have effect of so relieving us.

Page 79: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 79 of 125 Signature of Contractor with seal

6. This guarantee will not be discharged due to the change in the constitution of the

Bank or the said Contractor(s).

7. We hereby waive the necessity of your demanding the said Contractor before

presenting us with the demand.

8. We . . . . . . . . . . . . (Name of the Bank) . . . . . . branch lastly undertake not to

revoke this guarantee except with the previous consent of TPCL, in writing.

9. This guarantee shall be valid upto the full contract period with additional irrevocable

period of six months from the date of completion of job and due fulfillment of the

contract i.e for a total period of One and half years. Notwithstanding anything

contained herein before our liability against this guarantee is restricted to Rs.. . . . . .

. (Rupees.….. …. . only) and it will remain in force till . . . . . ………..) unless a claim or

demand in writing is made against us under this guarantee before the expiry of six

months from the aforesaid date that is before . . . . . . . of . . . . ……….. …. ( . .

………………..) all your rights under the said guarantee shall be forfeited and we shall be

relieved and discharged from all liability hereunder.

Notwithstanding anything contained herein:

Our liability under this Bank Guarantee shall not exceed Rs.___________/= (Rupees

__________________________________ only).

This Bank Guarantee shall be valid upto ______. unless this guarantees extended for

further period on demand from TPCL without referring to Contractor.

We are liable to pay the guaranteed amount or any part thereof under this Bank

Guarantee only if you serve upon us a written claim or demand on or before _______

or within the period extended after------------based on the demand from TPCL.

IN WITNESS WHEREOF I/We of the Bank signed and sealed this guarantee on the day

of _______________ , ______ being herewith duly authorised by the Bank.

Witness : For and on behalf of the

Bank

Name :

Address :

Page 80: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 80 of 125 Signature of Contractor with seal

12. SPECIAL CONDITIONS

11.0 Working Hours

11.1 The premises is subject to continuous occupation of all the 24 hours of a day.

The manpower deployment at various locations shall be decided in consultation

with TPCL. Shift allotment, general shift allocation of the manpower will be

mutually decided in consultation with TPCL and approved by TPCL. The working

hours of staff shall be 9 hours (8 hours Plus 1 hour for Lunch / Tea Break)

within the quoted rate.

12.0 Adequacy of Contractor’s Staff

12.1 It is understood that the service activities are to be performed with utmost

diligence and expediency so as to maintain the highest standards of O&M

Services. To achieve this, Contractor shall maintain adequate level of staff of

good technical competence at site at all times.

12.2 If, at any time, during the currency of the Contract, Contractor’s staffing, in the

opinion of Owner, is inadequate to meet the requirements of Contract services,

Owner may so notify Contractor, who shall thereupon take immediate steps to

increase its staff at site. Contractor shall effect such increases within a period

of maximum Seven Days following the procedure outlined elsewhere in the

contract agreement. If within the specified period Contractor does not or fails

to increase the staff as required, Owner may itself or through other parties hire

additional staff to supplement that of Contractor at the cost fixed by the owner

to be deducted from the payment of Contractor.

12.3 Failure of Contractor to comply with the instructions of Owner may be grounds

for determination by Owner that Contractor is not proceeding with the

performance of services with due diligence to ensure fulfillment of contractual

requirements. 13.0 Conditions of Performance

13.1 Contractor confirms and assures that:

13.1.1 Contractor has the requisite skilled and qualified personnel to perform

the services.

13.1.2 Contractor has inspected the premises and is familiar with the

conditions related to performance of the services.

13.1.3. Contractor shall at all times ensure that the supply of know-how,

Manpower, Materials, Equipment, Tools and Vehicles shall be adequate to

satisfactorily undertake the scope of services without delay.

13.1.4. Contractor shall at all times ensure that the services are being carried

out in the most expeditious efficient manner consistent with the best interests

of Owner, and in good and professional manner and in accordance with sound

industry practice.

13.1.5. Contractor shall perform and provide the services in accordance with

provisions of this Contract and shall exercise all reasonable skill, care diligence

and judgment in performance of the services.

Page 81: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 81 of 125 Signature of Contractor with seal

14.2 Owner has discussed and agreed with Contractor as per the Contract, the

general basis for execution of services, Contractor shall provide procedures for

Owner approval in accordance with Annexure ‘A’ which shall be based upon

good working practice in order to maintain the services/equipment at a high

level of efficiency and to provide safe working conditions. If any question arises

between Contractor and Owner regarding particular work procedure followed

or proposed to be followed by Contractor, Contractor must justify to Owner the

soundness of such procedure and shall obtain Owner’s written approval before

the same may be affected. Provision or otherwise of such approval shall not

relieve Contractor of any of its obligations under this Contract.

Owner shall have the right to check and make remarks on any or all procedures

proposed to be adopted by Contractor for the performance of services.

Contractor shall submit such work procedure for Owner’s review and approval.

14.3 Contractor shall notify the Owner as soon as Contractor knows of any difficulty

in performing the services. If, at any time during the performance of the

services, Contractor’s actual progress is inadequate to meet the requirements

of the Contract, Owner may so notify Contractor who shall thereupon take such

steps as may be necessary to improve its performance. If Contractor does not

improve its performance to meet the approved and accepted schedule, Owner

may require an increase in Over time working hours, an increase in the number

of Manpower and Equipment, Plant, tools etc. all without any additional

payment by Owner to Contractor. Neither such notice by Owner nor Owner’s

failure to issue such notice shall relieve Contractor of its obligations to achieve

the performance required by Contract.

14.4 If Contractor fails to perform any of the services then Owner has the

undisputable right to claim damages and hire a third party to perform such

services, and the incurred amount i.e. the additional amount payable to the

third party by virtue of assigning services until expiry date of Contract shall be

recovered from any monies due to Contractor under the Contract.

14.5 In the event that Contractor fails to progress the services in accordance with

accepted Schedule of work and thereby incurs Owner in additional cost and /

or expense through the re-Organization and / or re-scheduling of dependant

third party claims in consequence thereof, then to the extent that Contractor is

at fault, Contractor shall reimburse all such direct and verifiable costs and

expenses to Owner and Owner may deduct such sums from the value of any

invoice submitted by Contractor or from any sums due or owing which may

become due or owing to Contractor.

15.0 Variations in Scope of Work

15.1 Additional and modification works shall be subject to the provisions made under

this contract Agreement.

15.2 Additional and modification works related to scope of services.

15.2.1 Owner may frequently have some additional works, modifications etc at site

related to the Scope of Services to be carried out. Owner has the right to make

use of Manpower, materials, Equipment, Tools & Vehicles made available at

site by the Contractor, for carrying out the additional services. Contractor shall

carry out such additional works without any additional charges to Owner.

However, the cost of materials required for such works shall be paid as per the

provision under this contract.

Page 82: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 82 of 125 Signature of Contractor with seal

15.2.2 Owner has the right to waive the charges of damages due to routine programme

performance shortfalls observed of Contractor by Owner during that period for

using its Manpower, materials, Equipment, Tools and Vehicles for carrying out

the additional works.

16. Labour

16.1 Contractor shall be responsible for the engagement, employment, transport,

working and living conditions of personnel and in respect of all matters

connected therewith. Contractor shall at all times during the continuance of this

Agreement conform in all respects to and carry out all obligations imposed on it

by the provisions and requirements of the Employees Provident Fund

(Miscellaneous Provision) Act, 1952, Payment of Gratuity Act, 1952,

Employment State Insurance Act, 1948, Maternity Benefit Act, 1961, Minimum

Wages Act, 1923, Equal Remuneration Act, 1976, Payment of Wages Act, 1936,

Payment of Bonus Act, 1965, Contract Labour (Regulation and Abolition) Act,

1971 and any applicable law in the country where any of the services are

performed or regulations issued including without limitation all laws, regulations

and requirements of Government of India/State Government.

All the proposed staff / personnel shall possess high standard of Integrity, have

no affiliation with any political parties or trade unions. This has to be followed

during the entire contract period.

16.2 Contractor shall in its dealing with the personnel for the time being employed

on or in connection with the Agreement have due regard to all recognized

festivals. Contractor shall also observe all relevant local customs and such other

conditions and instructions as may be issued to Contractor from time to time by

Owner

17. Contractor shall administer any National Labour on employment on terms and

conditions not less favorable than those established for equivalent sites or

locations within India.

17.1. Contractor shall at all times take all reasonable precautions to prevent any

unlawful, riotous or disorderly conduct by or amongst its employees and for the

preservation of peace and protection of persons and property in the

neighborhood of the site against the same.

17.2. Upon the outbreak of any strike or labour dispute involving any of Contractor’s

personnel engaged on the services, Contractor shall forthwith give details

thereof to Owner. If any dispute arises between the contract labour/labour/

employees and Contractor agency, the owner will not be responsible in any

manner. The Contractor” shall not stop or cause stoppage of work on account

of strike or other agitation during the period of contract. The Contractor agrees

that it shall be liable for all consequences for the delay caused or loss / damages

suffered by the Owner due to the stoppage / strike by the Contractor. TPCL

shall recover the cost incurred due to this from the Contractor’s running account

bills.

17.3 Contractor shall within twenty four (24) hours of any occurrence of any accident

at or about the site or in connection with the execution of the services or any

injury, lose or damage to any personnel or to property of Contractor, Owner or

of a third party, report such occurrence to the competent authority whenever

such a report is required by law.

17.4 Contractor shall be responsible for the observance of all provisions of this Article

by any Sub-contractor employed by it in the execution of this Agreement.

Page 83: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 83 of 125 Signature of Contractor with seal

17.5 Owner shall be at liberty to object to and require Contractor to remove forthwith

from the site any person employed by Contractor in or about execution or

performance of services who in the opinion of Owner has committed a

misconduct or whose employment is otherwise considered to be undesirable.

Contractor without the written permission of Owner shall not again employ such

person upon services at any circumstances.

18. Contractor’s Working Hours

18.1 Normal daily working hours for Contractor’s personnel, except those working on

rotational shift basis will be prepared by Contractor and approved by Owner.

Sundays will be observed as weekly rest days except in case of persons who will

be working on shift basis. In this contract, the shift pattern shall comply with

local regulations governing the engagement of Labour, such as Contract Labour

Law, Shop and Establishment Act etc.

18.2 Persons working on shift basis will follow the weekly shift schedule to be prepared

by Contractor and approved by Owner. Contractor shall arrange to provide at

his cost relievers for its Shift Personnel.

18.3 Contractor will have to work after normal working hours (as per clause 19.1

above) and on Sundays / Holidays to fulfill its obligation of services. Overtime if

any for such work shall be to Contractor’s account deemed to have been included

in the rates quoted.

18.4 Contractor is responsible and bound to provide coverage for 24 hours a day

throughout the Agreement period to attend to any work of the services with full

mobilisation as required at site and as and when directed by Owner’s

Representative(s) without any extra cost to Owner.

During the festive days, Contractor at no extra cost to Owner shall make such

adjustment as necessary to the working arrangement at each location of the

premises to meet such exigencies as may be directed by Owner.

18.5 Each Shift Working Hours will be 9 hours Pattern (8 hours plus 1 hour Lunch

Break). Round the clock coverage should be there throughout the year including

Sundays and Government Holidays.

18.6 TPCL will not pay extra who are working on Government Holidays, National

Holidays and Sundays. If any such work is carried out by the Contractor, it is

deemed to have been included in the rates quoted by the Contractor.

19. Declaration:

The Contractor shall provide a Declaration that he will make all Statutory

Payments like PF & ESI to his employees and remitted all applicable taxes to the

Government.

Age – Limit: Age – Limit for Officers / Staff employed by the Contractor is 20

to 55 years

19.1 Conflict of Interest:

Contractor shall conduct its operations in a lawful manner consistent with good

international practices and standards for such type of services.

Page 84: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 84 of 125 Signature of Contractor with seal

19.2 Neither Contractor nor any of its subsidiaries or affiliates shall in connection

with the services enter into a contract, give an undertaking, bid, enter into a

Joint Venture Partnership, have any relations with a Third Party or any other

arrangement to perform any services, to supply goods or equipment which may

be to Owner’s detriment.

Page 85: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 85 of 125 Signature of Contractor with seal

Annexure – ‘A’

CO-ORDINATION PROCEDURE This procedure outlines various responsibilities of Representative(s) nominated by Owner and contractor for the Contract. Contractor will carry out proper execution of the services under the supervision of Owner’s Representative(s).

1.0 Communication 1.1 English language will be used for all purposes.

i) All written communication shall be done at site level directly between

Owner and Contractor. All efforts must be made to keep correspondence to a minimum. If, for expediency, telephonic conversation is used, this must be confirmed in writing within two (2) working days, by both parties.

ii) Notwithstanding any other provision under this Contract Agreement, hand delivery will be an approved means of exchange of letters.

iii) Contractor shall prepare and issue Minutes of all Meetings and shall be

responsible for obtaining approval of these minutes from Owner prior to release within two (2) working days of the meeting.

2.0 Site Instructions 2.1 Instructions shall be confirmed, in writing, using a numbered site instruction,

and signed by Owner. Contractor is required to sign one copy of each instruction as confirmation of its receipt.

2.2 Should Contractor consider that he has received any instruction or order which

has involved it in cost outside the Scope of Services covered by the Agreement, contractor must within forty eight (48) hours communicate in writing full details of its justification to Owner complete with break up for cost details, for consideration.

3.0 Reports and Services Records

3.1 Contractor is required to prepare and submit to Owner various routine and

special reports relating to the performance of the services.

3.2 i) Contractor is required to submit daily reports of all activities.

ii) A set of “Formats” currently in use for the Records of Performance of the

Scope of Services.

iii) Owner has the right to modify the present “Formats” in use or introduce

new “Formats” as and when required to meet the services requirements. Contractor is obliged to prepare and maintain such records.

Page 86: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 86 of 125 Signature of Contractor with seal

4.0 Permits / Permissions

Security Passes

The Owner may issue required passes to contractor staff assigned to the project

as situation warrant at any point of time. Contractor shall contact the Owner

as soon as such exigencies arise for the details of the procedure. Contractor

shall familiarize himself with all requirements of the Owner on contract award

so that time delay on account of passes shall be minimized. Owner shall arrange

for passes as required by the contract as soon as the request from the

contractor is received.

Any delay or expense incurred, resulting from securing passes from the Owner

shall not entitle contractor to any claim for extension of mobilization time or

completion dates or additional payments.

Page 87: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 87 of 125 Signature of Contractor with seal

13. FORMATS

Page 88: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 88 of 125 Signature of Contractor with seal

13A- GENERAL

i) Format – A: Structure of Organization

ii) Format – B: Personnel

Page 89: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 89 of 125 Signature of Contractor with seal

FORMAT – A

STRUCTURE OF ORGANISATION OF THE BIDDER

1. Name of Applicant firm

2.

a

Registered Office Address

Postal Address

Telephone Number

E-mail

Fax Number

b. Office address through which this work will be

handled and name of officer in-charge and the

telephone/ fax numbers/ e-mail id.

c. Year of establishment and location of

Establishment

3. Number of years experience in Integrated

Operations & Non-Comprehensive Maintenance of

ACMV,BAS,DG by Contractor.

4. The applicant firm is

a) Proprietary Firm

b) a Firm in Partnership

c) a Limited Company or Corporation

d) a Group of companies

e) a firm in joint venture/ tie up with a foreign

company

5 In case of company, please enclose Memorandum

and Articles of Association along with Certificate

of Incorporation and certificate of

commencement of business

6 In case of Firm, registered under the partnership

act 1932 please enclose details of partners along

with certificate of registrations, details of their

business and partnership deed etc., duly attested

by notary

7. Attach the Organization Chart showing the

structure of the organization including the names

of the Directors and position of Officers.

8 Bank of the company (please enclose self-

attested photocopy)

Bank and Branch Name

Account No

Account Type

MICR Code

IFSC code

Page 90: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 90 of 125 Signature of Contractor with seal

9 PAN of the Bidder (Please enclose self attested

photocopy of PAN)

10 GST Number of the Bidder (Please enclose self

attested photocopy of GST Registration

Certificate issued by relevant authorities)

11 PF Registration of the Bidder (Please enclosed

self attested photocopy)

12 ESI Registration of the bidder (Please enclose self

attested photocopy)

13 IT Return for the last 3 Financial years (Please

enclose self attested photocopy)

14 Has the Bidder’s contract with any organization

ever been terminated due to poor performance (if

so, give name of work and reasons for not

completing work)

15 Has the Bidder’s Security Deposit for any contract

has ever been forfeited (if so, give name of work

and reasons for not completing work)

16 Has the Bidder suffered insolvency/bankruptcy in

the last five years? (Yes/ No)

17 Has the Bidder been blacklisted by any

organization? (if so, give name of work and

reasons for not completing work)

18 Is the Bidder’s net worth negative? (Yes/ No)

19 Were you ever required to suspend work for a

period of more than 3 months? If yes, give the

name of work and reasons thereof.

20 Have you ever left the work awarded to you

incomplete? (if so, give name of work and

reasons for not completing work)

21 In how many of your works were penalties

imposed for delays and out of how many works

handled in that year (please give details)

22 In how many of your works cases of litigation

have arisen out of how many works handled in

that year?

a) Income tax clearance certificate for

Organisation / Firm.

b) State Permanent Account number.

a) Adequate and satisfactory evidence to take up the

ACMV, BAS, DG work with reference to the

requirements as mentioned in the tender notice.

Enclose Annual report / Balance sheet and P & L

statements for the past five years.

b) Banker’s overdrafts and credit facilities available.

c) Particulars of registration etc. if registered with

any Government, Semi-Government, Municipal

or other organization, /ISO 9001 Certification

(Give details including classification license etc.)

d) Sales tax Registration no:

TNGST

Page 91: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 91 of 125 Signature of Contractor with seal

CST

e) GST of any other state

f) Others (Specify)

23 Please give two references of firms (Engineers,

Architects or top Officials of client Organisations)

for whom you may have carried out the above

works from whom TIDEL PARK COIMBATORE

LTD., can verify directly about the ability,

competence or capability of your organisation.

Preferably attach certificates duly signed by the

top officials of the organizations in their

letterhead.

24. Give details of your plans for Sub-Contractors

with full details, if any, in terms of percentage of

works.

25 Do you have any tie-up with foreign company? If

yes, give nature of tie-up, since when and full details

of company with name and address. Necessary

proofs have to be attached.

26 Copy of license under Contract Labour Act 1970

(Form No: XXVI) of the clients satisfying the Pre

Qualification Criteria (Please enclose self attested

photocopy)

Place:

Date: Signature of Applicant with seal

Note:

1. The Details as required to be submitted with supporting documents for each criteria

mentioned at each row.

2. Bids with alterations/ Corrections shall be attested by the Bidder.

I/We

________________________________________________________________ do

hereby declare that the entries made are true to the best of my/our knowledge and

also that we shall be bound by the acts of my/our duly constituted Attorney.

I/We

________________________________________________________________ do

hereby declare that I/We have not been penalised for poor quality of work during the

last five years.

I/We, further understand that in case of any information submitted by me/us being

found to be incorrect either before or even after the award of license. TIDEL will have

the right to summarily reject the bid, cancel the License or revoke the same at any

time without assigning any reason whatsoever.

I/We

__________________________________________________________________

hereby declare that I/We have not been black list by any Govt/Semi/PSU or any other

organization.

Page 92: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 92 of 125 Signature of Contractor with seal

FORMAT – B

PERSONNEL DETAILS OF THE BIDDER

Give details of key Technical and Administrative Personnel (who could be

assigned for this works) of the bidder in the following proforma.

A. Details of the Board of Directors

Name of the Director(s)

Organisation

Address

B. Key Technical and Administrative Personnel

and Consultants:

1) Individual’s Name

2) Qualification

3) Present position of office

4) Professional experience and details of

Integrated Operation & Comprehensive

Maintenance Services carried out

5) Years with the applicant

6) Language known

7) Additional information

C. Details of Service Personnel to take

care of various services.

Place:

Date:

Signature of Applicant with seal

Page 93: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 93 of 125 Signature of Contractor with seal

13B – AIR CONDITIONING AND MECHANICAL VENTILATION SYSTEM WORKS

1. Format – C : Experience in Operation & Maintenance of

ACMV and Connected works

2. Format – D : Experience of ongoing ACMV and

Connected works in O&M Works

3. Format – E : Details of facilities available for performing

services

4. Format – F : Certificates

Page 94: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 94 of 125 Signature of Contractor with seal

Page 95: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 95 of 125 Signature of Contractor with seal

FORMAT – C

EXPERIENCE OF COMPLETED O&M JOBS

Give details of the similar type of OPERATION AND MAINTENANCE OF ACMV AND

CONNECTED WORKS work (satisfying the requirements mentioned in the tender

notice) completed during the last 5 years in the following proforma (separate form for

each work)

1. Name of work and location

2. Client's name, address, contact person, Phone

No., fax No., and e-mail ID

3. In case of Indian Company, was there any tie-up

with foreign company? If yes, give name,

address and details of company with nature of

tie-up and since when.

4. Total tendered cost of work (Agreement No. and

Date)

5. Brief description of works including principal

features and main items of the work.

6. Name of applicant’s Building & Facility Manager

of the work and professional Qualifications.

7. Period of Contract

1. Originally stipulated time limit

2. Renewal time, if any.

8. Were there any

penalties/fines/stop - notice/compensation/liqui

dated damages imposed? (Yes or No) (If yes give

details, amount and explanation).

9. Details of litigations / arbitration cases, if any,

pertaining to works completed.

10. Attach client's certificate as may be available.

(Signed by Authorised Signatory of not below the

rank of Director) along with copy of work order,

agreement clearly stating the scope and details

of operation and maintenance of ACMV and

Connected works work.

Page 96: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 96 of 125 Signature of Contractor with seal

FORMAT – D

EXPERIENCE OF ONGOING O&M JOBS

Give details of OPERATION AND MAINTENANCE OF ACMV AND CONNECTED WORKS

(satisfying the requirements mentioned in the tender notice) ongoing and performance

progress as on the date of submission of pre-qualification document in the following

proforma. (Separate form for each work)

1. Name of work and location

2. Client's name, address, contact person, Phone No.,

Fax No., and e-mail ID

3. In case of Indian Company, Is there any tie-up with

foreign company? If yes, give name, address and

details of company with nature of tie-up and since

when.

4. Total tendered cost of work (Agreement No. and

Date; copy to be attached)

5. Name of Applicant's Building & Facility Manager

with professional qualifications.

6. Brief description of work including principal

features and main items.

7. Details of works on hand

a. Present stage of work.

b. Stipulated date of completion

c. Anticipated date of completion

d. Present stage of payment receipt (percentage)

8. Reason for delay if any in carrying out the job.

9. Were there any penalties / fines / stop – notice /

compensation / liquidated damages imposed? (Yes

or No). (If Yes, give details, amount and

explanation).

10. Were there any fines, claims or stop notice filed by

the Owner? (Yes or No)

(If yes, give details, amount and explanation)

11. Details of litigations/arbitration cases, if any,

pertaining to works ongoing.

Page 97: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 97 of 125 Signature of Contractor with seal

12. Attach client's certificate, as may be available (Not

below the rank of Director or equivalent) along with

copy of work order, agreement clearly stating the

scope and details of operation and maintenance of

ACMV and Connected works.

Page 98: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 98 of 125 Signature of Contractor with seal

FORMAT – E

DETAILS OF FACILITIES AVAILABLE WITH OPERATION AND MAINTENANCE OF ACMV

AND CONNECTED WORKS CONTRACTOR FOR PERFORMANCE OF SERVICES.

Page 99: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 99 of 125 Signature of Contractor with seal

FORMAT-F

CERTIFICATES

Certificates in support of suitability, technical know-how and capability for having

successfully completed the OPERATION AND MAINTENANCE OF ACMV AND

CONNECTED WORKS during the last five years along with copy of work order,

agreement clearly stating the scope and details of work.

Page 100: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 100 of 125 Signature of Contractor with seal

13C – BUILDING AUTOMATION SYSTEM WORKS

1. Format – G : Experience in Operation & Maintenance of

BAS and Connected works

2. Format – H : Experience of ongoing BAS and

Connected works in O&M Works

3. Format – I : Details of facilities available for performing

services

4. Format – J : Certificates

Page 101: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 101 of 125 Signature of Contractor with seal

FORMAT – G

EXPERIENCE OF COMPLETED O&M JOBS

Give details of the similar type of OPERATION AND MAINTENANCE OF BAS WORKS

work (satisfying the requirements mentioned in the tender notice) completed during

the last 5 years in the following proforma (separate form for each work)

1. Name of work and location

2. Client's name, address, contact person, Phone

No., fax No., and e-mail ID

3. In case of Indian Company, was there any tie-up

with foreign company? If yes, give name,

address and details of company with nature of

tie-up and since when.

4. Total tendered cost of work (Agreement No. and

Date)

5. Brief description of works including principal

features and main items of the work.

6. Name of applicant’s Building & Facility Manager

of the work and professional Qualifications.

7. Period of Contract

3. Originally stipulated time limit

4. Renewal time, if any.

8. Were there any

penalties/fines/stop - notice/compensation/liqui

dated damages imposed? (Yes or No) (If yes give

details, amount and explanation).

9. Details of litigations / arbitration cases, if any,

pertaining to works completed.

10. Attach client's certificate as may be available.

(Signed by Authorised Signatory of not below the

rank of Director) along with copy of work order,

agreement clearly stating the scope and details

of operation and maintenance of BAS works

work.

Page 102: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 102 of 125 Signature of Contractor with seal

FORMAT – H

EXPERIENCE OF ONGOING O&M JOBS

Give details of OPERATION AND MAINTENANCE OF BAS WORKS (satisfying the

requirements mentioned in the tender notice) ongoing and performance progress as

on the date of submission of pre-qualification document in the following proforma.

(Separate form for each work)

1. Name of work and location

2. Client's name, address, contact person, Phone No.,

Fax No., and e-mail ID

3. In case of Indian Company, Is there any tie-up with

foreign company? If yes, give name, address and

details of company with nature of tie-up and since

when.

4. Total tendered cost of work (Agreement No. and

Date; copy to be attached)

5. Name of Applicant's Building & Facility Manager

with professional qualifications.

6. Brief description of work including principal

features and main items.

7. Details of works on hand

a. Present stage of work.

b. Stipulated date of completion

c. Anticipated date of completion

d. Present stage of payment receipt (percentage)

8. Reason for delay if any in carrying out the job.

9. Were there any penalties / fines / stop – notice /

compensation / liquidated damages imposed? (Yes

or No). (If Yes, give details, amount and

explanation).

10. Were there any fines, claims or stop notice filed by

the Owner? (Yes or No)

(If yes, give details, amount and explanation)

11. Details of litigations/arbitration cases, if any,

pertaining to works ongoing.

Page 103: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 103 of 125 Signature of Contractor with seal

12. Attach client's certificate, as may be available (Not

below the rank of Director or equivalent) along with

copy of work order, agreement clearly stating the

scope and details of operation and maintenance of

BAS and Connected works.

Page 104: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 104 of 125 Signature of Contractor with seal

FORMAT – I

DETAILS OF FACILITIES AVAILABLE WITH OPERATION AND MAINTENANCE OF BAS

WORKS CONTRACTOR FOR PERFORMANCE OF SERVICES.

Page 105: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 105 of 125 Signature of Contractor with seal

FORMAT-J

CERTIFICATES

Certificates in support of suitability, technical know-how and capability for having

successfully completed the OPERATION AND MAINTENANCE OF HONEYWELL BAS

WORKS during the last five years along with copy of work order, agreement clearly

stating the scope and details of work.

Page 106: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 106 of 125 Signature of Contractor with seal

13D – DIESEL GENSET AND CONNECTED WORKS

FORMATS

1) Format – K : Experience in Operation & Maintenance of

completed Diesel

Generator Sets & Connected works

2) Format – L : Experience of ongoing Diesel Generator Sets and

Connected Works in Operation and Maintenance

works

3) Format – M : Details of facilities available for performing

Services

4) Format – O : Certificates

Page 107: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 107 of 125 Signature of Contractor with seal

FORMAT – K

EXPERIENCE OF COMPLETED O&M JOBS

Give details of the similar type of OPERATION AND MAINTENANCE OF DIESEL

GENERATOR SETS AND CONNECTED WORKS work (satisfying the requirements

mentioned in the tender notice) completed during the last 5 years in the following

proforma (separate form for each work)

1. Name of work and location

2. Client's name, address, contact person, Phone

No., fax No., and e-mail ID

3. In case of Indian Company, was there any tie-up

with foreign company? If yes, give name,

address and details of company with nature of

tie-up and since when.

4. Total tendered cost of work (Agreement No. and

Date)

5. Brief description of works including principal

features and main items of the work.

6. Name of applicant’s Building & Facility Manager

of the work and professional Qualifications.

7. Period of Contract

5. Originally stipulated time limit

6. Renewal time, if any.

8. Were there any

penalties/fines/stop - notice/compensation/liqui

dated damages imposed? (Yes or No)(If yes give

details, amount and explanation).

9. Details of litigations / arbitration cases, if any,

pertaining to works completed.

10. Attach client's certificate as may be available.

(Signed by Authorised Signatory

of not below the rank of Director) along with copy

of work order, agreement clearly stating the

scope and details of operation and maintenance

of Diesel Generator Sets and Connected works

work.

Page 108: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 108 of 125 Signature of Contractor with seal

FORMAT – L

EXPERIENCE OF ONGOING O&M JOBS

Give details of OPERATION AND MAINTENANCE OF DIESEL GENERATOR SETS AND

CONNECTED WORKS work (satisfying the requirements mentioned in the tender

notice) ongoing and performance progress as on the date of submission of pre-

qualification document in the following proforma. (Separate form for each work)

1. Name of work and location

2. Client's name, address, contact person, Phone No.,

Fax No., and e-mail ID

3. In case of Indian Company, Is there any tie-up with

foreign company? If yes, give name, address and

details of company with nature of tie-up and since

when.

4. Total tendered cost of work (Agreement No. and

Date; copy to be attached)

5. Name of Applicant's Building & Facility Manager

with professional qualifications.

6. Brief description of work including principal

features and main items.

7. Details of works on hand

a. Present stage of work.

b. Stipulated date of completion

c. Anticipated date of completion

d. Present stage of payment receipt (percentage)

8. Reason for delay if any in carrying out the job.

9. Were there any penalties / fines / stop – notice /

compensation / liquidated damages imposed? (Yes

or No). (If Yes, give details, amount and

explanation).

10. Were there any fines, claims or stop notice filed by

the Owner? (Yes or No)

(If yes, give details, amount and explanation)

11. Details of litigations/arbitration cases, if any,

pertaining to works ongoing.

Page 109: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 109 of 125 Signature of Contractor with seal

12. Attach client's certificate, as may be available (Not

below the rank of Director or equivalent) along with

copy of work order, agreement clearly stating the

scope and details of operation and maintenance of

Diesel Generator Sets and Connected works.

Page 110: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 110 of 125 Signature of Contractor with seal

FORMAT – M

Details of facilities available with OPERATION AND MAINTENANCE OF DIESEL

GENERATOR SETS AND CONNECTED WORKS contractor for performance of services.

Page 111: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 111 of 125 Signature of Contractor with seal

FORMAT- N

CERTIFICATES

Certificates in support of suitability, technical know-how and capability for having

successfully completed the OPERATION AND MAINTENANCE OF DIESEL GENERATOR

SETS AND CONNECTED WORKS work during the last five years along with copy of work

order, agreement clearly stating the scope and details of work.

Page 112: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 112 of 125 Signature of Contractor with seal

UNDERTAKING MAINTENANCE OF SYSTEM/EQUIPMENT/PREMISES (To be executed on Company Letter Head)

We___________________________ (Name & address of the bidder/contractor)

undertake that we will maintain the whole equipment, its sub-equipment, sub-

system(s) & premises properly in smooth running condition.

As we have accepted and offered the prices for maintenance contract in the submitted

bid, if any equipment or its related parts or machinery or property of TPCL found

damaged/not working properly/abnormal sound/heating/leakage/wiring damage/

insulation damaged/ corruption of software/equipment parts missing/the loss of any

items/spare part damage etc. on account of failure or negligence of the workers

deployed by us, then we shall be fully responsible for rectification of interrupted system

and for also keeping the whole system in completely smooth running condition.

We also undertake that we will replace/repair the faulty equipment/property

immediately. The make of replace item/equipment shall be similar to the existing items

or reputed make as per agreed by TPCL.

Signature of Authorised person:

Name

Page 113: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 113 of 125 Signature of Contractor with seal

14. HAND BOOK ON HEALTH AND SAFETY AT WORK

FOR CONTRACTORS WORKING IN TIDEL PARK

“Contracter” – Shall mean Integrated Operations & Non-

Comprehensive Maintenance of

ACMV,BAS,DG contractor

“Owner” - Shall mean TIDEL Park Coimbatore Ltd.

Page 114: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 114 of 125 Signature of Contractor with seal

TABLE OF CONTENTS SECTION

1. INTRODUCTION 2. RULES FOR GENERAL OPERATIONS

2.1 Access

2.2 Accident Reporting

2.3 Contracts & Sub-Contracts Tools & Equipments.

2.4 Hazardous Materials

2.5 Dust and Fume Control

2.6 Fire Hazards and Precaution

2.7 Machinery Safety

2.8 Noise

2.9 Overhead Working

2.10 Working at Height

2.11 Safety Clothes and Equipment

2.12 Plant Services

2.13 Supervision

2.14 Warning signs and Notices

2.15 Fogging

2.16 Pest control

3. TOOLS

3.1 Electrically Driven Portable Tools

3.2 Compressed Air Tools

3.3 Percussion Cartridge Tools

3.4 Hoisting and Lifting.

3.5 Movement of Plant and Machinery

3.6 Powered Industrial Trucks

Page 115: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 115 of 125 Signature of Contractor with seal

SECTION – 1

INTRODUCTION:

This document defines the operations undertaken by Contractors and sub-Contractors

on this premises, which can give rise to hazards to those engaged in the work and

others that may be working, standing or passing in the vicinity.

It is the Owner’s endeavor to secure a high standard of safety at site. Therefore,

Contractors and sub-Contractors must know their duties under common law, both for

establishments, and their own employees and the occupants to conduct their business

and methods of work to conform to the best practices as per the Owner’s ISO14001

policies and standards. Before the Owner, allows any contracting or sub- contracting firm to carry out work

on its premises, the Owner insists that Contractors and sub-Contractors understand

their duties regarding safe practices for themselves, others and regulations covering

the type of work they will be carrying out. In furtherance to this policy, rules herein have been devised to bring to the notice of

Contractors and sub-Contractors, some of the more common hazards, and appropriate

preventive measures in connection with the erection, construction, cleaning, painting,

alteration or demolition of plant, machinery and buildings. The Owner is confident that the observance of these rules will be no hindrance to

progress the work, but will assist in the avoidance of accidents.

IT IS IN A TERM OF ALL CONTRACTS BETWEEN THE OWNER AND

CONTRACTORS THAT THEY AND ANY SUB-CONTRACTORS, APPOINTED BY

THEM COMPLY WITH THESE RULES AND THEIR CO-OPERATION IS THEREFORE

OBLIGATORY IN CARRYING OUT THE PRECAUTIONS LAID DOWN.

Section – 2 : Details general rules which are applicable to most Contractors and sub-

Contractors. Section – 3 : Details specific rules which must be followed where applicable, where a

particular type of work is to be undertaken.

All Contractors Supervisors will make sure that the Engineering Services / Safety

Manager on this premises are notified as and when himself and others (Sub-

Contractors) are reporting for work on that site.

Page 116: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 116 of 125 Signature of Contractor with seal

SECTION 2

RULES FOR GENERAL OPERATIONS:

2.1 ACCESS:

- Nothing shall be done or omitted to be done by Contractors or Sub-

Contractors or their employees to render unsafe or obstruct:

- any means of access to the places at which people are required

to work.

- the passage of people and / or vehicles whether on a defined

gangway or not, unless permission is obtained from the

designated safety officer - access for emergency apparatus, such

as firefighting equipment

- Contractors and sub-Contractors shall nevertheless provide

adequate fencing, lighting and warning signs to ensure safety at

all times

- While carrying out maintenance works, necessary signages to be

provided at the respective locations.

2.2 ACCIDENT AND INCIDENT REPORTING:

All notifiable accidents, dangerous occurrences and potential hazard situations

shall be reported to the safety officer of TPCL.

Injuries are to be treated by experienced medical staff available at site at the

contractor cost.

2.3 CONTRACTORS AND SUB-CONTRACTORS’ TOOLS AND EQUIPMENTS:

All Contractors and sub-Contractors tools and equipments must comply with

statutory regulations and approved codes of practices.

2.4 HAZARDOUS MATERIALS:

The Contract must inform the safety officer of TPCL, prior to commencement of

work, procurement of or materials connected with the contract work of a

hazardous nature. The Contract will have to secure storage for any such

material.

2.5 DUST AND FUME CONTROL:

Contractors and sub-Contractors must inform the safety officer of TPCL at this

premises of all processes producing dust or fumes, and under the conditions as

laid down in the Factories Act 1948, Sections 14 & 17 the safety precautions

are to be fulfilled.

2.6 FIRE HAZARDS AND PRECAUTIONS:

When at site, all fire regulations, as well as regulations under Section 38 and

subsequent amendments if any under the Factories Act 1948, must be observed

Page 117: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 117 of 125 Signature of Contractor with seal

at all times. Awareness about the above to be educated to all staffs who are to

be deployed in this contract. 2.7 MACHINERY SAFETY:

Contractors and sub-Contractors working at these premises must not remove

or displace any guard, fencing or other safety equipment which is designed to

protect personnel or machinery or any place where safety equipment has been

provided without the written permission of the safety officer or his designated

representative.

On completion of any work, any guards that had to be removed must be

replaced immediately and whilst work is being carried out, machinery must not

be operated. The requirement of the Factories Act Sections 21-26 and

subsequent amendments if any must be followed: 2.8 NOISE:

Contractors and sub-Contractors working at this premises must obtain

permission from the safety officer/Owner if the processes being employed to

carry out that work significantly increase the ambient noise level in that area

being worked.

2.9 OVERHEAD WORKING:

No work may be carried out above the heads of people or over gangways or

roads, until all precautions have been taken to ensure the safety of the persons

below, and until the safety officer/Owner gives permission. Each specific site of

overhead working will require consent from the safety officer. This will be given

after satisfactory inspection.

Work may be carried out in the vicinity of power cables only when permission

is obtained from the safety officer and/or Owners representative.

Work connected with overhead safety includes the movement of long metal

objects, machinery, jibs, masts, arms or other elevated parts.

2.10 WORKING AT HEIGHT:

All temporary structure erected by Contractors or sub- Contractors for the

purpose of allowing their staff to work at heights of more than 2 M. above floor

level must be constructed in accordance with the Safety Regulations laid down.

Whenever possible, ladders are to be made of wood and in good condition.

Metal ladders must not be used where there is any possibility of the ladder

coming into contact with an electrical conductor.

Roof working must be properly supervised.

2.11 SAFETY CLOTHES / UNIFORM AND EQUIPMENT:

This will be supplied by Contractors and Sub-Contractors who are working on

sites and must be adequate for the well being of their staff engaged in the type

of work contracted for.

Page 118: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 118 of 125 Signature of Contractor with seal

The equipment and its use must comply with the regulations and codes of

practice as laid down that apply to the conditions of work being undertaken.

Uniform and PPE materials should be provided for all the Staff.

Green colour reflector jackets shall be provided for Technical team in addition

to uniform.

Contractors and sub-Contractors will be responsible for the use of any tools and

equipment that is supplied by them, or their staff to the exclusion of all

responsibility of the Owner. Tools will be maintained to the highest standard of

safety. Whilst in the possession of such tools, the person so using said tools is

responsible for the continued maintenance of safety standards.

It is the individual’s responsibility to ensure that the tools he works with are

suitable for the job, and in a safe condition prior to work commencement. All

necessary tools and equipment to complete a contract should be supplied by

the Contract. Due provision must be made during contract preparation. 2.12 PLANT SERVICES:

Before using plant services such as electricity, permission to do so must be

obtained from the appropriate authority, Owner/Safety Officer.

2.13 SUPERVISION:

Contractors working at this premises must ensure that their staff are

adequately supervised.

2.14 WARNING SIGNS AND NOTICES:

Suitable warning signs are to be displayed at the respective locations,

warning of potential hazards.

Page 119: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 119 of 125 Signature of Contractor with seal

SECTION – 3

TOOLS

3.1 ELECTRICALLY DRIVEN PORTABLE TOOLS:

Permission is to be obtained from the nominated person before any Contract or

sub-Contract’s electrical hand tools can be connected to the electricity supply.

Connection must be by 3-core and 3-pin plugs and sockets, except when tools

are double insulated on a 2-wire supply. Where the supply is 3-phase, 4-core

cable and 4-pin plugs and sockets with earth connections must be used.

Connections without proper sockets are not permitted

Make-shift connections are prohibited.

The use of extension cables is discouraged, but sometimes necessary.

Portable electric lamps must be the ‘Gripper’ type with caged wire protection

for the bulk and precautions as laid down under Section 36-37 of the Factories

Act 1948 and subsequent amendments if any, must be observed.

In all cases, with the exception of double insulated tools, the metal work of the

tools must be effectively earthed, also any flexible metallic cable coverings

must be earthed.

3.2 COMPRESSED AIR TOOLS

Contractors and sub-Contractors must obtain permission to use any

compressed air supply at this premises. Contractors and sub-Contractors must

also provide suitable noise suppression for pneumatic hammers, drills etc.

3.3 PERCUSSION CARTRIDGE TOOLS

Permission to use percussion tools must be obtained from the designated safety

officer/Owner prior to the use of these tools.

Also when using percussion tools, it is the individual duty to ensure that the

charges used in said tools are correct. These tools are to be handled as

dangerous weapons, never leave tools unattended, never leave tools charged

or store charged, never point tools at personnel, always lock up when

finished both tool and charges.

3.4 HOISTING AND LIFTING:

Permission must be obtained prior to the use of Plant and equipment, from the

Owner or other nominated responsible person.

Equipment must be adequate for the purpose required and anchorage approved

by the site safety officer/Owner.

All equipment so used must have been examined by a competent person, and

where necessary a certificate obtained in accordance with Sections 28 and 29

of the Factories Act 1948 and subsequent amendments if any shall be observed.

No object is to be left unattended whilst using lifting equipment.

Page 120: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 120 of 125 Signature of Contractor with seal

3.5 MOVEMENT OF PLANT AND MACHINERY

Permission must be obtained from the appropriate authorities prior to the

movement of construction materials, plant or equipment in and around

premises.

3.6 POWERED INDUSTRIAL TRUCKS

Permission must be obtained from the appropriate authorities prior to the use

of lift-trucks by Contractors or sub-Contractors at this premises.

Trucks must only be driven by competent licensed personnel with valid license

and must comply with statutory regulations.

Page 121: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 121 of 125 Signature of Contractor with seal

SECTION – 4

GUIDELINES FOR CONTRACTORS AND SUB- CONTRACTORS

1. Safe working practices must be observed at all times.

2. It is the responsibility of the contractors and sub- contractors staff to use

appropriates personal protection. It is the Contracts and sub-Contracts

obligation to supply necessary protective equipment and clothing.

3. Certain areas are designated hazardous (e.g. noisy areas) and warning signs

must be obeyed.

4. Where the contractors and sub- contractors work presents a potential hazard,

appropriate notices must be supplied and displayed, and the area made secure

as far as is reasonably possible.

5. The Owner will not provide tools, materials, lifting or access equipment, fixings

or raw materials, unless by previous arrangement.

6. Any equipment brought to site by contracts and sub- contracts must not be

used by untrained persons, and attention is drawn to the indemnity clause of

the Owner orders, which states that the Contracts is liable for any consequent

damage or loss to people, equipment or buildings.

7. All welding, burning and grinding operations which could potentially cause fire

must be reported to security.

8. Vehicle parking will be in designated areas only.

9. No smoking is allowed inside the building and service building, near the fuel

storage tank, waste oil storage area, scrap dumping yard, waste collection

yard, LPG stored area and wherever hazardous area notified by the Owner. This

has to be strictly enforced by the Safety officer/Fire officer.

10. No food is to be consumed or left in work areas.

11. Warning signs and speed restrictions must be displayed and be observed.

12. Place of work to be left in a tidy and safe condition at the end of each work

period.

13. Care to be taken against contamination of any product of paint, oil, etc.

14. All injuries must be reported to the Ambulance Authority or to Security

officer/staff who shall all be trained in First Aid.

The above has been received and read by Contractors / Sub – Contractors and we

agree to comply with these Rules (See foot-note)

NOTE:

The Contractor/Bidder will ensure that Sub – Contractor shall receive and sign a copy

of these Rules.

Page 122: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 122 of 125 Signature of Contractor with seal

15. Conditions of BOQ

1) The rate quoted includes all expenses, cost of Manpower, tools & equipments etc.,

including overheads and profits for the lumpsum prices quoted in the Bill of Quantities. The

quoted price to be exclusive of GST and all other taxes as the same is exempted being

the contract is in SEZ (Special Economic Zone). The Total rate quoted for One year of

services will be considered for the purpose of deciding the competitive tender.

2) The rate shall include all statutory payments, payable to the contractor

workman i.e., Minimum wages notified by TN Government, ESI, PF, Bonus etc., and

any other statutory taxes and levies notified by the government from time to time and

will remain fixed throughout the contract period and for extended period.

3) Computation of Manpower cost:

Basic Rate as per GO No.102 dated 5th Mar 2019

Leave salary to be considered for 22 days (10 days national holidays

plus 12 days casual leave) on Basic plus DA

PF 13% on Basic plus DA plus Leave Salary.

ESI / Insurance 3.25% on Basic plus DA

(ESI to be covered for the eligible staff and staff who are

exempted from ESI are to be covered under insurance).

Bonus 8.33% on Basic plus DA plus Leave Salary

Uniform 2% on Basic plus DA plus Leave Salary

4) Service charges should not be less than 2% of the total cost.

5) From BOQ Sl. No 1.01 to 1.34, only service charges, Basic rate, DA and other

allowance to be provided and 1.41,1.42 only service charge cost needs to be provided.

6) If the quoted rate offered by the tenderer is unreasonably high, TPCL shall

adopt the bench mark of the rates quoted by the other tenderer for the same items

and arrive suitably. TPCL’s decision on this will be final and binding on the Tenderer

for the items of this price bid.

8) All workers should be given one day week off on rotational basis. Manpower

rate includes scheduled mandays on Sundays / National holidays and week off to

ensure 24 x 7 operations.

9) Service charges quoted by the bidder should include all expenditure on

providing the resources / managerial / supervisory / administrative services by all

means to get the work done through the deployed staff.

Page 123: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 123 of 125 Signature of Contractor with seal

16. Insurance

1. The Contractor shall be responsible for all injury or damage to persons, animals

or things, and for all damage to property which may arise from any factor of

omission on the part of the Contract or any sub-Contractor employed by them

or any of their employees.

2. The Contractor shall indemnify and keep indemnified the Employer and hold

him harmless in respect of all and any loss and expenses arising from any such

injury or damage to persons or property as aforesaid and also against any claim

made in respect of injury or damage, whether under any statute or otherwise

and also in respect of any award or compensation or damage consequent upon

such claim.

3. The Contractor shall also indemnify the employer against all which may be upon

the Employer, whether under the workmen's compensation Act or any other

statute in force, during the currency of this contract or at common Law in respect

of any employee of the Contractor or of any Sub-Contractor and shall at his own

expense effect and maintain until the completion of the contract, with an

insurance Company, approved by the Employer, a Policy of Insurance against

such risks (with a limit of liability of not less than Rs 5.00 (five) lakhs per

occurrence)and deposit such policy or policies with the Employer from time to

time during the currency of this contract.

4. In default of the Contractor insuring as provided above, the Employer may so

insure and may deduct the premiums paid from any moneys due or which may

become due to the Contractor.

5. The Contractor shall be responsible for any liability which may not be covered

by the Insurance Policies referred to above and also for all other damages to

any person, animal or defective carrying out of this contract, whatever, may be

the reasons due to which the damage shall have been caused.

6. The Contractor shall also indemnify and keep indemnified the Employer against

all and any cost, charges or expenses arising out of any claim or proceedings

relating to the works and also in respect of any award of damages or

compensation arising therefrom.

7. Without prejudice to the other rights of the Employer against Contractor in

respect of such default, the Employer shall be entitled to deduct from any sums

payable to the Contractor the amount of any damages, compensation costs,

charges and other expenses paid by the Employer and which are payable by

the Contractor under this clause.

8. Contractor shall, prior to the commencement of any site activity submit the

Insurance Confirmation Letter – Annexure regarding the required Insurance

Policies to be put in place by Contractor. TPCL reserves the right to examine

the policy wording and require evidence that the Policy Premium has been paid

Page 124: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 124 of 125 Signature of Contractor with seal

to the Insurers, and that it shall remain in force, throughout the duration of the

Contract.

9. All deductions or liabilities in excess of the indemnities provided under the

insurance arranged by Contractor / Sub-contractor and / or TPCL shall be for

the account of and paid by Contractor and his Sub-contractors.

10. TPCL shall not accept any responsibility whatsoever for any loss of or damage

to any property or personal effects belonging to Contractor’s employees or to

those of Sub-contractors employed by them.

Page 125: (A JV of TIDCO, ELCOT, TIDEL ... - TIDEL Park Coimbatore

TIDEL PARK COIMBATORE LTD TENDER FOR INTEGRATED OPERATION & NON-COMPREHENSIVE MAINTENANCE SERVICES - Vol.I

Tender Notice No: A-17012/003/2020-CR Page 125 of 125 Signature of Contractor with seal

Annexure

INSURANCE CONFIRMATION LETTER

(To be typed on Contractor’s Letterhead, Signed

& Stamped by Authorised Person)

To

TIDEL Park Coimbatore Ltd.

ELCOSEZ

Aerodrome Post

Coimbatore - 641014

Dear Sir,

Sub : Confirmation of Insurance Policies Contract / Agreement No.

…………… for Integrated Operation & Non Comprehensive Maintenance

of ACMV, BAS, DG Sets & Connected Works at TIDEL PARK

COIMBATORE LTD.

------------

We hereby confirm that we have effected valid insurance policy(ies) expiring on

……………….. which comply(ies) with all the requirements and conditions stipulated in

the Insurance and Indemnity Article of the above Contract / Agreement including inter-

alia :-

• Waiver of subrogation against its servants, agents, employees, subsidiaries

and all other companies in TPCL’s Group and

• ………… being included / named as an additional insured in the capacity of

principal which are endorsed to the insurance policy(ies).

Corporate or Company Seal _____________________

Authorized Signature

Name of Contractor

By:

Title